Anti-CorruptionClean Construction System
Seoul Metropolitan Infrastructure Headquarters
&UNDP Seoul Policy Centre
2
Part 1Introduction & Overview of Seoul’s Clean Construction System
Part 2Details of Seoul’s One-Project Management Information System (One-PMIS) and the Public Information Disclosure System, “Allimi”
Part 3Key Success factors, Lessons Learnt, and Policy Recommendations
Structure of the Presentation Series
7
Corruption and lack of required maintenance Disasters from shoddy construction
Side effects of fast growth and con-struction boom
8
?Solution
Realization: efficient and transparent management of public construction projects matters for the lives of citizens.
Policy makers and citizens worked together to find a systematic solution to the problems of shoddy con-struction.
9
Improvements are invented only by those who can feel that something is not good.
-Friedrich Nietzsche
10
+ +Improve
efficiencyof construction
governance
Satisfy citizen’s
Right to know
Practice clean construction
administration
The Clean Construction System (CCS)
Innovation
Open Clean
11
Four components of CCS
Allimi?Information Disclosure system for
citizens
One-PMIS
AutomatedSub-contractor Payment Sys-
tem
ElectronicHumanResourcesManagementSystem
Allimi+
14
One-PMIS
One-PMIS
Visit to public
organizationfor sharing info
Difficult to data management,
document storage
Difficult to systematic
project management
15
- Enables users to monitor in real-time the status of construction materials, workers, and equipment being used
- Facilitates systematic management of work processes
One-PMIS
16
One-PMIS
Contractors
Contractdetails
Seoul Officials Supervisors
Reporting documentmanagement
Safetymanagement
Enhanced management efficiency and construction quality
History & Record
management
One-PMIS
18
Real-time public information portal that never be-comes “dead” storage of outdated information
Allimi
19
Contract details
+
Construction Project Info
Construction photo
Key stakeholders
List of sanctions
Overview
Register for site-visit
Citizen participation
zRequests & questions
Allimi
22
Institutionalization of One-PMIS UseHow Seoul Has Done- Recommends the use of One-PMIS for all of its construction projects whose total budget exceeds KRW 20 million won, or about USD 18,000.
- Runs a monthly training program for its users and provides
user support through the operation of a call center, offering remote support service and providing online
manual service.
- Seoul has decided (in May 2016) to add a dedicated clause into
the “Special Conditions” section of its construction con-tracts,
making the use of One-PMIS mandatory for the contract-holders.