route 1 widening "pardon our dust" meeting, april 27, 2016

24
Route 1 Widening PARDON OUR DUST BRIEFING April 27 th , 2016 – 6:30 PM Freedom High School Auditorium 15201 Neabsco Mills Road Woodbridge, VA 22191

Upload: vdot-northern-virginia

Post on 17-Feb-2017

4.362 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

Route 1 WideningPARDON OUR DUST BRIEFING

April 27th, 2016 – 6:30 PM

Freedom High School Auditorium15201 Neabsco Mills Road

Woodbridge, VA 22191

Page 2: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

2

Tonight's Objectives• Introduction of the Construction Team• Present Project Scope of Work

– Widen U.S. 1 from four to six lanes between Mary's Way and Annapolis Way

– Enhance access to the Woodbridge VRE kiss-and-ride facility– Construct new Route 1 bridge at Marumsco Creek– Improvements to Route 1 and Occoquan Road to improve traffic

operations– Construct a ten-foot shared-use path and six-foot sidewalk– Underground utilities along Route 1 (duct bank work has been

completed)• Construction Elements

– Sequence of Construction– Detours

• Answer your Questions

Page 3: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

3

Project Team• Virginia Department of Transportation• Prince William County• Contractor: Fort Myer Construction

Corporation

Page 4: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

4

ROUTE 1 WIDENINGConstruction Team & Contact Information

VDOT Construction Management contact information:• Chan B. Basnayake, P.E., PMP, CCM - Area Construction Engineer

– (703) 259-2947 [email protected]• Oscar D. Jamilla, DPE, PMP - Sr. Construction Manager

– (703) 259- 2769 [email protected]• Mike Hamp – Project Inspector

– (571) 722-6919 [email protected]• Michelle Stubenbordt – Project Records Manager/Sr. Inspector

– (571) 289-8003 [email protected]• Kathy Poole, P.E., CCM – Office Engineer

– (571) 319-6509 [email protected]

Contractor: Fort Myer Construction Corporation contact information:• Ardie Kalantar – Project Manager

– (202) 497-5377 [email protected]• Fabio Fernandes – Project Engineer

– (202) 345-0695 [email protected]• Rick Fernandes – Vice President

– (202) 437-4353 [email protected]

Field office location (open during normal business hours):– 13408 Jefferson Davis Highway, Woodbridge, VA 22191– Phone Number: TBD

Project updates will be posted on VDOT’s website at:http://www.virginiadot.org/projects/northernvirginia/route_1_widening.asp

Page 5: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

5

Project Timeline

• Contract Executed: March 25th, 2016

• Notice to Proceed Date: April 11th, 2016

• Start of Construction: April 12th, 2016

• Final Completion: November 29th, 2019

Contract Value = $43,246,647.92

Page 6: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

6

Project LocationProject 0123-076-004, C501

Page 7: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

7

Project Information

Phase 2 FutureRoute 123 Interchange

Marumsco CreekBridge

End ProjectOccoquan River Bridge

Begin ProjectIntx. Marys Way

Project Field OfficeM

arys

Way

Mt.

Plea

sant

Dr

ive

Daw

son

Beac

h Ro

adOc

coqu

an R

oad

Rout

e 12

3

Occ

oqua

n R

iver

Page 8: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

8

Project InformationProject Field Office

VRE Station

Marumsco Creek

Belmont Bay

I-95 Interchange

CSXT RailroadKiss And Ride

Mar

ys W

ay

Mt.

Plea

sant

Dr

ive

Daw

son

Beac

h Ro

ad

Occo

quan

Roa

d

Rout

e 12

3

Occ

oqua

n R

iver

Page 9: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

9

Project InformationProject Field Office

Ornamental FenceRetaining Walls

Mar

ys W

ay

Occo

quan

Roa

dCSXT Railroad

Rout

e 12

3

Occ

oqua

n R

iver

Mt.

Plea

sant

Dr

ive

Daw

son

Beac

h Ro

ad

Page 10: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

10

Typical Section

Page 11: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

11

• Place Advance Warning Signs• Clearing and Grubbing • Building Demolitions • Remove Existing Raised Concrete Medians• Construct Temporary Sidewalks and Reroute Pedestrian Traffic to Southbound Side of Route 1• Construct NB Proposed Pavement, Retaining Walls, Sidewalks and Drainage From Station 49+25 to Station 67+25• Construct Temporary Pavement Wedge for Driveway Access

Construction Stage 1: thru Aug 2016

Occ

oqua

n Ro

ad

US Route 1

Daw

son

Beac

h Ro

ad

Easy Street

Page 12: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

12

Construction Stage 2-1: Sept 2016 – Dec 2016

• Install Temporary Signals at Occoquan Road Intersection• Reroute Pedestrian Traffic to the Northbound Side of Route 1• Shift NB and SB Traffic to the East Using Existing Pavement and Pavement Placed in Previous

Stage• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 49+50 to

Station 64+00 and Easy Street Connector• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 64+00 to Station 67+75

