Kevin Fok
Senior Project Manager
(248) 825-1043
Energy Storage Project
Perspectives and Case
Studies34th Annual International Battery Seminar & Exhibit
Fort Lauderdale, FL
March 20-23, 2017
1. LG Overview2. Market Growth & Project Phase Framework3. Planning & Procurement4. Deployment & Integration5. Operations & Maintenance6. Recent Deployments7. Conclusions
LG Chem Michigan, Inc.
LG Chem Michigan, Inc. in Holland, MI
Produces battery cells and battery packsCustomers include GM and Chrysler
The start of what is now a regular occurrence; a forklift loads batteries
to be shipped from the LG Chem plant
http://www.mlive.com/business/west-
michigan/index.ssf/2013/11/lg_chem_celebrates_first_shipm.html
http://www.hollandsentinel.com/news/20170214/lg-chem-to-add-new-production-facility-adding-100-150-jobs-in-holland-area
Links verified March 2, 2017
LG Chem Power, Inc. – Troy, MI
• Automotive market: Engineering, program management, and technical support
• ESS market: Sales, project management, and technical support
Market Growth
• Significant growth during the past several years:
- Important testing & evaluation systems continue to be installed
- Fully commercial systems with long-term performance guarantees are also being installed
- Deployments in multiple market segments: grid, commercial & industrial, and residential
Positioned for Continued Growth
Matt Roberts, “The Path Forward for Energy Storage
in the US”, NY-BEST Annual Meeting & Conference,
Albany, NY, March 8-9, 2017
“We forecast the US energy storage market will grow more quickly than the consensus expectation. Increasing penetration of renewable power generation is significantly disrupting peak and non-peak power demand, particularly in regulated states.”
Links verified March 2, 2017
February 5, 2017 report from Morgan Stanley, “Energy Storage An Underappreciated Disruptor”
http://www.utilitydive.com/news/morgan-stanley-us-energy-storage-market-could-grow-to-145-gwh-with-ferc-su/435767/
Project Phases: Example Summary
Electric Power Research Institute, ESIC Energy Storage Implementation Guide 2016, 3002008899, Technical Report, December 2016
Planning & Procurement
Electric Power Research Institute, ESIC Energy Storage Implementation Guide 2016, 3002008899, Technical Report, December 2016
Planning: Engineering Teamwork
Core Website: http://core-usa.com/what-do-engineers-do/, Posted 1/14/13
16
Links verified March 2, 2017
Planning: The Project Team is Critical
Energy Storage System
Project Manager
EPC Contractor
Project Manager
Site Manager
Site Field Service
Engineer
Safety Manager Quality Manager Site Engineer HVAC Fire Suppression Construction Security
Battery Supplier PCS Supplier EMS Supplier O&M Contractor Decommissioning
Engineering Design
Team
Electrical EngineerCivil Engineer
(Foundation)
Civil Engineer
(Structural)
Civil Engineer
(Geotechnical)
IT Communications
Engineer
Project Site Team
Site Manager Quality Manager
Safety Manager Field Services
This chart is an approximation and is abbreviated.
Broad involvement of disciplines and roles.
Case Study: Planning–System Design: SCE TSP
SCE TSP: Case Study on System Design
• Met stringent standards:
Electrolyte: Evaluated using Cup Burner Test NFPA 2001 Standard on Clean Agent Fire Extinguishing Systems (2012 edition)
Battery Cells: UL Listed (UL 1642)
Battery Modules: UL Listed (UL 1973)
Battery Rack with Modules Installed: Electromagnetic compatibility (FCC Part 15B)
Battery Protection Unit: Electromagnetic compatibility:
Conducted Emission EN 61000-6-3:2007+a1:2011
Electrostatic Discharge(ESD) EN 61000-4-2:2009
Radiated RF Electromagnetic Fields EN 61000-4-3:2006+A2:2010
Electrical Fast Transients / Burst(EFT) EN 61000-4-4:2004+A2:2010
Surges EN 61000-4-5:2006
Immunity to Conducted Disturbances EN 61000-4-6:2009
Power Frequency Magnetic Field Immunity Test EN 61000-4-8:2010
Voltage Dips and Interruptions EN 61000-4-11:2004
Battery Racks with Modules Installed:
Tested to IEEE 693-2005 (IEEE Recommended Practice for Seismic Design of Substations)
Meet Zone 4 seismic requirements
PCS modules:
UL Listed (UL 1741)
• Site Security System
Utility customer designed and completed security system to substation standards
Planning: Product Listing Example – UL 1642 and UL 1973
External short circuit
