environmental impact assessment (eia)mofe.gov.np/noticefile/eia sardu_ bridge_sk _1566806043.pdf ·...
TRANSCRIPT
Environmental Impact Assessment (EIA)
Study of
Sardu Khola Bridge Project
Along Dharan-Mangalbare-Bishnupaduka Road, Sunsari District,
Province no. 1
Submitted to:
Government of Nepal
Ministry of Forest and Environment Singha Durbar, Kathmandu
Submitted through:
Government of Nepal
Ministry of Federal Affairs and General Administration Singha Durbar, Kathmandu
Proponent:
Department of Local Infrastructure Shree Mahal, Pulchok, Lalitpur, Nepal
Telephone: 977-1-5555001, 5555362, 5543197
Fax: 0977-1-5555724
Email: [email protected] , [email protected]
August, 2019
EIA of Sardu Khola Bridge Project DoLI
ii
Table of Contents
Table of Contents .............................................................................................................. ii
List of Figures .................................................................................................................. vii
ANNEXEXS.................................................................................................................... viii
Acronyms and Abbreviations ......................................................................................... ix
कारयकारी सारााश ..................................................................................................................... ix
Executive Summary ....................................................................................................... xiv
CHAPTER 1: INTRODUCTION .....................................................................................1
1.1 Name of the Proposal and Brief Introduction ............................................................1
1.2 Name and Address of the Proponent ..........................................................................1
1.3 Institutional Responsibility for Preparing EIA Report ...............................................1
1.4 Name and Address of Institute Preparing the Report .................................................2
1.5 EIA Study Team and Declaration ..............................................................................2
CHAPTER 2: SUMMARY OF THE PROPOSAL.........................................................3
2.1 Introduction ................................................................................................................3
2.1.1 General Project Background ...................................................................................3
2.1.2 Necessity of Sardu Khola Bridge ............................................................................3
2.2 Project Location .........................................................................................................4
2.2.1 Salient Features of the Project .................................................................................4
2.3 Project Area Delineation ............................................................................................8
2.4 Objectives of the Proposal..........................................................................................8
2.5 Objectives of the EIA Study ......................................................................................8
2.6 Rationale for conducting EIA ....................................................................................9
2.7 Impact on land use......................................................................................................9
2.8 Adverse Impact on Environment, Impact on Human Life, Population Pressure .......9
2.9 Damaged to be suffered by local goods and objects ................................................10
2.10 Approach Road .......................................................................................................10
CHAPTER 3: METHODOLOGY ADOPTED .............................................................11
3.1 Preparatory Works for EIA Conduction...................................................................12
3.2 Preparation of Scoping Document and Terms of Reference (TOR) ........................12
3.3 Conduction of Field Data Collection for EIA Study ................................................13
3.4 Preparation of EIA Document ..................................................................................16
EIA of Sardu Khola Bridge Project DoLI
iii
CHAPTER 4: DETAILS OF THE PROJECT .............................................................18
4.1 Type of Proposal ......................................................................................................18
4.2 Bridge Design ...........................................................................................................18
4.3 Land Requirement ....................................................................................................18
4.4 Construction Approach and Activities .....................................................................18
4.5 Possible Emissions and Waste Generation...............................................................19
4.6 Energy Use ...............................................................................................................20
4.7 Human Resource ......................................................................................................20
4.8 Project Implementation Schedule.............................................................................20
CHAPTER 5: EXISTING ENVIRONMENTAL CONDITION .................................21
5.1 Physical Environment ..............................................................................................21
5.1.1 Physiography and Topography ..........................................................................21
5.1.2 Geology and Soil Type ......................................................................................22
5.1.3 Engineering Geology .........................................................................................23
5.1.4 Geomorphology .................................................................................................23
5.1.5 River Bank Stability ..........................................................................................23
5.1.6 Flood and Sedimentation ...................................................................................23
5.1.7 Ground water Condition ....................................................................................24
5.1.8 Seismicity of the Project area ............................................................................24
5.1.9 Climate...............................................................................................................25
5.1.10 Drainage and Hydrology .................................................................................26
5.1.11 Air Quality, Water Quality and Noise Levels .................................................26
5.1.12 Land Use ..........................................................................................................27
5.2 Biological Environment ...........................................................................................27
5.2.1 Forests within Project Area ...............................................................................27
5.2.2 Vegetation ..........................................................................................................28
5.2.2 Ethno-Botany and NTFPs ..................................................................................29
5.2.3 Domesticated Plants ..........................................................................................31
5.2.4 Rare, Threatened and Protected Plants ..............................................................31
5.2.5 Wildlife ..............................................................................................................31
5.3 Socio Economic and Cultural Environment .............................................................34
5.3.1 Population and Household .................................................................................34
EIA of Sardu Khola Bridge Project DoLI
iv
5.3.2 House Type, Ownership and Settlement Pattern ...............................................35
5.3.3 Caste and Ethnicity ............................................................................................35
5.3.4 Language ...........................................................................................................36
5.3.5 Religion and Culture ..........................................................................................37
5.3.6 Literacy and Education ......................................................................................37
5.3.7 Occupation .........................................................................................................38
5.3.8 Migration Pattern ...............................................................................................38
5.3.9 Public Health and Sanitation .............................................................................38
5.3.10 Energy Use ......................................................................................................38
5.3.11 Service Facilities..............................................................................................39
CHAPTER 6: IDENTIFICATION OF IMPACTS ......................................................42
6.1 Beneficial Impacts ....................................................................................................42
6.1.1 Beneficial Impacts during Construction Phase ..................................................42
6.1.2 Beneficial Impacts during Operation Phase ......................................................43
6.2 Adverse Impacts .......................................................................................................44
6.2.1 Pre-Construction Phase......................................................................................44
6.2.2 Construction Phase ............................................................................................44
6.2.3 Operation Phase .................................................................................................48
CHAPTER 7: PROJECT ALTERNATIVES ...............................................................53
7.1 No Action Option .....................................................................................................53
7.2 Project Alternative....................................................................................................53
7.3 Alternative Location/Site .........................................................................................53
7.4 Alternative Design and Construction Approach ......................................................54
7.5 Alternative Schedule and Process ............................................................................54
7.6 Alternative Resources ..............................................................................................54
7.7 Other matters ............................................................................................................54
CHAPTER 8: ENVIRONMENTAL IMPACTS, ENHANCEMENT AND
MITIGATION MEASURES ..........................................................................................55
8.1 Beneficial Impacts and Augmentation Measures .....................................................55
8.2 Adverse Impacts and Mitigation Measures ..............................................................56
8.3 Actions, Impact and Mitigation Measures ...............................................................61
CHAPTER 9: ENVIRONMENTAL MANAGEMENT PLAN ...................................69
EIA of Sardu Khola Bridge Project DoLI
v
9.1 Environmental Management Plan (EMP) and its Objectives...................................69
9.2 Statutory Requirement or Legal and Procedural Bases ............................................69
9.3 Institutions and their Roles .......................................................................................70
9.4 Environment Management during Construction and Operation ..............................71
9.4.1 Spoil Management Plan .....................................................................................72
9.4.2 Pollution Abatement Plan (Pertaining to Air Quality, Water Quality and Solid
Waste) 72
9.4.3 Construction and Temporary Facillity Site Rehabilitation Management Plan ..73
9.4.4 Terrestrial Ecology: Habitat Protection, Restoration and Management Plan ....73
9.4.5 Aquatic Ecology: Habitat Protection, Restoration and ManagementPlan .........74
9.4.6 President Chure-Tarai-Madhesh Conservation Area Impact Minimization and
Co- ordination Plan .....................................................................................................74
9.4.7 Occupational Health and Safety (OHS) Management Plan...............................74
9.4.8 Construction Camp Management Plan ..............................................................75
9.4.9 Construction Traffic Management Plan ............................................................75
9.4.10 Emergency Preparedness and Management Plan ............................................76
9.4.11 Permits and Approval Plan ..............................................................................76
9.4.12 Public Health and Safety Management Plan ...................................................76
9.4.13 Public Grievance Redress and Management Plan ...........................................77
9.4.14 Project Information Management Plan ............................................................77
9.4.15 Environmental Impacts Mitigation Management Plan ....................................77
9.5 Cost of Implementation of Mitigation and Augmentation Measures .......................84
9.5.1 Tree Plantation Plan (Bio-engineering) .............................................................85
9.5.2 Cost for Training and Awareness ......................................................................86
CHAPTER 10: REVIEW OF RELEVANT ACTS, RULES, REGULATIONS AND
GUIDELINES ..................................................................................................................87
CHAPTER 11: ENVIRONMENTAL MONITORING ................................................96
11.1 Matter to be monitored while implementing the Proposal .....................................96
11.1.1 Baseline Monitoring ........................................................................................97
11.1.2 Compliance Monitoring ...................................................................................97
11.1.3 Impact Monitoring ...........................................................................................97
11.2 Monitoring Indicators .............................................................................................97
11.3 Record Keeping, Reporting and Corrective Actions ............................................104
EIA of Sardu Khola Bridge Project DoLI
vi
11.4 Costs of Environmental Monitoring .....................................................................104
11.5 Environmental Auditing .......................................................................................105
CHAPTER 12: PARTICULAR OF THE COST AND RETURNS OF THE
PROPOSAL ....................................................................................................................111
12.1 Summary of Cost ..................................................................................................111
12.2 Comparision of Costs ...........................................................................................111
CHAPTER 13: CONCLUSION....................................................................................112
References .......................................................................................................................113
List of Tables
Table 1: Study Team ............................................................................................................ 2
Table 2: Salient Features of Bridge Project ......................................................................... 4
Table 3: Impact Area Delineation ........................................................................................ 8
Table 4: Summary of Public Consultations Conducted ..................................................... 15
Table 5: Summary of Public Hearing Conducted ............................................................. 16
Table 6: Land Requirement for the Bridge Project and Access ......................................... 18
Table 7: Quantity of Different Construction Materials Required ...................................... 19
Table 8: Project Implementation Schedule ........................................................................ 20
Table 9: Seasonal and Annual Climatic Normals for Sunsari District .............................. 25
Table 10: Annual minimum, maximum and average temperature of Dharan ................... 25
Table 11: Annual minimum, maximum and average temperature of Dharan ................... 25
Table 12: Relativity Humidity of Dharan .......................................................................... 25
Table 13: Water Quality of Sardu Khola ........................................................................... 27
Table 14: Vegetation within the Project Area.................................................................... 28
Table 15: Ethno-botany of Project Area ............................................................................ 29
Table 16: Mammals of Project Area .................................................................................. 31
Table 17: Avifauna of Project Area ................................................................................... 32
Table 18: Herpetofauna of Project Area ............................................................................ 33
Table 19: Rare, Threatened and Protected Animals Found in Project Area ...................... 33
Table 20: Population of the Project Area ........................................................................... 34
Table 21: Percentage of caste/ethnic composition within Project Area ............................ 35
Table 22: Percentage of people speaking mother tongue within Project Area .................. 36
Table 23: Population that have completed the education level within ZOI ....................... 37
EIA of Sardu Khola Bridge Project DoLI
vii
Table 24: Source of energy for lightening purpose ........................................................... 39
Table 25: Source of energy for cooking purpose ............................................................... 39
Table 26: Source of drinking water ................................................................................... 39
Table 27: Summary of the Beneficial Impacts and Scores ................................................ 49
Table 28: Summary of Adverse Environmental Impact and Scores .................................. 50
Table 29: Beneficial Environmental Impacts and Proposed Enhancement Measures ....... 62
Table 30: Adverse Environmental Impacts and Proposed Mitigation Measures .............. 62
Table 31: Institutional Roles and Responsibilities ............................................................. 70
Table 32: Environmental Impacts Mitigation Management Plan. ..................................... 78
Table 33: Cost for Impact Mitigation and Augmentation .................................................. 85
Table 34: Cost for Bio-engineering ................................................................................... 86
Table 35: Cost associated with training and awareness ..................................................... 86
Table 36: Review of Relevant Acts, Rules, Regulations and Guidelines .......................... 87
Table 37: Parameters selected for monitoring ................................................................... 98
Table 38: Compliance Monitoring for Sardu Khola Bridge Project ................................ 100
Table 39: Impact / Effect Monitoring for the Sardu Khola Bridge Project ..................... 101
Table 40: Estimated Cost for Environmental Monitoring ............................................... 104
Table 41: Environmental Auditing Framework for Sardu Khola Bridge Project ............ 106
Table 42: Environmental Management Cost ................................................................... 111
Table 43: Cost and Returns of the Proposal ..................................................................... 111
List of Figures
Figure 1: Bridge Location in District Map .......................................................................... 6
Figure 2: Bridge Location in Topographical Map ............................................................... 7
Figure 3: Bridge Location in Google Earth ......................................................................... 7
Figure 4: Geological Map of the Project Area ................................................................... 22
Figure 5: Seismic Risk Map of Nepal (After Bajracharya, 1994) ..................................... 24
Figure 6: Catchment Area of Sardu Khola at Bridge Site ................................................. 26
Figure 7: Forest towards Right Bank ................................................................................. 28
Figure 8: Environment Management Organization Structure ............................................ 71
EIA of Sardu Khola Bridge Project DoLI
viii
ANNEXEXS
Annex 1: SD/ToR approval letter & Approved Terms of Reference (ToR)
Annex 2: Consent from President Chure-Terai Madhesh Conservation Development
Committee
Annex 3: Information Collection Checklists
Annex 4: Minute of Public Consultation with Jalkanya CFUG
Annex 5: Public Consultation Notice and Minute of Public Hearing
Annex 6: Recommendation Letters of the Affected VDC
Annex 7: General Arrangement of Bridge
Annex 8: Location Map of Bridge
Annex 9: Declaration from EIA Study Team Member
Annex 10: Photographs
EIA of Sardu Khola Bridge Project DoLI
ix
Acronyms and Abbreviations
masl: meter above sea level
BS: Bikram Sambat
CBO: Community Based Organization
CCA: Chure Conservation Area
CFUGs: Community Forest User Group
CITES: Convention on International Trade in
Endangered Species of wild fauna and flora
cm: Centimeter
dBA: Decibel (A)
DCC: District Coordination Committee
DFO: Division Forest Office
DHM: Department of Hydrology and
Meteorology
DMG: Department of Mines and Geology
DoLI: Department of Local Infrastructure
DoR: Department of Roads
EA: Environmental Assessment
EIA: Environmental Impact Assessment
EMP: Environment Management Plan
EPA: Environment Protection Act
EPR: Environment Protection Rules
GIS: Geographical Information System
GoN: Government of Nepal
HFL: Highest Flood Level
HH: Household
IDO: Infrastructure Development Office
IEE: Initial Environmental Examination
IIZ: Indirecct Impact Zone
IUCN: International Union for Conservation of
Nature
LBS: Local Bridge Section
LEP: Labor based Environmentally
Friendly and Participatory Approach
LPG: Liquefied Petroleum Gas
LRBP: Local Road Bridge Programme
LRBS: Local Road Bridge Section
LRBSU: Local Road Bridge Support Unit
m : Meter
MoFAGA: Ministry of Federal Affairs and
General Administration
MoFE: Ministry of Forests and
Environment
MoPID : Ministry of Physical
Infrastructure and Development
NA: Not Applicable
NAAQS: National Ambient Air Quality
Standards
NGO: Non Governmental Organization
NTFPs: Non Timber Forest Products
PAFs: Project Affected Families
PCU: Project Coordination Unit
RCC: Reinforced Cement Concrete
RM: Rural Municipality
RoW: Right of Way
SD: Scoping Document
SDC: Swiss Agency for Development and
Cooperation
SWCA: Soil and Water Conservation Act
TA: Technical Assistance
ToR: Terms of Reference
VDC: Village Development Committee
www: World Wide Web
ZoI: Zone of Influence
EIA of Sardu Khola Bridge Project DoLI
ix
कारयकारी सारााश
पषठभमि
सथानीर सडक पल कारयकरि नपाल सरकारको आरथयक लगानी र मसिस मिकास तथा सहरोग मनरोगको परामिमिक
सहरोगिा साचामलत कारयकरि हो । रस कारयकरिको उददशर पल मनिायणिा रामिर र सथानीर (मनजी र सािदामरक)
सासथाको कषिता अमभबमि गरी दशभरर सिा र अिसरिा पहचको सिार गनय रहको छ । रो कारयकरि नपालका
समपणय मजललािा लाग गररएको छ । रसको आिारभत साझदारका रपिा सथानीर पिायिार मिभाग रहका छ ।
परदश ना . १, सनसरी मजलला, िरान- िागलबार-मिषणपादका सडक खणडिा पन सदय खोला पल पमन सथानीर
पिायिार मिभागको सथानीर सडक पल कारयकरि अतगयतक एउाा कारयकरि हो । रो िातािरणीर परभाि िलराङकन
परमतिदन सो पल मनिायण र साचालनका करििा पनय सकन सकारातिक तथा नकारातिक िातािरणीर एिा सािामजक
परभािलाई समबोिन गनयको लामग तरार गररएको हो ।
परसतािक
िरान – िागलबार – मिषणपादका सडक खणड अतगयत सनसरी मजलला मसथत िडा ना ११ र िडा ना २० को
मसिाना भई बगन सदय खोला िामथ पककी सडक पल मनिायण गन परसतािको कारयकारी मनकार एिा िातािरणीर
परभाि िलराङकनको लामग परसतािकको रपिा सथानीर पिायिार मिभाग रहको छ ।
परसतािकको ठगाना मनमनानसार रहको छ :
सथानीर पिायिार मिभाग
शरी िहल, पलचोक, लमलतपर, नपाल
समपकय फोन : ०१ - ५५३२०१९
इिल : [email protected]
िातािरणीर परभाि िलराङकनका उददशर
रस िातािरणीर परभाि िलराङकन अधररनको उददशर आरोजनालाई िातािरणीर पकषबाा िलरङकन गरी
आरोजनालाई परामिमिक तथा िातािरणीर पकषबाा ददगो बनाउन हो । रस अधररनको दौरान आरोजना
कारायिरन गदायका सकारातिक तथा तथा नकारातिक परभािहरको पमहचान गरी, सकारातिक परभािहरलाई
बढोततरी गन र नकारातिक असरहरलाई रमनकरण गन उपारहर पमहचान गरी परसताि गन सित आरोजनाको
उददशर हो ।
परसतािको सादरभयकता
सदय नदीिा बनन रस िोारिल पलल सनसरी मजललाको िरान उप - िहानगरपामलका िडा ना ११ र २० का
गरामिण बमसतहर जसत सगरिाथा ाोल, ३४ घर ाोल, मसरान दिी गाउ , मबषणपादका आददलाई िरान - िागलबार
-मिषणपादका िागयको िाधरिबाा अर कषतरसग सि िौसििा रातारातको िाधरिल जोडनछ । रस पलको
मनिायणल सथानीर िामसदाका लामग सहज, सरमकषत र भरपदो रातारातको िागय परसतत गन छ । साथ रस
आरोजनाल सथानीर सतरिा वयापाररक दकरराकलापलाई परोतसाहन गरी रोजगारी परिियन गन दमखछ । सथानी
रसतरिा उतपाददत िसतहरल मिशष गरी दि र दिजर उतपादन, फलफल, तरकारी, कखराको मनकासी सहज
गराई रामरो बजारिलर परापत भ आर आजयनको अिसर सजना हन दमखछ भन पल मनिायण गदाय आिशरक पन
EIA of Sardu Khola Bridge Project DoLI
x
िानि सरोत परदान गरी रस कषतरिा रोजगारीको अिसथािा सिार हन दमखछ । तसथय उपरकत सथानिा पल
मनिायणको आिसरकता सादरभयक छ ।
परसतािको मििरण तथा अधररन मिमि
बकस डीजाइन परकारको रो पलको लमबाई कररब १२१ मिार र पाी बाहकको चौडाई ७.५ मिार रहन छ र पाी
पल को दारा, बारा दब तफय १.१मि रहको छ । २६0 ४९’२६.४९” उततरी अकषााश र ८७0१५’१०.४९” पिी
दशातरिा सिदि सतहबाा ३१० मिारको उचाईिा परसतामित रो पल हाल भान चोक बजारबाा कररब ४.५
दकमि पमिििा अिमसथत छ । रो पलको दारा दकनार सनसरी मजलला िरान उप-िहानगरपामलका, िडा ना. २०
को मसरान दिी गाउ नमजक पदयछ भन बारा दकनार सनसरी मजलला, िरान उप-िहानगरपामलका, िडा ना. ११
को सगरिाथा ाोल, ३४ घर बमसत नमजक पदयछ । आरोजनाको कल लागत ि.अ.क. समहत न.र.
१३,९८,२०,४३८. ३३ लागन दमखछ ।
परिख पलिा पन रो सदय खोला पल चर सारमकषत कषतरिा मनिायण गररन भएकोल िातािरण सारकषण मनरिािली,
१९९७ को मनरि ३ अतगयतको अनसची २ को मिशष कषतर सरोकारको अः(२) अनसार िातािरणीर परभािको
वयिहारीक तथा ठाउ मबषश रमनकरण तथा लाभबदघीका उपारहर सझाि गनय िातािरणीर परभाि िलराङकन
कारय आिशरक दमखछ । रो िातािरणीर परभाि िलराङकन परमतिदन नपाल सरकारको काननी आिशरकता परा
गनय आिशरक सदभय सािागरीहरको पिय अधररन तथा सथलगत अधररन र िन तथा िातािरण ितरालरको (िा.
