Transcript

U.S. Department of State Roof Maintenance Program

I N F O R M A T I O N F O R O F F E R O R S N o . 1

DATE: February 11, 2019

POST: San Salvador, El Salvador

SUBJECT: DCR Roof Replacement

This information to Offerors is to provide answers to questions posed by the contractors and to provide

supplemental information to the contractors. This information is non-binding and is not part of the

Contract Documents.

1. FRONT ELEVATION 2. FRONT ELEVATION

3. FRONT ELEVATION 4. ROOF AREA "A"

5. ROOF AREA "A" 6. ROOF AREA "A"

U.S. Department of State Roof Maintenance Program

7. ROOF AREA "A" 8. ROOF AREA "A"

9. INTERNAL GUTTER ROOF AREA "A" 10. ROOF AREA "I"

11. ROOF AREA "I" 12. ROOF AREA "B"

U.S. Department of State Roof Maintenance Program

13. ROOF AREA "F" 14. ROOF AREA "F"

15. ROOF AREA "F" 16. ROOF AREA "F"

17. METAL WALKWAY ROOF AREA "F" 18. METAL WALKWAY ROOF AREA "F"

U.S. Department of State Roof Maintenance Program

19. ROOF AREA "G" & "H" 20. ROOF AREA "G"

21. ROOF AREA "G" 22. ROOF AREA I

23. ROOF AREA E

U.S. Department of State Roof Maintenance Program


Top Related