eia_nh6
TRANSCRIPT
-
8/11/2019 EIA_nh6
1/42
NATIONAL HIGHWAYS AUTHORITY OF INDIA(Ministry of Road Transport & Highways, Govt. of India,New Delhi)
Consultancy Services for Preparation of Detailed Project Reportfor Rehabilitation and Upgradation of NH Stretches Under
NHDP-IVB
Section III: Jamshedpur-Baharagora-Kharagpur(NH-33 & NH-6)
Group B- Package No. JH/DPR/NHDP-IV/05
-
8/11/2019 EIA_nh6
2/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
EXECUTIVE SUMMARY- ENVIRONMENTAL IMPACT ASSESSMENT (EIA)
DISTRICT - WEST MEDINIPUR (WEST BENGAL)
1.0 ENVIRONMENTAL IMPACT ASSESSMENT AND ENVIRONMENTAL MANAGEMENT PLAN
1.1 INTRODUCTION
The proposed project is widening and strengthening of existing 2 lane to 4 lane of Mahulia to Baharagorasection of NH- 33 from (Km 277.500 to Km 332.990) and from Baharagora to Kharagpur section of NH-6
from (Km 199.500 to Km 129.600) in the State of Jharkhand and West Bengal.The proposed project is a
part of National Highway Development Project Phase-IV B (Group B Package No JH/DPR/NHDP-IV/05).
The project road stretch of NH-33 starts at village Mahulia (Km 277.500) and terminates at Baharagora (Km
332.990) and meets NH-6. There is a flyover section from Km 332+990 to Km 333+500 of NH-33 and
included in design length of NH-6. The next section on NH-6 proceeds from Baharagora (Km 199.500) andterminates at Kharagpur (Km 129.600). The National Highways NH-33 & NH-6 traverse across four (4)
blocks in East Singhbhum district of Jharkhand State (Ghatshila, Dalbhumgarh, Chakuliya, Baharagora) and
four (4) blocks in West Medinipur district of West Bengal State (Kharagpur I, Jhadgram, Jambuni, Gopi-
Vallabhpur II (Baliyabera)).The details of project stretches are provided in Table 1.1.
Table 1.1 Details o f Project Streches
State District National Project Road Stretch Existing Chainage Length
-
8/11/2019 EIA_nh6
3/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
various development projects requiring prior clearance from Ministry of Environment and Forests (MoEF).As per Schedule of the Notification; the Highway project falls under Physical Infrastructure including
Environmental Services and have been listed under item no. 7(f), including new highways or expansion ofexisting highways. The projects and activities under the Notification have been classified into twocategories- Category A and Category B, based on the spatial extent of potential impacts on human healthand natural and manmade resources. The highway projects have also been classified into two categories-Category A and Category B based on the following conditions:
Note: Highways include Expressways
Moreover any project or activity specified in Category B will be treated as Category A if located in whole
or in part with in 10 km from the boundary of:
1. Protected areas notified under the Wild Life (Protection) Act, 1972;
2. Critically Polluted areas as notified by Central Pollution Control Board from time to time;
3. Eco sensitive areas as notified under section 3 of Environment Protection Act, 1986 such as
Mahabaleshwar, Panchangi, Matheran, Pachmarhi, Dahanu, Doon Valley; and
4. Inter State boundaries and international boundaries.
C t i ti f t j t
Category A i) New National Highways; andii) Expansion of National Highways, greater than 30 km involving additional right
of way greater than 20m involving land acquisition.Category B i) All New State Highway Projects; and
ii) State Highway expansion projects in hilly terrain (above 1,000 m AMSL) andor ecologically sensitive areas.
-
8/11/2019 EIA_nh6
4/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
1.2 BRIEF DESCRIPTION OF PROJECT ROAD IN WEST MEDINIPUR DISTRICT OF WEST BENGAL
The salient features of the project proposal have been summarized in the following Table 1.2Table 1.2: Project Description
S.No Salient Features Description
1. Proposed Project in the District Rehabilitation and Up gradation of NH-6 Section from Km
185.150 (Chirchira) to Km 129.600 (Kharagpur) in the State
of West Bengal from existing 2 Lane Configuration to 4 Lane
Divided Carriageway Configuration,
(Length in East Singhbhum: 55.550 Km)2. State West Bengal
3 District West Medinipur
4 Starting Chainage of project road in
District
Chirchira(Jharkhand/West Bengal Border km 185.150 of NH-6)
5 Ending Chainage of project road in
District
Km 129.600 (Kharagpur) of NH-6
6 Total length of roject road in District 55.55 kms on NH-6
(Refer Table 1.1)
7 Total no. of settlements along the
project road in District
30 villages (impacted)
(Refer Table 1.3)
8 Right of Way (ROW) Existing: varies from 45 m to 108m Proposed: 60 m
9 Carriageway Existing: 2 Lane Configuration
Proposed:4LaneDividedCarriageway
-
8/11/2019 EIA_nh6
5/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
S.No Salient Features Description
17 Toll Plaza proposed One location
At km 158+250 on NH-618 Bus Bays Proposed 8 Nos.