ितरीसतरीर) मनणयरदवारा २०७६।०२।१० गत सिीकत कषतर मनिायरण परमतिदन र कारयसची र रािपमत चर तराई
ििस सारकषण मिकास समिमतको २०७५।०८।२६ िा परापत अधररन सिीकमतका सतयहरको अमिनिा रमह तरार
गररएको छ ।
आरोजनाको मिदयिान िातािरणीर अिसथा
चर पियतबाा सर हन सदय खोला िलहरबाा पानी परापत गन नदी हो । अधररन कषतर पिी नपालको चर, मशिामलक
कषतरिा अिमसथत छ । भौगरभयक दमिकोणल आरोजना सथल मसिामलका कषतरको तललो मशिामलक इकाईिा पदयछ ।
रो कषतरिा सराडसाोन, िडसाोन जसता नरि र चमनलो खालका चटटानहर रहका छन । पलको दि तफय नदील
थपारको िााोको बाकलो तह रहको छ । परसतामित पलको दि तफयको जगहर मशिामलक चटटान िामथ नदील
थपारको िााोिा अिमसथत छ ।
आरोजना कषतरिा उषण हािापानी पाइछ । रस कषतरको िारषयक औशत अमिकति तापकरि ३०.१ मड.स. साथ
िारषयक औशत रनति तापकरि १८.६ मड.स. र िारषयक औशत िषाय १,७९४.३ मिमि हछ । पल मनिायण सथलिा
नदीको जलािार कषतर १९.६ ि.दक.िी. रहको छ । पलको दीगो पनको लामग मनिायण सथलिा नदीको सिरपका
कारण दि तािा ताीर सिारकारय अतरािशरक दमखछ । रहा िार, जल तथा धिनी परदषणका सरोतहर दमखएका
छ नन ।
आरोजना कषतर चर सारकषण कषतर मभतर पदयछ । आरोजना कषतर िरपरका िनिा मससौ र खरर िखर रपिा पाइछ ।
री िनिा मससौ सग, आप, बडािार, बोािाररो, जािन, हरो र बरोका रखहर पमन पाईछ । आरोजना कषतर
नमजक पाइन बनसपमतिा खतका कालािा लगाइएका रखहरिा आर, कागती, करा, अमबा, काहर, रसत
डालघास रखहरिा दबदब, मभिल, दकि, कटिरो आदद रहका छन । तर रो पल मनिायणका करििा कन पमन रख
काटनपन अिसथा छ न । पल परसताि गररएको ठाउ िानिीर बसोबास कषतरिा पन भएकोल रहा िरजतको आित
जाित मिरल हन गरको छ, तथामप िरपरका जागलिा भन तराई एिा मभतरी तराई कषतरिा पाइन िरजतहर जसत
EIA of Sardu Khola Bridge Project DoLI
xi
फराउरो, लागर, रातो बादर, बदल, मचततल, लोखक, राउरी िसा, आदी पाइछन । सदय खोला नदीिा बदना,
बाि सहर, ईल, कतल, असलाशाकय , पोथी, रह िाछा आदी पाइछन।
परतकषर परभामित कषतरको जनसाखरा १,२७५ परष र १,३८० िमहला गारी जमिा २,६५५ रहको छ र पररिारको
आकार ४.९९ रहको छ । राई जमत पमछ मलमब, निार, कषतरी, तािााङ, बराहमण, कामि, िगर, जमतका िामनसको
बाहलरता आरोजना कषतरिा रहको छ । आरोजना कषतरको साकषरता दर ७९.१३ परमतशत रहको छ । आरोजना
कषतरका िर जसो वयमकतहर द मनक जरालादारी र िजदरी कारयिा सालगन छन । रहाका अर पशािा बरापार र
ि दमशक रोजगार िहतिपणय छन । परभामित कषतरिा एक सिासर चौकील रस कषतरिा सिासर सिा परौद आएको
छ र मब.पी. कोइराला सिासर मबजञान सासथान िरान, लाभगरमहको लामग िखर सिासर सासथा रहको छ । अमिकााश
घरिरी मपउनको लामग िाराबाा आउन पानीिा अमशरत रहका छन । ७८.९५ परमतशत भदा बदढ घरिरील बारो-
गरास र बादक २१.०५ परमतशत घरिरील दाउरालाई परिख इिनको रपिा आरोजनाको परतकषर परभामित सथानिा
पररोग गदयछन र उजरालोको लामग ९९ परमतशत भदा बडी रामिर मिदयत दवारा लाभामित छन जहा जमिा ४
घरिरील उजजरालोको लामग िटटीतल को पररोग गदयछन । रहाको सथानीर िजार िागलबार बजार हो भन िखर
बजार िरान हो ।
िातािरणीर परभािहर
सकारातिक परभािहर
आरोजना मनिायणका करििा ततकाल दमखएका सकारातिक परभािहरिा उललखमनर वयमकत ददन बराबरको
असथारी रोजगारीको अिसर सजना र सथानीर जनताको दकषता अमभिमि रहका छन । आरोजना परभामित कषतरका
गरीब, अशहार र मपछमडएका िगयलाइ परररोजनाको उपभोकताबाा गररन रोजगारीका कारयहरिा पराथमिकता
ददइनछ । रस गरी आरोजना साचालन पमछ हन सकारातिक परभािहरिा िरान उप िहानगरपामलका िडा ना ११
र २० का जनतालाई िरान – िागलबार - मिषणपादका सडकिा बष भरी रातारातको समििा तथा पहच, सथानीर
कमष उपज तथा फलफलजर कमष उदयोगको परिदरिन, आरथयक मिकास, आदद रहका छन । पल साचालनिा
आएपमछ आरोजना परभामित कषतरका जनताहरलाई सािामजक सिा जसत ः सिासर, मशकषा, सािदामरक सिा,
बजार तथा अर समबिािा सहज र ित पहच परापत हनछ । रस पलको मनिायण पमछ रस कषतरिा द मनक उपभोगर
बसतहर, खादय तथा अर बसतहरको आपरतय सहज हनछ भन रस कषतरको कमष उपजल पमन सहज बजार परापत
गनछ जसल गदाय जीिनसतर बमि हनछ ।
नकारातिक परभािहर
आरोजना मनिायणका करििा िातािरणको सािामजक अिरििा दमखनसकन परिख नकारातिक परभािहरिा उपलबि
सिा समििािा दिाि, सथानीर र आगतक कािदारहर मबच दवद मसजयना, पशागत सिासर तथा सरकषािा परभाि,
आदद िखर सरोकारका रहका छन । अर असरहरिा कारय र जराला मितरणिा लमगक मिभद, जोमखिपणय कारयिा
नािालकहरको पररोग, असिसथ आिासका कारण फ मलन रोग, शारीररक समपकयका कारण सन रौन रोग हनसकन
दमखछन । साथ आरोजना साचालन पिात उपलबि समििाका कारण सडक दकनारिा अवयिमसथत िसोिास
बढन गई सडक कषतर अमतकरिण हन समभािना पमन रहछ ।
पल मनिायण परकरािा पररोग हन उपकरण, सिारीसािन एिा रसारमनक ततिहरको कारण धिमन, हािा र पानी
परदमषत हन सकछ । पलको मनिायण करििा मनसकन िााोका कारण नदीको पानी परदमषत हन सकछ । फोहोरको
उमचत वयिसथापन नभएिा जल तथा जमिको परदषणल अर नकारातिक परभाि मनमतराउन समभािना रहछ ।
EIA of Sardu Khola Bridge Project DoLI
xii
मनिायण सािामगरहरको सिमचत भणडारण तथा साचालन नगदाय चहािाका कारण सतही तथा भमिगत जल परदमषत
हनसकदछ । ज मिक िातािरणिा पन परभािको सदभयिा िनसपमत तथा िरजतिा परतरकष नकारातिक परभाि
पन दखखाद न । समडिा तथा परदषणको कारण जलीर पररमसथमतकीर परणाली र सदय खोलाका िाछािा पन
परभािलाई परिख चासोको मिषर हो ।
रमनकरणका उपारहर
आरोजनाको नकारातिक असरहर रमनकरण गनयका लामग मिमभनन वयिहाररक तथा मितवयरी उपारहर सझाि
गररएको छ । आरोजनाका परसतािक िा रसको परमतमनमि (मनिायण वयिसारी) ल आरोजना मनिायण तथा
साचालनको अिमििा रसता उपारहर अिलमबन गन छन । आरोजना मनिायण अिमिको लामग रनीकरणका
उपारहर लाग गन मजमििारी ठकदारको हनछ । अिलमबन गररन कही परिख उपारहर मनमनानसार छन ।
आरोजनािा परभामित जनतालाई मनिायण कारयिा समबमित रोजगारीिा पराथमिकता ददइनछ र
मशपिलक तामलिदवारा मतनको कषिता अमभबमि गररन छ ।
ताीर काान, भकषर र बाढी जोमखि रनीकरण गनय आिशरक नदी ताबि, बकषारोपण, बारो-
इजीनीररीङगको वयिसथा मिलाइन छ । खोलाको उपललो कषतरिा कररब १५० मि र तललो कषतरिा ५०
मि अमतररकत ताबि मनिायण गररनछ ।
पलको मनिायण करििा मनसकन िााोलाई उमचत सथानिा भडारण गरी पलका सारचना िा पनः भनय,
खालाा खालाी पनय र पहच सडक मनिायणिा पररोग गररन छ ।
सथानीर सिा समििािा दिाि कि गनय ठकदारल द मनक उपभोगर आिशरकता जसत खान पानी, साचार,
मिजली तथा खाना पकाउन इिन, आददको वयिसथा करामपमभतर गन छ । मनिायण गमतमिमिका कारण
कन भौमतक सारचनािा कषमत हन गएिा तरसको पनरनयिायण िा पनसथायपना गररन छ ।
पशागत सिासर र सरकषाको सरोकारका लामग आिशरक तरारी गररन छ । कािदारहरलाई हलिा,
पजा, बा, सरकषातिक पाी, चसिा, िासक आदद परदान गररन छ । मनिायण र भणडारणसथलिा अनामिकत
परिश र गमतमिमि रोकन खतराका साकतहर, छकबार एिा पालको वयिसथा गररन छ ।
करामप तथा मनिायण कषतरबाा ५० मि पर असथाई चपीको वयिसथा गररन छ र मतनलाई पानीको सरोतबाा
५० मि पर रामखन छ ।
आरोजना मनिायणको करििा मनसकन घरल तथा मनिायणजर फोहोरि लालाई नदीकषतर बाा पर उपरकत
सथानिा र भाडोिा साकलन गररन छ । पनः पररोग हनसकन िसत जसत डरि, बोरा, िात आददलाई जमिा
गरी किाडीिालाई बमचन छ ।
मनिायण गमतमिमििा पररोग हन तल तथा अर रसारमनक पदाथयहरलाई उपरकत सथानिा धरानपियक
भणडारण तथा उपरोग गररन छ ।
िातािरणीर वयिसथापन रोजना
सदय खोला पलको िातािरणीर वयिसथापन रोजनाल िातािरणीर परभाि िलराङकन अधररन परमतिदनिा
सझाइएका रमनकरणका उपारहर र अनगिनको परदकररानकल एिा सिरानकल कारायिरनलाई समनमित गन
वयिसथापकीर आिशरकता तथा परदकररालाई सिाको छ । आरोजनाको सिगर िातािरणीर वयिसथापन
परसतािकको मजमििारी मभतर पदयछ र रो परसतािक आफ ल िा मनिायण वयिसारी िाफय त गराइनछ ।
िातािरणीर वयिसथापनको समबििा आिशरक सचना तथा ि जञामनक आिार परदान गनय आरोजना मनिायणपिय,
मनिायणको सिरिा र साचालनको सिरिा िातािरणको अिसथाको जानकारी साकलन र अमभलख गनय
EIA of Sardu Khola Bridge Project DoLI
xiii
िातािरणीर अनगिन रोजना परसताि गररएको छ । आरोजना मनिायणको र साचालनको सिरिा कारायिरन गन
गरी दई परकारको अनगिनको वयिसथा गररएको छ , परभाि अनगिन र मनरिपालन अनगिन । री दई परकारको
अनगिनको लामग अनगिनका सचक, मिमि, सथान, बारमबारता, सिर तमलका र मजमििार कारयकारी मनकार
पमहचान गररएको छ । आरोजना मनिायणको अनगिन सथानीर पिायिार मिभाग तथा आरोजना साचालनको
अनगिन सथानीर पिायिार मिभाग, सथानीर सडक पल कारयकरि तथा मजललाका अर मनकारहरल गनछन ।
िातािरणीर अनगिनको लामग र ३,३५,०००/- मिमनरोजन गररएको छ भन पमहचान गररएका परभािहरको
रमनकरणका उपारहर अिलमबन गनयको लामग र ७,६५,०००/- हजार छाराइएको छ ।
िातािरणीर सारतरहरल कमतको दरसत काि गरका छन भनन रदकन गनय र आरोजनाका िासतमिक परभािको
पमहचान गनय, परभाि अनिानको दरसतता र अिलमबन गररएका रमनकरणका उपारहरको परभािकाररता जाचन
िातािरणीर लखापरीकषण रोजनाको खाका पमन रस परमतिदनिा परसतत गररएको छ । िातािरण सारकषण
मनरिािली २०५४ ल सझाए अनरप आरोजना सर भएको २ िषय पिात रसको िातािरणीर लखा परीकषण
गररनछ । आरोजनाको समपणय िातािरण वयिसथापनको खचय तथा मनिायण वयिसारीको काननी दामरतिको भार
परसतािकल िहोनछ ।
मनषकषय
रस सतरको आरोजनाका लामग आरोजनाबाा हन नकारातिक असरहर नगर छन । िर जसो असरहर सथानीर
सतरि मनिायण चरणिा िातर मसमित छन । आरोजनाबाा हन नकारातिक असरहर ददइएका रमनकरणका
उपारहरबाा कि गनय सदकछ । िातािरणीर वयिसथापन रोजनाको मभतर सिाीएका उपारहर अिलमबन गरीए
परररोजना कषतरिा भौमतक, ज मिक, सािामजक तथा सासकमतक िातािरणिा ठलो असरपन दमखद न । साथ रो
आरोजनाल कस को मनजी जगगा अमिगरहण गदन र कन परकारल कन रख पमन काटद न । रो आरोजना रािको
सडक साजाल तरार गन एउाा पिायिार पमन हो । तरस ल आरोजनाको परकमत, रसको अिमसथमत, सथानीर
जनसिदारहरको आरोरोजना परमतको रमच तथा पमहचान गररएका समभामित नकारातिक असरहरलाई
िधरनजर गद िातािरणीर परभाि िलराङकन अधररनल मनदशन गर अनरपको रमनकरण तथा
अमभिमिकरणका उपारहर अिलमबन गरी आरोजना रथामसघर साचालन गनय उपरकत दमखछ ।
EIA of Sardu Khola Bridge Project DoLI
xiv
Executive Summary
Background
Local Roads Bridge Programme (LRBP) has been financed by the Government of Nepal
(GoN) with technical assistance from Swiss Agency for Development and Cooperation
(SDC) to improve the access to services and opportunities throughout the country and
strengthen Capacities of national, local institutions (private and communities) in bridge
sector. This programme is present in all the districts of the country. The basic partner is
principally DoLI.
Sardu Khola Bridge (Sunsari District) along Dharan - Mangalbare – Bishnupaduka road
is one of the projects under DoLI, LRBP. This EIA report has been prepared to address the
likely environmental and social impact, both beneficial and adverse, due to the proposed
bridge construction and operation in the project influenced area.
The Proponent
DoLI is the implementing agency and the proponent of the the Environmental Impact
Assessment (EIA) study for the construction of motorable bridge over the Sardu Khola at
Sunsari at the border of wards 11 and 20 of Dharan Sub-Metropolitan city of Sunsari
District, Province no.1 along Dharan - Mangalbare – Bishnupaduka road.
Full Address of the Proponent:
Department of Local Infrastructure
Shree Mahal, Pulchok, Lalitpur, Nepal
Telephone: 01-5532019
Email: [email protected]
Objectives of EIA
The aim of EIA study is to access the project from the environmental point of view and
make the proposed project technically and environmentally sustainable and to identify
beneficial and adverse impact upon the implementation of the proposed proposal and
recommend the measures for the enhancement of beneficial impacts and mitigation
measures for the adverse impacts.
Relevancy of the Proposal
The construction of the motorable bridge over the Sardu Khola will provide all weather
connectivity to the remote and isolated settlements of wards 11 and 20 as of Sagarmatha
Tole, 34 Ghare Tole, Siran Devi Gaun, Bishnupaduka etc. will be connected to Dharan
Sub-Metropolitan city of Sunsari District via; short stretch of Dharan - Mangalbare -
Bishnupaduka Road. The construction of bridge will also provide easy, safe and reliable
access route to the local people. Furthermore, the project will also encourage the local
commercial activities and will increase the employment opportunities at local level. Local
products like milk and milk products, fruits, vegetables and poultrycan get the market value
with easy transportation access and also creates better income opportunities. Similarly, the
project will also offer the employment opportunities by engaging rural people in
construction works. As such construction of the brige at this location is logical.
EIA of Sardu Khola Bridge Project DoLI
xv
Project Description and Study Methodology
This design of Box Bridge is about 121 m long with a carriageway width of 7.5.m with foot
path of 1.1m at both sides of the bridge. The proposed bridge is located at 260 49’26.49”N
latitude and 870 15’10.49”E longitude and elevation of 310m about 4.5 km West from
Bhanu chowk. The right bank of the proposed bridge site lies close to Siran devi gaun,
Ward no. 20 and the left bank lies close to Sagarmatha Tole, 34 Ghare settlement, Ward
No. 11 within Dharan Sub - Meteropolitian city of Sunsari District.The estimated total
project cost including VAT is NRs. 13, 98,20,438.33.
Since, the Sardu Khola Bridge is a major bridge being constructed within the boundary of
environmentally sensitive area designated as the Churia Conservation Area, EIA is
essential as per the special area consideration {L (2)} of Schedule 2 under Rule 3 of
Environmental Protection Rules (EPR 1997) to suggest the appropriate practical & site
specific mitigation/enhancement measures. This EIA report has been prepared following
necessary desk and field study and defined procedure and also on the basis of the SD and
ToR approved by the Ministry level decision of the MoFE on 2076-02-10 (2019-05-24)
and the conditions of consent from President Chure-Terai Madhesh Conservation
Development Committee was obtained in 2075/08/26 to fulfill the statutory requirement of
GoN.
Existing Environmental Condition
The Sardu Khola is a springfed river and originates from the Chure Range.
Physiographically, the study area lies in the Churia/Siwalik zone of Central Nepal.
Geologically, the project site is located within the Lower Siwalik unit of the Siwalik zone
which is mainly composed of sandstones, and mudstones and calcareous deposits. The
project area has thick alluvial deposits of the Sardu River on both banks exhibiting definite
fluvial cycles. The foundations of the proposed bridge on both banks are located in the
alluvial deposits overlying Siwalik Rock.
The climate of the project area is tropical. The annual average rainfall is 1,794.3 mm and
the average annual maximum temperature is 30.10C and average annual minimum
temperature is 18.60C. The Sardu Khola is a perennial river with significant discharge.
Total catchment area of the river at proposed bridge site is 19.6 Km2. Location of the bridge
and the nature of the Sardu Khola call for river training for sustainability of the bridge.
Sources of air, water and noise pollution are literally absent as of now.
The project area lies in Churia Conservation Area. The forest around the project area is
dominated by Sisoo (Dalbergia sisoo) and Khair (Acacia catechu) forest. Along with such
trees the forest consists of Bot Dhairo (Lagerstroemia parviflora), Badadhar (Artocarpus
lakoocha Wall), Jamun (Syzigium cumini), Harro (Terminalia chebula), Barro (Terminalia
bellirica) etc. The vegetation in the immediate vicinity of the project site is limited to sparse
fodder tress along the cultivated land as Guava, Mango, Aaru, Katahar etc. and few trees
species of Dabdabe ,Bhimal, Kimu, Kutmero etc. planted as flood protection against
agriculture field abutting the Sardu River. The area where the bridge has been proposed is
predominantly human habitation with infrequent movement of animals. However, the
EIA of Sardu Khola Bridge Project DoLI
xvi
surrounding forest harbours mammalian species typical of Terai and inner Terai region of
Nepal like Rato Bandar (Macaca mullata), Langur (Semnopithecus entellus), Bandel (Sus
scrofa), Chital (Axis axis), Squirrel (Sciuridae sps.), Nyauri musa (Talpa sps.) etc. Fish
species like Buduna (Garra annandalei), Bam Sahar (Tor spp.), Eel (Anguilla bengalensis),
Katle (Acrossocheilus hexagonolepis), Aslashark (Wallago attu), Pothi (Puntius spp.) and
Rhou (Labeo rohita) are found except in dry season where river gets completely dry.
The total population of the direct influence project area is 2,655 with 1,275 male and 1,380
female. The total household size is 4.99. The population of the project area is dominated
by Rai, Limbu, Newar, Chhetri, Tamang, Brahman followed by Kami and Magar. Total
literacy of the project area is 79.13%. Agriculture and livestock rearing is the major
occupation of the project area. Other occupations include small business and aboard jobs.
Health care service is being delivered by one of the Health Post in the project area (Bhanu
Chowk) and people goes to B.P. Koirala Institute of Health Sciences for better health
facilities. Most of the household depend on piped tap water for drinking. Almost 78.95%
households depend on bio-gas for cooking and more than 99 % have national electricity
available as a lighting source. Mangalbare bazaar is the local market center and the major
market is Dharan.
Environmental Impacts
Beneficial Impacts
The immediate beneficial impact from the project during construction phase is generation
of temporary employment opportunity of significant persondays together with skill
enhancementfor local people. Poor, vulnerable and socially excluded people of ZoI will get
priority in project related jobsthat are administered through users. The major beneficial
impacts after project completion includes enhanced accessibility and transportation facility
throughout the year to the people of both wards 11 and 20 of Dharan Sub-Metropolitan city
along Dharan - Mangalbare - Bishnupaduka Road which helps in promotion of agro-
enterprises based on local agricultural and horticultural products and economic
development. Once in operation the bridge will offer easy, comfortable and quick access to
people of the area to social service facilities like health, education, market and other
facilities. Likewise, this will ease the supply of daily consumables, food and others and
provide market to local agricultural products which will improve the quality of living.
Adverse Impacts
Among the adverse impact on the social domain of the environment, pressure on existing
service facilities, possible conflict and clash between local and outside workers,
occupational health and safety are of chief concern. Other impacts are gender
discrimination in task and wage distribution, involvement of children in risky works,
diseases due to unhygienic living condition, communicable diseases and STDs, etc. During
operation phase, ribbon settlement along the project alignment could develop haphazardly
and encroachment might occur along approach road.
EIA of Sardu Khola Bridge Project DoLI
xvii
Construction activity may produce noise, water and air pollution due to operation of
construction equipments and vehicles and use of synthetic chemicals. Spoil from work for
bridge construction may mix with the river water and increase the sediment load. Improper
storage and handling of construction materials and chemicals may cause surface and ground
water pollution and soil pollution through leakage and seepage. Regarding the impact on
biological environment, no direct impact on forest and wildlife is envisaged as the bridge
is proposed amongst settlement. The major concern is impact on aquatic ecology due to
sediment and fresh water fish aboding the Sardu Khola.
Mitigation Measures
A number of practical and cost effective mitigation measures have been suggested to
prevent, correct and compensate the adverse effects of the project implementation. The
project proponent or its representative/contractoris bound to implement these measures
during the construction and operation of the project. For construction phase, contractor will
be responsible for the implementation of the mitigation measures. Some of the major
measures to be adopted are as follows:
The affected people will be given high priority in employment opportunities and
opportunity to local people will be maximized during construction phase. Similarly,
their skills will be enhanced through necessary trainings.
Proper engineering and bio-engineering techniques will be adopted to protect bank
cutting and erosion and avoid flood risk. River training works will be extended to
150 m upstream and 50 m downstream along the both banks of the Sardu Khola.
Spoil generated during construction work will be stored properly and reused in
backfilling and to reclaim depressions and approach road construction.
To reduce the pressure on service facilities, contractor will managesome utilities
like communication, lighting and cooking energy, drinking water supply, etc within
the camp.Any damages to physical infrastructures will be reconstructed or
rehabilitated.
To address the issue of occupational health and safety, proper safety arrangements
will be made. Safety equipment such as helmets, boots, gloves, safety belts, safety
glasses and masks will be provided to the workers working in the construction sites.
Warning signs, posts, barriers and guards will be installed to restrict access of
unauthorized persons to construction sites.
Arrangements of temporary latrines will be made for workers and they will be
placed 50 m away from water bodies.
All the camp wastes and construction wastes will be placed in the designated waste
collection pits away from the water path. The separate storage areas will be
established for all punctured containers (drums, carboys, flasks etc) and will be
processed for selling to scavengers.
