environmental aspects & impacts register

45
ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER | Environmental Aspects & Impacts Register Disposition Statement This generic Register of Environmental Aspects and Impacts should be read in conjunction with McLaren Construction Ltd Aspects and Impacts Procedure, the individual Site Environmental Risk Assessments and Environmental and Emergency Plans. These detail how the generic environmental aspects apply and how any site-specific risks or actual impacts are identified and prevented, controlled or mitigated. This statement explains the process by which environmental aspects have been identified and evaluated for significance. The aspects have been grouped into the following topics: 1. Resource efficiency (non-renewable resources, energy and water) 2. Traffic and transport 3. Ground contamination 4. Water and effluent discharge 5. Noise, vibration and other nuisances 6. Air emissions (dusts, odours, greenhouse gases, ozone depleting substances, solvents etc.) 7. Toxic and hazardous substances (including oils and fuels) 8. Deleterious materials (asbestos, PCBs, etc.) 9. Wastes 10. Visual impact / townscape / landscape (including site lighting) 11. Cultural heritage and archaeology 12. Wildlife and natural features 13. Environmental emergencies and external occurrences (impact/collision, flood, etc.) 14. Indirect Environmental impacts An example of the process by which aspects and impacts were identified is as follows: one aspect identified in the register is wastes and their disposal to landfill. This aspect was considered significant because of the variety and importance of the potential impacts consequent to the degradation of the wastes after tipping (leachates, methane / greenhouse gases, odours, visual impact, health concerns, etc.).

Upload: others

Post on 18-Oct-2021

144 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

Environmental Aspects & Impacts Register

Disposition Statement

This generic Register of Environmental Aspects and Impacts should be read in conjunction with McLaren Construction Ltd Aspects and Impacts Procedure, the

individual Site Environmental Risk Assessments and Environmental and Emergency Plans. These detail how the generic environmental aspects apply and how any

site-specific risks or actual impacts are identified and prevented, controlled or mitigated.

This statement explains the process by which environmental aspects have been identified and evaluated for significance. The aspects have been grouped into the

following topics:

1. Resource efficiency (non-renewable resources, energy and water)

2. Traffic and transport

3. Ground contamination

4. Water and effluent discharge

5. Noise, vibration and other nuisances

6. Air emissions (dusts, odours, greenhouse gases, ozone depleting substances, solvents etc.)

7. Toxic and hazardous substances (including oils and fuels)

8. Deleterious materials (asbestos, PCBs, etc.)

9. Wastes

10. Visual impact / townscape / landscape (including site lighting)

11. Cultural heritage and archaeology

12. Wildlife and natural features

13. Environmental emergencies and external occurrences (impact/collision, flood, etc.)

14. Indirect Environmental impacts

An example of the process by which aspects and impacts were identified is as follows: one aspect identified in the register is wastes and their disposal to landfill.

This aspect was considered significant because of the variety and importance of the potential impacts consequent to the degradation of the wastes after tipping

(leachates, methane / greenhouse gases, odours, visual impact, health concerns, etc.).

Page 2: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

All wastes are automatically considered “significant” due to the specific commitment in the policy statement identifying them for particular attention, as well as the

detailed legal requirements that govern their day-to-day management (policy commitment to comply).

Aspects arising from normal, abnormal and emergency situations have also been identified, including project start-up (demolition and clearance), normal

operations (building and site management) and finishing phases of the project. Examples of abnormal or even emergency wastes would be the need to dispose of

asbestos, or contaminated soil following a spill.

The significant environmental aspects associated with wastes from various activities at operating sites are dealt with in Section 9 below and include:

• Emissions to air / landfill gases

• Releases to water / leachates

• Contamination of land

• Inefficient use of raw materials and natural resources

• Localised nuisance and health impacts close to landfill sites

Consideration has also been given to past, current and future activities, products and services - for example, the requirement for an increasing proportion of

construction materials to be derived from recycled sources.

Page 3: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: RESOURCE EFFICIENCY

Ref Source(s) Impact Description Key To

Impacts

Significance

Status Mitigation & Control

1.1

All activities

using

minerals,

metals,

cements,

timber, etc.

Depletion of mineral resources that are mined,

quarried or otherwise extracted from the natural

environment will deprive future generations of the

ability to enjoy a similar lifestyle to that enjoyed

today.

Key is to maximise resource efficiency, avoid waste

and seek alternative “renewable” resources. Avoid

the use of certain metals and toxic materials where

possible. Design component can influence full life

cycle of building – e.g. through the specification of

control devices.

1,2,3,4,5

Significant

Procurement Objective

Policy on FSC-certified timber

Environmental Project Design / EGN1

1.2

All activities

using energy

Depletion of fossil fuel resources that are mined,

quarried or otherwise extracted from the natural

environment will deprive future generations of the

ability to enjoy a similar lifestyle to that enjoyed

today.

Key is to maximise fuel efficiency, avoid waste and

seek alternative “renewable” fuels. Need to

maximise energy efficiency throughout full building

life cycle. See also Air emissions and greenhouse gas

/ climate change impacts.

1,2,3,4,5

Significant

Energy efficiency objectives at office

premises

Environmental Plan

Environmental Project Design / EGN1

EGN13 Energy Conservation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 4: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

1.3 All activities

using water

Excessive consumption can deplete national

reserves and /or place an additional burden on

existing water supplies.

In the case of abstraction from underground

sources, water consumption also affects the water

table and can have a negative impact on aquatic

ecosystems. The use of suitable control devices can

help to reduce consumption.

1,2,3,4 Significant EGN3 Permits and consents (abstraction

and dewatering)

Environmental Plan

Environmental Project Design / EGN1

1.4 All activities

wherein

resources are

consumed

Environmental damage from the extraction,

processing and distribution processes of natural

resources, whether renewable or not.

1,2,3,4,5 Significant Procurement Objective

Policy on FSC-certified timber

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 5: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: TRAFFIC & TRANSPORT

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

2.1 Pre-tender /

Tender /

Design

Location of the site may generate increases in traffic

volume, resulting in localised congestion, parking

problems and potential nuisance to site neighbours

during both construction and operation.

1, 2, 3 Significant Environmental Plan – traffic management

plan

EGN4 Traffic Management

2.2 Vehicular

Movement &

Access

Increased localised traffic movements and possible

congestion of access routes.

Additional impacts include mud on roads from site

vehicles and potential contamination of land and

water adjacent to routes through dispersal of

polluted run-off from road surfaces.

See also emissions to air, wastes, nuisance, etc.

(Note that Group Environmental Policy identifies

vehicle emissions as key issue).

1, 2, 3 Significant Environmental Plan – traffic management

plan

EGN5 Traffic Management

2.3 Office

Operation

Increased localised traffic movements and possible

congestion of access routes and parking in

surrounding area.

1, 2, 3 Significant EGN5 Traffic Management

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 6: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: GROUND CONTAMINATION

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

3.1 Pre-tender /

Tender /

Design

The impacts to ground quality resulting from the

design, its construction and operation as well as

previous land-uses generating risks to the design

itself.

The MCL Environmental Policy identifies land

contamination as a key issue for prioritisation.