(Refer Table 1.6)
19 Truck laybyes 3 Nos.
(Refer Table 1.7)
20 Wayside Amenities /Rest Area Nil
21 Total Land Acquisition in the project 27.72 Ha. (0.07 Ha Govt. land and 27.64 Ha Private land)
22 Existing trees within ROW of 60 m Total : 20,413 trees
23 Compensatory plantation Three times the trees cut has been proposed as
Compensatory Plantation.
Approx. 61,300 trees
24 Total No. of trees to be planted in
District
Additional three rows trees have been proposed (As per
IRC:SP-21:2009.) to be planted apart from Compensatory
Plantation.Approx. 43,500 trees
25 No. of rows of trees to be planted
along the District
3 Rows of trees on both sides of the road
26 River/Channel crossings 5 irrigation channels crossings and 2 river crossings in WestBengal stretch.
27 Total Cost of the project Rs. 974.25 Crores
-
8/11/2019 EIA_nh6
6/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
The list of impacted villages along the project road in West Medinipur district is given in Table 1.3
Table 1.3 List of impacted villages along the Project Road in West Medinipur District
S. No Name of village District
1 Patna West Medinipur
2 Khemashouli West Medinipur
3 Doarkhol West Medinipur
4 Kalaikunda West Medinipur
5 Pathri West Medinipur
6 Salika West Medinipur
7 Dewanmara I West Medinipur
8 Sadatpur West Medinipur
9 Rajpura West Medinipur
10 Kismatbalibhasa West Medinipur
11 Kalsibhanga West Medinipur
12 Khasjangal West Medinipur
13 Sidamdihi West Medinipur14 Jangalkhas West Medinipur
15 Pheko West Medinipur
16 Barakala West Medinipur
17 Ukta West Medinipur
18 Shalgura West Medinipur
19 Bandarbani West Medinipur
20 Gundurghura West Medinipur
21 Netura West Medinipur
22 S k ib W t M di i
-
8/11/2019 EIA_nh6
7/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
S. No
Existing Design ServiceRoad Length
(m)
LHS/RHS/B
oth
Chainage (km) Chainage (km)
From To From To Width(m)
4 178 176.9 23.220 24.350 7 1130 Both
5 166.8 165.65 34.457 35.600 7 1143 Both
6 159.6 158.7 41.620 42.560 7 940 Both
7 152.325 151.7 48.900 49.560 7 660 Both
8 145.575 144.2 55.720 57.050 7 1330 Both
9 142.275 139.375 58.980 61.870 7 2890 BothTotal Length 11708
Table 1.5: List of proposed Underpasses along the Project Road in West Medinipur District
Vehicular Underpasses
S. No.Design
Chainage(km)
Existing Chainage(km)
Proposed Spanarrangement
(No. x Length xHeight)
Total Width (m)
On NH - 6
1 20 + 206 181+046 1 x 12 x 5.5 2 x 12.00 + Median
2 34 + 802 166 + 457 2 x 12 x 5.5 2 x 12.00 + Median
3 56 + 550 144 + 706 1 x 12 x 5.5 2 x 12.00 + Median
4 59 + 110 142 + 122 1 x 12 x 5.5 2 x 12.00 + Median
-
8/11/2019 EIA_nh6
8/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
S. No.Design
Chainage(km)
Existing Chainage
(km)
Proposed Spanarrangement
(No. x Length xHeight)
Total Width
(m)
2 28 + 546 172 + 713 1 x 5 x 3.5 2 x 12.00 + Median
3 32 + 296 168 + 963 1 x 5 x 3.5 2 x 12.00 + Median
4 33 + 821 167 + 437 1 x 5 x 3.5 2 x 12.00 + Median
5 38 + 471 162 + 791 1 x 5 x 3.5 2 x 12.00 + Median
6 40 + 392 160 + 843 1 x 5 x 3.5 2 x 12.00 + Median
7 52 + 411 148 + 830 1 x 5 x 3.5 2 x 12.00 + Median
Table 1.6: List of Bus bays along the Project Road in West Medinipur District
S.No.
