7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 1/17
8/6/2015 Method Statement for Conduit Installation Including Accessories PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 1/17
Method
Statement for
Conduit
Installation
Including
Accessories
PVC & GI
2Like
Tweet 0
Below is a
comprehensive method
statement for conduit
installation which can be used
for purpose of any project and it
can be approved easily by
consultants because it covers all
aspects of a standard conduit
installation method.
We have also given the
download link for method
statement for conduit installation
on below page which will help
you to easily modify the word
and excel files that also include
ITP, inspection checklists and
Home Download Method Statements Project Quality Plan Disclaimer
Privacy Policy Support Project HSE Plan Inspection Checklists
Project Management Request A Method Statement
START A CONVERSATION
367 people like this.Like Share
SUBSCRIBE
You will Receive Each New Method Statement In Your Email as Soon as It Is
Published.
Enter your email address:
Subscribe
Delivered by FeedBurner
"We recommend these Project Management Templates for delivering
your projects successfully."
POPULAR METHODSTATEMENTS
List Of Mandatory Tests For Transformers August 5th, 2015
The following routine tests specified in IEC726 shall be carried out at
the manufacturer's works on [...]
List Of Common Tests For Diesel Generator Testing August 5th, 2015
The following site tests shall be carried out in order to determine whether the
DG material and appa [...]
Method Statement For Testing And CommissioningOf Laboratory Air Flow Control System & Fumes
9 Email
Shar e
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 2/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://www.methodstatementhq.com/method-statement-insta llation-gi-conduits-accessories.html 2/17
risk assessment etc.
TABLE OF CONTENTS
1. Purpose
2. Scope
3. Legislation and
Code of Practice
4. Reference
5. Definitions6.
Resources
6.1. Equipment
6.2. Safety of
Equipment’s
7. Safety Precautions
7.1. Construction
Hazards
7.2. Personal Protective
Equipment
7.3. Safety Training and
Emergency procedures
7.4. First Aid
8.Detailed
Construction
Sequence
(Methodology)
8.1. Procedure
9.Construction
Program9.1
Housekeeping9.2
Protection of Executed
Works9.3
Responsibilities
9.4 Records
10.Inspection and
Testing
11.Related Forms
Hood MonitoringJuly 27th, 2015
Below is the method statement description for performing the testing and
commissioning of laboratory [...]
METHOD STATEMENT FOR THE COMMISSIONINGOF EC2001 EASI-CHECK EMERGENCY LIGHTING
MONITORING SYSTEM WITH OR WITHOUT SITEMONITOR/GRAPHICS PACKAGEJuly 20th, 2015
This method statement is for commissioning of Easi-Check Emergency
Lighting Monitoring Systems compr [...]
Download Method Statement for Installation Of DehumidifiersJuly 13th, 2015
Download Method Statement for Installation Of Dehumidifiers Downloadpackage contains the Method S [...]
Download Method Statement for Installation Of Earthing & Bonding System & AccessoriesJuly 12th, 2015
Download Method Statement for Installation Of Earthing & Bonding System &
Accessories Down [...]
Download Method Statement for Installation Of Chilled Water Pressurization Unit & Expansion TankJuly 7th, 2015
Download Method Statement for Installation Of Chilled Water Pressurization
Unit & Expansion Tank [...]
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 3/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 3/17
12.Attachments
1. Purpose
This document describes the
method statement for conduit
installation which includes GI &
PVC conduits and accessoriesfor the project, and to ensure
that all concerned persons are
familiar with the sequence of
activities, utilization of resources,
and execution of the works in
compliance with applicable
Safety and Quality Procedures,
and Project Documents and
Specification.
DOWNLOAD METHOD
STATEMENT IN WORD
FORMAT
2. Scope of Works
For Installation of
GI Conduits
This method statement isintended to outline the activities
and the methods used for the
Installation of GI conduits and
accessories. All activities will be
carried out in accordance with
the contract details and in full
compliance to the Contract
Specifications and documents.
All work within the rights-of-way
of the standards and
specifications will be done in
compliance with requirements
issued by authorities.
3. Legislation and Code of
Li
0
T
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 4/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 4/17
Practice
All related codes and
standards referenced in the
project electrical
specifications.