1,2,3,4 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN8 Land Contamination

3.2 Demolition Demolition of existing structures may necessitate

removal or decommissioning of possible sources of

contamination (e.g. on site dumping grounds,

asbestos, old storage tanks above and below

ground, machine bases, sumps etc). These may

have created historical contamination as well as

present an on-going contamination risk.

1, 2, 3, 4 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

3.3 Concrete

Structures

‘Aggressive’ contaminants may attack building, its

foundations and services.

1, 2, 3 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

3.4 Earthworks /

Excavation

Excavation and stockpiling of contaminated spoil

may expose potentially harmful contaminants within

the spoil to site workers or site neighbours (e.g.

during dry conditions).

Contaminants may be mobilised to surface waters or

even groundwater.

1, 2, 3, 4 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 7: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

3.5 Dewatering Waters pumped from contaminated site may

contain excessive levels of pollutants and require

specialist handing and disposal arrangements. Risk

of polluting watercourses.

1, 2, 3, 4 Significant

Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

3.6 Piling Mobilisation of existing contamination vertically or

horizontally through the strata, contaminating

deeper groundwater resources.

1, 2, 3, 4 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

3.7 Storage &

Use of

Chemicals &

Oils

Improper storage and spillages of chemicals/oils to

the ground may cause or contribute to existing

contamination of soil and groundwater.

1, 2, 3, 4 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

EGN10 Oil and chemical storage

3.8 Waste

Storage

Leachates from waste storage areas can cause or

contribute to ground contamination.

In addition to a negative visual impact, litter

accumulation can also be considered a form of land

contamination.

1, 2, 3 Significant Environmental Plan

Procedure EP09 Contaminated land

EGN9 Land Contamination

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 8: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: WATER AND EFFLUENT DISCHARGE

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

4.1 Pre-tender /

Tender /

Design

Design may pollute water resources during

construction and operation. Potential contamination

of groundwater, controlled waters or drainage

systems can result through spillage, run-off, abuse,

vandalism, pumping, de-watering or other

operations.

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

4.2

May involve decommissioning of structures that

contain pollutants (e.g. fuel tanks, chemical stores,

machine bases etc). If not handled properly, these

pollutants may enter surface water/drainage

systems causing pollution.

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

4.3 Earthworks /

Excavation

Pollution of drainage system and/or watercourses

with contaminated particulate matter from spoil

heaps/haul roads.

Sediment run-off to surface waters, affecting aquatic

biota.

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

4.4 De-watering Disposal of abstracted groundwater from

contaminated sites or silty water may pollute

watercourses with impacts upon water quality,

habitats and amenity.

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 9: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

4.5 Concrete

Pours /

Batching

Cement powders/fines have potential to cause

pollution of watercourses if not contained.

Cementitious wastes can damage aquatic life and

contribute to loss of amenity.

1,2,3,4 Significant

Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

4.6 Piling Piling can create a pathway through which

contaminants in the upper soil layers may pass to

deeper sensitive groundwater resources (e.g.

aquifers).

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharges

4.7 Vehicular

Movement &

Access

Pollution of drainage systems and water courses

with oils (hydrocarbons) from vehicles, particulates

and other chemicals. Vehicle / wheel wash effluents.

1,2,3,4 Significant Environmental Plan

EGN3 Permits and Consents

EGN8 Water and Effluent Discharge

4.8 Use of Plant

& Machinery

Potential for losses of oils (fuel, hydraulic oil etc)

from items of plant to surface waters.

1,2,3,4 Significant Environmental Plan

EGN8 Water and Effluent Discharges

4.9 Storage / Use

of Chemicals

/ Oils

Spillage of oils and chemicals from storage failure

and poor handling.

1,2,3,4 Significant Environmental Plan

EGN10 Oil and chemical storage

EGN8 Water and Effluent Discharges

Emergency response plan

4.10 Waste

Storage

Leachates from waste storage areas causing

pollution of surface waters.

1,2,3,4 Significant Environmental Plan

EGN8 Water and Effluent Discharges

EGN4 Waste management

4.11 Site

effluents:

A number of effluents can be generated on site

including waste hygiene waters / sewage, silty

waters from excavations, oils, contaminated wash

waters, etc.

Effluents may contain contaminants and alter the

background characteristic of waters into which they

are discharged – BOD / COD, suspended solids, pH,

oil sheen, chemical content etc.

1,2,3,4 Significant

Environmental Plan

EGN3 Permits and Consents

EGN4 Waste management …

EGN8 Water and Effluent Discharges

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 10: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: NOISE, VIBRATION & OTHER NUISANCES

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

5.1 Pre-tender /

Tender /

Design

Potential for works to present a nuisance both

during construction and operation. Nuisances are

varied but include noise, vibration, dust, odour and

lighting. Group policy has noise from plant and

equipment as a priority.

The MCL Environmental Policy identifies localised

nuisances as a key issue for prioritisation.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

5.2 Demolition

of existing

structure

Dust, noise and vibration may annoy site

neighbours. When it settles, dusts can also damage

crops and contribute to silt pollution in surface

waters.

Lighting may also cause annoyance if not managed

correctly.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

5.3 Earthworks /

Excavation

Dust from excavations may annoy site neighbours

and potentially pose a health risk if contaminated.

Lighting may also cause annoyance if not managed

correctly.

Odours from contaminated sites may cause

annoyance and/or adverse health effects.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 11: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

5.4 Concrete

Batching

Dust, noise & vibration may annoy site neighbours.

Lighting may also cause annoyance if not managed

correctly.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

5.5 Piling Noise & vibration from piling may disturb site

neighbours and cause a nuisance.

Lighting may also cause annoyance if not managed

correctly.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

5.6 Construction

activities

Dusts may be generated by cutting materials

(drainage, masonry and paving flags). Vibration may

result from drilling and breaking operations.

1,2,3 Significant Environmental Plan

EGN6 Noise and Vibration

5.7 Use of Plant

& Machinery

Excessive noise can present hazard to workers.

Excessive noise levels may cause nuisance to site

neighbours/residents (e.g. consider siting of air

conditioning / lift equipment). Extreme cases may

lead to prosecution by the Local Authority or even

civil actions.

Smoke, exhaust gases and particulate matter from

plant and equipment have nuisance potential.

Lighting from vehicles may also cause annoyance if

not managed correctly.

1, 2, 3 Significant Environmental Plan

EGN6 Noise and Vibration

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 12: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

5.8 Vehicle

Movement &

Access

Dust from unsurfaced roads may cause nuisance.

Dust may damage or cause equipment to

malfunction.

Engine noise may cause nuisance when close to

sensitive receptors – when in motion or idling.

Audible vehicle alarms and horns/klaxons can also

generate noise.

1, 2, 3 Significant Environmental Plan

EGN7 Dust and Air pollution

5.9 Waste

Handling &

Storage

Wastes may be transported both on and off-site

causing litter problems.

Storage of contaminated or odorous wastes causing

nuisance to site neighbours.

Certain wastes may attract vermin that can spread

to adjacent sites.

1, 2, 3 Significant Environmental Plan

EGN4 Waste management…

EGN7 Dust and Air pollution

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 13: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: AIR EMISSIONS

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

6.1 Pre-tender /

Tender /

Design

Impacts resulting from the construction and

operation of the design as detailed in the following

rows.