Existing Chainage (km) Design Chainage (km) LHS/RHS
On NH-6
1 141+950 59+304 LHS
2 141+900 59+354 RHS3 145+175 56+085 LHS
4 145+325 55+935 RHS
5 166+280 35+000 LHS
6 166+500 34+770 RHS
7 183+975 17+292 LHS
8 183+775 17+492 RHS
-
8/11/2019 EIA_nh6
9/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
The monthly mean maximum and minimum temperatures as collected for Midnapore (nearest IMD
station) is 47.20C (June) and 0.60C (January) respectively. The project area receives average
rainfall between 1300 mm and 1500 mm. About 80 percent of the total rainfall is concentratedduring the months of July to September. The relative humidity varies between 56 % (March) to
84% (August) in Midnapore. Mean wind speeds are observed to be highest in the months of May
and June at (9.0 Kmph 6.8 Kmph).
Ambient Air Quality data was collected during the month of October and November, 2012 from four
(4) locations in West Medinipur District. The parameters monitored were Particulate Matter
(
-
8/11/2019 EIA_nh6
10/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
In West Medinipur District, the surface water quality sample was collected from two (2) locations.
The physico-chemical analysis of water samples revealed that the water quality criteria of studyarea falls in the range of Class B water prescribed by CPCB (as per the overall result) and hence
recommended for outdoor bathing and to be used for drinking water after conventional treatment
and disinfection. All the measured parameters were observed well within the prescribed limit.
Ground water quality was assessed from the hand pump along the project area at two (2) locations
in Medinipur District. Presence of faecal coliform and E coliis observed at GWQ-4 (tube well). The
count of total coliform is also high at GWQ-4. This shows that tube well water at Nimpura village is
contaminated with feces. Hence, the water of this location is not fit for drinking. All other
physiochemical parameters are well within the limits of IS:10500 at all monitoring locations. (Water
quality standard as per BIS (IS: 10500:1991))
About 60 borrow areas have been identified in West Medinipur district along NH-6. Necessary
approvals from concerned gram panchayats have been obtained. Also, one stone quarry site have
been identified at Silda in West Bengal.
Around 2.79 ha and 0.92 ha of protected forest land will be required to be diverted for the project
road section of NH-6 in Kharagpur and Jhargram forest division respectively in the state of West
Bengal. The details of forest land that needs to be diverted for non-forest purpose are given as
follows:
St t & F t Vill R d id N t f L d L d t b L d t b
-
8/11/2019 EIA_nh6
11/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
State &District
ForestDivision
Village Road side Nature of Land-Reserve/Protected
Forest/Jangaljhari
Land to bediverted
(acre)
Land to bediverted(Hectare)
Khasjungal(906)
LHS/RHS Protected Forest 0.030 0.012
Bankshol RHS Protected Forest 0.088 0.036
Dhabijangal LHS/RHS Protected Forest 0.308 0.125
Lodhashuli LH Protected Forest 0.119 0.048
Jangalkhas(681)
LHS/RHS Protected Forest 0.452 0.183
Dogeriya LHS/RHS Protected Forest 0.858 0.347
Total 2.27 0.92
Total Forest Land to be divert ed in West Bengal 9.16 3.71Source: As per Forest Clearance diversion proposal submitted to Principle Chief Conservator of Forest
Predominant tree species found along NH-6 project road section in West Bengal are Arjun, Jhakra
Potash, Sakhua, Doka and Neem. Total no. of affected trees in West Medinipur is around 20,413
(within proposed RoW). No endangered flora and fauna species are located within the proposed
project corridor. Three times the tree cut will be planted as Compensatory Afforestation as per
provision of Forest Conservation Act, 1980. Apart from this additional plantation along the highway
shall be taken up as per IRC:SP-21:2009. Shrubs will be planted in median.
The project area does not fall under any critically polluted industrial area as notified by Central
-
8/11/2019 EIA_nh6
12/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
alignment. About 20,413 trees are likely to be cut in the district, for which compensatory plantation of around
61,300 trees have been considered (1:3 ratio). Also, Additional tree plantation in three rows will be carried
out along the project road as per IRC:SP-21:2009 which would ultimately enhance the overall surroundingenvironmental condition and ambience of the area. The key environmental issues identified due to the
project are as follows
S. No. Environmental
Issues
Impacts Location Remarks
1 Land
Environment
Loss of land Throughout the road length
where the required ROW is
less than 60m
During pre
construction period
Loss of properties /
structures
More pronounced in built-up
areas
Loss of Forest Land Protected and Reserved
Forest along the road
2 Roadside
Vegetation
Tree cutting Through out the stretch
3 Soil Loss of top soil Throughout the stretch, borrowarea, stockyard, campsite
During constructionperiod
Soil Contamination Campsite, stockyard, vehicle
and equipment servicing
station
During construction
period
4 Air Environment Deterioration of air
quality
At construction site and plant
operation site/stockyards
During construction
period
N i N i P ll i A i i d l D i i
-
8/11/2019 EIA_nh6
13/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t West Medinipur (West Bengal) Public Hearing Documents
S. No. Environmental
Issues
Impacts Location Remarks
Accident hazardsfor road users
At construction zone especiallytemporary diversion and haul
roads
During theoperation phase,
the safety of the
road users will
enhance due to
provision of divided
carriageway,
underpasses,service roads,
better safety sign
boards, etc.
