Route 1 WideningPARDON OUR DUST BRIEFING
April 27th, 2016 – 6:30 PM
Freedom High School Auditorium15201 Neabsco Mills Road
Woodbridge, VA 22191
2
Tonight's Objectives• Introduction of the Construction Team• Present Project Scope of Work
– Widen U.S. 1 from four to six lanes between Mary's Way and Annapolis Way
– Enhance access to the Woodbridge VRE kiss-and-ride facility– Construct new Route 1 bridge at Marumsco Creek– Improvements to Route 1 and Occoquan Road to improve traffic
operations– Construct a ten-foot shared-use path and six-foot sidewalk– Underground utilities along Route 1 (duct bank work has been
completed)• Construction Elements
– Sequence of Construction– Detours
• Answer your Questions
3
Project Team• Virginia Department of Transportation• Prince William County• Contractor: Fort Myer Construction
Corporation
4
ROUTE 1 WIDENINGConstruction Team & Contact Information
VDOT Construction Management contact information:• Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer
– (703) 259-2947 [email protected]• Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager
– (703) 259- 2769 [email protected]• Mike Hamp – Project Inspector
– (571) 722-6919 [email protected]• Michelle Stubenbordt – Project Records Manager/Sr. Inspector
– (571) 289-8003 [email protected]• Kathy Poole, P.E., CCM – Office Engineer
– (571) 319-6509 [email protected]
Contractor: Fort Myer Construction Corporation contact information:• Ardie Kalantar – Project Manager
– (202) 497-5377 [email protected]• Fabio Fernandes – Project Engineer
– (202) 345-0695 [email protected]• Rick Fernandes – Vice President
– (202) 437-4353 [email protected]
Field office location (open during normal business hours):– 13408 Jefferson Davis Highway, Woodbridge, VA 22191– Phone Number: TBD
Project updates will be posted on VDOT’s website at:http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp
5
Project Timeline
• Contract Executed: March 25th, 2016
• Notice to Proceed Date: April 11th, 2016
• Start of Construction: April 12th, 2016
• Final Completion: November 29th, 2019
Contract Value = $43,246,647.92
6
Project LocationProject 0123-076-004, C501
7
Project Information
Phase 2 FutureRoute 123 Interchange
Marumsco CreekBridge
End ProjectOccoquan River Bridge
Begin ProjectIntx. Marys Way
Project Field OfficeM
arys
Way
Mt.
Plea
sant
Dr
ive
Daw
son
Beac
h Ro
adOc
coqu
an R
oad
Rout
e 12
3
Occ
oqua
n R
iver
8
Project InformationProject Field Office
VRE Station
Marumsco Creek
Belmont Bay
I-95 Interchange
CSXT RailroadKiss And Ride
Mar
ys W
ay
Mt.
Plea
sant
Dr
ive
Daw
son
Beac
h Ro
ad
Occo
quan
Roa
d
Rout
e 12
3
Occ
oqua
n R
iver
9
Project InformationProject Field Office
Ornamental FenceRetaining Walls
Mar
ys W
ay
Occo
quan
Roa
dCSXT Railroad
Rout
e 12
3
Occ
oqua
n R
iver
Mt.
