elasto-plastic three dimensional analysis of shielded tunnels, with special application on greater...
DESCRIPTION
Ph. D, Thesis, Ain Shams University, Cairo, Egypt.TRANSCRIPT
Ain Shams University Faculty of Engineering
Elasto-Plastic Three Dimensional Analysis of Shielded Tunnels, with Special Application on
Greater Cairo Metro
By Sayed Mohamed El-Sayed Mohamed Ahmed
B. Sc., Civil Engineering “Structural” - Hon. (1993) M. Sc., Civil Engineering “Structural” - (1998) Ain Shams University - Faculty of Engineering
SUBMITTED IN PARTIAL FULFILLMENT FOR THE REQUIREMENTS OF THE DEGREE OF
DOCTOR OF PHILOSOPHY
Supervisors
Prof. Dr. Mona M. Eid Professor of Geotechnical Engineering
Ain Shams University
Dr. Ali Abd El-Fathah Ali Associate Professor of Geotechnical
Engineering Ain Shams University
Dr. Hesham M. Helmy Assistant Professor of Geotechnical
Engineering Ain Shams University
Cairo - 2001
IINNFFOORRMMAATTIIOONN AABBOOUUTT TTHHEE RREESSEEAARRCCHHEERR
Name : Sayed Mohamed El-Sayed Mohamed Ahmed
Date of Birth : Jan. 20, 1970
Place of Birth : Cairo, Egypt.
Qualifications : B. Sc. Degree in Civil Engineering (Structural)
Faculty of Engineering, Ain Shams University
Hon. (1993)
M. Sc. Degree in Civil Engineering (Structural)
Faculty of Engineering, Ain Shams University (1998)
Present Job : Assistant Lecturer in Structural Engineering
Department, Faculty of Engineering, Ain Shams
University
EEXXAAMMIINNIINNGG CCOOMMMMIITTTTEEEE
Name and Affiliation Signature
1- Prof. Dr. Abd El-Rahman S. Bazaraa Professor of Structural Engineering
Faculty of Engineering – Cairo University
2- Prof. Dr. Fathalla M. El-Nahhas Professor of Geotechnical Engineering
Faculty of Engineering – Ain Shams University
3- Prof. Dr. Mona M. Eid Professor of Geotechnical Engineering
Faculty of Engineering – Ain Shams University
4- Dr. Ali A. A. Ahmed Associate Professor of Geotechnical Engineering
Faculty of Engineering – Ain Shams University
SSTTAATTEEMMEENNTT
This dissertation is submitted to Ain Shams University for the degree
of Doctor of Philosophy in Civil Engineering (Structural).
The work included in this thesis was carried out by the author in the
Department of Structural Engineering, Ain Shams University from 1998 to
2001.
No part of this thesis has been submitted for a degree or qualification
at any other university or institution.
Date : April 7, 2001
Signature : Sayed M. El-Sayed
Name : Sayed Mohamed El-Sayed Mohamed Ahmed
Ain Shams University Faculty of Engineering
Department of Structural Engineering Abstract of Ph. D. thesis submitted by:
Sayed Mohamed El-Sayed Mohamed Ahmed Title of thesis
Elasto-plastic Three Dimensional Analysis of Shielded Tunnels, with Special Application on Greater Cairo Metro
Supervisors: Prof. Mona M. Eid Dr. Ali A. Ahmed Dr. Hesham M. Helmy
ABSTRACT
The Egyptian tunneling activities have augmented in the last two decades
for several purposes such as construction of subways, sewers and road tunnels.
The preponderance of the Egyptian tunnels are constructed through soft soils
under high ground water pressures in which tunneling can trigger substantial
ground deformations. The prevailing subsurface conditions limited the
construction methods to full face tunneling machines; otherwise tunneling cannot
be proceeding. The Bentonite Slurry Shields proved to be very successful in
many mega Egyptian tunneling projects.
The objects of the present study is to introduce a sophisticated three-
dimensional numerical model of the Bentonite Slurry Tunneling Machine by
adapting the main factors affecting the pressurized Bentonite Slurry Tunneling
such as unloading forces due to excavation, ground constitutive nonlinearity,
interface condition, engineering properties of shield, rate of advance, machine
overcutting, face pressure, yielding zones, the tail grouting and the hardening
characteristics of the grout material. Soil constitutive behavior is represented
using the hyperbolic elastoplastic model to account for the effect of the stress
level, stress path and the confining pressure. Shield and tunnel lining elements
are represented by elastic elements considering the different stiffness of the liner
and the shield. The interface of the soil-shield and soil-lining is represented by a
three dimensional hyperbolic gap element and grouting element with initial
grouting stress. Special incremental technique is used to account for the variable
mesh size due to excavation and lining erection using pseudo-time technique
combined with Newton-Raphson iterative procedure. A nonlinear finite element
program was developed and used to analyze the tunneling status in three giant
projects, which are considered the foremost Bentonite Slurry tunneling projects
in Egypt. The case studies are the Greater Cairo Metro-Line 2, El-Salam Syphon
and the intersection of Al-Azhar Twin Road Tunnels and the CWO sewer.
Comparing the results of the developed numerical three-dimensional
idealization of the Bentonite Slurry Tunneling with the field measurements
compiled during the construction of the studied tunnels indicated the capability
of such sophisticated modeling to develop realistic pattern of ground subsidence
associated with tunneling. The results implied that, simulating the details of
tunneling operation through the modeling formulation is considered as the basis
for optimum idealization and is badly needed for realistic updating of the ground-
tunneling interaction. Furthermore, the three-dimensional tunneling analysis is
considered as the entirely capable arrangement to simulate very sophisticated
problems such as the intersection of multiple tunnels that cannot be preceded by
means of two-dimensional analysis or empirical approach superposition.
Consequently, the deformations and the internal forces developed in underground
pipelines and sewers due to tunneling can be estimated. The results of the
intersection of AlAzhar Road Tunnels and CWO sewer show that pre-excavation
grouting proved to be a salutary process to control the deformation and the
internal forces developed in underground structures due to tunneling. The results
of the numerical modeling of the case studies are compared with the field
measurements compiled during tunneling activities in order to assess the
proposed numerical model.
Keywords: Bentonite slurry tunneling; three-dimensional analysis; nonlinear
finite element; gap parameter; tailskin grouting; gap element; field
measurements; multiple tunnels; tunnel intersections; grouting
measures.
AACCKKNNOOWWLLEEDDGGEEMMEENNTT At the completion of this work I would like to sincerely acknowledge my
dear mentor Prof. Dr. Mona M. Eid. Her scientific and personal advice kindly
overwhelmed me all through the period of progress of this work, a fact that gave
me great momentum in completion of this thesis.
No words suffice to show how gratified am I to Dr. Ali A. Ahmed who
undertook the difficult task of genuinely advising me throughout the course of
this thesis. He kindly guided me with his distinctive advice till this work finally
came true. He spared no effort for the sake of completion and satisfaction of this
thesis. His immense support made it possible to overcome all the difficulties that
had faced me till this work was finally concluded.
I am also extremely grateful to Dr. Hesham M. Helmy for his great
support and supervision throughout this thesis. His contribution to my
personality, scientific knowledge and engineering profession is tremendously
colossal.
I would like also to extend my profound gratefulness to Prof. Dr. F. El-
Nahhas, Dr. K. Esmail and Dr. H. Abdelalla of Ain Shams University; Dr. K.
Bäppler of Herrenknecht Tunnelvortriebstechnik; and Eng. Mohamed Farghaly
for their kind help during the course of the thesis.
Finally I am greatly indebted to my family for their support and
encouragement.
Sayed M. El-Sayed
Cairo – 2001
Dedication
To my family
TTAABBLLEE OOFF CCOONNTTEENNTTSS
1. Introduction 1.1. General.............................................................................................................1
1.2. The Objects of this Research...........................................................................3
1.3. Organization of This Thesis ............................................................................4
2. Construction, Monitoring and Design of Shielded Tunnels 2.1. Introduction .....................................................................................................6
2.2. Non-pressurized Shields..................................................................................8
2.3. Pressurized Shields ........................................................................................12
2.3.1. Introduction ............................................................................................12
2.3.2. Compressed Air Shields .........................................................................16
2.3.3. Liquid Support Shields ...........................................................................19
2.3.4.Earth Support Shields ..............................................................................22
2.4. Tunnel Monitoring.........................................................................................25
2.4.1. Deformation Instrumentations................................................................30
2.4.1.1. Extensometers..................................................................................32
2.4.1.2. Inclinometers ...................................................................................32
2.4.2. Convergence Measurements...................................................................37
2.4.3. Stress Measurements ..............................................................................39
2.4.3.1. Strain Gauges...................................................................................40
2.4.3.2. Piezometers......................................................................................40
2.5.Design Aspects of Shielded Tunnels..............................................................44
2.5.1. Face Stability ..........................................................................................45
2.5.2. Ground Deformation ..............................................................................49
2.5.2.1. Ground Loss ....................................................................................49
2.5.2.2. The Deformation Field ....................................................................50
2.5.2.3. The Effect of the Ground Subsidence on Buildings........................53
2.5.3. Design of Tunnel Lining ........................................................................55
2.5.3.1. General Considerations in Lining Design .......................................55
2.5.3.2. Methods of Tunnel Lining Design ..................................................59
2.6. Tunneling Projects in Egypt ..........................................................................74
3. Tunneling Idealization 3.1. Introduction ...................................................................................................79
3.2. Finite Element Formulation...........................................................................83
3.3. The Constitutive Model.................................................................................88
3.4. Interface Formulation ....................................................................................99
3.5. Nonlinear Solution Techniques ...................................................................104
3.5.1. Incremental Techniques........................................................................104
3.5.2. Mixed Techniques ................................................................................107
3.5.3. Convergence Criteria............................................................................110
3.5.4. Calculation of Stresses from Strains ....................................................111
3.6. Excavation and Lining Installation Modeling .............................................113
3.7. Programming Aspects of the Model............................................................115
4. Greater Cairo Metro 4.1. Introduction .................................................................................................118
4.2. Line 2 - Phase 1A ........................................................................................121
4.2.1. Geological Conditions ..........................................................................121
4.2.2. TBM Selection and Operation Parameters ...........................................122
4.3. Model Verification at Lot 16.......................................................................130
4.3.1. Results of the Numerical Model...........................................................135
4.3.1.1. The Stress Level Field ...................................................................135
4.3.1.2. The Deformation field ...................................................................135
4.3.1.3. The Stress field ..............................................................................136
4.3.1.4. The Lining Deformation and Straining Actions............................146
4.4. Model Verification at Lot 12.......................................................................153
4.4.1. Numerical Simulation...........................................................................153
4.4.2. Results of the Numerical Model...........................................................155
4.5. Stabilization Measures and Deformation Field ...........................................160
4.5.1. Introduction ..........................................................................................160
4.5.2. The Face Pressure and the Face Stability.............................................160
4.5.3. Effect of the Gap Parameter on The Deformation Field ......................167
4.5.4. The Effect of Tail Grouting..................................................................168
5. Case Histories of Multiple and Twin Tunnels 5.1. Introduction .................................................................................................189
5.2. El-Salam Syphon Project.............................................................................189
5.2.1. Numerical Idealization .........................................................................192
Stratum............................................................................................................192
5.2.2. Results of the Numerical Analysis .......................................................194
5.3. Intersection of Al-Azhar Tunnels and the CWO Sewer..............................198
5.3.1. Site Geological and Geotechnical Conditions......................................199
5.3.2. Untreated Ground Analysis ..................................................................200
5.3.2.1. The model ......................................................................................200
5.3.2.2. Results of the Numerical Model....................................................203
5.3.3. Treated Ground Analysis......................................................................213
5.3.3.1. Motivation .....................................................................................213
5.3.3.2. Modeling of the grouted material ..................................................213
5.3.3.3. Results of the Numerical Model....................................................215
6. Summary, Conclusion and Recommendations for Further
Studies 6.1. Summary......................................................................................................221
6.2. Conclusion ...................................................................................................223
6.3. Recommendations for Further Studies ........................................................231
7. References and Bibliography ..........................................................232
LLIISSTT OOFF TTAABBLLEESS
Table Page
Table (2.1) Open face non-pressurized TBMs (after Monsees, 1996) …11
Table (2.2) Values of tunnel distortion (after Peck, 1969) …61
Table (4.1) TBM operational parameters (after Richards et al, 1997) …123
Table (4.2) The estimated subsurface nonlinear geotechnical
parameters
…131
Table (4.3) Lining straining actions at Lot 16 …147
Table (5.1) The estimated geotechnical nonlinear properties for El-
Salam Syphon - section “C”
…192
Table (5.2) The estimated nonlinear soil properties for the intersection
of the CWO sewer and Al-Azhar Tunnels
…200
Table (5.3) Grouting effect on the sandy soil parameters for tunneling
projects (after Tan and Clough, 1980)
…214
LLIISSTT OOFF FFIIGGUURREESS
Figure Page
Fig. (2.1) Basic feature of an open face shield (after Szechy, 1967) …10
Fig. (2.2) Segmental lining (after Ezzeldine, 1995) …14
Fig. (2.3) Tail seal systems (after Esmail, 1997) …15
Fig. (2.4) Compressed-air TBM used in Cairo Wastewater Project
(after Shalaby, 1990)
…18
Fig. (2.5) The Hydroshield (after Herrenknecht AG, Germany) …21
Fig. (2.6) The EPB TBM (after Herrenknecht AG, Germany) …24
Fig. (2.7) Schematic diagram of a pneumatic device (after Joyce,
1982)
…29
Fig. (2.8) Schematic diagram of a vibrating wire device (after Joyce,
1982)
…29
Fig. (2.9) Measuring point for monitoring surface settlement (after
EM 110-2-1908, 1995)
…31
Fig. (2.10) Single and multiple rod extensometers’ installation (after
Soil Instruments Ltd., 1999)
…33
Fig. (2.11) Installation of magnetic multiple point extensometers
(after Soil Instruments Ltd.,1999)
…34
Fig. (2.12) Installation of inclinometers (after Soil Instruments Ltd.,
1999)
…35
Fig. (2.13) Inclinometer measurement of displacement (after Soil
Instruments Ltd., 1999)
…36
Fig. (2.14) Patterns of convergence rates (after EM 1110-2901,1997) …38
Fig. (2.15) Tape extensometer installation and usage (after Soil
Instruments Ltd., 1999)
…38
Fig. (2.16) Different types of vibrating wire strain gauges (after El-
Nahhas, 1980)
…42
Fig. (2.17) Piezometer types (after Murray, 1990) …43
Fig. (2.18) Face stability coefficients for cohesionless soil (after
Atkinson and Mair, 1981)
…47
Fig. (2.19) Face stability number for cohesive soils (after Thomson,
1995)
…48
Fig. (2.20) The ground subsidence Gaussian distibution (after
Schmidt, 1967)
…52
Fig. (2.21) Shallow tunnel model (after Szechy, 1967) …64
Fig. (2.22) Check of bottom heave (after Szechy, 1967) …65
Fig. (2.23) Analysis of deep tunnels (after Szechy, 1967) …65
Fig. (2.24) Bierbäumer Theory for ground arching (after Szechy,
1967)
…66
Fig. (2.25) Bodrov-Gorelik’s Method (after Szechy, 1967) …67
Fig. (2.26) Polygonal Method (after Szechy, 1967) …67
Fig. (2.27) GRC-SRC Method (after Ahmed, 1991) …69
Fig. (2.28) Moment and thrust coefficients (after Burns et al., 1964) …72
Fig. (2.29) Egyptian tunneling projects (after El-Nahhas, 1999) …76
Fig. (2.30) Cairo Wastewater Project (after El-Nahhas, 1999) …77
Fig. (2.31) Rehabilitation of Ahmed Hamdy Tunnel (after Otsuka and
Kamel, 1994)
…78
Fig. (3.1) Modeling features of soft ground shielded tunneling …81
Fig. (3.2) Interface modeling …82
Fig. (3.3) Natural axes of hexahedral parent element …87
Fig. (3.4) Typical triaxial results …94
Fig. (3.5) Hyperbolic Stress Strain Curve (after Duncan and Chang,
1970)
…95
Fig. (3.6) Determination of Hyperbolic Model parameters (after
Duncan and Chang, 1970)
…95
Fig. (3.7) Mohr-Coulomb failure criterion …96
Fig. (3.8) Determination of the modulus number and exponent
number (after Duncan and Chang, 1970)
…96
Fig. (3.9) Determination of F and G (after Duncan et al., 1980) …97
Fig. (3.10) Determination the unloading modulus Eur (after Duncan et
al., 1984)
…97
Fig. (3.11) Effect of stress path on the soil modulii (after Duncan et
al., 1984)
…98
Fig. (3.12) Gap modeling (after Cook, 1989) …102
Fig. (3.13) Three-dimensional interface element local and global axes …103
Fig. (3.14) Stress-deformation curves for hyperbolic interface element
(after Dessouki, 1985)
…103
Fig. (3.15) Application of incremental methods in nonlinear finite
element (After Owen and Hinton, 1980)
…106
Fig. (3.16) Incremental Iterative Newton-Raphson Method (After
Owen and Hinton, 1980)
…108
Fig. (3.17) Incremental Iterative Modified Newton-Raphson Method
(After Owen and Hinton, 1980)
…109
Fig. (3.18) Stress Reversal Algorithm (after Desai and Abel, 1972) …114
Fig. (3.19) Program modules for nonlinear FE code …117
Fig. (4.1) Greater Cairo Metro Network …120
Fig. (4.2) Line 2 – Phase 1 routing (After Richards et al, 1997) …120
Fig. (4.3) Grading of the granular deposits (After Richards et al,
1997)
…124
Fig. (4.4) BSS used in the second line (after El-Nahhas, 1999) …124
Fig. (4.5) Cutting face of the BSS (After Richards et al, 1997) …125
Fig. (4.6) Bolted reinforced concrete segments (After Richards et al,
1997)
…128
Fig. (4.7) Ground water sealing measures (After Richards et al.,
1997)
…129
Fig. (4.8) Fig. (4.8) The Slurry Plant (After Richards et al, 1997) …132
Fig. (4.9) Subsurface conditions at Lot 16 (after Ardman-ACE,
1991)
…132
Fig. (4.10) Initial mesh of Lot 16 …134
Fig. (4.11) Mesh after 21 steps …134
Fig. (4.12) Maximum stress level …137
Fig. (4.13) Displacement in x direction in mm …137
Fig. (4.14) Displacement in y direction in mm …138
Fig. (4.15) Displacement in z direction in mm …138
Fig. (4.16) Surficial settlement along the tunnel axis for Lot 16 …139
Fig. (4.17) Surficial settlement perpendicular to the tunnel axis at Lot
16
…140
Fig. (4.18) Measured and estimated lateral displacement for a vertical
plane at 9.40 m from the tunnel CL
…141
Fig. (4.19) The distribution of the normal stress in x-direction (t/m2) …142
Fig. (4.20) The distribution of the normal stress in y-direction (t/m2) …142
Fig. (4.21) The distribution of the normal stress in z-direction (t/m2) …143
Fig. (4.22) The distribution of the shear stress in x-y plane (t/m2) …143
Fig. (4.23) The distribution of the shear stress in y-z plane (t/m2) …144
Fig. (4.24) The distribution of the shear stress in z-x plane (t/m2) …144
Fig. (4.25) The distribution of the major principal stress (t/m2) …145
Fig. (4.26) The distribution of the intermediate principal stress (t/m2) …145
Fig (4.27) The distribution of the minor principal stress (t/m2) …146
Fig. (4.28) Lining modes of deformation (magnification factor =
20000)
…148
Fig. (4.29) The distribution of the normal stress in x-direction (t/m2) …149
Fig. (4.30) The distribution of the normal stress in y-direction (t/m2) …149
Fig. (4.31) The distribution of the normal stress in z-direction (t/m2) …150
Fig. (4.32) The distribution of the shear stress in x-y plane (t/m2) …150
Fig. (4.33) The distribution of the shear stress in y-z plane (t/m2) …151
Fig. (4.34) The distribution of the shear stress in z-x plane (t/m2) …151
Fig. (4.35) Lining pressure in t/m2 …152
Fig. (4.36) Initial mesh for Lot 12 (after Ardman-ACE, 1991) …154
Fig. (4.37) Surficial settlement along the tunnel axis for Lot 12 …156
Fig. (4.38) Surficial settlement trough perpendicular the tunnel axis
for Lot 12
…157
Fig. (4.39) Settlement versus depth along the tunnel axis for Lot 12 …158
Fig. (4.40) Settlement versus distance at a depth of 12.50 m for Lot 12 …159
Fig. (4.41) Distribution of the face axial displacement for different
face pressure values
…162
Fig. (4.42) The effect of the face pressure on the maximum axial
displacement
…163
Fig. (4.43) The effect of the face pressure on the surface vertical
deformation
…164
Fig. (4.43) The effect of soil arching on the face limiting equilibrium …165
Fig. (4.45) The effect of the face pressure on the maximum surface vertical
deformation.
…166
Fig. (4.46) The effect of the overcutting loss on the surface vertical
deformation.
…170
Fig. (4.47) Surficial vertical deformation trough for overcutting loss =
0.0%
…171
Fig. (4.48) Surficial vertical deformation trough for overcutting loss =
0.05 %
…172
Fig. (4.49) Surficial vertical deformation trough for overcutting loss =
0.30 %
…173
Fig. (4.50) Surficial vertical deformation trough for overcutting loss =
0.50 %
…174
Fig. (4.51) Surficial vertical deformation trough for overcutting loss =
0.75 %
…175
Fig. (4.52) Surficial vertical deformation trough for overcutting loss =
1.00 %
…176
Fig. (4.53) The effect of the overcutting loss on the maximum surface
vertical deformation.
…177
Fig. (4.54) Surficial vertical deformation trough for (a) overcutting
loss = 0.00 % and (b) overcutting loss = 1.00 %
…178
Fig. (4.55) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.0%
…179
Fig. (4.56) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.05%
…180
Fig. (4.57) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.3%
…181
Fig (4.58) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.5%
…182
Fig. (4.59) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.75%
…183
Fig. (4.60) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 1.0%
…184
Fig. (4.61) The effect of the tail grouting pressure on the maximum
surface vertical deformation.
…185
Fig. (4.62) The effect of the tail grouting pressure on the vertical
deformation of the crown and the invert
…186
Fig. (4.63) The effect of the tail grouting pressure on the maximum
vertical deformation of the crown and the invert
…187
Fig. (4.64) The analogue – a man pulling bricks around a room (after
Simpson, 1993)
…188
Fig. (5.1) North Sinai Developing Project (after Mazen and Craig,
1994)
…191
Fig. (5.2) El-Salam Syphon vertical alignment (after Mazen and
Craig, 1994)
…191
Fig. (5.3) Mesh for the inclined tunnels …193
Fig. (5.4) Geotechnical subsurface conditions at the instrumented
section “C” (after Esmail, 1997)
…193
Fig. (5.5) Surficial vertical deformation after construction of tunnel
T1
…195
Fig. (5.6) Surficial vertical deformation after construction of tunnel
T2
…195
Fig. (5.7) Surficial vertical deformation after construction of tunnel
T3
…196
Fig. (5.8) Surficial vertical deformation after construction of tunnel
T4
…196
Fig. (5.9) Surficial settlement troughs due to individual tunnels …197
Fig. (5.10) General layout of Al-Azhar Road Tunnels (after Ramond
and Guillien, 1999)
…201
Fig. (5.11) Mesh for the intersection …202
Fig. (5.12) Subsurface conditions at the site of the intersection …203
Fig. (5.13) Maximum stress level after driving the north tunnel …205
Fig. (5.14) Maximum stress level after driving the south tunnel …205
Fig. (5.15) Vertical deformation in mm after driving the south tunnel …206
Fig. (5.16) Vertical deformation in mm after driving the south tunnel …206
Fig. (5.17) Surficial vertical deformation of the untreated grounds …207
Fig. (5.18) Vertical deformation of the CWO tunnel in mm (the north
tunnel heading approaches the intersection)
…208
Fig. (5.19) Axial stresses of the CWO tunnel in t/m2 (the north tunnel
heading approaches the intersection)
…208
Fig. (5.20) Vertical deformation of the CWO tunnel in mm (the north
tunnel is completed)
…209
Fig. (5.21) Axial stresses of the CWO tunnel in t/m2 (the north tunnel
is completed)
…209
Fig. (5.22) Vertical deformation of the CWO tunnel in mm (the south
tunnel heading approaches the intersection)
…210
Fig. (5.23) Axial stresses of the CWO tunnel in t/m2 (the south tunnel
heading approaches the intersection)
…210
Fig. (5.24) Vertical deformation of the CWO tunnel in mm (the south
tunnel is completed)
…211
Fig. (5.25) Axial stresses of the CWO tunnel in t/m2 (the south tunnel
is completed)
…211
Fig. (5.26) Final deformation of the CWO tunnel (deformation
magnification factor 1000)
…212
Fig. (5.27) Some projects that used grouting techniques (after Tan and
Clough, 1980) …214
Fig. (5.28) Final vertical deformation of the CWO tunnel in mm
(weak grouting)
…216
Fig. (5.29) Final axial stresses of the CWO tunnel in t/m2 (weak
grouting)
…216
Fig. (5.30) Final vertical deformation of the CWO tunnel in mm
(medium grouting)
…217
Fig. (5.31) Final axial stresses of the CWO tunnel in t/m2 (medium
grouting)
…217
Fig. (5.32) Final vertical deformation of the CWO tunnel in mm
(strong grouting)
…218
Fig. (5.33) Final axial stresses of the CWO tunnel in t/m2 (strong
grouting)
…218
Fig. (5.34) Final vertical deformation of the CWO tunnel in mm (very
strong grouting)
…219
Fig. (5.35) Final axial stresses of the CWO tunnel in t/m2 (very strong
grouting)
…219
Fig. (5.36) Effect of grouting on the maximum internal stresses in the
CWO sewer
…220
Fig. (5.37) Effect of grouting on the maximum settlement of the CWO
sewer
…220
1
Chapter One
INTRODUCTION
1.1. General
Tunnels were utilized since the dawn of history. Man made use of caverns
as shelters and dwellings in the Prehistoric Ages. The old civilizations in Egypt,
Greece, India, Iraq, and Italy used hand-tunneling techniques to dig the ground
for several purposes such as mining, water supplying, burial and war. Tunnel
construction has been accelerating significantly since the Second World War.
The use of modern metallurgy and the contemporary hard alloys enables the
tunnel boring machines (TBMs) to work in a wide spectrum of ground condition
ranging from soft soil to very competent rocks. Modern and powerful machinery
provided tools to excavate tunnels and transport the spoil away. Current
surveying and GPS systems tolerate only a few centimeters deviation of tunnel
routing during driving. The development of new pressurized techniques allows
tunnel constructing even through unfavorable conditions such as soft ground and
high water table conditions.
Public and government resistance is continually solidifying against
disruption of traffic, trade and the environment caused by open-cut tunneling in
the urban congested areas. To meet challenge of the restricted requirements of
underground works, new and sophisticated tunneling techniques are used instead
of open-cut methods. Tunneling Engineering brings under one banner a diversity
of non-disruptive procedures for the installing of the underground facilities that
enclose both empirical thumb-rules and theoretical studies. As tunneling practice
is significantly ahead of its theoretical background, empirical rules based on
observational studies are frequently exploited; however, they cannot include the
impact of the new and improved methods used in tunnel driving on the ground
2
stability and groundwater control. Since tunnel failures can be extremely
threatening to life and properties, more research is required in the field of
tunneling to transform tunneling from art to science and to provide us with a
deep insight of the behavior of tunnels. To accomplish this goal, the theoretical
studies and the tunnel monitoring programs should be integrated to assess
tunneling in diverse ground conditions using suitable installation procedures.
New studies should model the complex ground behavior as well as the new
sophisticated tunneling techniques.
Many two-dimensional researches were conducted focusing on the crucial
factors affecting the tunnel construction and the safety of the surrounding
structures models. Hamdy (1989) and Ali (1990) considered the unloading
caused by soil removal is carried out in an incremental sense. At the end of each
increment the amount of ground loss is estimated; when the ground loss reaches
a specified value, the calculation is terminated. Ahmed (1991) used the
incremental non-linear FEM combined with the Convergent-Confinement
Approach of lining analysis to update the ground-lining interaction in which
beam elements are used to model the lining while two-dimensional plane strain
elements are used to model the soil. Esmail (1997) successfully used the Gap
Parameter Technique with some modifications to allow the simulation of the
tunnel construction stages.
Although, two-dimensional models are considered superior to the
empirical rules-of-thumb through allowing some modeling to the construction
techniques, they cannot grasp all the aspect of the tunneling process. Three-
dimensional models bestow more information about the face stability, tail
grouting and displacement field around and ahead of the tunnel. Till soon, little
literature is available in which the tunnel is presented by three-dimensional
model. This type of modeling is difficult to implement because of needed
computing and numerical capabilities especially when using the advanced
nonlinear soil models and gaps or interfaces. The complications in modeling of
3
soil excavation, shield driving, overcutting and tail grouting further obstacle this
type of analysis especially for soft ground pressurized shielded tunneling.
1.2. The Objectives of the Current Research
The Egyptian tunneling activities have augmented in the last two decades
for several purposes such as construction of subways, sewers and road tunnels. It
is anticipated that tunneling activities will continue at the same rate for at least
another decade to complete the plans of infrastructure renewing (El-Nahhas,
1999). The preponderance of the Egyptian tunnels were built through soft
grounds under high ground water pressures in which the pressurized closed face
shielded tunneling is considered the due method to advance tunnels to maintain
the ground stability and safety of operators. Egyptian tunnels impose many
diverse problems during routing, design and construction. The foremost problems
are related to the damage of surrounding feeble buildings due to surface and
subsurface ground subsidence. Prediction of deformation field around tunnels is
an inevitability to anticipate the potential impairments to neighboring buildings
and utilities.
The foremost goal of this study is to develop a three-dimensional model
that can capture the different aspects of soft ground pressurized shielded
tunneling. The developed model incorporates the sophisticated ground support
measures so as to provide a realistic predication of the deformation field
associated with tunneling in the geotechnical conditions prevailing in the
Egyptian tunneling projects. The developed model is used to update the studies
related to the bentonite slurry technique, which was used in Greater Cairo Metro
Project and many other giant Egyptian projects and proved to be very successful.
To achieve the goals of the anticipated enquiries, a nonlinear finite element
program, with capabilities of three-dimensional analysis, nonlinear soil
constitutive behavior and interface modeling, was developed by the author. A
special three-dimensional hyperbolic interface prestressed element is exploited to
4
model the soil-shield-lining interface. The proposed numerical model is used to
evaluate three case studies of the giant tunneling projects constructed in Egypt
namely, Greater Cairo Metro, El-Salam Syphon and the intersection of Al-Azhar
Twin Road Tunnels and the CWO sewer pipe at Port Said Street. The later two
case histories represent multiple tunnels in which three-dimensional analysis was
seldom utilized; they are typical three-dimensional problems that cannot be
simulated precisely using two-dimensional models or empirical superposition
techniques. The precautionary pre-treatment using soil grouting to minimize the
effect of Al-Azhar tunnels on the CWO sewer is investigated. The results of the
numerical modeling of the three case studies are then compared with the field
measurements compiled during tunneling activities in order to assess the validity
of the developed numerical model.
1.3. Outline of the Thesis
The thesis consists of six chapters. In the following section, the contents
of each chapter are briefed:
Chapter (2) describes the different aspects of shielded tunneling and the
techniques used in soft ground condition. The ground water effect on
the construction techniques is illustrated. A review of tunnel
instrumentations and the geotechnical aspects of tunneling design are
elucidated. The Different methods of ground deformation estimation
and effect of these deformations on structures are reviewed. The
evaluation methods of the induced internal forces in the lining are
surveyed. Face pressure and its effect of the face stability and ground
deformation are clarified. Ground improvement techniques used to
minimize the harmful effect of tunneling and increase the tunneling
stability are discussed.