Oils and other chemicals used in construction activities will be handled carefully
and stored in fallow land away from the river beds by using impervious layers.
EIA of Sardu Khola Bridge Project DoLI
xviii
Environmental Management Plan
Environmental Management Plan (EMP) of Sardu Khola Bridge sets out environmental
management requirements and procedures to ensure that all mitigation measures and
monitoring requirements specified in this EIA study report will be carried out insubsequent
stagesof project. Overall project environmental management is the responsibility of
proponent through self or contractor.
Environmental monitoring plan has been proposed to investigate and understand the quality
of the environment prior to project and keep records of the project impact on the
environmental quality during construction and operation phases of the project so as to
provide reliable information and scientific basis for environmental management. Two types
of monitoring: Impact Monitoring and Compliance Monitoring have been proposed to
implement during the project construction and operation phases. It has identified the
indicators, methods, location, frequency and schedule and the competent authority for these
two types of monitoring. The DOLI will perform monitoring of the project implementation.
The DoLI, LRBP with district bodies will monitor during operation phase. For the
environmental monitoring, NRs 3,35,000 has been allocated. NRs 7,65,000 has been
allocated for mitigation of the predicted impacts.
Environmental audit plan has been proposed to provide the basis to examine how well the
environmental instruments have worked and enabled to assess the actual environmental
impacts, accuracy of prediction, effectiveness of environmental mitigation measures
adopted and functioning of monitoring mechanism. The Audit will be carried out as
specified as in EPR 1997 after 2 years of commencement of the project. The proponent will
cover all the environment management costs in addition to the legal liabilities of the
contractors.
Conclusion
Most of the identified and perceived impacts of the project are of low significance
compared to the project of this scale. With the set of mitigation measures, most of the
identified adverse impacts can be minimised and/or compensated and limited to locality
and construction period. Once the measures outlined in the EMP are implemented, there is
no risk for residual impacts that may affect the physical, biological, socio-economic and
cultural environment of the project area. No private land will be acquired and no trees to
be felled by any means for this project. It is an important infrastructure to facilitate road
network of the nation. Hence, it is advisable implement the project as soon as possible by
adopting appropriate mitigation and enhancement measures as suggested in this EIA study
report considering the local interest, nature, location and identified impacts of the project.
EIA of Sardu Khola Bridge Project DoLI
1
CHAPTER 1: INTRODUCTION
1.1 Name of the Proposal and Brief Introduction
The name of this Proposal is:
“Environmental Impact Assessment of Sardu Khola Bridge along, Dharan-Mangalbare-
Bishnupaduka road” in Sunsari District.
The aggrement for conductiong Environmental Impact Assessment of Sardu Khola Bridge
along, Dharan-Mangalbare-Bishnupaduka road” at Sunsari District, Province no. 1 (here
in referred to as “the Project”) was issued by the proponent DoLI, LRBP to the consultant
company.
Sardu Khola Bridge along Dharan-Mangalbare-Bishnupaduka road is one of the projects
under DoLI, LRBP. As the project lies within the boundary of environmentally sensitive
region, the Chure now declared as the Chure Conservation Area (CCA), Environmental
Impact Assessment (EIA) study is mandatory according to the national law and is necessary
to address the likely environmental and social impact, both beneficial and adverse, due to
the proposed bridge construction and operation in the project influenced area.
This EIA report has been prepared based on the Scoping Document (SD) and Terms of
Reference (ToR) approved by the Ministry of Forest and Environment (MoFE) on 2076-
02-14 (2019-05-28) (The approval letter and approved SD and ToR have been attached in
Annex 1). The consent for EIA Study from President Chure-Terai Madhesh Conservation
Development Committee was obtained in 2075/08/26 (Annex 2).
1.2 Name and Address of the Proponent
The proponent and executing agency of the“Environmental Impact Assessment of Sardu
Khola Bridge along, Dharan-Mangalbare-Bishnupaduka road” at Sunsari District is
Department of Local Infrastructure (DoLI)
The address of Proponent is:
Department of Local Infrastructure
Shree Mahal, Pulchok, Lalitpur, Nepal
Telephone: 01-5532019
Email: [email protected]
1.3 Institutional Responsibility for Preparing EIA Report
Local Roads Bridge Support Unit (LRBSU), the technical support unit of the Local Roads
Bridge Programme (LRBP) has awarded consultancy services to Green Consult (Pvt.) Ltd.
who was responsible for conducting the necessary desk and field study and preparing
Scoping Document (SD), Terms of Reference (ToR) and final EIA Report on behalf of the
proponent adhering with the prevailing legislations and facilitate approval by the Ministry
of Forest and Environment (MoFE).
EIA of Sardu Khola Bridge Project DoLI
2
1.4 Name and Address of Institute Preparing the Report
The present EIA Document has been prepared for the Project Proponent by the following
Consulting Firm.
Green Consult (Pvt.) Ltd.,
Dhumbarahi, Kathmandu
Email: [email protected]
1.5 EIA Study Team and Declaration
The overall responsibility of the contents of this EIA study lies with the Report preparing
institution, namely Green Consult (Pvt.) Ltd.
All the team members involved in the preparation of this Report, have duly declared their
involvement and have taken due responsibility in preparation of this EIA Document. The
declaration forms from the Study Team members are attached in Annex 9. The study was
carried out by a team of qualified professionals which consisted of the followings:
Table 1: Study Team
SN Position Name of Member Qualification
1 Team Leader Dinesh P. Bhatta MSc in Env.
Engineering
2 Environmentalist Rabi Bhattarai M.Sc in Env. Science
3 Environmentalist Sagar Niroula M.Sc in Env Science
4 Biologist Kaustuv Raj Neupane M.Sc in Zoology
5 Geologist Sanjib Sapkota M.Sc in Geology
6 Socio-economist Sundar Neupane M.A in RD
EIA of Sardu Khola Bridge Project DoLI
3
CHAPTER 2: SUMMARY OF THE PROPOSAL
2.1 Introduction
2.1.1 General Project Background
Local Roads Bridge Programme (LRBP) has come from the understanding that one of the
major causes of rural poverty in Nepal is lack of access to the markets and service centers
due to the absence of adequately maintained local roads and bridges connecting them.
Without the reliable motorable crossings on the rivers, people living in the area are not able
to get maximum benefit from the roads constructed and also the investments made in road
are not fully utilized.
Upon GoN’s request, Swiss Agency for Development and Corporation (SDC) agreed to
provide a Technical Assistant (TA) to DoLI to support the implementation of LRBP. The
main goal of the Motorable Bridge Programme is ‘People in the programme districts have
improved livelihoods’.The main objective of LRBP is to improve the access to services and
opportunities and strengthen the capacities of national and local institution (private and
communities) in bridge sectors.
The major components of the programs includes; construction and piloting of new bridges
and approaches, general knowledge and technology transfer, formulate policies, strategies,
norms, standards targeting bridge and capacity building of stakeholders including
Government of Nepal (GoN), local bodies, private sectors and communities. The major
outcomes of the project are to ensure improved access to services and opportunities to
people and to ensure that national and local institutions adopt appropriate local road bridge
strategy.
2.1.2 Necessity of Sardu Khola Bridge
Sardu Khola Bridge is proposed in Dharan-Mangalbare-Bishnupaduka road which
connects the remote and isolated settlements of Bishnupaduka with Dharan city as well as
Sub-Metropolitan city Office.
In absence of the bridge at the location, vehicles have to detour to reach the religious place.
Currently vehicles do not ply across the river. A motorable bridge over the Sardu Khola is
essential to make the road all weather. Construction of the bridge will provide quick, safe
and reliable access to the people and vehicles travelling on this route. The proposed bridge
will also enhance the regional commercial activities and employment opportunities with
enhancing road connectivity. Bishnupaduka is one of the religious places of Sunsari
District. Bishnupaduka is also a hub of agricultural products like Turmeric and other
vegetable products. People are using this route to bring products to the market in
Mangalbare Bazar (ward No 11 on Left bank) and Dharan Agricultural Market centre.
Beside this, the proposed bridge will also connect Ahale region of Dhankuta and Bhojpur
too. In addition, other popular areas like Barahachhetra and Chinde bhanjyang can be gone
through Bhisnu paduka and this bridge will support the concept of “Religious Tourism”
route forwarded by the Dharan Sub metropolitan city.
EIA of Sardu Khola Bridge Project DoLI
4
The local agricultural products from Bishnu paduka like milk & milk products, poultry,
vegetables and fruits can get the market value providing better earning opportunities. The
project will also provide the employment opportunities by engaging rural people during
construction of the project. Furthermore, people of these villages will be benefited with
access of better health services, education and other social services.
EIA study of the river-crossing facility is necessary in order to assess the environmental
consequences of the changes in socio-economic, cultural and bio-physical environment of
the project as a result of project implementation and suggest appropriate, practical and site-
specific mitigation and enhancement measures for the likely impacts.
Upon GoN’s request, Swiss Agency for Development and Corporation (SDC) agreed to
provide a Technical Assistant (TA) to DoLIDAR (now DoLI) to support the
implementation of LRBP. The main goal of the Motorable Bridge Programme is ‘People
in the programme districts have improved livelihoods.’
Overall construction management will be the responsibility of LBS/DoLI. For this the
capacity will be strengthened and innovative approaches will be piloted working through
users committees, enhancing labour component in the construction, inclusive participation
of the work-force, adequate social welfare for the workers; social issues will also be closely
monitored by PCU/LBS with the support of LRBSU (TA team); and appropriate and
effective maintenance systems will be developed, tested and adopted.
2.2 Project Location
The bridge site is proposed over the Sardu Khola between wards 11 and 20 of Dharan Sub
metropolitan city along Dharan-Mangalbare-Bishnupaduka road in Sunsari District. The
proposed bridge is located at 26°49'26.49"N latitude and 87°15'10.79"E longitude and
elevation of 310 masl about about 4.5 km west from Bhanu Chowk one of the major city
center of Dharan. The project lies within Dharan Sub-Metropolitan City, Sunsari District,
Province no. 1. The bridge connects wards 11 and 20 of Dharan Sub Metropolitan City.
Left bank of the proposed bridge lies at Sagarmatha Tole, 34 ghare tole ward No 11 and
right bank lies at Siran Devi Gaun, Bishnu Paduka, and Ward No 20 of Dharan Sub-
metropolitan City. Both the settlements on left and right bank are squatter settlements. The
location of the proposed project is depicted in the district map, topographical map and
google earth image in Figure 2, Figure 3 and Figure 4 respectively.
2.2.1 Salient Features of the Project
The features of the proposed project are summarized in the table below (Table 5).
Table 2: Salient Features of Bridge Project
Project Sardu Khola Bridge Project
Location
Province 1
District Sunsari
Left bank Dharan Submetropolitan City 11, Mangalbare
Right bank Dharan Submetropolitan City 20, Bishnupaduka
Name of Road Dharan-Mangalbare-Bishnupaduka
EIA of Sardu Khola Bridge Project DoLI
5
Project Sardu Khola Bridge Project
Classification of Road Rural Road
Type of Road Surface Gravel and Earthen
Origination and destination of Road Dharan city and Bishnupaduka
Location of the Bridge Border of wards 11 and 20 of Dharan Submetropolitan
city
Geographical Longitude and Latitude Latitude 26°49'26.49"N
Longitude 87°15'10.79"E
Terrain River Valley and Foot Hill of Churia
Altitude 310 msl
Climate Sub-Tropical
Width of River at Bridge Site 125 m
Information on Structure
Total Length of Bridge 121 m
Classification of Bridge Major
Span Arrangement 14 no of boxes of size (5m *8m)
Width of Carriageway 7.5 m
Width of Footpath 1.1 m on each side
Type of Superstructure Box
Type of Foundation Open Foundation
Hydrology and Design Data
Catchment area of bridge site 19.6 sq Km.
Design Discharge 370.52
Project cost NRs.
Total Cost with 13% VAT 13,98,20,438.33
Construction Management
Estimated Construction Period 24 months
Supervision DoLI
Compliance Monitoring DoLI , LRBSU, LRBP
Maintenance Dharan Submetropolitan City, Local Bridge Committe,
different organisations
(Source: LRBP, 2018)
EIA of Sardu Khola Bridge Project DoLI
6
Figure 1: Bridge Location in District Map
EIA of Sardu Khola Bridge Project DoLI
7
Figure 2: Bridge Location in Topographical Map
Figure 3: Bridge Location in Google Earth
EIA of Sardu Khola Bridge Project DoLI
8
2.3 Project Area Delineation
For the purpose of the EIA study, the project area or the zone of impact (ZoI) is defined as
the area for the construction of the project structures/features as well as the area that will
be impacted due to the construction and operation of the project. The right bank of the
proposed bridge site lies on ward no. 20 and the left bank lies on ward no. 11 of Dharan
Submetropolitan City in Sunsari District. The project area has been further classified as
“core project area or direct impact zone” and “surrounding area or indirect impact zone” as
per expert judgement and practices on similar projects.
Core Project Area: The core project area or the direct impact zone includes the area or
wards of the submetroplitan city where the project structures including stockpiling yards
and camp sites are located and the land that will be acquired permanently for the project
construction. According to National EIA Guidelines, 1993, direct impact area refers to the
area where direct alteration in the existing environmental conditions takes place as a
consequence of project activities. It has been considered as an area around radius of 500 m
from bridge axis.
Surrounding Area: The surrounding area or the indirect impact zone included the area or
wards of the submetropolitan city that surround the core project area and where no any
project structures are located but the construction and operation of the proposed project
bring some environmental repercussions. It has been considered as an area around radius
of 2 km from the core project area.
Table 3: Impact Area Delineation
Project Areas (ZoI) Locations
Core project area/direct
impact zone
Right bank includes area of ward 20 of Dharan
Submetropolitan City and towards left bank areas of ward
11 of Dharan Submetropolitan City of Sunsari District.
Surrounding area/indirect
impact zone
Wards 11 and 20 of Dharan Submetropolitan City.
2.4 Objectives of the Proposal
The main objective of the proposal is to construct 121m long, a Motorable Bridge over
Sardu khola along Dharan-Mangalbare-Bishnupaduka road
2.5 Objectives of the EIA Study
The objectives of the EIA study are to identify the potential environmental impacts of
the proposed Motorable Bridge and to formulate strategies to avoid and minimize
adverse impact and enhance the beneficial impacts. The main objectives of this EIA
study are to:
To collect and document the baseline data of physical, biological, socio-economic
and cultural environment.
To analyze the data and determine the potential adverse and beneficial impacts in
terms of magnitude, extent and duration.
To prepare mitigation, monitoring, auditing and environmental management plan.
EIA of Sardu Khola Bridge Project DoLI
9
To provide platform for public to raise their issues about the implementation of
the project.
To advise decision makers regarding the implementation of the project.
2.6 Rationale for conducting EIA
The right bank of the proposed bridge lies in Chure Conservation Area. As per the
statutory requirement provided in Environmental Protection Act (EPA) 1997, and
Environmental Protection Rule (EPR), 1997 and subsequent amendments in 1999, 2007,
and 2009, Schedule 2 under Rule 3, (A), Forest Sector, (7) (Nepal Gazette, Part 5,
2064/05/03 with recent amendments Part 2, 2073/7/29), medium to big type construction
activities inside conservation area should go through EIA. Likewise, under the special
area consideration (अः ३) under Schedule 2, any construction works inside conservation
area should go through EIA. Hence EIA study of the proposal is mandatory.
EIA of the proposed bridge project is necessary in order to assess the environmental
consequences of the construction and operation of proposed bridge and to suggest
appropriate, practical and site-specific mitigation and enhancement measures. The
assessment has been carried out to fulfill the study of environmental assessments work
and further helps on construction of bridge after the approval of this study report. The
consent for EIA Study from President Chure-Terai Madhesh Conservation Development
Committee was needed and was obtained at the dated 2075/8/26.
2.7 Impact on land use
The proposed project is construction of new motorable bridge over Sardu Khola. The
project lies on at the left bank Dharan Submetropolitan city ward no. 11, Mangalbare
and at right bank Dharan Submetropolitan city ward no. 20, Bishnupaduka where there
is already gravel and earthen rural road on each side named as Dharan-Mangalbare-
Bishnupaduka. The bridge will cover 0.13ha of government land whereas 0.17ha of river
area will be occupied to protect it. Moreover, the proposed project requires temporary
camp site and storage site in the project area. The total temporary land required for
construction of labor camp 0.01ha and storage camp will be 0.04ha. The project
construct labor camp and storage camp in the barren land in the project site. River bank
will be eroded during the construction of foundation of bridge. Moreover there is impact
on land related to camp site such as solid and liquid waste. Pollution on the Sardu Khola
will be seen due to leakage from construction camp and labor camp site. The movement
of vehicle will pollute surface water and soil in the camp site. The storage of construction
materials will impact on the aesthetic beauty of the site.
2.8 Adverse Impact on Environment, Impact on Human Life,
Population Pressure
Due to the construction of proposed Pedestrian suspension bridge there wil be adverse
environmental impacts in the different sector of the Environment.
EIA of Sardu Khola Bridge Project DoLI
10
The major Physical and chemical impacts of the project are clearance of land for the
construction of bridge foundation, River bank erosion, sedimentation during excavation,
labor camp construction and solid waste management, stockpiling of construction
materials, occupational health and safety, impact on access road, air and noise pollution
during transportation of construction materials, scouring at mat and pier foundation,
disruption of natural water flow, reinstatement of camp sites etc. Likewise major
biological impacts are removal of forest and loss of trees, possibility of accident and
health safety of the workers etc.
2.9 Damaged to be suffered by local goods and objects
The Proposed bridge construction activities affects total of 0.363ha land where
permanently land use type of 0.313ha is used where river and flood plain 0.13ha for
bridge, river and flood plain 0.17ha for river protection, river/flood plain and community
forest area of 0.013ha permanently whereas temporarily 0.05ha is needed where
construction yard and stockpiling area constitutes 0.04ha, and remaining 0.01ha is for
construction camp, except this there is no any goods and objects damaged by this project.
2.10 Approach Road
There is already existing road on both right and left banks and no approach road is needed.
However, approach road towards left bank (around 20 m) needs to be widened and
upgraded and embankment of both roads has to be raised to reach the bridge height.
EIA of Sardu Khola Bridge Project DoLI
11
CHAPTER 3: METHODOLOGY ADOPTED
In this Chapter, the methodology adopted during the conduction of this EIA Study Report
for the Sardu Khola Bridge construction project is briefly described. The chapter describes
the general method adopted, the details of the Scoping Process and field data collection,
including analysis and Report Presentation.
The EIA study has followed the basic steps outlined in EPA/EPR-1997, and National EIA
Guidelines-1993. Necessary information was generated through review of technical
documents and field works. During field visits, area experts were involved in identifying
issues and possible impacts related to the Project activities, by the method of inspection,
verifications, observations and discussions with local residents and key informants.
Secondary information was collected through published reports and interpretation of maps
and photographs. Primary information was generated through questionnaire, checklist,
measurement and consultation. Furthermore, local people were contacted and interviewed
to solicit information. A number of stakeholders meetings and Focus Group Discussions
(FGD) was held in the Project areas.
The principal steps undertaken in the EIA methodology to accomplish the assignment were:
Literature review of Relevant Documents and Map Interpretation,
Public Consultation with CFUG was process which included (Details are attached
in Annex 4):
Public Notice was forwarded by proponent to respective local ward and municipal
bodies, where people of the locality were given all information through ward 11
and 20.
Formal meetings were held in the different places with related stakeholders.
Public Hearing with local residents, information dissemination and feedback
received (on 25 June 2019, at Devi Gau, ward no.20 Dharan Sub-Metropolitan
City, details are presented in (Annex 5)
EIA Scoping Document and ToR preparation and approval (Approved TOR
attached in Annex 1)
Site inspection and field study to collect primary information on physical,
biological, socio-economic, cultural and historical issues,
Verification of secondary information through cross-check of data, interview and
participatory discussion with local people,
Public hearing to disseminate the Project related information including anticipated
impacts and proposed mitigation measures and to incorporate the public interest
and aspirations into the finalization of the study and project design (Annex 5),
Compilation of Data, Identification of potential impacts, mitigation measures,
EMP, and other Chapters as per EIA requirements for final EIA report.
EIA of Sardu Khola Bridge Project DoLI
12
3.1 Preparatory Works for EIA Conduction
3.1.1 Desk Study
During preparation of EIA report different published literatures (data and information) were
reviewed in order to get required information for conduction of this study and report
preparation. The following steps were followed during the desk review:
Collection and review of secondary sources of information from various sources
including internet or websites, organizational and institutional libraries of different
governmental organizations and non-governmental organization.
Initial interaction and consultation with the local community and district level
stakeholders.
Delineation of geographical boundary of the influence area on the topographical
map.
Preparation of project specific checklist.
3.1.2 Literature Review
Relevant information for the study was collected through extensive review of literature.
Relevant documents and reports were collected and reviewed to detail out the nature of the
Project and identify the preliminary list of potential environmental impacts. The detail
review of “Detailed Design Report, 2017” of proposed Project was done extensively.In
conjunction with this report, 1:25,000 topographic maps, geological maps and Google maps
of project area were collected and information from Kirtipur Municipality were also
collected and reviewed. After the review of literature and documents, the Study Team
delineated the areas, where the Project is expected to have its impacts. Maps were prepared
showing potential development areas, natural resources and possible impacts on them from
Project activities. Based on this information, a base-map of the Project area was prepared
for its use during field surveys.
3.1.3 Review of Relevant Government’s Policies, Laws, Guidelines and Manuals
The proposed Project attracts the following policies, laws, guidelines, manuals and
standards of Government of Nepal (GoN). Apart from the GoN policies, laws, guidelines
and standards, the project will also attract the President Chure Terai Madesh Master Plan
and standards. The relevant national policies, acts, rules and guidelines attracted by the
proposed project summarized in Chapter 9 of this Report.
3.1.4 Study of Maps/Other Maps
Topographical maps were analyzed carefully along the road alignment together with field
verification by all experts analyzing direct and indirect impact zones in the project area.
Similarly, Geological Maps and Satellite Images are also used to study the existing geology
of the proposed project area.
3.2 Preparation of Scoping Document and Terms of Reference (TOR)
The Scoping for the EIA was undertaken in accordance with the EPA/EPR-1997 to
determine the scope of the EIA, and to inform stakeholders about the proposed Project and
EIA of Sardu Khola Bridge Project DoLI
13
to received their comments on relevant environmental issues and identify priority issues for
environmental assessment. Scoping exercise, besides review of Project‟s Detailed
Feasibility Report and other Project related literature, included publication of 15 days
Public Notice ( Scoping Annex- 2 ), inspections of Project construction site, and discussions
with local people, stakeholders and concerned government officials. The environmental
issues of priority concerns in the scoping document were based on the experiences of the
consultants on the similar type of Projects incorporating the concern received during formal
and informal deliberations with local people and other concerned stakeholders.