During operation phase, the improvement of the road have positive influence by virtue of better accessibility,
low vehicle operating cost, quick accessing to marketing centers, educational and medical facilities,
improvement of the wayside amenities, etc. and thus provide tremendous opportunities of socio-economic
development of the region. Development of the green belt along the project, removal of bottlenecks, betterriding quality, proper safety provision for road users, planned wayside amenities, provision of bus stops and
lay byes with proper safety arrangements, provision of underpasses for the local villagers, landscaping are
the major features, which have been included in the project and will help in enhancing overall environmental
and social conditions of the area located all along the project stretch compared to the existing situation.
All the above issues have been adequately addressed in Project design and Environmental Management
-
8/11/2019 EIA_nh6
14/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t East Singhbhum (Jharkhand) Public Hearing Documents
Table 1.8: Environmental Management Action Plan
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional ResponsibilityPlanning and
ExecutionSupervision
A. PRE-CONSTRUCTION STAGE-1 Land and Properties Loss Land acquisition will be marginal. The acquisition of land and
private properties will be carried out in accordance with the RAPand entitlement framework for the project.
Early identification of entitlement for Compensation and Advanceplanning of Resettlement And Rehabilitation Action Plan toCompensate the Losses
All the affected people will be compensated as per NPRR beforecommencement of Construction works
PIU - NHAIKharagpur and
RevenueDepartmentWest
Bengal
PIU - NHAIKharagpur
-2 Preservation of Trees The alignment has been designed to minimize the tree loss. About48,873 trees located within 60m RoW (28,460 in Jharkhand and20,413 in West Bengal). All efforts will be made in design to savemaximum trees.
Compensatory plantation will be carried out as per Forest(Conservation) Act, 1980.
Apart from Compensatory plantation Green belt development onboth sides has been designed throughout the project stretch as perIRC SP-21:2009. Shrub plantation in median is also proposed.
Compensatory Afforestation to be carried out as per Forest(Conservation) Act and Forest Rules of Jharkhand & West Bengal.
PIU - NHAIKharagpur and
Forest Department,Jharkhand &West
Bengal
IC,PIU NHAIKharagpur
-3 Location of crushers, hot-mixplants, WMM Plant, ConcreteBatching plants etc.
Stone crushers, Hot mix plants: WMM Plants and ConcreteBatching plants will be sited sufficiently away from settlements,agricultural operations and any commercial establishments. Suchplants will be located at least 500m away from the nearest
ConcessionaireIC,
PIU - NHAIKharagpur
-
8/11/2019 EIA_nh6
15/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
village/settlement preferably in the predominant downwind side.Mobile equipment can be placed within 50 m from the nearestdwelling.
The Concessionaire shall submit a detailed layout plan for all suchsites and approval of the Environmental Expert of IndependentConsultant (IC) shall be necessary prior to their establishment.
Arrangement to control dust pollution through provision of wind
screens, sprinklers and dust encapsulation will have to be providedat all such sites especially for crushers. Use of buildings andequipment within the plant site as wind barriers may be considered.
Specifications of crushers and hot mix plants will comply with therequirements of the relevant current emission control legislationsand Consent/NOC for all such plants shall be submitted to the
-
8/11/2019 EIA_nh6
16/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
construction and to be installed close to waterway/str ams, must bechecked and certified fit, especially with respect to the potentialleakage of oil and grease.
The inspection should verify that:Equipment is clean (free of mud, dirt an oil)Equipment is in good working order.A drip pan is available for equipment that will be stored on site.Concessionaire has a spill kit
Operator is trained on the refueling, maintenance andemergency spill.A logbook will be maintained documenting all fuelling andmaintenance events (date, time, location, condition of site,weather conditions, amount of fuel on maintenance event,issues).Adequate inspections will be conducted during the construction
-
8/11/2019 EIA_nh6
17/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
PIU.
In addition to testing for the quality of borrow materials by the IC,the environmental experts of the IC will be required to inspect everyborrow area location prior to approval. All borrow areas will berehabilitated as per the Borrow Rehabilitation Plan.
A- Quarry Areas The quarry materials requirement of this project will be taken fromthe existing approved quarries along the project highway. Threequarries have been identified for the project - Potka, Baharagorha
in East Singhbhum district of Jharkhand and Silda in WestMedinipur of West Bengal. Mining Plan giving details of mining hasbeen prepared and submitted to State Mining Department.
