method statement for conduit installation including accessories pvc & gi

17
 8/6/2015 Method Statement for Conduit Installation Including Accessories PVC & GI http://w ww. me thodstatem enthq.com /m ethod- statem ent- instal lati on-g i-condui ts- accessor ies.htm l 1/17 Method Statement for  Conduit Installation I n cluding A ccessories P VC & GI 2 Like Tweet  0 Below is a comprehensive method statement for conduit installation which can be used for purpose of any project and it can be approved easily by consultants because it covers all aspects of a standard conduit installation method. We have also given the download link for method statement for conduit installation on below page which will help you to easily modify the word and excel files that also include ITP, inspection checklists and Home Downlo ad Me thod Sta te me n ts Pro jec t Q ua lity Plan Disclaimer  Pr iv a cy Poli cy Su pp ort Project HSE Plan Inspec tion Checklists Pro jec t Manage men t Req ues t A Met hod Sta tement START A CONVERSATION 367 people like this. Li ke Share SUBSCRIBE You will Receive Each New Method Statement In Your Email as Soon as It Is Published. Enter your email address: Subscribe Delivered by FeedBurner "We recommend these Project Management Templates for delivering your projects successfully." POPULAR METHODSTATEMENT S List Of Mandatory Tests For Transformers  August 5th, 2015 The following routine tests specified in IEC726 shall be carried out at the manufacturer's works on [...] List Of Common Tests For Diesel Generator Testing  August 5th, 2015 The following site tests shall be carried out in order to determine whether the DG material and appa  [...] Method Statement For Testing And Commissioning Of Laboratory Air Flow Control System & Fumes 9 Email Shar e

Upload: gangadharan000

Post on 13-Jan-2016

267 views

Category:

Documents


20 download

DESCRIPTION

Method Statement for Conduit Installation Including Accessories PVC & GI

TRANSCRIPT

Page 1: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 1/17

8/6/2015 Method Statement for Conduit Installation Including Accessories PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 1/17

Method

Statement for 

Conduit

Installation

Including

Accessories

PVC & GI

2Like

Tweet   0

Below is a

comprehensive method

statement for conduit

installation  which can be used

for purpose of any project and it

can be approved easily by

consultants because it covers all

aspects of a standard conduit

installation method.

We have also given the

download link for method 

statement for conduit installation

on below page which will help

you to easily modify the word

and excel files that also include

ITP, inspection checklists and

Home Download Method Statements Project Quality Plan Disclaimer 

Privacy Policy Support Project HSE Plan Inspection Checklists

Project Management Request A Method Statement

START A CONVERSATION

367 people like this.Like Share

SUBSCRIBE

You will Receive Each New Method Statement In Your Email as Soon as It Is

Published.

Enter your email address:

Subscribe

Delivered by FeedBurner 

"We recommend these Project Management Templates for delivering 

your projects successfully." 

POPULAR METHODSTATEMENTS

List Of Mandatory Tests For Transformers August 5th, 2015

The following routine tests specified in IEC726 shall be carried out at

the manufacturer's works on [...]

List Of Common Tests For Diesel Generator Testing August 5th, 2015

The following site tests shall be carried out in order to determine whether the

DG material and appa  [...]

Method Statement For Testing And CommissioningOf Laboratory Air Flow Control System & Fumes

9 Email

Shar e

Page 2: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 2/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://www.methodstatementhq.com/method-statement-insta llation-gi-conduits-accessories.html   2/17

risk assessment etc.

TABLE OF CONTENTS

1. Purpose  

2. Scope

3. Legislation and

Code of Practice

4. Reference

5. Definitions6.

Resources

 

6.1. Equipment

6.2. Safety of 

Equipment’s

7. Safety Precautions

7.1. Construction

Hazards

7.2. Personal Protective

Equipment

7.3. Safety Training and

Emergency procedures

7.4. First Aid

8.Detailed

Construction

Sequence

(Methodology)

8.1. Procedure

9.Construction

Program9.1

Housekeeping9.2

Protection of Executed

Works9.3

Responsibilities

9.4 Records

10.Inspection and

Testing

11.Related Forms

 Hood MonitoringJuly 27th, 2015

Below is the method statement description for performing the testing and

commissioning of laboratory   [...]