4. Reference
Contract Specifications
Approved Drawings
5. Definitions
6. Resources
6.1. Equipment / Tools
NO. DESCRIPTION
1 Bending machine
2 Die sets
3 Measuring tape
4 Screw driver
5 Chalk mate thread
6 Oil
7 Drill machine
8 Screw driver
6.2 Safety of Equipment’s
Necessary measures will be
taken for the safety of the
equipment and any other works
affected by the works subject of
this document. Relevant entities
which might require protection
include any such works in the
vicinity of the area of work or on
the service access or discharge
path.
9
Share
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 5/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 5/17
The construction team will
ensure that any such
requirements are documented.
7. Health, Safety &
the Environment
The hazards identified above will
be controlled under the overall
Project Safety Plan which is a
separate document
communicated to all parties on
the project.
7.2. Personal Protective
Equipment (tick as
appropriate)
The works subject of thisdocument requires that the PPE
must be used as required.
7.3. Safety Training and
Emergency procedures
Before commencing any works,
all employees will attend a site
safety induction training to
ensure all safety measures are
understood and implemented
and to cover specific procedures
in case of emergency. If
necessary, practical training
exercises will be conducted on
escape routes, signage,
evacuation and rescue.
DOWNLOAD METHOD
STATEMENT IN WORD
FORMAT
7.4. First Aid
Prior to the commencement of
work, arrangements will be
made for medical facilities and
medical personnel to be
available from prompt attention
to the injured person. The
contractor’s vehicle assigned tothe job site will be used for
transporting the injured person
to the first aid station and to the
nearest hospital when required.
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 6/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 6/17
8. method
statement for
conduit
installation
General Procedure for conduit
installation is given below after
which area wise details are
provided like method statement
for conduit installation in slab,
walls and exposed areas etc.
Steps for exposed conduit
installation on walls &
ceilings etc.
Step 1: Take the following
drawings approved for
construction.
GI conduits layout
complete with section
details.
MEP coordination drawing
complete with section
details.
Architectural Drawing
Step 2: Procedure of method
statement for conduit installation
1. Check the route of GI
conduiting to make sure
that it is free from debris
and obstruction of any
other activity.
2. Arrange scaffolding of
sufficient height which is
checked by scaffolding
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 7/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 7/17
inspector/ safety officer
before using the same for
installation.
3. Mark the reference points
on wall/ column as per civil
architectural drawing.
4. Identify the circuit start
point and end points to
mark the conduit route as
per approved drawings.
5. Make hole in wall/concrete
using drill machine for
rawal plug, fix rawal plug
inside hole and then fix
base of saddle by screw
every 2 meter span.
6. Use recommended andapproved GI conduiting &
bends as per site condition
and drawing. Remove
sharp edge of cut length of
conduit by filing.
7. Install conduits and all
accessories as per
approved shop drawing
and tight with saddle and
screw, make joints using
threaded fittings.
8. Installation of GI conduits
shall be checked by
internal quality engineer as
per drawings and quality of
installation before offering
consultant/client for
inspection.
9. Conduits are not to cross
pipe shafts, vents or
opening.
10. Additional threaded cuts on
GI conduits are to be
painted with zinc based
coating resistant to
corrosion.
11. Approved clamps to be
used for the supports.
12. Maximum spacing of
supports for different
conduit sizes to be
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 8/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 8/17
clarified.
13. Conduits on walls are to be
run neatly, horizontally or
vertically.
14. Conduits are to be used for
exposed installations over
false ceilings when the
false ceiling is used as
return plenum.
15. Conduits is to be used for
all installation in elevator
machine room and shafts,
electrical equipment
rooms, parking floor, solid
waste rooms, etc.
16. All works on site will be as
per electrical specificationsand as per applicable
electrical wiring
regulations.
17. The risk assessment
mentioning necessary
control measures shall be
attached to this method
statement to follow and
implement the
requirements
method statement for
conduit installation In
Concrete Slab
Following tools should be
arranged before starting the job.
Dia (20 & 25 ) mm pipe
Bender
Mini Hacksaw Frame with
Blades
Choke Lime Powder with
sufficient length of Thread
500gm Hammer
Measuring Tape
End Cutter ( Kalwa )
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 9/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 9/17
PVC Conduit Installation
Procedure
Ensure that the civil people
have finished ply/post
tension work on the slab.