Chapter (3) describes the elements of the developed model. Finite element
idealization is formulated with emphasis on nonlinear techniques and
5
the modeling of excavation and construction. The used nonlinear
models and nonlinear numerical procedures are explained.
Hyperbolic three-dimensional interface element formulations are
described. The proposed tunnel model is illustrated emphasizing on
simulating of the different stages of tunnel construction.
Chapter (4) comprises a three-dimensional analysis of the shielded tunneling
used during the construction of Greater Cairo Metro–Line2–Phase
1A. Different ground support measures and tunneling factors
included in the analysis are evaluated parametrically. Results are
compared to the field measurement compiled during the construction
for two different Lots. The geotechnical and constructional details
affecting the resulting deformation fields are clarified to recommend
successful tunneling conditions.
Chapter (5) encloses a three-dimensional study of multiple and twin tunnels. Two
case histories are discussed; namely, El-Salam Syphon and the
intersection of Al-Azhar and the CWO sewer. Two cases represent
different cases of subsurface condition and alignments. Different
factors affecting the mutual interaction of the analyzed tunnels are
discussed. The effect of ground modification utilizing pre-grouting
measures, so as to minimize the tunneling effect in tunnel
intersections, is assessed parametrically.
Chapter (6) presents a summary of the studies that were implemented in this
thesis along with different concluding points and annotations of the
considered case histories. Finally, recommendations for further
studies are pointed out.
6
Chapter Two
CONSTRUCTION, MONITORING AND DESIGN OF
SHIELDED TUNNELS
2.1. Introduction
While in prison for debt, a French engineer, Marc Brunel, watched a
worm boring through wood, using the hard shell on its head as a shield as it
tunneled into the wood, the worm excreted a substance that formed a rigid lining
behind it. Brunel copied this idea on a large scale. He used a large iron frame to
protect the sides of a tunnel while masons are lining the inside with brick. After
he patented his idea in 1820, Brunel used it in the construction of the Thames
tunnel in Britain during the period of 1825-1843. The employed shield consisted
of twelve sections; each was three-foot wide in which workers could excavate the
face then the whole cast iron assembly was inched forward, a section of brick
lining was built behind. During the construction, the tunnel was flooded at least 5
times; the consequent toll of death, injury and disease was quite formidable.
Further significant developments in subaqueous shielded tunneling were the
application of cast iron segmental linings installed in conjunction with the shield
advance and the use of compressed air in 1873 under Hudson river to overcome
water inflow problems. The performance of shielded TBM was enormously
enhanced by introduction of the bentonite slurry and the earth pressure balance
TBMs.
Selection of appropriate shields requires consideration of ground and
water condition, tunnel size, support system and the excavation environment. The
main factor that influences the choice of tunneling technique is the ground and
water condition as it favors the choice of some methods and present major
7
limitations on some other tunneling techniques. Wittaker and Frith (1990)
divided the major categories of ground conditions in tunneling as following:
a) Soft grounds: soft grounds include clays, gravels, sands and
weathered rocks in various states of decomposition. These
materials impart no difficulties in digging out and can easily be
removed by hand-excavation. However the difficulties in tunneling
arise from their position with respect to the groundwater table that
may result in mud and other unconsolidated material inflow to the
tunnel and associated ground loss. Tunneling in soft ground
conditions generally employs shields as standard practice to
provide safe working environment for workers. Almost all the
Egyptian underground constructions are situated within water-
bearing soft ground of various soil deposits and weak rocks.
b) Rock conditions: Rock strengths cover a wide range from relatively
weak sedimentary rocks of 10-40 MPa to strong igneous rocks of
150-300 MPa. Low strength rocks may prove advantageous to
machine excavation while high rock strength may preclude
machine excavation but require minimal temporary support. Tarkoy
and Byram (1991) reported recently the use of modern tunnel
boring machines instead of the drill-and-blast techniques in many
competent rock formations in Hong Kong.
c) Mixed face conditions: Tunneling at the bedrock horizon often
results in the upper part of the tunnel face being in soil or heavily
weathered rock while the lower part of the face is in rock. This
condition presents problems with machine tunneling and in
connection with provision of effective temporary support.
The shielded machines are classified into two main types (Wittaker and
Frith, 1990; Thomson; 1995 & Sutcliffe, 1996): non-pressurized and pressurized
8
TBMs. In the first category, TBMs cannot apply counterbalancing pressure at the
face while the second type of TBMs has a bulkhead that is provided to prevent
the face from collapse by applying a counterbalancing face pressure.
2.2. Non-pressurized Shields
Non-pressurized shields do not use counterbalancing pressure at the face
that may be used to minimize the ground deformation resulting from the potential
face instability. This type of TBMs has usually open or part-open face in which
direct or limited access to the face, or to a point immediately behind the face
cutters, is available. Access to the face allows operators to identify and deal with
any natural or artificial obstructions.
Non-pressurized TBMs are used for shorter drives in stable ground
conditions. Open face shields tend to be favored where the ground is sufficiently
firm to be free standing or where no measure of face support is required. The
open non-pressurized techniques are suitable for a wide range of cohesive ground
including rock, clays and silty clays, which can be below the groundwater table.
Non-cohesive soils above the water table are also suitable, but become less
appropriate with existence of groundwater pressure in cohesionless soils.
In case of low rates of advance, drainage of the face soil takes place,
which causes the strength of cohesive soils to change from cohesive to frictional
and the stand-up time will be short. To avoid these time-dependent face stability
problems in cohesive soils, the rate of machine advance should be sufficiently
rapid to ensure that undrained conditions will prevail. As the cohesive soil
becomes less plastic and more permeable, rates of advance have to be increased
to maintain undrained conditions. Where this is not possible then some form of
pressurized support of the face is necessary to avoid instability.
9
Szechy (1967) illustrated the basic structural features of an open shield as
following:
1. Shield body. This part of the shield is essentially a steel cylindrical
shell appropriately stiffened with ribs and bracing members. The shield
body houses the equipment such as hydraulic rams and pumping
equipment for pushing the shield forward relative to the lining as
shown in Fig. (2.1). A typical length of shield body is around 2 m
although it is dependent upon the diameter of the excavation.
2. Shield tail. The tail pan of the shield structure extends behind the
shield body and serves the purpose of providing space within which
the lining segments are erected during the tunnel lining stage. The tail
width is normally about one and a half times the unit lining width.
Additionally there is the necessity for a clearance width of the order of
25 mm between the tail and lining to permit alignment corrections.
3. Cutting edge. This part of the shield forms the leading edge and
requires to be heavily reinforced with steel plating. The cutting edge is
also frequently coated with an abrasion-resistant material to assist
cutting in harder ground. A common structural feature is the provision
of a hood forming the upper half of the shield cutting edge, which
gives protection to operators particularly when adjusting and
advancing the breast boards. Not all cutting edges incorporate a hood
feature in shield tunneling projects.
Non-pressurized shields can be classified into: manual, semi-mechanical,
mechanical and blind, with a number of variations within each of these classes.
Table (2.1) describes the different types of non-pressurized TBMs.
10
Fig. (2.1) Basic feature of an open face shield (after Szechy, 1967)
Advance Cutting Edge Shield Body Tail
Hydraulic Ram
Pressure Distribution
Ring
I- Ground Excavation in preparation for shield advance
II- Shield advance by rams pushing against tunnel lining via a pressure distribution ring
III- Retraction of pushing rams and erection of next ring of segmental support.
New Ring
11
Table (2.1): Non-pressurized TBMs (after Monsees, 1996).
Type Description Notes Sketch
Hand-dug (manual)
shield
Good for short, small tunnels in hard, non-
collapsing soils. Usually equipped with
face jacks to hold breasting at the face. If soil conditions require it, this machine may have movable hood
and/or deck
A direct descendent of the Brunel shield. Now
largely replaced by more mechanized equipment. Sometimes used at the
head of large cross-section, jacked tunnels.
Semi-mechanized
Similar to the hand-dug shield, but with a back
hoe, boom cutter (roadheader) or the like
Until very recently, the most common shield. Often equipped with
“pie plate” breasting and one or more tables. Can
have trouble in soft, loose, or running
ground. Compressed air may be used for face
stability in poor ground.
Mechanized
A fully mechanized machine. Excavates
with a full-face cutter wheel and pick or disc
cutters.
Manufactured with a
wide variety of cutting tools for various soils Face openings (doors,
guillotine, and the like) can be adjusted to
control the muck taken in versus the advance of the machine May also
be used when compressed air for face stability in poor ground.
Blind shield
A blind simple shield used in very soft clays and silts. Adjusting the aperture opening and
the advance rate controls muck
discharge.
Used in harbor and river
crossings in very soft soils. Often results in a wave for mound of soil
over the machine.
12
2.3. Pressurized Shields
2.3.1. Introduction
The need for a machine capable of tunneling through non-cohesive ground
both above and below the water table, without affecting the overlying properties
gives rise to special types of TBMs known as pressurized closed face machines.
These machines incorporate a pressure chamber immediately behind the front
cutting head or disc. The chamber, filled with compressed air, water, slurry or
soil, provides a counterbalance pressure to soil and water pressures. No access to
the face is available and all operations are controlled by the machine operator,
who will be stationed at a control console in the rear of the shield. Special seals
are incorporated between the cutter head and machine body for the purpose of
sealing mud and water. Various designs of seal have been employed, with multi-
lip seals proving successful. The propelling movement of the shield requires a
longitudinally solid liner to offer the support. Special measures are required to
seal the joint between the shield tail and the installed lining segments against the
grouting pressure that is injected behind the segments. Tail grout is used to
counterbalance the ground and water radial pressure and minimize the ground
loss.
Precast concrete or cast iron segmental lining is the prevailing lining
system for soft ground TBMs. A small segment, the key, is often included in the
system; Fig.(2.2) describes this system. The segment shape is usually rectangular
or trapezoidal to allow the control of tunnel curved alignment. The assembly of
the lining system takes place inside the tail of the shield in a staggered system.
Special care must be paid to the joint insulation and compressibility. Bituminous
packing or rubber gaskets are usually used for the joint filling in the insulation
layer. Precast concrete segments are assembled either by a tongue-and-groove
interlocking system or by bolting.
13
Esmail (1997) summarized the main three types of the tail seal used for
pressurized TBMs as rubber seal, steel brush seal and Extru-concrete seal. Fig.
(2.3.a) shows a typical rubber seal. The stiffness of rubber seals is frequently
insufficient to close the gaps between inaccurately placed segments. The steel
brush seal is arranged in as many as five rows, one behind the other as shown in
Fig. (2.3.b). Grease is pumped into the chambers between the individual rows,
whereby the grease pressure in each chamber is increased towards the shield tail
so that the last chamber pressure is about 2 bars higher than the grouting pressure
in order to prevent the grout from penetrating through the brushes to the shield
interior. The Extru-concrete seal system comprises a movable steel ring used to
close the shield tail joint and supported by hydraulic jacks from the body of the
shield as shown in Fig. (2.3.c). The hydraulic jack circuit is linked to a regulated
gas reservoir, which provides the elastic spring. The steel device is sealed against
the shield tail with a rubber seal, and with spring strips against the segments.
Extru-concrete is pumped through the movable steel device into the shield tail
joint. The Extru-concrete is a normal concrete with chemical additives to
improve its hardening-rate. The gaps between inaccurately placed segments are
sealed by the concrete
Although the pressure balance machines have been designed to operate in
unstable soil conditions such as non-cohesive soils below the water table,
practically, they are used in a much wider range of soil conditions. Many
variations of pressure chamber shield have been developed some of which
incorporate crushing devices to cope with stones and boulders. Various
pressurizing techniques are employed; the oldest technique is to use the
compressed air as a counter measure against the groundwater pressure. Modern
techniques include liquid or earth supporting measures. The following section
describes the different types of the pressurized TBMs and the different aspects of
each type.
14
Fig. (2.2) Segmental lining (after Ezzeldine, 1995)
15
Fig. (2.3) Tail seal systems (after Esmail, 1997)
16
2.3.2. Compressed Air Shields
Compressed air was used as early as 1830 by a British engineer (Thomas
Cochrane) in sinking caissons. In 1873, Clinton Haskins promoted a railway
tunnel under the Hudson River in New York, which used compressed air to
support the tunnel against the pressure of water above the tunnel. Compressed air
working is used in conjunction with open face shields in subaqueous conditions
so as to hold back the soil and groundwater by applying a counterbalancing air
pressure. Fig. (2.4) shows the details of the compressed air TBM used in Cairo
Wastewater Project. The air pressure is used to prohibit groundwater intrusion
into the tunnel. The result is decreased movement of the ground into the tunnel.
Drying up of the tunnel face by the action of compressed air will encourage non-
cohesive wet soils to exhibit improved ability to stand and to be controlled by
breasting. The ground properties in the dried region must be sufficient to prevent
face instability (Ezzeldine, 1995). Sometimes, pre-grouting either from the
ground surface or from the face may be used to increase the ground strength.
Special attention needs to be paid to effectively seal the space between the
lining and the excavated tunnel sides in order to maintain steady air pressure.
Where open gravel with little interstitial material such as sand occurs, then
compressed air losses can easily arise. In this case, air losses may be limited by
the application of bentonite or a bentonite-cement mixture at the face. Escapes of
compressed air through permeable beds of overlying unconsolidated materials
can result in piping action and possibly give rise to forming a significant path for
water to flow into the tunnel. The pressurized zone extends from the tunnel face
backward up to the bulkhead at some distance behind the shield. At the shield
tail, the ground surface is under air pressure limiting the possibility of ground or
water intrusion into the working zone. Therefore, the need for the grout and the
tail seal is diminished, as they are needed to deal with ground under supportive
air pressure. A conventional grouting system may be regarded as sufficient in
many instances. In these cases, pea gravel is used as the primary grout material
17
followed by mortar sometime later. The required longitudinal reaction from the
lining system is relatively low in this type of pressurized TBMs.
A compressor air plant located above the ground surface is used for
supplying compressed air to maintain the face pressure, providing power supply
to air tools for excavation, drilling, air winching, and other purposes. A cooling
system must be incorporated into the compressor to release the generated heat
from the compressed air and to reduce its humidity by condensation. A bulkhead
is constructed to seal off the working space from outside air. The bulkhead must
include air locks to allow material and personnel passage to the face. Two
separate types of locks are necessary: locks for personnel and for materials as the
rate of air decompression of the personnel lock is regulated to be slower than that
required for the material lock for hygienic reasons. The bulkhead must be
fabricated with great care in order to insure that no voids are left for air to escape
through joints around air, slurry and power pipes passing through it. Ezzeldine
(1995) described two configurations of the compressed air bulkhead as
following:
1. The bulkhead is constructed close to the pressurized face
using a steel cylinder lock. The head part only is locked off
to avoid working in compressed air. The operator can handle
the excavating equipment in the inside pressurized zone or
in free air by observation through a glass panel or with the
aid of a TV camera. It is still possible for a man to enter the
chamber if necessary to remove any obstructions such as
boulders.
2. The bulkhead is constructed on the ground at the head of the
shaft. In this case, a T-lock may be placed at the shaft
entrance. All work in the line, the shield and the shaft
bottom is accomplished under compressed air.
18
Working in compressed air for a long time can be a serious health hazard.
So, whenever operating pressure is needed to be greater than one bar, pressurized
closed face shields offer a less hazardous alternative to compressed air working.
Fig. (2.4) Compressed-air TBM used in Cairo Wastewater Project
(after Shalaby, 1990)
Faceram
Sliding table
Backhoe 875 mm
1500 max.
4260 O/A Body 9000 STK 1375 Tail Skin Shovel Rams
19
2.3.3. Liquid Support Shields
A suspension or water is maintained at a pressure immediately behind the
cutting head in a pressure chamber to balance the excavated face. The simplest
form of the liquid support shields employs water pressure. The appropriate soil
conditions for this type of equipment are cohesive soils that may incorporate
cobbles, and sands and gravels. A cone crusher may be used to reduce all gravel
or boulder material to a defined maximum particle size before it enters the
pressure chamber to be pumped away as slurry. Frequently an auger-powered
cutter head carries the excavated spoil back into the water pressure chamber,
where it is mixed and transported to the surface by a pumped slurry system. For
this type of water-based slurry treatment and disposal are less complex and costly
than for bentonite slurries.
The pressurized Bentonite Slurry shields were introduced in the 1960s for
segmental tunneling. The basic principle of operation of this method is to inject a
pressurized slurry mixture into a chamber enclosing the working face as shown
in Fig. (2.5). The shield area in which the cutting wheel is rotating is designed as
the extraction chamber. A slurry pressure inside the chamber is set to balance the
groundwater head and the sufficient soil pressure to prevent soil instability. The
face is excavated with full-face rotating cutting faces that may be flat-faced plate,
drum or dome-shaped. The excavated material is forced into the pressurized
slurry chamber behind the head cutting head through slits or ports. Some Slurry
Shields also have a crushing capability. Stones and cobbles passing into the
pressure chamber are diverted into a crusher chamber that reduces them to an
acceptable size for pumping. Unwanted consolidation can occur through several
mechanisms including loss of groundwater into the tunnel face where face
support slurry does not precisely balance groundwater pressures. Permanent
surface settlement can be caused where face instability is allowed to develop.
20
Unless the earth pressure at the face is precisely balanced there will
always be movement at the ground surface. If the face is allowed to move
towards the shield when a tunneling shield is advancing, it will result in a zone of
surface settlement traveling in front of the shield. Conversely if the shield is
forced forward into the face so that soil moves away from the shield, it can result
in a zone of surface heave traveling in front of the shield. The required balance
between these two extremes is a shield, which advances at such a rate that the
soil neither moves towards the shield nor is thrust away. The pressure at the
shield face should ideally be maintained at the at-rest pressure to avoid horizontal
compression or expansion of the soil and prevent settlement or heave.
The difference between water-pressure and slurry-pressure machines and
when either would be appropriate to be used is not readily distinct. For some
cohesive soils it may only be necessary to use water that forms perfectly
adequate slurry for face support and spoil conveyance as it is mixed with the
natural excavated soil. In non-cohesive fine-grained soils above the water table,
the slurry will penetrate the face only a little, so no special measures are needed,
except to ensure that excess slurry pressures do not cause soil fissuring. In
coarse-grained non-cohesive soil, however, the objective is for the slurry to
create a zone of penetration and to build up a filter cake. In open-structured
ground, such as gravel or cobbles, even greater care needs to be given to the
slurry formulation and its additives to avoid loss of material and pressure. The
slurry has a bentonite base but various additives may improve its stabilizing
performance. Depending on the nature of the soil, the slurry needs to be designed
with appropriate additives, such as polymers and cellulose-based materials, if it is
to fulfill these objectives. Soils exposed at the tunnel face are penetrated by the
slurry and become sufficiently solidified to be suitable for excavation by the
cutter head of the machine. The material cut collects in the invert where agitation
causes liquefaction sufficient for pumping out of the tunnel together with soil
particles and cobbles if present. The bentonite is returned to the face after
21
separation. It should be pointed out that slurry pressure balance machines are
now often selected not only for the geotechnical advantages of pressure balance
in difficult soil conditions but also for their technical and economic efficiency
even in stable soil formations.
1. Cutting wheel 5. Compressed air lock 9. Compressed air buffer
2. Cutting wheel drive 6. Erector 10. Submerged wall
3. Extraction chamber 7. Lining segments 11. Suspension
4. Pressure wall 8. Tunneling jacks 12. Conveyor pipe
Fig. (2.5) The Hydroshield (after Herrenknecht AG, Germany)
22
2.3.4.Earth Support Shields
These shields use the excavated soil as the medium to provide the required
face pressure. Some versions operate with a disc head and ports; others with
spoke configurations in which arrangement and the opening ratio are determined
by the nature of the ground. Earth Pressure Balance Shields (EPBSs) are most
suited to soft and unstable formations including high plasticity clays, silts and
granular soils with a high percentage of fines. Machines combine a slurry
chamber with mechanical earth pressure balance, are frequently employed where
ground movement is a primary concern. These machines are less well suited to
highly permeable soils and where there are hard inclusions. As the shield
advances, the spoil is forced into the chamber behind, forming an impermeable
plastic mass, which is maintained at a predetermined balancing pressure. The
spoil is removed from this chamber by an auger conveyor. A variety of devices
control pressure and spoil discharge to the required level. The configuration of
Herrenknecht EPBS system is shown in Fig. (2.6).
Broadly speaking, slurry machines are designed primarily for sandy or
gravelly soils. As long as a bentonite cake can be formed, it is possible to
maintain face stability by applying a counter balance pressure. Slurry machines
can be used in clayey ground but the slurry treatment process may require more
time and be more costly if the clay disaggregates in the slurry mud. EPBSs are
preferred to slurry machines when the grain size of the soil decreases to silts and
clays because of its mucking system. Low permeability clayey silty layers can
safely be kept stable by applying an earth pressure. Other parameters to be
considered when selecting a tunnel machine include items such as the surface
area capacity for treatment plant with fine-grained soils, discharge regulations,
cost of additives for EPBSs, … etc.
In several cases manufacturers have combined the advantages of slurry
pressure chamber and mechanical earthpressure balance. Thomson (1995)
23
referred to these combined pressure feature machines as combined pressure
machines. Examples of the combined machines includes
• Slime Shield: The Daiho Company from Japan developed this type
of TBM for working in high groundwater pressure conditions or in
sandy soils that have no plastic flow. Slurry based on bentonite or
other chemical additives is injected into the chamber in relatively
small percentages. This is then mixed in with the natural soil to
produce the required plastic flowing material, which is also
impervious.
• Iseki Mechanical Earth Pressure Counter-Balance Shield
(MEPCBS): This type provides a degree of mechanical earth
balance by having the cutting head mounted so that it can be
independently pressed against the soil face. By using a combination
of slurry pressure and mechanical earth pressure, the shield
pressure can be maintained at a level above the active earth
pressure but below the passive earth pressure reducing the risk of
settlement and heave. It also allows a better control over the
volume of soil removed by adjusting the openings on the face disc.
MEPCBSs are particularly suited to working in water-bearing
sands, silts and clays.
• Herrenknecht Mixshield TBM: This machine involves many types
of face support measures. The counter pressure can be applied
using compressed air, slurry or the excavated ground itself. The
change from mode to another is fast and incorporated in the
machine design; thus, a wide spectrum of ground can be excavated
employing the same TBM (Herrenknecht and Maidl, 1994)
24
1. Cutting wheel 5. Compressed air lock 9. Conveyor belt
2. Cutting wheel drive 6. Erector 10. Screw Conveyor
3. Extraction chamber 7. Lining segments
4. Pressure wall 8. Tunneling jacks
Fig. (2.6) The EPB TBM (after Herrenknecht AG, Germany)
25
2.4. Tunnel Monitoring
Many construction contracts for tunnels incorporate the geotechnical
instrumentation and monitoring program as an integral part of the construction
work. Tunneling monitoring programs can be considered as a safety measure to
assure no excessive ground deformation will endanger the nearby buildings and
utilities. Another motive for conducting tunneling instrumentation program is the
subsurface conditions, which are usually too complex to ensure a reliable and
economic design of tunnels. The designer has to make some assumptions to carry
out an initial design that scopes for modification if unforeseen conditions arise on
the basis of the feedback of the monitoring observations. The instrumentation
program provides the geotechnical engineer with information for checking and
verifying his design assumptions.
An instrumentation program is a comprehensive approach that assures that
all aspects of instrumentation from planning and design through maintenance and
rehabilitation are commensurate with the overall purpose. To be fruitful, such
monitoring programs must be carried out for well-defined purposes, be well
planned, and be supported by competent staff through completion and
implementation of results from the monitoring program. The principal objectives
of a geotechnical instrumentation plan may be generally grouped into the
following four categories:
1. Analytical, assessment of the data obtained from geotechnical
instrumentation may be utilized to verify design parameters, design
assumptions and evaluate construction techniques.
2. Prediction of future performance, instrumentation data should be used in
justifiable predictions of future behavior of tunnels in similar
environments.
3. Legal evaluation, valid instrumentation data can be valuable for potential
litigation relative to construction claims.
26
4. Development and verification of future designs, analysis of the
performance of existing tunnels and instrumentation data generated during
operation, can be used to advance the state-of-the-art of design and
construction.
More than one type of the same instrument may be used to provide a
backup system even when its accuracy is significantly less than that of the
primary system. Repeatability can also give a clue to data correctness. It is often
worthwhile to take many readings over a short time span to determine whether a
lack of normal repeatability indicates suspect data. Murray (1990) discussed the
layout of the instrumentation program. He concluded that the most practical
approach is to provide detailed monitoring at a few locations where the
conditions are considered more critical and to augment this information with
settlement observations from elsewhere. The most critical areas could be those
where the structures are highest, where the soft soils are deepest, or where the
consequences of failure are most unacceptable. The wrong type of instruments
placed in inappropriate locations can provide information that may be confusing,
or divert attention away from other signs of potential distress. The factors needed
to be considered in selecting a particular design of instrument are summarized as
following:
1. The instrument must be able to be transported and installed without
damage or significant change of calibration. It must be able to
withstand the effects of construction and sustained loading.
2. The use of simple direct operating mechanisms may avoid the
problems of maintenance and reliability. Conversely, if complex
systems were to be used, possibly because of a requirement for
automation or accuracy, consideration would need to be given to how
such instruments should be maintained.
27
3. Damage by construction activity may be minimized or even prevented
by placing the monitoring system outside the area of the construction
activity.
4. A particular design of instrument may more readily lend itself to a
requirement for automatic data logging.
5. The choice of instrument on the basis of cost should include the costs
incurred in installing, reading and evaluating the data.
6. Some types of instrument employ measurement principles that have
better stability characteristics than the other ones.
7. The selection of a particular instrument to attain a desired accuracy can
have an influence on most of the other factors referred to above.
Most instrumentation measurement methods consist of three components:
a transducer, a data acquisition system, and a linkage between these two
components. A transducer is a module that translates a physical change into
analogous electrical signals whilst data acquisition systems are the portable
readout units. The different measuring techniques used in geotechnical
instrumentation are classified into one of the following categories:
(a) Pneumatic devices. Pneumatic devices are used in pneumatic piezometers,
earth pressure cells, and liquid level settlement gages. The schematic
diagram in Fig. (2.7) illustrates the structure of a pneumatic device where
the measurements are made under a condition of no gas flow. While the
increasing gas pressure applied to the inlet tube is less than the required
pressure (p), it merely builds up until the applied gas pressure just exceeds
(p). At this moment, the diaphragm deflects allowing gas to circulate
behind it into the outlet tube and flow is recognized using a gas flow
detector. The applied pressure can be read on a Bourdon tube or an
electrical pressure gage.
28
(b) Vibrating wire devices. Vibrating wire devices are used in piezometers,
earth pressure cells, and liquid level settlement gages and deformation
gages. In a vibrating wire device a length of steel wire is clamped at its
ends and tensioned so that it is free to vibrate at its natural frequency. The
frequency of the vibration of the wire varies with small relative
movements between the two end clamps of the vibrating wire device. The
wire can therefore be used as a pressure sensor as shown in Fig. (2.8). The
wire is plucked magnetically by an electrical coil attached near the wire at
its midpoint, and either this same coil or a second coil is used to measure
the period or frequency of vibration which is dependent on the bending of
the diaphragm and hence on the pressure (p). The attached wire is under
near maximum tension at zero pressure. This tension applies the greatest
demand on the clamping and annealing of wire, a condition that may
cause creeping and slippage of the wire at the clamps, which results in a
frequency reduction unrelated to strain. This is commonly known as drift
of the baseline pressure or zero drift.
(c) Electrical resistance devices. Electrical resistance devices are sued in
strain gauges, which in turn have been used in many measurement
devices. An electrical resistance strain gage is a conductor with the basic
property that resistance changes in direct proportion to change in length.
Measuring resistance a Wheatstone bridge circuit can be used to calculate
the linear deformation of the wire.
(d) Other devices that use the electric or the magnetic field changes due to
linear deformations.
Geotechnical instrumentation for tunneling projects may be classified into
two main types namely: the deformation-measuring instruments, and the stress-
measuring instruments. The deformation instruments are used to assess the
ground displacement fields and the convergence of the lining. The stress-
29
measuring instruments are used to measure the pore water pressure, the soil
pressure and stresses in lining segments. In the following, a brief description of
each type is given.
Gas Flow Detector
Inlet tube
Outlet tube
Pressure GaugeTransducer Body
Pressure (p)
Flexible diaphragmattached to
transducer bodyaround rim
Inlet valve
Gas supply
Fig. (2.7) Schematic diagram of a pneumatic device (after Joyce, 1982)
Transducer Body
Flexible diaphragm
Pressure (p) Signal cable Frequency counter
Tensioned steel vibrating wire
Electric coil Fig. (2.8) Schematic diagram of a vibrating wire device (after Joyce, 1982)
30
2.4.1. Deformation Instrumentations
The ground displacement around tunnels could be classified as ground
superficial settlement and subsurface displacements that occur in both vertical
and horizontal directions. Any instrumentation program should be designed
carefully to fulfill the requirements of those two categories of displacement.
Another type of the deformation measurements is the tunnel convergence
measurements. In this part the two categories of deformation measurements are
discussed. A main concern of tunnel construction in soft ground is the
measurements of the ground displacements caused due to tunnel excavation to
evaluate their effects on the neighboring structures. Ground deformation
measurements are used to measure the deformation of the soil or rock mass. The
measurements are taken at varying distances depending on ground conditions. If
the ground conditions change frequently, the measuring sections are arranged
more frequently. The instruments for measuring ground deformation are grouped
into the following categories:
1. Surveying Methods. Surveying methods are used to monitor the
magnitude and rate of horizontal and vertical deformations of the
surface monuments near the tunnel routing. When subsurface
deformation measuring instruments are installed, surveying methods
are also often used to relate instrument measurements to a reference
datum. Surveying methods include optical leveling, taping, traverse
lines, measuring offsets from a baseline, triangulation, electronic
distance measurement, trigonometric leveling, photogrammetric
methods, and the satellite-based global positioning system. All
surveying methods must be referenced to a stable reference datum: a
benchmark for vertical deformation measurements and a horizontal
control station for horizontal deformation measurements. Great care
must be taken to ensure stability of reference datum. Surface
measuring points (points on the surface that are used for survey
observations, and that may move) must be stable and robust points that
31
will survive throughout the project life, and must be isolated from the
influence of frost heave and seasonal moisture changes. Fig. (2.9)
shows a typical measuring point for monitoring settlement on the
surface of ground.
2. Extensometers: Extensometers are devices for monitoring the
changing distance between two or more points along a common axis.
3. Inclinometers: Inclinometers are devices for monitoring deformation
parallel and normal to the axis of a flexible pipe by means of a probe
passing along the pipe.
Fig. (2.9) Measuring point for monitoring surface settlement
(after EM 110-2-1908, 1995)
32
2.4.1.1. Extensometers
The single and multiple point rod extensometers are devices to monitor
displacements at various depths employing a rod or multi-rods, which are
anchored at one end of a borehole as shown in Fig. (2.10). Relative movements
between the end anchors and the reference tube of the borehole are measured
with either a dial depth gauge or a vibrating wire transducer. The multi-point
magnetic extensometer contains ring magnets sliding on a central access tube.
