ehhs- portrait boards- final

Upload: viktoria-sundqvist

Post on 03-Apr-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 EHHS- Portrait Boards- Final

    1/5

    Existing Site Plan

    BUS DROP ZONE

    PARKING

    ATHLETICS/

    STUDENT

    PARKING

    SERVICE

    ENTRY PLAZA

    SERVICE

    EXISTING BUILDING

    EXISTING

    WINGS TO BE

    DEMOLISHED

    AT END OFPROJECT

    Existing site:

    Lacks fire lane access to entire school

    One entrance point

    All traffic must go through main parking or bus

    drop-off

    Parking behind school unclear, dead-end

    Parking remote from athletic fields

    BUS DROP ZONE

    PARKING

    ATHLETICS

    PARKING

    ENTRY PLAZA

    SERVICE

    STUDENT

    PARKING90 SP

    40 SP

    100 SP

    90 SP

    PARENT DROP-OFF

    Proposed Site Plan

    Provide safety improvements to site:

    Fire lane access to entire school Separation of Bus, Student, Parent traffic

    Additional parking capacity

    More parking close to athletic fields

  • 7/28/2019 EHHS- Portrait Boards- Final

    2/5

    LECTURE

    HALL

    NEW GYM

    LOCKERS

    LOCKERS

    LIBRARY AUDITORIUM

    MECHANICAL

    MUSIC

    CAFE-

    TERIA

    MAIN

    ADMIN

    SUPPORT

    SERVGUID

    FAM

    CON

    SCI

    ACADEMICS

    NEW SCIENCE WING

    PHOTO ART

    KIT/

    SERV

    BUSN

    TECH

    ED

    COM

    LAB

    FITNESS

    T TTM

    LKR

    TM

    LKR

    Provide sprinkler system

    and develop fire wall to

    meet current codes

    NURSET T

    T T

    T T T

    and main Gym,

    ganize PE spaces

    vide distance

    ning capabilities

    vide LMC with

    cated computersace for patron use

    Proposed Concept Plan

    and Kitchen/Servery

    Cafeteria seating

    mproved efficiency

    Dedicated

    Language Lab

    New Science wing of

    efficient, well organized

    lab & support spaces

    Provide additional

    Support Services, Guidance

    and Health office space

    Improve internal circulation;

    co-locate discipline areas;

    provide faculty meeting space

    Improve security and

    access control

    Proposed responses to NEASC recommendations:

    Improve internal circulation

    Co-locate discipline areas

    Improve cross-disciplinary connections

    Provide faculty collaboration space

    Renovate / improve Science labs

    Add capacity to Gym and lockers

    Add to Student Services, Health & Guidance areas

    Make comprehensive technology upgrades

    BUS DROP ZONE

    ENTRY PLAZA

    GYM

    LIBRARY

    CAFETERIAMAIN

    OFF

    LOCKERS LOCKERS

    AUDITORIUM

    MUSIC

    ACADEMICS

    SUPPORT

    SERV

    GUID

    FAM CON

    SCI

    PHOTO

    ART

    KIT/

    SERVBUSN

    TECH

    ED

    FITNESS

    NURSE

    SCIENCESCIENCE

    LIBRARY

    HLTHBOE

    IT

    MECHANICAL

    Existing Building Plan

  • 7/28/2019 EHHS- Portrait Boards- Final

    3/5

    Entry Courtyard with Science Wing Beyond

    Provide safety improvements to site:

    Visible and secure main entry

    nfrastructure Improvements

    R-50 roof over

    existing deck

    R-25 furred

    exterior wall

    R-4 Low-E windows

    w/ Light shelf/shade

    Light fixtures w/

    Daylight dimming

    Energy Recovery

    Ventilation Unit

    Bulkhead for

    ductwork access

    MEP systems

    distribution in

    corridor ceilings

    New flooring New lockers

    Technology w/

    pathways in furredacoustically

    improved walls

    Insulation in the exterior walls and roof

    Energy efficient / operable windows

    Complete sprinkler system

    Energy efficient mechanical ventilation system

    Code compliant doors and hardware

    Hallway lockers sized for backpacks

    Integrated technology backbone

    New ceiling

    Cross section of Typical Classroom

  • 7/28/2019 EHHS- Portrait Boards- Final

    4/5

    Classroom Space

    Provide mix of appropriately

    zed classrooms of correct quantity

    Provide comprehensive integrated technology

    ackbone and additional equipment

    esign must integrate multiple devices

    Existing Classroom

    Science Labs

    ovide new Science wing of efficiently sized

    d organized lab and support spaces.

    ossible Design

    Existing Science Lab

  • 7/28/2019 EHHS- Portrait Boards- Final

    5/5

    Gym

    rovide new bleachers meeting HC requirements

    expanded Gym with additional practice space

    rovide new PE lockers

    ossible Design

    Existing Gymnasium

    Cafeteria

    Existing Cafeteria

    Reorganize Kitchen/Servery

    and Cafeteria seating space

    for improved efficiency

    New seating area frees space for

    adjacent Admin functions

    ossible Design