Arrange the approved shop
drawings for the area of
installation.
Mark first the wall location
for lower floor in slab as
per latest Architecture
layout so that it will be easy
to locate the drops for
switch, thermostat and any
other drops required for
electrical system.
Mark the opening size in
Electrical Room and
Telephone room as per
approved electrical
drawing.
Mark the Electrical points
on the slab as per
approved Electrical Layout
and fix proper shape and
size of the Circular Boxwith the help of nail/mess
in case of plywood slab
and provide steel bar
chairs for fixing the box in
case of post tension slab.
Just after completing the
first layer of steel, start pvc
conduiting work with
different sizes of conduit
based on electrical system
requirements and as per
drawings. Always loop the
two way switches with 20
mm conduit as the number
of wires will be more and
only switch drop pipe will
not be sufficient for pulling
all these wires.
Try to avoid theoverlapping of conduits
and keep some distance
between the conduits for
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 10/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 10/17
low current and
power/Lights.
Just after completing the
work tight the conduits with
binding wire and mark the
circuit numbers.
identification for the raised
pipe in slab for upper slabto be done for power, TV
and telephone systems
and closing the mouth of
pipe with the help of
masking tape .
The site Engineer/Foreman
should check the proper
size of conduit and circular
box, opening size in both
Electrical and Telephone
room and be sure the work
is completed as per
approved Electrical shop
drawing.
Before the concrete
pouring the PVC conduit
installation to be inspected
and approved by
consultant/client/contractor.
During concrete pouring,
keep electricians for taking
care of conduit to avoid
any damage by others or
dislocation of joints.
method statement for
conduit installation (GI
Box & GI/PVC Conduitin Walls)
Following tools should be
arranged before starting the job.
9” Grinder with cutting disc
Mini Hacksaw Frame with
Blades
White chalk /Marker
1 KG Hammer
Measuring Tape
Sprit Level
Water Level Pipe
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 11/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 11/17
Point & Flat Chisels
Trowel
Pipe Bender
Method Statement for
Conduit Installation inside
the Wall – PVC
Ensure that the civil people
have finished block wall
and clearance is given to
proceed for electrical
works.
Check the required
reference markings are
available for FFL (finished
floor levels).
Mark the location of
switch/socket and conduit
route on proper height
based on approved shop
drawing.
Ensure the box size andaccordingly cut a bit larger
size of box in marked place
of block wall with sufficient
depth.
Start cutting the marked
place for conduit run with
the help of grinder and chip
with hammer after cutting.
Fix the GI Metal box of appropriate size and level
with the help of spirit level.
The bottom portion of box
should match the marked
level as per consultant
approved height for switch/
socket and/or as per local
applicable wiring regulation
requirements.
Apply cement filler to fix the
box properly and leave for
setting, insert the required
lengths of conduits on their
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 12/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 12/17
paths and don’t connect
with boxes until next day.
Next day, after setting of
box connect the dropped
conduits for switch/socket
to the box.
Make sure the conduits are
not visible from outside
their route which could lead
improper plastering.
Before the plastering work
issue the inspection
requests for client so that
approval can be taken.
GI Conduit Installation
(Exposed Conduiting)
Take the following shop
drawings approved for
construction.
GI Conduiting layout
complete with section
details.
MEP coordination
drawing complete with
section details.
Architectural Drawing
Check the route of GI
Conduiting free from debris
and no obstruction of any
other activity. Arrange
scaffolding of sufficient
height approved by HSE
officer.
Mark the reference points
on wall/ column as per civil
architectural drawing.
Identify the circuit start
point and end & mark GI
Conduiting route as per
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 13/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 13/17
approved drawings.
Make hole in concrete for
anchor bolts/rawel plug &
fix rawel plug inside hole
then fix base of saddle by
screw every 1m span.
Use approved GI
Conduiting & bends as per
site condition and drawing.
Remove sharp edge of cut
length of conduit by filing.
Join the lengths using the
threaded joints and fittings.
Install conduit and tight
with saddle and screw.
