1BHEL requested NTPC to re-route the 11KV Line passing through the Plant.

2BHEL requested NTPC to resolve the land issue and provide a trouble free land to expedite the progress

3BHEL requested NTPC to arrange CISF patrolling during the present working hours (08:00 AM to 17:30 PM)

4BHEL requested NTPC to expedite the Fencing to get an encumbrance free land to expedite the work

Grading & LevelingAREA LEVELLING & GRADING WORK:-

1Awarded to M/s Zuberi Engineering Company on 02.09.2014

2M/s Zuberi Engineering Companyreported at site in 3rd week of October, 2014.

3M/s Zuberi has started their works and shifted reference point(Co-Ordinate and Bench Mark) from NTPC Tandwa office to plant area as given by NTPC.

4Started the Survey work & work formally inagurated in presence of NTPC Official on 03 Nov. 2014.

5 M/s Zuberi have started levelling works by engaging excavator on 13th Nov. 2014 with reference co-ordinates but on date 16 Nov. 2014 levelling works had been stopped by villagers due to land related issues with NTPC.

6BHEL has identified Location of 10 nos. grid pillar for BTG area and M/s Zuberi Engineering Company started excavation work to install grid pillar on 25/11/2014.

7Two Nos. Grid pillar from NTPC reference point has been erected/installed and 3nos is in progress near proposed NTPC/BHEL office in plant area & rest 05 nos. is balance.

8Villagers have again stopped excavation work of Grid Pillar for BTG area due to same land related issues on 29/11/2014 at 03:00 pm..

9Survey Work for pre work level is in progress.RESOURSE DEPLOYMENT

Sl NoDESCRIPTIONNoSTATUSREMARKS

1Poclain 04 NoIdleIdle since 16.11.20142Dumper 30T Capacity04 NoIdleIdle since 16.11.20143Bolero / Bolero Camper02 NoWorking4Total Station01 Set IdleIdle since 16.11.20145Auto Level with Levelling Staff 01 Set Working6Manpowers30 Head4 Head Engaged26 Head Idle

GTIDAILY PROGRESS REPORT

DWG REF.:- PE-GE-405-602-C002 (Rev. 01)BORE HOLE TESTDATE :- 13/12/2014

GEOTECHNICAL INVESTIGATION OF NKSTPP 3x660 MW SITESL No BORE NOCO-ORDINATEGROUND LEVELSTATUSDEPTH (In m)SOIL (in m)ROCK (in m)LOCATIONNORTHEAST140118258171457.089Completed304.6525.35BOILER AREA241118258113456.638Completed30426344117568171455.692Completed40*4.2526.75445116568173453.611Completed202.917.1COMP HOUSE585115448613456.26Completed102.67.4BHEL OFFICE 686115918543457.672Completed202.517.5NTPS OFFICE 7117119398103453.361Completed204.7515.25TP - 2 AREA828120918113458.108Completed30*4.121.65TP - 1 AREA937118898113458.087Completed305.224.8BOILER AREA1039118508142457.176Completed304.2522.251129120918171457.815Completed35*4.225.05TP - 1 AREA1236119238142458.806Completed303.0526.95BOILER AREA1390115818341455.858Completed202.5517.45IDCT AREA1432120228113458.088Completed307.120.65BOILER AREA1531120228113458.958Completed304261688115388381456.729Completed204.7515.25IDCT AREA1722117987937457.457Completed35524.5CHIMNEY AREA1838118898187457.92Completed302.824.45BOILER AREA1933119858142458.953Completed304.1522.152034119588171458.742Completed303.7525.252123117837947456.855Completed30CHIMNEY AREA2213119327937460.287Completed402314119147937459.912Completed302430120568142458.325Completed30BOILER AREA2524117837925457.219Completed30CHIMNEY AREA263120477947459.577Completed30CHIMNEY AREA271459.32Completed355.75CHIMNEY AREA288460.05Running303.25IDCT AREA299460.398Completed253.25IDCT AREA3015460.141Completed303.5CHIMNEY AREA3125455.79Completed306IDCT AREA3227456.14Completed253.45IDCT AREA3362458.25Completed202.2517.75IDCT AREA34113458.072Completed303IDCT AREA3535459.131running30IDCT AREA362455.7Completed27.1IDCT AREANote :-1. Total no of Bore Hole = 120 Nos. 2. No. of Rigs = 8 Nos. 3. Additional 02 nos. rigs will be engage upto 18th Dec. 2014.4. Plate Load Test (PLT) started on 25/11/2014.5. DCPT has started on 29/11/2014.6. ERT has been started on 30/11/2014 and completed on 05/12/2014.7. Other test will be started from second week of Dec. 2014.* - As per ref. Note - 2 bore hole shall be drilled upto the depth indicated against each bore hole or upto 5 m in rock with continious RQD(Rock Quality Designation) of 50% whichever is earlier.

113GEOTECHNICAL INVESTIGATIONS TO BE CONDUCTED : -

Sl NoINVESTIGATIONPOINTS ALLOCATEDSTATUSREMARKS

1BORE HOLE (BH)12034/12008 nos. Rigs is working at site

2PLATE LOAD TEST (PLT)152/15done PLT 11.