The magnets are fixed in the ground at locations where movement is to be
monitored as shown in Fig. (2.11). A probe within the access tube and senses the
positions of magnets outside the tube. The rod probes incorporate two switches at
a fixed gauge length separation, permitting precise measurements between pairs
of adjacent magnet targets. Switches close on entering a magnetic field activating
a buzzer or indicator light in the reading instrument or cable drum. The magnetic
multi-point extensometers can monitor any number of points at little extra cost
and with no increase of borehole diameter. Displacements can be measured in
two or three dimensions by combining this instrument with an inclinometer or
settlement gauge.
2.4.1.2. Inclinometers
An inclinometer is a device for measuring the inclination from the vertical
of a structure or casing to which the inclinometer is attached. The inclinometer
system involves a torpedo probe, fitted with guide wheels. The probe contains a
tilt sensor, connected by a graduated cable to a digital readout unit. Fig. (2.12)
shows the component and the installation of the inclinometer. The inclinometer
probe is inserted into the grooves of specially installed access tubing. The tilt
sensor enables the horizontal deviation between the probe axis and the vertical
plane to be recorded. Measurement of tilt and probe depth are used to compute
the horizontal deviation of installed access tubing from true vertical. The
installation borehole is drilled to a depth beyond the zone of anticipated
movement to ensure that a satisfactory fixed datum is provided. The borehole is
33
either grouted before or after access tubing installation or can be backfilled with
sand or pea-gravel after access tubing installation. Access tubes are joined using
couplings and filled with water to overcome buoyancy and ingress of grout
during installation. Readings are taken at regular depth intervals of 0.5 m or l.0 m
within the access tubing, measured by graduation markers on the cable. Figs.
(2.13) shows the measuring technique of the inclinometer system. The lateral
displacement of the access tubing is obtained by integration of the observed
horizontal deviation from the initial base readings. Measurement of vertical
deviation caused by settlement or heave can be obtained by fitting the
inclinometer access tubing with magnetic targets that is retained by leaf springs
in boreholes, or attached to plates embedded in soil or fill.
Fig. (2.10) Rod extensometer installation
(after Soil Instruments Ltd., 1999)
34
Fig. (2.11) Installation of magnetic multiple point extensometers
(after Soil Instruments Ltd., 1999)
35
Fig. (2.12) Installation of inclinometers
(after Soil Instruments Ltd., 1999)
36
Fig. (2.13) Inclinometer measurement of displacement
(after Soil Instruments Ltd., 1999)
θ
x sin θ
37
2.4.2. Convergence Measurements
The behavior of a tunnel is generally exhibited in the convergence of the
tunnel lining and the enfolding ground. Convergence of the tunnel lining is an
important indicator of tunnel stability, which is relatively easier to measure than
loads, strains, and stresses. The rate of convergence is the most important
parameter to be observed. Fig. (2.14) shows conceptually several time plots of
rate of convergence; curves (a) and (b) show decreasing convergence, indicating
eventual stability of the structure while curves (c), (d) and (e) indicate instability
problem of the tunnel.
The common convergence measurement is one taken across the horizontal
diameter. Vertical measurements are not usually taken due to interference with
equipment and traffic. There are two techniques for convergence measurements;
namely:
1. Surveying: Using of precision tapes and precision leveling techniques
to measure absolute displacement of fixed points or relative
displacements between measuring points. This method of measurement
has high degree of accuracy that ranges between 0.01 and 0.1 mm for
relative displacement and 2 mm for absolute displacement. Obtaining
access clear sight to the reference points, locating instrument stations
out of the way of construction and providing stable reference datum
are the major problems in using these techniques.
2. Tape extensometers: The tape extensometer is portable tape used to
measure displacement between pairs of permanently fixed reference
studs or eyebolts grouted into shallow drill holes in the lining as shown
in Fig. (2.15). The tape unit comprises a stainless steel measuring tape
with equally spaced precision punched holes. The resolution of the dial
gauge is usually 0.05mm.
38
Con
verg
ence
Rat
e
Time
b
c
de
a
Fig. (2.14) Patterns of convergence rates
(after EM 1110-2-2901, 1997)
Fig. (2.15) Tape extensometer installation and usage
(after Soil Instruments Ltd., 1999)
39
2.4.3. Stress Measurements
Pressures exist in a soil mass due to the weight of overburden, water, and
external loads. Tunneling changes the state of stresses in the soil mass in the
neighborhood of the tunnel. It may be important to quantify the effect of tunnel
on the state of stress in soil to estimate the contact stress between the soil mass
and the tunnel lining. However, these types of measurements are usually not
successful, because the presence of the soil stress instruments affects the
measured stresses and the installation will also obscure the work of the TBM
(O’Rouke, 1979). A better alternative is to equip the lining with sets of strain
gages for determining strains and loads in the lining and hence revealing the
acting soil pressure on the lining using back analysis. Tunnels and tunnel
construction techniques may affect the water pressure inside the soil. In this case
the groundwater requires monitoring for the following reasons:
1. Groundwater resources must be protected for environmental and
economical reasons.
2. The tunnel could act as a groundwater drain and causes problems of
ground stability.
3. Groundwater lowering could result in unacceptable formation
compaction or consolidation, resulting in ground surface settlements.
4. Hydraulic tunnels’ leakage could propagate through the soil and cause
seepage that may lead to ground stability problems.
Piezometers are used to measure groundwater pressure. They are installed
in boreholes from the ground surface and from the tunnel lining. In the following
sections, the different types of strain gauges and piezometers are described.
40
2.4.3.1. Strain Gauges
Strain gauges are used for measuring the strains in concrete or steel lining.
The stresses within these sections are calculated from the strains by using
theories of elasticity that relate the strain state to the stress state. Bending
moments and thrust forces in the lining are then calculated from the stresses.
Two types of gages are generally used for measuring strains: surface gages and
embedded gages. Strain gages can be further divided into short and long-term
depending on the duration of measurements.
Usually short-term strains are best measured by electrical type gages,
while some long-term strains (e.g., creep and shrinkage) can be conveniently
measured using detachable mechanical gages. El-Nahhas (1980) describes three
types of vibrating wire strain gauges to be used in tunnel monitoring programs,
namely: weldable gauges used for steel lining, surface gauges and embedded
gauges used for inside and outside walls of concrete lining. Fig. (2.16) shows
some details of the three types of strain gauges.
2.4.3.2. Piezometers
The basic principle of all piezometers is that the porewater pressure in the
soil is transmitted through a porous element to a measuring mechanism. Most
piezometers require some movement of pore water to activate the measuring unit.
The time required for water to flow to or from the piezometer to create
equalization with the porewater pressure is called the time lag. Time lag is not
significant when piezometers are installed in highly pervious soils such as coarse
sands.
Standpipes or Casagrande piezometers are the simplest and the cheapest
piezometers. They consist of simple tubes with a porous tip connected to its
lower end. Groundwater level corresponds to the height of the water surface in
the standpipe above the piezometer tip, which is measured with a dipmeter or
41
using Bourdon gauge for artesian water. Bentonite and grout are used to seal the
borehole above the tip. The vibrating-wire or pressure transducer piezometer has
a tip comprises a porous element integral with a diaphragm type vibrating wire
pressure transducer, installed in boreholes. The pore pressure is transmitted
through the porous element causing a deflection in a diaphragm. The deflection is
measured using the vibrating-wire transducer. An airline is required to maintain
atmospheric pressure on the non-water side of the diaphragm. The volume of
flow required for pressure equalization at a diaphragm piezometer is very small,
and the time lag is very short.
The pneumatic piezometer has a tip comprises a porous element integral
with a proven diaphragm transducer, installed either in a borehole or by pushing
into shallow depths in soft soil. Twin tubes connect the transducer to the portable
readout unit. Air or nitrogen is forced down one line and when its pressure equals
the pore water pressure it forces open the membrane valve and flows up the
return line to a flow indicator. The balance pressure can then be read off a
Bourdon gauge.
The hydraulic piezometer has a porous piezometer tip installed and sealed
above the measuring level. The tip is connected to the readout location by twin
tubes. De-aired water is circulated through the tubes until the tubes and the tip
fire completely filled; they remain filled throughout the working life of the
installation and can at any time be re-flushed to remove air or gases that may
have accumulated. The pore water pressure at the piezometer tip can then be
measured at the remote end of either water tube, making a correction for the head
difference between the tip and the measuring gauge. The instrument measures
pore pressures by measuring the head of water using mercury manometers. Fig.
(2.17) shows the features of the different piezometer types.
42
Fig. (2.16) Different types of vibrating wire
strain gauges (after El-Nahhas, 1980)
43
Fig. (2.17) Piezometer Types (after Murray, 1990)
44
2.5.Design Aspects of Shielded Tunnels
Performance deficiencies and failures in tunneling not only endanger the
tunnel itself but also may imperil nearby buildings and utilities resulting in life
and property losses. The tunnel designer has every obligation to elude any
conceivable harmful tunneling effects and to guarantee a competent and
economical method of tunneling. There are several basic considerations in the
design of soft ground shielded tunnels; Monsees (1996) concluded the following
design aspects of soft ground tunnels:
1. Face stability: Face stability prognosis along the full tunnel routing is
required to assess the prospects of the collapse of the excavated face to
into the tunnel and to choose the amended equipment and methods of
tunnel construction. The stability of the tunnel face is contingent upon the
type of the ground being excavated, the ground inherent stress and
groundwater condition, the rate of advancement, the face size and face
supporting technique.
2. Ground deformation: Excavation of tunnels causes dilatation of
enfolding ground into the excavation. The magnitude of those movements
is a function of soil type, the presence of water, rates of tunnel advance,
the tunnel size and the tunnel support. Ground disturbance at the tunnel
triggers off a chain of movements up to ground surface leading to
formation of subsidence troughs that may cause damage to nearby
structures at the ground surface.
3. Lining stability: Tunnel lining is the structural system that maintains
the shape and the stability of the excavated tunnel by means of supporting
the surrounding ground after shield advancement. The induced lining
stresses and deformations arising from interaction with the surrounding
convergent ground must be estimated to ensure satisfactory performance
of the constructed tunnel. Lining waterproofing, invulnerability to the
hydrostatic ground pressures and appropriate countermeasures to water
45
ingress or egress are vital to guarantee safe construction and operation of
the tunnel.
4. Ground improvement: In designing a tunneling project, it may be
feasible to use prior treatment (e.g., dewatering, grouting, freezing, etc.) of
the ground in order to provide stable working conditions (Korbin and
Brekke, 1978; & Jones and Brown, 1978). Pre-treatment of the ground is a
usual measure in open-cut and shaft sinking (Flint, 1994) but much less
common in tunneling due to its high costs.
In this section, the different considerations and precautionary measures
related to face stability, ground deformation and lining analysis are enlightened.
2.5.1. Face Stability
There are two approaches to assure the face stability namely: the empirical
approach and the rational approach. The empirical approach is based on the
observations of face stability during past mining and tunneling activities. This
approach was put forward in a system of ground classifications (Terzaghi, 1950).
Conversely, the quantitative approach is based on soil mechanics and employing
the limit equilibrium methods in which the ratio of restoring force to failure-
driving force is calculated as a factor of safety. A factor of safety of magnitude
less than unity indicates instability and collapse, whereas a factor of one or more
indicates stability against inward movement. The higher the factor of safety, the
smaller the likely magnitude of inward movement and the greater the possibility
of outward movement. Thomson (1995) described the factor of safety as a “factor
of safety against inward movement” with a recommended value not less than 1.5
and not greater than 2.
Atkinson and Mair (1981) described a method of analysis for calculating
the required face support pressure (pF) to maintain stability in drained
cohesionless soil using the following equation:
46
γ′+= TpqTp cosF + the porewater pressure … (2.1)
where q is ground surface surcharge, p'co is soil effective overburden pressure at
the crown level, Tγ is tunnel face stability coefficient for soil weight and Ts is the
tunnel face stability coefficient for surface surcharge. The face stability
coefficient can be determined from Fig. (2.18). The stability of cohesive soils is
determined using undrained shear strength analysis. Peck (1969) employed the
overload factor or the stability number (Ns) that was proposed by Broms and
Bennermark (1967). The stability factor is given by:
u
Fsos C
ppN −= … (2.2)
where pso is soil total overburden pressure at the springline level and Cu is
undrained shear strength of soil. Peck established that the unit value of the
stability number or less would ensure face stability. Thomson (1995) indicated
that the safe stability number depends on the ratio of springline depth and the
tunnel diameter as shown in Fig. (2.19). The designer has to assess the undrained
shear strength based on the nature of the cohesive soil as undrained analysis
refers to the immediate condition only. If a cohesive soil has a high permeability
due to its structure then the undrained strength will eventually reduce with time
after excavation and the stability number calculated will rise.
Eisenstein and Ezzeldine (1994) conducted a total stress three-dimensional
and axisymmetric finite element analysis to study the face stability; they
concluded that the required face pressure could be given by:
( ) ( )acsoaF Kc2IpKIp −= φ …(2.3)
where Iφ is the influence factor of frictional resistance, Ic is the influence factor of
cohesive resistance and Ka is the coefficient of active earth pressure. They
compared the results of their analytic model to 23 case histories, in which good
agreements were exhibited between the model results and the observed face
stability.
47
0
1
2
0 10 20 30 40
φ' (o)
T
0
0.5
1
0 10 20 30 40
φ' (o)
Ts
Fig. (2.18) Face stability coefficients for cohesionless soil
(after Atkinson and Mair, 1981)
Crown depth/tunnel diameter
0.5
1.0
2.0 3.0
48
0
1
2
3
4
5
0 1 2 3 4 5
Ns
Fig. (2.19) Face stability number for cohesive soils
(after Thomson, 1995)
Unstable
Stable
Depth of springline/tunnel diameter
49
2.5.2. Ground Deformation
2.5.2.1. Ground Loss
Three capital roots of ground subsidence accompanying tunneling
activities are the axial ground losses in front of the tunnel, the radial ground
losses at the peripherals of the tunnel, consolidation and local instability.
Settlements occurring as a result of ground loss are controlled by the affinity of
the soil to dilate or densify when sheared. Dilation results in a small influenced
zone localized in the area above the tunnel, whereas densification is usually
coupled with movements expanding towards the surface of the soil. In undrained
cohesive soils, constant volume shearing is anticipated.
The ground losses (Vt) of tunnels in clays depend theoretically on the
stability number (Ns). Employing the cylindrical cavity contraction theory (Peck,
1969), the following equations are depicting the relation between the stability
number and the ground loss as following:
For (Ns ≥ 1)
)1Nexp(EC3
)1Nexp(C3E)1Nexp(C3V s
u
u
suu
sut −≅
−+−
=
and for (Ns ≤ 1)
u
ust E
CN3V =
…(2.4)
…(2.5)
where (Eu) is the undrained modulus of elasticity for the clay. Attewell et al.
(1986) estimated the total ground loss due to tunneling (Vt) as following:
434214434421shield behind the
gu
shield over the
ypbft VVVVVVV +++++= + time dependent consolidation …(2.6)
where (Vf) is the face loss, (Vb) is the radial loss over the shield, (Vp) is the
losses due to the upward pitch of the shield to account for the heavy nose of the
shield, (Vy) is the losses due to the curve maneuvering of the shield, (Vu) is the
radial loss over the erected lining and before grouting and (Vg) is the radial loss
over the erected lining after grouting. Consolidation in cohesive soil arises due to
50
the stress field changes during tunneling, which is generally characterized by
increasing the tangential stress and reduction of radial stresses. Long-term
seepage (if the tunnel works as an underground drain) can also cause increased
effective stresses and hence consolidation. The dissipation of pore water
pressures generated during excavation and construction can also result in
consolidation of the surrounding soil (Ghaboussi and Gioda, 1977; & Palmer and
Belshaw, 1978).
The value of ground losses is typically calculated as a percentage of the
volume of excavated material. An appropriate percentage can be estimated for
the ground, excavation and support conditions based on the literature on
tunneling. Glossop 1977) expressed empirically volume loss for stability number
ranging from (1.5-4) from his observations as:
Vt (%) = 1.33 Ns − 1.4 …(2.7)
In non-cohesive soils, contraction on disturbance could cause the surface loss to
be significantly greater than that at the TBM, while dilatation reduce the effect of
ground loss. Attewell et al. (1986) suggest a range of 3% to 10%, with a typical
value of 5% based on previous monitored projects.
2.5.2.2. The Deformation Field
There are three fundamental methods for predicting the deformation field;
namely: the empirical method that is based on normal probability curve fitting to
surface subsidence; the theoretical methods that are based on analogy between
tunneling and submerged sinks and continuum mechanics describing a new
cylindrical cavity in a prestressed medium; and the numerical methods that
employ the finite element method or the boundary element method. Schmidt
(1969) and Peck (1969) used the normal probability distribution curve for
predicting surface settlement as shown in Fig. (2.20) in which the maximum
surface settlement (Smax) occurs above the tunnel centerline. The volume of the
settlement trough (Vs) is given:
51
iS5.2iS2V maxmaxs ≅π= …(2.8)
where i is the distance between the peak and the point of inflexion of the curve.
From normal probability theory, the settlement at any point on the curve (S) at a
distance (x) from the centerline can be found using
−= 2
2
max i2xexpSS …(2.9)
For undrained deformation, the volume of settlement trough (Vs) will equal to the
ground loss volume (Vt). In non-cohesive soils, the choice of volume loss is
much more uncertain. The dilation or contraction of the soil will result in very
different volume losses at the surface. The estimation of the location of point of
inflection (i) depends upon both the depth of tunnel cover and shield diameter
(D) and the shear strength of the soil near to the surface. O'Reilly et al. (1982)
recommend the following expression
i = K z …(2.10)
where K is a constant and z is depth to tunnel center. They recommended values
of K of approximately 0.5 for cohesive soils, with typical values of
approximately 0.4 for stiff clays ranging to 0.7 for very soft clays, and 0.25 for
cohesionless soils. Schmidt (1969) proposed the following equation to estimate
(i) for clays:
i/D = 0.5 (z/D)0.8 …(2.11)
Attewell et al. (1986) conferred equations for the complete strain and
deformation fields around tunnels based on the Gauss Distribution assumption.
Atkinson et al. (1975); Butler and Hampton (1975); Cording and Hansmire
(1975); El-Nahhas (1980), (1986), (1991) and (1994); O’Reilly et al. (1982);
Clough et al. (1983); Hansmire and Cording (1985) Maidl and Hou (1990); and
Clough and Leca (1993) presented the measured deformation fields for some
tunneling projects.
52
Fig.
(2.2
0) T
he g
roun
d su
bsid
ence
Gau
ssia
n di
stib
utio
n (a
fter S
chm
idt,
1969
)
53
The theoretical methods for predicting the deformation field of tunnels
employed either the approach of submerged sinks in fluid mechanics or the
principles of continuum mechanics. The fluid flow techniques for estimation of
ground movements during tunneling use the analogy of submerged sink in an
ideal incompressible fluid. Sagaseta (1987) used this technique model
displacement field in incompressible (undrained) soil. This method has produced
good correlation with field data. The surface profile is similar to that produced by
the normal probability method but thought to better estimate the subsurface
movements, particularly those occurring close to the shield. The continuum
mechanics approach uses either the method of unloaded cylindrical cavity in an
elastic medium (Chew, 1994), or more complicated method of contracting
cylindrical cavity in an elastic-perfect plastic medium (Mair and Taylor, 1993).
The finite element provides a powerful tool to simulate the tunneling
construction. With the quick improvement in computer efficiency and
availability of very powerful codes, the finite element analysis is becoming a
versatile tool in tunneling analysis and estimation of ground subsidence (Gunn,
1993; & Loganathan and Poulos, 1998). The non-linearity of the ground and
lining can be introduced into the finite element analysis giving a good estimate of
the stress and deformation fields around tunnels (Orr et al., 1978; & Mair and
Taylor, 1993).
2.5.2.3. The Effect of the Ground Subsidence on Buildings
As the tunneling is advancing, a trough of settlement develops. Any structure
within the predominance of the developed settlement trough will be affected, and
on the other hand the presence of the structure modifies the trough. Tunneling
induced damage to buildings can be estimated roughly using the free field
displacement combined with a damage criterion. Skempton and MacDonald
(1956) presented the observational criterion of angular distortion. According to
their work, an angular distortion less than 1/300 is recommended for load bearing
54
walls and masonry-infilled panels in traditional frame building. Bjerrum (1963)
presented a relation between angular distortion and different building
performance. Grant et al. (1975) questioned Skempton-MacDonald Criterion to
assess potential damage to buildings by comparing the measured angular
distortion in about 200 case histories. Burland and Wroth (1975) presented an
analytical study in which they modeled any building as deep, elastic, simply
supported beam. They use the tensile strain as a measure of damage. Boscardin
and Cording (1989) and Broone (1997) modified the criterion of Burland and
Wroth to include the ground horizontal strain in calculation of the tensile strain.
Attewell et al. (1986) and Yoshida and Kusabuka (1994) used a method of
two-stage procedures to investigate the effect of the building existence on the
induced settlement trough. Firstly, the free surface settlement due to tunneling is
calculated using one of the analytical methods; then the final settlement can be
calculated using the following relation:
[ ] [ ]( ){ } [ ]{ }wKdKK gdsgds =+ …(2.12)
in which [Ks] presents the stiffness matrix of the structure, [Kgd] presents the
stiffness matrix of the ground interface with the building, {w} is the free field
displacement vector of the ground interface and {ds} is structure response. They
presented the ground as a Winkler medium and a half space using the finite
element method. Chen et al. (1999) employed a similar two-stage procedure to
assess the effect of tunneling on a previously installed pile. The free field
deformation was calculated using an analytical method and then applied on a pile
modeled using a combination of beam and boundary elements.
55
2.5.3. Design of Tunnel Lining
2.5.3.1. General Considerations in Lining Design
A lining is required to support the ring axial load, the circumferential
bending (and possible longitudinal bending when passing through different
strata), local buckling, shield jacking loads, asymmetrical loading at junctions
and enlargements, construction handling and erection loading, and is required to
resist corrosion. The practical and empirical rules of tunnel lining construction to
possess sufficient stability have preceded any supporting theory for many years.
The need for a scientific insight of the interaction between the tunnel lining and
the surrounding ground has arisen due to catastrophic nature of tunnel failures
and the unfamiliar nature of tunneling environment. The development of tunnel
lining design methods has lead to diminution of tunnel failures and optimization
of lining on both geotechnical and economical bases (O'Rouke, 1984).
Wittaker and Frith (1990) grouped tunnel linings into three main forms
some or all of which may be used in the construction of a tunnel: temporary
ground support, primary lining and secondary lining. In rock and stiff soil tunnels
where the ground has little stand-up time to allow the construction of the primary
lining some distance behind the face, then some form of temporary ground
support applied at the tunnel face is required e.g. rock bolts, shotcrete and steel
sets. Such support is not required in soft ground in conjunction with a shield
driven tunnel as the body of the shield provides temporary ground support itself.
A primary lining is the main structural component of the tunnel support system,
which is required to sustain the loads and deformations that the ground may
induce during the tunnel’s intended working life. Additional loads may be
imposed onto the lining during handling and erection as well as those induced as
a result of the shoving forward of the shielded tunneling machine by jacking
against the last support ring. Such loads may well exceed those imparted as a
result of ground loading in certain situations. A further function performed by the
primary lining is the control of water egress and ingress. A secondary lining
56
performs certain duties to supplement those of the primary lining, which do not
involve ground loading. Various tunnels require smooth bore profiles for their
intended use, e.g. sewer and water tunnels or aesthetic finishes for public usage,
e.g. highway and pedestrian tunnels. Erosion and corrosion protection for the
primary lining and further waterproofing may also be required, all of which are
provided by secondary linings.
The main consideration in the design of a tunnel lining is constructability
or its inter-relationship with the tunneling method to be employed to drive the
tunnel. In soft ground conditions where a shield driven tunnel is required, some
form of segmental lining will be required, either bolted or unbolted. Conversely,
if the tunnel has an appreciable stand-up time allowing dispensing of the
tunneling shield, then the use of a temporary support such as shotcrete followed
by either a poured or precast concrete primary lining may be appropriate. In
ground with good stand-up times, ribs and lagging or rock-bolting can be used as
the temporary support followed by a cast insitu primary concrete lining. Thus the
choice of lining type may well be made prior to any considerations concerning
the likely ground conditions. Finally the designer should be aware of the tunnel
usage, for example, a water transport tunnel requires a lining with good hydraulic
efficiency characteristics, thus leading to choice of a smooth bore lining.
Similarly, pedestrian and highway tunnels require aesthetic and durable finishes.
Segmental linings are usually associated with soft ground tunnels. They
are erected within the protection of a cylindrical tail shield. In these conditions
they can provide a one-pass system, furnishing both stabilization of the tunnel
opening during construction and a permanent service lining, or two-pass systems,
with the segments providing only construction stabilization, and a second-pass
poured concrete lining added for permanent service. Both types are structural
mechanisms that derive their stability wholly from the support provided by the
surrounding ground.
57
One of the very important considerations in designing a tunnel lining is if
the lining has to resist hydrostatic pressures either externally or internally then
this will in general govern the lining design and control the success of the
tunneling operation. There are various methods available to facilitate the
waterproofing of a tunnel varying from simple sealing of the longitudinal and
radial joints of the lining to the installation of a full waterproof membrane
between either the temporary and primary or primary and secondary linings. Any
water trapped behind the lining as a result of such measures is then channeled
away. The most common method is that of joint sealing which will inevitably not
achieve a completely dry tunnel but may reduce the water inflows to acceptable
levels. Bolted cast iron linings give better waterproofing than bolted concrete
linings in similar conditions. This is a result of cast iron linings lending
themselves to sealing and not suffering further cracking during handling and
construction.
The design of tunnels subjected to internal water pressures is a different
concept altogether as in many instances no leakage can be tolerated due to the
very high pressures in the tunnel and the disastrous effects that leakage may
cause to the surrounding environment. In such cases the tunnel can be made
completely impervious by the use of a steel lining backfilled with concrete. In
less severe cases where the internal pressure is reduced, measures include
increasing the rating of the rock mass by rock reinforcement thus enhancing its
resistance to internal pressure, or pressure grouting behind the concrete lining to
increase the external pressure opposing the internal pressure. Both techniques
effectively reduce the likelihood of the lining cracking and causing water loss.
Kuesel (1996) discussed the concepts that must be accounted for in
designing tunnel lining. He introduced some common characteristics that pervade
all lining systems:
58
1. The process of ground pretreatment, excavation, and ground
stabilization alter the primitive state of stress in the ground,
before the lining comes into contact with the ground.
2. The design of a tunnel lining cannot be considered as a
structure being subjected to well-defined values of loading, as
there is no absolute certainty of the actual ground behavior
following excavation. Thus, the problem should be considered
as one related to ground and structural behavior rather than
simply one governed entirely by structural features.
3. A lining cannot be loaded by ground deformations that occur
prior to its “activation”.
4. Tunnel lining behavior is a four dimensional problem.
During construction ground conditions at the tunnel heading
involve both transverse arching and longitudinal arching from
the unexcavated face. All ground properties are time
dependent particularly in the short term, which leads to the
commonly observed stand-up time phenomenon, which is
very beneficial in practical tunnel construction methods. The
timing of installation is very important variable in estimating
the loading carried by the lining.
5. In most cases (especially when considering the segmented
lining), the bending stiffness of structural linings is small
compared with its axial stiffness. Bending stiffness is
generally undesirable as it induces bending stresses in the
lining. Axial stiffness is of primary importance, as it
facilitates the redistribution of unequally distributed active
pressures and mobilizes passive pressures. The proper
criterion for judging lining behavior is therefore not adequate
59
strength to resist bending stresses, but adequate ductility to
conform to imposed deformations. However, it is essential to
perform effective contact grouting around the tunnel
periphery in order to benefit fully from the above mechanism.
This only applies to closed supports with circular and
elliptical profiles rather than to open supports such as arch
profiles without inverts or rock reinforcement techniques.
6. The most serious structural problems encountered with actual
lining behavior are related to absence of support - inadvertent
void left behind the lining- rather than to intensity and
distribution of loads.
7. Constructability considerations are likely to govern the
dimensions of the lining. The length and width of precast
concrete or metal segments are governed by shipping,
erection limitations, joint configuration, shield jacking loads
and handling stresses.
8. Grouting pressure is maximum at grouting ports and it is
reduced by friction at locations remote from the ports. Lining
design procedures usually neglect this action
2.5.3.2. Methods of Tunnel Lining Design
Methods of tunnel lining design emphasize the stage of the ground liner
interaction. Once the lining system is assembled to cover the tunnel
circumference, the lining is in position to start interacting with the surrounding
ground (the lining activation point). Stresses inside the lining and in the
surrounding ground undergo readjustments to reach the state of equilibrium. The
process of ground-liner interaction is affected by the lining and the surrounding
ground relative rigidity and stress changes during the construction stage. The
60
methods of tunnel lining design are divided into three distinct approaches,
namely: observational methods, analytical methods and numerical methods. In
the following sections, the three approaches are discussed.
2.5.3.2.1. OBSERVATIONAL LINING DESIGN
Peck (1969) and Peck et al. (1972) formulated recommendations based on
some observations of tunnel lining behavior in a variety of soil conditions. These
recommendations have become widely accepted as design criteria of flexible
circular tunnel linings. Peck concluded from his observations that flexible lining
should be designed for a uniform ring compression corresponding to the
overburden pressure at springline plus an arbitrary imposed distortion measured
as a percentage change in tunnel radius. The ring distortion can be controlled, if
necessary, by temporary internal tie rods or struts, until grouting is completed
and the ground is stabilized. He suggested considering the lining as fully flexible
ring if the following condition is satisfied
ELIL/Rm3 < 5 qu …(2.13)
where EL is the effective modulus of elasticity of the lining (reduced to half its
value in segmental lining), IL is the effective moment of inertia of lining per unit
length of the tunnel (reduced to 60-80% of the gross inertia in segmented lining)
and Rm is the mean radius of the lining. Tunnels constructed in sand, which
generally possess a higher stiffness than clays, can be considered as flexible rings
(Kuesel, 1996). The compressive stresses resulting from the assumed thrust is
given by
tRp mso=σ …(2.14)
where t is thickness of the tunnel lining. The bending stresses resulting from the
lining distortion is given by:
m
m
mL R
RR
tE5.1 ∆±=σ …(2.15)
where ∆Rm/Rm is a assumed according to the type of soil as given in Table (2.2).
61
Table (2.2) Values of tunnel distortion (after Peck, 1969)* Soil Type ∆Rm/Rm
Stiff to hard clays, stability number <2.5-3 Soft clays or silt, stability number >2.5-3 Dense or non-cohesive sand and most residual soils Loose sand
0.15-0.40 % 0.25-0.75 % 0.05-0.25 % 0.10-0.35 %
* Add 0.10-0.30 % for tunnels in compressed air. Add appropriate distortion of external effect
as passing neighbor tunnel. Values assume reasonable care in construction, excavation and
lining method.
2.5.3.2.2. Analytical Methods
In these methods, the analysis consists of representing the problem by
tractable equations based on well-established theories and empirical rules and
then solving them. No analytical solution could be found that fully satisfies all
requisites of the geometry, rock/soil behavioral laws and boundary conditions of
the problem. The use and development of analytical solutions, however, has
played an important role in the development of tunnel lining design (Iftimie,
1994). It is important to bear in mind, that analytical solutions are based on sets
of assumptions concerning all aspects of the problem, especially the ground
behavior laws, so it may be difficult to extrapolate the results directly to field
conditions. Considerable judgment may be required for meaningful application
of the results. Nevertheless, the solutions can be useful in giving additional
support to the results of more sophisticated design methods and as a means of
evaluating the sensitivity of the problem to changes in various parameters
affecting the design. This will assist in indicating the parameters that are of
primary and secondary importance.
62
2.5.3.2.3.Methods Based on Assumed Ground Pressures
These methods assume hypothetical or empirical ground pressure
distribution used to determine the internal forces and deformations of the lining.
