EGLINTON CROSSTOWNEglinton-Mount Pleasant Construction Liaison CommitteeJuly 11, 2017
![Page 2: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/2.jpg)
2
Agenda
• Eglinton Station Update
• Mount Pleasant Station Update
![Page 3: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/3.jpg)
3
Eglinton Station Updates
Complete
Demolition of the Salvation Army Community Church
Demolition of the abandoned TTC bus depot
Wet utilities stages 1-3 (of 4)
Toronto Hydro stages 1a, 1b
Summer/Fall 2017
• Water main and sanitary sewer relocation works are ongoing at the Yonge-Eglinton intersection
• Toronto Hydro relocation (2b) ongoing on Duplex to Hillsdale to Yonge
• Shoring is underway at the Salvation Army and TTC bus depot sites and along the south side of Eglinton (Three rigs now in operation)
– This is the major activity of 2017; maps attached for each stage
![Page 4: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/4.jpg)
4
Eglinton Station Shoring Stage 1
![Page 5: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/5.jpg)
5
Eglinton Station Shoring Stage 2a
![Page 6: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/6.jpg)
6
Eglinton Station Shoring Stage 2b
![Page 7: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/7.jpg)
7
Eglinton Station Shoring Stage 3
![Page 8: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/8.jpg)
8
Construction Progress Picture
A third rig mobilized at the bus depot site
Crews building a guide wall for shoring
![Page 9: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/9.jpg)
9
Mount Pleasant Station Construction Update
Complete
Demolition at 280 and 280 Eglinton Ave E to make way for the Secondary Entrance
Demolition at 256-58 Eglinton Ave E to make way for the Main Entrance
Installation of geotechnical monitoring equipment
Long-term closure of Rawlinson Ave for site trailers and laydown area
Shoring at the Main Entrance
Installation of temporary traffic signals
Summer 2017
• Continue hydro utilities relocation
• Commence sewer relocation at the Secondary Entrance site
• Piling in the roadway, beginning on the northwest side of Eglinton Avenue East
• Resume piling at the Secondary Entrance
![Page 10: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/10.jpg)
10
Mount Pleasant Station Lookahead
Year Quarter Construction ActivityApprox.
Duration
2017Q2-Q4
(April-December)
• Implement traffic staging on the north side of
Eglinton Ave E, and commence utilities relocation and
piling
• Implement traffic staging on the south side of
Eglinton Ave E, continue utilities relocation and piling
• 2 months
• 4 months
2018
Q1-Q2
(January-June)
• Shallow excavation and roof slab construction on the
south side of Eglinton Ave E
• 6 months
Q3-Q4
(July-December)
• Shallow excavation and roof slab construction on the
north side Eglinton Ave E
• 6 months
![Page 11: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/11.jpg)
11
Current Construction Staging
Began June 2017 for approximately two (2) months
NO TURNS IN ALL DIRECTIONSMT PLEASANT &
EGLINTON
![Page 12: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/12.jpg)
12
Mount Pleasant Station Concept Aerial View
Main Entrance
Secondary Entrance
*60% rendering
![Page 13: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/13.jpg)
13
Mount Pleasant Station Main Entrance
*60% rendering
![Page 14: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/14.jpg)
14
Mount Pleasant Station Secondary Entrance
*60% rendering
![Page 15: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/15.jpg)
15
Mount Pleasant Station Construction Progress
15
BACK FILLING TRENCH
EXPOSING UTILITIES
![Page 16: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/16.jpg)
16
Mount Pleasant Station Construction Progress
16
HYDRO TRENCHHYDRO POLE
WORK
![Page 17: Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017](https://reader034.vdocuments.net/reader034/viewer/2022050613/5a64e5ae7f8b9a88148b5de1/html5/thumbnails/17.jpg)
17
Mount Pleasant Station Construction Progress
17As of May 2017