BIM in offshore structures
Mick Hodgson
Oil and Gas Technology Forum
![Page 2: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/2.jpg)
Tekla for offshore structures
Model and detail offshore steel structures including jackets, decks and flares
Ideal for engineers, detailers and fabricators involved in the design, fabrication
and management of offshore projects
Collaborate and share design and detailing data, material requirements and
project status through the model from design to erection phase
[Date]
2
![Page 3: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/3.jpg)
Tekla Structures
offshore modeling
Tekla Structures software can
handle large and complex
projects
Modelling tools cover all kinds of
standard profiles and materials
including tubular and elliptical
sections all the way individual
welds and bolts
Tekla Structures can easily
integrate to all offshore industry
standard packages, such as
PDS, PDMS, providing error-free
design and detailing[Date]
3[Subject / Author, edit by clicking Insert > Header & Footer]
![Page 4: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/4.jpg)
Tekla Structures offshore modelling
[Date]
4
![Page 5: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/5.jpg)
[Date]
5
Tekla Structures offshore modelling
![Page 6: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/6.jpg)
Tekla Structures offshore modelling
Work simultaneously
– Engineers, project managers, detailers or any other
party who wishes to view or control the model
– Window to reliable project information during the
fabrication process
Quality control assured
– Information such as engineering drawings easy to
access and always up to-date
Model the whole project
– from initial concept studies including 4D
visualisation to the design of structures, safety
systems and sustainability
– all the way from commissioning, modifications to
eventual decommissioning
[Date]
6
![Page 7: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/7.jpg)
Tekla Structures offshore modelling
[Date]
7
![Page 8: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/8.jpg)
Offshore Weld tools
8
![Page 9: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/9.jpg)
Tekla Structures
offshore workshop drawings
[Date]
9
![Page 10: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/10.jpg)
Tekla Structures offshore engineering drawings
[Date]
10
![Page 11: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/11.jpg)
Tekla Structures offshore listings
[Date]
11
![Page 12: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/12.jpg)
Integrate Tekla Structures
[Date]
12
Other trades Structural
ArchiCad
Autocad, ADT,
Microstation
Intergraph PDS
Aveva PDMS
SmartPlant
Catia
Standards:
IFC, CIS/2, SDNF, DSTV,
Proprietary formats:
DWG, DXF, DGN, …
![Page 13: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/13.jpg)
[Date]
13[Subject / Author, edit by clicking Insert > Header & Footer]
![Page 14: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/14.jpg)
[Date]
14Import/Export Samples
IMPORT
DWG/DXF
3D DXF
DSTV
SDNF
PDMS
CIMsteel (CIS/2)
Staad
SACS
Monorail
HLI
Calma
Plantview
MicasPlus
Eureka LPM
EXPORT:
DWG/DXF
3D DXF
DSTV
SDNF
PDMS
CIMsteel (CIS/2)
Staad
PML (ModelDraft)
PML (Frameworks)
HLI
Calma
MicroSAS
3D DGN
KISS
![Page 15: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/15.jpg)
[Date]
15Scheduling and planning Fabrication and logistics
Organization - A
BIM Consultant
Organization - B Organization - C
![Page 16: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/16.jpg)
[Date]
16[Subject / Author, edit by clicking Insert > Header & Footer]
Import/Export SamplesImport/Export Samples
![Page 17: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/17.jpg)
[Date]
17[Subject / Author, edit by clicking Insert > Header & Footer]
Import/Export SamplesImport/Export Samples
![Page 18: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/18.jpg)
[Date]
18[Subject / Author, edit by clicking Insert > Header & Footer]
Import/Export SamplesImport/Export Samples
![Page 19: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/19.jpg)
Construction Management
Module for Offshore Projects
Mick Hodgson
![Page 20: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/20.jpg)
Construction Management Module
CLASH CHECK MANAGER: Manage quality of design and
plans. Coordinate clashes and
utilize you detailing capacity
effectively
MODEL ORGANISER:Organize and manage your model.
Structure model and objects to
suitable purchase & work etc.
packages. Make reports & plans.
Create delivery lots
TASK MANAGER: Manage your detailing, fabrication and
erection schedules and sequences.
Coordinate schedules with customers
![Page 21: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/21.jpg)
BIM Estimation model created, material preliminary order and schedule created using
Task Manager and then exported to Primavera, Basic Clash check with Clash Check
Manager.
CM flow between the Companies
![Page 22: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/22.jpg)
[Date]
22[Subject / Author, edit by clicking Insert > Header & Footer]
Clash Check Manager example
![Page 23: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/23.jpg)
Contract won Primavera edited schedule imported back to Task Manager, detailing
progresses.
