Caisson, Pier, Drilled shaft, and Drilled pier are -often used interchangeably in foundation engineering; all refer to a cast-in-place pile generally having a diameter ofabout 750 mm or more, with or without steel reinforcement and with o without an enlarged bottom. Sometimes the diameter can be as small as 305 mm. Advantages: 1. A single drilled shaft may be used instead of a group of piles. . !onstructing drilled shafts in deposits of dense sand and gra"el is easier than 3. #rilled shafts may be constructed before grading operations are completed. $. %hen piles are dri"en by a hammer, the ground "ibration may cause damage to near structures. &he use of drilled shafts a"oids this problem. 5. 'iles dri"en into clay soils may produce ground hea"ing and cause pre"iously dri mo"e laterally. (. &here is no hammer noise during the construction of drilled shafts; there is dur ). *ecause the base of a drilled shaft can be enlarged, it pro"ides great resistanc load. +. &he surface o"er which the base of the drilled shaft is constructed can be "isua . &he construction of drilled shafts generally utili es mobile e uipment, which, soil conditions, may pro"e to be more economical than methods of constructing pile 10. #rilled shafts ha"e high resistance to lateral loads. Disadvantages: 1. &he concreting operation may be delayed by bad weather and always super"ision. . As in the case of braced cuts, deep e/ca"ations for drilled shafts may induce ground loss and damage to nearby structures.

Upload: john-philip-garcia

Post on 04-Oct-2015

229 views

Category:

Documents


0 download

DESCRIPTION

shaft

TRANSCRIPT

Caisson, Pier, Drilled shaft, and Drilled pierare -often used interchangeably in foundation engineering; all refer to a cast-in-place pile generally having a diameter ofabout 750 mmor more, with or without steel reinforcement and with or without an enlarged bottom. Sometimes the diameter can be as small as 305 mm.

Advantages:1. A single drilled shaft may be used instead of a group of piles.2. Constructing drilled shafts in deposits of dense sand and gravel is easier than driving piles.3. Drilled shafts may be constructed before grading operations are completed.4. When piles are driven by a hammer, the ground vibration may cause damage to nearby structures. The use of drilled shafts avoids this problem.5. Piles driven into clay soils may produce ground heaving and cause previously driven piles to move laterally.6. There is no hammer noise during the construction of drilled shafts; there is during pile driving.7. Because the base of a drilled shaft can be enlarged, it provides great resistance to the uplifting load.8. The surface over which the base of the drilled shaft is constructed can be visually inspected.9. The construction of drilled shafts generally utilizes mobile equipment, which, under proper soil conditions, may prove to be more economical than methods of constructing pile foundations.10. Drilled shafts have high resistance to lateral loads.

Disadvantages: 1. The concreting operation may be delayed by bad weather and always needs close supervision. 2. As in the case of braced cuts, deep excavations for drilled shafts may induce substantial ground loss and damage to nearby structures.Drilled Shaft Schematic

Types of Drilled shaft1. Straight Shaft - It extends through the upper layer(s) of poor soil, and its tip rests on a strong load-bearing soil layer or rock. The shaft can be cased with steel shell or pipe when required (as it is with cased, cast-in-place concrete piles). For such shafts, the resistance to the applied load may develop from end bearing and also from side friction at the shaft perimeter and soil interface.

2. Belled Shaft - A belled shaft (see Figures b and c) consists of a straight shaft with a bell at the bottom, which rests on good bearing soil. The bell can be constructed in the shape of a dome (see Figure b), or it can be angled (see Figure c). For angled bells, the underreaming tools that are commercially available can make to angles with the vertical.

Construction ProceduresThere are three major types of construction methods: the dry method, the casing method, and the wet method.1. Dry Method of ConstructionThis method is employed in soils and rocks that are above the water table and that will not cave in when the hole is drilled to its full depth. The sequence of construction, shown in Figure 12.2, is as follows:Step 1.The excavation is completed (and belled if desired), using proper drilling tools, and the spoils from the hole are deposited nearby. (See Figure 12.2a.)Step 2.Concrete is then poured into the cylindrical hole. (See Figure 12.2b.)Step 3. If desired, a rebar cage is placed in the upper portion of the shaft. (See Figure 12.2c.)Step 4.Concreting is then completed, and the drilled shaft will be as shown in Figure 12.2

2. Casing Method of Construction - This method is used in soils or rocks in which caving or excessive deformation is likely to occur when the borehole is excavated. The sequence of construction is shown in Figure 12.3 and may be explained as follows:

Step 1. The excavation procedure is initiated as in the case of the dry method of construction. (See Figure 12.3a.)Step 2.When the caving soil is encountered, bentonite slurry is introduced into the borehole. (See Figure 12.3b.) Drilling is continued until the excavation goes past the caving soil and a layer of impermeable soil or rock is encountered.Step3. A casing is then introduced into the hole. (See Figure 12.3c.)Step 4.The slurry is bailed out of the casing with a submersible pump. (See Figure 12.3d.)Step 5. A smaller drill that can pass through the casing is introduced into the hole, and excavation continues. (See Figure 12.3e.)Step 6.If needed, the base of the excavated hole can then be enlarged, using an underreamer. (See Figure 12.3f.)Step 7. If reinforcing steel is needed, the rebar cage needs to extend the full length of the excavation. Concrete is then poured into the excavation and the casing is gradually pulled out. (See Figure 12.3g.)Step 8. Figure 12.3h shows the completed drilled shaft

3. Wet Method of Construction-This method is sometimes referred to as the slurry displacement method. Slurry is used to keep the borehole open during the entire depth of excavation. (See Figure 12.4.) Following are the steps involved in the wet method of construction:

Step 1. Excavation continues to full depth with slurry. (See Figure 12.4a.)Step 2.If reinforcement is required, the rebar cage is placed in the slurry. (See Figure 12.4b.)Step 3.Concrete that will displace the volume of slurry is then placed in the drill hole. (See Figure 12.4c.)Step 4. Figure 12.4d shows the completed drilled shaft. Figure 12.5 shows a drilled shaft under construction using the dry

Equipment1. Rotary Table-the rotary table is a machine that transmits energy from a power unit to rotate Kelly bar.

2. Kelly Bar-usually attached to a crane, or built into a truck or modified excavator.

MaterialsRebar cage- is constructed of longitudinal bars bent into rungs or continuous spirals.

Slurry- is sometimes used during the drilling. The purpose of this fluid is to support the walls of the excavation.

Grout - is used for both core holes and CSL pipes.