The issues and possible impacts identified in the Scoping Document were categorically
tabulated as Issues identified and prioritized for EIA Study and were incorporated in the
Terms of Reference (ToR). The ToR was prepared by including these potential issues, as
per the Schedule-4 of EPR pertaining to Rule-4 and Rule-5 (attached in Annex 1). The main
EIA study was focused on the detailed analysis of the environmental issues identified in
the approved SD and ToR. The Scoping Document and Terms of Reference (ToR) was
approved by MoFE, after its formal review, dated on 28th May, 2019 (2076/02/14).
3.3 Conduction of Field Data Collection for EIA Study
3.3.1 Site Inspection and Field Study
After the approval of Scoping Document and ToR, field studies were conducted in the
Project site areas in an extensive manner. A study team‟s professionals visited and
collected the overall basic information regarding the Project site area and site-specific
information. The data collection and field study was carried out in the months of May till
June 2019.
3.3.2 Field Study and Collection of Baseline Data
The detail field study was conducted to generate information on physical and biological
resources and social status. Information on major flora and fauna species was collected
though walk over survey and interacting with the local people. The study team also
discussed with the officials of the district organization, local bodies, and district forest
office and personnel to verify the information and collected their concerns and opinions.
The brief description on the Field Study methods is given here under.
Physical Environment Survey:
Field observation and walk-through survey was adopted to verify information. The physical
factors have direct impact on the construction and operation of the project to the project
site. Prior to the implementation of projects it is essential to collect and analyze different
data pertaining to hydrology, weathers data. The required data from physical aspects
includes; Topographical data, climatic data, meteorological data (temperature and
precipitation), geological, land use pattern, water, air and noise quality, solid waste
management system/ spoil disposal, workcamp and labor camp other information
concerning physical resources of the project area was collected. All these data and other
relevant information are collected from available topographical map, aerial photographs,
field tests and site observation consultation with local communities of the project site.
EIA of Sardu Khola Bridge Project DoLI
14
Biological Environment Survey:
During the biological survey, observational visit to forests within the Project area, were
carried out and interaction meetings with key persons were carried out. During the
observational visit, entire treeswithin the proposed sitewere enumerated and information
on biological environment and management issues of community forests user groups and
their public concerns were acquired. The officials of Jalkanya Community Forest Users
Groups (CFUGs), local concerned committee, representatives of political party
representatives were consulted. The participants were informed about the project activities
and potential impacts and mitigating efforts of the project. Further, environmental
sensitivity, environmental development efforts and concerns of the area had also been
discussed with the participants. General information on the state of community forest,
forest tree, shrub/herbs and other species of different values available in the community
forests were acquired. Information about number of community of forest, types of species,
and existing condition of community forest were also collected during the meetings while
consultation. Enquiry was also made on wildlife species, aquatic species and barren land
available in community forests for likely requirement of afforestation.
In case of aquatic species, Sardu Khola being non-perenial River the major fish species
found were Buduna (Garra annandalei), Bam Sahar (Tor spp.), Eel (Anguilla bengalensis),
Katle (Acrossocheilus hexagonolepis), Aslashark (Wallago attu), Pothi (Puntius spp.) and
Rhou (Labeo rohita). The existing river has not good fish biodiversity. Local fishermen are
not engaged to catch fish species in Shardu River for economic purpose. In the dry season
the river gets complete dry so no fish can be found in the location. However, during wet
season the river gets frequently flooded.
Socio-economic and Cultural Survey:
Information on socio-economic and cultural features of the Project area (of immediate
vicinity of, 34 ghare tole ward no. 11 including population, ethnicity, occupation status,
education level has collected through focus group discussion and questionnaire survey.
Similarly, description of Siran Devi Gaun settlement pattern, religion, cultural and religious
sites, sources of energy and energy consumption, social infrastructures, market centers, etc.
were collected and described. The secondary information of Dharan Sub- Metropolitan City
was collected by reviewing different published literatures, information, particularly the
CBS data. The Jalkanya CFUG is in immediate vicinity of the Project area, so its cultural
aspects were also studied alongwith issues regarding environmental impacts which may
arise due to proposed work. During the field visit different issues regarding social and
environment and its possible positive and negative impacts were collected from the local
level stakeholders.
3.3.3 Conduction of Consultation, Interactions Meeting and Public Hearing
During the field study, study team contacted the local people to solicit their concerns and
opinions on physical, biological, socio-economic, cultural and historical aspects. The
public input have been documented in this Report. Public consultation specifically with
CFUG member and public hearing meetings are given in Annex 4 and Annex 5.
EIA of Sardu Khola Bridge Project DoLI
15
a) Interaction Meetings
Various level of different formal informal interaction meeting, Stakeholder Consultation
was held in the project area regarding the project during this scoping process. Local
institutions which are also played vital role as local stakeholders. The involved participants
were; Jalkanya Community Forest User Group, and Dharan Sub-Metropolitan city ward
no. 11 and 20. Local individuals are also participated in the meeting significantly. Summary
of Public Consultations Conducted are summarized in the Table 4 below:
Table 4: Summary of Public Consultations Conducted Type of Discussion Date Purpose of
Consultation
Nos. of Participants
Public Consultation 2076/2/29 – Jalkanya
CFUG member House.
To know CFUG’s
opinion towards
proposed project
13
6 Male
7 Female
Issues and suggestion
of meeting
1. While constructing Sardu Khola Bridge promotion of positive or
benefical impacts should be prioritized as far as possible while reducing
negative impacts and urge to start construction process as soon as
possible.
2. Jalkanya Community User Group found no any negative impact due to
proposed project so start and finishing of construction of Sardu Khola
Bridge to be done within contract time.
(Source: Field Survey, 2019)
The details of the meetings conducted are included in Annex 4.
b) Focus Group Discussion
A Focus Group Discussion was carried out at Jalkanya Devi Community User group
member’s house on June, 2019, to understand the existing socio-economic and cultural
situation and identify issues and concerns of the local people about the project. During
discussion, people’s understanding of the Project’s suitability, short-term, long-term
impacts and benefits were discussed. Altogether 13 people were presented in the
discussion. These individuals were chosen on the basis of effective institution working who
were nearby settlements.
c) Public Hearing Meeting
A Public Hearing program was conducted at the Project site on 25 June 2019 (Asar 10
2076). The objective of the meeting was to disseminate the information included in the
draft EIA Report and inform about the Project‟s status. The EIA Report was presented with
a short description of the environmental impacts, both beneficial and adverse, and the
mitigation measures, their monitoring and the associated cost were also explained. The
representatives from the DoLI, as the proponent agency, were also present in the meeting,
to interact with the local people. The participating people welcomed the Project‟s activities,
and expressed happiness in the Project’s proposal to include plans and budgetfor social
enhancement and local area development of accessibility to city area all around the year.
The main concerned of the people was regarding the protection of bank at both sides
upstream and downstream and bioengineering on access road to bridge. The proponent
expressed that the issues will be settled in alegally acceptable manner with the provision of
EIA of Sardu Khola Bridge Project DoLI
16
environmental protection measures to be done by contractor during construction, prior to
project implementation and duly notified to all the stakeholders.
Table 5: Summary of Public Hearing Conducted Type of Discussion Date Purpose of
Consultation
Nos. of Participants
Public Hearing 2076/3/10 – Jana Jagaran
Bal Bikash Kendra, Devi
Gaun ward 20. Dharan
Sub-Metropolitan City
To know stakeholder
opinion, suggestion and
issues towards
proposed project
41
30 Male
11 Female
Issues and suggestion
of meeting
1. There should be provision of bank protection on both sides of the bridge.
2. Afforestation programme should be launched.
3. While working at community forest area, care must be taken for minimal
impact inside community forest.
4. Bioengineering should be done on acces road to bridge height.
5. The proposed work have more positive/ beneficial impacts so,
community requests and urge for onstruction work to be forwarded as
soon as possible.
(Source: Field Survey, 2019)
The details of the meetings are summarized in Annex 5.
3.4 Preparation of EIA Document
3.4.1 Compilation of Baseline Information, Impact Identification, Prediction and
Evaluation
Based on the primary and secondary information the possible environmental impacts were
identified considering proposed Project activities and its interaction with surrounding
environment and accordingly the impacts were evaluated and presented in Chapter 6 in
accordance to Schedule 6 of EPR, 1997. The National EIA Guidelines, 1993 was followed
for the evaluation of impacts on the basis of magnitude, extent, duration and for providing
score value.
3.4.2 Prescription of Mitigation and Enhancement Measures, Monitoring and
Auditing
The mitigation and enhancement measures were proposed in order to ameliorate the
beneficial impacts and avoid or mitigate the adverse impacts considering the identified
impacts, their nature, extent and complexity, identified during the EIA exercise. While
recommending the mitigation option, a realistic approach was applied such that the
measures could be employed in the local context, and discussed in Chapter 8. Monitoring
plan is formulated to assess the effectiveness and implementation status of mitigation and
benefit augmentation measures. Auditing plan was also designed to verify the past and
current environmental performance and given in Chapter 10.
3.4.3 Preparation of Environment Management Plan
Environment Management Plan (EMP) was prepared to ensure and evaluate the
effectiveness of each of the mitigation and enhancement measures adopted to minimize the
environmental impacts and to ameliorate the overall environmental conditions within the
region of influence. The basic objectives of EMP are that it clearly spells out the
EIA of Sardu Khola Bridge Project DoLI
17
environmental concerns of the Project and prescribes a systematic environmental
management system to be followed to attain the environmental improvements in and
around the Project vicinity. The associated costs for adopting mitigation measures and
enhancement measures were also estimated and given in Chapter 8.
3.4.4 Alternative Analysis
A Chapter on the possible alternative options to the Project‟s design and its components
was identified and discussed in Chapter 7.
3.4.5 Preparation of EIA Draft Report
After doing all the study the preparation of draft report was done and Public hearing
program at project affected area was carried out. Concern of local stakeholder and local
people were taken on the preliminary draft. Then final EIA report was prepared. After the
completion of report, it was forwarded to Ministry of Forest and Environment through
Ministry of Federal Affairs and General Administration.
The general arrangement and concrete outline of the Sardu River Bridge is attached in
Annex 7 and the Location map of the bridge in contour map is attached in Annex 8.
3.5 Study Limitations
This EIA study has followed the basic concept of EIA as to make the EIA report site-
specific, to the extent possible. This study limits primary information along the project area
for physical, biological and socio-economic and cultural information. The information
related to Indirect Impact Zones were based on secondary information. Furthermore, the
limitations of the socio-economic Household Survey, encountered during the survey were:
The socio-economic household survey was done in squatter settlements which was
10m far from proposed bridge location on left bank where local authorities were
concerned about expansion of such squatter settelements and people were very
reluctant not to answer such socio-economic conditions as they wanted to setteled
down there so put forwarded their hesitations on answering such questionnaire.
EIA of Sardu Khola Bridge Project DoLI
18
CHAPTER 4: DETAILS OF THE PROJECT
In this Chapter, brief engineering details of the various components of the proposed Project
are given, which have been referred from the Detailed Feasibility Report prepared by the
LRBP Study Team.
4.1 Type of Proposal
The present proposal is of the type for construction of motorable box bridge of span 121m
along Dharan – Mangalbare - Bishnu paduka road.
4.2 Bridge Design
The main design characterstics of this proposed Project is palnned as 14 box each of size
(5m*8m). The score factors were taken into consideration while adopting to work on Chure
region.
4.3 Land Requirement
Land acquisition on permanent basis is not required for the project however about 0.05 ha
will be used temporarily for construction yard, stockpiling and labor camp. There is no
need of private land and all the land used will be government owned land. The description
of the land requirement is described in the Table 6.
Table 6: Land Requirement for the Bridge Project and Access
Project
Component
Private Government Land use
Type
Total
(ha) Temporary Permanent Temporary Permanent
Bridge 0 0 0 0.13 River and
flood plain
0.13
River
Protection
0.17 River and
flood plain
0.17
Approach
Road
0.013 River /
flood plain
and
community
forest
0.013
Construction
Yard and
Stockpiling
Area
0 0 0.04 0 River and
flood plain
0.04
Construction
Camp
0 0 0.01 0 River and
flood plain
0.01
Total 0 0 0.05 0.313 0.363
0 0.363 0.363 Source: Field Study, 2019
4.4 Construction Approach and Activities
Construction approach: The construction of bridge and approach road will follow a
combaination of machinery and Labor based Environmentally Friendly and Participatory
(LEP) approach by ensuring minimal damage to local environment.
EIA of Sardu Khola Bridge Project DoLI
19
Construction technology: Technology employed in construction will be machine
supported LEP methods.
Construction activities: Activities during construction includes civil works, river training
& bio-engineering, social development, and environmental protection activities.
Construction equipments: Equipments like grader, vibrator, vibrator roller, water
browser, loader, roller and mixer will be used at construction sites during construction
period. Vehicles like trucks will convey the necessary raw materials and equipments to the
construction site.
Construction Materials: The design parameters will adopt the design standard of
DoR/IRC. Various construction materials required for construction of the proposed bridge
include cement aggregates of various grades, sand, stone, geotextile, reinforcement,
binding wire, planks, struts, nails, GI pipe, paint, mesh wire, selvedge, bearing, expansion
joints etc. The quantity of these raw materials will be presented in following Table 7.
Table 7: Quantity of Different Construction Materials Required
SN Materials Quantity Unit SN Materials Quantity Unit
1 Aggregate 20-40 mm 1230.57 m3 11 Mesh Wire 10swg 57960 kg
2 Aggregate 10-20mm 1107.99 m3 12 Selvedge Wire
&swg 8184 kg
3 Aggregate 10mm &
down 312.08 m3 13 Binding wire 4119.9 kg
4 Subbase aggregate 172.8 m3 14 Planks 38mm
thick.
66.51 M3
5 Coarse sand 956.94 m3 15 struts, ballies, etc. 18.31
6 Sand 484.72 m3 16 Nails, spikes, etc. 5583.64 kg
7 Stone 915.53 m3 17 GI Pipe 783.36 m
8 Cement 971.22 t 18 Paint 51.46 lit
9 Timber 5437.84 m3 19 Suitable Material 228.99 cum
10 Reinforcement 184.75 t 20 Water 78,6125 lit Source: Design and Estimate Document of Sardu Khola Bridge Project, 2018
***Necessary aggregates will be obtained from authorized supplier.
4.5 Possible Emissions and Waste Generation
There are potential environmental implicationsof implementation of the proposal. Different
type of wastes and pollutants are assumed to be produced during the construction phase of
the project but no wastes are assumed to be produced by the project itself after the
construction.
Solid Wastes: Spoil is produced mainly during the excavation. The spoil generated will be
used used up in backfilling foundation pits and trenches. Additional material will be
required to fill the approach road.Prior to filling, the spoil will be piled up in an environment
friendly manner.Steel and other metal wastes will be assembled at the site. Liquid and
Semi-liquid Wastes: The quality of water in the river appears to be good without any
anthropogenic pollution. However, oil and grease used during the construction phase can
cause water pollution which will be managed in an environment friendly manner.
EIA of Sardu Khola Bridge Project DoLI
20
Air Pollution: During the excavation process and operation of vehicles and equipments,
dust and soil particles that go airborne are assumed to deteriorate the air quality.
Noise Pollution: Operation of diesel generators, excavators, vibrators, dozers and other
construction activities may increase the noise level.
4.6 Energy Use
Gasoline and electrical energy will be used during the construction phase. Diesel will be
used for the transportation of construction materials and running other diesel run
equipments. The area is connected with national grid and hence will be the main source for
electric energy. Use of firewood is assumed to be minimal as laborers at the camp will use
kerosene and LPG cylinders for cooking and heating purpose. For the project it is estimated
that around 300.69 lit of diesel and 9,643.80 lit of petrol will be needed.
4.7 Human Resource
Construction of the proposed bridge will require about 1,02,214.52 human days of input
from different capacity of workers that constitute 79,538.24 human days of unskilled
person power and 22,676.28 human days of skilled person power that includes engineers,
technicians and operator.
4.8 Project Implementation Schedule
Table 8 shows the implementation schedule of the Sardu Khola Bridge Project.
Construction work will be halted during monsoon season (i.e. July, August and September).
Table 8: Project Implementation Schedule
SN Activities 2018 2019 2020 2021
III I II III I II III I II III
1 Detail Survey, Design and Estimate
2 EIA and Approval
3 Project Implementation (Bridge
Construction)
A General Items
B Site Clearance
C Foundation
D Substructure
E Superstructure
F River Training Works
G Access Road
Note: I = (January, February, March), II = (April, May, June), III = (July, August, September), IV = (October,
November, December), (III = Monsoon)
EIA of Sardu Khola Bridge Project DoLI
21
CHAPTER 5: EXISTING ENVIRONMENTAL CONDITION
This section deals in brief with the existing environmental setting of the project area with
regard to physical, biological, socio-economic and cultural environment and interpretation
of the baseline information with view of impact assessment and environmental
management.
5.1 Physical Environment
5.1.1 Physiography and Topography
Physiographically, the project area lies in the Churia/Siwalik Range. The topographic
setting of immediate bridge site is abutting river terraces along both the banks. Right bank
of the proposed bridge site is Chure hill while left bank is flat river valley (Dharan City).
The present bridge location is at Latitude 26°49'26.49"N, Longitude 87°15'10.79"E and at
an elevation of 310 amsl which consists of alluvium on both sides and the alluvial deposits
are lying upon the Siwalik rocks. The river is straight at the project site.
The landuse pattern of the project site especially along the catchment is dominated by forest
covering upto (49.4%) and cultivated land (23.4%). Other land use type includes bush,
sand, grass, water body, barren land and cutting and cliff area.
EIA of Sardu Khola Bridge Project DoLI
22
5.1.2 Geology and Soil Type
Figure 4: Geological Map of the Project Area
The project area lies on the Siwalik foothills at Sardu Khola which separates the Siwaliks
succession on the right bank and alluvial fan at the left bank. Geologically the area lies on
the Siwaliks, which can be further classified as Lower Siwaliks and the Middle Siwaliks.
This area has been well studied by various scientists since early.
Bordet and Latreille (1955) investigated the Siwaliks around Dharan, where Bordet (1961)
identified the following cyclic succession (the thickness of a cycle varies from 10 to 20 m)
from the bottom to top:
(1) Cross bedded micaceous sandstones with small pebbles of quartz or foliated crystalline
rocks; conglomerates containing metamorphic pebbles; they constitute a fining-upwards
sequence topped by beds of lignite; and
(2) Greenish gray to pale yellow claystones with yellow calcareous nodules. He also
reported some bivalves and gastropods, and remarked that the formation is folded with
steep dips towards the north.
The Lower Siwaliks of this region are exposed mainly in the outer belt of the
Barahakshetra–Dharan area. In the lower reach of the Sardu Khola, west of Dharan, the
Lower Siwaliks is represented by thick- to very thick-bedded, medium- to fine-grained,
light gray-green to dark gray sandstones interbedded with green-gray and red purple,
EIA of Sardu Khola Bridge Project DoLI
23
variegated mudstones. Sporadically, they also contain thin (5 cm) coal seams. A thick
(more than 3 m) yellow-brown residual soil is generally found on top of the sandstones.
The Middle Siwaliks of the Barahakshetra–Dharan area consist of coarse- to very coarse-
grained, cross stratified, biotite-rich, pepper-and-salt sandstones, containing a few
conglomerate lenses and thin beds. The sandstones gradually pass upwards to gray or dark
gray mudstones containing plant remains.
The construction site lies on the flood plain hence the geotechnical parameters of the soil
is to be determined prior to the design of the bridge. The soil of this site has been termed
as moderate bearing capacity with high permeability. The bed rock in the area is not
expected within 5 meters.
5.1.3 Engineering Geology
The soil on the both bank of the river is alluvial type with coarse sand and cobbles. The
exposure of bedrocks lack in the construction site. The soil in the area has been classified
as river terrace deposit consisting of sub angular to rounded pebbly and gravelly materials
of quartzite, gneiss, schist phyllite mixed with fine sand, silt and clay, locally developed
and distributed along the sides of the streams with thickness up to 2 m.
5.1.4 Geomorphology
The area lies in the Siwaliks Range that exhibits very rugged terrain with deeply dissected
gullies and steep slopes on the right bank where the lower alluvial terrace on the left bank.
The Siwalikss of the region is characterized by low terraces, alluvial fans, badlands, and a
thin soil cover. This landform contributes a huge amount of sediment to the rivers through
gullies and tributaries. A majority of the rivers originating from this range are mainly
ephemeral and the proposed river is springfed type.. The physiography of the area is
dominantly controlled by the geology. The Siwalikss consisting of soft sandstones exhibit
highly dissected topography; the river valleys are wider and straighter. The resistant Middle
Siwalikss are characterized by high hills, steep slopes, and deeply dissected gullies. The
rivers and streams flowing through the Siwalikss carry much sediment.
5.1.5 River Bank Stability
The Banks on the both sides are the elevated alluvial terrace as a flood plain. The banks on
the area is suffering from bank erosion and is being controlled by embankments. The huge
amount of sediments from the upstream during the monsoon can create a problem. The
deposition of sediments in the river bed can lead the river to get directed towards the bank,
which in this case must be critically considered. The proper management of the river course
is recommended for protecting the bank from erosion with proper embankments on both
banks.
5.1.6 Flood and Sedimentation
As mentioned above, the project site is vulnerable to frequent flooding. As, the catchment
area lies in chure region with fragile soil mainly of granual type during monsoon season
EIA of Sardu Khola Bridge Project DoLI
24
the river will carry heavy sediment load. The overall process of building proposed bridge
will help in yielding good, long-term payoff for resource users, their communities and the
environment on critical part of activities they carry out on watersheds as a result if
constructed in environment friendly manner then helps in watershed management of the
local watershed with participatory approach of local communities.
5.1.7 Ground water Condition
The river is the springfed type, which flows only in the monsoon with minor contribution
from the groundwater. The river flows only for few months after the monsoon and for rest
of the months remains dry. Due to alluvial soil with cobbles and pebbles the water infiltrates
to the great depth making the area dry. Few springs are located at the foothills on the right
bank. These sources serve as an important source of water in the dry period. The ground
water level of project area was below 20m. Further as this bridge type is “multi cell Box
Bridge” each of size (5m*8m) whose foundation is generally laid on river bed and cut-off
wall is provided up to the score depth to safeguard the foundation. Thus, ground water
condition has no significant role for this project.
5.1.8 Seismicity of the Project area
Nepal is considered to be an active seismic zone due to continuous collision between the
Indian and the Eurasian tectonic plates. The National Seismological Centre, Department of
Mines and Geology (DMG) has prepared a micro seismic epicenter map of Nepal Himalaya
and adjoining region (1:200,000). The map shows distribution pattern of earthquake
epicenters in Nepal and adjoining region. The map also suggests that Eastern Terai of Nepal
is seismically more active than other parts of Nepal.
In order to determine seismic coefficient, a seismic design code for Nepal has been
prepared. Bajrachrya (1994) divided the whole country into five seismic risk zones (Figure
6). According to the map of Bajracharya (1994), the Sardu Khola Bridge location lies in
the high seismic risk zone of Nepal.
