Electrical Predictive

and Preventative

Maintenance

Mose Ramieh III – CE Power

Page 2: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 3: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Electrical and mechanical

equipment is subject to

failure, at the worst

possible time, for no

apparent reason.

- Mose Ramieh III

Page 4: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 5: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 6: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 7: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 8: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

There are two types of

facilities…

Page 9: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Those that have HAD a

failure…

Page 10: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

And those that will…

Page 11: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

IEEE 493-2007

Page 12: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 13: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Agenda

• Safety and Maintenance

• Types of equipment failures

• Non-Intrusive Predictive Options

• Somewhat Intrusive Predictive

Options

• Intrusive Options

Page 14: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Electrical

Maintenance

&

SafetyNFPA 70B, 70E, IEEE

Page 15: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 16: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

NFPA 70EStandard for Electrical Safety in the Workplace

– Electrical Arc, Flash, and Blast

– Safe work practices

– Energized Electrical Work Permit

– Minimum PPE Requirements

– Make systems electrically safe prior to work

– Mechanical controls (IR Windows)

Page 17: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Article 110.4

Multiemployer Relationship

States:

On multiemployer worksites (in all industry

sectors), more than one employer may be

responsible for hazardous conditions that

violate safe work practices.

Page 18: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Reasons for Electrical

Predictive and

Preventive

Maintenance

Page 19: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Safety

• To minimize unsafe conditions

• Avoid personnel injuries

• Reliability Centered Maintenance is

directed by safety first, then

economics. When determined that

safety is not a factor, then preventive

maintenance is justified on economic

grounds. IEEE 493-2007 Section 5.5

Page 20: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Economics

• To avoid future and more costly

equipment failures.

• To avoid premature equipment

failures.

• To avoid interruption of services to

production and processes.

Page 21: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Legal & Contracts

• Avoid legal consequences and/or to

meet legislated mandates (Codes &

Standards)

• To comply with insurance

company requirements.

Page 22: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Go Green

• Avoid environmental damage

• Accomplish equipment life

cycle extension.

Page 23: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Downtime=Money!

Page 24: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

NFPA 70B

Page 25: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

IEEE 493-2007

5.3.2 Causes of Electrical Failure

Page 26: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 27: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

IEEE 493-2007

5.3.2 Causes of Electrical Failure

Page 28: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Insulation Failures

Page 29: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 30: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Mechanical Failures

Page 31: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Mechanical Failures

Page 32: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Non-Invasive PdM

Page 33: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

House Keeping

Page 34: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Walk Through Inspections

Page 35: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 36: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

What You Can’t See

Page 37: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

What is Partial Discharge (PD)?

PD is a localized electrical discharge in an

insulation system that does not completely

bridge the electrodes

Phase to Phase

or

Phase to Ground

Page 38: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

What is Partial Discharge?

PMDT Proprietary

Partial Discharge EmissionLightHeatOdor (Ozone)SoundElectromagnetic pulse

Typical PD TypesCorona dischargeFloating dischargeParticle discharge Void discharge Surface discharge

Page 39: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

PD Activity

0

90

180

270

360

Partial Discharge Pulses

Negative Polarity

Pulse in positive half

cycle and Positive

polarity pulse in

negative half cycle

One 60Hz Cycle

V

TEV

signal

(nano

Secs)

-ve

4.1 mS

Page 40: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Detection Bandwidth

TEV: 3MHz~100MHz

UHF: 300MHz~1500MHz

AE: 20kHz~300kHz

Ultrasonic:40kHz

HFCT: 500kHz~50MHz

ApplicationGISMV switchgearPower cableTransformer

PMDT Proprietary

Level I PD Detection Services

Page 41: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Level I PD Detection Services

• UHF – Radio Frequency

• TEV – Transient Earth

Voltage (capacitive)

• Ultrasonic (airborne acoustic)

Page 42: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 43: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Typical Retrofit Switchgear Application

Sensor Selection Guideline

RFCT – One for every cable-set (in or out)

Coupling Capacitors – One set for every 3 structures

RFCT

Coupling Capacitors

LEGEND

Load Cables or Bus

Switchgear Cable Compartment

L1 L2 L3

52MV Power Circuit Breaker

Cable Shields

Breaker Cubicle 1 Breaker Cubicle 2 Breaker Cubicle 3 Breaker Cubicle 4 Breaker Cubicle 5 Breaker Cubicle 6

Page 44: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

On-Line Partial Discharge

Continuous Monitoring

Page 45: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Transformer Oil Samples

Page 46: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 47: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Slightly Invasive PdM

Page 48: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Thermographic Surveys

Page 49: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Subject

149.0

Ref.