1,2,3,4 Significant Environmental Plan

6.2 Vehicular

Movements

& Access

Vehicle exhaust emissions (NOX SOX CO CO2 PM etc)

contribute to global warming, acid rain and

respiratory health problems.

Dust emissions from unsurfaced roads and dirty

vehicles, uncovered loads, etc. Exceeding relevant

guide limits for key pollutants, especially where in

the vicinity of sensitive receptors.

1, 2, 3, 4,

5

Significant Environmental Plan

EGN7 Dust and Air Pollution

6.3 Use of Plant

& Equipment

Exhaust emissions (NOX SOX CO CO2 PM etc), welding

fumes emissions etc. Potential explosion from

emissions of gases or chemicals.

Exceeding relevant guide limits for key pollutants,

especially where in the vicinity of sensitive

receptors.

1, 2, 3, 4,

5

Significant Environmental Plan

EGN7 Dust and Air Pollution

6.4 Demolition

Construction

Dust from building/structure demolition.

Fibrous materials from deleterious materials (e.g.

asbestos) that have potentially adverse human

health effects. Blown polystyrene and similar

materials may also use ozone-depleting chemicals as

their propellant.

1, 2, 3, 4 Significant Environmental Plan

EGN7 Dust and Air Pollution

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 14: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

6.5 Unauthorised

fires

Smoke fumes and particulates released from

burning vegetation or other waste materials. Dark

smoke is unsightly and bonfires can be considered a

“nuisance” under the legislation (e.g. when smoke

obscures roads).

1,2,3,4 Significant Environmental Plan

EGN7 Dust and Air Pollution

6.5 Painting /

Coating

Use of chemicals and solvents, especially Volatile

Organic Compounds (VOCs) from paints & varnishes,

contribute to ozone depletion.

1, 2, 3, 4,

5

Significant Environmental Plan

EGN7 Dust and Air Pollution

6.6 Heating

Systems

Installation

Exhaust gases NOX, CO CO2 etc) from the

combustion of fuels (typically gas and oil) for heating

of water that contribute to global warming and acid

rain.

1, 2, 3, 4,

5

Significant Environmental Plan

EGN7 Dust and Air Pollution

6.7 Cooling

Systems

Installation

Use of refrigerants that have global warming and

ozone depleting potential (e.g. CFCs, HCFCs, HFCs

etc).

Potential release of bacteria (legionella) to the air

from water treatment systems (e.g. cooling towers

and evaporative condensers).

1, 2, 3, 4,

5

Significant Environmental Plan

EGN7 Dust and Air Pollution

6.8 Ventilation Potential release of bacteria to air via humidification

systems

1, 2, 3, 4 Significant Environmental Plan

6.9 Office

Operation

Use of electricity indirectly contributes to global

warming and acid rain (NOX, SOX, CO2 etc)

Potential release of bacteria (legionella) to air from

cooling and ventilation systems in building.

1,2,3,4,5 Significant Environmental Plan

EGN7 Dust and Air Pollution

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 15: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: TOXIC AND HAZARDOUS SUBSTANCES

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

7.1 All activities

using

hazardous

materials

A wide range of hazardous, irritant, toxic, corrosive,

poisonous and inflammable materials may be

present on site at any time.

Accordingly a variety of controls may need to be

used to ensure their safe storage, handling, use and

disposal – see Health and Safety procedures (ref.

COSHH etc.) – depending upon the type and

quantity of substances involved.

1,2,3,4,5 Significant –

comply with legal

requirements

Environmental Plan

COSHH assessments

7.2 Fuels and oils These materials need careful storage in order to

prevent accidental release to the environment.

Bowsers should have spill trays and, where possible,

be fitted with double skins to contain leaks. All oils

and fuels should be stored on sealed surfaces with

some secondary containment or spill kit.

1,2,3,4,5 Significant Environmental Plan

EGN10 Oil and chemical storage

7.3 Radioactive

materials?

Not normally present on MCL sites (but may be ref.

hospitals etc.??)

1,2,3,4,5 Significant where

present

Subcontractor selection

7.4 Sharps / First

Aid waste

Sharp objects such as broken knife blades present a

safety hazard and may need special waste storage

containers. Similarly, any bandages or other First Aid

waste

1,2,3,4,5 Significant where

present

Environmental Plan

EGN4 Waste management…

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 16: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: DELETERIOUS MATERIALS

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

8.1 Pre-tender /

Tender /

Design

Design / works may incorporate deleterious materials

where alternatives exist (e.g. Ozone Depleting

Substances, etc)

1,2,3,4,5 Significant Environmental Plan

8.2 Demolition Possible presence of deleterious materials within the

fabric of existing buildings or structures (e.g. asbestos

in ceiling tiles, roof linings, chimney/stack linings etc).

Asbestos fibres become airborne once disturbed and

can cause serious respiratory diseases.

1, 2, 3 Significant Environmental Plan

SHE003 procedure

8.3 Excavation /

Earthworks

Possible presence of deleterious materials in the

ground from previous land-uses presenting

environmental and health and safety risks.

1, 2, 3 Significant Environmental Plan

EGN9 Land Contamination

EP09 Contaminated Land

8.4 Office

Operation

Potential asbestos containing materials within the

fabric of the building that present a risk to employees

(e.g. fire doors, boiler rooms, etc)

1, 2, 3 Significant Environmental Plan

SHE003 procedure

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 17: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: WASTE

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

9.1 Pre-tender /

Tender /

Design

Design / works may involve the generation of

significant waste materials that require disposal to

landfill and miss potential for re-use, recycling. MCL

suppliers and subcontractors will generate “active,

inert and special” wastes. Waste management and

minimisation are key McLaren Policy issues.

‘Special wastes’ present an additional threat to the

environment and/or human health. Possible cross

contamination of wastes (i.e. poor segregation) may

prohibit recycling or reprocessing of the materials.

Poor waste management may also result in litter,

pollution of land and water, and there is an

additional fire risk where wastes accumulate.

Wastes attract vermin.

1,2,3,4,5 All wastes are

significant -

comply with legal

and Group policy

commitments

Objectives on wastes

Environmental Plan

EGN4 waste management and minimisation

9.2 Vegetation

Clearance

Generation of green wastes, possibly some ‘difficult’

green wastes (e.g. invasive plants – Giant Hogweed,

Japanese Knotweed, etc – that require special

treatment) to landfill or mulching centres.

Disposal in landfill has associated impacts from

landfill gases and leachates.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan – (local composting

plans?)

EGN4 waste management and minimisation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 18: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

9.3 Demolition Generation of aggregate, timber, metal, plastic,

spoil, tiles, deleterious materials to landfill.

Disposal in landfill and possible associated landfill

gases and leachates. Unnecessary disposal of

materials that may be recycled or re-used.

Some wastes may be ‘special wastes’ (i.e. toxic or

hazardous to human health), thus requiring

specialist treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.4 Earthworks /

Excavation

Generation of spoil, contaminated spoil to landfill.

Disposal in landfill and possible associated landfill

gases and leachates. Unnecessary disposal of fill that

may be recycled or re-used.

Spoil from contaminated sites may be ‘special

waste’ presenting risks to worker health and safety

and requiring specialist treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.5 De-watering Discharge of water, contaminated water to

controlled/foul waters.

Pollution of ‘controlled’ waters from discharge of

liquid wastewaters to surface waters, soakaways etc

(where discharged to controlled waters).

