Directorate of Town Planning & Survey – Approvals Submission and
Follow up Procedures
Lunch Time Seminar
By: Omar Habouch13th of October, 2008
Contents
DTP&S OBS and the key departments/personnel.
DTP&S approval with respect to the project process stages.
What is preceding the DTP&S approval stage.
DTP&S approval letter formation.
Data required based on the type of approval submitted and its format.
Who is responsible for following up with DTP&S until approval is obtained.
Objectives
To establish submission and follow-up procedures
To identify the requirements for DTP&S approval request
To accelerate the approval process and minimize time wastage on follow-up activities (meetings and discussions)
Director General
CEO
Customer Service Centre
Land Allocation Office
Branches Affairs Office
Development & Follow-up Office
Director General’s Office
Planning Studies Office
CEO Assist. For Resources Affairs
CEO Assist. for Technical Affairs
Legal Affairs Office
PR Office
HR & Finance Department
IT DepartmentCompensation
Department
Public Services
Department
Geographical Information Department
Survey Department
HR Sec. E-GovernmentCompensation
Sec.
Financial Resources
Sec.
Technical Support &
Networks Sec.
Estimation Sec.
Admin Services Sec.
Programmes & Systems Sec.
Technical Sec.
Buildings Department
Roads & Transportation
Sec.
Geographical Information
Management Sec.
Basic Services Sec.
Data Treating & Developing
Sec.
Naming & Numbering Sec.
Geographical Data Exchange
Sec.
Survey Sec.
Drawing & Issue Sec.
Building License Sec.
Survey Projects Sec.
Building Inspection & Consultants’Qualification
Sec.
DTP&S OBS
DTP&S OBS – Key Dept. (s)
Director General
CEO
Customer Service Centre
Land Allocation Office
Branches Affairs Office
Development & Follow-up Office
Director General’s Office
Planning Studies Office
CEO Assist. For Resources Affairs
CEO Assist. for Technical Affairs
PR Office
HR & Finance Department
IT DepartmentCompensation
Department
Public Services
Department
Geographical Information Department
Survey Department
HR Sec. E-GovernmentCompensation
Sec.
Financial Resources
Sec.
Technical Support &
Networks Sec.
Estimation Sec.
Admin Services Sec.
Programmes & Systems Sec.
Technical Sec.
Buildings Department
Roads & Transportation
Sec.
Geographical Information
Management Sec.
Basic Services Sec.
Data Treating & Developing
Sec.
Naming & Numbering Sec.
Geographical Data Exchange
Sec.
Survey Sec.
Drawing & Issue Sec.
Building License Sec.
Survey Projects Sec.
Building Inspection & Consultants’Qualification
Sec.
DTP&S OBS – Key Personnel
Mr. Salah Bin Bitee – Director General
Eng. Hamdi Fareed – Acting Head of Public Services Department
Eng. Ali Shahin – Head of Basic Services Section
Eng. Akef Al Jamal – Head of Basic Services Division
DTP&S Approval With Respect To The Project Process Stages
PROSPECT STAGE
PROJECT INCEPTION REPORT
PRELIMINARY DESIGN
DTP&S APPROVAL
TENDER PERIOD
CONSTRUCTION CONTRACT
ESTABLISHMENT
DETAILED DESIGN
What Is Preceding The DTP&S Approval Stage?
PROSPECT STAGE
PROJECT INCEPTION REPORT
PRELIMINARY DESIGN
Prepare Preliminary Drawings
Issue RFI to Service Authorities
Submit to DTP&S for formal planning approval
Proceed to Detailed Design/Prepare & Submit Preliminary Design Report
Approved?