Figure 5: Seismic Risk Map of Nepal (After Bajracharya, 1994)
Project Site
EIA of Sardu Khola Bridge Project DoLI
25
5.1.9 Climate
Considering the altitude of the project site, the project area has sub-tropical climatic
conditions. As per DHM data, the average maximum temperature for Sunsari district is
30.1°C and average minimum temperature is 18.6°C. Precipitation here averages 1794.3
mm. The climatic data from last 5 years released by DHM shows the warming trend in the
area as the average annual temperature of 2017 was 25.6°C with annual maximum
temperature as 30.5°C and minimum annual temperature of 20.6°C,. The table belows
shows the detail climate data of Dharan and its trend for last 5 years.
Table 9: Seasonal and Annual Climatic Normals for Sunsari District
Season Winter Premonsoon Monsoon Postmonsoon Annual
Precipitation (mm) 32.8 226.9 1433.6 101.1 1794.3
Maximum Temperature (°C) 24.5 32.6 32.5 30.1 30.1
Minimum Temperature (°C) 10.4 19.3 24.7 17.8 18.6 (Source: DHM 2018)
Table 10: Annual minimum, maximum and average temperature of Dharan
Year 2013 2014 2015 2016 2017
min/max/avg
mi
n
ma
x
av
g
mi
n
ma
x
av
g
mi
n
ma
x
av
g
mi
n
ma
x
av
g
mi
n
ma
x
av
g
Temperature
(°C)
20.
3
29.
9
25.
1
20.
2
29.
7
24.
9
20.
4
29.
8
25.
1
20.
8
30.
1
25.
5
20.
6
30.
5
25.
6
(Source: DHM 2018)
Table 11: Annual minimum, maximum and average temperature of Dharan
Year 2013 2014 2015 2016 2017
Precipitation (mm) 2212 1684.9 1802.7 2362.2 2215.7
(Source: DHM 2018)
Table 12: Relativity Humidity of Dharan
Time 8:45 5:45
Year 2013 2014 2015 2016 2017 2013 2014 2015 2016 2017
RH 72.7 75.4 76.8 80.1 79.8 73.7 76.2 80.4 79 79.1
(Source: DHM 2018)
EIA of Sardu Khola Bridge Project DoLI
26
5.1.10 Drainage and Hydrology
The Sardu Khola is intermittent river of Sunsari District draining significantly during rainy
season only. It is a springfed river and originates from the Chure Range.
Figure 6: Catchment Area of Sardu Khola at Bridge Site
The catchment area of the river is just 19.6 square km at bridge site. The elevation
difference of the catchment at the bridge site is from 310 m to 1564 m amsl. The longest
length of the river up to the bridge site is 9.92 km.
5.1.11 Air Quality, Water Quality and Noise Levels
Air Quality: There is no significant air polluting industries at the vicinity of bridge site at
present. The potential sources of air pollutants are limited to vehicular emission for the
physical closeness of the bridge site to the approach road. The emission from vehicular
traffic within Dharan city and access road may be considered as the source of non-point
emission with no significant impact at the project area. Provided non-continuous sources
of emission, the ambient air quality of the area is assumed to be within the National
Ambient Air Quality Standards (NAAQS). However, during the vehicular movement in the
earthen road, fugitive emissions could be high at the local level.
Water Quality: Water quality of the Sardu Khola is believed to be suitable for aquatic life
and irrigation. Any source of pollution is not visible along the river alignment, however
during monsoon water becomes turbid due to high load of suspended sediment. The table
below shows the water quality of sardu khola.
EIA of Sardu Khola Bridge Project DoLI
27
Table 13: Water Quality of Sardu Khola
S.N. Parameters Observed Value
1. Temperature (0C) 27
2. pH 7.7
3. Electrical Conductivity (micro-siemens) 486
4. Total Suspended Solids, (mg/l) 108
5. Dissolved Oxygen, (mg/l) 7.4
6. Total Hardness as CaCO3, (mg/l) 129
7. Total Alkalinity as CaCO3, (mg/l) 123
8. Free Carbon dioxide, (mg/l) 4.6
9. Chloride, (mg/l) 58
(Source: Field Survey, 2019, Water analysis kit was used for test)
Noise Levels: Similarly, source of noise pollution are very infrequent in the area except
from passing vehicles in the access road. The noise data of the left bank was found to be
55 db whereas on right bank it was 49db.
5.1.12 Land Use
The landuse in the ZoI is dominated by agricultural land and settlement, river bank,
waterway and forest. The land use pattern of the project site especially along the catchment
is dominated by forest covering up to 49.4 % and cultivated land (23.4%). Other land se
type includes bush, sand, grass, cutting and cliff area, build up area and water body. Within
the immediate banks, beside barren flood plain of Sardu river, the land use pattern towards
left bank is dense settlement area and towards right bank is newly afforested forest land.
5.2 Biological Environment
The project lies within the boundary of Chure Protected Region. Apart from this, it does
not fall in any restricted areas or places of cultural, historical and archeological
importance/monuments, wildlife reserves and national parks. The approach road of 0.013ha
needs to be acquire as it falls under river/flood plain and community forest on right bank
of the proposed project.
5.2.1 Forests within Project Area
Project site trveresed through only one Community Managed Forest that is Jalkanya CFUG.
Community Forest User Groups (CFUGs) have been organized under the present forestry
sector policy responsible for the protecting, harvesting, and regenerating community forest.
CFUG in turn can use 75% of the income from community forest for the community
development activities and rest 25% for the community forestry development activities.
Forest type existing along the bridge construction site is mainly riverine forest Sisoo
(Dalbergia sisoo) and Khair (Acacia catechu). However, project construction site is lies in
Section-3 of Jalkanya CFUG which was afforested by Community around 6 years ago. This
section of forest is disturbed high within 200 meters from exiting road and adjoining to
Siran Devi Gaun.
EIA of Sardu Khola Bridge Project DoLI
28
Figure 7: Forest towards Right Bank
5.2.2 Vegetation
The project area lies in the tropical to sub-tropical vegetation zone. The major tree species
found within and near the project area are presented in Table 14 below.
Table 14: Vegetation within the Project Area
Local Name Scientific Name Plant’s Family
Aanp Mangifera indica L. Anacardiaceae
Badahar Artocarpus lakoocha Wall Moraceae
Bakenu Melia azederach L. Meliaceae
Bamboo Bambus spp Poaceae
Banjhi Anogeissus latifolius Combretaceae
Bar Ficus bengalensis L. Moraceae
Barro Terminalia bellirica Combretaceae
Bel Aegle marmelos(L) Corr. Rutaceae
Bhalayo Rhus javanica L. Anacardiaceae
Bot Dhayaro Lagerstroemia parviflora Roxb. Lythraceae
Narival Cocos nucifera L. Palmae
Dabdabe Garuga Pinanata Roxb. Burseraceae
Dhaiyaro Woodfordia fruticosa (L) Kurz. Lythraceae
Gidari Premna integrifolia L. Verbenaceae
Haade Lagerstroemia parviflora Roxb. Lythraceae
Hallunde Lannea coromandelica (Houtt.)Merr Anacardiaceae
Harro Terminalia chebula Combretaceae
Katahar Artocarpus heterophyllus Lam Moraceae
Jamun Syzigium cumini Myrtaceae
Karma Adina cordifolia Rubiaceae
EIA of Sardu Khola Bridge Project DoLI
29
Local Name Scientific Name Plant’s Family
Kabro Ficus lacor Moraceae
Kadam Anthocephalus chinensis Rubiaceae
Kumbi Cochlospermum religiosum Cochlospermaceae Source: Field Survey, 2018
Within the construction area there is no presence of any trees either of pole size or greater
than pole size or less than pole size.
5.2.2 Ethno-Botany and NTFPs
The biological resources play influential role in the socio-economic condition and life style
of local people. Diverse ethnic groups inhabit the project area. They use different biological
resources in various ways, like food, medicine and others. People around the project
location reported different utilities of the plant resources found in the area, though
currently, there is no record of commercial utilization of such resources in the project area.
The common plants of enthobotanical importance are listed in Table 15.
Table 15: Ethno-botany of Project Area
Local name Scientific name Plant’s Family Remarks
Asuro Adhatoda vesica Acantheceae Medicinal
Sangle Dobinea vulgaris Aceraceae
Lunde Amaranthus spinosus Amarantaceae Vegetable
Apamarga Achyranthus aspera Amaranthaceae Medicinal
Bhringaraj Alternanthera sessilis Amaranthaceae
Datiwan Achyranthes aspera Amaranthaceae
Bhakmilo Rhus javanica Anacardiaceae Pickle
Kanga Bhalayo Rhus wallichii Anacardiaceae
Dabdabe Lannae coromandelica Anacardiaceae
Lapsi Choerospondias axillaris Anacardiaceae Pickle
Chuwa Plumeria rubra Apocynaceae
Sarpa makai Arisaema sp. Araceae Fodder
Aanka Calotropis gigantea Asclepiedaceae Medicinal
Galeni Sambucus hookeri Caprifoliaceae
Abijalo Drymaria cordata Caryophyllaceae Medicinal
Bethu Chenopodium album Chenopodiaceae Vegetable
Barro Terminalia bellirica Combretaceae Medicinal
Ilame jhar Ageratum conyzoides Compositae
Bhede kuro Xanthium strumarium Compositae
Elephantopus scaber Compositae Medicinal
Hachhau jhar Dichrocephala integrifolia Compositae Medicinal
Kalijhar Eupatorium adenophorum Compositae
Titepati Artemisia indica Compositae Medicinal
Kuro Bidens pilosa Compositae
Mikania micrantha Compositae
Aule kalijhar Chromolaena odorata Compositae
Nilo Ilame Ageratum houstonianum Compositae
Kanike ghas Parthenium hysterophorus Compositae Fodder
Amarlata Cuscuta reflexa Convolvulaceae Medicinal
EIA of Sardu Khola Bridge Project DoLI
30
Local name Scientific name Plant’s Family Remarks
Pani sag Rorippa nasturtium Cruciferae Vegetable
Bhyakur Dioscorea deltoidea Dioscoreaceae Food
Bantarul Dioscorea bulbifera Dioscoreaceae Food
Sal Shorea robusta Dipterocarpaceae Timber
Guelo Elaeagnus parvifolia Elaeagnaceae
Rudraksha Elaeocarpus sphaericus Elaeocarpaceae Religious
Laligurans Rhododendron arboreum Ericaceae Medicine
Angeri Lyonia ovalifolia Ericaceae Medicinal
Ader Ricinus communis Euphorbiaceae
Amala Phyllanthus emblica Euphorbiaceae Medicinal
Ranikhel Jatropha curcas Euphorbiaceae Biofuel
Dhude Euphorbia hirta Euphorbiaceae
Khirro Sapium insigne Euphorbiaceae
Lalupate Euphorbia pulcherrima Euphorbiaceae
Sindhure Mallotus philippensis Euphorbiaceae Fodder
Pithari Trewia nudiflora Euphorbiaceae Timber
Maledo Macaranga indica Euphorbiaceae Timber/Fodder
Banjhi Anogeissus latifolius Combretaceae Timber
Katus Castanopsis indica Fagaceae Fruit
Hydrila Hydrilla verticillata Hydrocharitaceae
Okhar Juglans regia Juglandaceae Fruit/Timber
Dhusure Colebrookea oppositifolia Labiatae Packaging
Ghurbis Leucosceptrum sp. Labiatae
Pudina Mentha arvensis Labiatae Medicinal/Pickle
Leucas cephalotes Labiatea
Kutmero Litsea monopelata Lauraceae Fodder
Koiralo Bauhinia purpurea Leguminaceae Fodder/Timber
Taanki Bauhinia variegata Leguminaceae Fodder/Timber
Cassia sophera Leguminaceae
Cassia tora Leguminaceae
Kauso Mucuna nigricans Leguminaceae Medicinal
Khayar Acacia catechu Leguminaceae Timber
Phaledo Erythrina stricta Leguminaceae Fodder
Rajbrikchya Cassia fistula Leguminaceae Medicinal
Baldengra Mucuna macrocarpa Leguminoidae Medicinal
Bhatmase Desmodium confertum Leguminoidae Fodder
Bhorla Bauhinia vahlii Leguminoidae Packaging
Bhuletro Butia minor Leguminoidae Erosion
Lajjawati Mimosa pudica Leguminoidae
Bhimsenpati Buddleja asiatica Loganiaceae Medicinal
Hadchud Viscum album Lorenthaceae Medicinal
Dhaero Woodfordia fructicosa Lythraceae Pickle Source: Field Survey, 2018
EIA of Sardu Khola Bridge Project DoLI
31
5.2.3 Domesticated Plants
Local people have planted fruit trees like Mango (Magnifera indica), Litchi (Litchi
chinensis), Nibuwa (Citrus limonum), Aaru (Prunus persica), Kagati (Citrus aurantifolia),
Banana (Musa paradisiaca), Gauva (Psidium guajava), Katahar (Artocarpus
heterophyllus), etc. and fodder trees like Dabdabe (Garuga pinnata), Bhimal (Grewia
optiva), Kimu (Morus alba), Kutmero (Litsea monopetala), etc. Besides, people grow
numerous other crops, vegetables, pulses and fruits for household utilization or selling in
the market and those form quite a long list.
5.2.4 Rare, Threatened and Protected Plants
Among the plant species recorded in the project vicinity area, Shorea robusta, is protected
by government of Nepal under the Forest Act, 2049. However, these plants will not be
affected by project implementation.
5.2.5 Wildlife
The forest of Chure region and especially that of the inner Terai is heavily disturbed due to
human activities and natural disasters as well. So the otherwise inherently diverse zone in
terms of wildlife is very infrequently attended by very few wild animals. Moreover, the
area where the bridge has been proposed is prodominantly human habitation with
infrequent movement of animals. However, the surrounding forest harbours mammalian
species typical of Terai and inner Terai region of Nepal which sometimes venture as far as
the bridge site. Based on direct encounters, indicator and information given by the local
people, the fauna composition including the common birds, mammals, herpeto-fauna and
fish found in the ZoI of the project site is briefly summarized below:
Mammals: Fox (Canis aureus), House Rat (Rattus rattus), were reported as common
species found the project adjoining areas by consultation of the public. However not a
single mammalian species was observed during the field visit except bats flying in the
evening.
Table 16: Mammals of Project Area
S.N. Family Scientific Name Common Name Local Name
1. Canidae Vulpes bengalensis Bengal fox Fyauro
2. Cercopithecidae Semnopithecus entellus Hanuman langur Langur
3. Cercopithecidae Macaca mulatta Rhesus monkey Rato Bandar
4. Suidae Sus scrofa Wild boar Bandel
5. Cervidae Axis axis Spotted deer Chital
6. Scuiridae Ratufa bicolor Black giant squirrel Lokharke
7. Herpestidae Herpestes nyula Indian mongoose Nyauri musa
8. Mustelidae Vivericula indica Small Indian civet Kala Source: Field Survey, 2018
Avifauna: The common species of birds reported in the project area were Cattle Egret
(Bubulcus ibis), Pond Heron (Ardeola grayii), White throated Kingfisher (Halcyon
coromanda) Vented Bulbull (Pycnonotus cafer), Chive (Dicrusus sp), Fisto (Orthrotomus
sp), Dove (Streptopelia Chinensis), Common Crow (Corvus splendens), Sparrow (Passer
EIA of Sardu Khola Bridge Project DoLI
32
domesticus), Myana (Acridotheres tristis) were the birds observed during the field study.
The other birds found in surrounding of Project area are given in table below. However
there is no presence of vulture near and around the project vicinity and its surrounding even
though project vicinity have Simal trees.
Table 17: Avifauna of Project Area
Family Scientific Name
Common Name Nepali Name
Ciconiidae Leptoptilos javanicus Lesser Adjutant Garud
Corvidae Urocissa erythrorhyncha
Red-billed blue
magpie Lampuchhre
Laniidae Lanius tephronotus Grey-backed shrike Bhadrai
Corvidae Corvus splendens House crow Kag
Ardeidae Bubulcus ibis Cattle Egret Bakulla
Ardeidae Ardea cinerea Grey Heron Fushro bakulla
Ardeidae Mesophoyx intermedia Intermediate Egret
Majhoulaseto
bakulla
Ardeidae Adreola grayii Pond Heron Askote bakulla
Centropodidae Centropus sinensis Crow Pheasant Dhode koili
Columbidae Streptopelia chinensis Spotted Dove Dhukur
Coraciidae Coracias benghalensis Indian Roller Theuwa
Corvidae Dendrocitta vagabunda Indian Tree Pie Kokale
Corvidae Coracina macei Large Cuckooshrike
Latusakbirahi
chara
Cuculidae Cuculus micropterus Indian Cuckoo Koili
Dicruridae Dicrurus adsimilis Black Drongo Chibe
Megalaimidae Megalaima asiatica Blue-throated Barbet Kuthruke
Muscicapidae Copychus saularis
Oriental Magpie
Robin Dhobi chara
Passeridae Passer domesticus House Sparrow Bhangera
Picidae Dinopium benghalense
Lesser Golden-Backed
Woodpecker Lahache
Pycnonotidae Pycnonotus cafer Red-vented Bulbul Jureli
Pycnonotidae Pycnonotus leucogenys White-cheeked Bulbul Julfe jureli
Bucerotidae Anthracoceros albirostris Oriental pied hornbill Dhanesh
Sylviidae Phylloscopus fuligiventer Smoky warbler Dhwause fisto
Sylviidae Phylloscopus maculipennis Ashy-throated warbler
Fushrokanthe
fisto
Muscicapidae Luscinia brunnea Indian blue robin Nilo robin
Sylviidae Pteruthius xanthochlorus Green shrike babbler
Harit
bhadraibhyakur Source: Field Survey, 2018
Herpetofauna: The common species reported were Common Karait (Bungarus caeruleus),
Common Garden Lizard (Calotes versicolor), House Gecko (Hemidactylus spp). White
Lipped Pit Viper (Trimeresurus albolabris), Khasrebhyaguta (Bufo spp.), Frog
(Hoplobatrachus tigerinus), Cobra (Naja Sps) were the herpetofaunas found in the
subproject area. The other common species are given in table below.
EIA of Sardu Khola Bridge Project DoLI
33
Table 18: Herpetofauna of Project Area
Family Scientific Name
Common Name Nepali Name
Reptiles
Agamidae Calotes versicolor versicolor Common garden lizard Cheparo
Gekkonidae Hemidactylus brookii brookii Spotted house gecko Mausuli
Gekkonidae H. flaviviridis Yellow bellied house gecko Mausuli
Gekkonidae H. frenatus Common house gecko Mausuli
Varanidae Varanus bengalensis Indian monitor Gohoro
Varanidae V. flavescens Yellow monitor Sungohoro
Tephlopidae Rhamphotyphlops braminus Common blind snake Telia sanp
Boidae Python molurus bivittatus Burmese Rock python Ajhingar
Colubridae Amphiesma stolatum Checkered keelback Harhare
Colubridae Ptyas mucosa mucosa Asiatic rat snake Dhaman
Colubridae Xenochrophis piscator Water snake Pani sanp
Elapidae Bungarus caeruleus Common krait Karet
Elapidae Naja naja Cobra Goman
Elapidae Ophiophagus Hannah King cobra Rajgoman
Amphibia
Bufonidae Bufo melanostictus Common Asian toad Khasre bhyaguta
Raniidae Hoplobatrachus tigerinus Indian bull frog Bhyaguta
Raniidae H. crassus Jerdon’s bull frog Bhyaguta
Raniidae Euphlyctus cyanophlyctis Skittering frog Sano bhyaguta
Rhacophoridae Polypedates maculates Common Indian tree frog Rukh bhyaguta
Source: Field Survey, 2018
Fish: The major fish species found were Buduna (Garra annandalei), Bam Sahar (Tor
spp.), Eel (Anguilla bengalensis), Katle (Acrossocheilus hexagonolepis), Aslashark
(Wallago attu), Pothi (Puntius spp.) and Rhou (Labeo rohita). The existing river has not
good fish biodiversity. Local fishermen are not engaged to catch fish species in Shardu
River for economic purpose. In the dry season the river gets complete dry so no fish can
be found in the location. However, during wet season the river gets frequently flooded.
5.2.6 Rare, Threatened and Protected Wildlife
Among the faunal species recorded in the project location, five species including four
mammals and one reptile were specified different protection status. Though none of the
animals recorded were nationally protected by GoN under National Parks and Wildlife
Conservation Act, 1973, all of these species were listed in different appendices of CITES.
Table 19: Rare, Threatened and Protected Animals Found in Project Area
SN Scientific Name Local
Name
Legal Status Local
Status
Local
Use GoN IUCN CITES
1 Macaca mullata Rato
Bandar
II Common Pest
2 Semnopithecus
entellus
Langur LC I Common
3 Canis aureus Syal LC III Common Pest
4 Vulpes bengalensis Fyauro LC III Rare
EIA of Sardu Khola Bridge Project DoLI
34
5 Ptyas mucosus Dhaman II Rare
6 Panthera pardus Chituwa NT I Rare Pest
7 Martes flavigula Malsapro LC III Common Pest
8 Felis chaus Ban
Biralo
LC II Rare Pest
9 Herpestes edwardsi Nyauri
Musa
III Common
10 Milvus migrans Kalo Chil LC II Common
11 Bubo nipalensis Ullu LC II Rare
12 Glaucidium radiatum Ullu LC II Rare
13 Ptyas mucosus Dhaman II Common
CITIES Appendices
Appendix I: Species threatened with extinction
Appendix II: Species not yet threatened, but could become endangered if trade is not
controlled
Appendix III: Species identified by any party as being subject to regulation in that country
and which require international co-operation to control trade
IUCN Red List (1995)
LR: Low Risk, NT: Near Threatened, LC: Least Concern, VU: Vulnerable, EN:
Endangered, CR: Critically Endangered, K: Insufficiently Known
5.3 Socio Economic and Cultural Environment
5.3.1 Population and Household
The bridge lies within Dharan Submetropolican City. According to CBS 2011 and 2017,
total population in project area of Dharan Submetropolitan City is 137,705 in 32,693
households. Similarly, total population in project specific ward (wards 11 and 20) is 15,094
in 3,502 households. Total Population along with male and female within project area is
given in table below.
Table 20: Population of the Project Area
Impact Zone Total
Household
Population
Total Population Male Female
Dharan
Submetropolitan
City / ZOI
32,693 137,705 64,671 73,034
Ward 11 and 20 /IIZ 3,502 15,094 7,050 8,044
DIZ 532 2,655 1,275 1,380
Source: CBS, 2012
The above table show cased fewer number of male populationon both wards of project
influence area and Sub-metropolitan city as many have left countries for foreign
employment opportunities (Gulf, Europe, Australia, U.S.A, U.K) after peace process in
Nepal. The 34 Ghare settlement towards left bank and Siran Devi Gaun settlement towards
right bank lies within DIZ. There are 500 households within DIZ of left bank and 32
households within DIZ of right bank. Both of these settlements are squatter settlement area.
EIA of Sardu Khola Bridge Project DoLI
35
5.3.2 House Type, Ownership and Settlement Pattern
Within ZOI, it is noticed that around 35% of the houses are modern with RCC with pillar,
Cement bonded bricks/stone wall type and RCC Roof, 50% semi modern houses with
Cement bonded bricks/stone foundation type and wall type and Galvanized iron Roof, 15%
traditional houses with Mud bonded bricks/stone or wooden piller foundation type, Mud
bonded bricks/stone or Wood/ planks/Bamboo outer wall and Galvanized iron/
Thatch/straw/ Wood/ planks roof type. Around 60% of total household are self owned and
around 30% are rented within ZOI.