Pollution of foul sewers from discharge of liquid

wastewaters (where discharged to sewer).

Possible programme delays and costs due to

regulatory involvement (e.g. consents/permits

determinations, negotiations with Environment

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

EGN8 Water and effluent discharges

Page 19: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

Agency/Water Service Company etc).

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

9.6 Grouting

Piling

Generation of spoil, contaminated spoil, bentonite

slurry.

Disposal in landfill and possible associated landfill

gases and leachates. Unnecessary disposal of fill that

may be recycled or reused.

Spoil from contaminated sites may be ‘special

waste’ presenting risks to worker health and safety

and requiring specialist treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.7 Brickwork /

Blockwork

Generation of bricks/blocks and cement

Disposal in landfill. Unnecessary disposal of

materials that may be re-used / recycled.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.8 Welding Generation of empty gas bottles and welding rods.

Disposal in landfill.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.9 Carpentry Generation of timber.

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of timber that may be re-used

/ recycled.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 20: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

9.10 Painting /

Coating /

Decorating

Generation of paints, solvents, containers.

Disposal in landfill and possible associated landfill

gases and leachates.

Paints, solvents and containers may be ‘special

waste’ presenting risks to worker health and safety

and requiring specialist treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.11 Plumbing Generation of plastic/metal piping sections, lagging,

solder, packaging

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of items that may be re-

used/recycled.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.12 Plastering Generation of plaster, plaster board, timbers,

packaging

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of items that may be re-

used/recycled.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 21: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

9.13 Furnishings Generation of wood, metal, wire/cabling,

ceramics/tiles, glues, paints, epoxies, sealants,

containers, packaging

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of items that may be re-

used/recycled.

Some items may be ‘special waste’ presenting risks

to worker health and safety and requiring specialist

treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.14 Roofing Generation of metals, felt, tar/bitumen, insulation,

pvc sheeting

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of items that may be re-

used/recycled.

Some items may be ‘special waste’ presenting risks

to worker health and safety and requiring specialist

treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 22: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

9.15 Vehicle and

plant repair

&

maintenance

Generation of oils/greases, refrigerants, aggregates,

glues, paints, sealants, containers, packaging

Disposal in landfill and possible associated landfill

gases and leachates.

Unnecessary disposal of items that may be re-

used/recycled.

Some items may be ‘special waste’ presenting risks

to worker health and safety and requiring specialist

treatment/disposal.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.16 Storage &

Use of

Chemicals

/Oils

Generation of waste chemicals and oils; used

chemical and oil containers. NB - Also need to

consider any contaminated materials used to clean

up after a spill, fire or other environmental incident.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.17 Office

Operations

Generation of paper, cardboard, toner cartridges,

food wastes, furniture, electronic hardware,

packaging

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.18 Purchasing of

Materials

Generation of variety of unnecessary wastes

through over-ordering.

1,2,3,4,5 All wastes are

significant -

comply with legal

and policy

requirements

Environmental Plan

EGN4 waste management and minimisation

9.19 Waste

transport

and disposal

Potential for abusive / fly tipping or incorrect

disposal and treatment if the transport / disposal

process is not managed properly.

2,3,4,5 All wastes are

significant -

comply with legal

and policy

Environmental Plan – subcontractor

controls / waste plans

EGN4 waste management and minimisation

Page 23: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

ASPECT GROUPING: LANDSCAPE & VISUAL

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

10.1 Pre-

tender/Tend

er/Design

Design may be incompatible with surrounding

landscape. Adverse effects on designated sites

(World Heritage Site, Area of Outstanding Natural

Beauty, National Park, Country Park, Special

Landscape Area, Registered Parks or Gardens, etc).

1, 2, 3, 4 Significant Environmental Plan

EGN12 Ecology and Wildlife

EGN1 Environmental design

10.2 Vegetation

Clearance

Reduction in visual amenity due to the

removal/loss/displacement of natural landscape

features (e.g. mature trees, woodland, hedgerows

etc).

1, 2, 3, 4 Significant Environmental Plan

EGN12 Ecology and Wildlife

EGN1 Environmental design

10.3 Demolition

of Existing

Structures

Reduction in visual amenity due to the

removal/loss/displacement of structures (e.g. listed

buildings, scheduled monument/structures etc).

1, 2, 3, 4 Significant Environmental Plan

EGN1 Environmental design

EGN11 Archaeology and built heritage

10.4 All under

‘Erection of

Structure’

The construction of building/structure that is

incompatible with the landscape character.

1, 3, 3, 4 Significant Environmental Plan

EGN1 Environmental design

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 24: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: HERITAGE & ARCHAEOLOGY

Ref Source(s) Impact Description Key To

Impacts

Significance Status Mitigation & Control

11.1 Pre-tender /

Tender /

Design

Damage/disturbance/destruction of features of

cultural, historical or archaeological importance

as detailed below.

1, 2, 3 Significant Environmental Plan

EGN11 Archaeology and built heritage

11.2 Vegetation

Clearance

Destruction/damage to ‘important’ hedgerow,

protected on the grounds of its archaeological

and ecological importance.

Project delays due to regulatory involvement (e.g.

hedgerow retention notices, determination

periods, consents/approvals etc).

1, 2, 3 Significant Environmental Plan

EGN11 Archaeology and built heritage

11.3 Excavation &

Earthworks

Discovery of expected / unexpected

archaeological finds (e.g. burnt or blackened

materials, brick or tile fragments, coins, pottery

or bone fragments, skeletons, timber joints or

post holes, brick or stone foundations, infilled

ditches or middens).

Project delays due to regulatory involvement (e.g.

physical investigation, damage assessments,

consents/approvals for protected structures).

1, 2, 3 Significant Environmental Plan

EGN11 Archaeology and built heritage

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 25: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

11.4 Building

Demolition

Damage/destruction of protected buildings or

structures (e.g. Listed Buildings, Scheduled

Ancient Monuments).

Project delays due to regulatory involvement (e.g.

physical investigation, damage assessments,

consents/approvals for protected structures).

1, 2, 3 Significant Environmental Plan

EGN11 Archaeology and built heritage

11.5 Piling Possible damage to heritage features through

transmitted vibrations.

1, 2, 3 Significant Environmental Plan

EGN11 Archaeology and built heritage

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 26: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: WILDLIFE & NATURAL FEATURES

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

12.1 Pre-tender /

Tender /

Design

Works may temporarily or irreversibly impact on

ecology during siting, construction, operation and

demolition (impacts are detailed below).

1, 2, 3,4,5 Significant Environmental Plan

EGN12 Ecology and wildlife

12.2 Site /

Vegetation

Clearance

Temporary and potentially irreversible loss of

habitat through change in land-use, destruction of

ecosystem and occupation of land for structure or

construction site compound.

Damage/destruction and disturbance to adjacent or

nearby statutory sites (e.g.Sites of Special Scientific

Interest, Areas of Outstanding Natural Beauty,

National Nature Reserves etc).

Damage/destruction and/or disturbance to

protected flora and fauna as a result of the above.

Damage/destruction to protected trees or their

roots.