In case the Concessionaire decides to use quarries other thanrecommended by Consultants, then it will be selected based on thesuitability of the materials.
ConcessionaireIC,
PIU NHAIKharagpur
-
8/11/2019 EIA_nh6
18/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
Concessionaire will extract water from fixed locations and consultthe Environmental Expert before finalizing the locations. TheConcessionaire will not be allowed to pump water from any
irrigation canal and surface water bodies used by the community.The Concessionaire is required to comply with the requirements ofthe State Ground Water Department and seek its approval for doingso and submit copies of the permission to Environmental Expert ofIC and PIU.
A- Site identification for disposal
of unsuitable materials
The Concessionaire shall identify site(s) away from the project area
where unsuitable materials (debris, solid waste) generated in thecourse of the construction can be safely disposed off. Suchlocations shall be inspected by the Environmental Expert ofIndependent Consultant and approved in consultation with the PIUbefore construction work starts.
ConcessionaireIC,
PIU NHAIKharagpur
A-1 Construction camp location,design and lay-out
Sitting of the construction camps will be as per the guidelinesbelow:
-
8/11/2019 EIA_nh6
19/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
Environmental Expert will have to be provided by theConcessionaire.
A-11 Arrangements for temporaryland
The Concessionaire as per prevalent rules will carry outnegotiations with the landowners for obtaining their consent fortemporary use of lands for workers camp, construction sites/hot mixplants/traffic detours etc. The Environmental Expert will ensure thatthe clearing up of the site prior to handling over to the owner (afterconstruction or completion of the activity) is duly carried out by theConcessionaire.
ConcessionaireIC,
PIU NHAIKharagpur
B CONSTRUCTION PHASEB-1 Clearing & Grubbing Vegetation will be removed from the construction zone before
commencement of construction. All works will be carried out such
that the damage or disruption to flora other that those identified for
cutting is minimum.
-
8/11/2019 EIA_nh6
20/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
surface construction, subject to the suitability of the materials and approval
of the Engineer and Environmental Expert as follows:
The existing base and sub-base material shall be recycled assub-base for the haul road or access roadsThe existing bitumen surface may be utilized for the paving ofcross roads, access roads and paving works in constructionsites and campus, temporary traffic diversions etc.Any place specifically directed by the Engineer.
The Concessionaire will suitably dispose off unutilized debris
materials at pre-designated disposal locations, subject to the
approval of the Environmental Expert. At locations identified for
disposal of residual bituminous wastes, the disposal will be carried
out over a 60 mm thick layer of rammed clay so as to eliminate the
Kharagpur
-
8/11/2019 EIA_nh6
21/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
B- Disposal of other construction
waste
The Environmental Expert will approve these disposal sites after
conducting a joint inspection on the site with the Concessionaire.
Non- bituminous wastes may be dumped in borrow pits (preferably
located in barren lands) covered with a layer of the soil. No new
disposal site shall be created as part of the project, except with
prior approval of the Environmental Expert. All waste materials will
be completely disposed of and the site will be fully cleaned and
certified by Environmental Expert before handing over.
All waste material will be completely disposed of and the site will be
fully cleaned and certified by Environmental Expert before handling
over.
ConcessionaireIC,
PIU NHAIKharagpur
B- Stripping, stocking and The topsoil from all areas of cutting and all areas to be permanently
-
8/11/2019 EIA_nh6
22/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
with gunny bags or vegetation.
(c) It will be ensured by the Concessionaire that the topsoil
will not be unnecessarily trafficked either before stripping
or when in stockpiles.
Such stockpiled topsoil will be utilized for-
Covering all disturbed areas including borrow areasTop dressing of the road embankment and fill slopesIn the agricultural fields of farmers, acquired temporarily.
Residential topsoil, if there any will be utilized for the plantation.
B- Accessibility The Concessionaire will provide safe and convenient passage for
vehicles, pedestrians and livestock to and from roadsides and
property access as connecting the project road. The
-
8/11/2019 EIA_nh6
23/42
-
8/11/2019 EIA_nh6
24/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
B- Construction water The Concessionaire will arrange adequate supply and storage of
water for the whole construction period at his own costs. The
Concessionaire will submit a list of source/s from where water will
be used for the project to IC and PIU.
The Concessionaire will source the requirement of water
preferentially from ground water but with prior permission from the
Competent authority/ authorities, if required. A copy of the
permission will be submitted to IC and PIU prior to initiation of
construction.
The Concessionaire will take all precaution to minimize the wastage
of water in the construction process/operation.