METHOD STATEMENT FOR THE COMMISSIONINGOF EC2001 EASI-CHECK EMERGENCY LIGHTING

MONITORING SYSTEM WITH OR WITHOUT SITEMONITOR/GRAPHICS PACKAGEJuly 20th, 2015

This method statement is for commissioning of Easi-Check Emergency

Lighting Monitoring Systems compr   [...]

Download Method Statement for Installation Of DehumidifiersJuly 13th, 2015

Download Method Statement for Installation Of Dehumidifiers Downloadpackage contains the Method S   [...]

Download Method Statement for Installation Of Earthing & Bonding System & AccessoriesJuly 12th, 2015

Download Method Statement for Installation Of Earthing & Bonding System &

 Accessories Down [...]

Download Method Statement for Installation Of Chilled Water Pressurization Unit & Expansion TankJuly 7th, 2015

Download Method Statement for Installation Of Chilled Water Pressurization

Unit & Expansion Tank   [...]

Page 3: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 3/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 3/17

12.Attachments

1. Purpose

This document describes the

method statement for conduit

installation which includes GI &

PVC conduits and accessoriesfor the project, and to ensure

that all concerned persons are

familiar with the sequence of 

activities, utilization of resources,

and execution of the works in

compliance with applicable

Safety and Quality Procedures,

and Project Documents and

Specification.

DOWNLOAD METHOD

STATEMENT IN WORD

FORMAT

2. Scope of Works

For Installation of 

GI Conduits

This method statement isintended to outline the activities

and the methods used for the

Installation of GI conduits and

accessories. All activities will be

carried out in accordance with

the contract details and in full

compliance to the Contract

Specifications and documents.

 All work within the rights-of-way

of the standards and

specifications will be done in

compliance with requirements

issued by authorities.

3. Legislation and Code of 

Li

0

T

Page 4: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 4/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 4/17

Practice

 All related codes and

standards referenced in the

project electrical

specifications.

4. Reference

Contract Specifications

 Approved Drawings

5. Definitions

6. Resources

6.1. Equipment / Tools

NO. DESCRIPTION

1   Bending machine

2   Die sets

3   Measuring tape

4   Screw driver 

5   Chalk mate thread

6   Oil

7   Drill machine

8   Screw driver 

6.2 Safety of Equipment’s

Necessary measures will be

taken for the safety of the

equipment and any other works

affected by the works subject of 

this document. Relevant entities

which might require protection

include any such works in the

vicinity of the area of work or on

the service access or discharge

path.

9

Email

Share

Page 5: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 5/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 5/17

The construction team will

ensure that any such

requirements are documented.

  7. Health, Safety &

the Environment

The hazards identified above will

be controlled under the overall

Project Safety Plan which is a

separate document

communicated to all parties on

the project.

7.2. Personal Protective

Equipment (tick as

appropriate)

The works subject of thisdocument requires that the PPE

must be used as required.

7.3. Safety Training and

Emergency procedures

Before commencing any works,

all employees will attend a site

safety induction training to

ensure all safety measures are

understood and implemented

and to cover specific procedures

in case of emergency. If 

necessary, practical training

exercises will be conducted on

escape routes, signage,

evacuation and rescue.

DOWNLOAD METHOD

STATEMENT IN WORD

FORMAT

7.4. First Aid

Prior to the commencement of 

work, arrangements will be

made for medical facilities and

medical personnel to be

available from prompt attention

to the injured person. The

contractor’s vehicle assigned tothe job site will be used for 

transporting the injured person

to the first aid station and to the

nearest hospital when required.