The most important potential loads acting on tunnels are earth pressures and
water pressure. Loads due to vehicle traffic on the surface can be safely neglected
unless the tunnel is of the cut and cover type or the depth of overburden is very
small. Szechy (1967) divided the earth pressure into roof pressure, lateral
pressure and bottom pressure. Roof pressure results from the overburden soil
above the tunnel. Bottom pressure results from the bottom reaction and the heave
of the tunnel bottom due to the stress relief. Lateral pressure results from the
lining supporting action to the ground. He has pointed out that more exact
determination of lateral earthpressure must consider the passive resistance
mobilized by deformation and lateral outward displacement of the lining. This
has been accomplished in the other methods that consider the ground as either
Winkler springs or as a continuum.
The methods based on assumed ground pressures do not consider the
stress changes due to method of tunnel installation. This may explain their poor
correlation with field measurements. Water pressure can be estimated based on
the static distribution of the water pressures inside the soil mass unless the
seepage forces arise from the tunnel existence.
Terzaghi (1936) studied the soil arching using a moving trapdoor at the
bottom of a container full of compacted sands. Terzaghi noticed that the arching
is taking effect 2.5B above the trapdoor, where B is the trapdoor width). He
assumed a vertical failure surfaces and concluded that the pressure acting on the
trap-door is given by:
φ−⋅+
φ−−
φ−γ
=σ tanB
zk2expqtanB
zk2exp1tank2
)B/c2(B rr
rv
…(2.16)
63
where q is the surcharge acting on the top of the soil surface and kr is the
earthpressure coefficient, which he assumed to be unity. The vertical pressure on
the yielding door at very large depth is given by
γ=σ B87.0v …(2.17)
Terzaghi (1946) used the trapdoor results to calculate the load acting on
tunnels. He considered a rectangular tunnel as shown in Fig. (2.21). The roof
pressure is given by:
φ−⋅+
φ−−
φ−γ
=σ tanB
Hk2expqtanB
Hk2exp1tank2
)B/c2(B rr
rv
…(2.18)
The sides are treated as retaining walls where active earthpressure is assumed.
The bottom must be checked for heaving as shown in Fig. (2.22). Terzaghi also
studied the arching of deep tunnels (H>5B). He assumed that arching occurs in
5B above the tunnel and rest of the overburden can be considered as a surcharge
load acting over the failure zone as shown in Fig. (2.23).
Bierbäumer (Szechy, 1967) also introduced a similar theory wehere the
roof pressure σv is given by:
σ α γv H= …(2.19)
αφ φ
φ= −
⋅ −+ ⋅ −
1 45 22 45 2
2tan tan ( / )tan( / )
o
o
Hb m
…(2.20)
where H, B and m are shown in Fig. (2.24); α varies from 1.0 for shallow tunnels
to tan4 (45o-φ/2) for deep tunnels (H>5B). The sides are treated as retaining walls
where the total horizontal force (P) is given by active earth pressure as in
Terzaghi’s Method.
64
Peck (1969) reported that, according to records of measurements in a
number of tunnels, the magnitude of lining pressure after stress relief at the
construction stage could be as low as 20% of the overburden pressure. He
suggested it would be a safe assumption to let the magnitude of the lining load
equal to the full overburden pressure because the amount of stress relief is
unquantifiable. He stated that the lining stress tends to approach the original
overburden pressure in the long term due to soil creep. This assumption is
justified in shallow tunnels where the arching has little effect on the lining
pressure.
Fig. (2.21) Shallow tunnel model (after Szechy, 1967)
65
Fig. (2.22) Check of bottom heave (after Szechy, 1967)
Fig. (2.23) Analysis of deep tunnels (after Szechy, 1967)
66
Fig. (2.24) Bierbäumer Theory for ground arching
(after Szechy, 1967)
2.5.3.2.4. Methods Based on Subgrade Reaction Theory
Unlike the previous analysis, the methods based on subgrade reaction
theory consider the dependency of the soil pressure on lining deformation. Soil
behavior is described by Winkler's subgrade reaction coefficient. Bodrov and
Gorelik (Szechy, 1967) applied the principle of least potential energy to solution
of elastically embedded ring in Winkler medium. Whenever the section deforms
outward, elastic reactions are mobilized as shown in Fig. (2.25). The solution
procedure uses Fourier series to present the load and the reaction resulting in
very intricate mathematical formulae. An alternative procedure to Bodrov-
Gorelik method is to reduce the tedious mathematics required for solution of the
elastically restrained ring by replacing it by a polygon. Radial rods that can resist
the outward displacements but cannot resist the inward displacements provide the
ground reactions as shown in Fig. (2.26). Bougayeva and Davidov (Szechy,
1967) simplified the analysis by assuming the ground reaction. Ebaid (1978)
used Bougayeva’s Method in determining the moment in segmental lining by
considering the lining is a series of circular hinged-end frame elements. Ebaid
67
and Hammad (1978) and Hammad (1978) gave a solution for maximum moment
using this method. Hammad (1977) used a method based on subgrade reaction to
assess the stresses in U-shaped tunnels. The foremost shortcoming of the
methods based on the subgrade reaction is that they do not consider the effect of
tunnel construction procedures.
Fig. (2.25) Bodrov-Gorelik’s Method (after Szechy, 1967)
Fig. (2.26) Polygonal Method (after Szechy, 1967)
68
2.5.3.2.5. Methods Based on Convergence-Confinement Approach (CC)
The convergence-confinement approach is a procedure in which the soil-
lining interaction is analyzed by considering the behavior of each of the soil and
the liner independently using the ground reaction curve (GRC) and the support
reaction curve (SRC) to determine the equilibrium condition of the soil-lining
interaction (Ahmed, 1991).
This method enables calculation of the pressure applied to the support by
the intersection of the two characteristic curves of the lining (SRC) and the
enfolding ground (GRC) relating the radial stresses as a function of radial strain,
as shown in Fig. (2.27). The reaction curves offer a more realistic representation
of the interaction sequence of the lining with the surrounding soil. They are of
great value when used as a tool for qualitative discussions on some of the
parameters involved in the design of linings for tunnels in soil.
El-Nahhas (1980) and Ahmed (1991) gave a brief history of development
of the Convergence-Confinement Approach. It was introduced for rock tunnels
by Pacher (1964). Rabcewicz (1964, 1965) uses this approach as a design tool
for the NATM. Deere et al. (1969) discussed the use of the reaction curves for
soft ground tunnels. Lombardi (1970, 1973) examined analytically the factors
affecting the ground and support reaction curves. Kaiser (1981), Brown et al.
(1981) and Hoek (1968) presented closed form solutions for the GRC. Eisenstein
and Negro (1985) examined the nonlinear constitutive soil relations on the
ground characteristic curve and the combination of this method with finite
element analysis.
69
F
S
C
σrf
σrc
σrs
σrf
σrc
σrs σ
rs
GRCSRCRigid SRC
δrRadial Displacement
σ rR
adia
l Str
ess
Fig. (2.27) Convergence-Confinement Approach
(after Ahmed, 1991)
C
S
F
70
2.5.3.2.6. Methods Based on Continuum Mechanics
Closed-form solutions for the interaction of an elastic medium with a
buried cylinder were derived by Burns and Richard (1964) and Hoek (1986)
using extensional shell theory for the shell and Michell's formulation of Airy's
stress function for the soil medium. Although the analysis was originally
developed to study the behavior of culverts, Peck et al. (1972) and Einstein and
Schwarz (1979) used it to calculate the internal forces and deformation of a
tunnel lining of intermediate flexibility. They assumed that the case of full
slippage between the lining and the soil would approximate more nearly the
behavior of soft ground tunnel lining.
The lining stiffness is divided into two separate and distinct types. The
first is an extensional stiffness, represented by the Compressibility Ratio "C",
which is a measure of the equal all-around uniform pressure necessary to cause a
unit diametrical strain of the lining with no change in shape. The second is a
flexural stiffness, represented by the Flexibility Ratio "F", which is a measure of
the magnitude of the non-uniform pressure necessary to cause a unit diametrical
strain which results in a change in shape of the lining. The derived formulas for
these coefficients are given in the following:
m2L
L
ss
s
R)1(tE
)21)(1(E
C
ν−
ν−ν+=
…(2.21)
and
3m
2L
LL
s
s
R)1(IE6
)1(E
F
ν−
ν+=
…(2.22)
71
where Es is the modulus of deformation of the ground, υs is the Poisson’s ratio of
the ground, IL is the second moment of inertia of the liner plate and υL is the
Poisson’s ratio of the liner plate.
The variation of bending moment with the flexibility ratio, and the
variation of thrust with the compressibility ratio are given in dimensionless form
in Fig. (2.28). Generally, the plots indicate that the lining behaves as a flexible
lining if the Flexibility Ratio is greater than 10.
A similar attempt to analyze the behavior of a tunnel lining, using the Airy
stress function, is given by Morgan (1961). His analysis was based on the
assumption that the lining deforms in an elliptical mode. This analysis was
corrected and extended to more realistic conditions by Muir Wood (1975). Curtis
et al. (1976); & Curtis and Rock (1977) studied the effect of shear stresses on the
radial deformation of the soil. They gave formulae for the thrust and bending
moments in the lining for cases of no shear interaction and full shear interaction
between the lining and the surrounding soil as it was described before.
The methods based on continuum mechanics have introduced a few
factors, which were overlooked by some of the preceding methods. The
assumptions of continuum mechanics analyses however, limit their use to deep
tunnels in a homogeneous, isotropic, elastic ground. The derivation of similar
formulas for different boundary conditions, different construction techniques and
considering nonlinear constitutive soil behavior would be tedious and
formidable.
72
Fig.
(2.2
8) M
omen
t and
thru
st c
oeff
icie
nts (
afte
r Bur
ns e
t al.,
196
4)
73
2.5.3.2.7. Numerical Methods
The assumptions made in formulating analytical solutions are generally
too simple to allow it to retain a degree of relationship to the problem in
question. Moreover, the inclusion of the method of construction of the tunnel and
soil nonlinearity in the analytical solution is practically unfeasible. The
development of faster, cheaper computers and improved knowledge concerning
the behavior of soils and modeling construction stages, have soared the design
techniques that are based on numerical simulation. Several numerical models
employing two-dimensional plane strain or axisymmetric models have been
reported (Ranken and Ghaboussi, 1975; Ghaboussi and Gioda, 1977; Orr et al.,
1978; Ghaboussi et al, 1983; Rowe et al, 1983; Hamdy, 1989; Ahmed, 1991,
Adashi et al., 1991; Gunn, 1993; Mair and Taylor, 1993; Ahmed, 1994; Yoshida
and Kusabuka, 1994; Esmail, 1997; Abdrabbo et al., 1998 and Chen et al., 1999)
Little literature is available in which tunneling is presented using three-
dimensional numerical models. Complications in presenting soil excavation,
shield driving, overcutting and tailskin grouting obstacles this type of analysis in
addition to its high computational cost especially when employing the nonlinear
soil models (Smith and Griffiths, 1998). Nomoto et al. (1999) considered the
centrifugal testing as a three-dimensional model that is superior to numerical
ones. Recently, some research work was directed towards to three-dimensional
numerical analysis (Ezzeldine, 1995; Mansour, 1996; Augrade, 1997, Abu-
Krisha, 1998 and Shou, 2000). Newly developed models based on probabilistic
models and soft computing have been recently utilized (Touran et al., 1997 and
Shi et al., 1998).
74
2.6. Tunneling Projects in Egypt
During the last two decades, several tunneling projects have been
executed in Egypt including sewage tunnels, syphons, subways and road tunnels.
Fig. (2.29) shows the location of some of the Egyptian tunneling projects. El-
Nahhas (1999) and The International Tunneling Authority (ITA) web site1
surveyed many of these projects. The following tunneling projects have been
reported:
• Cairo Wastewater Project: The project comprises the construction
a spinal deep collecting tunnel from Maadi in the South to Ameria
in the North as shown in Fig. (2.30). The construction of the main
part of the spine tunnel was accomplished using five-meter
compressed air TBM. Work on the main tunnels of Cairo
wastewater project (Contract 15) has been completed in 1997. The
Maadi rock tunnel commenced using a 5.35 m Herrenknecht TBM
with hard rock cutter head in which approximately 100 m had been
driven by the end of march 2000. Design work for the connecting
tunnels required to discharge sewage flows to the Maadi Rock
tunnel section of the main spine sewer is under preparation.
• Greater Cairo Metro: The first line of the Greater Cairo Metro or
the regional line was completed in 1989 and was the first subway
metro line in Africa and the Middle East. The second line was
completed recently using bentonite slurry technology. The second
line extends from Shubra El-Kheima to Giza Suburban areas.
Details of the second line project are elucidated in Chapter (4). The
third line is planned to extend about 7 km from Embaba to El
Darasah.
1 www.ita-aites.org
75
• Al-Azhar Road Tunnels: Work on the first of Al-Azhar Twin Road
tunnels below the old Islamic heart of Cairo has been completed.
The second tunnel is anticipated to be completed by year 2001.
Each tunnel will be about 2.6 km long in which 1.8 km are bored
using bentonite slurry TBM and the remaining being the cut-and-
cover entrances and exits. The subsurface works of the two
ventilation shafts and the installation of the electromechanical plant
have been completed. Chapter (5) provides an analysis for the
intersection of Al-Azhar tunnels with the Cairo Wastewater spinal
tunnel.
• Suez Canal Road Tunnels: The only road tunnel connecting Sinai
with the east coast of the Suez Canal, Ahmed Hamdy Tunnel, was
finished in 1983 using open-face tunneling. The deteriorating lining
of this tunnel was covered during rehabilitation with a new cast-in-
place reinforced concrete lining, 450 mm thick (Otsuka and Kamel,
1994 & Ahmed, 2000) as shown in Fig. (2.31). The Authority for
Tunnels has received proposals for the construction of a road
tunnel, on a BOT basis, below the Suez Canal, 20 km south of Port
Said from 2 consortia, one Egyptian and one French. The tunnel
will carry traffic to the proposed harbor and industrial development
planned on the east side of the Canal as well as forming part of the
international coastal highway.
• El-Salam Syphon: This project was intended to transport the Nile
water below Suez Canal to Sinai for land reclamation using four
parallel tunnels. Each tunnel is about 750 m long. Chapter (5)
includes a description of this project.
• Alexandria Wastewater Project: The central main collector of the
proposed network was constructed under central Alexandria,
76
starting from the Mediterranean coast and advancing southwards
using EPB TBMs of about 2.25 m diameter.
Fig. (2.29) Egyptian tunneling projects (after El-Nahhas, 1999)
77
Fig. (2.30) Cairo tunneling projects (after El-Nahhas, 1999)
78
Fig. (2.31) Rehabilitation of Ahmed Hamdy Tunnel
(after Otsuka and Kamel, 1994)
79
Chapter Three
TUNNELING IDEALIZATION
3.1. Introduction Tunneling is an intricate nonlinear time-dependent three-dimensional
process. The comprehensive features in tunneling simulation that should be
included in the requisite modeling are illustrated in Fig. (3.1) and summarized as
following:
• The nonlinear soil constitutive behavior, which depends mainly on the
stress path, confining pressure and rate of loading;
• The unloading forces developed during ground excavation and the
potential seepage towards or away from the tunnel;
• The radial and axial ground loss and the overcutting gap;
• The pressurized excavation boundaries and ground support measures;
• The effect of the potential marginal yield zones around the tunnel;
• The tailskin grouting and the hardening of grouting material with time;
• TBM advancement and lining installation;
• The mutual interaction between the excavated tunnel and the surrounding
underground pre-erected pipelines and tunnels.
In view of the preceding modeling features, we cannot regard the
observational rules, which are commonly used to describe the tunneling
deformation fields and lining stresses, as reliable bases for tunneling analysis
even under the same ground conditions (which is very unlikely as well), as the
different installation procedures and various modeling features are not
deliberated in these rules. Tunneling researches frequently employed two-
dimensional models to simulate tunneling installations and different phases of
80
ground-lining interaction. The displacement field is approximated in plain strain
models by neglecting the non-radial deformations while the stress and
displacement field is approximated into symmetric fields in axisymmetric
models. Although two-dimensional numerical models are superior to the rules-
of-thumb, the oversimplifications in the analysis in two-dimensional models
materialize a justifiable source of uncertainty in employing the obtained results in
design and analysis. Little literature is available in which soft ground tunneling is
idealized using three-dimensional models due to the required high computational
cost especially when employing the nonlinear soil models.
In the present research, a nonlinear three-dimensional model is developed
to present a genuine simulation of the induced displacement fields. The soil,
shield and liner are modeled using eight-node hexahedral isoparametric finite
elements. Soils constitutive behavior is presented by employing hyperbolic
nonlinear model having a variable modulii according to confining pressure and
stress path.
The shield-soil interface is modeled using a hyperbolic gap element. The
liner-grout-soil interface is modeled by introducing grout elements with
incremental strength parameters; time hardening characteristics; and initial
hydrostatic pressure equal to the grouting pressure. Fig. (3.2) illustrates the
proposed arrangement of the interface modeling. The tunnel heading and face
pressure is introduced to examine the face stability and effect of the face losses
on the deformation field.
The excavation of ground, the liner activation and the liner-ground
interaction are considered in a special incremental pseudo-time iterative
technique. In this chapter, the numerical aspects of proposed tunneling
simulation are established. The techniques to simulate the complex nonlinear
shield–lining–soil interaction and the construction technique of the pressurized
shielded tunneling are demonstrated.
81
Fig.
(3.1
) Mod
elin
g fe
atur
es o
f sof
t gro
und
shie
lded
tunn
elin
g
Ove
rcut
Segm
enta
l lin
ing
TBM
Pressurized face
Inst
alla
tion
Shaf
t
Prob
able
def
orm
atio
n fie
ld
Soft
pres
suriz
ed
grou
t H
ard
grou
t
Exca
vatio
n
Tails
kin
grou
ting
and
linin
g in
stal
latio
n
& T
BM
ad
vanc
emen
t
Con
verg
ent
grou
nd
Muc
king
di
spos
al
Und
ergr
ound
St
ruct
ures
Y
ield
ed z
one
Ove
rcut
Segm
enta
l lin
ing
TBM
Pressurized face
Inst
alla
tion
Shaf
t
Prob
able
def
orm
atio
n fie
ld
Soft
pres
suriz
ed
grou
t H
ard
grou
t
Exca
vatio
n
Tails
kin
grou
ting
and
linin
g in
stal
latio
n
& T
BM
ad
vanc
emen
t
Con
verg
ent
grou
nd
Face
los
ses a
nd
pote
ntia
l see
page
Muc
king
di
spos
al
Und
ergr
ound
St
ruct
ures
Y
ield
ed z
one
82
Fig. (3.2) Interface modeling
Overcut
Hexahedra shield elements
Gap elements
Hexahedra soil elements
(a) Shield-soil interface modeling
Hexahedral liner elements
Hexahedral soil elements
Hexahedral grouting elements (initially
under hydrostatic grouting pressure)
(b) Liner-grouting-soil interface modeling
Tail gap
Shield/Liner
Enfolding ground
83
3.2. Finite Element Formulation Finite element (FE) procedures are employed because of their great
capability to deal with the nonlinear geotechnical problems (ETL 1110-2-544,
1995). The FE uses interpolation basis functions or shape functions [Ne], which
are spatial polynomials relating the generic displacement vector {ue} at any point
in a sub-domain or element to the nodal displacement vector {Ue} of the element
(Zienkiewics, 1977) as following:
{ue} = [Ne] {Ue} …(3.1)
The same shape functions are used to relate the coordinates of any point inside
the element {xe} to the coordinate of the nodal points {Xe}, i.e.
{xe} = [Ne] {Xe} …(3.2)
The eight-node hexahedral tri-linear element is used to model soil, lining
and grouting. Axelsson and Baker (1984) pointed out that the usage of linear
elements is advantageous in dense meshes (h-refined meshes) other than higher
order elements in coarse meshes (p-refined meshes) because of their small
spectral number. The shape functions of used element are formulated in the
natural system of coordinates {ξ} as shown in Fig. (3.3) by the following indicial
expression (Pullan, 1998):
Ni = (1+ξi ξ)(1+ηi η)(1+ζi ζ)/8 …(3.3)
The relations between the generic displacement vector {ue} and the strain
vector {εe} is defined using a an operator [Ae] as
{εe} = [Ae] {ue} …(3.4)
in which [Ae] is given by:
84
[ ]
∂∂
∂∂
∂∂
∂∂
∂∂
∂∂
∂∂
∂∂
∂∂
=
x0
z
yz0
0xy
z00
0y
0
00x
Ae
…(3.5)
The relation between the nodal displacement and the strain can be written as:
{εe} = [Be] {Ue} …(3.6)
where
[Be] = [Ae] [Ne] …(3.7)
The constitutive matrix [De] describes the relation between the stress and
the strain as following:
{σe} = [De] {εe} …(3.8)
so
{σe} = [Be][De]{Ue} …(3.9)
Applying the principle of virtual work
{ } { } { } { } { } { } { } { }eT
eS
eT
eV
eT
eV
eT
e PUdStudVudVeee
+δ+γδ=σδε ∫∫∫ …(3.10)
85
where { } { } { }eee Uandu, δδδε are a compatible set of virtual strains, displacements
and nodal displacements; {γe} is the body force vector (usually the gravitational
forces) applied to volume of element Ve ; {te} is the surface traction vector along
the boundary of the element Se and {Pe} is the nodal force vector
Replacing { }eδε by [Be]{δUe} and {δue} by [Ne]{δUe} we get another
version of the virtual work equation with no required virtual displacement field:
[ ] { } [ ] { } [ ] { } { }eS
eT
eV
eT
eV
eT
e PdStNdVNdVBeee
++γ=σ ∫∫∫ …(3.11)
Substitute for {σe} by [Be] {Ue} we get
[ ] [ ][ ] { } [ ] { } [ ] { } { }eS
eT
eV
eT
eeV
eeT
e PdStNdVNUdVBDBeee
++γ= ∫∫∫ …(3.12)
or
[Ke] {Ue} = {Fe} …(3.13)
where
[Ke] The element stiffness matrix = [ ] [ ] [ ]∫eV
eeT
e dVBDB …(3.14)
and
{Fe} The element load vector = { } [ ] { } [ ] { }∫∫ +γ+ee S
eT
eV
eT
ee dStNdVNP …(3.15)
In order to form the [Be] matrix, the derivatives of the shape functions are
required with respect to the global spatial coordinates. For any shape function Nk,
the derivative with respect to {x} can be calculated using the chain rule as
following:
{ } [ ] { }ξ∂∂
=∂∂ − k1k NJ
xN …(3.16)
86
where
[J] is the Jacobian matrix = }{}x{
ξ∂∂ = [ ] { }( )ee XN
}{ξ∂∂ …(3.17)
The stiffness matrix is written as:
[ ] [ ] [ ] [ ]∫=mapV
mapeeT
ee dV)Jdet(BDB]K[ …(3.18)
Where Vmap is the volume of the parent (mapped) element in the natural
coordinates’ space {ξ}. A similar expression can be used to evaluate the body
forces, i.e.
[ ] { } [ ] { }∫∫ γ=γmape V
mapeT
eV
eT
e dV])Jdet([NdVN …(3.19)
Numerical integration technique is used to evaluate the element matrices.
The element matrices are then assembled to form the system matrix. The nodal
forces resulting from inter-element tractions are canceling each other. Surface
tractions contribute to the load vector in case of external boundaries only. When
summed, element nodal point loads are grouped into external nodal forces.
87
Fig. (3.3) Natural axes of hexahedral parent element
1 2
3 4
5 6
7 8
ξ
η
ζ
88
3.3. The Constitutive Model The nonlinear finite element Method is characterized by the dependence
of the stiffness coefficients on the state of stress and the stress path. The foremost
source of nonlinearity is the material constitutive relations because they are
highly dependent on the state of stress. There are many models to account for the
material nonlinearity. The stress-strain relationship of soil should be expressed in
incremental form to account for the path-dependency. Using the incremental
form of the constitutive matrix [Det], the element stiffness matrix [Ket] can be
rewritten as:
[ ] [ ] [ ][ ]∫=eV
eett
eet dVBDBK …(3.20)
Duncan and Chang (1970) proposed the hyperbolic model and used it in
analyzing embankment deformation. The parameters of the model can be
determined from conventional triaxial test results. Because of its simplicity, this
model has been used in many other geotechnical applications (Chan, 1989;
Ahmed, 1991; Abdel-Rahman, 1993; Esmail, 1997; and Duncan, 1996). A
typical triaxial compression test yields the results shown in Fig. (3.4). The
deviator stress and axial strain relationship can be approximated by a hyperbola
passing through the origin and has an asymptotic value of (σ1 - σ3)ult and initial
tangent (E0) as shown in Fig. (3.5).The equation of the hyperbola is:
( )
( )ult310
31
E1
σ−σε
+
ε=σ−σ
…(3.21)
To determine the values of E0 and (σ1 - σ3)ult from the conventional
triaxial test results, the previous equation can be rewritten a linear form:
89
( ) ( )ult31031 E1
σ−σε
+=σ−σ
ε …(3.22)
Taking ε as the abscissa and ( )31 σ−σε as the ordinate, the parameters used to
describe the hyperbola can be determined as shown in Fig. (3.6). The value of
(σ1-σ3)ult , which is reached only at strain equal to infinity, is always greater than
the actual deviator stress at failure (σ1 - σ3)f , so a ratio called the Failure Ratio
(Rf) is introduced to related the ultimate and actual failure stresses, Rf is defined
as:
( )( )ult31
f31fR
σ−σσ−σ
= …(3.23)
Hence, the stress-strain relation is given by:
( )
( )f31
f
0
31 RE1
σ−σε⋅
+
ε=σ−σ
…(3.24)
The value of (σ1 - σ3)f can be determined from the Mohr-Coulomb failure
criterion as shown in Fig. (3.7) and as given by the following equation:
( )φ−
φσ+φ=σ−σ
sin1sin2cosC2 3
f31 …(3.25)
Substituting in the hyperbola equation
( ) ( )φσ+φ
φ−⋅ε⋅+
ε=σ−σ
sin2cosC2sin1R
E1
3
f
0
31
…(3.26)
The above equation can be rewritten as:
90
( )( ) ( )
φσ+φ
φ−⋅σ−σ⋅−
σ−σ=ε
sin2cosC2sin1R1E
3
31f0
31
…(3.27)
Nonlinear analysis should be performed in increments, so it is necessary to
determine the incremental stiffness of the material. In the hyperbolic model, the
tangent modulus can be determined by differentiating the stress strain curve of
the material at constant confining stress σ3 as:
( )( ) 2
3
31f0
31
31t sin2cosC2
sin1R1E
)(dd1
d)(dE
φσ+φφ−σ−σ
−=
σ−σε
=ε
σ−σ=
…(3.28)
Janbu (1963) suggested that the initial tangent modulus is dependent of
the confining pressure (σ3). He proposed the following relation:
n
a
3a0 p
KpE
σ=
…(3.29)
where pa is the atmospheric pressure = 1 bar = 10.3 t/m2, K is the modulus
number (dimensionless) and n is the exponent number (dimensionless). Janbu’s
equation suggests that the initial modulus increases with the confining pressure
(σ3) according to a power law relationship. The confining pressure (σ3) increases
with soil depth. Stiffness of most soils cannot increase indefinitely with increase
in depth. A value of n less than one implies that the effect of σ3 on the rate of
increase of the initial modulus is diminishing with increasing depth. Value of n
greater than one has been reported in soft soils, however this can result in
unrealistically high modulus at great depth. The modulus number and the
exponent number can be determined from triaxial test results by taking the
logarithm of both sides of previous equation resulting as following:
91
( )
σ+=
a
3
a
0
plognKlog
pElog
…(3.30)
Value of (log (K)) can be determined from the intercept of the straight line at σ3
= Pa and n can be determined from the slope as shown in Fig. (3.8). Substituting
for E0 in Et
( )( ) n
a
3
2
3
31fat psin2cosC2
sin1R1KpE
σ
φσ+φφ−σ−σ
−= …(3.31)
It should be noted that, if tension exists in the soil, the minor principal stress (σ3)
will become negative and the tangent modulus can not be evaluated if (σ3) is less
than zero, so a very small value of E is assumed in tension zones.
A constant Poisson’s ratio may be assumed in the hyperbolic model.
Duncan et al. (1980) presented a hyperbolic relationship for the axial strain in
relation to the radial strain under triaxial test condition. They proposed the
following formula for Poisson’s ratio
2a
3
rt )A1(
plogFG
dd
−
σ⋅−
=εε
−=ν
…(3.32)
under the constraint
5.00 t <ν≤ …(3.33)
where
92
( )( ) n
a
3
3
31fa
31
psin2cosC2sin1R1Kp
d)(A
σ
φσ+φφ−σ−σ
−
σ−σ=
…(3.34)
and εr is the radial strain; G, F and d are material parameters than be determined
from Fig. (3.9)
Unloading is modeled by specifying a different modulus, which results in
non-zero strains when returning to the initial state of stress of the material, as
shown in Fig. (3.10). The modulus Eur is used during the unloading-reloading
cycle. Eur is given by:
n
a
3aurur p
pKE
σ=
…(3.35)
where Kur is the number of unloading modulus and may be assumed from twice
to three times the loading modulus number (K). During the finite element
analysis, it is not possible to determine the region, which is subjected to loading
or unloading in advance in order to decide whether the loading modulus or
unloading modulus should be used during the first iteration. Since the loading
modulus is normally lower than the unloading modulus, the use of the loading
modulus can lead to numerical divergence when unloading occurs. Using the
unloading-reloading modulus during the first iteration of every loading step will
underestimate the displacement in the first iteration if loading occurs. The correct
loading or unloading modulus will be used in subsequent iterations according to
a parameter defined by Duncan et al. (1984). This parameter is called the loading
level (LL) and defined as:
4
a
3
3
31
psincosC)(LL
σ⋅
φσ+φσ−σ
= …(3.36)
LL is calculated for each Gauss point and compared to the maximum value
93
reached during the loading history at the same Gauss point (LLmax). Three
different cases may arise, namely:
1. If ( maxLLLL ≥ ) then loading is taking place and the used modulus E’=Et
2. If ( maxLL75.0LL ≤ ) then unloading is taking place and used modulus E’=Eur
3. If ( maxmax LL75.0LLLL >> ) then neutral loading is taking place and the used
modulus E is given by interpolation as shown in Fig. (3.11)
After determining the appropriate value of (E´) and (υt) the constitutive
matrix [Det] can be formed as:
[ ]
ν−
ν−
ν−ν−νν
νν−νννν−
ν−ν+′
=
2)21(00000
02
)21(0000
002
)21(000
000)1(000)1(000)1(
)21)(1(ED
t
t
t
ttt
ttt
ttt
ttet
…(3.37)
The resulting constitutive matrix [De] is symmetric; therefore, the element
elastoplastic stiffness matrix is symmetric too. The previous property is a major
advantage of this model especially in three-dimensional analysis as the resulting
system stiffness matrix may be placed in a symmetric half-banded storage.