ConcessionaireIC,
PIU NHAIKharagpur
B-1 Drainage & Flood Control The Concessionaire will ensure that construction materials like
earth, stone are disposed off so that they does not block the flow of
-
8/11/2019 EIA_nh6
25/42
-
8/11/2019 EIA_nh6
26/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
all liquid wastes disposed off form the sites meet the discharge
standards.
B-1 Water pollution from fuel and
lubricants
The Concessionaire will ensure that all construction vehicle parking
location, fuels/lubricants storage sites, vehicles, machinery and
equipment maintenance sites are located at least 100m away from
any water body. The Concessionaire will also ensure that spillage
of fuels and lubricants do not contaminate the ground.
If fuel storage and refueling areas are located on agricultural land
or areas supporting vegetation, the topsoil will be stripped,
stockpiled and returned after cessation of such activities.
All location and layout plans of such sites will be submitted by the
Concessionaire prior to their establishment and will be approved by
the Environmental Expert and PIU. The Concessionaire will arrange
ConcessionaireIC,
PIU NHAIKharagpur
-
8/11/2019 EIA_nh6
27/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
Crushers licensed by the Jharkhand & West Bengal Pollution
Control Boards shall be used for the project.
Fly ash shall be used as per IRC SP 58 Guidelines.
On daily basis it will be ensured that all dumpers carrying fly ash
are fully covered by tarpaulin
Water Sprinkling during loading and unloading of fly ash shall be
periodically carried out.
Storage of fly ash within enclosures shall be done and regular
water sprinkling will be ensured over the stack.
-
8/11/2019 EIA_nh6
28/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
All plants and equipments used in construction shall strictly
conform to the MoEF/CPCB/JSPCB/WBPCB noise standards.
All vehicles and equipment used in construction will be fitted
with exhaust silencers.
Servicing of all construction vehicles and machinery will be
done for exhaust silences and will be checked and if found
defective will be replaced.
All the construction sites within 150m of the nearest habitation,
noisy construction work such as crushing, concrete mixing will be
stopped during the night time between 10.00 pm to 6.00 am.
No noisy construction activities will be permitted around educational
institutions/health centers (silence zones) up to a distance of 100 m
from the sensitive receptors.
Kharagpur
-
8/11/2019 EIA_nh6
29/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
working in crushing, compaction, or concrete mixing operation.
Adequate safety measures for workers during handling of
materials at site.
The Concessionaire will comply with all the precautions as required
for ensuring the safety of the workmen as per the International
Labour Organization (ILO).
The Concessionaire will not employ any person below the age of 14
years for any work and no woman will be employed on the work of
painting with products containing lead in any form.
The Concessionaire will also ensure that no paint containing lead or
lead products is used except in the form of paste or readymade
paint. They will provide facemasks for use to the workers when
-
8/11/2019 EIA_nh6
30/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
The Concessionaire will ensure that all signs, barricades, pavement
markings are provided as per the MoRTH specifications or as
directed by the Engineer. Before taking up construction on any
section of the existing road, a Traffic Management Plan will be
devised and implemented to the satisfaction of the
Concessionaires vehicle drivers must be strictly controlled
particularly when plying on local/village roads.
B-1 Risk from electrical
equipments
The Concessionaire will take all required precautions to prevent
danger from electrical equipment and ensure that
No material will be stacked or placed as to cause danger or
inconvenience to any person or the public.
All necessary fencing and lights is provided to protect the
public in construction zones.IC,
-
8/11/2019 EIA_nh6
31/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
Equipment and trained nursing staff at construction camp.
B-21 Informatory Signs and
Hoardings
The Concessionaire will provide, erect and maintain
informatory/safety signs, hoardings written in English and local
language, wherever required or as suggested by the Environmental
Expert of IC.
Concessionaire
IC,
PIU NHAIKharagpur
B-2 Road side Plantation Strategy The Concessionaire will carry out the plantation as per the Green
Belt Development Plan prepared for the project as per IRC-SP:21:
2009.
The Environmental Expert of IC will inspect regularly the survival
rate of the plants and compliances with regards to tree plantation
guidelines.
Concessionaire,
Forest Department
Jharkhand & West
Bengal.
IC,
PIU NHAIKharagpur
B-2 Accommodation for labour
Camps
The Concessionaire will follow all relevant provisions for
constructionandmaintenanceoflabourcamp.
-
8/11/2019 EIA_nh6
32/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
every workplace/labour camp at suitable and easily accessible
places and regular maintenance of such facilities.
If any water storage tank is provided, the bottom of the tank will
be kept at least 1m above from the surrounding ground level.
If water is drawn from any existing well, which is within 30m
proximity of any toilet, drain or other source of pollution, the
well will be disinfected before water is used for drinking.
