Total Project Snapshot Report2011 Legislature TPS Report 55611v1

$2,000,000Approved

Agency: Commerce, Community and Economic DevelopmentGrants to Municipalities (AS 37.05.315)

Federal Tax ID: 92-0030845Grant Recipient: Kodiak Island Borough

Project Title: Project Type: Remodel, Reconstruction and Upgrades

Kodiak Island Borough - Anton Larsen Dock

State Funding Requested: $2,000,000 House District: 36 / ROne-Time Need

Brief Project Description:Engineering and design and construction for the replacement of the heavily used and deterioratingfloating dock in Anton Larsen Bay.

Funding Plan: Total Project Cost: $2,095,000 Funding Already Secured: ($95,000)FY2012 State Funding Request: ($2,000,000)Project Deficit: $0 Funding Details:

The Kodiak Island Borough will contribute $15,000 toward this project.

Detailed Project Description and Justification:The Anton Larsen Floating Dock is located 18 miles from the town of Kodiak. It was originally constructed as a supply dockfor work associated with the Terror Lake Hydroelectric Project. Instead of dismantling the dock upon the completion of thedam, the Borough became interested in it. It is a facility that is heavily used by residents of the rural communities of PortLions and Ouzinkie, as well as those living on the island’s west side. During the summer it is also used by charter boats andsport and commercial fishermen. This interest resulted from the boating public’s desire for a safer route to the community of Kodiak through Anton LarsenBay. A road leads to the City of Kodiak from this dock, bypassing the potential risk to loss of life and property that is hugewhen navigating around Spruce Cape. Spruce Cape is one of the most dangerous stretches of water on Kodiak Island andmany people risk navigating around this cape to receive essential services. The KIB improved the dock in 1995 by drivingpiles and refurbishing the floating dock structure. Much more needs to be done to replace the dock and piles and design animprovement to this important facility.Total project cost is estimated at $2 million.

Project Timeline:The Kodiak Island Borough is prepared to move forward with the design phase when funding is in place.

Entity Responsible for the Ongoing Operation and Maintenance of this Project:Kodiak Island Borough

For use by Co-chair Staff Only:

Page 1

Contact Name: Astrid LievanoContact Number: 907-465-2487

10:25 AM 5/27/2011

Page 2: Kodiak Island Borough - Anton Larsen Dock

Total Project Snapshot Report2011 Legislature TPS Report 55611v1

Grant Recipient Contact Information:Name: Rick GiffordTitle: ManagerAddress: 710 Mill Bay Road

Kodiak, Alaska 99615Phone Number: (907)486-9302Email: [email protected]

Has this project been through a public review process at the local level and is it a community priority? X Yes No

For use by Co-chair Staff Only:

Page 2

Contact Name: Astrid LievanoContact Number: 907-465-2487

10:25 AM 5/27/2011

Page 3: Kodiak Island Borough - Anton Larsen Dock

!.

!.

!.

Kodiak

Ouzinkie

Port Lions

Anton Larsen Dock ReplacementMap Scale = 1:250,000

Project Location

/

Kodiak I

sland

Page 4: Kodiak Island Borough - Anton Larsen Dock

Anton Larsen Dock

Anton Larsen Dock ReplacementImagery Courtesy of NRCS (2004) Map Scale = 1:2400

Kodiak I

sland

® Current Dock Condition