Page 1: Effective PM Management

Effective PM Management with eMaint X3

Page 2: Effective PM Management

Topics for Discussion

PM Schedules and Setup

Tools/Options for Better PM Planning

Generating and Managing PMs

Page 3: Effective PM Management

PM Schedules and Setup

Page 4: Effective PM Management

PM Schedules and Setup Basic Anatomy of the PM Schedule

Calendar Based: Static vs. Shadow

Meter Based: Static vs. Shadow

Suppression

Skip Days

Page 5: Effective PM Management

Anatomy of the PM Schedule

Page 6: Effective PM Management

Anatomy of the PM Schedule

Page 7: Effective PM Management

Maintenance Calendar

Page 8: Effective PM Management

Scenario: Calendar SchedulingIf we PROJECT what MIGHT

happen…..

Legend:

= PM Generate

= PM Close

= Baseline Interval

= New Calendar Interval

= New Meter Interval

11/4

9/25 10/25 11/25

9/30

11/49/30

12/4

12/14

10/30 1/14 2/17Another approach…

25 21

31 31 31 31

12/25 1/25 2/25

12/2

23

2/211/17

Page 9: Effective PM Management

Solution: Use of Shadow on Calendar

Instead of this… Try this…

Page 10: Effective PM Management

Scenario: Meter Scheduling

31500 32500 33550 33600

Monday Tuesday1000 Additional Miles

32500 Total Miles

Wednesday1050 Additional Miles

33550 Total Miles

Thursday50 Additional Miles33600 Total Miles

RUNNING

Page 11: Effective PM Management

Scenario: Meter Scheduling

TOTALS

Monday500 Units Produced

500 Units Total

Tuesday1200 Units Produced

1700 Units Total

Wednesday100 Units Produced

1800 Units Total

Thursday500 Units Produced

2300 Units Total

500 1200 100 500

Page 12: Effective PM Management

Scenario: Meter SchedulingIf we PROJECT what MIGHT happen…

Legend:

= PM Generate

= PM Close

= Baseline Interval

= New Calendar Interval

= New Meter Interval

10/5

100 Hrs. 150 Hrs.

10/25

50 Hrs. 200 Hrs.

100 Hrs.

9/25 10/30

250 Hrs.250 Hrs. 25 Hrs.

11/27

9/25 250 Hrs.

11/14 250 Hrs.

10/20 250 Hrs.

OR…

Page 13: Effective PM Management

Shadow Meter •Displays current meter reading•Option to enter reading•‘Adjust Next PM Interval’ is automatic with Shadow Meter, so no need to checkmark.

Solution: Use of Shadow on Meter

Static: Produces the next PM based on the reading at the time the PM was generated.

Shadow: Produces next PM based on the reading at the time the work order is closed.

Page 14: Effective PM Management

Scenario: Calendar Suppression

Goal: Setup a weekly PM to produce only on Tuesdays, but not if

previous PM work order is still open. What is best way to accomplish?

Scenario: PM Generated on 10/2/07

Page 15: Effective PM Management

Scenario: Calendar Suppression

Hint: On Close out, update the Next PM Date to the following Tuesday since the completed date is later than the Next PM

date.

Page 16: Effective PM Management

Scenario: Meter Suppression

With Suppress set to True, new work order will not

generate until the current work order is closed, even though meter threshold

has been met.

Page 17: Effective PM Management

Scenario: Skip Days on PM Schedule

Goal: Setup Daily PMs so they will produce every day

except weekends. XXX

X

XXX

X

Page 18: Effective PM Management

Tools/Options for PM Planning

Page 19: Effective PM Management

Tools/Options for PM Planning

Estimated Hours Routing and Sequencing PM Groups Nesting Tasks vs. Procedures PM Parts Planning and Usage PM Assignments

◦‘Assign To’ field◦Assignment Table

Page 20: Effective PM Management
Page 21: Effective PM Management

Scenario: PM Routing & Sequencing

PM SchedulePM Routes allow groups of individual PM schedule records to be related to each other.

Route Sequencer option allows you to manipulate the route sequence.

Route Sequence allows you to control the order of the route, allowing personnel to follow the correct/optimized sequence for performing PM tasks. PM Manager

Page 22: Effective PM Management

Scenario: PM Routing & Sequencing

PM Generation

Page 23: Effective PM Management

Scenario: PM GroupingPM Schedule Similar to the Route

field, the PM Group field can be used to categorize PMs so they can be managed as a group.

PM Generation

During PM Generation, you can filter based on PM Group to only display tasks related to that group.

Page 24: Effective PM Management

Scenario: Nesting

Daily Task

Procedure AProcedure BProcedure C

Weekly Task

Procedure AProcedure BProcedure C+ Procedure D+ Procedure E

Monthly Task

Procedure AProcedure BProcedure CProcedure DProcedure E+ Procedure F+ Procedure G

Page 25: Effective PM Management

Scenario: Nesting

Page 26: Effective PM Management

Scenario: PM Tasks vs. Procedures

Procedures

Break down the task into separate procedures.

Allows ability to “mix and match” individual task procedures to create more complex tasks.

Allows individual procedures to be assigned standard repair times for greater accuracy.

Perfect for safety procedures (i.e., lock out/tag out) which may be combined with various other procedures to create the required tasks.

Page 27: Effective PM Management

Planning for Parts Usage on PMs

Page 28: Effective PM Management

Planning for Parts Usage on PMs

PM Generation

Work Order Close out

Page 29: Effective PM Management

‘Assign To’ Option

PM “Assign To”

Page 30: Effective PM Management

Assignments OptionPM Assignments

Page 31: Effective PM Management

PM Assignments

Assignments Option

Page 32: Effective PM Management

Generating and Managing PMs

Page 33: Effective PM Management

Generating and Managing PMs

Generating PMs◦Automatic Generate/PM Settings◦Manually Generate◦PM Generate Menu

PM Publisher Importing Meter Readings PM Manager

Page 34: Effective PM Management

Options for Generating PMs

Automatic

Page 35: Effective PM Management

Options for Generating PMs

Manually Generate

Page 36: Effective PM Management

Options for Generating PMs

PM Generation – Preview

Page 37: Effective PM Management

Options for Generating PMs

PM Generation - Complete

Page 38: Effective PM Management

PM Task – Publishing Changes

Page 39: Effective PM Management

Importing Meters

Page 40: Effective PM Management

PM Manager

Change Values

Update standard times

PM Projection

Change Next PM Date

Route Sequencing

Page 41: Effective PM Management

Q & A