All such wells will be entirely covered and provided with a trap
door, which will be dust proof and waterproof.
A reliable pump will be fitted to each covered well. The trap
door will be kept locked and opened only for cleaning or
inspection, which will be done at least once in a month.
Environmental Expert will be required to inspect the labour camp
once in a week to ensure the compliance of the EMP.
-
8/11/2019 EIA_nh6
33/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
purpose and covered with 15cm, layer of waste or refuse and
then covered with a layer of earth for a fortnight.
B-2 Waste disposal The Concessionaire will provide segregated garbage bins in the
camps and ensure that these are regularly emptied and disposed
off in a hygienic manner as per the Comprehensive Solid Waste
Management Plan approved by the Environmental Expert of IC.
Unless otherwise arranged by local municipal authority,
arrangements for disposal of night soils (human excreta) suitably
approved by the local municipal authority or as directed by
Environmental Expert, will be arranged by the Concessionaire.
ConcessionaireIC,
PIU NHAI
Kharagpur
B-2 Pollution Monitoring The periodic monitoring of the ambient air quality, noise level, water
(both ground and surface water) quality, soil pollution/contamination
-
8/11/2019 EIA_nh6
34/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
relocated utilities, hand pumps and other relocated structures if
any; status of rehabilitation of borrow areas.
C-2 Maintenance of Drainage PIU will ensure that all drains (side drains, cross drains etc.) are
periodically cleared especially before monsoon season to facilitate
the quick passage of rainwater and avoid flooding.
PIU will ensure that all the sediment and oil and grease traps set up
at the water bodies are cleared once in every three months.
ConcessionaireIC,
PIU NHAIKharagpur
C-3 Pollution Monitoring The periodic monitoring of the ambient air quality, noise level, water
(both ground and surface water) quality, soil pollution/contamination
in the selected locations as suggested in environmental monitoring
plan will be the responsibility of Concessionaire.Concessionaire
IC,PIU NHAI
-
8/11/2019 EIA_nh6
35/42
Detailed Project Report Jamshedpur -Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distri ct East Singhbhum (Jharkhand) Public Hearing Documents
S. No.Environmental Issues &
ImpactsMitigation Measures
Institutional Responsibility
Planning andExecution
Supervision
Necessary hoardings will be erected indicating the availability of
ROW and legal charges for encroachment of ROW. Budgetary
provisions are to be made to control the ribbon development along
project road.
Safety of public and road users shall be maintained through traffic
control and management throughout the operation period. Trauma
centers for treatment of accident victims should be established at
regular intervals and operated to the full satisfaction of PIU.
C-5 Corporate Social Responsibility
(CSR)
As part of CSR, the following provisions are suggested :
Undertaking regular road safety, HIV/AIDs, health awareness
campaigns
Assistance to improve skills for income generation to
community people
Development of schools, health cares, dispensaries or public PIU-NHAI
-
8/11/2019 EIA_nh6
36/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t Medinipur (West Bengal) Public Hearing Documents
1.5.2 Environmental Monitoring Plan
The Monitoring Program during construction (3 years) and operation (2 years) phases is given in
Table 1.9
Table 1.9: Environmental Monitoring Plan
Parameter Locations Duration Frequency
Air Quality:
PM10, PM2.5, SO2, NOx, CO
1. Plant site, HMP and Stone
Crusher during
construction phase2. Locations of baseline
data monitoring
3. Sensitive Areas e.g.
Schools etc
24 hours
sampling
Once in a
season
Noise Level
Leq dB (A) (Day and Night)
Average and Peak values
Locations of baseline data
monitoring
24 hours
Continuous
sampling
Once in a
season
Surface and Ground Water Quality:
for different physical chemical and
biological parameters
Locations of baseline data
monitoring
Grab Sampling Once in aseason
Soil Quality Monitoring Locations of baseline data
monitoring
Composite
Sample
Once in aseason
-
8/11/2019 EIA_nh6
37/42
Detailed Project Report Jamshedpur Baharagora Kharagpur (NH 33 & NH 6)
-
8/11/2019 EIA_nh6
38/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t Medinipur (West Bengal) Public Hearing Documents
2.0 RESETTLEMENT ACTION PLAN (RAP)
2.1 INTRODUCTIONThis Resettlement Action Plan (RAP) report has been prepared as per the National Policy on the
Resettlement and Rehabilitation of Project Affected Families - 2007 (NPRR 2007), National Highways Act
(NH Act), 1956; and Jharkhand Rehabilitation and Resettlement Policy, 2008 and is based on data
collected from field survey. The primary purpose for preparing Resettlement Action Plan (RAP) is to assess
the socio-economic condition of the Project Affected Persons (PAPs) in order to minimise and provide
mitigative measures. Since the displacement is indispensable, rehabilitation shall be done in such a manner
so that the standard of living of PAPs is restored. Special attention will be paid to the vulnerable groups.RAP has provisions to ensure that PAPs are compensated at replacement value for the assets lost and to
enable them to regain or improve their socio-economic status enjoyed prior to the project. Implementation of
the RAP will be done on data so modified.