94
Fig. (3.4) Typical triaxial results
Intermediate σ3
High σ3
Low σ3
ε
σ1 − σ3
Low σ3
Intermediate σ3
High σ3
ε
εv = ε + 2εr
95
Fig. (3.5) Hyperbolic Stress Strain Curve (after Duncan and Chang, 1970)
Fig. (3.6) Determination of Hyperbolic Model
parameters (after Duncan and Chang, 1970)
σ1−σ3
(σ1−σ3)ult
ε 1
Ε0
31 σ−σε
ε
ult31 )(1σ−σ
1
1/Eo
96
Fig. (3.7) Mohr-Coulomb yield criterion
Fig. (3.8) Determination of the modulus number and
exponent number (after Duncan and Chang, 1970)
σ
τ
φ
σ3 σ1
C
σ
a
3
plog
a
i
pElog
Log (pa)
Log(K) 1
n
97
Fig. (3.9) Determination of F and G (after Duncan et al., 1980)
Fig. (3.10) Determination of the unloading modulus Eur
(after Duncan et al., 1984)
ε
σ1−σ3
1
n
a
3aurur p
pKE
σ=
G
σ
a
3
plog
Log (pa)
vt (1-A2)
1
F
98
Fig. (3.11) Effect of stress path on the soil modulii (after Duncan et al., 1984)
LLmax 0.75 LLmax
Et
Eur
LL
E
99
3.4. Interface Formulation In order to obtain a good estimate of the deformability of different
continua at their interfaces, interface finite elements are inserted between the
nodes of the different material boundaries to account for the potential relative
movements between their boundaries. Cook et al. (1989) illustrates the concept
of gap element using the one-dimensional module shown in Fig. (3.12). The gap
element has a stiffness discontinuity between the tension fictitious stiffness (s)
and the compression substantial stiffness (s+S). Cook pointed out that the force
increment must be small enough to grasp the point of gap closure.
The spring type hyperbolic interface element used by Dessouki (1985),
gave a consistent representation of the state of normal and shearing stresses
between the soil media and the structural elements. It has only two nodes as
shown in Fig. (3.13), which are initially separated by a gap when no stresses exist
between the two materials. The element local stiffness matrix [k’e] is based on
two uncoupled stiffness coefficients (kn) for formal force and (kt) for shear force.
[ ]
−−
−−
−−
=′
tt
tt
nn
tt
tt
nn
e
k00k000k00k000k00kk00k000k00k000k00k
k
…(3.38)
The shear stiffness (kt) increases with an increase in the normal stress and
decreases with increasing the shear stress (Duncan et al., 1998). Its variation is
nonlinear as shown in Fig. (3.14). This nonlinear shear stress-shear displacement
relationship can be given in a hyperbolic form as:
ultti
ixy vk1
vA
τ′
+
′=τ
…(3.39)
100
where v' is the displacement along local y’ axis, Kti is the initial shear stiffness,
τult is asymptotic value of shear stress and Ai is the area between adjacent
interfaces. Similarly
ultti
ixz wk1
wA
τ′
+
′=τ
…(3.40)
Where w' is the displacement along local z’ axis. The initial shear stiffness (ksi)
is related to the normal stress at the interface by Janbu power relation:
p
a
niwiti p
Akk
σγ=
…(3.41)
where ki is a dimensionless stiffness number, γw is the unit weight of water, σn is
the normal stress at the interface and p is the shear stiffness exponent. The
ultimate shear stress (τult) is related the failure shear stress (τf) by the relation:
ultfsf R τ=τ …(3.42)
The relation relates the failure shear stress to the normal stress at the interface is:
δσ=τ tannf …(3.43)
The tangential shear stiffness (kt) is obtained by differentiating τ w.r.t. v’, hence:
p
a
n
2
n
sfiwit ptan
R1Akk
σ
δσ
τ−γ=
…(3.44)
The relation between global stiffness matrix [Ke] and local stiffness matrix [K’e]
101
is given by:
[ ] [ ] [ ][ ]TKTK et
e ′= …(3.45)
The transformation matrix [T] is given by:
[ ]
=
333
222
111
333
222
111
nml000nml000nml000000nml000nml000nml
T …(3.46)
where (l1, m1, n1), (l2, m2, n2) and (l3, m3, n3) are the direction cosines for the
local axes x’, y’ and z’ respectively (Weaver and Johnston, 1984).
The grouting is introduced behind the TBM by applying a hydrostatic
pressure equal to the grouting pressure. The force vector {Fgrouting} due to
applying this initial grouting pressure is estimated by the following equations.
{ } [ ] { }∑ ∫ σ−=elementsgrouting V
eT
egrouting
e
dVBF …(3.47)
The stiffness of the grouting element undergoes time hardening. Adopting a
hyperbolic relation, the uniaxial strength (f) of the grouting is given by:
c50
ftt
tf ′+
= …(3.48)
where (fc’) is the cylinder strength after 28 days, (t) is the time and (t50) is the
time at which the cylinder strength is half the value of (fc’). Assuming the rate
and the advance distance of the TBM is (R) and (D) respectively, then the
previous equation may be rewritten in the following form:
c50
fR/Dt
R/Df ′+
= …(3.49)
102
Fig. (3.12) Gap modeling (after Cook et al., 1989)
g
s
S
δ
f
f
δ s 1
S + s
1
g
103
Fig. (3.13) Three-dimensional interface element local and global axes
Fig. (3.14) Stress-deformation curves for hyperbolic interface element
(after Dessouki, 1985)
x
y
z
x' y'
z' g
w
v
u
w'
u'
v'
τ A
i
v' or w'
τult Ai
1
kti
kt 1
104
3.5. Nonlinear Solution Techniques Chan (1996) discussed the formulation and solution techniques for nonlinear
finite elements. They classified the used techniques into three categories; namely:
the iterative methods; the incremental or step-wise methods; and the mixed or
step-iterative methods. Iterative methods are not usually used in solution of
elastoplastic systems for the following reasons:
1. The material constitutive relations are usually described incrementally,
which imposes the use of incremental and mixed methods
2. The nonlinear systems are path-dependent and iterations alone may be
misleading in determining the loading and the unloading localities in the
system.
3. The loading is usually given in an incremental form.
In the following sections, the nonlinear formulation techniques of the finite
element are reviewed with emphasis on the methods implemented in the model.
3.5.1. Incremental Techniques
After we assemble the element matrices into system matrices we can get
the following equation:
[ ]{ } { }FUK t&& = …(3.50)
where:
[Kt] is the system tangential matrix = [ ]∑=
elementsof.No
1eetK …(3.51)
and
{ }F& is the increment load vector = { }∑=
elementsof.No
1eeF& …(3.52)
Equation (3.50) may be rewritten in the following form
{ }{ } [ ]tKUF
=∂∂ …(3.53)
105
To solve the previous differential equation, we can use the following techniques:
1. Euler Integration Scheme: In this method, the relation between the load
increment }F{& and the displacement increment }U{ & is approximated by:
[ ] { } { }FUK ttEuler
ttt
t && ∆+∆+= …(3.54)
Where left superscript denotes a pseudo time used to describe the load and
displacement increments. The time (t) indicates the beginning of the step
and time (t+∆t) indicates the end of the increment. The displacement
increments are obtained using the previous equation and the total
displacement is given by:
{ } { } { }Eulerttttt UUU &∆+∆+ +≅ …(3.55)
The stiffness matrix is evaluated at the end of the previous step, which
may lead to a gross error as shown in Fig. (3.15).
2.Modified Euler Integration Scheme: To increase the accuracy, the
Modified-Euler scheme may be used. In this method, the solution is
carried out for the half increment of load so we can get
[ ] { } { }F5.0UK tt2/ttt && ∆+∆+⋅= …(3.56)
Using the above equation, we can get { }U2/tt &∆+ and hence we can calculate
[ ]K2/tt ∆+ . The displacement increment { }Utt &∆+ is obtained using:
[ ] { } { }FUK tttt2/tt && ∆+∆+∆+ = …(3.57)
106
A comparison between the integration schemas is shown in Fig. (3.15),
which reveals increasing of accuracy by using Modified Euler integration
scheme.
Fig. (3.15) Application of incremental methods in nonlinear finite element
(after Owen and Hinton, 1980)
Euler.Mtt U&∆+
Eulertt U&∆+
F
U
t+∆tF
tF Ftt &∆+
tU tUEuler tUM.Euler
1 tKt
1 t+∆t/2Kt
1
t+∆t/2Kt
107
3.5.2. Mixed Techniques
These techniques employ the initial stress method that was described by
Zienkiewics (1977). The equilibrium equations are casted in residual forms using
either tangent stiffness or constant stiffness matrices during each increment. Two
main types have been used by most of the finite element codes namely:
1.The Incremental Iterative Newton-Raphson Method (NR): In this
method, the load vector is the residual vector resulting from the difference
between the applied force and the resisting straining forces. The stiffness
matrix and the residual vector are calculated at the beginning of each
iteration. The i+1 iteration is described by the following equation:
[ ] { } { }RUK tt1i
tt1i
itt ∆++
∆+
+∆+ =& …(3.58)
where
{ } { } [ ] { }∑ ∫=
∆+∆+∆++ σ−==
elements of No.
1e Ve
tti
Te
tttt1i
e
dVBFVector ResidualR …(3.59)
and
{ } { } { }UUU tt1i
tti
tt1i
&∆+
+∆+∆+
+ += …(3.60)
The left subscript denotes the iteration process. If the iteration superscript
is zero that means the matrix or vector is calculated at the end of the
previous time step. Fig. (3.16) shows the application of this method on a
single degree of freedom.
2.The Incremental Iterative Modified Newton-Raphson Method (MNR):
The residual vector is updated at the beginning of each iteration. A
constant stiffness matrix (usually elastic) is used. The i+1 iteration is
described by the following equation:
108
[ ] { } { }RUK tt1i
tt1i
0 ∆++
∆+
+ =& …(3.61)
The MNR method is shown diagrammatically for a single degree of
freedom in Fig. (3.17).
Due to inclusion of special interface element that has a high sensitivity to
displacement state along the interfaces, the NR was preferred to be used in the
code. Open gap elements were excluded from contribution to the residual vector.
The tensile stiffness was not set to trivial values to allow monotonic gradual
closure of the gap other than an unstable convergence that may result in
undesired changes in the stress path (Duncan et al., 1998)
Fig. (3.16) Incremental Iterative Newton-Raphson Method
(after Owen and Hinton, 1980)
Rtt2
∆+ Ftt ∆+
Ft
RF tt1
tt ∆+∆+ =&
[ ] { }∑ ∫=
∆+ σelements of No.
1e Ve
tti
Te
e
dVB
UU tt0
t ∆+= Utt1
∆+ Utt2
∆+ U
F
Utt1&∆+
1
KK tt0
t ∆+=
1
Ktt1
∆+
Utt2&∆+
109
Fig. (3.17) Incremental Iterative Modified Newton-Raphson Method
(after Owen and Hinton, 1980)
Rtt3
∆+
[ ] { }∑ ∫=
∆+ σelements of No.
1e Ve
tti
Te
e
dVB
K0
Rtt2
∆+
Ftt ∆+
Ft
RF tt1
tt ∆+∆+ =&
UU tt0
t ∆+= Utt1
∆+ Utt2
∆+ U
F
Utt1&∆+
1
Utt2&∆+
K0 1
110
3.5.3. Convergence Criteria
NR and MNR methods seek an approximate solution to the problem,
therefore there is always some error associated with the solution. It is important
that this error is not too large to ensure that the solution obtained represents a
realistic solution to the problem. On the other hand, increased accuracy of the
solution requires more computer time and increases the time and cost of the
analysis. Consequently a measure of convergence is required to optimize the use
of computer resource and to terminate the calculation at the appropriate time.
Such measure will also give the convergence characteristics of the problem if the
solution becomes unstable and diverge. There are two basic methods to measure
the convergence characteristic for the displacement finite element method;
namely:
1. Displacement Criterion: The displacement criterion uses nodal
displacements as the basic measure of the convergence characteristic.
Since there are many nodal points in a finite element mesh, the
displacement norm is used instead of the displacement at a particular
node. The Euclidean norm of a vector {U} is defined as:
{ }U Uii
n
==∑ 2
1
…(3.62)
Therefore convergence is defined as:
{ }{ } utt
i
tti
U
Uε≤
∆+
∆+ &
…(3.63)
Where ε u is the displacement tolerance.
2. Force Criterion: The force criterion uses the residual vector norm as
the basic measure of the convergence characteristic. The force
convergence is defined as:
111
{ }{ } Ftt
0
tt1i
R
Rε≤
∆+
∆++
…(3.64)
Where Fε is the force tolerance.
The choice of the convergence criteria and tolerance is largely dependent
on the problem being analyzed. The displacement criterion is adopted in this
thesis because of the existence of interface elements in the analysis. Interfaces
with significant compression stiffness coefficients extremely magnify the
residuals. The displacement criterion may be considered as more “stable”
criterion in this case as it exhibits a unified trend of convergence.
3.5.4. Calculation of Stresses from Strains
The calculation of stresses is not only required as an output quantity but
also affects the solution in the next iterations and increments as the constitutive
relations is a function of the calculated stress. Therefore the stresses must be
calculated as accurate as possible. The incremental strain vector at each Gauss
point can be calculated from:
{ } [ ] { }ett1iee
tt1i UB &&
∆+
+∆++ =ε …(3.65)
The tangential constitutive matrix is given by:
{ }{ } [ ]et
e
e D=ε∂σ∂ …(3.66)
hence, the stress increment can be calculated from the following integration
(Chan, 1989):
112
{ } { } { } { } [ ] { }{ }
{ }
∫ε
ε
∆+∆++
∆+∆++
∆++
∆+
ε+σ=σ+σ=σtt1i
tti
dDettti
tt1i
tti
tt1i &
…(3.67)
Numerical integration may be used to evaluate the integral in the stress
calculations. There are many schemes to evaluate the integral, one of the simplest
method is to use Euler Integration Scheme by approximate the integral as
following:
{ } { } [ ] { }ε+σ≅σ ∆++
∆+∆+∆++ &tt
1iettti
tti
tt1i D …(3.68)
A more elaborate method is to use Modified Euler Integration Scheme as
following:
{ } { } [ ] { }ε+σ≅σ ∆++
∆+∆+∆++ &tt
1iettti
tti
tt2/1i D …(3.69)
Then we calculate [ ]ettt2/1i D∆+
+ using the predicated stress { }σ∆++
tt2/1i . The stress can be
calculated using
{ } { } [ ] { }ε+σ≅σ ∆++
∆++
∆+∆++ &tt
1iettt2/1i
tti
tt1i D …(3.70)
Other methods include the Runge-Kutta methods of various orders. To
minimize errors induced with this integration the strain increment may be divided
into small sub-increment and one of the integration methods is used. Smith and
Griffiths (1998) and Chen and Mizuno (1990) described another algorithm to
retrieve the stress increment from the strain increment in an elastoplastic model.
This algorithm assures that the state of stress will not violate the yield surface,
however it is very convoluted and limited to constant elastic modulii.
113
3.6. Excavation and Lining Installation Modeling The tunnel excavation is a continuous and not a discrete process; yet, the
excavation is modeled by removing a cluster of ground elements from the finite
element meshing. The accuracy of the process increases as the number and size
of excavated (removed) elements per every excavation step are kept as small as
possible. The Stress Reversal Algorithm (SRA) can model excavation by
considering the traction pressures t{Τ} between the excavated and the
unexcavated elements. This traction is in equilibrium with stress t{σ}, the applied
gravity body load t{γ} and any external nodal load (Desai and Abel, 1972). The
excavation is formed by relaxing t{Τ} along the boundary surface between the
excavated and the unexcavated grounds (Sexc), that may be implemented by
applying a pressure − t{Τ} along the excavated boundary as shown in Fig. (3.18),
resulting in a new residual load vector given by:
{ } [ ] { }FdS}T{NR tt
.elements unexc. S
tTe
tt1
exc
&∆+∆+ +−= ∑ ∫ …(3.71)
Ghabossi et al. (1983) presented the Multiple Forming Residual Algorithm
(MFRA), which is an equivalent scheme to calculate the effect of the relaxed
traction vector that is better than the SRA from the computational point of view.
By studying the equilibrium unexcavated ground equilibrium at pseudo time (t),
we will get the following:
{ } [ ] [ ]∑ ∫∑ ∫==
σ=+elements unexc.
1e Ve
tTe
elements unexc.
1e S
tTe
t
unexexc
dV}{BdS}T{NF …(3.72)
where Vunex is volume of the unexcavated ground. Rearranging the last equation
114
[ ] { } [ ]∑ ∫∑ ∫==
σ−=−elements unexc.
1e Ve
tTe
telements unexc.
1e S
tTe
unexexc
dV}{BFdS}T{N …(3.73)
consequently, the residual form at time (t+∆t) is given by
{ } { } [ ] { } [ ]∑ ∫∑ ∫=
∆+∆+
=
∆+∆+ σ−=σ−=elements unexc.
1e Ve
tt0
Te
ttelements unexc.
1e Ve
tTe
tttt
unexunex
dV}{BFdV}{BFR …(3.74)
Hence the excavation is simply introduced into analysis by reforming the residual
vector for the unexcavated ground using the stresses calculated from previous
stage (Bentler, 1998). Another aspect of changing the solution domain is that we
have to renumber the steering vector used in stiffness assembly and recalculate
the size of the system matrices. The lining elements are new elements that must
be added to the mesh by activating these elements. The required changes are to
reconstruct the residual vector, the steering vector and recalculate the size of the
global matrices.
Fig. (3.18) Stress Reversal Algorithm (after Desai and Abel, 1972)
σv
σh
τ
σ
Before Excavation
τ
σ
Excavation
Increment
τvh
Sexc
115
3.7. Programming Aspects of the Model Using the previous modeling concepts, a computer program was prepared
employing a skyline solver in order to minimize the storage size of the assembled
stiffness matrix (Zienkiewics, 1977). The program is divided into twelve key
modules in which each module is subdivided into one or more subroutines. The
processing and data flow through the modules are shown schematically in Fig.
(3.19). The modules and their functions are described in following section:
1- Master module: This module controls the flow of data and calculation
steps.
2- Initialization or zeroing module: This module functions to initialize to
zero various vectors and matrices at the beginning of the solution
process.
3- Data input and checking module: This module handles input data
defining the initial geometry, boundary conditions, material properties
and initial stress field. The data are checked using diagnostic routines.
If errors occur, they will be flagged and the program is terminated.
Once used, this module is not invoked again.
4- Staging module: This module reads changes in the loading and
application of excavation, lining installation, face pressure and tailskin
grouting.
5- Loading module: This module organizes the calculations of nodal
forces due to various forms of loading (gravitational, traction, etc.) for
each stage.
6- Residual force module: The function of this module is to calculate the
residual or ‘out of balance’ nodal forces at the active stage.
7- Residual increment module: This module precedes an incremental
scheme of the applied residual vector evaluated by the residual force
module.
8- Stiffness module: this module organizes the evaluations of the stiffness
matrix for each element according to its type. The stiffness matrices are
assembled in a system stiffness matrix.
116
9- Solution module: The purpose of this module is to reduce and solve the
governing set of simultaneous equations to give the nodal displacement
and force reactions at the restrained nodal points.
10- The stress and strain calculation module: This module is used to
calculate the stress and strain.
11- Convergence module: In this module, the convergence of the nonlinear
solution is checked against a given criterion.
12- The output module: This module is used to print out output of the
computer analysis.
117
Fig. (3.19) Program modules for nonlinear FE code
Initialization or zeroing module
Input data and checking module
Staging module
Residual incrementing module
Stiffness module
Solution module
Stress and strain cal. module
Convergence module
Output module
Main or master module
NR
Loading module
Residual force module
Increment loop
Iteration loop
Staging loop
118
Chapter Four
GREATER CAIRO METRO
4.1. Introduction Cairo population has soared in the recent decades from 3.5 millions in
1960 to more than 20 millions today; it is considered now as one of the most
congested cities in the world. As Cairo began its rapid population explosion in
the 1960's and 1970's, the need for a new mass transportation system was
inevitable. Studies carried out between 1970 and 1974 suggested to construct the
Greater Cairo Metro to be the major mass transportation system.
The Greater Cairo Metro comprises a regional line and two urban lines.
The first line of the Greater Cairo Metro or the regional line was completed in
1989 and was the first subway metro line in Africa and the Middle East. It is 42.5
km long from El-Marg at the North of Cairo to Helwan at the South with about
4.5 km underground part through downtown area. The underground part of the
first line was constructed employing the Cut-and-Cover (C&C) techniques. The
second line extends from Shubra El-Kheima to Giza suburban areas. The third
line is planned to extend about 7 km from Embaba to El Darasah. Fig. (4.1)
shows the arrangement of this network.
The second line is a double deck circular bored tunnel having an
excavated diameter of 9.4m and extending about 18.5km. The line serves 18
Stations including 12 underground. The route of the 2nd Line generally follows
existing streets in order to minimize the tunneling effect on the adjacent
structures as it passes through the most heavily populated and congested areas in
Cairo. Starting as a surface line in Shubra El-Kheima north of Cairo, the line
119
heads south on a viaduct then down into the tunnel part. The tunnel crosses
Ismailia Canal to Cairo Governorate then pursues southward to central Cairo
where it turns west to cross the two Nile branches to Giza Governorate then
changes to on-grade line at Boulak El-Dakrour and continues southward parallel
to the Upper Egypt Railways up to its terminal Station at the Giza suburban
areas.
The 2nd line was constructed and put into operation in two phases. Phase
1A, from Shubra El-Kheima to its intersection with Line 1 at Mubarak Station.
Phase 1B starts from Mubarak Station and terminates at Sadat Station which
forms another interchange with the older first line. Phase 2 extends across to the
west bank of the Nile and terminates at Giza Suburban Station south of Cairo.
The vertical alignment of Phase 1 is shown in Fig. (4.2).
Phase 1 includes a 2.4 km long surficial section and an 8.5 km
underground section in which only 1.4 km was constructed using the C&C
method employing diaphragm walls and sheet piling. Grouted plugs at the toe
level of the diaphragm wall were used to cut off seepage in a manner similar to
the construction of Stations. Slurry cut-off walls divide the tunnel length into
sections and allow excavation to begin in one section while the grouting work
and diaphragm walling continues farther along. The crossing of the Ismailia
Canal was constructed within overlapping sheet piled cofferdams. On completion
of the sheet piling, the cofferdam was backfilled to allow ground treatment to be
carried outs again forming a plug at the base of the excavation.
The following sections describe the construction and instrumentation
details of the bored tunnel of Line 2 – Phase 1A as reported by Richards et al
(1997); Esmail(1997); El-Nahhas (1999); and Ezzeldine (1999).
120
Line 1
Line 2-Phase 1 Line 2-Phase 2
Line 3 Fig. (4.1) Greater Cairo Metro Network
Fig. (4.2) Line 2 – Phase 1 routing (after Richards et al, 1997)
Phase 2
121
4.2. Line 2 – Phase 1A
4.2.1. Geological Conditions The geology of Cairo has been outlined by Shata (1988); he concluded
that Cairo is underlain by tertiary sedimentary rocks and quaternary soils, both
underlain by older basement rocks. The project area lies totally within the
geomorphic unit known as the young alluvial plain that represents the majority of
the lowland portion of the Nile Valley in the Cairo area. The Nile River deposits
governed the subsurface and groundwater conditions. The Pleistocene age
sediments in the alluvial plain are generally fairly consistent with depth, but vary
somewhat laterally as a result of the long history of river meanders, and alternate
cycles of sedimentation and erosion before the construction of Aswan High Dam
in Upper Egypt in the 1960's. These sediments are approximately 60-90 meters
thick in the Cairo area.
According to the Ardman-ACE (1991) and Hamza Associates (1993), the
geotechnical features of the project comprise a surficial man-made fill layer,
which varies in thickness from place to place according to human activities,
underlain by a natural deposit of medium to stiff, relatively massive cohesive
clay-silt layer, which also varies in thickness. This cohesive layer is underlain by
a silty sand transition zone followed by an extensive deposit of coarse sand,
which extends downward beneath the limits for Metro construction. The sandy
deposits are usually poorly graded containing lenses of silts and clays or gravels,
and infrequently contains layers of cobbles and sometimes boulders at depths up
to about 30m.
The ground water level varies seasonally with the level of the Nile River,
with the water level low in the winter when releases from Aswan High Dam are
at a minimum. In addition, it varies annually with the river level as some years
have a higher flow rate than others depending upon precipitation and run off rates
122
in Central Africa in the watershed of the upper Nile. Broadly speaking, the
groundwater regime in Cairo region consists of two distinct categories:
1. The groundwater above the clay layer and within the fill layer, which is
generally a perched water table and often recharged by leaky utilities.
2. The groundwater below the clay layer, which is not usually influenced by
surficial sources as it lies within the confined aquifer formed by the deep
granular deposits.
4.2.2. TBM Selection and Operation Parameters The prevailing subsurface conditions of the bored tunnel are generally
water bearing granular soils consisting of a deep coarse sand deposit overlain
with a finer stained transition layer. Such geological formations limit the tunnel
construction methods to pressurized full face tunneling machines. The fines
content (size less than 0.075 mm) would vary from approximately 7 or 8 percent
in the deep sand stratum to about 60 percent or more in the overlying finer
grained deposits. The gradation of the coarse sand and the overlying transition
zone are shown in Fig. (4.3). Compressed air tunneling with such a large face
area was not feasible due to the difference in water pressure from the crown to
invert of the tunnel and because of the expected high air losses in the permeable
ground. Two identical Herrenknecht BSS TBMs of 9.4m diameter, were selected
to drive the tunnels. The details of the employed TBM are shown in Fig. (4.4).
The TBM is composed of three basic components: the cutterhead, the main shield
body and the tailskin with a total weight of about 600 tons. To satisfy the
required schedule, one of the TBMs was installed at Khalafawi and drove
through the completed box at St. Theresa then removed at Rod El-Farag. The
second TBM was installed at Rod el-Farag, drove through the completed box at
Masarra and removed at Mubarak. Both TBMs then were transported to Attaba,
where one of them drove back towards Mubarak and the other drove through the
completed box at Awkaf to Sadat.
123
The cutterhead of the TBM is capable of operation in either direction of
rotation, with cutter teeth arranged accordingly. The cutterhead was initially
equipped with 280 cutter teeth and 21 dual 38 cm diameter roller disc cutters as
show in Fig. (4.5). However, after the initial tunnel drive in Lot 12, nine of the
central roller disc pairs were removed to provide more open area in the
cutterhead face to allow better material flows into the cutting chamber. The
openings in the cutterhead face allowed passage of material up to 200 mm in
size. The machine was not equipped with a crusher to break this material size
into smaller pieces in order to minimize potential blockages of the mucking
system. Inside the cutting chamber, two counter-rotating agitator wheels were
installed to keep the excavated solids in suspension until removal by the slurry
suction pumps. Face pressure of the bentonite slurry was provided and controlled
by an air chamber built into the body of the shield. The shield was equipped with
a two-chamber air lock to allow up to four workmen to enter the cutting chamber
to repair or replace machine components as required. Table (4.1) summarized the
various TBM operating parameters.
Table (4.1) TBM operational parameters (after Richards et al, 1997)
Operational parameter Unit Installed capacity Normal range of operation
Total installed power kW (HP) 2450 (3264) --- Rotary drive power kW (HP) 1000 (1360) ---
Rotary power/face area kW/m2 14.3 --- Torque m.t. 770 440
Rotation speed rpm 0-2.25 1-1.5 Advance rate mm/min 50 25-45
Agitator speed rpm 0-50 50 No. of jacks pairs 15 All Total thrust Tons 6000 2000-2500
Slurry pump power kW (HP) 2190 (2978) --- Slurry pump feed m3/hr 1400 1100-1300
Bentonite face pressure bars 3 1.5-2.5 Grout injection capacity m3/hr 40 15-20 Grout injection pressure bars >40 3.0-3.5
124
Fig. (4.3) Grading of the granular deposits
(after Richards et al, 1997)
Fig. (4.4) BSS used in the second line
(after El-Nahhas, 1999)
125
Fig. (4.5) Cutting face of the BSS
(after Richards et al, 1997)
The TBMs were designed to include automatic tail void grouting as the
machine advanced. Injection pressure was controlled by upper and lower limit
sensors, with the limits adjustable. The injection pipes were embedded in the tail-
skin of the machine at four sets of dual (normal and spare) injection pipes
embedded in the perimeter of the tailskin of the shield. The normal injection
points were located at the 2, 4, 8, and 10 o'clock positions. Backup or spare
injection ports were located at approximately the 3, 6, 9 and 12 o'clock positions.
The tail void grout used was a lime and silica fume based mortar. This mortar
provided strengths of about 1.0-1.2 MPa (10-12 kg/cm2) in 28 days, and had
setting times of about 12-16 hours. This long setting time prevented set up of the
grout in the grout mixing tank, pump, and injection piping system during short
126
repair stoppage period. The tailskin was equipped with a fat plate seal at the rear,
backed up by two wire brush seals as illustrated in Chapter (2) and shown in Fig.
(4.4). A paper pulp based mastic material was continuously injected between the
tail seals to provide a supplemental seal against ground water and tail void grout
ingress around the perimeter of the erected lining. The pressure was always in
excess of the hydrostatic water pressure in order to allow a certain amount of the
mixture water to bleed into the surrounding ground, leaving a more dense (and
higher strength) mortar material than in the laboratory specimens. The injection
system allows for immediate adjustment of injection parameters such as volumes
and pressures.
The measured surface settlements associated with tunneling were less than
14mm on average basis, and alignment deviations averaging less than 25mm.
Production rates up to 580m/month were achieved, with average production of
4.8m/shift, 13.4m/day and 78m/week. The completed tunnels in the second line
are lined with seven bolted precast reinforced concrete segments of 1.5 m length
and a key as shown in Fig. (4.6). The lining has 8.35 m inside diameter and 40
cm thickness producing an external diameter of 9.15 m. The segments were
assembled within the machine shield tail. The lining should be completely
watertight under a head of approximately 2 bar of water pressure employing
elastomeric gaskets and a hydrophilic seal installed behind the elastomeric
gaskets. The tunnel lining joints between individual segments were required by
specification to be caulked in a groove cast into the four sides of each segment at
the inside surface as shown in Fig. (4.7). The specified water tightness of the
tunnel should be achieved without this caulking. The shield used an
electromechanical erector for segment installation, having 6 degrees of freedom
and a lifting capacity of eight tons. The erector used a vacuum pick up system,
with the vacuum seals arranged to provide seals for both the larger regular
segments and the smaller key segment. Installation procedures required
127
retightening the bolts after starting the shove for the next ring in order to
compensate for bolt loosening resulting from gasket compression.
A treatment plant was designed for slurry processing at a rate of 1500
m3/hr at a density between 1.0 and 1.2 gm/cm3. It was designed to handle a
maximum of 15 percent of the solids > 7.5mm in size, 99 percent between
7.5mm and 80 microns, and 15 percent smaller than 80 microns. The treatment
process included several steps of solids removal, starting with passage of the
slurry over a vibrator screen to remove particles > 7.5mm. The next step passed
the slurry through six cyclone desanding units removing particles down to 150
microns. Finally, the slurry passed through two units of eight cyclones each for
silt removal down to 80 microns in size. The layout of the treatment plant is
shown in Fig. (4.8).
The technical specification and contract documents of the second line
included a special section on insitu geotechnical monitoring implemented by the
contractors during construction of the tunnel. The monitoring program was
partitioned into the following four phases (El-Nahhas, 1999):
1. Dilapidation survey of existing buildings and other structures located in
the vicinity of the tunnel route.
2. An extensively instrumented test section located at the early stage of
advance of each TBM.
3. Measurement of settlement troughs at control sections at intervals of
about 20 m along the tunnel route.
4. Detailed monitoring of special structures situated along the route.
Two test sections, south of El-Khalafawy Station (Lot 12) and south of
Rod El-Farag Station (Lot 16), were heavily instrumented during the construction
128
Line 2 - Phase 1A. Hamza Associates (1995) presented a detailed report to
evaluate the tunnel monitoring for Lots 12 and 16 in addition to some
instrumentations at Lot 14. The instrumentation observations were used to
evaluate the tunneling techniques and the ground response during the stages of
the advance of the TBMs.