DIZ of the proposed bridge location is squatter area with clustered settlement. Within DIZ,
most of the houses (around 40%) are traditional, 10% are modern and 50% traditional.
Squatter settlements in the banks of Sardu and Seuti Khola are major encroachment of the
river banks and flood plain seen on Dharan. 34 ghare settlement reside on nearby project
vivinity within IIZ land without legal rights. They live in informal settlements without basic
infrastructure and services provided by government. The settlements is characterized as
slums due to their impoverished living conditions, highly congested spaces and an absence
of public facilities such as safe drinking water, sanitation and waste management.
5.3.3 Caste and Ethnicity
The project areas were characterized by the presence of diverse ethnic groups. The
population of the ZOI is dominated by Rai (20.72%) followed by the Limbu (11.66%),
Newar (11.06%), Chhetree (10.67%), Tamang (7.26%), Brahmin Hill (7.09%), Kami
(6.19%), Magar (4.22%) and rest below 4%. Following table shows the population
distribution by caste/ethnicity within ZOI.
Table 21: Percentage of caste/ethnic composition within Project Area
S.N. Caste/Ethnicity Popn % S.N. Caste/Ethnicity Popn % S.N. Caste/Ethnicity Popn %
1 Rai 28536 20.72 29 Hajam/Thakur 344 0.25 57 Mewahang Bala 42 0.03
2 Limbu 16061 11.66 30 Brahman - Tarai 299 0.22 58 Sudhi 40 0.03
3 Newar 15237 11.06 31 Bangali 281 0.2 59 Danuwar 40 0.03
4 Chhetree 14692 10.67 32 Dom 247 0.18 60 Dev 37 0.03
5 Tamang 10003 7.26 33 Rajput 213 0.15 61 Kewat 36 0.03
6 Brahman - Hill 9764 7.09 34 Jhangad/Dhagar 201 0.15 62 Ghale 33 0.02
7 Kami 8526 6.19 35 Dhimal 160 0.12 63 Thami 32 0.02
8 Magar 5810 4.22 36 Dhanuk 158 0.11 64 Tatma/Tatwa 31 0.02
9 Damai/Dholi 2968 2.16 37 Thakuri 154 0.11 65 Musahar 26 0.02
10 Gurung 2669 1.94 38 Thulung 139 0.1 66 Kumal 24 0.02
11 Kulung 2036 1.48 39 Samgpang 137 0.1 67 Kanu 21 0.02
12 Gharti/Bhujel 1858 1.35 40 Chamar/Harijan/Ram 135 0.1 68 Lohar 21 0.02
13 Musalman 1803 1.31 41 Rajbansi 119 0.09 69 Nachhiring 21 0.02
14 Marwadi 1684 1.22 42 Punjabi/Shikh 106 0.08 70 Halkhor 18 0.01
15 Tharu 1568 1.14 43 Kayastha 101 0.07 71 Dusadh/Pasawan/Pasi 16 0.01
16 Sarki 1489 1.08 44 Bhote 97 0.07 72 Kumhar 15 0.01
17 Teli 1233 0.9 45 Baraee 95 0.07 73 Bantar/Sardar 15 0.01
EIA of Sardu Khola Bridge Project DoLI
36
S.N. Caste/Ethnicity Popn % S.N. Caste/Ethnicity Popn % S.N. Caste/Ethnicity Popn %
18 Bantaba 977 0.71 46 Sonar 87 0.06 74 Rajdhob 15 0.01
19 Sherpa 940 0.68 47 Badi 83 0.06 75 Khatwe 14 0.01
20 Yakkha 728 0.53 48 Mallaha 77 0.06 76 Lepcha 12 0.01
21 Sanyasi/Dashnami 619 0.45 49 Bahing 76 0.06 77 Dhunia 12 0.01
22 Haluwai 619 0.45 50 Khawas 73 0.05 78 Munda 11 0.01
23 Sunuwar 581 0.42 51 Khaling 71 0.05 79 Others 236 0.17
24 Chamling 569 0.41 52 Badhaee 70 0.05 80 Dalit Others 89 0.06
25 Majhi 482 0.35 53 Koiri/Kushwaha 61 0.04 81 Janajati Others 19 0.01
26 Kathbaniyan 456 0.33 54 Satar/Santhal 50 0.04 82 Terai Others 174 0.13
27 Yadav 391 0.28 55 Dhobi 49 0.04 83 Undefined Others 258 0.19
28 Kalwar 346 0.25 56 Yamphu 44 0.03 84 Foreigner 25 0.02
Source: CBS, 2014
Within DIZ also, Rai are the dominant ones. In 34 Ghare settlement area, 150 hhs are Rai
followed by 100 hhs Dalits, 60 Limbu, 40 Tamang, 40 Newar, 20 Chhetree, 20 Brahmin,
10 Magar and 60 others. In Siran Devi Gaun settlement area, 23 hhs are Rai followed by 7
Tamang and 2 Dalits (Bishowkarma)
5.3.4 Language
Within ZOI, majority of the people of the project area speak Nepali language (42.49%)
followed by Limbu (10.06%), Newar (7.38%), Rai (5.94%), Tamang (5.93%) and Bantawa
(5.84%). Following table shows the population by mother tongue.
Table 22: Percentage of people speaking mother tongue within Project Area
S.N.
Languag
e Popn
%
S.N
. Language
Pop
n %
S.N
. Language
Pop
n %
1 Nepali
5851
5
42.4
9 18 Tharu 789
0.5
7 35 Puma 119
0.0
9
2 Limbu
1385
1
10.0
6 19 Thulung 721
0.5
2 36 Rajbanshi 75
0.0
5
3 Newar
1016
0 7.38 20 Bhojpuri 595
0.4
3 37 Lohorung 72
0.0
5
4 Rai 8182
5.94 21 Sunuwar 527
0.3
8 38 Chhiling 71
0.0
5
5 Tamang 8171
5.93 22 Dumi 503
0.3
7 39
Yamphu/Yamph
e 65
0.0
5
6 Bantawa 8042
5.84 23 Bhujel 489
0.3
6 40 Santhali 33
0.0
2
7 Maithili 4483
3.26 24 Bahing 397
0.2
9 41 Doteli 32
0.0
2
8 Magar 4331
3.15 25 Khaling 350
0.2
5 42 English 23
0.0
2
9
Chamlin
g 3596
2.61 26 Wambule 320
0.2
3 43 Punjabi 22
0.0
2
10 Kulung 2128
1.55 27 Mewahang 240
0.1
7 44 Dhimal 20
0.0
1
11 Gurung 1736
1.26 28 Sindhi 215
0.1
6 45 Khash 20
0.0
1
12 Sampang 1436
1.04 29 Bangla 212
0.1
5 46 Thami 16
0.0
1
13 Urdu 1173
0.85 30 Koyee 178
0.1
3 47 Danuwar 14
0.0
1
14 Hindi 1082
0.79 31 Nachhiring 168
0.1
2 48 Tilung 14
0.0
1
EIA of Sardu Khola Bridge Project DoLI
37
S.N.
Languag
e Popn
%
S.N
. Language
Pop
n %
S.N
. Language
Pop
n %
15 Rajsthani 1004
0.73 32
Uranw/Ura
u 166
0.1
2 49 Lapcha 11
0.0
1
16 Yakkha 896
0.65 33 Majhi 159
0.1
2 50 Others 847
0.6
2
17 Sherpa 839
0.61 34 Dungmali 123
0.0
9 51 Not Reported 474
0.3
4
Source: CBS, 2014
Within DIZ, most of the people speak Nepali (50%) followed Rai (25%), Limbu (12%) and
Tamang (8%) and remaining others.
5.3.5 Religion and Culture
Majority (55%) of people of the project area follow Hindut hat is followed by Budism and
the rest in small number follow other religions. Hence, they celebrate the common Hindu
festivals like Dashain, Tihar, Saune Sankranti, Makar Sankranti, Tamu Lhosar, Chaite
Dashain, Baisakh Purnima, Bhailo Purnima, Janai Purnima and Tij. The life rituals like
naming, thread ceremony, marriage and death ceremony are observed as per the respective
caste and ethnicity. Their cultural pattern and social life also has a deep rooted relationship
with the nature. They also believe on portfolio of God and Goddess attached with the
resources on which human life exists.
5.3.6 Literacy and Education
Considering the population above 5 years of age, the total literacy of ZOI is 82.84% (male
89.29% and female 77.20%). Literacy rate towards left bank side is higher (84.50%) than
that towards right bank side (73.76). The literacy status, population, aged 5 years and above
by literacy status, sex of ZOI is given in tables below.
Table 23: Population that have completed the education level within ZOI
Education Level
Population that have completed the educational level
Both Sex Male Female
Beginner 3118 1611 1507
Primary (1-5) 29833 15185 14648
Lower secondary (6 -8) 20414 10023 10391
Secondary (9 -10) 15751 7744 8007
S.L.C. & equiv. 19294 9456 9838
Inter-mediate & equiv. 9317 4676 4641
Graduate & equiv. 4141 2520 1621
Post Graduate equiv. & above 1319 907 412
Others 53 33 20
Non-formal education 3837 1692 2145
Level not stated 304 139 165 Source: CBS, 2014
Within DIZ, around 1000 people have completed S.L.C and equivalent level of education,
500 people inter-mediate and equivalent, 100 people graduate equivalnet, and 10 people
have compleded Post Graduate equivalent & above level of education.
There are around 2 primary and 1 secondary level schools within DIZ. As the ZOI includes
Dharan City itself, the area is well facilated with educational institutions including B.P
EIA of Sardu Khola Bridge Project DoLI
38
Koirala Institute of Health Sciences and Institute of Engineering Purwanchal Campus
(Eastern Region Campus).
5.3.7 Occupation
Within 34 Ghare settlement of DIZ, most of the households (more than 95%) are involved
in daily labor and only 2% are involved in business, 2% in government services and 1%
non government services. Within Siran Devi Gaun settlement of DIZ, 24 hhs are involved
in labor, 8 hhs business and 2 agriculture. However, within ZOI, most of the people are
involved in agriculture followed by services and business.
Due to topography and soil types agriculture is a perfect source of income generation near
project site. The bridge connects rural setting of Bishnupaduka area with Dharan city which
is the major market hub of Sunsari district. The agricultural and livestock products
(vegetables and dairy products) are daily brought to market centres.The project area is
reknowned for local chicken and kalo bangur. The hilly areas of project vicinity have
potential of professional cow and goat farming, which can be encouraged as the hill
sourroundings have enough grazing lands. Also, ward number 20 is famous for ginger and
turmeric farming.
5.3.8 Migration Pattern
Both in-migration and out-migration were reported in the project area. There are many
cases of migration that go unregistered. Dharan City towards left bank of the proposed
bridge is growing rapidly with many households from nearby region migrating towards the
city both permanently and temporary for jobs and business. People going abroad for
employment are more common these days among the youths. The major destinations
common to the youth in the project area are India, Malaysia, Dubai and Qatar.
5.3.9 Public Health and Sanitation
The project area is well equipped with health facilities as there is one health post within
DIZ and many health institutions including B.P Koirala Institute of Health Sciences within
ZOI. According to the District Health Office (2071 B.S.), the major health problems of the
area are helmenthiasis, headache, gastritis, pyrexia of unknown origin, respiratory tract
infection, impetigo, typhoid/enteric fever, tonsillitis, diarrhea, etc. The health status of
people has improved because of increased awareness towards health and sanitation.
As of 2011, 72.69 % of the households in the project area had modern flush type toilet,
23.66% have ordinary toilet while nearly just 2.92% are household without toilet facility,
(CBS, 2011) while remaining falls in other non-reported category.
5.3.10 Energy Use
The project affected area is connected with national grid electricity facility and hence
electricity is the main source of energy for lightning. Within DIZ, most of the households
(beside 4 HHs in Siran Devi Gaun that use kerosene for lightning) use electricity for
lightning. Aournd 40 HHs in 34 Ghare have solar facility for lightning beside electricity.
Following table shows the source of lightening within ZOI.
EIA of Sardu Khola Bridge Project DoLI
39
Table 24: Source of energy for lightening purpose
Total Households Fuel usually used for lighting
Electricity Kerosene Bio gas Solar Others Not Stated
32,693 31,136 1,065 133 22 100 237
Source: CBS, 2014
In case of cooking, 100 HHs in 34 Ghare within DIZ use fire wood and remaining 400 use
biogas. Simlarly, within DIZ of Siran Devi Gaun, 12 HHs use fire wood for cooking and
remaining 20 use biogas. Following table shows the source of cooking within ZOI.
Table 25: Source of energy for cooking purpose
Total
household
Fuel usually used for cooking
Wood /
firewood Kerosene LP gas
Santhi/
guitha
(cow
dung)
Bio
gas Electricity Others
Not
Stated
32,693 11,405 474 20,259 16 213 12 83 231
Source: CBS, 2014
5.3.11 Service Facilities
Drinking Water Supply:
Tap water is the main source of drinking water within project area. Settlements within DIZ
(Both banks), are using piped water sourced from nearby spring towards Bishnupaduka.
For other domestic purpose like washing cloths, people use river water from Sardu River
when available. Following table shows the source of drinking water within ZOI.
Table 26: Source of drinking water
Total
househol
d
Main source of drinking water
Tap/pipe
d water
Tubewell
/
handpum
p
Covered
well/kuw
a
Uncovere
d
well/kuwa
Spou
t
water
River
/strea
m
Other
s
Not
State
d
162,279 46,804 109,667 660 1,142 873 296 2,003 834
Source: CBS, 2014
Communication: Communication facility has infiltrated to almost all the places in the
project area through mobile servicesof various types. The cable phones used in the past are
losing popularity due to easily accessible mobile network. Radio and FM network has come
within the access of local people. However very limited households are able to enjoy
television. Internet service and printed media is yet to gain popularity in the area.
Electricity and Lighting: Most of the places in the project area have been supplied with
electricity through national transmission. According to CBS (2014), 80.82% of the
households have been using electicity from national transmission for lighting the house.
Remainging households have been relying on conventional fuel (kerosene), solar energy,
biogas and other.
EIA of Sardu Khola Bridge Project DoLI
40
Trade/business, industries: The project area lacks big industries and beside shops, bakery,
rice mill and local metal industries, no other trade/business activities are noticed within
project area. The recent turn of events happenings around Sardu with ward level activities
people from the uphill settelements of Bhanjyang have started Machhamar Homestay to
target people coming to Bishnupaduka which might be beneficial for 133 local houses at
Bhanjyang village which is 6km far from right bank of bridge. The other chances of opening
hotels and tiffin houses as small scale business (due to increased religious activities after
construction of the bridge), would be also very promising to locals. The nearest market
people would often travel to Bishnu paduka for religious visit which might result in several
income generating activities.
Local development activities: The project area is adjoining to Dharan city which is highly
active in local development activities. Different development activities like infrastructure
construction, tourism promotion, business activities, industrial activities, health and
educational institutions etc. are growing rapidly within the project area
Fuel Wood: With the growing access, the non-conventional fuel like Liquid Petroleum Gas
(LPG) is used on project vicinity and sourroundings by all the households.
Road and Transportation: The local level authorities have plans for promoting Dharan-
Mangalbare Bishnupaduka road for connecting rural areas of Bhojpur and Dhankuta
districts. The essentiality of Sradu Khola Bridge then plays strategically huge role in
promotion of connectivity and communication of rural areas of different distrcits to city
areas. The bridge not only promotes internal tourism due to cultural aspeccts of
Bishnupaduka but also helps in connectivity of rural areas to city areas.
River Crossing Facilities: There is no any provision of crossing Sardu Khola from bridge
as people are crossing the khola by walking. Also, there is under-construction of RCC
Bridge about 2km downstream at chatara line road.
Law and Order: During the field survey, the general law and order situation of the area
was found to be satisfactory. The nearest police post is stationed at mangalbare which is
1.5km left bank alongside ward no 11 on dharan- mangalbare road. All the three security
agencies of Nepal likewise, Nepal Police, Armed Police Force and Nepal Army have their
presence at district level. Minor disputes are solved by the involvement of local ward level
leader in coordination with local tol bikash samiti.
Market Centers: Mangalbare Bazaar is the nearest market in the project area whereas
Dharan is the major market centre.
Business and Industries: Different types of business enterprises and industries involved
in production and distribution of various types of goods and services in the project area.
The type and number of business/industries includes Mill, Furniture, Electrical/Electronics
and Computer Institute Construction Service.There are various other types of businesses,
especially shop stalls locally known as hat bazar at Mangalbare where various types of
items like garments, construction materials, groceries, restaurants, liquors,
EIA of Sardu Khola Bridge Project DoLI
41
medicine/clinics, cosmetics and tailor are found. The major business tooks place in Dharan
Bazar.
Major Religious, Historical, Natural, Touristic and Cultural Sites: Bishnu paduka is
the major religious site of the project area which is 6 km far from the proposed bridge
location. Similarly, the access road leads to nearest chure hill from where sight-seeing of
Dharan city can be observed. The newly opening of Machhamare Homestay at Bhanjyang
village which is 6km far from right bank of proposed project site is recent approach made
by local public for promotion on cultural tourism to Bishnupaduka. Hence, the project area
has high tourism potential (mainly religious tourism).
As most of the population belong to Hindu religion, they celebrate the common Hindu
festivals like Dashain, Tihar, Saune Sankranti, Makar Sankranti, Tamu Lhosar, Chaite
Dashain, Baisakh Purnima, FaguPurnima, Janai Purnima and Tij. The life rituals like
naming, thread ceremony, marriage and death ceremony are observed as per the respective
caste and ethnicity. Their cultural pattern and social life also have a deep rooted relationship
with the nature. They also believe on portfolio of God and Goddess attached with the
resources on which human life exists.
Non-Governmental Organization and Activities: A number of NGOs CFUG, are
working in the field of forest and environmental protection, water supply and sanitation,
disaster,women awareness, rural livelihood and income generating activities in the project
area and its vicinity.
EIA of Sardu Khola Bridge Project DoLI
42
CHAPTER 6: IDENTIFICATION OF IMPACTS
The impacts are examined on the basis of baseline condition of project area and likely
impacts during construction and operation phases. Such impacts have been identified based
on site observation, field survey & information obtained from the stakeholders and few
were identified from value judgment. The impacts are expressed in terms of their
magnitude, extent and duration.
6.1 Beneficial Impacts
6.1.1 Beneficial Impacts during Construction Phase
Employment Opportunities
During construction, the project will generate significant mandays of temporary
employment opportunities that constitutes unskilled personpower and skilled personpower
including engineers, technicians and operators. People will be required for excavation,
concrete works, scaffolding, gabion box weaving, transportation, supervision and
management during construction of this project and local people based on their
qualification and skill will have additional income opportunities. This will uplift the
economic status of the ZoI. However, if earned wage is saved and utilized for micro and
small scaled enterprises, benefit will be durable. The envisaged impact will be direct, local,
short term in nature, having high magnitude and hence will be very significant.
Enhancement of Technical Skills
This project not only provides employment opportunities to the poor and unskilled but also
supports in transfer of skills and technical know-how to work in similar construction works.
The employment opportunity will, on the other hand, be able to develop project type
specific skill among the workers which could subsequently be used in other project. These
skills will encourage the locals in getting long term employment opportunities. Workers
will acquire the additional knowledge through training in material handling, occupational
safety, general environment, health and social precautionary measures.
The envisaged impact will be indirect, local, long term in nature, having medium magnitude
and will be significant.
Increased Trade and Business Opportunities
During construction period, different types of commercial activities will come into
operation in order to meet the demand of construction crew. In general, the enterprises will
include food and teashops, groceries, lodges and restaurants for serving construction crews.
The demand for local products such as pulses, milk, meat, vegetables, fruits (especially
mango, litchi, etc) etc. will rise during the construction period which may provide added
impetus for local production and marketing. This will contribute to the local rural economy
and may help reduce rural poverty. The Machhamare Homestay at Bhanjyang village is
already showing signs of possible promotion of local tourism hospitality with the proposed
project at Sardu Khola. Such benefits may contribute to enterprise development, which
EIA of Sardu Khola Bridge Project DoLI
43
often continues to entrench beyond construction period. The project will give due priority
to the local products, local market and local petty contractors.
The envisaged impact will be indirect, local, short term in nature, having medium
magnitude and will be significant.
6.1.2 Beneficial Impacts during Operation Phase
Reduced Traffic Disruption
Vehicles can ply across the river only at some shallow point and that is possible only during
low flow conditions. After the completion of the project, the flow will not hamper the river
crossing in any season. People from the remote and isolated settlements of wards 11 and
20 of Dharan Sub-metropolitan City, will have more convenient access to the
Bishnupaduka as well as to the Dharan city due to ease of accessibility on Dharan-
Mangalbare-Bishnupaduka road. In the mean time, the time and cost of
travelling/transportation will also be reduced significantly. Similarly, the bridge will
encourage the transportation all year round.
The envisaged impact will be direct, local and the long terms having high magnitude hence
will be very significant.
Improvement of Transportation Services
Access to services is irregular and difficult at present. The new opening will connect two
wards of Dharan Sub-Metropolitan City on either bank of Sardu Khola. The road traffic
will increase as religious place of Bishnu paduka will be focal point of travveling on as
transportation services along approach road will be also improved. Once the road/bridge is
in operation, people will have cheap and easy access for various goods such as seeds,
chemical fertilizer and technology leading to increase in agricultural production and
diversification as well as their market. Good quality of road and structures will give rise to
number of public vehicles and competition thereby resulting low transportation cost. This
connection will also strengthen social and cultural ties among people living towards either
bank.
The envisaged impact will be direct, local and long term impact having medium magnitude
hence will be very significant.
Promotion of Agro-enterprise Related to Horticultural Products
Road access is crucial for economic development. With the operation of the bridge, a
reliable access will be established with the rural villages and this will promote agro-based
(crops and horticulture) and livestock based (dairy and meat) enterprises which have higher
prospects in the area. The 71 ethno-botanical plants having different use identified in area
and as mentioned in baseline will find more use, value and further processing as more
technicians will visit in the locality due to new connectivity. Moreover, the surroundings
have been identified as pockets for tropical fruits like Banana, Mango and Litchi.
Marketting of these fruits will be eased by the existence of the bridge.
EIA of Sardu Khola Bridge Project DoLI
44
The envisaged impact will be indirect, regional and long term having high magnitude,
hence will be very significant.
Access to Public Services and Basic Utilities
The construction of bridge will provide un-obstructed and reliable access to different basic
facilities like education, health, market, etc to the people of project area through means of
transportation for daily conveyance. People of remote locality of two wards will have easy
access to Dharan Sub-Metropolitan City for bigger health care facility, so is the case for
markets centers and education. The bridge will ease the vehicular movement and immediate
service of ambulance. The envisaged impact upon education, health and others will be
direct, long term, regional, of medium magnitude, hence will be very significant.
Timely construction of the proposed bridge and its regular maintenance will generate the
service in time and sustain the service.