Page 6: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 6/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 6/17

8. method

statement for 

conduit

installation

General Procedure for conduit

installation is given below after 

which area wise details are

provided like method statement

for conduit installation  in slab,

walls and exposed areas etc.

Steps for exposed conduit

installation on walls &

ceilings etc.

Step 1:  Take the following

drawings approved for 

construction.

GI conduits layout

complete with section

details.

MEP coordination drawing

complete with section

details.

 Architectural Drawing

Step 2: Procedure of method

statement for conduit installation

1. Check the route of GI

conduiting to make sure

that it is free from debris

and obstruction of any

other activity.

2. Arrange scaffolding of 

sufficient height which is

checked by scaffolding

Page 7: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 7/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 7/17

inspector/ safety officer 

before using the same for 

installation.

3. Mark the reference points

on wall/ column as per civil

architectural drawing.

4. Identify the circuit start

point and end points to

mark the conduit route as

per approved drawings.

5. Make hole in wall/concrete

using drill machine for 

rawal plug, fix rawal plug

inside hole and then fix

base of saddle by screw

every 2 meter span.

6. Use recommended andapproved GI conduiting &

bends as per site condition

and drawing. Remove

sharp edge of cut length of 

conduit by filing.

7. Install conduits and all

accessories as per 

approved shop drawing

and tight with saddle and

screw, make joints using

threaded fittings.

8. Installation of GI conduits

shall be checked by

internal quality engineer as

per drawings and quality of 

installation before offering

consultant/client for 

inspection.

9. Conduits are not to cross

pipe shafts, vents or 

opening.

10. Additional threaded cuts on

GI conduits are to be

painted with zinc based

coating resistant to

corrosion.

11. Approved clamps to be

used for the supports.

12. Maximum spacing of 

supports for different

conduit sizes to be

Page 8: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 8/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 8/17

clarified.

13. Conduits on walls are to be

run neatly, horizontally or 

vertically.

14. Conduits are to be used for 

exposed installations over 

false ceilings when the

false ceiling is used as

return plenum.

15. Conduits is to be used for 

all installation in elevator 

machine room and shafts,

electrical equipment

rooms, parking floor, solid

waste rooms, etc.

16. All works on site will be as

per electrical specificationsand as per applicable

electrical wiring

regulations.

17. The risk assessment

mentioning necessary

control measures shall be

attached to this method

statement to follow and

implement the

requirements

method statement for 

conduit installation In

Concrete Slab

Following tools should be

arranged before starting the job.

Dia (20 & 25 ) mm pipe

Bender 

Mini Hacksaw Frame with

Blades

Choke Lime Powder with

sufficient length of Thread

500gm Hammer 

Measuring Tape

End Cutter ( Kalwa )

Page 9: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 9/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 9/17

PVC Conduit Installation

Procedure

Ensure that the civil people

have finished ply/post

tension work on the slab.

 Arrange the approved shop

drawings for the area of 

installation.

Mark first the wall location

for lower floor in slab as

per latest Architecture

layout so that it will be easy

to locate the drops for 

switch, thermostat and any

other drops required for 

electrical system.

Mark the opening size in

Electrical Room and

Telephone room as per 

approved electrical

drawing.

Mark the Electrical points

on the slab as per 

approved Electrical Layout

and fix proper shape and

size of the Circular Boxwith the help of nail/mess

in case of plywood slab

and provide steel bar 

chairs for fixing the box in

case of post tension slab.

Just after completing the

first layer of steel, start pvc

conduiting work with

different sizes of conduit

based on electrical system

requirements and as per 

drawings. Always loop the

two way switches with 20

mm conduit as the number 

of wires will be more and

only switch drop pipe will

not be sufficient for pulling

all these wires.

Try to avoid theoverlapping of conduits

and keep some distance

between the conduits for 

Page 10: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 10/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 10/17

low current and

power/Lights.