Fig. (4.6) Bolted reinforced concrete segments
(after Richards et al, 1997)
129
Fig. (4.7) Lining groundwater sealing measures
(after Richards et al., 1997)
1. Screen: size > 7.5 mm. 2. Cyclone: 7.5mm ≤ size ≥ 150 microns. 3. Cyclone: 150 microns ≤ size ≥ 80 microns. 4. Intermediate holding tank. 5. Muck discharge conveyor 6. Bentonite supply
Fig. (4.8) The slurry treatment plant
(after Richards et al, 1997)
130
4.3. Model Verification at Lot 16 This section authenticates the proposed numerical model at Lot 16
(between Rod El Farag Station. and Masarra Station). The analysis of
displacements and stresses around the tunnel is carried out using the proposed
model as described in Chapter (3). The results are compared with the field
measurements compiled during the construction of the tunnel to verify the model
assumption and study the prevailing parameters affecting tunneling. The
subsurface conditions were investigated using deep borings. According to
Ardman-ACE (1991) and Hamza Associates (1993), the soil log in Lot 16 is
shown in Fig. (4.9). The following distinctive layers are identified:
1. FILL: Appears at the ground surface and extends to a depth of about 3.0
m. The fill contains asphalt, sand, clay and limestone pieces.
2. CLAY-SILT: A medium to stiff silty clay or clayey silt layer exists below
the fill and extends to a depth of about 4.50 m below ground surface.
3. SAND: A medium dense to very dense fine to medium sand layer
underlies the previous clay and extends to the end of the borings. This
sand contains a substantial percentage of silt, which becomes lesser with
depth. The top 5 meters have substantial silt content and may be classified
as silty sand. Some clay pockets, gravel and cobbles exist at different
depths.
4. GROUNDWATER: Groundwater appears at about 1.9 m
Soil elements are represented using the hyperbolic elastoplastic model to
account for the effect of the stress level, stress path and confining pressure on the
stress-strain relationship. Nonlinear soil parameters used in the FE discretization
are estimated according to the geotechnical properties of the acknowledged
layers and are summarized in Table (4.2).
131
Table (4.2) The estimated subsurface nonlinear geotechnical parameters Stratum FILL CLAY – SILT Silty SAND Dense SAND
φ 15 0 30 37
C (kg/cm2) 0 0.8 0 0
γ (t/m3) 1.7 1.8 1.9 2.0
ko 1.0 0.74 0.50 0.40
K 150 225 350 600
N 0.6 0.55 0.5 0.5
Rf 0.70 0.75 0.8 0.8
υ 0.4 0.4 0.35 0.3
Shield and tunnel lining elements are represented by elastic elements with
different elastic properties to account for the different stiffness of the lining and
the shield. The shields modulus of elasticity is assumed to be 2000 t/cm2 with a
Poison’s ratio of 0.3. The lining is assumed to have a 140 t/cm2 modulus with a
Poison’s ratio of 0.15. The assumed lining modulus contains a judicial reduction
of about 30% to account for its segmental nature. The interface of the soil-shield
and soil-lining is represented by a three dimensional hyperbolic gap element and
grouting element with initial grouting pressure at the Gauss points. The grouting
elements have a variable stiffness in accordance with the advance rate of the
TBM as described in Chapter (3) assuming that the rate of advance of the
machine is 13 m/day and the half-strength time is 3days.
Special incremental technique is used to account for the variable mesh
size due to excavation and lining installation using the incremental pseudo time
technique combined with Newton-Raphson Iterative Technique. The technical
data of the employed TBM recommended the total ground loss as 0.5%. The
measured insitu ground surface settlements were used to compute the volume of
ground surface settlement trough, which is converted to a volume of ground loss
around the TBM. Hamza Associates (1995) reported the total volume of about
132
0.23%ground loss. The face loss was estimated to be about 0.09%, i.e. the loss
along perimeter of the TBM (which is mainly due to the overcutting) is about
0.14%. These data were introduced into the model. The grouting pressure is
assumed to be 3.25 bar. The face pressure is assigned to 2.0 bars.
Fig. (4.9) Subsurface conditions at Lot 16
(after Ardman-ACE, 1991)
Excavated diameter 9.40 m
133
The finite elements mesh used in the analysis is shown in Fig. (4.10) with
total of 3276 nodes, 2592 solid hexahedral elements and 207 joint elements to
represent the interface between the soil and lining. The analysis required about 6
hours using an INTEL PENTIUM II 300 computer with 64 MB RAM. The
tunneling activity was idealized in 21 incremental steps. The mesh at the end of
the 21st steps is shown in Fig. (4.11).
The idealization incorporates different constructional aspects of the TBM,
i.e. the face pressure, the overcutting, the tail gap, the tailskin grouting and lining
installation, as well as the nonlinear constitutive soil relations and the time-
hardening behavior of the grouting material as illustrated in Chapter (3). The
analysis is based on the effective stresses. Seepage towards or away from the
tunnel is neglected. This assumption is justified by the field measurements of the
excess water pressures, which are generally insignificant due to the effect of the
developed mud cake at the tunnel face. The GID pre/post processor1 was used to
visualize the developed analysis.
The GID environment accepts only nodal quantities; as the maximum
stress level and the stresses are computed at the Gauss points of the elements
during the solution stage for best possible accuracy, a special program that
applies an interpolation scheme was employed to obtain the stress level and the
stresses at the nodes. The visualization capabilities of the GID support element
layering that can be used to plot sub-regions of the mesh. Using the layering
feature, three rows of elements were removed from the plotting to minimize the
boundary condition effect on the results. The soil elements and the lining
elements are presented individually because of their different modeling.
1 Shareware from International Center For Numerical Methods In Engineering (CIMNE)-Spain, URL
http://gid.cimne.upc.es
134
Fig. (4.10) Initial mesh of Lot 16
Fig. (4.11) Mesh after 21 steps
56 m
76 m
18 m
27 m
Tunnel advance direction 45 m
135
4.3.1. Results of the Numerical Model
4.3.1.1. The Stress Level Field
The stress level is defined as the ratio between the actual deviator stress
and the maximum deviator stress that can be sustained by the soil as defined by
Mohr-Coulomb criterion. The maximum stress level distribution in soil elements
is depicted in Fig. (4.12).
The results show a pronounced increase in the maximum stress level
around the tunnel environs, i.e. this zone is fully or partially yielded due to the
tunneling activities. The yielded zone is substantially revealed at the crown and
at the springline. At the invert the stress level is near its pre-tunneling value.
Another yielded zone is shown at the face due to the partial stress release at the
tunnel heading. The face yielded zone is nearly a semi-sphere while the
peripheral yielded zone has an eccentric cylindrical shape. The presence of the
yield zone affects the deformation field profoundly due to the stiffness
degradation around the tunnel.
4.3.1.2. The Deformation field
Figs. (4.13 to 4.15) demonstrate the deformation field around the tunnel.
The horizontal displacement in x direction shows a movement towards the tunnel
at the ground surface and in the inverse direction below, this may be attributed to
high grouting pressure compared to the much lower horizontal soil pressure. The
vertical deformation comprises settlement above the crown and heave beneath
the invert due to radial stress relief at the tunnel and the face.
The settlement above the crown increases with depth up to the plastic zone
where it shows a decreasing rate due to influence of the grouting pressure. The
axial deformation of the lining shows a surface deformation towards the shield
and a face deformation towards the tunnel. Figs. (4.16 to 4.18) show a good
136
agreement between the results of the numerical model and the observed surface
settlement as well as lateral displacement. The maximum surface settlement is
about 18 mm. The settlement at the face is 7 mm (i.e. 40% of the maximum
settlement). The settlement trough extends to a distance of 25 m ahead of the
tunnel, which is about 2.6 times the excavated diameter of the tunnel. The
settlement increases after the passing of the TBM to a distance of 45 m, which is
about 4.8 times the excavated diameter. The actual settlement trough is wider
than the predicated one. The settlement trough extends to a distance of 20 meters
(i.e. about 2 times the excavated diameter).
4.3.1.3. The Stress field
Figs. (4.19 to 4.27) show the soil stress field. The compressive stresses are
positive and the values are in t/m2. The vertical stress (σy) shows a relaxation
trend towards the tunnel’s crown and the invert. The stress above the crown has a
conspicuous uniform trend resulting from the arching effect that mitigates the
overburden soil. The reduction in vertical stress however is more significant
below the invert, however a minor heave is connoted due to the elastic nature of
the tunnel peripheral underneath the invert.
The distribution of horizontal stress in x-direction (σx) shows a perceptible
increase at the springline with inconsequential changes elsewhere. The horizontal
stress in z-direction (σz) shows a noticeable decrease around the tunnel and at the
face. The major and the minor principal stresses show a significant decrease
around the tunnel while the intermediate stress is almost unaltered due to the
adjacent tunneling process. The shear stress distribution shows that the
components in the y-z and x-z planes are more substantial than the shear stresses
in the x-y plane. The plain strain analysis is less adequate in view of these
distributions.
137
Fig. (4.12) Maximum stress level
Fig. (4.13) Displacement in x direction (mm)
138
Fig. (4.14) Displacement in y direction (mm)
Fig. (4.15) Displacement in z direction (mm)
139
Fig.
(4.1
6) S
urfic
ial s
ettle
men
t alo
ng th
e tu
nnel
axi
s for
Lot
16
140
Fig.
(4.1
7) S
urfic
ial s
ettle
men
t per
pend
icul
ar to
the
tunn
el a
xis a
t Lot
16
141
Fig. (4.18) Measured and estimated lateral displacement for
a vertical plane at 9.40 m from the tunnel CL
FE Measured (after Hamza Associates, 1995)
Lateral displacement (mm) D
epth
(m)
142
Fig. (4.19) The distribution of the normal stress in x-direction (t/m2)
Fig. (4.20) The distribution of the normal stress in y-direction (t/m2)
143
Fig. (4.21) The distribution of the normal stress in z-direction (t/m2)
Fig. (4.22) The distribution of the shear stress in x-y plane (t/m2)
144
Fig. (4.23) The distribution of the shear stress in y-z plane (t/m2)
Fig. (4.24) The distribution of the shear stress in z-x plane (t/m2)
145
Fig. (4.25) The distribution of the major principal stress (t/m2)
Fig. (4.26) The distribution of the intermediate principal stress (t/m2)
146
Fig (4.27) The distribution of the minor principal stress (t/m2)
4.3.1.4. The Lining Deformation and Straining Actions
Fig. (4.28) shows the deformation modes of the lining. An oval shape is
commonly perceived. The invert heave and the crown settlement are generally
greater than the springline outward deformation. The crown settlement increases
with the distance from the tail. Final deformation mode, Fig. (4.28.f), is
characterized with less invert heave compared to the crown settlement. The
springline deformation decreases vaguely to smaller values with the increase of
the time of installation. Figs. (4.29) to (4.34) show the stresses in the lining due
to the effective earth stresses; the negative normal stresses indicate a tension zone
and the positive values indicate compressive stresses. The water pressure causes
an additional radial compressive stress of about 18kg/cm2. The face support
counter reaction causes an additional axial compressive stress of 26 kg/cm2. The
147
results of the FE plus the additional stresses for a section 48m behind the tail, are
shown in Table (4.3). The thrust and the bending moments are also calculated by
the integration of the stresses and shown in the following Table.
Table (4.3) Lining straining actions at Lot 16
External surface Internal surface
Location
Radial
normal
stress
(kg/cm2)
Axial
normal
stress
(kg/cm2)
Radial
normal
stress
(kg/cm2)
Axial
normal
stress
(kg/cm2)
Radial
thrust
(t/m)
Radial
moment
(m.t/m)
Crown 28.8 42.5 22.6 39.4 103 0.1
Springline 31.3 29.3 42.5 30.3 148 -0.18
Invert 28.4 21.5 21.7 20.7 100 0.11
The concluded results show that the thrusting force is the major straining
action in the lining. The moment is very small and may be justifiably neglected.
Consequently, no special modeling is needed to account for the segmental nature
of the lining. The maximum thrust occurs at the springline with a value of 148
t/m, which is very close to the assumption of no arching. Fig. (4.35) compares
the results of the insitu radial stresses and the estimated lining pressure. The
figure shows a minor reduction of the stress at the invert and a trivial increase at
the springline and at the crown. The tunnel is classified as a shallow tunnel in
which the arching effect is small. The axial force at the crown is unexpectedly
larger than the force at the invert. Embedded strain gauges indicate a tensile
strain at the invert, which is not accountable based on the fact that the face
support gives a higher reaction at the lining invert. This may be attributed to the
friction between the lower part of the lining and surrounding unyielded soil. A
much less friction is anticipated at the upper half due to the relatively low
overburden and the higher tendency to yield.
148
Original shape
Deformed shape
Fig. (4.28) Lining modes of deformation
(magnification factor = 20000)
149
Fig. (4.29) The distribution of the normal stress in x-direction (t/m2)
Fig. (4.30) The distribution of the normal stress in y-direction (t/m2)
150
Fig. (4.31) The distribution of the normal stress in z-direction (t/m2)
Fig. (4.32) The distribution of the shear stress in x-y plane (t/m2)
151
Fig. (4.33) The distribution of the shear stress in y-z plane (t/m2)
Fig. (4.34) The distribution of the shear stress in z-x plane (t/m2)
152
Fig. (4.35) tunnel lining pressure in t/m2:
(a),(b),(c) distribution of estimated lining pressure
(d),(e),(f) distribution of the initial insitu radial stresses
153
4.4. Model Verification at Lot 12
4.4.1. Numerical Simulation This section verifies the proposed numerical model at Lot 12 (between El-
Khalafawi and St. Theresa). The analysis results are evaluated using the field
measurements compiled during the construction of the tunnel. According to
Hamza Associates (1993) and Ezzeldine (1999), the prevailing soil profile at Lot
12 is shown in Fig. (4.36). The soil is presumptuously composed of the following
distinctive layers:
1. FILL: Appears at the ground surface and extends to a depth of
about 1.5 m below ground surface.
2. CLAY-SILT: A medium stiff silty clay layer exists below the fill
and extends to a depth of about 6.5m below ground surface.
3. SAND: A medium dense to very dense fine to medium sand layer
underlies the previous clay and extends to the end of the borings.
This sand contains a substantial percentage of silt becomes lesser
with depth. The top 3 meters is classified as silty sand.
4. GROUNDWATER: Groundwater appears at about 3.0 m
The nonlinear ground parameters are assigned as updated at Lot 16.
Hyperbolic elastoplastic soil elements are used. Shield and tunnel lining elements
are represented by elastic materials with different elastic characteristics to
comprise the different stiffness of the lining and the shield. The interface of the
soil-shield and soil-lining is represented by a three dimensional hyperbolic gap
element and grouting element with initial grouting stress. The finite elements
mesh used in the analysis comprises 2968 nodes, 2322 solid hexahedral elements
and 198 joint elements to represent the interface between the soil and lining.
154
Fig. (4.36) Subsurface conditions at Lot 12
(after Ardman-ACE, 1991)
Excavated diameter 9.40 m
155
4.4.2. Results of the Numerical Model The different geotechnical and constructional details of the tunneling
status at Lot 12 were incorporated in the proposed geotechnical model. Face
pressure and grouting characteristics of Lot 16 were adopted herein.
The analysis results are compared with the field measurements. Figs. (4.37
and 4.38) show a good agreement between the surface settlement troughs
resulting from the model compared to the measured values. The maximum
settlement in this case is about 11 mm. The maximum settlement is less than Lot
16 due to the different soil profile and depth of the tunnel center. The settlement
trough extends 25 m ahead of the TBM face and 45 m behind the TBM face,
which are the same limits for Lot 16. The settlement trough width is about 18 m.
The model predicates some heave beyond settlement trough with a maximum
value of 1.5 mm.
Fig. (4.39) shows the variation of the vertical deformation with depth. The
final settlement (48 m behind the face) is almost constant with depth up to about
10 m then it increases slightly in a distance of 2.5 m to reach a value of 12.5 mm
and then decreases to the tunnel crown. The tunnel invert experiences a heave of
6.5 mm, which slightly decreases to the end of the mesh. According to Hamza
Associates instrumentation report (1995), the constant settlement variation in
tunneling was observed frequently during the monitoring phase.
A deep settlement point at depth of 12.5 m was indicated in Fig. (4.39)
along with a surface settlement point; the two points show a good conformity
with the analysis results. The observations of the deep settlement points versus
the TBM passage distance are shown in Fig. (4.40) with the FE results. Fair
agreement is observed between the predicated profile and measured values.
156
Fig.
(4.3
7) S
urfic
ial s
ettle
men
t alo
ng th
e tu
nnel
axi
s for
Lot
12
157
Fig.
(4.3
8) S
urfic
ial s
ettle
men
t tro
ugh
perp
endi
cula
r the
tunn
el a
xis f
or L
ot 1
2
158
Fig. (4.39) Settlement versus depth along the tunnel axis for Lot 12
159
Fig.
(4.4
0) S
ettle
men
t ver
sus t
he fa
ce d
ista
nce
at d
epth
of 1
2.5
m fo
r Lot
12
160
4.5. Stabilization Measures and Deformation Field
4.5.1. Introduction The model incorporates the different measures used to stabilize the
excavation; namely: The face pressure, tail grouting and the lining installation.
The face pressure is applied as a traction pressure on the face elements while the
grouting pressure is applied through using of special pre-stressed grouting
elements that have a hardening behavior with time.
Excavation and lining installation cause an incessantly altering to the
mesh and thus necessitating special numerical procedures in the program. The
overcutting loss is modeled using a peripheral gap element that allows the ground
convergence around the TBM. In this section, different ground stabilization
means related to construction of Greater Cairo Metro–Line 2 (Lot 12) are
studied quantitatively in conjunction with the effect of overcutting losses (the
Gap Parameter) on the ground deformation field.
4.5.2. The Face Pressure and the Face Stability The face stability is a major concern in the design of soft grounds tunnels.
Face failures may lead to catastrophes and life losses inside the tunnel and
enormous ground deformation endangering the surrounding buildings and buried
utilities above or in vicinity of the tunnel. The BSS supplies the required face
stabilization through a slurry pressure that exceeds the water pressure by a
fraction of the effective overburden pressure as it was described in Chapter (3).
The effective slurry pressure (face pressure that is in excess of the
hydrostatic pore water pressure) is studied parametrically assuming values of 0.0,
2.0, 4.5, 9.0 and 18.0 t/m2. The resulting face axial deformation is shown in Fig.
(4.41). This figure shows large axial deformation towards the tunnel for the face
161
pressure values of (pf’ = 0) and (pf’ = 2 t/m2) and much less for the case of (pf’ =
4.5 t/m2). The axial deformation tends to reverse direction for ((pf’ = 9 t/m2) and
(pf’ = 18 t/m2). The maximum axial deformation versus the face pressure is
shown in Fig. (4.42). The limiting pressure appears at 2 t/m2, i.e. 40% of the
effective active pressure (about 5 t/m2) of the far field. The difference between
the estimated limiting face pressure and active earth pressure of the overburden
pressure results from the arching effect which occurs due to stiffness degradation
in the yielded zone near the face resulting in a reduction in the face pressure as
shown in Fig. (4.43).
The surface settlement for different values of the face pressure is shown in
Fig. (4.44). Increasing the face pressure causes little heave in front of the tunnel
face and reduces the maximum settlement slightly. Fig. (4.45) depicts the
surficial settlement and heave versus the face pressure. The figure shows that the
maximum heave in front of the face is increased in the same rate as the maximum
settlement is reduced behind the TBM.
Adapting a safety factor of 2, the analysis shows that 80% of active
earthpressure can be a good estimate of the safe face pressure in shallow tunnels
in which the face losses are substantially reduced. Increasing the face pressure
furthermore will cause some heave in front of the TBM that can slightly reduce
the maximum settlement by the same amount. It should be noted that the slurry
pressure is higher than the hydrostatic water pressure by the effective face
support value. This excess causes outward flow pattern from the slurry chamber
to the ground in the vicinity of the face. This flow tendency helps to form the
bentonite cake at the excavated face and reduces the effect of any seepage
towards the face. The slurry cake also reduces the effect of the inverse flow from
the slurry chamber to grounds enfolding the tunnel and this explains the minimal
increase in the water pressure due to the tunnel construction.
162
Fig. (4.41) Distribution of the face axial displacement for
different face pressure values
Axial displacement of the face (mm)
Dis
tanc
e fr
om th
e in
vert/
tunn
el d
iam
eter
163
Fig. (4.42) The effect of the face pressure on the
maximum axial displacement
Effective face pressure (t/m2)
Axi
al d
ispl
acem
ent o
f the
face
cen
ter
(mm
)
164
Fig. (4.43) The effect of soil arching on the face limiting equilibrium
σv
ko σv
σv’
ka σv’
Yielded zone having
degraded stiffness
TBM
Limiting effective face pressure
σv ko σv ka σv
State of stress in the
far field
σ
τ
Shear envelope
σv’ ka σv
’
Limiting circle without the effect of arching
Limiting circle with the effect of arching
165
Fig.
(4.4
4) T
he e
ffec
t of t
he fa
ce p
ress
ure
on th
e su
rfac
e ve
rtica
l def
orm
atio
n
166
Fig.
(4.4
5) T
he e
ffec
t of t
he fa
ce p
ress
ure
on th
e m
axim
um su
rfac
e ve
rtica
l def
orm
atio
n
167
4.5.3. Effect of the Gap Parameter on The Deformation Field The overcutting loss is one of the most pronounced sources of the ground
deformation in tunnels. The overcutting is modeled as a peripheral ground loss
around the TBM. A special nonlinear interface element is employed to fulfill the
compatibility between the tunnel and the enfolding ground taking void between
them into considerations.
The effect of the overcutting on the surficial ground deformation is shown
in Figs. (4.46) to (4.53) for different overcutting losses (0.00, 0.05, 0.3, 0.5, 0.75
and 1.00%) as well as the verification case (overcutting loss = 0.15%). For no
radial loss around the TBM (overcutting loss = 0.00), the ground settlement
above the tunnel CL is accompanied with a heave of the same magnitude away
from the CL. The heave is reduced and settlement increases considerably when
increasing the overcutting loss by a slight percentile (0.05%). Increasing the
overcutting loss furthermore reduces the heave to almost nil while the settlement
increases substantially as shown in Fig. (4.53).
The width of the settlement trough increases with the increase of the radial
loss from about 8 m at no overcutting to 27 m at 1% overcutting loss in contrast
to the common rules of thumb that relate the width of the settlement trough to the
geometrical configuration only as stated in Chapter (2). Fig. (4.54) shows an
isometric view of the surficial deformation field for the extreme case (overcutting
loss = 0.00 and 1.00%). The figure shows how the deformation field
characteristics are considerably dependent of the overcutting. Although
overcutting can significantly increase the settlement associated with tunneling, it
is inevitable because it helps driving the TBM specially at curved routing.
The vertical distributions of the vertical deformation at the tunnel CL are
shown in Figs. (4.55) to (4.60) for the different overcutting losses. The
168
distribution of the vertical deformation is generally settlement above the crown
and heave below the invert. The settlement distribution for low overcutting losses
(less than 0.5%) is more or less constant to a depth of 8 m. The settlement rate
from the previous depth increases up to a depth of 10 m and then decreases to the
tunnel crown due to the effect of the tail grouting.
The ratio between the surface settlement and crown settlement for
overcutting losses less than 0.5% is generally less than unity due to the tail
grouting. The ratio increases above unity for cases above 0.5% (about 1.35% at
1.00% overcutting loss). The heave below the invert decreases from 10 mm at no
overcutting to 5 mm at 1% overcutting loss. The difference is localized in the top
2 m below the invert where sudden increase is conspicuous in low overcutting
losses.
4.5.4. The Effect of Tail Grouting The function of the tail grouting is to fill the annular void between the
erected lining rings and the excavated ground. The grouting pressure should be
always greater than the hydrostatic water pressure in order to allow the mixture
water to bleed into nearby ground and was commonly selected equal to the soil
total stress at the springline.
The effect of the tail grouting on the surficial deformation field was
studied parametrically assuming the effective tail grouting pressure equal to 0,
17.5 and 40 t/m2. Fig. (4.61) shows the effect of the grouting pressure of the
surface settlement, which appears to be trivial. Figs. (4.62) and (4.63)
demonstrate the effect of the grouting pressure on vertical deformation of the
crown and the invert. The crown experiences settlement at low grouting pressure
(0 and 17.5 t/m2); however, the deformation turns to heave at higher grouting
pressures (40 t/m2). The invert undergoes heave that is almost insensitive to the
169
grouting pressure. This result may be attributed to the existence of yielded zone
around the tunnel especially in the crown zone causing the soil to compress
locally without affecting the ground surface. In the invert zone, the ground
behaves elastically so that the effect of the grouting pressure is minimal.
A conceptional model to present the effect of tail grouting on the surface
settlement trough was offered by Simpson (1993). Observing the results of
laboratory tests of reversal stress paths, he concluded that soils generally offer
less resistance to continuation of straining in the direction they were previously
following than they do to the reverse direction, which means that on reversal of
the stress path, the strains tend to continue in their previous direction before
swinging round to follow the new path. He mimicked that behavior by a man
pulling strings attached to bricks during his turning back as shown in Fig. (4.64).
Similar conclusion was offered by El-Nahhas (1999) in comparing
between the performance of the tail grouting of Cairo Wastewater Project (3-6%
ground loss) and tailskin grouting of Greater Cairo Metro project (generally less
than 1%) in which the grouting pressure values were not foremost factor other
than the location in which the tail grouting started to be functional as tail
grouting in Cairo Wastewater project started after installation of a few rings to
prevent potential damages to tail seal.
During the construction of greater Cairo Metro, the tail annular void’s
volume was 7.24 m3/m. The grouting volume usually exceeded by 9% in average
to allow grouting bleeding and in some extreme cases by 160% in which the
grouting material flowed past the TBM to the face producing no heave to the
surface ground.
170
Fig.
(4.4
6) T
he e
ffec
t of t
he o
verc
uttin
g lo
ss o
n th
e su
rfac
e ve
rtica
l def
orm
atio
n
171
Fig.
(4.4
7) S
urfic
ial v
ertic
al d
efor
mat
ion
troug
h fo
r ove
rcut
ting
loss
= 0
.0%
172
Fig.
(4.4
8) S
urfic
ial v
ertic
al d
efor
mat
ion
troug
h fo
r ove
rcut
ting
loss
= 0
.05
%
173
Figu
re (4
.49)
Sur
ficia
l ver
tical
def
orm
atio
n tro
ugh
for o
verc
uttin
g lo
ss =
0.3
0 %
174
Fig.
(4.5
0) S
urfic
ial v
ertic
al d
efor
mat
ion
troug
h fo
r ove
rcut
ting
loss
= 0
.50
%
175
Fig.
(4.5
1) S
urfic
ial v
ertic
al d
efor
mat
ion
troug
h fo
r ove
rcut
ting
loss
= 0
.75
%
176
Fig.
(4.5
2) S
urfic
ial v
ertic
al d
efor
mat
ion
troug
h fo
r ove
rcut
ting
loss
= 1
.00
%
177
Fig.
(4.5
3) T
he e
ffec
t of t
he o
verc
uttin
g lo
ss o
n th
e m
axim
um su
rfac
e ve
rtica
l def
orm
atio
n
178
Fig. (4.54) Surficial vertical deformation trough for
(a) overcutting loss = 0.00 % and (b) overcutting loss = 1.00 %
(a)
(b)
179
Fig. (4.55) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.0%
180
Fig. (4.56) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.05%
181
Fig. (4.57) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.3%
182
Fig. (4.58) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.5%
183
Fig. (4.59) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 0.75%
184
Fig. (4.60) The distribution of vertical deformation at the tunnel CL
for overcutting loss = 1.0%
185
Fig.
(4.6
1) T
he e
ffec
t of t
he ta
il gr
outin
g pr
essu
re o
n th
e m
axim
um su
rfac
e ve
rtica
l def
orm
atio
n
186
Fig.
(4.6
2) T
he e
ffec
t of t
he ta
il gr
outin
g pr
essu
re o
n th
e ve
rtica
l def
orm
atio
n of
the
crow
n an
d th
e in
vert
187
Fig.
(4.6
3) T
he e
ffec
t of t
he ta
il gr
outin
g pr
essu
re o
n th
e m
axim
um v
ertic
al d
efor
mat
ion
of th
e cr
own
and
the
inve
rt
188
Fig. (4.64) The analogue – a man pulling bricks around a room
(after Simpson, 1993)
189
Chapter Five
CASE HISTORIES OF MULTIPLE AND TWIN TUNNELS
5.1. Introduction Tunneling deformation fields are significantly modified due to mutual
interaction of adjacent or intersecting tunnels. Multiple tunnels comprise
distinguishable convoluted three-dimensional problems that cannot be analyzed
precisely utilizing simplified two-dimensional analysis or empirical superposition
techniques. The nonlinear three-dimensional simulation presented for the Greater
Cairo Metro analysis can be viewed in broader perspective as it is extended in
this chapter, bidding an appropriate framework to analyze multiple tunnels
constructed using the same technique. Two cases of multiple tunnels are
analyzed; namely: El-Salam Syphon; and Al-Azhar Twin Road tunnels at the
location of their intersection with the CWO sewer. The modifications to ground
deformation fields are investigated. The pre-grouting measure used to minimize
the effect of tunneling on the CWO sewer is evaluated parametrically.
5.2. El-Salam Syphon Project The population explosion devotes Egypt no alternative but to accelerate
land reclamation projects such as North Sinai Development Project. This project
was first conceived in the late 1970s in order to develop a total area of 400,000
feddans in Northern Sinai as shown in Fig. (5.1). The project comprises three
main elements, namely: E1-Salam Canal, west of the Suez Canal; the syphon
under the Suez Canal; and El-Sheikh Gaber Canal, in Northern Sinai. The
irrigation for this development requires up to 160 m3/sec of water to be
transferred from the existing El-Salam Canal on the west bank to El-Sheikh
190
Gaber Canal on the east bank. The transferred irrigation water is provided from
the Damietta branch of the River Nile, El-Sirw drain and Bahr Hadous drain. The
water is transported from the east to the west of the Suez Canal under the Suez
Canal through El-Salam Syphon, which comprises four bored tunnels. Fig. (5.2)
shows the vertical alignment of the four tunnels.
The geological nature of the subsurface is predominately gray silty clays
and yellowish gray sand. The surficial soft clays layer thickness ranges between
4 and 50 m of high to very high plasticity covered by "Sabkha", which is very
salty dark gray silty clay with very low consistencies. The sensitivity of these
clays is medium and ranges around 2 and the consistency varies from very soft to
stiff. The tunnel alignment enters into the sand layer that is under artesian water
pressure. The coefficient of permeability of this sand layer is high at about 10-4
m/sec. The maximum water pressure is estimated to be 4.5 bars. The tunnel
boring machine (6.54 m outer diameter) chosen by the contractor to excavate and
construct the primary segmental linings of the tunnels is a Herrenknecht
mixshield. The machine has been specially designed to work at 4.5 bar operating
pressure, on inclinations of up to 20%, and is capable of negotiating curves of
500 m radius. The overcutting void was estimated to be 1.00% of the excavated
ground volume that might be increased to 1.85% in some abnormal difficult
conditions. The annular gap between the cut annulus and the external surface of
the primary lining is filled with a grout injected through special pipes integrated
in the TBM tailskin. The tailskin is fitted with three rows of wire brush seal
enclosing two grease filled voids that are continually pumped full of grease at
pressure during the operation of the TBM to ensure an effective seal against
ingress of ground water.