Plea
sant
Dr
ive
Daw
son
Beac
h Ro
ad
10
Typical Section
11
• Place Advance Warning Signs• Clearing and Grubbing • Building Demolitions • Remove Existing Raised Concrete Medians• Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound Side of Route 1• Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage From Station 49+25 to Station 67+25• Construct Temporary Pavement Wedge for Driveway Access
Construction Stage 1: thru Aug 2016
Occ
oqua
n Ro
ad
US Route 1
Daw
son
Beac
h Ro
ad
Easy Street
12
Construction Stage 2-1: Sept 2016 – Dec 2016
• Install Temporary Signals at Occoquan Road Intersection• Reroute Pedestrian Traffic to the Northbound Side of Route 1• Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous
Stage• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to
Station 64+00 and Easy Street Connector• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 64+00 to Station 67+75
Daw
son
Beac
h Ro
ad
Easy StreetEasy Street South
Occ
oqua
n Ro
ad
Mar
ys W
ay
US Route 1
Easy
Str
eet
Conn
ecto
r
Mar
umsc
o C
reek
13
Construction Stage 2-2 and 2-3: Jan 2017 – June 2017
Daw
son
Beac
h Ro
ad
Easy StreetEasy Street South
Occ
oqua
n Ro
ad
Mar
ys W
ay
• Close Easy Street South and Detour Traffic to Easy Street Connector and Construct Easy Street South Entrance• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 39+50 to Station 49+50• Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)
US Route 1M
arum
sco
Cre
ek
Easy
Str
eet
Conn
ecto
r
14
Construction Stage 3-1: July 2017 – Oct 2017
• Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2• Construct SB Proposed Pavement from Station 42+50 to Station 51+25• Construct Second Stage of the Bridge over Marumsco Creek• Install Temporary Signals at Annapolis Way and Occoquan Road• Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road• Relocate Waterlines and Sanitary Sewers
US Route 1
Mar
ys W
ay
Easy Street South
Mar
umsc
o C
reek
15
Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018
• Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75 and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00
• Construct WB Lanes of Annapolis Way• Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3-
3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes) • Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd• Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A)• Reroute Route 123 Traffic to Detour (Stage 3-4B)• Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B)
US Route 1
Occ
oqua
n Ro
ad
Rout
e 12
3
Route 123 Detour A
nnap
olis
W
ay
16
Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018
• Install Temporary Signals at Annapolis Way and Route 123 Intersections • Shift Route 123 Traffic to Newly Constructed Route 123 Pavement • Detour Annapolis Way Traffic and Construct Remaining Annapolis Way• Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3)• Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to
Bridge and Pavement Placed in Previous Stages• Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4)
Ann
apol
is
Way
Rout
e 12
3
US Route 1
17
Construction Stage 4-5: Jan 2019 – Apr 2019
• Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00
• Construct Third Stage of the Bridge over Marumsco Creek
18
Construction Stages 5 and 6: May 2019 – Nov 2019
STAGE 5• Construct NB Proposed Pavement from Station 38+25 to Station 42+50• Install Temporary Signal at Dawson Beach Road• Construct Dawson Beach Road Intersection • Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00• Shift NB Traffic to Newly Constructed NB Lanes• Construct Raised Median
STAGE 6• Place Final Pavement Surface and Pavement Markings
Mar
ys
Way
Daw
son
Beac
h Ro
ad
Occ
oqua
n Ro
ad
Mar
umsc
o C
reek
Easy Street South
19
Lane Closure Restrictions
Lane Closures will only be permitted:
Day Hours
Monday - Thursday 9:30 AM – 3:00 PM10:00 PM – 5:00 AM
Friday 9:30 AM – 12:00 PM10:00 PM – 9:00 AM
Saturday - Sunday 10:00 PM – 8:00 AM
Sunday - Monday 10:00 PM – 5:00 AM
Two-way Traffic Will Be Maintained At All Times!
20
Night Work
• Installation of Traffic Control Devices• Traffic Shifts• Pavement Milling and Overlays• Pavement Striping• Utility Relocations• Lane Closures
21
Rout
e 1
Furnace
Road
Annapolis
Way
Occoquan
Road
Route 123
Horner Road
Annapolis Way Detour – Stage 4
22
Pedestrian Detours & Bus Stop Coordination
• There Will be Several Pedestrian Detours
• Pedestrian Detour Signs Will be Provided
• All Bus Stops Will be Maintained During All Phases of Construction
• Bus Stops May be Temporarily Relocated But Will Remain ADA Compliant
23
Kiss and Ride
• Facilities Will Remain Open During Construction and After Construction
24
Question & Answer Session