Energy Efficiency . . .
Process vs. Program
Tom Henry – Armstrong International, Inc.
Henry Molise – Pfizer (retired)
![Page 2: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/2.jpg)
2
Discussion OutlineDiscussion OutlineDiscussion OutlineDiscussion Outline
• Introduction
•Topic Definition
•Case Study Example
•Concluding Remarks
![Page 3: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/3.jpg)
3
IntroductionIntroductionIntroductionIntroduction
• Pfizer – The world’s leading producer of pharmaceutical products . . . With Kalamazoo, MI as it’s largest global manufacturing facility (Formerly known as Upjohn and Pharmacia)
• Armstrong International – A 104 year old, privately held, global company focused on delivering Intelligent System Solutions for Steam, Air and Hot Water Utilities. (Providing Products to Providing Utilities)
![Page 4: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/4.jpg)
4
DefinitionDefinitionDefinitionDefinition
• Program – A plan for a coherent sequence of incidents (A start and stop!)
• Process – A progressively continuing operation that consists of a series of controlled actions systematically directed toward a particular result
![Page 5: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/5.jpg)
5
Process vs. Program at the Process vs. Program at the Kalamazoo, MI facilityKalamazoo, MI facility
Process vs. Program at the Process vs. Program at the Kalamazoo, MI facilityKalamazoo, MI facility
• In 1980’s, trap testing eliminated from the maintenance budget as a well intentioned cost savings (6000 steam traps) Program Ends!
• Armstrong performed pilot study (5 years later) with resulting economics justifying a budget from management
![Page 6: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/6.jpg)
6
Process vs. ProgramProcess vs. ProgramProcess vs. ProgramProcess vs. Program• Armstrong assisted testing and replacement
of all 6000 traps and provided software for steam loss measurement
• First year savings: $479,000
Production time improved in some areas
• First year investment: $110,000 (all costs)
• Management created budget for future years from “fuel saved”
(The Process Begins!)
![Page 7: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/7.jpg)
7
Process vs. ProgramProcess vs. ProgramProcess vs. ProgramProcess vs. Program• Subsequent years Pfizer staffed one person to test
and monitor traps
• Every year management realized a net positive cash flow from the “Process” (annual savings $50,000 - $100,000)
• Due to retirement, Armstrong provided the on-site technician for last 3 years with similar financial results
• Armstrong’s on-site technician also provides total steam system troubleshooting
• Over 10 years Pfizer/Armstrong have recognized more than $1,000,000 in savings from just this “PROCESS”
![Page 8: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/8.jpg)
8
Other Pfizer/Armstrong Other Pfizer/Armstrong Energy InitiativesEnergy Initiatives
Other Pfizer/Armstrong Other Pfizer/Armstrong Energy InitiativesEnergy Initiatives
• Armstrong has gone on to provide complete steam system audits at Pfizer’s Puerto Rico and Italy facilities
• These audits have recognized an additional $1 million dollars in energy conservation projects
• Armstrong also conducted a turnkey implementation of heat pipes for “free” cooling for HVAC make-up air in Puerto Rico
![Page 9: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/9.jpg)
9
Concluding CommentsConcluding CommentsConcluding CommentsConcluding Comments
Pick it ‘over’ again . . . the low-hanging fruit grows back!
Pick ItAgain
F _
RUI
T
![Page 10: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/10.jpg)
10
Concluding Comments Concluding Comments (cont’d)(cont’d)
Concluding Comments Concluding Comments (cont’d)(cont’d)
• Develop Processes not Programs when dealing with energy initiatives
• Because many energy projects have attractive paybacks, form partnerships with vendors that can stretch your resources and accomplish your cost reduction objectives
• Remember . . . Low-hanging fruit . . . Grows again!
![Page 11: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/11.jpg)
11
Other Armstrong Other Armstrong SolutionsSolutions
Other Armstrong Other Armstrong SolutionsSolutions
• Steam and Condensate System Optimization
• Hot Water System Optimization
• Process Air System Optimization
• Turnkey Project Services
• Energy Project Financing Services
• Operation and Maintenance Services
• Asset Management ServicesTom [email protected]
![Page 12: Energy Efficiency... Process vs. Program Tom Henry – Armstrong International, Inc. tomh@armstrong-intl.com Henry Molise – Pfizer (retired) ctmolise@juno.com](https://reader036.vdocuments.net/reader036/viewer/2022062423/5697bf9a1a28abf838c91f80/html5/thumbnails/12.jpg)
12
Pfizer/ArmstrongPfizer/ArmstrongPfizer/ArmstrongPfizer/Armstrong
““A Process Partnership”!A Process Partnership”!““A Process Partnership”!A Process Partnership”!