A circular waterproofed bolted reinforced concrete segmental lining was
chosen as the primary lining. The external diameter of the primary lining is
6.34m with 30 cm thickness, consisting of 7 segments in addition to a key
191
segment forming each ring. The primary lining has been designed to withstand
75% of overburden and 100% hydrostatic pressure at the maximum depth to axis
of approximately 45 meters. A secondary insitu unreinforced concrete lining with
an internal diameter of 5.100 m was poured to enhance the hydraulic
performance, increase durability and reduce maintenance costs. The secondary
lining has been designed to withstand the full overburden and hydrostatic
pressures. Different aspects of the project are described by Mazen and Craig
(1994); & Esmail (1997).
Fig. (5.1) North Sinai Developing Project (after Mazen and Craig, 1994)
Fig. (5.2) El-Salam Syphon vertical alignment (after Mazen and Craig, 1994)
C
192
5.2.1. Numerical Idealization A numerical analysis was performed to simulate the tunneling conditions
and to estimate the tunneling-induced ground deformation field. The analyzed
section corresponding to instrumented section "C", which is located at the east
shoulder near Ismailia - Port said highway. The monitoring system at this section
consisted of ground surface settlement points distributed along a line
perpendicular to the tunnels centerline (Esmail, 1997).
The analysis commenced with simulation of the construction of the first
tunnel T1 (the tunnel to the north) and ending with excavation of last tunnel T4
(the tunnel to the south). The section lies at a sloping route (1V : 5H). The finite
element model is shown in Fig. (5.3). The mesh incorporates 3094 nodes, 2640
hexahedral elements and 416 interface elements. The analysis stages were carried
out through 480 increments. The nonlinear analysis was performed in a similarly
to Greater Cairo Metro. The geotechnical nonlinear properties of the subsurface
strata are summarized in Fig. (5.4) and Table (5.1).
Table (5.1) The estimated nonlinear properties for El-Salam Syphon at
section “C”
Stratum Very soft to soft CLAY Medium dense to dense SAND
φ 0 33
C (kg/cm2) 2 0
γ (t/m3) 1.7 1.8
ko 1.00 0.46
K 150 350
N 0.55 0.5
Rf 0.75 0.8
υ 0.49 0.3
193
Fig. (5.3) Initial mesh for the inclined El-Salam tunnels
Fig. (5.4) Geotechnical subsurface conditions at the instrumented section “C”
(after Esmail, 1997)
40 m
105 m 48.6 m
T4 T3
T2 T1
Excavated diameter
6.54 m
194
5.2.2. Results of the Numerical Analysis During the analysis, the tunnels were excavated in a sequential order
beginning with T1, then T2, T3 and finally T4. Due to the reported difficulty in
driving the first tunnel, the overcut was estimated to be 1.85% (Esmail, 1997).
Surficial settlement troughs were concluded from the analysis results. The
settlement trough after construction of the first tunnel (T1) is outlined in Fig.
(5.5). The trough is slightly unsymmetrical, due to the variation in the mesh
density, showing a fairly broader values that the reported settlement with a close
agreement above the tunnel. The maximum surficial settlement is about 15mm
above the T1. A wider settlement trough is anticipated after the construction of
all tunnels as shown in Figs. (5.6) to (5.8). The maximum settlement changes to
29 mm after construction of T2, 40 mm after construction of T3 and 48 mm after
construction of T4. Due to the constraint of the available monitoring data, only
the trough of the first tunnel was compared to the analysis results.
The incremental settlement troughs after construction of each tunnel are
shown in Fig. (5.9). The settlement trough of each tunnel is estimated by
subtraction of consecutive troughs resulting from the construction of two
sequential tunnels. The troughs are fairly symmetric yet showing some tendency
to increase towards the newer tunnels. The settlements due to the new tunnels are
always greater than those resulting from older ones.
Considering the individual troughs in Fig. (5.9), we can deduce that the
minimum peak is shown at the trough of T1 with a value of about 15 mm while
the maximum peak of the settlement trough resulting from the construction of T4
is about 21 mm. This difference may be attributed to the overlapping of the
yielding zones of the old and the new tunnels. The maximum total settlement is
located above T3.
195
Fig. (5.5) Surficial vertical deformation after construction of tunnel T1
Fig. (5.6) Surficial vertical deformation after construction of tunnel T2
Distance (m)
Surf
icia
l ver
tical
dis
plac
emen
t (m
m)
Distance (m)
Surf
icia
l ver
tical
dis
plac
emen
t (m
m)
Predicated Measured (after Esmail, 1997)
196
Fig. (5.7) Surficial vertical deformation after construction of tunnel T3
Fig. (5.8) Surficial vertical deformation after construction of tunnel T4
Distance (m)
Surf
icia
l ver
tical
dis
plac
emen
t (m
m)
Distance (m)
Surf
icia
l ver
tical
dis
plac
emen
t (m
m)
197
Fig.
(5.9
) Sur
ficia
l set
tlem
ent t
roug
hs d
ue to
indi
vidu
al tu
nnel
s
198
5.3. Intersection of Al-Azhar Tunnels and the CWO Sewer
Assessment of tunneling effects on the buried utilities is an intricate three-
dimensional problem. Previous studies tried to predict the induced internal
stresses in pipeline due to their intersection with tunnel routing using a simplified
Winkler model (Attewell et al, 1986) or simplified plane strain finite element
model (Ghaboussi et al. 1983).
Attewell et al (1986) elucidated the different measures to be taken to
reduce the effect of tunneling on existing pipelines. Controlling the ground loss
induced by tunneling proves to be the most beneficial measure to reduce the
effect of tunneling to adjacent utilities. Supplementary measures incorporate
increasing the tunnel depth and using ground modification procedures to enhance
the strength parameters and deformation parameters of the soil.
A three-dimensional model is used to analyze the tunneling conditions at
the intersection of Al-Azhar Road Tunnels (excavated diameter 9.40 m and
spaced 18.7 m apart) and the CWO sewer (5 m external diameter) at Port Said
Street. The specific crossing is especially important because tunneling is
designed to pass underneath the CWO sewer with a minimum distance of 4 m.
Precautionary measures to minimize the tunneling effect on the existing CWO
pipe included the reinforcing of the ground underneath the sewer with grout
injection in form of two walls and carrying out intense instrumentation plan
during the TBM passage.
The instrumentation scheme applied at the CWO crossing includes
Settlement Points at shallow depths and Extensometers to provide information
about settlement at different depths. Elevation Reference Points were constructed
on buildings to provide information about building movements. Inclinometers
points were constructed deep in ground to provide information about horizontal
199
movement at selected depths. Fig. (5.10) shows the layout of Al-Azhar Twin
Road Tunnels and site of the intersection near Port Said Street.
5.3.1. Site Geological and Geotechnical Conditions According to the AMBRIC (1983) and Hamza Associates (1998), the
major soil units for zone of the intersection of Al-Azhar and CWO tunnels are as
following:
1. MAN-MADE FILL: The depth of this layer was found to be erratic
in level and ranged between 0.3 and 12.6 m below ground surface
with an average value of 6.66 m. A broad spectrum of grading was
encountered in layer varying from silty clay to gravelly cobbles.
The average texture is clayey, sandy, gravelly silt of intermediate
plasticity (MI).
2. SILTY CLAY AND CLAYEY SILT: This layer follows the man-made
fill with thickness varying between 0 to 17 m. According to the site
investigation reports, this layer extends from depth 6.66 m to depth
11.66 m at the intersection. The layer is logged as gray or brown
and varies in consistency from very soft to very stiff and often
highly fissured. The fissures sometimes contain an infill or dusting
of silt or fine sand. Occasionally slickensiding is reported. The
predominating minerals are intermediate to high plasticity clays (CI
to CH).
3. VERY SILTY SAND: This layer has a fine material (finer than sieve
# 200) that varies between 15% and 35% with a median value of
24%. The layer extends from depth 11.66 m to depth 15 m.
4. SAND: This layer was encountered in the majority of the boreholes.
Clay lenses are found in some boreholes within this layer. In
borehole (210) the layer extends from depth 15 m to depth 20 m
200
(end of borehole). The grading tests showed mostly clean medium
sand (fine materials are less than 5%) with fairly uniform texture.
The mean value of the effective diameter is 0.17 mm.
5. SAND - GRAVEL: This unit may be located as a band or lenses
within the previous layer. The layer lower bound is not defined.
The mean grading of this unit is gravelly, medium to coarse sand.
The average effective diameter is 0.27 mm.
6. The groundwater: The groundwater depth varies from about 3 m to
5 m from the ground surface. At the intersection location, the
ground water depth was reported at 3.40 m
5.3.2. Untreated Ground Analysis
5.3.2.1. The model
The finite elements mesh used in the analysis is shown in Fig. (5.11) with
total of 3421 nodes, 2816 soil elements, 512 lining and grouting elements and
272 joint elements to represent the interface between the soil and lining. The
values of the soil parameters are given in Table (5.2) and Fig (5.12).
Table (5.2) The estimated nonlinear soil properties for the intersection of the
CWO sewer and Al-Azhar Tunnels.
Stratum FILL CLAY –
SILT Silty SAND
Dense
SAND
Gravelly
SAND
φ 23 0 30 35 41
C (kg/cm2) 0.2 1.0 0 0 0
γ (t/m3) 1.65 1.8 1.90 1.95 2.0
ko 1.00 0.74 0.50 0.43 0.35
K 150 200 350 600 750
N 0.6 0.55 0.5 0.5 0.5
Rf 0.73 0.75 0.8 0.8 0.8
υ 0.4 0.4 0.35 0.3 0.3
201
Fig.
(5.1
0) G
ener
al la
yout
of A
l-Azh
ar R
oad
Tunn
els (
afte
r Ram
ond
and
Gui
llien
199
9)
The
inte
rsec
tion
with
the
CW
O
Sew
er
202
Fig. (5.11) Mesh for the intersection
29.1 m
29.8 m
18.7 m
40.0 m
40.0 m 38.0 m
38.0 m
CWO
203
Fig. (5.12) Subsurface conditions at the site of the intersection
(after Hamza Associates, 1998)
5.3.2.2. Results of the Numerical Model
5.3.2.2.1. The maximum stress level field The results of the maximum stress level field are shown in Figs. (5.13)
and (5.14). These figures show a zone of yielded soil in the vicinity of the
tunnels. The significance of this zone was illustrated in the results of the analysis
of the Greater Cairo Metro and El-Salam Syphon. The pre-existence of the north-
tunnel yielding zone before construction of the south tunnel, leads to some bias
in the settlement trough towards the south tunnel in a similar way to El-Salam
Syphon Case
First tunnel Second tunnel
204
5.3.2.2.2. The deformation field The vertical deformation field is shown in Figs. (5.15) and (5.16). The
settlement of the zone far from the CWO crossing (average values from the mesh
edges) shows a fair agreement with the measured trough during driving of the
north tunnel as shown in Fig. (5.17). The settlement trough above the CWO has
less maximum values due to the restraining action of the CWO sewer. The
maximum value of the settlement during driving of the north tunnel is about 4.2
mm but increases to about 9 mm after the south tunnel is completed. The
monitoring data compiled during the construction of the south tunnel was
unavailable during the time of the thesis.
5.3.2.2.3. Effect of the Deformation Field on the CWO Tunnel Construction of Al-Azhar twin tunnels is coupled with surface and
subsurface ground movements as illustrated in the previous section. The resulting
deformation causes potential impairments to the neighboring CWO tunnel
especially as the elevation difference between the CWO invert and the crown of
Al-Azhar Tunnels is only 4m.
The effect of the construction of Al-Azhar Road Tunnels on the
deformation and the internal stresses of the CWO sewer is shown in Figs. (5.18)
to (5.25). The vertical settlement increases from 2.36 mm (as the north tunnel
heading approaches the CWO tunnel) to a final value of 13.7 mm. The axial
compression stress changes from 4 kg/cm2 to 15.6 kg/cm2 and the axial tension
stress changes from 1.84 kg/cm2 to 11.6 kg/cm2. The deformed shape of the
CWO after completion of the south tunnel is shown in Fig. (5.26). It must be
noted that the analysis detects two zones affected by the tensile stresses; namely,
the invert at the intersection zone and the crown beyond the intersection zone,
which corresponds to two conditions of hanging and sagging moments.
205
Fig. (5.13) Maximum stress level after driving the north tunnel
Fig. (5.14) Maximum stress level after driving the south tunnel
206
Fig. (5.15) Vertical deformation in mm after driving the north tunnel
Fig. (5.16) Vertical deformation in mm after driving the south tunnel
207
Fig.
(5.1
7) S
urfic
ial v
ertic
al d
efor
mat
ion
of th
e un
treat
ed g
roun
ds
(Firs
t) (S
econ
d)
208
Fig. (5.18) Vertical deformation of the CWO tunnel in mm
(the north tunnel heading approaches the intersection)
Fig. (5.19) Axial stresses of the CWO tunnel in t/m2
(the north tunnel heading approaches the intersection)
209
Fig. (5.20) Vertical deformation of the CWO tunnel in mm
(the north tunnel is completed)
Fig. (5.21) Axial stresses of the CWO tunnel in t/m2
(the north tunnel is completed)
210
Fig. (5.22) Vertical deformation of the CWO tunnel in mm
(the south tunnel heading approaches the intersection)
Fig. (5.23) Axial stresses of the CWO tunnel in t/m2
(the south tunnel heading approaches the intersection)
211
Fig. (5.24) Vertical deformation of the CWO tunnel in mm
(the south tunnel is completed)
Fig. (5.25) Axial stresses of the CWO tunnel in t/m2
(the south tunnel is completed)
212
Fig. (5.26) Final deformation of the CWO tunnel
(deformation magnification factor 1000)
213
5.3.3. Treated Ground Analysis
5.3.3.1. Motivation
The construction of Al-Azhar Road Tunnels without protective measures
would cause substantial stresses in the CWO sewer located above the twin
tunnel. The selected ground stabilization scheme was to form two grouted walls
on the sides of the sewer tunnel. Grouting proved to be a very salutary process to
minimize the deformation field resulting from tunneling. Tan and Clough (1980)
studied the grouting utilization in tunnels. They enumerated some projects where
injection proved to be a very beneficial practice during construction of tunnels.
Some of these projects are shown in Fig. (5.27).
The effect of grouting can be recognized as increasing the soil stiffness
and shear parameters. During their study, Tan and Clough (1980) provide a scale
of the effect of grouting on sandy soil properties. The scale is shown in Table
(5.3). In this section, the using of grouting as a protective measure to minimize
the effect of the construction of Al-Azhar Tunnels on the CWO sewer is studied
parametrically using the scale proposed by Tan and Clough.
5.3.3.2. Modeling of the grouted material
Bell (1993) showed that the change in the angle of friction (φ) of sandy
soil caused by grouting is generally insignificant. Using Table (5.3), the cohesion
parameter of the grouted soil can be estimated (assuming no change in the
frictional angle of the stabilized soil) using the following equation:
φ
+=
245tan2
qco
ungrouted
…(5.1)
where qun is the unconfined compressive strength of grouted soil. The effect of
grouting on the soil stiffness is implemented sing the ratio SR, defined in Table
(5.3), as following
214
KSRKgrouted ⋅= …(5.2)
where Kgrouted is Duncan and Chang strength parameter for grouted soil and K is
the strength parameter of the ungrouted soil. Grouting may change the state of
stresses inside the soil mass but no quantifiable measurements of this effect was
reported in the literature. The present study ignores such effect and concentrates
on the effect of grouting in increasing strength and stiffness of the grouted soil.
Table (5.3) Grouting effect on the sandy soil parameters for tunneling projects (after Tan and Clough, 1980)
Unconfined compressive strength for
different relative density (t/m2) Grouting
designation Loose Medium Dense
Ratio of stiffness of
grouted to ungrouted
soil (SR)
Weak
Medium
Strong
Very Strong
0.87
2.18
4.35
6.96
1.81
4.57
9.14
14.6
3.84
9.57
19.1
30.6
1.50
2.25
3.50
5.00
Fig. (5.27) The use of grouting in different tunneling projects
(after Tan and Clough, 1980)
215
5.3.3.3. Results of the Numerical Model
Employing the previous formulation of the effect of grouting on sandy soil
strength and stiffness, the deformation and the internal stresses of the CWO
sewer are concluded for different grouting categories. Figs (5.28) and (5.29)
show the final vertical deformation and axial stress of the CWO tunnel for a
stabilized soil employing weak grouting. The maximum deformation reduced
from 13.7 mm to 11.2 mm while the maximum compression reduced from 15.6
to 13.2 kg/cm2 and the maximum tensile stress reduced from 11.6 kg/cm2 to 8.3
kg/cm2.
Increasing the grouting effect reduces the internal stresses and the
deformation furthermore as shown in Figs. (5.30) to (5.35). The maximum
settlement of the CWO is reduced to 8.54 mm using very strong grouting. The
compression stress can be reduced to 12.8 kg/cm2 and tensile stress to 6.2 kg/cm2
using the same grouting category. It should be noted that, at high grouting
categories, the maximum tensile stress is found to occur at the crown;
conversely, at low grouting categories it occurs at the invert.
Figs. (5.36) and (5.37) summarized the effect of grouting on the internal
stresses and the settlement of the CWO sewer. The compression stresses
apparently approaches a limit that cannot be affected by higher stabilization
category other than strong grouting; however, the tensile stress and the settlement
reduced monotonically with increasing the grouting category but with a declining
rate.
The grouting measure proved to be successful by reducing the settlement
by 38% and tensile stress by 47%. Compression stress can only be reduced by
22% yet the most detrimental effect may result from the tensile stresses and the
deformation due to jointed nature of the sewer lining.
216
Fig. (5.28) Final vertical deformation of the CWO tunnel in mm
(weak grouting)
Fig. (5.29) Final axial stresses of the CWO tunnel in t/m2
(weak grouting)
217
Fig. (5.30) Final vertical deformation of the CWO tunnel in mm
(medium grouting)
Fig. (5.31) Final axial stresses of the CWO tunnel in t/m2
(medium grouting)
218
Fig. (5.32) Final vertical deformation of the CWO tunnel in mm
(strong grouting)
Fig. (5.33) Final axial stresses of the CWO tunnel in t/m2
(strong grouting)
219
Fig. (5.34) Final vertical deformation of the CWO tunnel in mm
(very strong grouting)
Fig. (5.35) Final axial stresses of the CWO tunnel in t/m2
(very strong grouting)
220
Ungrou
tedWea
k
Medium
Strong
V. stro
ng
Grouting Category
0
2
4
6
8
10
12
14
16
Stre
ss (k
g/sq
. cm
)
Compression stress Tensile stress
Fig. (5.36) Effect of grouting on the maximum
internal stresses in the CWO sewer
Ungrou
tedWea
k
Medium
Strong
V. stro
ng
Grouting Category
0
2
4
6
8
10
12
14
16
Settl
emen
t (m
m)
Fig. (5.37) Effect of grouting on the maximum
settlement of the CWO sewer
221
Chapter Six
SUMMARY, CONCLUSION AND RECOMMENDATIONS FOR
FURTHER STUDIES
6.1. Summary
Recently, many Egyptian tunnels have been constructed for several
purposes such as subways, sewers and road tunnels. Egyptian tunneling activities
are anticipated to carry on for at least a decade to achieve the proposed plans of
infrastructure refurbishment. The geotechnical conditions encountered during the
construction of these mega projects were typically soft soils or weak rocks under
high groundwater pressures in which tunneling must be conducted using
pressurized shielded tunneling. Soft ground tunneling imposes many engineering
challenges related to stability of the constructed tunnels and the hazard effect of
the resulting deformation field on the buried utilities and the structures in the
proximity of the tunnels. The ground deformations depend on the tunnel
installation procedure, the ground support measures, the soil stiffness in the
tunnel vicinity and ground restraints formed by underground structures.
An indispensable prerequisite to successful tunneling projects is to predict
the deformation in order to avert any potential damage of buildings or buried
utilities. Numerical simulation of tunneling processes is considered the most
appropriate tool for analysis of tunnels as the observational rules-of-thumb
cannot be considered reliable bases of analysis and design even for the same
ground condition as they cannot introduce the installation procedure into account.
Numerous researches employed either plane strain or axisymmetric models in
which the displacement field is approximated by neglecting the non-radial
222
deformations in the plane strain models and the stress and displacement field is
approximated by symmetric fields in axisymmetric models. Two-dimensional
models are superior to the observational rules; yet, the approximations in the
analysis form justifiable basis of unreliability in employing the obtained results
in design and analysis.
Three-dimensional models are intricate to implement because of needed
high capacity computing resources, which are not available beyond certain
academic institutions in the developing countries; besides the complications in
modeling of soil excavation, shield driving, overcutting and tailskin grouting. In
the present research, a nonlinear three-dimensional finite element model is
developed. Different sources of nonlinearly are deliberated; namely, the
nonlinear soil constitutive relationship, which is affected by the stress-path and
confining pressure; pressurized excavation boundaries and ground support
measures; ground loss and the overcutting gap; grouting pressure and hardening
of grouting material with time; and the changes in boundary conditions and size
of the mesh during the analysis, i.e. ground excavation, TBM advancement and
lining installation.
The soil, shield and liner are modeled using hexahedral solid elements
with hyperbolic non-linear behavior according to confining pressure and the
stress path. The shield-soil interface is simulated using a special hyperbolic gap
element with non-trivial tensile stiffness to model appropriately the convergent
behavior of the gap. The liner-grout-soil interface is introduced using grout
elements with incremental time-hardening parameters and initial hydrostatic
pressure equal to the grouting pressure. The tunnel construction process is
modeled by removing the excavated elements from the finite element meshing
and adding the lining elements to the mesh. The residual force vector for the
223
modified mesh is formed using the stresses calculated from previous staged
iteration. The changes are introduced as an incremental-iterative process.
A special nonlinear three-dimensional finite element program was
prepared using the proposed formulation of tunneling construction processes.
The model was applied in analysis of the single shallow bored tunnel of Greater
Cairo Metro - Line 2- Phase 1A at Lot 12 and Lot 16. The results of the
numerical model are compared with the measurements compiled during the
construction of the tunnel. A parametric study was conducted to divulge the
effects of the different tunneling conditions and the ground support measures on
the deformation field and lining stresses. The model was also extended to study
the deformation fields of the multiple deep tunnels of El-Salam Syphon and the
intersection of Al-Azhar Road Tunnels and the CWO sewer at Port Said Street.
The proposed numerical simulation was used to parametrically evaluate the pre-
grouting measure that was undertaken to minimize the effect of tunneling on the
CWO.
6.2. Conclusion
The case histories considered in this thesis, represent diverse tunneling
conditions. The single shallow tunnel of the Greater Cairo Metro was constructed
in the sand deposits while the deep Al-Azhar Twin Road Tunnels are constructed
in gravelly sand. El-Salam Syphon comprises four deep tunnels of smaller
diameter that were constructed in cohesive soft silty clay. The results of the
introduced three-dimensional model, which includes the different features of
bentonite slurry tunneling, soil nonlinearity and the interface conditions were
verified by comparing with field measurements compiled during implementation
of the monitoring program. Fair agreements between the predicated and the
224
measurement were concluded. From the results of the analysis and the parametric
study performed for each case history, the following points are concluded:
Greater Cairo Metro – Line 2 Phase 1A
1. A pronounced upsurge in the maximum stress level (which is
defined as the ratio between the actual deviator stress and the
maximum deviator stress) around the tunnel environs was
perceived. The tunnel vicinity is partially yielded due to the
tunneling activities in which the yielded zone is substantially
revealed at the crown and at the springline. At the invert the stress
level is estimated to be near its pre-tunneling value. Another
yielded zone is shown at the face due to the partial stress release at
the tunnel heading. The face yielded zone is nearly a semi-sphere
while the peripheral yielded zone has an eccentric cylindrical
shape. The presence of the yield zone affects the deformation field
profoundly due to the stiffness degradation around the tunnel. The
effect of the marginal yield zone is frequently considered in the
stability analysis yet its effect is underestimated in the deformation
analysis in the tunneling literature.
2. Due to its three-dimensional temperament, the model provides the
deformation field ahead, at, and after the passage of TBM. The
surficial settlement above the TBM face is estimated to be about
40% of the maximum settlement. The longitudinal settlement
trough extends to a distance of about 2.5 times the excavated
diameter of the tunnel before the TBM heading and about 5 times
the excavated diameter behind the TBM face.
225
3. The vertical stress shows a relaxation trend towards the tunnel’s
crown and the invert. The stress above the crown has a uniform
trend resulting from the arching effect that mitigates the overburden
soil. The reduction in vertical stress however is more significant
below the invert, however a minor heave is indicated due to the
elastic nature of the tunnel peripheral underneath the invert. The
major and the minor principal stresses show some decrease around
the tunnel while the intermediate stress is almost unaltered due to
the adjacent tunneling process.
4. The lining assumes an oval shape during the stage of its interaction
with the enfolding ground. The invert heave and the crown
settlement are generally greater than the springline outward
deformation. The crown settlement increases with the distance from
the tail. Deformation mode far from the TBM tail is characterized
with less invert heave compared to the crown settlement. The
springline deformation decreases vaguely to smaller values with the
increase of the time of installation.
5. The thrusting force is the major straining action in the lining. The
moment is very small and may be justifiably neglected.
Consequently, no special modeling is needed to account for the
segmental nature of the lining. The maximum thrust occurs at the
springline following the assumption of inconsequential arching. A
minor reduction of the stress occurs at the invert and a trivial
increase at the springline and at the crown. The tunnel is classified
as a shallow tunnel in which the arching effect is small. The axial
force at the crown is unexpectedly larger than the force at the invert
due to the friction between the lower part of the lining and
surrounding elastic soil. A much less friction is anticipated at the
226
upper half of the lining as a result of the relatively low overburden
and the higher tendency to yield.
6. The effective limiting face pressure is about 40% of the effective
active pressure, which is known to be the minimum principal stress
for the far field. The difference between the estimated limiting face
pressure and active earth pressure of the insitu stresses results from
the arching effect which occurs due to stiffness degradation in the
yielded zone near the face. Adapting a safety factor of 2, the
analysis shows that 80% of active earthpressure can be a good
estimate of the safe face pressure in case of shallow tunnels.
7. Increasing the face pressure furthermore will cause some heave in
front of the TBM that can slightly reduce the maximum settlement
by the same amount. On the other hand, the effective slurry
pressure causes outward flow pattern from the slurry chamber to
the ground in the vicinity of the face. This flow tendency helps to
form the bentonite cake at the excavated face and reduces the effect
of any seepage towards or away from the face. This explains the
minimal increase in the water pressure observed during the tunnel
construction.
8. The width of the settlement trough at Lot 12 increases by about 3.5
times with the increase of the radial loss from nil to 1%
respectively. This result contradicts the common rules-of-thumb
that relate the width of the settlement trough to the geometrical
configuration only.
9. The settlement distribution above the crown is more or less
constant to about 80% of the soil cover above the tunnel for low
overcutting losses (less than 0.5%) then a sudden increase occurs
227
due to the development of weak plastic zone above the crown. A
decrease in the settlement is estimated near the tunnel crown due to
the effect of the tail grouting. The ratio between the surface
settlement and crown settlement for overcutting losses smaller than
0.5% is generally less than unity due to the tail grouting. The ratio
increases above unity for cases above 0.5% (about 1.35 at 1.00%
overcutting loss).
10. The heave below the invert decreases by 50% when increasing the
overcutting losses from nil to 1%. The difference is localized in the
top 2 m below the invert where sudden increase is observed in low
overcutting losses.
11. The effect of tailskin grouting pressure was studied parametrically.
The crown experiences settlement at grouting pressure up to the
overburden pressure; however, the deformation turns to heave at
higher grouting pressures. The invert undergoes heave that is
almost insensitive to the grouting pressure. This development may
be attributed to the existence of plastic zone around the tunnel
especially at the crown neighborhood causing the soil to compress
locally without affecting the ground surface. At the invert, the
ground behaves elastically so that the effect of the grouting
pressure is minimal due to the relatively high confining pressure
and consequently high unloading-reloading modulus.
12. The grouting pressure can be interpreted as a mean to consolidate
the grout especially in the high permeability medium around the
tunnel provided by the sandy deposits; thus increasing the stiffness
of the annular tail void and decrease the possible ground loss at the
tail. However, tail grouting is not adequate measure against losses
that have already taken place before its application, as the surface
228
settlement trough is affected subtlety due to the presence of the
plastic zone around the tunnel.
13. The control of the surface and subsurface ground deformations in
Greater Cairo Metro is attributed to low peripheral overcutting
(about 0.15%) and swift application of the tail grouting at the tail of
the TBM.
Multiple Tunnels
El-Salam Syphon and Al-Azhar Twin Road Tunnels
1. The troughs of the four tunnels of El-Salam Syphon are fairly
symmetric yet showing some tendency to increase towards the
newer tunnel due to the interference of the developed plastic zones.
The minimum peak is shown at the trough of the first tunnel while
the maximum peak of the settlement trough resulting from the
construction of the fourth tunnel is about 40% greater than the first
peak. The maximum total settlement is located above the third
tunnel. Similarly, the existence of the Al-Azhar North tunnel
yielding zone before construction of the South tunnel, leads to
greater settlement above the newer tunnel.
2. The crossing of Al-Azhar Twin Road Tunnels and the CWO sewer
was assessed as the construction of Al-Azhar tunnels may cause
impairments to the neighboring CWO tunnel especially as the
elevation difference between the CWO invert and the crown of Al-
Azhar Tunnels is only 4m. The model provided the evolution of the
229
deformations and the internal stresses in the CWO during Al-Azhar
tunnels construction for untreated and pretreated grounds. The
vertical settlement increases by about 6 times as the north tunnel
heading approaches the CWO tunnel to its final value considering
the untreated ground condition; the axial compression stress
changes also by 4 times and the axial tension stress changes by 6
times of the values estimated as the north tunnel approaches the
crossing. The analysis detects two zones affected by the tensile
stresses; namely, the invert at the intersection zone and the crown
beyond the intersection zone, which corresponds to two conditions
of hanging and sagging moments.
3. Increasing the grouting effect reduces the internal stresses and the
deformation. At high grouting categories, the maximum tensile
stress is found to occur at the crown; conversely, at low grouting
categories it occurs at the invert. The compression stresses
apparently approach a limit that cannot be affected by higher
stabilization category other than strong grouting; however, the
tensile stress and the settlement reduced monotonically with
increasing the grouting category but with a declining rate.
4. The results of the intersection of Al-Azhar Road Tunnels and CWO
show that grouting proved to be a salutary process to control the
deformation and the internal forces (especially tensile stresses)
developed in underground structures due to tunneling. Grouting
reduces the settlement by 38% and tensile stress by 47%.
Compression stress can only be reduced by 22%.
General Conclusion
230
1. Comparing the results of the proposed numerical three-
dimensional idealization of the Bentonite Slurry Tunneling
with the field measurements compiled during the
construction of three major tunnel projects constructed in
Cairo indicated the capability of such sophisticated
modeling to develop realistic pattern of ground subsidence
associated with tunneling. Practicing the proposed numerical
model to the Greater Cairo Metro, El-Salam Syphon and Al-
Azhar tunnels confirmed precise results of the proposed
numerical model. The results implied that, simulating the
details of tunneling operation through the modeling
formulation is considered as the basis for an optimum
tunneling idealization. Adapting the main factors affecting
the pressurized bentonite slurry tunneling such as; unloading
forces due to excavation, ground nonlinearity, interface
condition, engineering properties of shield, rate of advance,
machine overcutting, face pressure, yielding zones and the
tail grouting, are needed for realistic updating of the ground-
tunneling interaction.
2. The three-dimensional tunneling analysis is considered as
the entirely capable arrangement to simulate very
sophisticated problems such as twin and multiple tunnels
and the intersection of different tunnels that cannot be
preceded by means of two-dimensional analysis or empirical
approach superposition. Consequently, the deformations and
the internal forces developed in underground pipelines and
sewers due to tunneling can be estimated.
