energy efficient solar solutions for developing countries
TRANSCRIPT
TLA international Energy Conference 2016
Uninterrupted Efficient Energy Solutions through Solar For
Urban Office Building And Cold Storage Applications
www.statconenergiaa.com MANOJ PANDE
ABOUT US
SOLAR
POWER
RAILWAYS
DEFENSE
Manufacturing Facility of 1,24,000 square feet Near Noida ( Pilkhua ) with >200 personnel currently working for the company .
Office Address: B-81 Sector 63, Noida, Uttar Pradesh
www.statconenergiaa.com
•Erratic Supply and poor quality of Grid
•Ever increasing cost of diesel and maintenance of Diesel Generator Sets
•DG Set running at less than 30% rated capacity causing a decrease in its life
•Loss of productivity among employees
•A sun exposed terrace causes extra strain on the Air conditioners
•Frequent power cuts of 10 minutes to 4 Hours
•Increasing cost of electricity with Time-Of-Day (TOD)
•Very High fixed charges bringing the electricity bill to > ₹ 9.50 Per Unit ($ 0.14 per
unit)
•Typically the peak load does not end at 4 pm and electricity charges can be as high as
15-20% in this TOD of 5pm- 10pm regime.
Present Scenario of Electricity in India
THE PROBLEM
A very common pattern across all developing countries exists where : a) The electricity is available daily for 12-18 hrs per day b) the electricity fails/interrupts 4-5 times per day and the duration may differ from
5 minutes to 4 hours
To cater for such unplanned and unpredictable failures almost all users do the following:
1. Run a higher rating DG Set at a power varying between 30% to 75% of its rated capacity, and
2. Keep free running of their DG Set for 2 minutes before switching off the DG Set.
THE PROBLEM
This results in : 1. Very High electricity bills owing to the higher rates of electricity 2. Ever rising cost of diesel adds to the increased bill
On all such interruptions there is at least 20-30 seconds of blackouts. While 1st one results into cost/unit being directly proportional to the percentage of loading, the 2nd one results in a situation of burning fuel at 0% load for 2 minutes every time the grid resumes.
Looking at the energy deficient scenario of our country , where everyone is forced to use diesel generator ( DG Set) as backup source of energy. An obvious quick fix solution through renewable energy sources to be driven by: a) through Government subsidy or b) Actual business models based on the usefulness and not mere investment opportunity.
THE PROBLEM
THE SOLUTION
Battery Based Solar Solutions for Uninterrupted Energy
1. Can Draw upon the power whenever required 2. Lead Acid Batteries can last long up to 6-10 years if treated properly 3. Almost Zero Pollution 4. Hybrid Inverters can export to the grid during lean load periods and
bring down the payback period 5. No loss of productivity as the Battery + Inverter acts as a UPS 6. Best possible solution for developing countries 7. Grid Tie inverters unsuitable due to their ineffectiveness against
frequent power outages
LOADS AND SYSTEM DETAILS
System Details: •PV Panels: 30KWp
•Inverter: 100 KWp •Type of Inverter System: HYBRID Grid Synchronised (ON GRID /OFF GRID) •Battery Capacity: 240V/ 300Ah
67% 6%
10%
17%
Distribution of loads
Air conditioners Light Loads
Computers Misc
Load Details: •Air Conditioners: Cassette + Split Type
•Computers •LED Lights •Television •Refrigerators •Coffee Machines •Fans • Water Pump
•Misc. Load Total Peak Load = 45 KWp
SPV present, Grid available. Battery Charged through MPPT charger + mains, Load supplied through Grid.
P1
P2 P3
P = (P2+P3)
Hybrid Solar Power System
Condition # 1
GRID
INTERLOCK DG SET OPTIONAL
CHARGING AC LOADS (Priority)
AC LOADS (Others)
SPV available, Grid available, Battery almost charged, surplus PV power used for AC loads connected.
P1
P2 P3
P = (P2+P3)-P1
GRID
INTERLOCK
Saving of electricity bills.
DG SET OPTIONAL
Condition # 2
Trickle Charging
Hybrid Solar Power System
AC LOADS (Priority)
AC LOADS (Others)
P3
P1
P2
P = P1-(P2+P3)
SPV available, Grid available, Battery almost charged, ZERO or very Little load: EXCESS POWER TO GRID
Pays You Back!
Condition # 3
CHARGED
Trickle charging
Hybrid Solar Power System
GRID
INTERLOCK DG SET OPTIONAL
AC LOADS (Priority)
AC LOADS (Others)
P1
P2 P3
SPV available, Grid unavailable, Battery almost charged, surplus PV power+ Battery used for AC loads (priority) connected.
Condition # 4
DISCHARGING
Hybrid Solar Power System
GRID
INTERLOCK DG SET OPTIONAL
AC LOADS (Priority)
AC LOADS (Others)
Low PV available (or absent) Grid absent. AC Load (priority) Supplied through stored battery energy
P1=P2
P2 P3=0
P =0
Condition # 5
DISCHARGING
Hybrid Solar Power System
GRID
INTERLOCK DG SET OPTIONAL
AC LOADS (Priority)
AC LOADS (Others)
SPV not available. Grid available, Battery charging through grid, Load supplied through Grid Optional Time based grid charging of battery also available
P1
P2 P3
P= (P2+P3)+P1
Condition # 6
CHARGING
Hybrid Solar Power System
GRID
INTERLOCK DG SET OPTIONAL
CHARGING AC LOADS (Priority)
AC LOADS (Others)
Condition # 7 SPV not available. Grid not available, Battery charging through DG SET, Load supplied through DG SET.
