Transcript
Page 1: Project Name: Sylvan Hills Middle School Project ... · Distribution: APS, SHMS Project Team Date: July 18, 2014 – July 24, 2014 Comments: Weekly Status Report _____ Current Activities

Ft, Lauderdale Office – 3575 NW 53 Street • Ft. Lauderdale, FL 33309 • Phone (954) 733-4211 • Fax (954) 485-9688 Orlando Office - 5337 Millenia Lakes Blvd., Suite 140 • Orlando, FL 32839-3391 • Phone: (321) 939-0583 • Fax: (321) 939-1998

Atlanta Office - 1201 Peachtree Street 400 Colony Square, Suite 200 Atlanta, GA 30361 Phone: (404) 877-9181 Fax: (404) 870-9046

James A. Cummings, Inc.

A Tutor Perini Company And Teaming Partner

Randolph & Company, Inc.

1201 Peachtree Street

400 Colony Square, Suite 200

Atlanta, GA 30361

T: 404-877-9181

F: 404-870-9046

Project Name: Sylvan Hills Middle School

Project #: 10182100

Distribution: APS, SHMS Project Team

Date: July 18, 2014 – July 24, 2014

Comments: Weekly Status Report

_________________________________________________________________________________________

Current Activities Site Work

• Installation of Underground Storm Water system is continuing

• Installation of Grease Trap

Cafeteria

• Underground plumbing and electrical installation continuing

• Installation of concrete masonry unit underway

Page 2: Project Name: Sylvan Hills Middle School Project ... · Distribution: APS, SHMS Project Team Date: July 18, 2014 – July 24, 2014 Comments: Weekly Status Report _____ Current Activities

Ft, Lauderdale Office – 3575 NW 53 Street • Ft. Lauderdale, FL 33309 • Phone (954) 733-4211 • Fax (954) 485-9688 Orlando Office - 5337 Millenia Lakes Blvd., Suite 140 • Orlando, FL 32839-3391 • Phone: (321) 939-0583 • Fax: (321) 939-1998

Atlanta Office - 1201 Peachtree Street 400 Colony Square, Suite 200 Atlanta, GA 30361 Phone: (404) 877-9181 Fax: (404) 870-9046

James A. Cummings, Inc.

A Tutor Perini Company And Teaming Partner

Randolph & Company, Inc.

1201 Peachtree Street

400 Colony Square, Suite 200

Atlanta, GA 30361

T: 404-877-9181

F: 404-870-9046

Classroom Wing

• Underground electrical installation proceeding

• Preparation for Reinforced Concrete Slab installation

Administrative

• Underground plumbing installation proceeding

• Preparation for Reinforced Concrete Footing installation and concrete pouring continuing

Future Activities

• Steel Erection Commencement –October, 2014

• Roof/ Enclosure Commencement – December, 2014

• Dry-In – February, 2015

• Interiors Commencement – March, 2015

• Finishes Commencement – May, 2015

• Substantial Completion – July 01, 2015