    Thiru Ambuj Sharma, I.A.S.,Commissioner of Municipal

    AdministrationChepauk, Chennai-5

    1. All Municipal Commissioner,2. All Regional Directors of Municipal

    Administration.3. All Corporation Commissioners4. All Executive Directors, 3rd Grade

    Municipality.

    Roc .No.5789/02/E1, dated. 23.6.05

    Sir,

    Sub: Shifting of poles, lines, cables, transformers etc. due toroad works and local bodies revised order Issued Regarding.

    Ref: G.O.Ms.No.7, Energy (C3) Department dated 23.2.2005.-----

    I enclose herewith a copy of the reference cited for information and

    necessary further action.

    The same may be acknowledged.

    Sd/-R.Raghunathan,for Commissioner of Municipal

    Administration

    Copy to: All Officers of this Office.

    //forwarded by order//

    Superintendent.

  • 8/14/2019 Eb-pole Shifting - g

    2/2

    Abstract

    Electricity Shifting of electric poles, lines, cables, transformers etc., - Bearing itsexpenditure in some cases by the requisitioning bodies and Government and insome cases by Tamil Nadu Electricity Board Revised Orders Issued.

    Energy (C3) Department

    G.O.Ms.No.7 Dated: 23.02.2005

    Read:

    1. G.O.Ms.No.101, Energy Department, dt.18.12.2001.2. From the Chairman, Tamil Nadu electricity Board D.O.

    Letter No.SE/Comml/EE.3/AEE.1/F.22/CR.1360/2002dt. 5.3.2002 and 31.12.2003.

    3. Government letter No.2145/C3/2002-17, dt.26.3.2004 anddt. 09.11.2004.

    ***ORDER:

    In supersession of the Orders issued in the G.O. read above, theGovernment issue the following revised orders for compliance by all theconcerned:-i) While the Government and Government Departments require the shifting,the cost relating to that should be remitted by them to Tamil Nadu Electricity Boardby adding those costs in the estimate of the respective works itself.ii) In the case of National Highways works, the expenditure on shifting shouldbe borne by the State Government as the Central Government will not bear thecost.iii) In regard to cost of shifting works required by the Corporation,

    Municipalities and Town Panchayats, those expenditures should be borne by themprovided the Tamil Nadu Electricity Board while preparing estimates for worksshould fix over heads charge only at 7.5 % covering all items such as centage,storage etc., The concession of fixing this charge of 7.5 % is applicable only forthe above mentioned local bodies.iv) In regard to Panchayats, Panchayat Unions, shifting expenditure should beborne by Tamil Nadu Electricity Board itself are these Institutions are financiallyweaker.

    (BY ORDER OF THE GOVERNOR)R.SATAPATHY,

    SECRETARY TO GOVERNMENT

    Toxxxxxxxxxx

    Copy to:The Municipal Administration and Water Supply Department, Chennai-9.

    /true copy/

    Superintendent.