CM flow between the Companies
![Page 24: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/24.jpg)
Task Manager link to Primavera or
MS Project
![Page 25: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/25.jpg)
Shipping packages created using Model Organiser and Steel projects data passed
back through Task Manager to schedule and also model objects
CM flow between the Companies
![Page 26: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/26.jpg)
23.4.2012
Task Manager Sequencing
Order of the individual
objects inside task
– By properties
– By location
– By dragging
– By picking
Automated date/time
calculation of the
individual objects
![Page 27: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/27.jpg)
Model Organiser Example Material
![Page 28: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/28.jpg)
Model Organiser Example Welds
![Page 29: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/29.jpg)
Final As-Built BIM model Clash Check using Clash Check Manager
CM flow between the Companies
![Page 30: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/30.jpg)
[Date]
30
Tekla Structures Integration To
ERP/MIS and CNC Systems
[Subject / Author, edit by clicking Insert > Header & Footer]
![Page 31: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/31.jpg)
Steel Projects PLM CNC Production / Planning
![Page 32: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/32.jpg)
Steel Projects PLM Bar Nesting
![Page 33: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/33.jpg)
Steel Projects PLM Plate Nesting
![Page 34: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/34.jpg)
Steel Projects PLM CNC Planning and Time
Calculation
![Page 35: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/35.jpg)
New range of specialised HGG tube to
tube components in Tekla
![Page 36: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/36.jpg)
Links direct to all HGG profiling CNC machines
![Page 37: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/37.jpg)
Final product
[Date]
37
![Page 38: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/38.jpg)
BIM for the JobsiteTekla Structures > Trimble LM80 Integration
Special Industry Session for Contractors
![Page 39: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/39.jpg)
Tools in Tekla to integrate with Trimble
[Date]
39
Create Layout
Points
Create Layout
Files
Create DWG / DXF
![Page 40: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/40.jpg)
Pass files over to Nomad
[Date]
40
DXF DWG
Point data
Layout Files
![Page 41: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/41.jpg)
Selectable Point Data and Background Data
• Work together to help with orientation on the job site
With points alone it is difficult to
visualize where you are
Adding the Background data
helps to clarify where you are
![Page 42: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/42.jpg)
Used directly in the field
Increasing productivity with model-based layout
Accurate model data
![Page 43: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/43.jpg)
Also used for fabrication set out applications
[Date]
43
![Page 44: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/44.jpg)
Tekla Open API™
Integrating & Enhancing Tekla Structures
Eric Beyer - Product Manager / Steel
![Page 45: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/45.jpg)
Some examples
Radial Grid
Mini Toolbar
Task Manager
…
![Page 46: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/46.jpg)
Tekla for offshore structures
• Some 120 offshore construction projects
completed
• including modular deck drilling and
production platforms, integrated deck
platforms, wellhead platforms and
accommodation platforms
• Offshore Division has used Tekla
Structures to design its platforms for two
years
[Date]
46
![Page 47: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/47.jpg)
Tekla for offshore structures
[Date]
47
Halfdan BB is an unmanned
platform situated in the North
Sea at a location where the
depth reaches 50 m
Halfdan BB Tekla model was used successfully for various
purposes:
- Continuous monitoring of the weight of the
structure and the position of the deck
structure’s centre of gravity during the
design phase
- Creation of drawings for the client and
authorities for certification purposes
- Output of lists of materials purchasing
- Identifying and correcting any conflicts with
equipment, piping, cables, access routes,
etc.
- Drawings for developing the workshop
designs used on the construction site
![Page 48: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/48.jpg)
Tekla for offshore structures
With Tekla Open API, Saipem
was able to generate added
value by exploiting its own
design organization
Saipem have further customised
Tekla Structures to integrate
into overall project work
processes, both at
engineering level and
material procurement and
fabrication activities
[Date]
48
![Page 49: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/49.jpg)
Tekla for offshore structures
[Date]
49
Saipem have been able to design,
detail and manage a range of
projects using Tekla Structures
with their customised tools
Creation of internal macros for:
- offshore joints & nodes
- material properties & class for
MMS codification
- engineering breakdown & fabrication
sequences
Integration with Material Management
System
![Page 50: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/50.jpg)
Tekla for offshore structures
Integration to Material Management System
[Date]
50
![Page 51: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/51.jpg)
Tekla for offshore structures
Structural breakdown
[Date]
51
![Page 52: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/52.jpg)
Tekla for offshore structuresAssembly breakdown structure
[Date]
52
![Page 53: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/53.jpg)
Tekla for offshore structures
“The greatest benefit of using Tekla lies in the ability to
oversee the whole project since all of the
information is encompassed in the model. This is
also true of the execution of feasibility studies and
initial steps, assessment and evaluation of weights
and centres of gravity and the speed of verification
of project variations over the course of the work.”
[Date]
53
![Page 54: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/54.jpg)
Tekla for offshore structures
“We believe that in the future, Tekla will
contribute to further boosting the efficiency of our work
processes as well as the quality of the results that can be
derived from the model.”
[Date]
54
![Page 55: Presentation 5 Tekla Mick Hodgson](https://reader036.vdocuments.net/reader036/viewer/2022081723/55cf96f8550346d0338ef97a/html5/thumbnails/55.jpg)
Thank YouMore about Tekla