Yes
No
DTP&S Approval Letter Formation
FAO (Service approval,
Data inquiry, etc)
The subject first and
then the name of the
project (not doing this
increase the possibility
of getting the letter
missed in DTP&S)
Arabic spelling and
translation check
Cc to SMDD, DPW,
DTP&S Coordinator and
optional to SM
Data Required –Pumping Station Location Approval
Location Plan
Three Proposed Locations (If possible)
Setting Out Plan
Elevations
Cross Sections
Two Sets of All Drawings
Location Plan
PS Location
Three Proposed Locations
PS Options
Nominate three locations and
prioritize them
Draw a selection zone
Take photos on site for the
proposed options (optional)
Identify the Plot No. for each
option (if possible) or show and
designate the surrounding
facilities (e.g. parks, mosques, etc)
Setting Out Plan
Odour Control Unit
Elevations
Maximum Height
Cross Sections
Data Required –Rising Main Route Approval
Location Plan
Layout Plans
Services Cross Sections
Two Sets of All Drawings
Location Plan
Layout Plans
Show the offset from building line at:
RM pends
Constant offset
Every change in the offset
Services Cross Sections
Typical Services Corridor
Utility All Road Corridor WidthsOffset from Building Line
(m)
Electricity 1.22
Water 2.14
Etisalat 3.35 (2.75 for all road corridor less than 18m width)
Natural Gas 5.0 ± 0.5 m
Foul and Surface Water Drainage
7.00 m
UAE Armed Forces Telecom System
To be agreed on project by project basis
Overhead Pylons, Others To be agreed on project by project basis
Source: Internal Memo Ref. PGS 400 and dated 19/11/2003
Typical Services Corridor
Data Required –Lifting Station Location Approval
Services Layout
Three Proposed Locations (If possible)
Cross Sections
Two Sets of All Drawings
Services Layout
LS in the parking or the verge of road
General Arrangement - Layout
Overall Width
Overall Length
General Arrangement - Cross Section
Data Required –Temporary Stormwater Storage Ponds
Location Plan
Services Layout
Temporary SWD PS Plan
Temporary SWD PS Cross Section
Two Sets of All Drawings
Services Layout
Pond Cross Section
Pond Layout Plan
Temp. Facilities
Temporary SWD PS Plan
Temporary SWD PS Cross Section
Who is Responsible?
Project Manager Responsibility:
• The drawings are clear, complete, and follows the DTP&S
restrictions and limitations.
• The Approval Letter issued with the required details,
justifications, enclosure, etc.
• Provide the DTP&S Coordinator with the required details
and explanations at the follow-up stage.
• PM to provide the coordinator with a realistic deadlines to
priorities the coordinator efforts.
• Single point of contact with the coordinator within Halcrow
to avoid conflicting messages from different members of the
project team.
Who is Responsible?
DTP&S Coordinator Responsibility:
• Liaise between the project manager and
the DTP&S engineer since DTP&S
requires a single representative to deal
with them on all projects.
Recommended Procedure
Current Procedure
HalcrowSM DTP&S
Recommended Procedure (not yet approved)
SMHalcrow DTP&S
Process Direction
DTP&S Coordinator
SM Coordinator
SM Coordinator
Recommended Procedure - Form
Guidelines Summary
Clear location plan to be provided for all types of
approvals.
Setting out and services layouts should be detailed and
includes plots numbers.
The proposed or existing services to be colored with
different colors in order to make them easily identified by
the DTP&S engineer.
Photos to be taken for proposed PS, LS, etc locations
Approval Letters have to be directed to the appropriate
DTP&S department.
Guidelines Summary
Lifting stations to be in the internal roads’ parking areas or
the verges.
The proposed pumping mains or gravity sewers to be
allocated at 7 to 9m offset from the building line.
Offset from building line has to be shown on the layouts at
RM pends, constant offset, and every change in the offset.
Services cross sections have to be provided at corridors
with congested existing and proposed services as well as
for every type of corridor width is being identified along
the RM route.
Guidelines Summary
Don’t Send more than one approval in one Letter. For
example, if you need to approve location for a pumping
station and its rising main route. It would be better to
approve the location of the pumping station and based on
that you apply for the approval of the rising main since the
location of the PS might change from the proposed one.