1, 2, 3,4,5 Significant Environmental Plan

EGN3 Permits and Consents

EGN12 Ecology and wildlife

12.3 Demolition Noise and dust emitted from demolition activities

may annoy site neighbours as well as impact upon

sensitive ecological receptors.

1, 2, 3, 4 Significant Environmental Plan

EGN12 Ecology and wildlife

12.4 De-watering De-watering may impact adjacent ecology by

causing alterations to groundwater levels and

stream/river flows.

1, 2, 3 Significant Environmental Plan

EGN12 Ecology and wildlife

Page 27: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

12.5 Use of Plant

& Machinery

Noise emitted from plant may cause

nuisance/disturbance to protected species (e.g.

nesting birds, bats etc)

1, 2, 3 Significant Environmental Plan

EGN12 Ecology and wildlife

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

12.6 Storage/Use

of Chemicals

& Oil

Potential for spillage of chemicals and oils to

ground/water may impact adjacent ecological

receptors by following the flow of surface or

groundwater off-site.

1, 2, 3 Significant Environmental Plan

EGN12 Ecology and wildlife

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 28: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: ENVIRONMENTAL EMERGENCIES AND EXTERNAL OCCURRENCES

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

13.1 Collision Collision / impact from road/site vehicle, train, plane

accident may result in fire, explosion, material

damage, spillage or other occurrences that generate

environmental impacts. Careful consideration should

therefore be given to locating stores etc. when

setting up site in order to avoid such risks.

1,2,3,4 Significant Environmental Plan

Emergency Plan

EGN2 Site set up

EGN16 material storage

EGN20 Spillage response

13.2 Fire Fire causes material loss but also has adverse

impacts on the environment:

• emissions of toxic fumes, smoke, dusts

• contaminated run-off fire-fighting waters

• generation of wastes (fire-damaged materials)

Prevention must be the priority, but it may also be

necessary to consider mitigation techniques to

minimise environmental damage (containment of

contaminated run-off or its diversion into a

sacrificial area rather than down drains).

1,2,3,4 Significant Environmental Plan

Emergency Plan

EGN8 Water and Effluent discharge

13.2 Weather Adverse weather conditions such as high winds and

flooding can damage the product (building and

contents) and/or plant, equipment and materials.

Check whether site is situated on floodplain and

take suitable actions in the event of any flood alerts

in order to minimise damage. Consider other

weather extremes (snow, ice, etc.) and their

potential effects on the works and the environment.

1,2,3,4 Significant Environmental Plan /

Emergency Plan

Page 29: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

13.3 External

releases

External release of pollutants (gas, dusts, liquids,..)

may have an impact upon the health and safety of

employees, and possibly upon materials or building

fabric depending upon their nature.

1,2,3,4 Significant Environmental Plan

Emergency Plan

EGN7 Dust and Air pollution

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 30: Environmental Aspects & Impacts Register

ENF001 | 05/13 Rev – ASPECTS & IMPACTS REGISTER |

ASPECT GROUPING: INDIRECT ENVIRONMENTAL ASPECTS

Ref Source(s) Impact Description Key To

Impacts

Significance

Status

Mitigation & Control

14.1 Product /

Building

operation

and use

Once the building is handed over, it will continue to

have most if not all of the aforementioned impacts

on the environment through periodic decoration

and repairs/refurbishment, grounds maintenance,

energy consumption etc.

McLaren is able to influence the full life cycle,

particularly when contracts are of a design and build

nature. Accordingly, full consideration should be

given in the design stage to the full life cycle effects

1,2,3,4,5 Significant Project Design

Handover procedure (copies of project EMS

documents

EGN1 Environmental design

14.2 Product /

Building

demolition

Upon decommissioning, there will be opportunities

to re-use or recycle building materials and

components.

Material selection and construction techniques can

influence the demolition process and

1,2,3,4,5 Significant Project Design

14.3

Interfaces

with Group/

other Jarvis

companies

Ability to influence or be influenced by other parts

of group (e.g. personnel policies on recruitment,

home working, car provision, etc.)

1,2,3,4,5 Significant SHE meetings and steering groups

EGN13 Energy conservation

Key To Impacts: 1 = Customer, 2 = Site Neighbours, 3 = Other Contractors, 4 = General Public, 5 = Global

Page 31: Environmental Aspects & Impacts Register
Page 32: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 2 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

AUTHORISATION AND ISSUE RECORD The following Project Environmental Plan has been prepared in accordance with the Environmental Management System (EMS) Procedure C9 – Operational Control. I authorise the use of this plan as the main control element of the EMS on the above contract. This should be read with the ‘Electronic’ access to the Documented Environment Management System and Manual. Name Adam Onyett Signature Date 29.08.13 Job Title SHEQ Coordinator

The Project Environmental Plan is to be issued to the Project Team, listed below, who shall agree to comply with its contents at site level and maintain the necessary documentation listed within it. The working copy of the plan is to be held on site and updated when applicable.

Name of Recipient Job Title Signature Date

The Site Manager, supported by the Contracts Manager and SHEQ Coordinator, is the key person within this system and shall be responsible for the following;

Method of work undertaken on the project matches the client and regulatory authorities’ requirements and minimises the effect of our works on the environment.

Verification that approved working procedures and regular inspections are implemented and all personnel are compliant.

Ensuring that all personnel on the project are aware of their responsibilities within the EMS, arranging training where necessary (via the SHEQ Coordinator).

Holding the current version of the EMS and advising the project team of the relevant procedures and records to be kept.

Page 33: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 3 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

1. DESCRIPTION OF PROJECT

The project is described in the Tender Information Pack issued by WSP and summarised in this Health & Safety Plan. This includes, but is not limited to, the following activities;

Mobilisation and Set up Trial Holes Unexploded Ordnance Survey Breaking up of Concrete Slabs if req Earthworks Installation of Sub Station Installation of Utility Services Installation of Drainage Construction of Site Access Road Traffic & Materials Management

Risk Assessments with an associated Method Statement will be produced for each of these activities prior to the commencement of any element of the works.

The Works is estimated to be a 40 week project to commence 19th August 2013.

2. RESPONSIBILITES WITHIN PROJECT TEAM

Specific environmental site responsibilities on this project are outlined in documents P4.R1.1 (for Contracts Manager) and P4.R1.2 (for Site Manager) of the OHSMS. These documents will be included in Section 1 of the Health & Safety ‘As Built’ File. Please read with the site staff structure and the roles and responsibilities for your position as designated or agreed. Agree your specific role on this project with the Contracts Manager (see Appendix C of the ‘C22 - Health and Safety Plan’). Site notice boards must be established as the company standard for the site office and welfare unit, with all emergency details clearly displayed.

