project name: sylvan hills middle school project ... · distribution: aps, shms project team date:...
TRANSCRIPT
Ft, Lauderdale Office – 3575 NW 53 Street • Ft. Lauderdale, FL 33309 • Phone (954) 733-4211 • Fax (954) 485-9688 Orlando Office - 5337 Millenia Lakes Blvd., Suite 140 • Orlando, FL 32839-3391 • Phone: (321) 939-0583 • Fax: (321) 939-1998
Atlanta Office - 1201 Peachtree Street 400 Colony Square, Suite 200 Atlanta, GA 30361 Phone: (404) 877-9181 Fax: (404) 870-9046
James A. Cummings, Inc.
A Tutor Perini Company And Teaming Partner
Randolph & Company, Inc.
1201 Peachtree Street
400 Colony Square, Suite 200
Atlanta, GA 30361
T: 404-877-9181
F: 404-870-9046
Project Name: Sylvan Hills Middle School
Project #: 10182100
Distribution: APS, SHMS Project Team
Date: July 18, 2014 – July 24, 2014
Comments: Weekly Status Report
_________________________________________________________________________________________
Current Activities Site Work
• Installation of Underground Storm Water system is continuing
• Installation of Grease Trap
Cafeteria
• Underground plumbing and electrical installation continuing
• Installation of concrete masonry unit underway
Ft, Lauderdale Office – 3575 NW 53 Street • Ft. Lauderdale, FL 33309 • Phone (954) 733-4211 • Fax (954) 485-9688 Orlando Office - 5337 Millenia Lakes Blvd., Suite 140 • Orlando, FL 32839-3391 • Phone: (321) 939-0583 • Fax: (321) 939-1998
Atlanta Office - 1201 Peachtree Street 400 Colony Square, Suite 200 Atlanta, GA 30361 Phone: (404) 877-9181 Fax: (404) 870-9046
James A. Cummings, Inc.
A Tutor Perini Company And Teaming Partner
Randolph & Company, Inc.
1201 Peachtree Street
400 Colony Square, Suite 200
Atlanta, GA 30361
T: 404-877-9181
F: 404-870-9046
Classroom Wing
• Underground electrical installation proceeding
• Preparation for Reinforced Concrete Slab installation
Administrative
• Underground plumbing installation proceeding
• Preparation for Reinforced Concrete Footing installation and concrete pouring continuing
Future Activities
• Steel Erection Commencement –October, 2014
• Roof/ Enclosure Commencement – December, 2014
• Dry-In – February, 2015
• Interiors Commencement – March, 2015
• Finishes Commencement – May, 2015
• Substantial Completion – July 01, 2015