6.2 Adverse Impacts
The adverse impacts during construction and subsequent operation and maintenance in
terms of physical, biological, socioeconomic, cultural and religious aspects due to project
actions are evaluated as follows:
6.2.1 Pre-Construction Phase
6.2.1.1 Biological Environment
Removal of Vegetation due to Site Clearance
The project does not require clearing of any trees except ground vegetation so the impact
is very minimal whereas for approach road 0.013ha needs to be acquire from river/flood
plain area and community forest. So there is minimal impact on biological environment.
6.2.1.2 Socio-economic and Cultural Environment
Land and Property Acquisition, and Compensation
Potential land required at proposed bridge site is government land. Land and property
acquisition and subsequent compensation measures will not be required for this project.
However the project will take consent of government land required for temporary purpose.
Issues related to community land and grazing
About 0.05ha land abutting Sardu Khola required for the project is Government land which
is not currently used for any productive community purpose. This will be used temporarily
for construction yard, construction vehicle parking, stockpiling and labor camp. There is
no conflict among communities regarding use of land by the project.
The proposed bridge location is not prime land for grazing for cattles including drinking
water for them and wallowing by buffalo.
6.2.2 Construction Phase
6.2.2.1 Socio-economic and Cultural Environment
EIA of Sardu Khola Bridge Project DoLI
45
Issues of effect on Social Services and Community Infrastructures
The construction crew will need services like water supply, electricity, telephone, provision
shop, health facilities, fuel, etc. which they will have to utilize from the existing facilities
in the area. This may create pressure on the existing common resources; especially water
supply, electricity and health service are already limited.
These envisaged impacts of the project will be direct, site specific, short term and of high
magnitude hence will be very significant.
Occupational Health and Safety Measures
During the construction phase, the construction workforces will be exposed to a number of
constructions related health risks and hazards. Fugitive emissions, noise and physical injury
during construction works such as slope cutting, foundation excavation, river training work
etc. may cause serious health impact. Unsafe drinking water, unhygienic sanitary condition
(i.e. lack of the latrine and sanitary facilities) in the construction camp can increase the risk
of additional and endemic diseases such as diarrhoea, dysentery and cholera.
The envisaged impact will be direct, local and short term having high magnitude hence
will be very significant.
Communicable Diseases
Certain communicable diseases might be transmitted by the outside workers. Workers
sharing the same camp facilityare at higher risk of such diseases. Intimacy between workers
and local people may spread diseases like HIV/AIDS and STDs.
The envisaged impact will beindirect, regional and long term having medium magnitude,
hence will be very significant.
Conflict between Locals and Outside Workers
Conflict may arise between the local people and outsider labours during the project
construction regarding recruitment and procurement for work. Presence of non-native
people may not be welcomed by the local residents. Additionally, the construction workers
may involve in gambling, alcoholism etc and eventually may get into conflict among
themselves or with the surrounding people. Similarly, workforce from outside may not be
familiar with the localculture of the project area and the disagreement may take the form
of argument ultimately creating conflict with local people.
The envisaged impact will be direct, local, short term, of low magnitude, hence will be
insignificant.
Gender Discrimination
As known from local consultation, discrepancy is already prevalent in the project area in
wage distribution among male and female labour forces. It is very likely that similar
treatment is continued while reimbursing the construction workforce involving the local.
The envisaged impact will be direct, local, short term, of medium magnitude, hence will be
significant.
EIA of Sardu Khola Bridge Project DoLI
46
Child Labour Issue
Most of the adolescents have been away from their homeland leaving only females and
children. Children have also been involved in productive work in the family. It is most
likely that children will be exploited by the contractors in the construction and related
works.
The envisaged impact will be direct, local, short term, of medium magnitude, hence will be
significant.
6.2.2.2 Physical Environment
Sediment Load in Sardu Khola
Excavation of sand and aggregates from the river flood plain can generate suspended
sediment load in the river. Such effects are also envisaged during the excavation of
foundations. This could affect the downstream channel.
The envisaged impact will be direct, local, short term and of low magnitude, hence will be
insignificant.
Stockpiling, Spoil Disposal and Transportation of Material
The major construction materials are steel, cement, sand and aggregate. Since the material
used for the construction is limited, stockpiling of steel, cement, sand and aggregates in the
construction yard and stockpiling yard (0.04ha) and for construction camp (0.01ha) of small
area will be acquired. Hence, few environmental implications are envisaged on air, water
and land.
Quarrying and Extraction of the River Bed Material
The required sand and aggregates will be sourced from the authorized supplier.
Thus, there is no issue in this regard.
Bank Stability and Cutting: As stated earlier, the area on the both sides consists of soft
sedimentary rocks and semi consolidated alluvium of Chure. The proposed project have no
such heavy cutting of the river banks for laying abutments and approach road whereas for
the left bank slightly slope should be cut for approach road where the natural slope is
found to be very gentle. The envisaged impact will be direct, site specific, long term, of
medium magnitude, hence will be significant.
Impact on Air Quality, Water Quality and Noise Level
Air Pollution: Diesel generator, machinery equipments, excavators, drillers, dozers and
transportation vehicles may introduce the fugitive & combustion emissions into
atmosphere. Dust emission can be expected to be high along approach road. Smoke & Dust
will also affect the road/bridge site, vegetation, local people and workers. The envisaged
direct impact due to air pollution will be, site specific and short terms and of medium
significance hence will be insignificant.
Water pollution: The water quality of river is in suitable range however construction and
personal activities of the labors may introduce several water pollutants into the river.
EIA of Sardu Khola Bridge Project DoLI
47
Probable water pollutants are turbidity, suspended & dissolved solids, fecal contamination,
oil & grease from vehicles and equipments, etc.The inappropriate use, storage, processing
& application of chemicals (i.e. fuel, lubricants, oils & acids and other materials) for the
construction may cause soil & ground water pollution. Fluid and solid waste resulting from
the construction camp may affect the nearby land and water body. Presence of pollutants
in the water may disrupt aquatic environment and dependent lives downstream.
These envisaged impacts due to the water pollution will be direct, local and short term in
nature and having moderate magnitude, hence will be significant.
Noise pollution: The present noise level of the area is very ambient. During the
construction period, operation of machines, excavators, power tiller, movementof
transporting vehicles, trucks and construction equipments will increase the existing noise
level.
The envisaged direct impact will be, site specific, short term, local and of medium
magnitude hence will be significant.
Impact due to Solid Waste Generation
Construction activities will produce solid wastes such as synthetic materials and some
forms of inorganic wastes, whereas, domestic activities will produce mainly food wastes
and excretory wastes. Improper dumping and management of these wastes can result in
unpleasant odors, deterioration of water quality in the river water and groundwater, visual
impacts that can cause health related hazards to the local inhabitants.The envisaged impact
will be direct, site specific, short term, of high magnitude, hence will be very significant.
6.2.2.3 Biological Environment
Impact on Aquatic ecology due to sediments from foundation excavation activities
Construction of bridge will require temporary diversion of River by construction of
diversion bund. Construction work in River will also increase chances of increase in
turbidity due to sediment load. The Sardu Khola has many species of aquatic life, including
fresh water fish species like Buduna (Garra annandalei), Bam Sahar (Tor spp.), Eel
(Anguilla bengalensis), Katle (Acrossocheilus hexagonolepis), Aslashark (Wallago attu),
Pothi (Puntius spp.) and Rhou (Labeo rohita), which may get adversely affected by such
activities and pollution in water.
The impact will be direct, high significance, local and short-term.
There will be various mechanical activities along the bank of Sardu River during the laying
of abutments. The involvement of heavy machineries and intensive construction activities
along the river channel hinder the activities of aquatic organisms, alongside the destruction
of their natural habitat. Similarly, some members of construction crew would involve
themselves in fishing activities in their spare time causing the population of some fish
species to decline.
This impact is envisaged to be medium magnitude, local and short term in duration and
limited to construction period.
EIA of Sardu Khola Bridge Project DoLI
48
Impacts on General, Rare, Endangered and Threatened Species of Flora and Fauna
The forest of Chure region and especially that of the inner Terai is heavily disturbed due to
human activities and natural disasters as well. So the otherwise inherently diverse zone in
terms of wildlife is very infrequently attended by very few wild animals. Moreover, the
area where the bridge has been proposed is prodominantly human habitation with
infrequent movement of animals. Hence, this impact is envisaged to be medium
significance, medium term in duration and local in extent.
Though infrequently, lowland mammals and birds visit the project site and surrounding.
Many wildlife species are rare. Visiting birds and animals could be disturbed due to
construction activities. Workforce may involve in hunting and poaching activities during
construction.
This anticipated impact will be indirect, local, short term, having medium magnitude, hence
will be significant.
6.2.2.4 Chemical Environment
Impacts of Construction Wastes (Chemically Hazardous Liquid Wastes and Solid
Wastes, Sanitary Wastes, and other Organic and Inorganic Wastes etc.)
Construction work will require oil and fuel, lubricants, imulsion paints and other chemical.
Intrusion of these matters into the water may deteriorate the water quality seriously. The
envisaged impact will be direct, site specific, short term, of medium to High magnitude,
hence will be very significant.
6.2.3 Operation Phase
6.2.3.1 Socio-economic and Cultural Environment
Ribbon Settlement along the Road
There is a possibility of concentration of commercial activities and settlements from hinter
land to approach road alignment. There are chances of erecting new and haphazard
settlements along the newly operated connectivity to open marketing options. This practice
could disturb the traffic, entice for encroachment of the RoW, increase possibility of
accidents, decline the aesthetic value and reduce the overall capacity of road. If such
practices are not controlled by enforcing specific legal actions.
The envisaged impact will be indirect, site specific, long term, of high magnitude, hence
will be very significant.
Bridge and Road Safety Measures, Accidents andLoss of Life and Property
There are chances of vehicular accidents on the approach curve and sharp turnings
especially on both side of proposed bridge. Inadequate provision of the road safety
measures like lack of signals and lack of enforcement of traffic rules during operation
period may invite accidents and even loss of life.
The envisaged impact will be direct, site specific, long term, of high magnitude, hence will
be very significant.
EIA of Sardu Khola Bridge Project DoLI
49
6.2.3.2 Physical Environment
Slope/Bank Instability and Sustainability of Bridge
The fluvial deposits and soft rock along the bridge and approach road embankmentat either
bank may become unstable triggering slope failure ultimately affecting the bridge
durability.
The envisaged impact willbe direct, site specific, long term and of moderate magnitude,
hence will be significant.
Impact due to Air and Noise Pollution
Increased number of additional vehicles due to availability of easy road access can cause
air and noise pollution. The noise of horns from vehicles can cause problem to nearby
community.
The impact will be direct, of low magnitude; site specific and long-term in nature hence
will be insignificant. However since the movement of vehicles is not expected to be high,
the impact will also be minimal and momentary.
The below Table 27 and Table 28 shows the summary of beneficial as well as adverse type
of impacts that were identified during the study along with their scores.
Table 27: Summary of the Beneficial Impacts and Scores
Activity Issues Related beneficial
impacts
Type of impact
Sig
nif
ica
ne
Imp
act
Ex
ten
t
Du
rati
on
Ma
gn
itu
de
Construction Phase
Construction of
bridge and
approach road
Employment opportunities Generation of temporary
employment and increase
in income level
D L
20
ST
05
H
60
Vs
85
Enhancement of technical
skill
Increase in income
generating activities and
employment opportunities
IN L
20
LT
20
M
20
S
60
Increased Trade and
Business opportunities
Increase in income level
of non-worker through
demand for local
agricultural products
IN L
20
ST
05
M
20
S
45
Operation stage
Operation of road
and bridge
Reduced traffic disruption Transportation facility in
the area all year round
D L
20
LT
20
H
60
Vs
100
Improvement of
transportation services
Safe travel, Improve
accessibility, saving of
travel time and cost
D L
20
LT
20
Mo
20
Vs
100
Promotion of agro-
enterprise
Economic improvement IN R
60
LT
20
H
60
Vs
140
Access over public
services and basic utilities
Easier access to
educational institutions,
D R
60
LT
20
Mo
20
Vs
100
EIA of Sardu Khola Bridge Project DoLI
50
Activity Issues Related beneficial
impacts
Type of impact
Sig
nif
ica
ne
Imp
act
Ex
ten
t
Du
rati
on
Ma
gn
itu
de
health institutions,
religious places etc.
Table 28: Summary of Adverse Environmental Impact and Scores
Activity Issues Related adverse Impacts Type of
impacts
Sig
nif
ica
nce
Imp
act
na
ture
E
xte
nt
Du
rati
on
Ma
gn
itu
d
e
Pre- construction
Project Planning and
design Process and reliability of
detail survey and design
Inappropriate alignment, construction
camps, asphalt plants, etc.,
encroachment of sensitive area
D L
20
ST
5
H
60
Vs
85
Construction Phase
Socio-economic and Cultural Environmental Impacts
Construction of bridge
and approach road
Impact on the social
services and community
infrastructure
Pressure on social service facilities
likewater supply.
D Ss
10
ST
10
H
60
Vs
80
Construction force and
occupational safety
Occupation Health and
Safety measures
Exposure of construction workforce to
related health risks and hazards due to
operation of machines & construction
work, improper sanitation etc.
D L
20
ST
05
H
60
Vs
85
Construction force and
communicable
diseases
Communicable diseases Impact on health of locals and
construction workers due to proximity
to infected person, Sexual contacts
and proliferation of HIV/AIDs and
STDs
ID R
60
LT
20
Mo
20
Vs
100
Operation of
construction camp
Conflict between locals
and outside workers
Conflict during work due to distinct
thought and cultural perception;
alcoholism and gambling.
D L
20
ST
05
Lo
10
In
35
Construction activity,
wage and female
participation
Gender discrimination Discrimination in wage/salary
distribution
D L
20
ST
05
Mo
20
S
45
Construction and child
involvement
Child labour issue Use of child labour force in risky jobs D L
20
ST
05
Mo
20
S
45
Physical Environmental Impacts
Construction activities Sedimen load in river
water
Impacts on the river and its biota by
increased turbidity
D Ss
10
ST
05
Lo
10
In
35
Excavation of
foundation, Storage of
construction materials
Stock piling, spoil/waste
disposal, Transport of
construction materials
Impact on the river ecology by
cement, soil and excavated materials
on water and others resources
D Ss
10
ST
05
Mo
20
In
35
Construction activity Bank stability Bank instability and chances of bank
failure
D Ss
10
LT
20
Mo
20
S
50
EIA of Sardu Khola Bridge Project DoLI
51
Activity Issues Related adverse Impacts Type of
impacts
Sig
nif
ica
nce
Imp
act
na
ture
E
xte
nt
Du
rati
on
Ma
gn
itu
d
e
Construction work
:Air, Water and Noise
pollution
Impacts on air quality due
to operation of
equipments and vehicles
Introduction of fugitive and
combustion emissions, dust (PM10)
and smoke, etc. and its impact on
workers, local people and vegetation
D Ss
10
ST
05
Mo
20
In
35
Impact on water quality Mixing of pollutants like turbidity,
fecal contamination, oil and grease
and other inorganic and organic
wastes resulting pollution of water
body.
D L
20
ST
05
Mo
20
S
45
Impact of noise from
operation of equipments
and vehicles
Health of local people and worker D L
20
ST
05
Lo
20
S
45
Construction work and
Solid waste generation
Impact due to solid waste
generation
Synthetic materials, construction and
domestic wastes reduce land and water
quality, aesthetics impacting on human
and environmental health
D Ss
10
ST
05
H
60
Vs
75
Biological Environment Impacts
Construction work, in
stream activities
Impact on Aquatic
ecology due to sediments
from excavation and
diversion
Increase turbidity and sediment load
causing pollution and fish movement
and illigal and illicit fishing by
workers on spare time
D L
20
ST
05
H
60
Vs
85
Construction work,
vehicle
movement on wildlife
distribution
Impacts on rare,
endangered, threatened
and endemic species
Hunting and poaching by workforce;
road collision and fatal injury to
wildlife and death; disturbance to
wildlife due to movement of vehicles
ID
L
20
ST
05
Mo
20
S
45
Chemical Environment Impacts
Use of chemicals in
construction works
Impacts of construction
wastes, oil and lubricants
spillage
Water pollution & impact on aquatic
animals due to oil, lubricants, acids.
suspended and dissolved solids, oil &
grease, fuels, organic wastes
D Ss
10
ST
05
H
60
Vs
75
Operation Phase
Socioeconomic and Cultural Environment Impacts
Operation of bridge
and the approach road
Ribbon settlement along
the project alignment
Development of Ribbon settlement
and encroachment of RoW, increased
accidents, delay in traffic movement
ID Ss
10
LT
20
H
60
Vs
90
Use of bridge and
approach road
Bridge and road safety
issues
Chances of road accidents in the
turnings of the Bridge/Road and Loss
of life and property
D Ss
10
LT
20
Mo
20
Vs
50
Physical Environment
Operation of bridge
and approach road
Bank instability and
failure and River shifting
Bank instability andcutting;
Foundation excavation by changed
river flow; Flood and safety of bridge
D Ss
10
LT
20
Mo
20
S
50
EIA of Sardu Khola Bridge Project DoLI
52
Activity Issues Related adverse Impacts Type of
impacts
Sig
nif
ica
nce
Imp
act
na
ture
E
xte
nt
Du
rati
on
Ma
gn
itu
d
e
Operation of vehicle Impact due to Airand
Noise pollution
Dust, smoke, noise level, due to
vehicle movement and problem to
local community
D Ss
10
LT
20
Lo
10
In
40
Note: D= Direct; ID = Indirect, Ss= Site Specific; L = Local, R = Regional; ST= Short Term, NA
= Not Applicable of No Impact, MT = Medium Term, LT = Long Term; Lo = Low, Mo =
Moderate, H = High, I=Insignificant, S=Significant, Vs=Very Significant, Hs=Highly
Significant
EIA of Sardu Khola Bridge Project DoLI
53
CHAPTER 7: PROJECT ALTERNATIVES
The aim of the project is to construct bridge and improve the transportation network for the
promotion of quick and safe connectivity. Various alternatives were considered to achieve
the project’s objectives in environment friendly manner.The alternatives were analyzed in
terms of:
No action option;
Project alternatives;
Alternative location/site;
Alternative design and construction approach;
Alternative schedule and process; and
Alternative resources and technology.
These alternatives are analysed and evaluated subsequently in following sub-headings;
7.1 No Action Option
People from the remote and isolated settlements of 11 and 20 of Dharan Sub- Metropolitan
City along Dharan-Mangalbare-Bishnupaduka road of Sunsari District have to detour and
will be deprived from the mainstream of the development through access if this option is
not implemented. In absence of motorable bridge the road do not serve access towards
Ward no. 20 of Dharan Sub- Metropolitan City and movement of people between banks of
Sardu khola is limited. People towards right bank have to detour to reach district headquater
Sunsari. The construction of the proposed bridge provides year round motorable access to
the people of immediate remote area from bridge site like sagarmatha Tole, 34 ghare tole,
to Siran Devi gaun, Bishnu paduka including other areas. Additionally, vegetables, fruits
and milk have high potential in ward no 20 of Dharan. The potential religious tourist’s
arrival may be also higher in Bishnu padulka as accessibility will be high with construction
of motorable bridge in proposed location.
7.2 Project Alternative
Culvert is not feasible because width of river is more than 6 m. Construction of the
Causeway also is not feasible considering the river characteristics as it has been observed
from the service of existing one. A suspension bridge also exists but is applicable for
pedestrians only. In this context, motorable bridge is identified as the best alternative over
it
7.3 Alternative Location/Site
Considering the identical nature of the geology along the river stretch, the only limiting
factor identified was the width of the river which is relatively narrower and channel is
straight at the proposed location. No other better and suitable alternative location for bridge
axis was found than the proposed one. Flow width (river channel) is wider down
streamwhile aligning approach road along both banks of the river is lengthly, costy and
EIA of Sardu Khola Bridge Project DoLI
54
time consuming towards upstreams. The bridge site other than selected one needs longer
bridge with more protection works, lengthy and complicated approach road construction,
and considerably higher cost of construction. Feasibility study has also revealed the
proposed bridge location as geologically and hydrologically more suitable than any other
immediate locations. Hence, the present site is best fit for the project. Nonetheless, owing
to the nature of the river, river training is necessary on both banks.
7.4 Alternative Design and Construction Approach
Considering the river bank, channel morphology, bed & bank materials, alignment of the
existing road, durability and maintenance cost, Box type bridge option is found to be
suitable. The construction approach selected is a labor based approach with minimum
utilization of the machine power as it provides maximum job opportunities to the local
people with minimal environmental implications.
7.5 Alternative Schedule and Process
The construction schedule has been proposed taking the climatic and hydrological
condition of the area into consideration. Similarly, the schedule of active construction of
foundation of the bridge is proposed in dry period to avoid the impact of high discharge of
the Sardu Khola during rainy season.
7.6 Alternative Resources
As cement and steel/iron has no alternative for the project construction, these materials will
be sourced from the Nepalese and nearest Indian market, Jogbani. Necessary aggregates
are locally available in the river. Among the construction modalities, maximization of labor
based option was preferred as it provides job opportunity to the local people. The proposed
bridge construction work shall have manual based work as far as possible and as mentioned
earlier.
7.7 Other matters
The alternative for the environmental management system could be the establishment of
the Environmental Monitoring Unit at MoFAGA/DoLI/BS. The unit will conduct the
monitoring work in the regular interval of time. It will be better if the environmental
monitoring unit comprises of the representatives of clients, consultant, contractor and the
local authorities as required. Timely meeting shall be conducted where the compliance
status and future necessities shall be discussed, and certain agreement could be decided.
Third party monitoring could also be an alternative.
EIA of Sardu Khola Bridge Project DoLI
55
CHAPTER 8: ENVIRONMENTAL IMPACTS,
ENHANCEMENT AND MITIGATION MEASURES
Mitigation and enhancement measures are designed to cope with adverse consequences and
to enhance the positive impacts on the environment because of the project implementation.
Mitigation measures are recommended actions that reduce, avoid or offset the potential
adverse environmental consequences of the project activities.
For the impacts, practical mitigation measures (or actions) have been proposed to mitigate
the possible environmental and social impacts that may result due to project
implementation (construction and operation). The proponent of the project has prime
responsibility in carrying out the indicated mitigation measures.Keeping in mind the
current political and social situation, several of these require sharing of responsibilities
with public authorities and local stakeholders. Four categories of environmental and social
mitigation measures are generally identified:
Preventive or Impact avoidance measures are usually implemented at the project
planning and design stage, in order to eliminate or minimize from the onset all
anticipated adverse impacts.
Corrective or Reductive measures are those used to eliminate a source of impact or
reduce its intensity to an optimal or acceptable extent.
Compensatory measures seek to compensate for impacts that cannot be mitigated and
for residual impacts of the project after implementation of mitigation measures.
Enhancement or Benefit Augmentation measures are used to improve existing
environmental or social conditions, which are not directly affected by the project. Such
measures may be implemented outside the study area. To be efficient, these measures
must be defined in cooperation with all stakeholders.
Adverse and beneficial impacts that are not identified or anticipated at this stage, if latter
discovered during the construction and operation stage of the project shall be duly taken
care of by the proponent.