AC LOADS (Priority)
P1
AC LOADS (Others)
P2 P3
P= (P2+P3)+P1
Hybrid Solar Power System
GRID
INTERLOCK DG SET OPTIONAL
CHARGING
FINANCIAL ANALYSIS
• Initial Investment: PV Panels: 250×120= 30KW= 12,42,400 ₹
Inverter: 100kVA= 10,00,000 ₹
Batteries: 2Vx120 /300Ah = 6,80,000 ₹
Mounting structure= 1,80,000 ₹
AJB=8,000 ₹
Wires=50,000 ₹
Installation and commissioning= 1,00,000 ₹
TOTAL= 22,60,000 ₹
• Savings & Payback Period Per unit cost of electricity= 9.86 ₹
Per unit cost of DG, electricity=22.83 ₹
(Note: we are considering 70% from electricity and 30% from DG for per unit cost) Total energy generated by solar per year (units) = 46530 units or KWH
Total savings per year ( in rupees) = 6,32,436 ₹
PAYBACK PERIOD
Payback period = 5.5 years
Details Of Solar Cold Storage Location : ETAWAH | U.P. | India
Months : Feb to Oct
PV capacity selected - 140 KWp
Battery - 700AH/500V Lead Acid,
Inverters : Hybrid (can also be used as Grid export)
* VFD 1 : 120 hp
* VFD 2 : 20 hp
* VFD 3 : 10 hp
• Cold storage is a well known term which means a huge storing area for vegetables/fruits ,Chocolates/ drugs etc. can be stored at a lower temperature in a controlled environment for preservation of its qualities / flavor etc. • So it does not need rocket science to understand the working of a cold storage.
• Typically a cold storage uses big compressor motor , water pump motor , blower motor, lights, fans and electricity for utility services.
WHAT IS A COLD STORAGE?
In India we have generally three categories of cold storages
Type 1 : Urban/Cities areas with 24 hrs electric supply . 10-15% Type 2: Areas with 16-18 hrs of Grid supply & 4-6 interruptions/ day. 50-65% Type 3: Areas with 12-14 hrs of Grid supply & 4-6 interruptions/ day. 20-30%
COLD STORAGE COSTS
ELECTRICITY BILL BREAKDOWN IN COLD STORAGES
GRID
DIESEL
MAINTENANCE
SALARIES
MISC
FIXED CHARGES
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
PV
Condition # 1 PV Present , Grid available, Battery charging + Motor & load requirement shared by both but with PV as priority
TEMPERATURE PROBE
CHARGING
COMPRESSOR 120HP
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 2 PV Present, Grid unavailable. Battery charging + Motor & load requirement met by PV with as Battery as buffer.
PV
TEMPERATURE PROBE
CHARGING
COMPRESSOR 120HP
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 3 PV present, Grid un-available. Battery charging + Motors load requirement met by PV. With temperature achieved by compressor
working in Energy saving mode.
PV
TEMPERATURE PROBE
CHARGING
COMPRESSOR 120HP
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 4 PV present, Grid available. Battery charged & Motors load requirement is met by PV. With temperature achieved ,compressor works
in Energy saving mode.
EXCESS POWER EXPORT TO GRID!!
TEMPERATURE PROBE
CHARGED
COMPRESSOR 120HP
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 5 PV & Grid un-available. Battery charging + Motors load requirement me by Battery only. With temperature achieved compressor working in Energy saving mode.
TEMPERATURE PROBE
DISCHARGING
COMPRESSOR 120HP
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 6 PV & Grid un-available. Battery loosing 30% capacity. DG1 starts supplying Battery + Motors load requirements.DG1 running at 90% Load. Better DG set utilization
TEMPERATURE PROBE
DISCHARGING
GRID
DG2 (320KW)
COMPRESSOR 120HP
VFD 2 10HP
~
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP
SINE WAVE INV.
~ LIGHT & FANS
LOAD
P L C
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 7 PV & Grid un-available. Battery losing 50% capacity. DG2 starts supplying Battery + Motors load requirements. DG2 running at >60% Load. After approx 2 hrs , changeover to DG1 anticipated.
TEMPERATURE PROBE
CHARGING
GRID
DG2 (320KW)
VFD 2 10HP
~
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP
SINE WAVE INV.
~ LIGHT & FANS
LOAD
P L C
COMPRESSOR 120HP
Solar Power System for Cold Storage
DG1(40KW)
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 8 Grid resumes. Battery charging + Motors load requirement met by Grid with Battery buffer .
COMPRESSOR 120HP
TEMPERATURE PROBE
CHARGING
GRID
DG2 (320KW)
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP LIGHT & FANS LOAD
P L C
VFD 2 10HP
~
SINE WAVE INV.
~
Solar Power System for Cold Storage
DG1(40KW)
GRID
MPPT CHARGER
MAIN CHARGER
C1
C2
BATTERY
AC change- over panel
Condition # 10 OFF SEASON PV Present , Grid available . PV Power EXPORT to Grid under Net-Metering .
DG2 (320KW)
COMPRESSOR 120HP
VFD 2 10HP
~
VFD 3 20HP
~ ~ ~ ~ ~
VFD 1 120HP
~ PUMP 1X10HP
VFD PANEL
BLOWERS 5X3 HP
SINE WAVE INV.
~ LIGHT & FANS
LOAD
TEMPERATURE PROBE P L C
-40
-20
0
20
40
60
80
100
120
0 5 10 15 20 25 30 35 40 45 50
TOTAL PV POWER BC POWER KW BATTERY POWER LOAD POWER KW