Specific Procedures and Responsibilities

Procedure

Description of Task Documents Generated Who

C9 Operational Control R1.C9 - Project Environmental Plan SC/CM C1 Legal & Other Requirements R1.C1 – Legal Requirements SC/CM C7 Communication R1.C7 – External Communication CM/SM C11 Emergency Planning R1.C11 – Emergency Plan

R2.C11 – Emergency Contacts CM/SM

C14 Legal Compliance R1.C1 – Legal Requirements SC/CM C15 Non Conformance Control R1.C15 – Non Conformance &

Corrective Action Record SC/CM/SM/G

C16 Control of Records R1.C16 – Control of Documents SM/E C17 Internal Audits R2.C17 – Internal Audit Record

R3.C17 – Site Review/Inspection SC SM

E1 Environment Aspects and Risk Assessment

R1.E1 – Significant Aspects and Impacts Summary

R2.E1 – Aspect Significance Assessment (Pollution)

R3.E1 – Aspect Significance

SC/CM/SM

Page 34: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 4 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

Assessment (Resources) R4.E1 – Significant Aspects Impact

Control Sheet H&S

Standard Site Specific Environmental

Information for Site Workers/Visitors

Method Statements & Induction SM

SC - SHEQ COORDINATOR CM - CONTRACTS MANAGER SM - SITE MANAGER G – GANGER 3. MONITORING AND AWARENESS

3.1 The Site Management Team is required to carry out regular monitoring of the system

and will complete a detailed checklist as part of an Environmental Site Review (detailed above). It is important that all established procedures are followed and that any problems are reported immediately. The site will also be subjected to a formal internal audit to assess the operation of the EMS.

3.2 Environmental awareness will be continually promoted and further improvements

discussed by carrying out Toolbox Talks on a regular basis to ensure that all operations are carried out to minimise the risk of pollution and reduce the volume of waste produced on site. All site personnel and sub-contractors will be required to sign the attendance record for these talks.

3.3 Environmental considerations will form part of the initial site induction, where the contents of this management plan will be disseminated to all personnel to ensure the awareness of its contents to all persons on site.

3.4 Noise will be monitored weekly using a handheld noise meter and logged on document ‘Noise Monitoring Record’.

3.5 Dust will be visually monitored daily and records kept within the ‘Dust Monitoring Record’.

3.6 Vibration will not be monitored as the level of vibration from the infrastructure works will be limited to compaction and tracking of plant, so is therefore deemed unnecessary.

3.7 There is a requirement to carry out water sampling on 4 watercourses around site. 4. CONTROL OF WORKS

4.1 All incidents, no matter how minor, are to be reported to D. Morgan Site Manager and Client team (see organisational chart Appendix A). External parties will be contacted if required by D Morgan Site Management.

4.2 Fuel will be stored on site in limited quantities in a COSHH store which will be bunded,

with a collection tray for spill prevention and control. Refuelling operations will be undertaken by daily visits from a mobile bowser and will take place in designated areas where drip trays will be utilised to catch any potential spillages.

4.3 To further mitigate any potential contamination to ground or watercourses, the bowser is equipped with a quick release fuel nozzle and all operated plant will be equipped with spill kits to tackle any spillages which may occur (no matter how minor).

Page 35: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 5 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

4.4 All site fitters will be inducted to site rules. Any waste arising from maintenance / fitting work shall be removed from site by the fitter and disposed of via either the D Morgan main office fitting service waste agreements (i.e. waste oils, grease cartridges, rags) or by our sub-contractor’s waste streams.

4.5 Plant, particularly articulated dump trucks, will have designated haul routes and

permitted areas for parking. These vehicles are to avoid causing any undue damage to flora and fauna which is not to be cleared in this phase of the works. Every effort will be made to reduce the impact of these works on the local ecology onsite.

4.6 Wherever possible materials will be reused locally not only to reduce waste, but also to

reduce emissions with localised rather than long haul movement of materials. It is also intended to maximise ‘dig once, place once’ options, minimising double handling of materials (saving both noise and emissions pollution).

4.7 Any hydraulic breaking operations will be kept to a minimum and within the agreed site

working hours. These operations, wherever possible, will be undertaken away from the site boundary and local residences.

4.8 Water management will be a high priority on this project. Localised bunding and lagoons

may be required to prevent surface water adversely affecting the works. It may also be necessary to excavate ‘grips’ or ‘v’ ditches to capture water and channel towards a holding area (lagoon), preferably the permanent works swales.

4.9 Where water has collected in excavations or sump holes and is required to be pumped

clear, the water will be recharged to adjacent grassed areas of site in order to prevent its release into any watercourse. If any is suspected to be contaminated (it has oily residues apparent, odour or discolouration) then it must not be pumped until verified.

4.10 Wherever possible all breakable materials on site will be processed to engineering

materials and used within the works. This will reduce the number of vehicular movements on the local roads and limit nuisance to the local community.

4.11 During the works all personnel shall remain vigilant to the potential of contaminated materials. If any materials are suspected to contain contamination (oily residues, odour or discolouration), then works will stop and samples will be taken to determine whether or not the materials are contaminated.

4.12 It is believed that asbestos containing materials may be found on site. During the clearance works all personnel shall be briefed as to the likely presence and on finding such materials they will be fenced off and a plan for dealing with them put in place. This will be to confirm that the materials contain asbestos; if notifiable then a specialist sub-contractor will be procured (if not, then trained D Morgan personnel will undertake the works); the materials will be double bagged in asbestos bags and placed in an enclosed skip for offsite disposal to a licensed site to accept asbestos waste.

4.13 There are no trees within this project that require specific protective measures and only those trees identified in the planning area for clearance will be removed.

4.14 During excavation works it is not anticipated that any archaeological findings will be made. However, all personnel will observe a watching brief and stop work immediately if any suspected archaeological findings are made.

4.15 Noise is a particular concern on all construction sites and as such every effort will be made to limit and control noisy operations. No plant will be left idling when not in use and

Page 36: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 6 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

all plant will be suitably silenced in line with its manufacture. Noisy operations will not be permitted to continue for prolonged periods and not undertaken outside of normal working hours.

4.16 Background noise monitoring will be undertaken prior to the commencement of the works. During the construction phase, periodic noise monitoring will be undertaken. This will be using a handheld device weekly over a 15 minute period at specific locations, observed at random times during the week.

4.17 Dust control, mitigation and monitoring measures will be put in place for the duration of remediation and earthworks on site. D Morgan will be employing dust suppression and sweeping of selected roads on and around site during the works, as and when considered necessary. The generation of dust on site will be minimised, particularly during drier weather and controlled by the use of dampening down techniques using water bowsers. A tractor and bowser will be used to damp down all haul routes and any other areas with the potential to generate dust. The site supervisory team will monitor dust generation closely.

4.18 All plant used on site will be modern and well maintained such that any emissions are

within acceptable limits for the plant being used. This also ensures optimum fuel consumption.

4.19 As the works are scheduled to progress through winter months, there will be a requirement for temporary lighting. This will be set up with task lighting towers at specific work areas. All lighting will be set up such that it is focussed on work areas and consideration will be made to avoid such lighting being directed near to sightings on live roads.

4.20 In order to maintain a high standard of good practice, Omega Warrington Limited has requested that the works are registered to the Considerate Constructors Scheme (CCS) and adhere to the scheme’s code of practice. In accordance with BREEAM requirements, a CCS score between 32 and 40 will be achieved and all sections within the scheme will achieve a score more than or equal to 3. The scheme will be implemented through each sub-contractor.

4.21 Additionally, all office staff must ensure they adopt the D Morgan ‘print both sides policy’

wherever possible and reduce the use of paper and printer ink as far as practicable. All personnel will be required to follow the ‘switch me off’ policy when leaving a room and switch off any electrical appliances which do not need to be consuming electricity.

4.22 Every effort must be made to segregate office, canteen and packaging waste and place in the relevant receptacles for recycling. There will be separate bins for paper, cardboard, plastics, cans and general waste.