Just after completing the

work tight the conduits with

binding wire and mark the

circuit numbers.

identification for the raised

pipe in slab for upper slabto be done for power, TV

and telephone systems

and closing the mouth of 

pipe with the help of 

masking tape .

The site Engineer/Foreman

should check the proper 

size of conduit and circular 

box, opening size in both

Electrical and Telephone

room and be sure the work

is completed as per 

approved Electrical shop

drawing.

Before the concrete

pouring the PVC conduit

installation to be inspected

and approved by

consultant/client/contractor.

During concrete pouring,

keep electricians for taking

care of conduit to avoid

any damage by others or 

dislocation of joints.

method statement for 

conduit installation (GI

Box & GI/PVC Conduitin Walls)

Following tools should be

arranged before starting the job.

9” Grinder with cutting disc

Mini Hacksaw Frame with

Blades

White chalk /Marker 

1 KG Hammer 

Measuring Tape

Sprit Level

Water Level Pipe

Page 11: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 11/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 11/17

Point & Flat Chisels

Trowel

Pipe Bender 

Method Statement for 

Conduit Installation inside

the Wall – PVC

Ensure that the civil people

have finished block wall

and clearance is given to

proceed for electrical

works.

Check the required

reference markings are

available for FFL (finished

floor levels).

Mark the location of 

switch/socket and conduit

route on proper height

based on approved shop

drawing.

Ensure the box size andaccordingly cut a bit larger 

size of box in marked place

of block wall with sufficient

depth.

Start cutting the marked

place for conduit run with

the help of grinder and chip

with hammer after cutting.

Fix the GI Metal box of appropriate size and level

with the help of spirit level.

The bottom portion of box

should match the marked

level as per consultant

approved height for switch/

socket and/or as per local

applicable wiring regulation

requirements.

 Apply cement filler to fix the

box properly and leave for 

setting, insert the required

lengths of conduits on their 

Page 12: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 12/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 12/17

paths and don’t connect

with boxes until next day.

Next day, after setting of 

box connect the dropped

conduits for switch/socket

to the box.

Make sure the conduits are

not visible from outside

their route which could lead

improper plastering.

Before the plastering work

issue the inspection

requests for client so that

approval can be taken.

GI Conduit Installation

(Exposed Conduiting)

Take the following shop

drawings approved for 

construction.

GI Conduiting layout

complete with section

details.

MEP coordination

drawing complete with

section details.

 Architectural Drawing

Check the route of GI

Conduiting free from debris

and no obstruction of any

other activity. Arrange

scaffolding of sufficient

height approved by HSE

officer.

Mark the reference points

on wall/ column as per civil

architectural drawing.

Identify the circuit start

point and end & mark GI

Conduiting route as per 

Page 13: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 13/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 13/17

approved drawings.

Make hole in concrete for 

anchor bolts/rawel plug &

fix rawel plug inside hole

then fix base of saddle by

screw every 1m span.

Use approved GI

Conduiting & bends as per 

site condition and drawing.

Remove sharp edge of cut

length of conduit by filing.

Join the lengths using the

threaded joints and fittings.

Install conduit and tight

with saddle and screw.

Make earthing of GI

Conduiting & Check for 

continuity.

 Apply the zinc paint on the

exposed threaded area

which is not covered.

Installation of GI

Conduiting shall be

checked by internal QA/QC

Engineer as per drawings

and quality of installationbefore offering

consultant/client for 

inspection.

9. Construction Program

 As per main project

program

9.1 Housekeeping

The work area shall be

maintained neat and tidy as

reasonably practical at all times.

 9.2 Protection of Executed

Works

Executed works in areas were

other works are still being

carried out shall be protected as

per the contract requirements.

 9.3 Responsibilities

9.4 Records

Page 14: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 14/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 14/17

In accordance with the Quality

Management System, the

following records will be

maintained as documentary

evidence of the establishment of 

this method statement:

10. Inspection and Testing

In Process works shall be

monitored for quality of 

workmanship and

installation against

approved shop drawings

by the relevant supervisor.