231
3. The principle of tunneling analysis considering the Gap
Parameter Approach is very dependent on the amount of the
machine overcutting; hence, the application of the machine
overcutting in such models must be treated very carefully to
sustain a realistic ground subsidence.
4. The overcutting losses influence, to a great extent, the
pattern of ground deformation associated with tunneling.
The ground loss measures are less efficient in reducing the
amount of surficial deformation if considerable overcutting
losses are incorporated due to the constitutive nature of soils
to resist reversed stress-path than to continue straining in the
same path.
5. Updating the tailskin grout hardening strength characteristics
around the tunnel lining is considered a main item in a good
tunneling idealization of the ground-lining-gap interaction to
obtain realistic results.
6. The state-of-art bentonite slurry tunneling technology that
was employed in Greater Cairo Metro and Al-Azhar Road
Tunnels, is considered as a very powerful technique to
provide the required stability measures for large diameter
tunnels driven in the Cairo geotechnical conditions, which
are generally described as pervious or semi-previous soft
soils under high groundwater pressure. The elements of
tunnel construction such as machine overcutting, face
pressure, lining erection and tailskin grouting provided
stable tunneling conditions characterized with high rate of
advance and minimum ground subsidence.
232
6.3. Recommendations for Further Studies The following aspects are recommended for research as an augmentation to
the present work:
1. Determination of the mechanical properties of tailskin grouting by
testing it under conditions that are similar to those prevailing in the
proximity of tunnels and not by using laboratory-prepared
specimens.
2. The flow of the water to or from the tunnel and its potential effects
on the ground stability and tunneling functionality.
3. The effect of injection on the state of stress of the ground to
provide basis for simulation of the pre-grouting processes to control
the deformation fields in neighborhood of newly constructed
tunnels.
4. Time dependent effects (creep and consolidation) of the cohesive
soil for multiple and twin tunnels.
5. The use of neurofuzzy and soft computing models as an alternative
to currently employed deterministic simulations.
6. The dynamic nature of the traffic loads inside urban subway and
road tunnels and their effects on surrounding structures.
233
REFERENCES AND BIBLIOGRAPHY
1.Abdel-Rahman, A. H., 1993, “Numerical Modelling of Concrete Diaphragm
Walls", M. Sc. Thesis, Ain Shams University, Cairo, Egypt.
2.Abdrabbo, E. M., Abd El-Lateef, H. A., and El-Nahhas, F. M., 1998,
"Effect of Tunneling on Adjacent Structures", Proc. of the 8th International
Congress, International Association for Engineering, Geology and
Environment, Vancouver, Canada.
3.Abu-Krisha, A. A., 1998, "Numerical Modeling of TBM Tunnelling in
Consolidated Clay", Ph. D. Thesis, Thesis, University of Innsbruck,
Austria.
4.Adashi, T., Yashima, A. and Kojima, K., 1991, "Behaviour and Simulation
of Sandy Ground Tunnels", Developments in Geotechnical Aspects of
Embankments, Excavation and Buried Structures, Edited By
Balasubramaniam A. S. et al., Balkema, Rotterdam, Netherlands, pp.291-
329.
5.Ahmed, A. A., 1991, "Interaction of Tunnel Lining and Ground", Ph. D.
Thesis, Ain Shams University, Cairo, Egypt.
6.Ahmed, A. A., 1994, "Analysis of Deck Road Tunnels", Proc. of
International Congress on Tunneling and Ground Conditions, ITA., Cairo,
Published by Balkema, Netherlands, pp. 469-476.
7.Ahmed, A. A., 2000, "Study on the Stability of Submerged Tunnels",
Scientific Bulletin, Vol. 35, No. 1, Ain Shams University, Faculty of
Engineering, pp. 27-41.
8.Ali, M. A. I., 1990, "Analysis of Shallow Soft Ground Tunnels", M. Sc.
Thesis, Ain Shams University, Cairo, Egypt.
234
9.AMBRIC, 1983, "Contract No. 4, Tunnels- Souk El Samak to Abdeen:
Geotechnical Information", Vol. 3, Ministry of Reconstruction and State for
Housing and Land Reclamation, Organization for the Execution of the
Greater Cairo Wastewater Project.
10.Ardaman-ACE, 1991, "Updating of Studies, Contract 21/M, Design Stage,
Phase 1, Geotechnical Report", Greater Cairo Metro, NAT, DS-01-L-T2.
11.Atkinson, J. H., Brown, E. T. and Potts, D. M., 1975, "Subsidence above
Shallow Tunnels in Soft Grounds", J. of Soil Mech. And Found. Div.,
ASCE, Vol. 103, GT9, pp. 307-325.
12.Atkinson, J. H. and Mair, R. J., 1981, "Soil Mechanics Aspect of Soft
Ground Tunnelling", Ground Engineering, Vol. 14, No. 5, pp. 20-28,
quoted from Thomson (1995).
13.Attewell, P., Yeates, J. and Selby, A., 1986, "Soil Movements Induced by
Tunnelling and Their Effects on Pipielines and Structures", Blackie & Sons
Ltd., Glasgow.
14.Augarde, C. E., 1997, "Numerical Modelling of Tunneling Processes for
Assessment of Damage to Structures", Ph. D. Thesis, University of Oxford.
15. Axelsson, O. and Baker, V., 1984," Finite Element Solution of Boundary
Value Problem: Theory and Computation", Academic Press Inc., Orlando.
16.Bejerrum, L., 1963, "Discussion on 'Proceeding of the European
Conference on Soil Mechanics and Foundation Engineering", Vol. III,
Publication No. 98, NGI, Oslo, Norway, quoted from Boone (1997).
17.Bell, F. G., 1993, "Engineering Treatment of Soils", E & FN SPON,
London, UK.
18.Bentler, D. J., 1998, "Finite Element Analysis of Deep Excavation", Ph. D.
Thesis, Virginia Polytechnic Institute and State University,Dept. of Civil
Engineering, USA.
19.Boscardin, M. D. and Cording, E. J., 1989, "Building Response to
235
Excavation-Induced Settlement", J. of Geotech. Eng., ASCE, Vol. 115, No.
1, pp. 1-21.
20.Broms, B. B. and Bennermark, H., 1967, "Stability of Clay at Vertical
Openings", J. of Soil Mechanics and Foundation Div., ASCE, Vol. 93,
SM1, pp. 71-94.
21.Broone, J. S., 1997, "Ground-Movement-Related Building Damage", J. of
Geotech. Eng., ASCE, Vol. 122, No. 11, pp. 886-896.
22.Brown, E. T., Bray, J. W., Ladanyi, B. and Hoek, E., 1981, "Ground
Response Curves for Rock Tunnels", J. of Geotechnical Engineering Div.,
ASCE, Vol. 109, No. 1, pp. 15-55.
23.Bulson, P. S., 1985, "Buried Structures: Static and Dynamic Strength",
Chapman and Hall, London.
24.Burland, J. B. and Wroth, C. P., 1975, "Settlment of Buildings and
Associated Damage", Build. Res. Establishment Current Paper, 33(75),
Building Research Establishment, Watford, England, quoted from Broone
(1997).
25.Burns, J. Q. and Richard, R. M., 1964, "Attenuation of Stresses for Buried
Cylinders", Proc. on Symposium on Soil-Structure Interaction, Tucson, pp.
378-392, quoted from O'Rouke (1984).
26.Butler, R. A. and Hampton, D., 1975, "Subsidence Over Soft Ground
Tunnel", J. of Geotech. Eng., ASCE, Vol. 105, No. 4, pp. 499-518.
27.Campenon Bernard-SGE, 1999, "Tunneling at the CWO Crossing, Results
of Montoring", El Azhar Road Tunnels Project, Detailed Design, NAT.
28.Chan, D., 1989, "SAGE: A Computer Program for Stress Analysis in
Geotechnical Engineering", Dept. of Civil Engineering, University of
Alberta, Edmonton, Alberta, T6G 2G7.
29.Chan, D., 1996, "Numerical Analysis of Soil Deformation in Geotechnical
Engineering", 7th ICSGE, Ain Shams University, Cairo, pp.147-186.
236
30.Chen, L. T., Poulos, H. G. and Loganathan, N., 1999, "Pile Responses
Caused by Tunneling", J. of Geotech. and Geoenvir. Eng., ASCE, Vol. 125,
No. 3, pp. 207-215.
31.Chen, W. F. and Mizuno, E., 1990, "Nonlinear Analysis in Soil Mechanics;
Theory and Implementation", Developments in Geotech. Eng., Elsevier,
Amsterdam, Netherlands.
32.Chew, L., 1994, "The Prediction of Surface Settlements due to Tunneling
in Soft Ground", M. Sc. Thesis, University of Oxford, quoted from
Augrade(1997).
33.Clough, J. W. and Leca, E., 1993, "EPB Shield Tunneling in Mixed Face
Conditions", J. of Geotech., ASCE, Vol. 119, No. 10, pp. 1640-1656.
34.Clough, J. W., Sweeney, B. P. and Finno, R. J., 1983, "Measured Soil
Response to EPB Shield Tunneling", J. of Geotech. Eng., ASCE, Vol. 109,
No. 2, pp. 131-149.
35.Cook, R. D., Malkus, D. S. and Plesha, M. E., 1989, "Concepts and
Applications of Finite Element Analysis", 3rd Ed., John Wiley and Sons.
36.Cording, E. J. and Hansmire, W. H., 1975, "Displacement Around Soft
Ground Tunnels", General Report, Proc. of the 5th Pan-American Conf. on
SMFE, Buenos Aires, Argentina, Vol. 4, pp. 571-633, quoted from El-
Nahhas (1980).
37.Curtis, D. J., Mott, Hay & Croydon, A., 1976, Correspondence on Wood
M., "The Circular Tunnels in Elastic Ground", Geotechnique, March,
quoted from Ebaid and Hammad (1978).
38.Curtis, D. J. and Rock, T. A., 1977, "Tunnel Lining – Design?", Computer
Methods in Tunnel Design, The Institution of Civil Engineers, London, pp.
175-182.
39.Deere, D. U., Peck, R. B., Monsees, J. E. and Schmidt, B., 1969, "Design
of Tunnel Liners and Support Systems", Report prepared for US
Department of Transportation, NTIS NO. PB 183 799, quoted from El-
237
Nahhas (1980).
40.Desai, C. S. and Abel, J. F., 1972, "Introduction to The Finite Element
Method", Van Nostrand Reinhold Co., NY, USA.
41.Dessouki, A. K., 1985, "Stability of Soil-Steel Structures", Ph. D. Thesis,
Dept. of Civil Engineering, University of Windsor, Ontario, Canada.
42.Duncan, J. M., 1996, "State-of-the-art: Limit Equilibrium and Finite
Element Analysis of Slopes", J. of Geotech. And Geoenvir. Eng., ASCE,
Vol. 122, No. 7, pp. 577-596.
43.Duncan, J. M., Bentler, D. J., Morrison, C. S. and Esterhuizen, J. J. B.,
1998, "SAGE User's Guide: A Finite Element Program for Static Analysis
of Geotechnical Engineering Problems", Virginia Polytechnic Institute and
State University,Dept. of Civil Engineering, USA.
44.Duncan, J. M., Byrne, P., Wong, K. S., Mabry, P., 1980, “Strength, Stress-
Strain and Bulk Modulus Parameters for Finite Element Analysis of
Stresses and Movements in Soil Masses”, Report No. UBC/GT/80-01,
University of California, quoted from Chan (1989).
45.Duncan, J. M. and Chang, C. Y., 1970, "Nonlinear Analysis of Stresses and
Strains in Soils", Journal of Soil Mech. And Found. Div., ASCE, Vol. 96,
No. SM5, pp. 1629-1653.
46.Duncan, J. M., Seed, R. B. Wong, K. S. and Ozawa, Y., 1984,
"FEADAM84, A Computer Program for Finite Element Analysis of Dams",
Virginia Polytechnic Inst. and State University, Dept. of Civil Engineering,
USA.
47.Ebaid, G. S., 1978, "Effect of Joints on Circular Tunnel Design", The
Bulletin of the Faculty of Engineering - Ain Shams University, No. 9, pp.
C11/1-C11/21.
48.Ebaid, G. S. and Hammad, M. E., 1978, "Some Aspects of the Design of
Circular Tunnels", Bulletin of the Faculty of Engineering, Ain Shams
University, No. 8, C83-C104.
238
49.Einstein, H. H. and Schwarz, C. W., 1979, "Simplified Analysis for Tunnel
Supports", J. of Geotech. Eng., ASCE, Vol. 105, No. 4, pp. 499-518.
50.Eisenstein, Z. and Ezzeldine, O., 1994, "The Role of Face Pressure for
Shields with Positive Ground Control", Proc. of the Int. Congress on
Tunnelling and Ground Conditions, Cairo, pp. 557-571.
51.Eisenstein, Z. and Negro, A., 1985, "Comprehensive Design Method for
Shallow Tunnels", Proc. Underground Structures in Urban Areas, ITA,
Praug, Vol. 1, pp.375-391.
52.El-Nahhas, F., 1980, "The Behaviour of Tunnels in Stiff Soils", Ph. D.
Thesis, Alberta University, Edmonton, Canada.
53.El-Nahhas, F. M., 1986, "Spatial Mode of Ground Subsidence above
Advancing Shielded Tunnels", Proc. of Int. Congress on Large
Underground Openings, Firenze, Italy, pp. 720-725.
54.El-Nahhas, F. M., 1991, "Ground Settlement Above Urban Tunnels
Constructed using Bentonite Slurry Machines", Proc. of the Int. Symposium
on Tunneling in Congested Cities, Cairo, pp. 61-74.
55.El-Nahhas, F. M., 1994, "Some Geotechnical Aspects of Shield Tunneling
in Cairo Area", Proc. of International Congress on Tunneling and Ground
Conditions, ITA., Cairo, Published by Balkema, Netherlands.
56.El-Nahhas, F. M., 1999, "Soft Ground Tunnelling In Egypt: Geotechnical
Challenges and Expectations", Tunnelling and Underground Space
Technology, Vol. 14, No. 3, pp. 245-256.
57.EM 1110-2-1908, 1995, "Instrumentation of Embankment Dams and
Levees", Washington D.C., Corps of Engineers, USA.
58.EM 1110-2-2901, 1997, "Tunnels and Shafts in Rock", Washington D.C.,
Corps of Engineers, USA.
59.Esmail, K. A., 1997, "Numerical Modeling of Deformation around Closed
Face Tunneling", Ph. D. Thesis, Ain Shams University, Cairo, Egypt.
239
60.ETL 1110-2-544, 1995, "Geotechnical Analysis by the Finite Element
Method", Washington D.C., Corps of Engineers, USA.
61.Ezzeldine, O. Y., 1995, "Design of Tunnels Constructed using Pressurized
Shield Methods", Ph. D. Thesis, University of Alberta, Canada.
62.Ezzeldine, O. Y., 1999, "Estimation of the Surface Displacement Field due
to Construction of Cairo Metro Line, El Khalafawy - St. Therese",
Tunnelling and Underground Space Technology, Vol. 14, No. 3, pp. 267-
279.
63.Finno, R. J. and Clough, G. W., 1985, "Evaluation of Soil Response to EPB
Shield Tunneling", J. of Geotech. Eng., ASCE, Vol. 111, No. 2, pp. 155-
173.
64.Flint, G. R., 1994, "Ameria Tunnel Junction using Freezing Technique",
Proc. of International Congress on Tunneling and Ground Conditions, ITA.,
Cairo, Published by Balkema, Netherlands, pp. 117-126.
65.Ghaboussi, J. and Gioda G., 1977, "On the Time-dependent Effect in
Advancing Tunnels", Int. J. for Numerical and Analytical Methods in
Geomechanics, Vol. 1, pp. 249-269.
66.Ghaboussi, J., Hansmire, W. H. and Harvey, P. W., 1983, "Finite Element
Simulation of Tunneling over Subways", J. of Geotechnical Engineering,
ASCE, Vol. 109, No. 3, pp. 318-334.
67.Gloosop, N. H., 1977, "Soil Deformations Caused by Soft Ground
Tuneelling", Ph. D. Thesis, University of Durham, UK, quoted from
Thomson (1995).
68.Grant, R., Christian, J. and Vanmarcke, E., 1975, "Differential Settlement
of Buildings", J. of Geotech. Eng., ASCE, Vol. 100, No. GT9, pp. 973-991.
69.Gunn, M. J., 1993 "The Prediction of Surface Settlement Profiles due to
Tunneling", Predictive Soil Mechanics, Proc. of the Wroth Memorial
Symposium, St. Catherine College, Oxford, UK.
240
70.Hamdy, U., 1989, "Deformation Analysis of Tunnels in Stiff Cohesive
Soils", M. Sc. Thesis, Ain Shams University, Cairo, Egypt.
71.Hammad, M. E., 1977, "Subgrade Reaction in U-Shaped Tunnels", J. of the
Egyptian Society of Engineers, Vol. XYI, No. 4, pp. 64-72.
72.Hammad, M. E., 1978, "Design of Circular Syphons Bored in Elastic
Ground", Bulletin of the Faculty of Engineering, Ain Shams University,
No. 9, C3/1-C3/12.
73.Hamza Associates, 1993, "Greater Cairo Metro Line 2, Shobra El Kheima
to Giza, Phase 1, Recommended Geotechnical Properties", Geotechnical
Report, NAT.
74.Hamza Associate, 1995, "Greater Cairo Metro: Phase (2) Tunnel
Monitoring", Comprehensive Report.
75.Hamza Associates, 1998, "Al Azhar Road Tunnel; Port Said, Al Azhar &
El Mosky Street", Geotechnical Report, NAT.
76.Hansmire, W. H. and Cording, E. J., 1985, "Soil Test Section: Case History
Summary", J. of Geotech. Eng., ASCE, Vol. 111, No. GT11, pp. 1301-
1320.
77.Herrenknecht, M. and Maidl, B., 1994, "Transferring the European
Experience Using Mix-shields for the Employment in Cairo", Proc.of the
Int. Congress on Tunneling and Ground Conditions, Cairo, pp. 333-337.
78.Hoek, K., 1968, "Stresses Against Underground Structural Cylinders", J. of
Soil Mech. and Found. Div., ASCE, Vol. 94, No. SM4, pp. 833-858.
79.Hosny, A. and El-Nahhas F., 1994, "Role of Geotechnical Monitoring in
Quality Management of Tunnelling Projects", Proc. of International
Congress on Tunneling and Ground Conditions, ITA., Cairo, Published by
Balkema, Netherlands, pp. 587-591.
80.Iftimie, T., 1994, "Prefabricated Lining, Conceptional Analysis and
Comparative Studies for Optimal Solution", Proc. of International Congress
241
on Tunneling and Ground Conditions, ITA., Cairo, Published by Balkema,
Netherlands, pp. 339-346.
81.Janbu, N., 1963, “Soil Compressibility as Determined by the Oedometer
and the Triaxial Tests”, Proc. European Conf. on SMFE, Wiesbaden, Vol.
1, pp. 19-25, quoted from Ahmed (1991).
82.Jenny, R. J., 1983, "Compressed Air Use in Soft Ground Tunneling", ", J.
of Const. Eng. and Man., ASCE, Vol. 109, No. 2, pp. 206-213.
83.Jones, S. J. and Brown, R. E., 1978, "Temporary Tunnel Support by
Artificial Ground Freezing", J. of Geotech. Eng., ASCE, Vol. 104, GT10,
pp. 1257-1276.
84.Joyce, M. C., 1982, "Site Investigation Practice", J. W. Arrowsmith Ltd,
Bristol, UK.
85.Kaiser, P. K., 1981, "Effect of Stress History on the Deformation
Behaviour of Underground Openings", 13th Canadian Rock Mechanics
Symposium, pp. 133-140, quoted from Ahmed (1991).
86.Korbin, G. and Brekke, L., 1978, "Field Study of Tunnel
Prereinforcement", J. of Geotechnical Engineering Div., ASCE, Vol. 104,
No. GT8, pp. 1091-1108.
87.Kuesel, T. R., 1996, "Tunnel Stabilization and Lining", In "Tunnel
Engineering Handbook", Chapman & Hall Publishing Co., NY,US, pp. 80-
96.
88.Loganathan, N. and Poulos, H. G., 1998, "Analytical Prediction for
Tunneling-Induced Ground Movements in Clays", J. of Geotech. and
Geoenvir. Eng., ASCE, Vol. 124, No. 9, pp. 846-856.
89.Lombardi, G., 1970, "The Influence of Rock Characteristics on the
Stability of Rock Cavities", Tunnels and Tunneling, Vol. 2, pp. 104-109,
quoted from El-Nahhas (1980).
90.Lombardi, G., 1973, "Dimensioning of Tunnel Linings with Regards to
242
Constructional Procedure", Tunnels and Tunneling, Vol. 5, pp. 340-351 ,
quoted from El-Nahhas (1980).
91.Maidl, B. and Hou, X., 1990, "Field Measurement of Ground Movements
and Variations of Pore Water Pressure Caused by EBP Shield
Construction", Tunnel and Underground Works Today and Future, Proc. of
the Int. Congress, ITA Annual Meeting, pp.335-347.
92.Mair, R. and Taylor R. , 1993, "Prediction of Clay Behaviour around
Tunnels using Plasticity Solutions", Predictive Soil Mechanics (Proc.,
Worth mem Symp.), Thomas Telfor, pp. 449-463.
93.Mansour, M., 1996, "Three-Dimensional Numerical Modelling of
Hydroshield Tunneling", Ph. D. Thesis, University of Innsbruck, Austria.
94.Matsumoto Y. and Nishioka, T., 1991, Theoretical Tunnel Mechanics",
Tokyo University, University of Tokyo Press.
95.Mazen, A. and Craig, R., 1994, "El-Salam Syphon under Suez Canal",
Proc. of the Int. Congress on Tunnelling and Ground Conditions, Cairo, pp.
181-186.
96.Monsees, J. M., 1996, "Soft Ground Tunneling", in "Tunnel Engineering
Handbook", Chapman & Hall Publishing Co., NY, USA, pp. 97-121.
97.Morgan, H. D., 1961," A Contribution to the Analysis of Stress in a
Circular Tunnel", Geotechnique, Vol. 11, pp. 37-46.
98.Muir Wood, A. M., 1975, "The Circular Tunnel in Elastic Ground",
Geotechnique, Vol. 25, pp. 115-127.
99.Murray, R. T., 1990, "Rapporteur's paper", Geotechnical Instrumentation in
Practice, Proceedings of the conference of geotechnical instrumentation in
civil engineering projects, Thomas Telford, London, England, pp 75-85.
100.Nomoto, T., Imamura, S., Hagiwara, T., Kusakabe, O and Fujii, N, 1999,
"Shield Tunnel Construction in Centrifuge", J. of Geotech. and Geoenv.
Eng., ASCE, Vol. 125, No. 4, pp. 289-300.
243
101.O'Rouke, J. E., 1979, "Soil Stress Measurement Experiences", J. of
Geotech. Eng., ASCE, Vol. 104, No. GT12, pp. 1501-1514.
102.O'Rouke, T. D., 1984, "Guidelines for Tunnel Lining Design", the
Technical Committee on Tunnel Lining Design of the Underground
Technology Research, ASCE.
103.O'Reilly, M., Mykes, P and New, B. M., 1982, "Settlements Above
Tunnels in the United Kingdom - Their Magnitude and Prediction", Proc. of
Tunneling' 82 Symposium, IMM, London, 1982, quoted from Atewell et al.
(1986).
104.Orr, T. L., Atkinson, C. P., Wroth, C. P., 1978, "Finite Element
Calculation for the Deformation Around Model Tunnels", Computer
Methods in Tunnel Design, The Institution of Civil Engineers, London, pp.
121-144.
105.Otsuka, T. and Kamel, I. A., 1994,"Rehabilitation of Ahmed Hamdy
Tunnel under Suez Canal – Part 1, Study and Design",Proc. of International
Congress on Tunneling and Ground Conditions, ITA., Cairo, Published by
Balkema, Netherlands, pp. 601-608.
106.Owen, D. R. and Hinton, E. H., 1980, "Finite Element in Plasticity:
Theory and Application", Pineridge Press Ltd., Swansea, UK.
107.Pacher, F., 1964, "Measurements of Deformation in a Test Gallery as a
Means of Investigating the Behaviour of the Rock Mass and of Specifying
Lining Requirements", Rock Mechanics and Engineering Geology,
Supplement I, pp. 146-161, quoted from El-Nahhas (1980).
108.Palmer, J. H. L. and Belshaw, D. J., 1978, "Deformations and Pore
Pressures in the Vicinity of a Precast, Segmented, Concrete-Lined Tunnel
in Clay", 31st Canadian Geotechnical Conference, Winnipeg, Alta., pp.174-
184.
109.Peck, R. B., 1969, "Deep Excavation and Tunneling in Soft Ground",
State-of-the-Art, Proceeding of the 7th International Conference on Soil
244
Mechanics and Foundation Engineering, Mexico City, Mexico, pp. 225-
290.
110.Peck, R. B., Hendron, Jr., A. J. & Mohraz, B., 1972, "State-of-the-Art of
Soft Ground Tunnelling" Proceedings of the 1st North American Rapid
Excavation and Tunneling Conference, Vol. 1, pp. 259-286.
111.Pullan, A., 1998, "FEM/BEM Notes", Dept. of Engineering Science, The
University of Auckland, New Zealand.
112.Rabcewicz, L. V., 1964, "The New Austrian Tunneling Method", Water
Power, Vol. 16, pp. 453-457, quoted from El-Nahhas (1980).
113.Rabcewicz, L. V., 1965, "The New Austrian Tunneling Method", Water
Power, Vol. 17, pp. 511-515, quoted from El-Nahhas (1980).
114.Ramond, P. and Guillien, S., 1999, "El Azhar Road Tunnels", Tunneling
and Underground Space Technology, Elsevier Science Ltd., Vol. 14, No. 3,
pp. 291-317.
115.Ranken, R. E. and Ghaboussi, J., 1975, "Tunnel Design Considerations:
Analysis of Stresses and Deformations Around Advancing Tunnels",
Report prepared for US Deportment of Transportation, UILU-ENG75-2016.
116.Richards, D. P., Ramond, P. and Herrenkenecht, M., 1997, "Slurry Shield
Tunnels on the Cairo Metro", General Report, RETC, Las Vegas, USA.
117.Rowe, R. K., Lo, K. Y. and Kack, G. J., 1983, "A Method of Estimating
Surface Settlement above Tunnels Constructed in Soft Grounds", Can.
Geotech. J., Vol. 20, pp. 11-22.
118.Sagaseta, C., 1987, "Analysis of Undrained Soil Deformation due to
Ground Loss", Geotechnique, Vol. 36, No. 3.
119.Saitoh, A., Gomi, K. and Shiraishi, T., 1994, "Influence Forecast and
Field Measurement of a Tunnel Excavation Crossing Right Above Existing
Tunnels", Proc. of International Congress on Tunneling and Ground
Conditions, ITA., Cairo, Published by Balkema, Netherlands, pp. 83-90.
245
120.Schmidt, B., 1969, "Settlement and Ground Movement Associated with
Tunneling in Soil", Ph. D. Thesis, University of Illinois, Urbana, Illinois,
USA.
121.Shalaby, A. G., 1990, "Behavior of tunnels in some Egyptian Soils", Ph.
D. Thesis, Ain Shames University, Cairo, Egypt.
122.Shata, A. A., 1988, “Geology of Cairo, Egypt”, Bulletin of the
Association of Engineering Geologists, Vol. XXV, No. 2, pp. 149-183.,
quoted from Richards (1997).
123.Shi, J., Ortigao, J. A. R. and Bai, J., 1998, "Modular Neural Networks for
Predicting Settlements During Tunneling", J. of Geotech. and Geoenvir.
Eng., ASCE, Vol. 124, No. 5, pp. 389-395.
124.Shou, K. J., 2000, "A Three-Dimensional Hybrid Boundary Element
Method for Non-linear Analysis of a Weak Plane Near an Underground
Excavation", Tunneling and Underground Space Technology, Elsevier
Science Ltd., Vol. 15, No. 2, pp. 215-226
125.Simpson, B., 1993, "Development and Application of a New Soil Model
for Predication of Ground Movements", Predictive Soil Mechanics, Proc. of
the Wroth Memorial Symposium, St. Catherine College, Oxford, UK.
126.Skempton, A. W. and MacDonald, D. H., 1956, "The Allowable
Settlements of Buildings", Proc., Inst. of Civil Engrs., Part III, The
Institution of Civil Engrs., London, pp. 727-768, quoted from Broone
(1997).
127.Smith, I. M. and Griffiths, D. V., 1998, "Programming the Finite Element
Method", 3rd Ed., John Wiley and Sons, NY, USA.
128.Soil Instruments Ltd., 1999, "Technical Data File", requested from
www.soil.co.uk.
129.Sutcliffe, H., 1996, "Tunnel Boring Machines"; in "Tunnel Engineering
Handbook", edited by Brickel, J. O., Kuesel, T. R. and King, E. H.,
Chapman & Hall, NY, USA.
246
130.Szechy, K, 1967, "The Art of Tunnelling", Akademia Kiado, Budapest,
Hungary,
131.Tan, D. Y. and Clough G. W., 1980, "Ground Control for Shallow
Tunnels by Soil Grouting", J. of Geotech. Eng., ASCE, Vol. 106, No. GT9,
pp. 1037-1057.
132.Tarkoy, P. J. and Byram, J. E., 1991, "The Advangaes of Tunnel Boring:
A Qualitative/Quantitive Comparison of D&B and TBM Excavation",
Hong Kong Engineer, Hong Kong.
133.Terzaghi, K., 1936, "Stress Distribution in Dry and in Saturated Sand
above a Yielding Trapdoor", Proc. 1st Intl. Congress on Soil Mech.,
Cambridge, MA, Vol. 1, quoted from Bulson (1985).
134.Terzaghi, K., 1946, "Rock Defects and Loads on Tunnel Support", in
"Rock Tunneling with Steel Supports", Edited by R. V. Proctor, T. White,
Commerial Shearing Co., Youngstown, Ohio, pp. 15-99, quoted from
O'Rouke (1984).
135.Terzaghi, K., 1950, "Geological Aspects pf Soft Ground Tunnelling",
Chapter 11 in "Applied Sedimentation, Edited by P. Transk, John Wiley &
Sons, NY, 1950, quoted from Thomson (1995).
136.Thomson, J., 1995, "Pipe Jacking and Microtunneling", 2nd edition,
Blackie Academic and Professional, Glasgow, UK.
137.Touran, A, 1997, "A Probabilistic Model for a Tunneling Project using a
Markov Chain", J. of Const. Eng. and Man., ASCE, Vol. 123, No. 4, pp.
444-449.
138.Touran, A. and Asai, T., 1987, "Simulation of Tunneling Operations", J.
of Const. Eng. and Man., ASCE, Vol. 113, No. 4, pp. 554-568
139.Weaver, W., Johnston, P., 1984, “Finite Elements for Structural
Analysis”, Prentice-Hall, NJ,USA.
140.Wittaker, B. N. and Frith, R. C., 1990, "Tunnelling: Design, Stability and
247
Construction", published by The Institution of Mining and Metallurgy,
London, U.K.
141.Yoshida, T. and Kusabuka, M., 1994, "Behaviour of Ground and Adjacent
Underground Piping During Shield Tunneling", Proc. of International
Congress on Tunneling and Ground Conditions, ITA., Cairo, Published by
Balkema, Netherlands, pp. 201-206.
142.Zienkiewics, O. C., 1977, "The Finite Element Method", 3rd ed.,
McGraw-Hill Book Company, London.