3CYCLIC PLATE LOAD TEST (CPLT)15NOT YET STARTEDWill be taken from Dec. first week

4DYNAMIC CONE PENETRATION TEST (DCPT)2219/22Running

5TRIAL PIT (TP)5NOT YET STARTEDWill be taken from Dec. first week

6CROSSHOLE SHEAR TEST (CST)6NOT YET STARTEDWill be taken from Dec. third week

7PRESSURE METER TEST (PMT)9NOT YET STARTEDWill be taken from Dec. third week

8ELECTRICAL RESISTIVITY TEST (ERT)3939/39Completed on 05/12/2014

9FPT5015/50Running

RESOURSE DEPLOYMENT

Sl NoDESCRIPTIONNoSTATUSREMARKS

1Boring & Drilling Rigs09 SetsWorking5 Nos. working in Bore Holes & 01 No woring in DCPT2DCPT Equipment01 Set Working3PLT Equipment01 Set WorkingWorking at PLT - 114Total Station01 Set Working5Auto Level with Levelling Staff 01 Set Working6Tractor01 Set Working7Tanker01 Set Working8Manpowers45 HeadsEngaged

DAILY INVESTIGATION STATUS

Sl NoInvestigationPoints in BTGPoints in BOPRemarksPointStatusPoints Status1BORE HOLE (BH)5624/566410/64 ...U/P

2PLATE LOAD TEST (PLT)30/3121/12U/P

3CYCLIC PLATE LOAD TEST (CPLT)150/1500Not Started

4DYNAMIC CONE PENETRATION TEST (DCPT)1311/1390/9U/P

5TRIAL PIT (TP)10/140/4Not Started

6CROSSHOLE SHEAR TEST (CST)60/600Not Started

7PRESSURE METER TEST (PMT)90/900Not Started

8ELECTRICAL RESISTIVITY TEST (ERT)1717/172222/22Completed

Awarding StatusCONTRACT AWARD STATUSSl NONAME OF PACKAGENAME OF AGENCYLOI REFERENCELOI DATECONTRACT PERIODREMARKS1Construction of OWNER's OfficeM/s J K ConstructionPSER:SCT:NKP-C 1551:14:LOI:379318.06.1405 Month Reported at site and ready to start their work. Obtaining labour licence is under process.2Levelling & Grading and Roads & Drains worksM/S Zuberi Engineering Co.JaipurPSER:SCT:NKP-C1562:14LOI:391802.09.1424 MonthWork started on 03.11.2014 but stopped on 16.11.2014 due to land problem.3Construction Power system M/S M J EngineeringRanchiPSER:SCT:NKP-E1575:14:LOI-S:4008, E:4009 and O&M401029.10.1422 Months Reported at site and ready to start their work. Obtaining labour licence is under process.4Geo-Technical Investigation (2nd, Stage)M/S C E Testing Co. Pvt. Ltd.KolkataPSER:SCT:NKP-C1604:14:LOI:402604.11.1402 MonthWork in progress5Construction of 07 Nos. storage sheds.M/S Pradeep Str. Devnt. Pvt. Ltd.KolkataPSER:SCT:NKP-C 1570:14:LOI:403407.11.147 Months Reported at site and ready to start their work. Obtaining labour licence is under process.6Development of open storage yard M/S Pradeep Str. Devnt. Pvt. Ltd.KolkataPSER:SCT:NKP-C 1580:14:LOI:404712.11.1410 Month Reported at site and ready to start their work. Obtaining labour licence is under process.7Construction of BHEL Field hostel & quarters M/S AKS Construction Pvt. Ltd.Ranchi.PSER:SCT:NKP-C 1590:14:LOI:407920.11.1410 MonthNot yet reported at Site.

Telephone NosTelephone Nos. of BHEL Employees posted at NKP SiteSl NoNameDesignationMobile No.1Sh. Saroj Kr. DasGeneral Manager70336984512Sh. Biswanath TirkeyAGM/Cnst. Manager70336984523Sh. Rajatendu RoyManager/Civil70336984554Md IslamSr. AE/Civil70336984565Sh. Sunny VikashEngineer/Electrical70336984546Sh. Nakul KumarAsst. Engineer/Civil70336984587Sh. Amit Kumar KamalAsst. Engineer/Civil70336984598Sh. Mithilesh KumarAsst. Engineer/Civil70336984539Sh. Ritesh Raj ShrivastavaAsst. Engineer/Civil947059170710Sh. Rkesh KumarAsst. Officer/HR7033698457

Photo

BORE HOLE WORK U/P AT BOILER - 3 AREA

BORE HOLE U/P AT BOILER - 1 AREABRE HOLE WORK U/P AT CHIMNEY - 2 AREAM/S ZUBERI POCKLAIN STILL IDLE SINCE 16/111/2014PLATE LOAD TEST U/P AT BOP AREAPLATE LOAD TEST FOR PLT-10 (BOP AREA)PLATE LOAD TEST U/P AT PLT-11 (BOP AREA)IDLE POCKLAIN AT CONSTRUCTION SITESURVEY WORK BY M/S ZUBERI IS U/PSURVEY WORK AT SWITHYARD AREA