Make earthing of GI
Conduiting & Check for
continuity.
Apply the zinc paint on the
exposed threaded area
which is not covered.
Installation of GI
Conduiting shall be
checked by internal QA/QC
Engineer as per drawings
and quality of installationbefore offering
consultant/client for
inspection.
9. Construction Program
As per main project
program
9.1 Housekeeping
The work area shall be
maintained neat and tidy as
reasonably practical at all times.
9.2 Protection of Executed
Works
Executed works in areas were
other works are still being
carried out shall be protected as
per the contract requirements.
9.3 Responsibilities
9.4 Records
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 14/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 14/17
In accordance with the Quality
Management System, the
following records will be
maintained as documentary
evidence of the establishment of
this method statement:
10. Inspection and Testing
In Process works shall be
monitored for quality of
workmanship and
installation against
approved shop drawings
by the relevant supervisor.
All works shall be inspected
for conformance to
specification.
The inspection formats
shall be used in
accordance with the
requirements of the main
contractor UNEC.
An inspection request for
the PVC conduits and
boxes shall be submitted
one day prior to the
consultant.
11. Related Forms
As per required forms,
from main contractor and
consultant.
12. Attachments
ITP
Installation ChecklistsRisk Assessment
DOWNLOAD METHOD
STATEMENT IN WORD
FORMAT
Share this:
Facebook 2 Reddit
Google Tumblr
More Method
Statements:
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 15/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 15/17
1. Method Of Statement For
Installation of GI
Conduits & Accessories
For Electrical Works
Method Of Statement For
Installation of GI Conduits &
Accessories For Electrical Works
is given below for the reference of our visitors if you want to use this
method statement...
2. Method Statement For
Installation of Motor
Control Centre MCC
Panel This below procedure
shall be followed for the installation
of MCC panels.All components /
materials received at site shall be
inspected and ensured against
approved material submittal. Any
discrepancies, damages etc...
3. Testing &
Commissioning Of CCTV
Cameras – Method
Statement The objectives of
the process of testing and
commissioning of CCTV camera
is to verify proper functioning of the
equipments and system after
installation, and to ensure the
performance of the installed
system...
4. Method Statement For
Installation Of CCTV
Camera Security System
The purpose of this method
statement is to provide guidelines
and steps for the cctv installation
of security systems by describing
the Work to be executed, how it is
to...
5. Method Statement For
Fire Alarm System
Installation & Testing
Below is the method statement for
the installation of fire alarm
system which can be modified for
different type of systems like
HSSD or Vesda etc. The steps are
very...
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 16/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 16/17
6. Method Statement For
Installation Of
Emergency Lighting
System The below method
statement describes some
standard operating steps to install
the emergency lighting system for
any kind of project the methodstatement can be modified as per
different project...
7. Method Statement For
Installation Of Electric
Water Heaters The
procedures for the installation and
fixing of electric water heaters with
supports and accessories shall be
done as per the manufacturer’s
recommended guidelines and
installation instructions and as
per...
8. METHOD STATEMENT
FOR TESTING &
COMMISSIONING OF
PRESSURIZATION UNIT
The purpose of this procedure is to
define the step by step method to
implement the correct practices for
the pre-commissioning &
commissioning of Pressurization
Unit through the guidelines
contained...
9. Method Of Statement For
Installation of wires and
cables – Wiring Below is the
list of equipment / Tools required
for installation of wires and cables,
which cab be used for different
projects after doing the
customization as per the project...
10. METHOD STATEMENT
FOR INSTALLATION OF
MDB, SMDB, DB, MCC &
CAPACITOR BANK 1.0
PURPOSE The purpose of
generating this method statement
is to define the procedure step by
step to implement the correct
practices for Installation of MDB,
SMDB, DB, MCC &...
7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI
http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 17/17
8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI
◀ Installation & Leakage
Testing Of Drainage Piping
Method Of Statement for
Testing & Commissioning Of
Water Filtration System ▶
Copyright 2015. All Rights Reserved. Copying and republishing of our content is not allowed.
Tags: architectural, GI Conduit,
Installation of GI Conduits &
Access ories, Method Statement,
Method Statement For Conduit
Installation, PVC Conduit,
statement, works