Abnormal charge / Overcharge
Forced discharge / Overdischarge
Crush Impact (cell) Shock Vibration Heating (cell)
UL 1642
CellsX X X X X X X X
UL 1973
Module& Rack
X X X X X X X
Temperature cycling
Low pressure (altitude) (cell)
Projectile / External fire
DropContinuous
low rate charging
Molded casing
heating test
Insulation or isolation resistance
Internal short circuit test orpropagation
test
UL 1642
CellsX X X
UL 1973
Module & Rack
X X X X X
Adapted from UL “Safety Issues for Lithium-Ion Batteries”, 2016
Planning: Product Listing Example – UL 9540
• Scope• Energy storage systems
• Construction criteria• Enclosure and electrical insulation• Enclosure ratings• Walk-in enclosures• General electrical safety• Electrical connections and components• Remote controls, communication• Safety analysis• Containment
• Construction requirements• Electrical connections and components• Remote controls, communications• Safety analysis• Fluid handling and containment• Fluid equipment• Hazardous spill containment• Containment of moving parts• Combustible concentrations• Fire detection and suppression• Markings• General instructions• Installation instructions• Operations and maintenance instructions
• Testing• Electric• Mechanical• Fluid containment• Environmental
Adapted from UL 9540 table of contents
Planning: Fire Suppression
• This report summarizes the main findings and recommendations from extensive fire and extinguisher testing program that evaluated a broad range of battery chemistries.” (Page 3)
• “The testing was conducted through much of 2016 on behalf of the New York State Energy Research & Development Authority (NYSERDA) and Consolidated Edison, as they engaged the New York City Fire Department (FDNY) and the New York City Department of Buildings (NY DOB) to address code and training updates required to accommodate deployment of energy storage in New York City.” (Page 3)
• LG Chem supplied samples to be tested.
• The link on the NYSERDA website is below:https://www.nyserda.ny.gov/Researchers-and-Policymakers/Energy-Storage
• “The main conclusion from the program is that installation of battery systems into buildings introduces risks, though these are manageable within existing building codes and fire fighting methods when appropriate conditions are met.” (Page 3)
Links verified March 2, 2017
Planning: Some LG Chem Activities in New York
1. ConEd and NYSERDA Fire Testing for FDNY and DOB for energy storage deployments in NYC• Final Report: Considerations for ESS Fire Safety
- Consolidated Edison and NYSERDA New York- https://www.nyserda.ny.gov/Researchers-and-Policymakers/Energy-Storage
• LG Chem submitted product samples
2. ConEd Brooklyn Queens Demand Management Program (BQDM) - Demand Energy• 300 kW / 1200 kWh LG Chem batteries• https://www.greentechmedia.com/articles/read/new-york-grid-microgrid-bqdm-con-ed-peak
3. ConEd Reforming the Energy Vision (REV) Demonstration – NRG• 1 MW / 4 MWh LG Chem batteries• http://www.utilitydive.com/news/coned-nrg-partner-on-4-mwh-mobile-battery-storage-demo-for-
rev-docket/437125/
Procurement
Electric Power Research Institute, ESIC Energy Storage Implementation Guide 2016, 3002008899, Technical Report, December 2016
• Define specifications and scope in a detailed manner
• Establish contractual documents carefully
• Plan resources and allocate time for contracting
Deployment & Integration
Electric Power Research Institute, ESIC Energy Storage Implementation Guide 2016, 3002008899, Technical Report, December 2016
Case Study: Construction – SCE TSP
Location Tehachapi, CA
Customer Southern California Edison
Power / Energy 8 MW / 32 MWh
Application Multi-Purpose
EPC LG Chem
Battery LG Chem
PCS ABB
InformationalWebsites
Video: “Tehachapi Storage Project Ribbon-Cutting”, Edison International Websitehttp://www.edison.com/home/innovation/energy-storage.html
News Video: “LG Chem Switches On 32 MWh Energy Storage System in California”, Electric Light & Power – Executive Insight - 9/26/14 Weekly Newscasthttp://www.elp.com/articles/2014/09/lg-chem-switches-on-32-mwh-energy-storage-system-in-california.html
News Video: “Large Battery Energy Storage Project Unveiled in Tehachapi”, KBAK Eyewitness News, 9/24/14http://bakersfieldnow.com/news/local/large-battery-energy-storage-project-unveiled-in-tehachapi