41.1

*>55.0°F

*<35.0°F

36.0

38.0

40.0

42.0

44.0

46.0

48.0

50.0

52.0

54.0

Page 50: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 51: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Survey Hazards

Page 52: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

IR Windows

Page 53: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Short Outage PdM

Page 54: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

IEEE 493-2007

5.3.2 Causes of Electrical Failure

• Dirt on moving parts can cause sluggishness

and improper electrical equipment

operations…

• Checking the mechanical operation of

devices and manually or electrically

operating any device that seldom operates

should be standard practice.

Page 55: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Seldom Operated

Page 56: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

“Traditional” Outage PM

Page 57: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

When to Test?

NETA MTS and NFPA 70B• Monthly

– Visual Inspections

– Make notes regarding operating status and house keeping

• Annually

– Thermographic Survey

– Out of Service Maintenance

• 1-5 Years

– Follow Manufacturer Guidelines

– NETA Guidelines (Handouts Available)

– Check with Insurance Carrier for additional Guidelines.

Page 58: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Circuit Breaker Testing

Page 59: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Circuit Breaker Testing

Page 60: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

“New” Vacuum Breaker

Technology

Page 61: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Breakdown Voltage

61

Page 62: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

62

Penning Diagram and Field Testing

Test Setup using Penning Discharge Principle.

Page 63: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

NFPA 70E Chapter 2 Safety Related

Maintenance Requirements

• Qualified Persons to conduct

maintenance.

• Over-current devices shall be

maintained.

• House keeping, House keeping

Page 64: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

NFPA 70E Chapter 2 Safety Related

Maintenance Requirements

“Failure to properly

maintain protective

devices can have an

adversely effect on

the arc flash hazard

analysis incident

values.”

Page 65: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Circuit Breaker Testing

Page 66: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Transformer Testing

Page 67: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Transformer Testing

• Insulation Resistance

• Winding Resistance

• Turns Ratio Test

• Power Factor (60Hz)

• Leakage Reactance

• On Load Tap Changer

Page 68: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Power Factor vs Frequency

Page 69: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 70: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Catch it Early or Pay Big $’s Later

Effect:

High temperature and moisture

content will dramatically lower

the mechanical strength of paper

insulation

Risks:

• Lower the expected life of

transformer

• Run transformer at lower rating

Temperature / °C

50 70 90 110 130

0,1

1

10

100

1000

Life

expe

cta

nce

/ a

Dry

1%

2%

3%

4%

L. E. Lundgaard, “Aging of oil-impregnated paper in power transformers”,

IEEE Transactions on Power Delivery, Jan. 2004

Page 71: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Dielectric Frequency Response

high

low

high

high

low

low

0,001 0,01 1 100

0,001

0,01

0,1

1

1000

Frequency / Hz

Dis

sip

atio

n f

acto

r

0,1 10

mo

istu

re a

nd

a

gin

g o

f ce

llulo

se

insula

tio

ng

eo

me

try

oil conductivity

moisture, aging of cellulose

Sufficient data

Typical:

• Dry transformer or low

temperature

-> 0,1 mHz, 2:50 hours

• Moderate wetness /

temperature -> 1 mHz, 22 min

• Wet transformer or hot

temperature -> 0,1 Hz, 5 min

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

New

1000

0.002

0.0001

5

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

1000

0.002

0.0001

5Moderate

44°C

Freq/Hz0.001 0.01 0.1 1.0 10

Dis

sip

ation

fa

cto

r

0.005

0.01

0.02

0.05

0.1

0.2

0.5

1

2

1000

0.002

0.0001

5

Heavily aged

Page 72: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 73: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

The General Curve Structure

Page 74: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Cable Testing

Page 75: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

VLF Cable Testing

Page 76: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

VLF Cable Test Results

Page 77: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Protective Relays and Meters

• Monthly

– Visual Inspection

– Record and Reset Targets

• Annually

– Pick up Test and Time

Electromechanical Relays

– Verify Setting of Solid State

• 1-5 Years (Out of Service)

– Pick Up Test

– Timing Test

– Verify Operational Scheme

Page 78: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

BEFORE AFTER

• Existing Electro-Mechanical Relays (124); CEPS provided NERC/FERC testing.

• Scope of Work included engineering, design, material, installation, and commissioning.

• Material scope included SEL 300G, 387E.

On-site RetrofillDayton Power &

Light – Killen Station

78

Page 79: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Data and Oscillographic Records

Page 80: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 81: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of
Page 82: Electrical Predictive and Preventative Maintenanceewh.ieee.org/r3/atlanta/ias/2016-2017_Presentations/2017-05-15_NFPA... · Power cable Transformer PMDT Proprietary ... – Out of

Questions?

Answers