5. EMERGENCY PROCEDURES

5.1 Fuel/Oil (or other potentially damaging substance) Spillage

In the event of a spillage incident the following procedure must be followed;

Eliminate sources of ignition and cordon off area. Attempt to contain the spillage without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of the

spillage, location and measures taken at present.

Page 37: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 7 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

Where necessary, use plant from the locality to form bunds, excavate to Dump Trucks or any other action which may contain/mitigate the spillage.

Use spill kits from the plant to clean up or if necessary use adjacent soils. Do not allow the spillage to enter a watercourse. Site Manager to inform WSP staff and, if necessary, contact the following;

o Fire 999 o Environment Agency 0800 807060 o United Utilities 0845 746 2200

Site Manager to liaise with the above and agree measures to remediate area. Site Manager to complete an ‘Incident Report Form’ or NCR.

5.2 Surface Water Release

In the event of surface water release the following procedure must be followed;

Attempt to contain the release without risk to personal health and safety. Inform a member of the Site Supervisory Team of the approximate volume of

water released, location and measures taken at present. Where necessary/possible, use plant from the locality to form bunds or excavate

a sump (remembering to check Permit to Dig prior to breaking ground). Site Supervisory Team to call in bowser or pumps to ensure that the release is

contained in the bund/sump and does not overflow. Site Manager to inform WSP staff and, if necessary, contact the following;

o Environment Agency 0800 807060 o United Utilities 0845 746 2200

Site Manager to liaise with the above and agree further/improved mitigation measures.

Site Manager to complete an ‘Incident Report Form’ or NCR.

5.3 Emergency Preparedness These emergency procedures should be brought to the attention of all site personnel and, at a suitable time during the works, drills should be carried out to ensure that the emergency arrangements are effective and understood by all personnel.

Page 38: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 8 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

SITE WASTE MANAGEMENT PLAN 6. SITE WASTE MANAGEMENT PLAN:

In line with the CL:AIRE Development Industry Code of Practice (2008) and under the objectives of the Site Waste Management Plan Regulations (England) 2008, the client and contractor shall provide a Site Waste Management Plan.

All materials will be separated/segregated as far as reasonably practicable in order to minimise the quantities of mixed materials. The waste hierarchy will be considered at all times.

The site arising materials are detailed in the tender documents and site method statements. The materials have been identified as soils, brick & concrete, vegetation, trees & hedges and general waste.

The fate of all materials will be tracked and recorded within the tables on the following pages of this Plan.

Typically; Soils Suitable engineering materials will be used for cut to fill operations. Unsuitable inert materials will be used within the landform. Brick and/or Concrete Any brick and/or concrete arising from the works will be processed (crushed) to produce engineering materials. Concrete will be crushed to 6F2 specification and brick will be used for hardcore purposes. Any tarmac arising from the works will be incorporated into the processed materials in quantities not exceeding those from the ‘Specification for Highway Works’, Series 600, Table 6/1 for the type of aggregate being produced. Vegetation, Trees & Hedges All vegetation, trees and hedges will be dealt with in the Site Clearance; chipped and cut up as necessary. Chippings will remain on site, with cuts and stumps being removed from site. General Waste All general waste will be separated into the following categories and recycled as far as possible; paper, cardboard, plastics, cans and general waste. The estimated quantities of these wastes is very low, but will be tracked throughout the works.

Page 39: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 9 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

WASTE RECORDS

Date removed

Quantity (m3)

Waste type Waste Carrier Waste Management

Facility taken to

Confirmation of delivery

Waste management route (reused on/off site, recycled on/off site, recovery, landfill,

otherwise disposed)

Transfer records received and filed

Page 40: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 10 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

ACTUAL QUANTITIES m3 / tonnes (delete as required) Waste Type

Waste Materials EWC Waste minimisation methods used

Volume re-used Volume recycled Volume recovered in other ways

Volume sent to landfill

on-site off-site on-site off-site

Iner

t

Concrete 17-01-01 Brick 17-01-02 Tiles / ceramics 17-01-03 Rubble (mix of concrete, brick, tiles etc)

17-01-07

Non

-haz

ardo

us

Soils 17-05-04 Metal 17-04-07 Timber 17-02-01 Plasterboard Cable & wiring 17-04-11 Office/canteen 20-01-01

(paper)

20-01-08 (canteen)

Glass 17-02-02 Plastic 17-02-03 Mixed waste

Haz

ardo

us Asbestos 17-06-05

Contaminated soil 17-05-03

Other

Page 41: Environmental Aspects & Impacts Register

PROJECT ENVIRONMENTAL PLAN

Omega South Zone 7 Phase 1

New Hey, Chester Road, Great Sutton, Ellesmere Port, Cheshire CH66 2LS Page 11 of 11

SHEQ / DM/ R1C9/REV02 JAN 12

WASTE QUANTITY COMPARISON Waste type

Waste Materials EWC Estimated Quantity Actual Quantity Difference (+/-) Reason for variance (m3 / tonnes) –

delete as appropriate (m3 / tonnes) - delete

as appropriate

Iner

t

Concrete 17-01-01 Brick 17-01-02 Tiles / ceramics 17-01-03 Rubble (mix of concrete, brick, tiles etc)

17-01-07

Non

-haz

ardo

us

Soils 17-05-04 Metal 17-04-07 Timber 17-02-01 Cable & wiring 17-04-11 Office/canteen 20-01-01

(paper)

20-01-08 (canteen)

Glass 17-02-02 Plastic 17-02-03 Mixed waste

Haz

ardo

us Asbestos 17-06-05

Contaminated soil 17-05-03

Other

Page 42: Environmental Aspects & Impacts Register

MMS 046 | 02/13 rev i 35 SHEQ MANAGEMENT PLAN |

Along with any client objectives issued and to assist the project team and contractors the following objectives have

been agreed with the project team

• Minimize dust during the project to surrounding environment

• Minimise waste and maximise recycling with a target of 2% waste to landfill

• Environmental awareness tool box talks to operatives on refuelling, house keeping, recycling etc

• Monitor aspects and impacts register

PRINCIPAL ENVIRONMENTAL LEGISLATION RELATING TO THE PROJECT

Refer to McLaren Legislation Register QMS 005 on McLaren Portal.

14.2 Liaison with Site Neighbours

Undertake leaflet or letter drops to all close neighbours to the site to inform them of the likely start date(s) for

construction and for any operations that may be particularly noisy or carried out an unsociable hours. This practice is

considered good practice as informed neighbours are less likely to complain.

14.3 Establishment of Site Accommodation

Wherever possible, the location for accommodation will be reviewed to avoid visual impact to adjoining neighbours

and for wastewater discharge to a suitable approved sewer. Alternative arrangements shall be made for disposal of

sewage via specialist contractor should this not be possible. If possible the accommodation will be sited on an area of

proposed hardstanding for incorporation into the contract works as this will avoid disruption of the existing

environment.

14.4 Environmental Impact & Aspect Control Measures

The following key control measures will assist in minimising the environmental impact. See also Pre-Commencement

Health Safety and Environmental Planning Meeting Record SAF01 for site specific environmental aspects and impacts

identification. ENF001 05/13 Environmental Aspects & Impacts Register found at Appendix 8.