2.2 PROJECT IMPACT
Based on socio-economic survey, a total of 266 private structures lie within 30 meters of either side of theexisting centerline of road both NH-6 and NH-33. The structures are residential, commercial or residential
cum commercial in their nature. The break-up of the structures and their typology is given inTables 2.1.
Table 2.1 Type and Area of Private Struc tures
Categories of losses No. of
Structure
Total Area of the
Structures (Sq.m)
Af fected Ar ea of St ructure
(Sq.m)
Detailed Project Report Jamshedpur Baharagora Kharagpur (NH 33 & NH 6)
-
8/11/2019 EIA_nh6
39/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t Medinipur (West Bengal) Public Hearing Documents
2.3 LAND REQUIRED
The project road section of NH33 will impact 103 villages of Jharkhand state and 30 villages of West
Bengal. Table 2.2 provides block/circle wise details of private and government land to be acquired under
this project.
Table2.2 Quantum of Land to be Acquired
District Circle /BlockGovernment Land
(area in sq/m)
Private Land
(area in sq/m)
East Singhbum Ghatshila 21540.85 183013.9
Dhalbhumgarh 72551.08 354405.1
Chakuliya 31644.43 110495.7Baharagora NH 33 38679.46 402484
Baharagora NH 06 32046.29 246872.3
Total Area in
Hectares 19.6462 129.7271
West Medinipur
Kharagpur I 00.00 162760.7
Jhargram 200.18 89845.29
Jamboni (Gidhni) 399.23 11168.45Gopi Vallabhpur II 102.81 12699
Total Area in
Hectares
0.0702 27.6473
Total land area to be acquired in both district s
in Hectares 19.7164 157.3744Source: Socio-Economic Survey, July 2011
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)
-
8/11/2019 EIA_nh6
40/42
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)Executive Summary: EIA Distric t Medinipur (West Bengal) Public Hearing Documents
organization (NGO) for RAP implementation and an independent agency for external monitoring. DRROs
(R&R Cell) at PIU will undertake RAP implementation, with the help of NGO appointed by ESDU. All the
RAP activities will be regularly reported to ESDU by PIU. PIU/R&R Cell will establish networking with district
administration (District Collectors office, Revenue Department etc.) to ensure timely implementation of RAP.
Networking with central/state/town departments will also be established (i) so as to link proposed income
restoration packages with government schemes, if any; (ii) for restoration/replacement of community
infrastructure such as water supply, sewerage, electricity/telephone network, irrigation canals etc.; and (iii)
for restoration/replacement of CPRs/public amenities such as shrines, schools etc.
The implementation schedule of RAP is presented in Table 2.3.
Table 2.3 Schedule of Land Acquisition and Resettlement Activities
S.
No.
Land Acquisition and Resettlement
Activi ties
Start Date Completion Date Duration
(days)
1 Revalidation of RP 1st of Month 1 30th of Month 2 60
2 RP Approval by NHAI 1st of Month 3 30th of Month 3 30
3 Issue of identity cards 1st of Month 4 30th of Month 4 30
4 Recruitment of Implementing NGO 1st of Month 3 30th of Month 3 30
5Information sharing, consultations and
All throughtheRPimplementationperiod
Detailed Project Report Jamshedpur-Baharagora-Kharagpur (NH-33 & NH-6)
-
8/11/2019 EIA_nh6
41/42
Detailed Project Report Jamshedpur Baharagora Kharagpur (NH 33 & NH 6)Executive Summary: EIA Distric t Medinipur (West Bengal) Public Hearing Documents
2.6 BUDGET
The estimated R & R budget is presented in Table 2.4.
Table 2.4: Estimated R&R Budget for Project
Sl. No. Item Unit Quantity Unit Rate /Acre (Rs)
Amount (inRs.)
(Crores)A Compensation: Land
1 Cost of private land along theroad: WB
hectares 27.72(68.49 acres)
10000000 68.49
2 Cost of private land along theroad: Jharkhand
hectares 149.37(369.10acres)
200000 7.38
3 Additional 30 % Solatium 22.7
Sub Total: Land 98.63
B Compensation: Structure
Affected Fami lies
1 Structure compensation: Sq m 23947.15 5000 12
Total 12.00
C Other Assistance
1 R&R Assistance to Structure
affected families
25.00
-
8/11/2019 EIA_nh6
42/42