 All works shall be inspected

for conformance to

specification.

The inspection formats

shall be used in

accordance with the

requirements of the main

contractor UNEC.

 An inspection request for 

the PVC conduits and

boxes shall be submitted

one day prior to the

consultant.

11. Related Forms

 As per required forms,

from main contractor and

consultant.

12. Attachments

ITP

Installation ChecklistsRisk Assessment

DOWNLOAD METHOD

STATEMENT IN WORD

FORMAT

Share this:

Facebook   2   Reddit

Google Tumblr  

More Method

Statements:

Page 15: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 15/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 15/17

1. Method Of Statement For 

Installation of GI

Conduits & Accessories

For Electrical Works

Method Of Statement For 

Installation of GI Conduits &

 Accessories For Electrical Works

is given below for the reference of our visitors if you want to use this

method statement...

2. Method Statement For 

Installation of Motor 

Control Centre MCC

Panel This below procedure

shall be followed for the installation

of MCC panels.All components /

materials received at site shall be

inspected and ensured against

approved material submittal. Any

discrepancies, damages etc...

3. Testing &

Commissioning Of CCTV

Cameras – Method

Statement The objectives of 

the process of testing and

commissioning of CCTV camera

is to verify proper functioning of the

equipments and system after 

installation, and to ensure the

performance of the installed

system...

4. Method Statement For 

Installation Of CCTV

Camera Security System

The purpose of this method

statement is to provide guidelines

and steps for the cctv installation

of security systems by describing

the Work to be executed, how it is

to...

5. Method Statement For 

Fire Alarm System

Installation & Testing

Below is the method statement for 

the installation of fire alarm

system which can be modified for 

different type of systems like

HSSD or Vesda etc. The steps are

very...

Page 16: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 16/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

http://w ww .m ethodstatem enthq.com /m ethod- statem ent- instal lati on- gi -condui ts- accessor ies.htm l 16/17

6. Method Statement For 

Installation Of 

Emergency Lighting

System The below method

statement describes some

standard operating steps to install

the emergency lighting system for 

any kind of project the methodstatement can be modified as per 

different project...

7. Method Statement For 

Installation Of Electric

Water Heaters The

procedures for the installation and

fixing of electric water heaters with

supports and accessories shall be

done as per the manufacturer’s

recommended guidelines and

installation instructions and as

per...

8. METHOD STATEMENT

FOR TESTING &

COMMISSIONING OF

PRESSURIZATION UNIT

The purpose of this procedure is to

define the step by step method to

implement the correct practices for 

the pre-commissioning &

commissioning of Pressurization

Unit through the guidelines

contained...

9. Method Of Statement For 

Installation of wires and

cables – Wiring Below is the

list of equipment / Tools required

for installation of wires and cables,

which cab be used for different

projects after doing the

customization as per the project...

10. METHOD STATEMENT

FOR INSTALLATION OF

MDB, SMDB, DB, MCC &

CAPACITOR BANK 1.0

PURPOSE The purpose of 

generating this method statement

is to define the procedure step by

step to implement the correct

practices for Installation of MDB,

SMDB, DB, MCC &...

Page 17: Method Statement for Conduit Installation Including Accessories PVC & GI

7/18/2019 Method Statement for Conduit Installation Including Accessories PVC & GI

http://slidepdf.com/reader/full/method-statement-for-conduit-installation-including-accessories-pvc-gi 17/17

8/6/2015 M ethod Statem ent for C onduit Instal lation Including Accessor ies PVC & GI

◀ Installation & Leakage

Testing Of Drainage Piping

Method Of Statement for 

Testing & Commissioning Of 

Water Filtration System ▶

Copyright 2015. All Rights Reserved. Copying and republishing of our content is not allowed.

Tags: architectural, GI Conduit,

Installation of GI Conduits &

 Access ories, Method Statement,

Method Statement For Conduit

Installation, PVC Conduit,

statement, works