Photos courtesy of Southern California Edison
Links verified March 2, 2017
Case Study: Construction - EPRI-Southern Company
Location Cedartown, GA
Customer EPRI and Southern Company
Power / Energy 1.0 MW / 2 MWh
Application Renewables integration
System Integrator LG Chem
Battery LG Chem
PCS ABB
InformationalWebsites
LG Chem Press Release:http://www.businesswire.com/news/home/20150917005768/en/LG-Chem-Powers-Energy-Storage-System-Solar#.VhBDBflViko
Southern Company Webpage:http://www.southerncompany.com/newsroom/2015/sep-2015/2015-09-17-so-cedartown.html
Photos courtesy of Southern Company
Links verified March 2, 2017
Case Study: EPRI-Southern Company - Construction
August 2014: First site visit
July 2015: Lifting battery container into place
July 2015: The battery container arriving
onsite
July 2015: The first batteries being delivered onsite
August 2015: Commissioning the system
September 2015: Battery container
ready for tours
September 2015: Ribbon-cutting
September 2015: Ribbon-cutting
preparations
Case Study - Construction: Village of Minster
Location Minster, OH
Customer Half Moon Ventures and the Village of Minster
Power / Energy 7 MW / 3 MWh
Application Frequency Regulation, T & D Deferral, and Demand Response
EPC S&C Electric
Battery LG Chem
PCS S&C Electric
Informational Websites
S&C Press Release, 5/6/16:https://www.sandc.com/en/news/sc-news/sc-completes-one-of-the-largest-energy-storage-systems-in-ohio/
S&C Time Lapse Video of Construction and Deployment:https://www.youtube.com/watch?v=YY3Fvf1cZps&feature=youtu.be
LG Chem Press Release, 6/9/16:http://www.businesswire.com/news/home/20160609006290/en/LG-Chem-Powers-Largest-Solar-Storage-Systems
Photo courtesy of S&C Electric and the Village of Minster
Winner: Energy Storage North America 2016 Centralized Storage Projecthttp://www.esnaexpo.com/awards/2016
Utility Dive 5 battery energy storage projects to watch in 2016http://www.utilitydive.com/news/5-battery-energy-storage-projects-to-watch-in-2016/409624/
Winner: Power Engineering Best New Renewable Project of the Year 2016http://www.power-eng.com/articles/print/volume-121/issue-1/features/best-new-projects-of-2016.html
Links verified March 2, 2017
Case Study - Construction: Village of Minster
31 Links verified March 2, 2017
S&C Time Lapse Video of Construction and Deployment:https://www.youtube.com/watch?v=YY3Fvf1cZps&feature
=youtu.be
Links verified March 2, 2017
Case Study: Commissioning - Snohomish PUD
Location Everett, WA
Customer Snohomish Public Utility District
Power / Energy 1 MW / 0.5 MWh
Application Renewables Integration
EPC Snohomish Public Utility District
Battery LG Chem
EMS 1Energy (Doosan GridTech as of July 2016)
PCS Parker
Informational WebsitesElectric Light & Power/ POWERGRID International , Video: LG Chem, 1Energy, Snohomish PUD commission energy storage system, 12/02/2015,
http://bcove.me/zsmi730y
Photo courtesy of Snohomish PUD
Modular Energy Storage Architecture (MESA)
Example of a MESA-compliant systemhttp://mesastandards.org/
LG Chem is a MESA Founding Member
Finalist: Energy Storage North America 2016Centralized Storage Project
http://www.esnaexpo.com/awards/2016
Links verified March 2, 2017
Case Study – Deployment & Commissioning: Duke Energy
Location New Richmond, OH
Customer Duke Energy
Power / Energy 2 MW / 0.5 MWh
Application Frequency Regulation
EPC Duke Energy
Battery LG Chem
EMS Greensmith
PCS Parker
Informational WebsitesDuke Energy Press Release, 11/18/15:
http://news.duke-energy.com/releases/batteries-spring-to-life-at-retired-duke-energy-coal-plant
Photo courtesy of Duke Energy
Links verified March 2, 2017
Operations & Maintenance
Electric Power Research Institute, ESIC Energy Storage Implementation Guide 2016, 3002008899, Technical Report, December 2016
Case Study – O&M: AES Warrior Run
Location Cumberland, MD
Customer AES
Power / Energy 10 MW / 3 MWh
Application Frequency Regulation
EPC AES
Battery LG Chem
PCS Parker
Informational WebsitesAES Press Release, 11/13/15:
http://www.aesenergystorage.com/2015/11/13/aes-reveals-advancion-4-with-first-commercial-deployment/
Photo courtesy of AES
Links verified March 2, 2017
Case Study – O&M: NextEra Lee-DeKalb
Location Lee DeKalb Wind Energy Center, Illinois
