Presentation
• Foothill Extension
• Phase 2A – Pasadena to Azusa
– Three Design-Build Projects
– Intermodal Parking Facilities and Enhancements
Design-Build Project: Scope of Work
• Procurement and Evaluation
• Q&A
Completing the Vision
Creation/Powers of the Authority • SB 1847 sponsored by State Senator (now Congressman) Adam Schiff effective January 1, 1999
updated October 2011 – AB706, sponsored by State Assembly
member Norma Torres
• Scope included current Metro Gold Line from Union Station to East Pasadena, and any fixed guide way to Claremont (now Montclair) • SB 1847 also provides the necessary powers to complete the project:
the ability to acquire right-of-way
issue debt
enter into joint development agreements
relocate utilities
accept grants, fees and allocations from all funding sources
enter into design build contracts
Strategic Partnership w/Metro
• We are not LACMTA / Metro • General Relationship
– Construction Authority plans, designs and builds the line (per Metro’s design/safety guidelines and specifications)
– Metro operates and maintains the line following construction
• Both agencies play a role in public safety planning and education
• Master Cooperative Agreement – Formalizes roles and responsibilities – MCA for Pasadena to Azusa and Azusa to Montclair segments
signed March 2010
Building by Phase
Planning/Construction Phases
• Pasadena to Azusa Extension – Fully Funded by Measure R – 11.5 Miles, 5 Cities, 6 Stations/Completion Anticipated 2015
Pasadena-Azusa Azusa-Montclair Airport Ext.
• Azusa to Montclair Extension - Proposed – 12.6 Miles, 6 Stations/Estimated Funding Needed is $550 Million
• Ontario Airport Extension - Proposed – Approximately 8 Miles/Unfunded
• Pasadena to Azusa comprises three design-build project packages: – Package 1 – Iconic Freeway Structure (I-210 Bridge) – Package 2 - Alignment Contract (11.5 miles) – Package 3 - Intermodal Parking Facilities and Enhancements
Pasadena-Azusa
Status: Pasadena to Azusa
Design-Build Packages
• Package 1: Iconic Freeway Structure over I-210 (approx. 584 linear feet)
• Package 2: Phase 2A Alignment, includes: Rail Track Alignment, Bridges, Crossings, Stations, Utilities, Systems, Signals (and related items), as well as a Maintenance & Operations Facility
• Package 3: – Intermodal Parking Facility at five of the six stations:
four multi-level parking structures and one surface parking lot.
– Intermodal Enhancements, including: bus pads and shelters, bike lockers and racks, sidewalks, ramps, enhanced crosswalks, trees and tree wells, pedestrian street lights, traffic signals and roadway improvements.
Package 1: Iconic Freeway Structure
Package 2: Phase 2A Alignment
Package 2 includes: Rail Track Alignment, Bridges, Crossings, Stations, Utilities, Systems, Signals, and Maintenance & Operations Facility.
Structures
Stations
Track
Crossings
Package 3: Intermodal Parking Facilities and Enhancements
Package 3 includes: parking structures, a surface parking lot, fencing, traffic signals, bus pads and shelters, bike racks and lockers, retaining walls, sidewalks, ramps, enhanced crosswalks, landscaping, trees and tree wells, pedestrian street lights, roadway improvements, other related work.
-13-
Intermodal Parking Facilities
And Enhancements Design-Build Project:
Scope of Work
Scope of Work: • Design-Build Project Quality Control
o Inspections o Testing
Quality Assurance • Public Agency Project Construction Work Plans
• Coordinate with: Cities Utility Owners Third Parties Alignment (DB2)
Contractor Metro (via Authority)
Intermodal Parking Facilities Five parking facilities:
Four parking structures
One surface parking lot
Utility Relocations
Retaining walls
SUSMP Requirements
Ventilation system, when required
Intermodal Enhancements Bike lockers and racks Bus pads and shelters Sidewalks, ramps and curb ramps Enhanced crosswalks Street trees and tree wells Pedestrian street lights Traffic signal and roadway improvements
Relocation of utilities Vacation of existing street Demolition of existing buildings/facilities
Arcadia Site
2-level Parking Structure with approx. 300 spaces Intermodal Enhancements on Santa Clara Street & 1st Ave
Arcadia
Multi-level Parking Structure with approx. 350 spaces
Monrovia
Surface Parking Lot with approx. 125 spaces Intermodal Enhancements on Duarte Rd and Highland Ave
Duarte
Retaining walls required Relocation of overhead utilities Relocation of drainage pump station
Irwindale Site
3-level Parking Structure with approx. 350 spaces Intermodal Enhancements on West Avenida Padilla
Irwindale
Intermodal Enhancements on Santa Fe Ave Joint Venture Parking Structure (not included in scope)*
Azusa-Alameda
3-level Parking Structure with approx. 200 spaces Intermodal Enhancements at Station Area & on Citrus Ave and Foothill Blvd
Azusa-Citrus
-25-
Procurement Process
Request for Statements of Qualifications
1. Goal: To create a shortlist of most-qualified teams
2. Evaluation Criteria: Related Project Experience (50 points) Staffing and Organization (35 points) Legal & Financial Qualifications (15 points)
3. Evaluation Criteria: Forms
4. Questions and Answers: Form E
5. Only Addenda are Binding
6. Single Point of Contact; No Ex Parte Communications§3.2
RFQ Procurement Milestones
RFQ MILESTONES ANTICIPATED DATES
Issue RFQ March 19, 2012
Pre-submittal Conference March 22, 2012
Questions Due April 16, 2012
Authority Response April 25, 2012
Statements of Qualification Due May 15, 2012
Interview Dates (if any) June 4-5, 2012
Announce Shortlist June 8, 2012
Recommend Award
Discussions (if any)
SOQ s received
5/15
Shortlist of Design-Build
Teams
6/8
Industry Review Draft Release
6/8
Industry Review Comments & Technical
One-on-Ones
7/9 – 7/30
8/29
Revised / Final Proposals
(if any)
10/24
RFQ Issued
1/9/13
Proposals Due
RFP Issued
2/27/13
3/19
11/15
Procurement: The Big Picture
Next Steps
Last Day for Submitting Written Questions April 16, 2012
Proposals Due May 15, 2012
Interview Date (if required) June 4-5, 2012
Shortlist Announced June 8, 2012
-30-
www.foothillextension.org