Daw

son

Beac

h Ro

ad

Easy StreetEasy Street South

Occ

oqua

n Ro

ad

Mar

ys W

ay

US Route 1

Easy

Str

eet

Conn

ecto

r

Mar

umsc

o C

reek

Page 13: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

13

Construction Stage 2-2 and 2-3: Jan 2017 – June 2017

Daw

son

Beac

h Ro

ad

Easy StreetEasy Street South

Occ

oqua

n Ro

ad

Mar

ys W

ay

• Close Easy Street South and Detour Traffic to Easy Street Connector and Construct Easy Street South Entrance• Construct SB Proposed Pavement, Retaining Walls, Trail and Drainage From Station 39+50 to Station 49+50• Construct First Stage of the Bridge over Marumsco Creek (Stage 2-3)

US Route 1M

arum

sco

Cre

ek

Easy

Str

eet

Conn

ecto

r

Page 14: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

14

Construction Stage 3-1: July 2017 – Oct 2017

• Shift SB Traffic to Pavement and Partial Bridge Constructed in Stage 2• Construct SB Proposed Pavement from Station 42+50 to Station 51+25• Construct Second Stage of the Bridge over Marumsco Creek• Install Temporary Signals at Annapolis Way and Occoquan Road• Reroute Route 123 Pedestrian Traffic to Horner Road and Occoquan Road• Relocate Waterlines and Sanitary Sewers

US Route 1

Mar

ys W

ay

Easy Street South

Mar

umsc

o C

reek

Page 15: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

15

Construction Stage 3-2, 3-3, 3-4: Nov 2017 – June 2018

• Construct SB Proposed Pavement, Trail and Drainage from Station 70+00 to Station 82+75 and from Station 84+00 to Station 97+50 and from Station 98+00 to Station 101+00

• Construct WB Lanes of Annapolis Way• Construct Occoquan Road Proposed Pavement, Drainage and Sidewalks in Three Phases (3-

3A WB Lanes, 3-3B Center Lanes and 3-3C EB Lanes) • Sanitary Sewer Relocations Concurrent with this Stage South of Occoquan Rd• Construct Route 123 Detour and Install Temporary Signal (Stage 3-4A)• Reroute Route 123 Traffic to Detour (Stage 3-4B)• Construct Route 123 Proposed Pavement, Sidewalks and Drainage (Stage 3-4B)

US Route 1

Occ

oqua

n Ro

ad

Rout

e 12

3

Route 123 Detour A

nnap

olis

W

ay

Page 16: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

16

Construction Stage 4-1, 4-2, 4-3, 4-4: July 2018 – Dec 2018

• Install Temporary Signals at Annapolis Way and Route 123 Intersections • Shift Route 123 Traffic to Newly Constructed Route 123 Pavement • Detour Annapolis Way Traffic and Construct Remaining Annapolis Way• Construct NB Proposed Pavement from Station 93+00 to Station 99+75 (Stage 4-3)• Install Temporary Signal at Occoquan Road and Shift NB and SB Traffic to the West to

Bridge and Pavement Placed in Previous Stages• Construct SB Proposed Pavement from Station 101+00 to Station 104+00 and NB Proposed Pavement from Station 99+75 to Station 104+00 (Stage 4-4)

Ann

apol

is

Way

Rout

e 12

3

US Route 1

Page 17: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

17

Construction Stage 4-5: Jan 2019 – Apr 2019

• Construct NB Proposed Pavement, Drainage, Retaining Walls and Sidewalk from Station 42+50 to Station 67+25 and from Station 69+25 to Station 82+00

• Construct Third Stage of the Bridge over Marumsco Creek

Page 18: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

18

Construction Stages 5 and 6: May 2019 – Nov 2019

STAGE 5• Construct NB Proposed Pavement from Station 38+25 to Station 42+50• Install Temporary Signal at Dawson Beach Road• Construct Dawson Beach Road Intersection • Construct Remaining Sections of SB Route 1 from Station 39+00 to Station 43+00• Shift NB Traffic to Newly Constructed NB Lanes• Construct Raised Median

STAGE 6• Place Final Pavement Surface and Pavement Markings

Mar

ys

Way

Daw

son

Beac

h Ro

ad

Occ

oqua

n Ro

ad

Mar

umsc

o C

reek

Easy Street South

Page 19: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

19

Lane Closure Restrictions

Lane Closures will only be permitted:

Day Hours

Monday - Thursday 9:30 AM – 3:00 PM10:00 PM – 5:00 AM

Friday 9:30 AM – 12:00 PM10:00 PM – 9:00 AM

Saturday - Sunday 10:00 PM – 8:00 AM

Sunday - Monday 10:00 PM – 5:00 AM

Two-way Traffic Will Be Maintained At All Times!

Page 20: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

20

Night Work

• Installation of Traffic Control Devices• Traffic Shifts• Pavement Milling and Overlays• Pavement Striping• Utility Relocations• Lane Closures

Page 21: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

21

Rout

e 1

Furnace

Road

Annapolis

Way

Occoquan

Road

Route 123

Horner Road

Annapolis Way Detour – Stage 4

Page 22: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

22

Pedestrian Detours & Bus Stop Coordination

• There Will be Several Pedestrian Detours

• Pedestrian Detour Signs Will be Provided

• All Bus Stops Will be Maintained During All Phases of Construction

• Bus Stops May be Temporarily Relocated But Will Remain ADA Compliant

Page 23: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

23

Kiss and Ride

• Facilities Will Remain Open During Construction and After Construction

Page 24: Route 1 Widening "Pardon Our Dust" Meeting, April 27, 2016

24

Question & Answer Session