Customer Nextera Energy Resources
Power / Energy 20 MW / 9 MWh
Application Frequency Regulation
EPC Blattner
System Integrator Greensmith
Battery LG Chem
PCS Not Disclosed
InformationalWebsites
EnergyNow, 5/31/15 Issue:http://www.nexteraenergy.com/energynow/2015/0515/0515_cover.shtml
DOE Energy Storage Database:http://www.energystorageexchange.org/projects/2017
NEER Video: A Promising Future for Energy Storage https://www.youtube.com/watch?v=Jn2CS5ca42U
EnergyNow, 5/31/15 Issue:http://www.nexteraenergy.com/energynow/2015/0515/0515_cover.shtml
https://www.youtube.com/watch?v=Jn2CS5ca42U
Links verified March 2, 2017
Case Study – O&M: NextEra Meyersdale
Location Meyersdale, PA
Customer NextEra Energy Resources
Power / Energy 18 MW
Application Frequency Regulation
EPC NextEra Energy Resources
Battery LG Chem
PCS Parker
Informational WebsitesNextEra, Energy Now, February 29, 2016:
http://www.nexteraenergy.com/energynow/2016/0216/0216_EnergyStorage.shtml
Photo courtesy of NextEra Energy Resources
Links verified March 2, 2017
Case Study – Solar + Storage: Entergy
Location New Orleans, LA
Customer Entergy New Orleans
Power / Energy 500 kW / 500 kWh
Application Solar + Storage
EPC Blattner Energy
Battery LG Chem
PCS GP Tech
Informational Websites
Entergy February 2, 2016 Press Release:http://www.entergynewsroom.com/latest-news/powering-future-entergy-new-orleans-breaks-ground-first-utility-scale-solar-project/
Video on Entergy Vimeo Channel, “Entergy New Orleans Solar Power Plant”:https://vimeo.com/185554150
Photos courtesy of Entergy New Orleans
Links verified March 2, 2017
Case Study – OCI Solar Power
Location San Antonio, TX
Customer OCI Solar
Power / Energy 1.0 MW / 250 kWh
Application Frequency Regulation, Solar PV Ramping
EPC Younicos
Battery LG Chem
PCS Younicos
Informational Websites
Younicos Website: Case Studyhttps://www.younicos.com/case-studies/texas/
Younicos Website: Case Study Filehttps://www.younicos.com/wp-content/uploads/2016/09/Younicos_Reference_Project_SanAntonio.pdf
Photos courtesy of Younicos
Links verified March 2, 2017
Case Study – Commercial & Industrial: Lockheed Martin
Location Syracuse, NY
Customer Lockheed Martin/ENGIE
Power / Energy 1 MW
Application Energy Efficiency and Ancillary Services
EPC Lockheed Martin
Battery LG Chem
Informational WebsitesLockheed Martin October 19, 2016 Press Release:
http://www.lockheedmartin.com/us/news/press-releases/2016/october/mfc-lockheed-martin-commissions-gridStar-energy-storage-system-new-york.html
Photo courtesy of Lockheed Martin
Links verified March 2, 2017
Case Study – Reliability: Florida Power and Light
Location Everglades National Park, FL
Customer Florida Power and Light
Power / Energy 1.5 MW
Application Reliability, Frequency Response, Peak Shaving, Volt-VAR
EPC NextEra Energy Resources
Battery LG Chem
PCS Dynapower
Informational Websites
Florida Power and Light Press Release, June 16, 2016:http://newsroom.fpl.com/2016-06-16-FPL-launches-innovative-energy-storage-project-in-conjunction-with-White-House-summit-on-scaling-renewable-energy-and-
storage
Photo courtesy of NextEra Energy Resources
Links verified March 2, 2017
Case Study – Frequency Regulation: NextEra Energy Resources
Location Yarmouth, ME
Customer NextEra Energy Resources
Power / Energy 16.2 MW
Application Frequency Regulation
EPC NextEra Energy Resources
Battery LG Chem
PCS Power Electronics
Informational Websites
Portland Press Herald, December 17, 2016:http://www.pressherald.com/2016/12/17/yarmouth-power-plant-installs-giant-battery-in-first-of-its-kind-project-in-new-england/
Photos courtesy of NextEra Energy Resources
Links verified March 2, 2017
Case Study – Testing: LG&E KU and EPRI
Location Harrodsburg, KY
Customer Electric Power Research Institute (EPRI) and Louisville Gas & Electric and Kentucky Utilities (LG&E KU)
Power / Energy 1.0 MW/2.0 MWh
Application Testing and evaluation for utility applications
Battery LG Chem
EMS Greensmith
PCS Dynapower
Informational Websites
Louisville Gas & Electric and Kentucky Utilities Press Release, February 28, 2017:https://lge-ku.com/newsroom/press-releases/2017/02/28/kentucky-power-plant-becomes-energy-storage-testing-ground
Photo courtesy of Louisville Gas & Electric and Kentucky Utilities
Links verified March 2, 2017