14.5 Earthworks Arisings

Arisings from earthworks and piling shall be stored on agreed areas for the placement of excavated materials on site.

Use arisings as much as practicable on site to minimise off-site disposal.

The objective is to ensure that the least impact is generated and ecologically sensitive areas of the site are not

damaged by indiscriminate dumping or storage.

14.6 Vehicles and Plant

If at all possible, designate specific times for deliveries outside normal peak hours and to avoid unsociable hours and

consequential disruption to neighbours.

Plant shall be positioned so that exhaust emissions do not cause damage or nuisance, and kept to a minimum by

regular maintenance.

14.7 Diesel Storage and Refuelling

Ensure that all diesel stored on site is in a secure tank and properly bunded. As far as practicable, ensure that all

refuelling is undertaken in a safe, appropriately designated area. Bunds should be of adequate capacity to contain

110% of the capacity, leakproof and kept empty of rainwater and other materials. This will avoid pollution of the

ground, and to avoid prosecution for pollution or nuisance.

Page 43: Environmental Aspects & Impacts Register

MMS 046 | 02/13 rev i 36 SHEQ MANAGEMENT PLAN |

14.8 Site Roads/Access routes

Ensure that site access roads are kept as clean as possible to prevent excessive contamination to the public highway.

Speed restrictions may also be imposed to prevent spread of dust.

14.9 Plant and Wheel Washing

No plant or equipment shall be washed out where there is the possibility of contamination to any natural

watercourse, particularly regarding concrete. When necessary, special washing facilities / locations shall be

established.

14.10 Storage of materials, fuels, oils and chemicals

All fuel, oil and chemicals shall be stored in containers specifically manufactured for the purpose, and/or

bunded/double skinned to prevent contamination in the event of spillage, damage. Tank capacity shall be checked

before delivery to prevent overfilling. Special care shall be taken when receiving and storing items such as oil,

chemicals, cement, lime, and paint to prevent spillage and contamination.

The contents of storage containers shall be clearly marked, to prevent accidental cross contamination.

‘Drums’ shall also be stored with lids uppermost to prevent leaking and contamination.

A licensed waste disposal contractor or the original supplier shall remove leaking or empty containers from site.

All valves and nozzles shall be protected from vandalism and unauthorised use by means of a padlock. Where this is

not possible, tanks/bowsers shall be stored in secure compound areas.

14.11 Noise

Choose plant and machinery to minimise noise emissions consistent with the technical requirements of the works. Use

noise suppression equipment if practicable. Adhere to any working hour restrictions that have been placed on the

project. Be vigilant at avoiding inadvertent excessive noise during night-time operations.

14.12 Dust

Provide damping down methods of any operations that may generate dust, these may include such activities as

earthworks, cutting, planning and sanding or by utilising plant and equipment with dust extraction and collection

facilities. Speed restrictions may assist on site access roads to mitigate this.

14.13 Lighting

The use of lighting for the works and temporary accommodation shall be carefully selected to ensure it is efficient and

effective, and positioned to ensure that light spillage is kept to a minimum.

14.14 Visual appearance

Care should be taken to ensure an overall positive attitude to housekeeping of the site, such as fencing, storage or

equipment and materials, avoidance of litter and windblown waste etc. This will provide all parties concerned with a

good impression of environmental controls leading to an enhanced perception

Page 44: Environmental Aspects & Impacts Register

MMS 046 | 02/13 rev i 37 SHEQ MANAGEMENT PLAN |

15. WASTE MANAGEMENT

15.1 Waste Storage

Take active steps to ensure that MCL responsibilities under the Environmental Permitting Regulations 2010 and the

Waste (England and Wales) Regulations 2011 are properly discharged, particularly in the accurate completion, and

secure retention, of waste transfer notes. Consider possibilities for segregation of waste into different mainstream

material types (wood, metals, etc) for possible recycling.

Waste shall be stored appropriately depending on type and classification, i.e. Controlled waste, Hazardous waste and

General wastes. In any event, waste storage shall be kept to a minimum and in suitable containers or locations for

disposal. Whenever possible segregation shall be implemented to allow for recycling.

Where Hazardous waste is identified, it shall only be segregated and stored following approved methods from the

Environment Agency.

MCL will maintain a Site Waste Management Plan (SWMP) in accordance with The Site Waste Management Plan

Regulations 2008 this can be found at in the master filing system located in the site office. The SWMP will be kept for

two years after the completion of the project and archived accordingly.

15.2 Waste Disposal

Duty of care shall be applied to all waste, and it shall be ensured that all waste disposals are carried out by registered

contractors and records of disposal controlled by waste transfer notes. Waste disposal containers/vehicles shall be

covered during transport to prevent contents escaping.

Hazardous waste shall be controlled and disposed of following the Environment Agency approved procedures, and by

implementing their consignment note system.

Hazardous Waste producer licence is to be applied prior to the commencement of the project

16. QUALITY PLAN

16.1 Project Description

A brief description of the works is detailed in the SHEQ Plan.

16.2 Management Responsibility

It is the Site Managers responsibility to ensure that the requirements of MCL’s Quality Management Policy Manual

and this Project Specific Quality Plan are implemented. The Site Manager will delegate responsibilities for quality

activities to members of the site management team.

Details of the site management structure are given in the SHEQ Plan.

16.3 Quality Plan & Quality System

16.4 Quality Policy

A copy of the Company’s Integrated Health Safety Quality and Environmental Policy is detailed in MMP which can be

found in all location.

Page 45: Environmental Aspects & Impacts Register

MMS 046 | 02/13 rev i 38 SHEQ MANAGEMENT PLAN |

16.5 Quality Manual & Project Quality Plan

To meet the requirements of the client, MCL applies a quality system in conjunction with other management controls.

MCL’s Management Procedures Manual (MMP) describes the system in detail. Specific contract Quality Management

requirements are detailed within this Quality Plan, or can be found in other sections of the SHEQ Plan and the

Company MMP procedures.

17. CONTRACT REVIEW

17.1 Contract Review Procedures

Contract Review Procedures are detailed within the Company MMP manual specifically by the Customer Focus and

Customer Related Processes (Tenders) process flow chart, which includes but is not limited to:-

• Tender Review

• Tender Adjudication

• Contract Award and Mobilisation

• Employer Pre – Contract Start Meeting

• Internal Pre – Contract Start Meeting

• Progress meetings

Reviews take place at award of contract, prior to commencing works and at regular intervals during the course of the

contract (usually monthly).

18. DESIGN CONTROL

18.1 Designer

The designer(s) where applicable, are detailed in the SHEQ Plan Directory

The designers will be accredited to a recognised professional body ie RIBA, ICE etc. and a copy of the certification will

be held on the designers file.

18.2 Design Control Procedures

Design will be controlled in accordance with Company MMP Manual specifically the Design and Development Process

Description flow chart which includes but is not limited to:-

• Identification of Design Requirements

• Risk Assessments

• Design Approval

• Appointing and Control of Design Authority

• Design Review Meeting Minutes

18.3 Design Review / Liaison with Client

Design meetings between the respective organisations will take place to review the design process. Calculations and

drawings will be forwarded to the client or their representative for comment / approval prior to related construction

works taking place. MMS033 – Design Approval Tracking Schedule refers.