effective pm management
TRANSCRIPT
Effective PM Management with eMaint X3
Topics for Discussion
PM Schedules and Setup
Tools/Options for Better PM Planning
Generating and Managing PMs
PM Schedules and Setup
PM Schedules and Setup Basic Anatomy of the PM Schedule
Calendar Based: Static vs. Shadow
Meter Based: Static vs. Shadow
Suppression
Skip Days
Anatomy of the PM Schedule
Anatomy of the PM Schedule
Maintenance Calendar
Scenario: Calendar SchedulingIf we PROJECT what MIGHT
happen…..
Legend:
= PM Generate
= PM Close
= Baseline Interval
= New Calendar Interval
= New Meter Interval
11/4
9/25 10/25 11/25
9/30
11/49/30
12/4
12/14
10/30 1/14 2/17Another approach…
25 21
31 31 31 31
12/25 1/25 2/25
12/2
23
2/211/17
Solution: Use of Shadow on Calendar
Instead of this… Try this…
Scenario: Meter Scheduling
31500 32500 33550 33600
Monday Tuesday1000 Additional Miles
32500 Total Miles
Wednesday1050 Additional Miles
33550 Total Miles
Thursday50 Additional Miles33600 Total Miles
RUNNING
Scenario: Meter Scheduling
TOTALS
Monday500 Units Produced
500 Units Total
Tuesday1200 Units Produced
1700 Units Total
Wednesday100 Units Produced
1800 Units Total
Thursday500 Units Produced
2300 Units Total
500 1200 100 500
Scenario: Meter SchedulingIf we PROJECT what MIGHT happen…
Legend:
= PM Generate
= PM Close
= Baseline Interval
= New Calendar Interval
= New Meter Interval
10/5
100 Hrs. 150 Hrs.
10/25
50 Hrs. 200 Hrs.
100 Hrs.
9/25 10/30
250 Hrs.250 Hrs. 25 Hrs.
11/27
9/25 250 Hrs.
11/14 250 Hrs.
10/20 250 Hrs.
OR…
Shadow Meter •Displays current meter reading•Option to enter reading•‘Adjust Next PM Interval’ is automatic with Shadow Meter, so no need to checkmark.
Solution: Use of Shadow on Meter
Static: Produces the next PM based on the reading at the time the PM was generated.
Shadow: Produces next PM based on the reading at the time the work order is closed.
Scenario: Calendar Suppression
Goal: Setup a weekly PM to produce only on Tuesdays, but not if
previous PM work order is still open. What is best way to accomplish?
Scenario: PM Generated on 10/2/07
Scenario: Calendar Suppression
Hint: On Close out, update the Next PM Date to the following Tuesday since the completed date is later than the Next PM
date.
Scenario: Meter Suppression
With Suppress set to True, new work order will not
generate until the current work order is closed, even though meter threshold
has been met.
Scenario: Skip Days on PM Schedule
Goal: Setup Daily PMs so they will produce every day
except weekends. XXX
X
XXX
X
Tools/Options for PM Planning
Tools/Options for PM Planning
Estimated Hours Routing and Sequencing PM Groups Nesting Tasks vs. Procedures PM Parts Planning and Usage PM Assignments
◦‘Assign To’ field◦Assignment Table
Scenario: PM Routing & Sequencing
PM SchedulePM Routes allow groups of individual PM schedule records to be related to each other.
Route Sequencer option allows you to manipulate the route sequence.
Route Sequence allows you to control the order of the route, allowing personnel to follow the correct/optimized sequence for performing PM tasks. PM Manager
Scenario: PM Routing & Sequencing
PM Generation
Scenario: PM GroupingPM Schedule Similar to the Route
field, the PM Group field can be used to categorize PMs so they can be managed as a group.
PM Generation
During PM Generation, you can filter based on PM Group to only display tasks related to that group.
Scenario: Nesting
Daily Task
Procedure AProcedure BProcedure C
Weekly Task
Procedure AProcedure BProcedure C+ Procedure D+ Procedure E
Monthly Task
Procedure AProcedure BProcedure CProcedure DProcedure E+ Procedure F+ Procedure G
Scenario: Nesting
Scenario: PM Tasks vs. Procedures
Procedures
Break down the task into separate procedures.
Allows ability to “mix and match” individual task procedures to create more complex tasks.
Allows individual procedures to be assigned standard repair times for greater accuracy.
Perfect for safety procedures (i.e., lock out/tag out) which may be combined with various other procedures to create the required tasks.
Planning for Parts Usage on PMs
Planning for Parts Usage on PMs
PM Generation
Work Order Close out
‘Assign To’ Option
PM “Assign To”
Assignments OptionPM Assignments
PM Assignments
Assignments Option
Generating and Managing PMs
Generating and Managing PMs
Generating PMs◦Automatic Generate/PM Settings◦Manually Generate◦PM Generate Menu
PM Publisher Importing Meter Readings PM Manager
Options for Generating PMs
Automatic
Options for Generating PMs
Manually Generate
Options for Generating PMs
PM Generation – Preview
Options for Generating PMs
PM Generation - Complete
PM Task – Publishing Changes
Importing Meters
PM Manager
Change Values
Update standard times
PM Projection
Change Next PM Date
Route Sequencing
Q & A