8.1 Beneficial Impacts and Augmentation Measures
No augmentation measure has been suggested for this benefit. However, the contractor will
be encouraged to give priority to local and marginalized people including women in
construction works as per their skills.
8.1.2 Beneficial Impacts during Operation Phase
Reduced Traffic Disruption
Regular/annual maintenance of the bridge and the approach road will be arranged by
proponent with the help of DCC. Annual budget will be allocated for this purpose.
Improvement of Transportation Services
Necessary arrangements will be made for protecting the bridge against the harm due to
anthropogenic and natural factors. This includes arrangement of regular inspection and
EIA of Sardu Khola Bridge Project DoLI
56
maintainace. The proponent will allocate budget for regular inspection and maintenance of
the bridge and its approaches.
Promotion of Agro-enterprise Related to Horticultural Products
No augmentation measure has been suggested for this benefit.
Access to Public Services and Basic Utilities
Timely construction of the proposed bridge and its regular maintenance will generate the
service in time and sustain the service.
8.2 Adverse Impacts and Mitigation Measures
8.2.1 Pre-construction Phase
8.2.1.1 Physical Environment
The mitigation measures adopted during design or pre-construction phases are of
preventive in nature with two basic objectives: (i) avoiding costly mitigation, and (ii)
awareness among the stakeholders for environment protection while constructing and
operating infrastructure services.
Route/Site Selection
The Site for the Bridge is appropriately selected considering all the technical and
environmental parameters. There is no new route selection but following the existing
alignment as discussed earlier in Chapter 7- Project Alternatives.
Detailed Survey and Design
The design parameters will adopt the design standard of DoR/ IRC. The works will be
executed through NCB based construction. River training will be used for stabilization of
the river banks. All provision proposed in the EMP of this EIA document will be fittingly
reflected in the Design.
The measures proposed during this phase include:
Including proven standards of good practices ( Incorporation of
Environmental Guidelines of then DoLIDAR and current DoLI and provisions
of the EMP of this EIA Document);
Avoidance of sensitive areas (appropriate selection of Bridge site, Approach
Road alignment, construction camps, asphalt plants);
Location of asphalt plants, and stockpiles away from settlements, cultivated
land and unstable area, (potential risks for later causing direct and
subsequent problems for surface and groundwater, water pollution, disruption
of waterways, air pollution, noise pollution, accelerated and uncontrolled dump
sites, landscape aesthetic sores, and public health & accident risks);
Minimise occupational health and safety risks (health / safety regulations,
adequate safety gears, planning for adequate signage and awareness
programmes);
EIA of Sardu Khola Bridge Project DoLI
57
Prevent inducement of uncertainties among locals relating to the Project (
Plan for timely process of public consultation. Ensure that the social survey
team is fully aware of the technical design and alignment centreline before
starting HH surveys);
Construction works may cause stresses, shortage and damage to local natural
resources like drinking water, irrigation water, soil and services ( plan and
study alternative and/or outside provision of required resources);
Loss of cultural heritage, it may (needs to be avoided to the extent possible,
seeking alternative solutions in close consultation with the affected
communities);
8.2.2 Construction Phase
8.2.2.1 Socio-economic and Cultural Environment
Issues of effect on Social Services and Community Infrastructures
The contractor will manage some utilities like communication, lighting and cooking
energy, drinking water supply, etc within the camp so as to avoid the pressure on local
services. The contractor will be responsible for reconstruction and rehabilitation of
damages due to their activities; any damage to existing road in project location, like
formation of ditches, will be controlled and rehabilitated. The responsibility of looking after
the amenities of the workers is the responsibility of the contractor.
Occupational Health and Safety Measures
The contractor will maintain occupational health and safety arrangement and strictly
enforce the safety measures.
Construction workers will be prior informed about job hazards, emergency
procedures and any other relevant safety measures.
Personal Protective Equipments (PPE) such as helmets, boots, gloves, safety belts,
safety glasses and masks will be provided to the workers working in the
construction sites.
Contractor will arrange the First Aid Kit Box and standby medicine for workforce
during working period and emergency situations.
In case of serious injury and accidents, the injured will be run to the nearest hospital
with the necessary diagnosis and treatment facilities.
Warning signs, posts, barriers and guards will be installed to restrict access of
unauthorized persons to construction sites.
Only authorized person will be allowed to operate heavy machinery and
equipments.
Temporary drinking water supply and latrine pit will be established at site.
Dust control will be done in the construction areas by sprinkling water.
Vehicles and equipments will be maintained in proper condition so that they
produce less noise.
Group accidental insurance will be done for the workers.
EIA of Sardu Khola Bridge Project DoLI
58
Communicable Diseases
Sanitary condition will be maintained in the construction camp by arranging toilets and
water supply. The toilets will be located at least 50 m away from the river. Workers will be
encouraged to keep their camps clean and tidy. Workers will be informed about STDs and
the preventive measures. Workers will undergo regular health check-ups in the construction
camp which will be arranged by the contractor.
Conflict between Locals and Outside Workers
Construction workers from outside the project area will be well-informed about the general
norms and values of society. The construction workforce will be instructed to respect local
people, especially the female members and observe/follow the local culture and tradition.
Workforce will be discouraged to involve in activities like gambling and alcoholism. Local
people will be informed about project activities, requirements and time schedules. Local
people will be given maximum priority in employment.
Gender Discrimination
Project will establish agreement with contractors to consider male and female equally for
wage distribution for works of similar nature. Male workers will be instructed to respect
their female counterparts.
Child Labour Issue
Child labour will be prohibited totally. Project will establish agreement with contractors to
prohibit child labour and the program will monitor the compliance regularly.
8.2.2.2 Physical Environment
Sediment Load in Sardu Khola
Excavated material will be stockpiled for use in river training works or for filling or
reclamation of land during approach road construction. Minimal cut and fill approach will
be adopted to protect the loose materials along slope from eroding and destabilizing.
Foundation works will be avoided in rainy season. Blockage of river flow will be cleared
immediately.Adoption of method of pumping mud slurry to avoid sediment load discharge
in the river while working on mat and piers is important. This is the subject of construction
management and on additional budget will be required for this.
Stockpiling, Spoil Disposal and Transportation of Material
Similarly the spoil generated is expected to be used up all. Small volume of spoil is
expected to be generated from foundation (open pier, abutment and protection structures)
excavation. Of the total spoil generated, significant volume will be used in backfilling in
foundation pits and trenches. The remaining spoil will be used in fill material for approach
road. And there will still be deficit of fill material for approach road.
Although, limited quantity of material will be used for construction, and all the spoil will
be used up, there may be some environmental implication of temporary storage of these
materials and can be minimized by adopting following measures:
Material will be stockpiled at fallow land and covered,
Proper drainage will be arranged around the stockpile area,
EIA of Sardu Khola Bridge Project DoLI
59
Required aggregates will be collected from river bed sustainably whenever
required,
Floodways, natural drainage paths, water bodies, farmlands will be avoided,
Stockpiling of the construction aggregates will be done above the high flood level
of the river,
Stockpiling of the cement and other materials in shaded structures within the
construction camp will be made,
Spoil generated from excavation of the abutment and foundations will be used for
land filling or reclamation for approach road construction and river training works.
These are the subject of construction management and no additional budget will be required
for this.
Bank Stability and Cutting:
Proper engineering and bioengineering techniques will be adopted to protect bank cutting
and erosion and avoid flood risk within 150 m upstream and 50 m downstream from the
bridge location. Construction of river training works with gabion (150 m u/s and 50 m d/s)
to minimize bank cutting.
Impact on Air Quality, Water Quality and Noise Level
Air Pollution: To mitigate the air pollution and its effect the following measures will be
carried out:
Construction equipments and vehicles will be regularly examined and maintained
in proper condition.
Water will be sprinkled along access road at least two times a day to reduce the dust
emission.
Proper protection works like fencing by GCI sheets or walls will be done at
excavation and disposal site.
Construction materials will be properly covered during conveyance.
Speed limit will be enforced for service vehicles.
Workers will be encouraged to use masks.
Water pollution: The proponent will adopt the following mitigation measures in order to
minimize the impact on the surface and ground water quality;
Disposal of the soil, sludge and the other wastes directly into the water body will
be avoided;
Prevention of the soil slippage at the toe of stockpile areas by installing barriers at
the perimeter;
Prohibition of the open urination and defecation by workers. Pit toilets will be
provided at the work sites;
Restriction of the vehicle washing in the river; and
Safe storage and the wise use of the chemicals.
Noise pollution:
The following mitigation measures will be adopted to minimize the noise pollution:
EIA of Sardu Khola Bridge Project DoLI
60
Concrete mixer, including other construction equipment etc. will be maintained in
proper condition by applying grease and lubricants.
Sound producing equipments will be preferred to use only in day time.
Earplug will be provided to the worker involved in equipment operations.
Aggregate screening measures will be kept at area away from settlement.
Impact due to Solid Waste Generation
The solid waste generated from the construction/labor camp will be segregated at source
and degradable waste will be used for composting.All the camp wastes and construction
wastes will be placed in the designated waste collection pits away from the water path. The
separate storage areas will be established for all punctured containers (drums, carboys,
flasks etc) and will be processed for selling to scavengers. Similarly, the offsite activities
of the workforce that are potential to cause pollution of surface and subsurface waters will
be prohibited.
8.2.2.3 Biological Environment
Impact on Aquatic ecology due to sediments from foundation excavation activities
To avoid disturbance to aquatic life due care will be given during temporary diversion of
river such that it will generate minimal sediments and have insignificant impact on
increasing turbidity of the river due to sediment. As far as possible the short diversion shall
assume natural stream flow. The workers will be strictly prohibited from fishing or using
any destructive fishing technique that will effect not only the fish population but also affect
other aquatic life.
Impacts on General, Rare, Endangered and Threatened Species of Flora and Fauna
Hunting and poaching by the construction crew will be strictly prohibited. The construction
activity will be managed so as to minimize disturbance to wildlife; speed limit will be
enforced for transporting vehicles.The impact can be minimized by employing the local
labours. Similarly, restriction will be put on construction workers from entering into the
local forest areas and the provision will be enforced as punishable offense. In addition,
restriction will be put on the use of wildlife meat in the construction camps. A hoarding
board will pe placed at bridge site to aware workers and locals alike on importance of
wildlife, conservation and importance and sensitivity of conserving Chure Region in terms
of biodiversity.
6.2.2.4 Chemical Environment
Impacts of Construction Wastes (Chemically Hazardous Liquid Wastes and Solid
Wastes, Sanitary Wastes, and other Organic and Inorganic Wastes etc.)
The chemicals used during construction will be handled properly. Similarly, proper
barricades will be established to isolate the construction material. Chemicals, oils and fuels
will be stored in the impervious floor in such a way that no leakage or spillage will occur
to drainage system.
EIA of Sardu Khola Bridge Project DoLI
61
6.2.3 Operation Phase
6.2.3.1 Socio-economic and Cultural Environment
Ribbon Settlement along the Road
The mitigation measures will be to discourage such settlements adjacent to the approach
Road and Bridge. Speed Limit signs shall be erected at such locations. Respective DCC/
Sub-Metropolitan /Wards and DAO will regulate the possible illicit construction and
activities along the road alignment so as to minimize the impacts. DCC/ Sub-Metropolitan
/Wards in coordination with DAO shall place hoarding board that clearly outlines the road’s
RoW and prohibition of construction of any kind of permanent structure within the RoW.
Bridge and Road Safety Measures, Accidents andLoss of Life and Property
Appropriate design will be adopted focusing required bridge and road safety measures.
Required delinators, safety signs, speed humps, road marking will be used as appropriate
along road and bridge. Four signposts will be installed near the bridge for this purpose.
Road safety measures will also be adopted following 3-Es (i.e. Engineering, Enforcement
and Education). The bridge and the approach road will be repaired and maintained
regularly. The DCC and DoLI will allocate budget for the regular inspection and the
maintenance of bridge.
6.2.3.2 Physical Environment
Slope/Bank Instability and Sustainability of Bridge
The slope will be stablized by appropriate engineering structure. Project infrastructure will
be protected by river training works upstream and downstream of the project and on both
banks. Cost has been provisioned in design and estimate document for river training works
and bank protection works. Bridge User Committee will be formed to enforce the protective
provisions and DCC will monitor on such activities. Bioengineering technique will be
adopted on the both banks. Afforestation of locally suitable species like Sissoo, Khayar,
and Bambool will be carried out along the bank area.
Impact due to Air and Noise Pollution
Road will be maintained frequently to minimize air and noise pollution. However since the
movement of vehicles is not expected to be high, the impact will also be minimal and
momentary.
8.3 Actions, Impact and Mitigation Measures
To avoid descriptive repetition, measures have been presented in tabular form against the
envisaged impacts along with the required cost estimation. This section has prescribed the
practical and cost effective mitigation measures to minimize and compensate the effects of
adverse impacts to acceptable level. The project proponent will ensure to implement these
measures during the construction and operation of the project. The below table represents
the beneficial impacts and enhancement measures (Table 29) as well as mitigation
measures for the reduction of impacts (Table 30) respectively.
EIA of Sardu Khola Bridge Project DoLI
62
Table 29: Beneficial Environmental Impacts and Proposed Enhancement Measures
Activity Issues Related beneficial
impacts
Benefit augmentation
measures
Responsible agencies
Executing
agencies
Supporting
agencies
Construction Phase
Increased
Trade and
Business
opportunities
Increase in income
level of non-worker
through demand for
local agricultural
products
Priority to local products,
local market and local
contractors
Contractor&
DoLI/LRBSU
DoLI/LRBSU
Operation stage
Operation of
road and
bridge
Reduced traffic
disruption
Transportation
facility in the area all
year round
Regular maintenance of
bridge and approach road
whenever necessary
DoLI/LRBSU DoLI/LRBSU
Improvement of
transportation
services
Safe travel, Improve
accessibility, saving
of travel time and
cost
Regular bridge and approach
maintenance
Allocation of budget for
regular inspection and
maintenance of the bridge.
DoLI/LRBSU DoLI/LRBSU
Promotion of
agro-enterprise
Economic
improvement
No augmentation measure
within the scope contractor or
proponent
Wards/ NGOs/
CBOs
DoLI/LRBSU
Access over
public services
and basic utilities
Easier access to
educational
institutions, health
institutions, religious
places etc.
Timely implementation of the
project
Regular maintenance of the
bridge
DoLI/LRBSU DoLI/LRBSU
Table 30: Adverse Environmental Impacts and Proposed Mitigation Measures
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
Pre- construction
Project
Planning and
design
Process and
reliability of
detail survey
and design
Inappropriate
alignment,
construction
camps, asphalt
plants, etc.,
encroachment
of sensitive
area
The bridge design will
follow the standard
methods.
All provision proposed in
the EMP of EIA
document will be
properly reflected in the
design.
LRBSU DoLI/LRBSU
Construction Phase
Socio-economic and Cultural Environmental Impacts
Construction
of bridge and
approach road
Impact on the
social services
and
Pressure on
social service
facilities
Provision of basic
utilities within camp
perimeter
Contractor/Proponent
DoLI/
Consultant
EIA of Sardu Khola Bridge Project DoLI
63
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
community
infrastructure
likewater
supply.
Building consensus with
local people for using
community
infrastructures and
resources
Any damage to existing
road in project location
like formation of ditches
shall be controlled and
rehabilitated.
Construction
force and
occupational
safety
Occupation
Health and
Safety
measures
Exposure of
construction
workforce to
related health
risks and
hazards due to
operation of
machines &
construction
work,
improper
sanitation etc.
Safety arrangements like
provision of First Aid Kit
Box and standby
medicine for workforce
during working period
and emergency.
Provision of PPE
(helmet, boots, globe,
mask and safety belts etc)
Provision of temporary
drinking water and toilets
in the construction
camps.
Maintenance of condition
of vehicles and
equipments.
Contractor/Proponent DoLI/
Consultant
Construction
force and
communicabl
e diseases
Communicabl
e diseases
Impact on
health of
locals and
construction
workers due to
proximity to
infected
person, Sexual
contacts and
proliferation
of HIV/AIDs
and STDs
Regular health check-up
in the construction camp.
Awareness using
pamphlets boards and
browsers.
Encouragement to keep
the camp clean and tidy.
Arrangement of toilet
with water supply 50 m
away from river.
Contractor/Proponent DoLI/
Consultant
Operation of
construction
camp
Conflict
between locals
and outside
workers
Conflict
during work
due to distinct
thought and
cultural
perception;
alcoholism
and gambling.
Informing worker about
general norms and values
of local community;
instructing them to
respect local culture and
tradition with humility.
Job opportunities to local
people will be
maximized.
Contractor/Proponent DoLI/
Consultant
EIA of Sardu Khola Bridge Project DoLI
64
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
Discouraging gambling
and alcoholism.
Formation of Public
Greviance Redress
Mechanism.
Construction
activity, wage
and female
participation
Gender
discrimination
Discriminatio
n in
wage/salary
distribution
Enforcement of non-
discriminatory policy
Positive discrimination,
empowerment and social
mobilization; related
trainings/programs
Contractor/Proponent DoLI/
Consultant
Construction
and child
involvement
Child labour
issue
Use of child
labour force in
risky jobs
Prohibition of use of
child labour in the force.
Agreement with
contractor to avoid use of
children below 18 yrs of
age.
Contractor/Proponent DoLI/
Consultant
Physical Environmental Impacts
Construction
activities
Sedimen load
in river water
Impacts on the
river and its
biota by
increased
turbidity
Proper drainage
arrangement in stockpile
area;
Immediate clearance of
the river path in case of
blockade;
Minimal cut and fill
approach;
Safe pumping out of mud
slurry.
Contractor/Proponent DoLI/
Consultant
Excavation of
foundation,
Storage of
construction
materials
Stock piling,
spoil/waste
disposal,
Transport of
construction
materials
Impact on the
river ecology
by cement,
soil and
excavated
materials on
water and
others
resources
Material will be
stockpiled at fallow land
and will be covered.
Proper drainage will be
arranged around the
stockpile area.
Floodways, natural
drainage paths, water
bodies, farmlands will be
avoided.
Sustainable collection of
river bed materials
whenever required,
Excavated materials will
be used for filling and
river training works.
Contractor/Proponent DoLI/
Consultant
EIA of Sardu Khola Bridge Project DoLI
65
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
Construction
activity
Bank stability Bank
instability and
chances of
bank failure
Due consideration of
existing slope and
minimal excavation
Construction of river
training works with
gabion (150 m u/s and 50
m d/s) to minimize bank
cutting.
Contractor/Proponent DoLI/
Consultant
Construction
work :Air,
Water and
Noise
pollution
Impacts on air
quality due to
operation of
equipments
and vehicles
Introduction
of fugitive and
combustion
emissions,
dust (PM10)
and smoke,
etc. and its
impact on
workers, local
people and
vegetation
Construction equipments
and vehicles will be
regularly examined and
maintained in proper
condition.
Water will be sprinkled
along access road at least
two times a day to reduce
the dust emission.
Proper protection works
like fencing by GCI
sheets or walls will be
done at excavation and
disposal site.
Construction materials
will be properly covered
during conveyance.
Enforcing vehicle speed
limit
Contractor/Proponent DoLI/
Consultant
Impact on
water quality
Mixing of
pollutants like
turbidity, fecal
contamination,
oil and grease
and other
inorganic and
organic wastes
resulting
pollution of
water body.
Disposal of the soil,
sludge and the other
wastes directly into the
water body will be
avoided,
Prohibition of the open
urination and defecation
by workers. Pit toilets
will be provided at the
work sites,
Restriction of the vehicle
washing in the river and
Safe storage and the wise
use of the chemicals.
Impact of
noise from
operation of
equipments
and vehicles
Health of local
people and
worker
Concrete mixer, vibrator,
etc. will be used with
possible sound
minimizing applications.
Sound producing
equipments will be
EIA of Sardu Khola Bridge Project DoLI
66
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
preferred to use only in
day time.
Earplug will be provided
to the worker involved in
equipment operations.
Construction
work and
Solid waste
generation
Impact due to
solid waste
generation
Synthetic
materials,
construction
and domestic
wastes reduce
land and water
quality,
aesthetics
impacting on
human and
environmental
health
Segregation of solid waste
at source;
Composting degradable
waste;
Separate collection and
storage arrangements and
that too far from
waterway;
Selling sellable wastes
like metals, bottles,
drums, etc.
Contractor/Proponent DoLI/
Consultant
Biological Environment Impacts
Construction
work, in
stream
activities
Impact on
Aquatic
ecology due to
sediments
from
excavation and
diversion
Increase
turbidity and
sediment load
causing
pollution and
fish movement
and illigal and
illicit fishing
by workers on
spare time
Due care during
temporary diversion and
chanelling water towards
the diversion;
Diversion channel
assuming natural flow;
Prohibiting construction
crew from illicit fishing
activities through
awareness.
Contractor/Proponent DoLI/
Consultant
Construction
work, vehicle
movement on
wildlife
distribution
Impacts on
rare,
endangered,
threatened and
endemic
species
Hunting and
poaching by
workforce;
road collision
and fatal
injury to
wildlife and
death;
disturbance to
wildlife due to
movement of
vehicles
Prohibiting construction
crew from hunting and
poaching
Enforcing speed limit and
traffic regulation for
transport vehicles
Maximizing numbers of
locals in construction
crew
Putting restriction on
construction workers
from entering into the
local forest areas and
enforcing this provision
as punishable offense
Putting restriction on the
use of wildlife meat in
the construction camps
Contractor/Proponent CCA, Sub-
Metropolitan
EIA of Sardu Khola Bridge Project DoLI
67
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
and treating breaching as
punishable offense
Hoarding board on
importance of wildlife
and conservation.
Chemical Environment Impacts
Use of
chemicals in
construction
works
Impacts of
construction
wastes, oil and
lubricants
spillage
Water
pollution &
impact on
aquatic
animals due to
oil, lubricants,
acids.
suspended and
dissolved
solids, oil &
grease, fuels,
organic wastes
Chemicals, oils and fuels
will be stored in the
impervious floor in such
a way that no leakage or
spillage will occur to
drainage system.
Monitoring and
controlling leakage and
spillage
Contractor/Proponent DoLI/
Consultant
Operation Phase
Socioeconomic and Cultural Environment Impacts
Operation of
bridge and the
approach road
Ribbon
settlement
along the
project
alignment
Development
of Ribbon
settlement and
encroachment
of RoW,
increased
accidents,
delay in traffic
movement
Appropriate planning and
enforcement of law;
Installation of speed
breakers and sign of road
safety.
DCC/ Sub-Mteropolitan
/Wards
CDO/DCC
Use of bridge
and approach
road
Bridge and
road safety
issues
Chances of
road accidents
in the turnings
of the
Bridge/Road
and Loss of
life and
property
Awareness by signboards
and traffic signs at critical
places & bridge sites;
Safety trainings to
drivers;
Adopting 3Es:
Engineering,
Enforcement and
Education.
Local people and drivers DoLI/
Consultant
Physical Environment
Operation of
bridge and
approach road
Bank
instability and
failure and
River shifting
Bank
instability
andcutting;
Foundation
excavation by
changed river
flow; Flood
Bank stabilization using
appropriate structure;
Enforcement of
protective provision
through Bridge User
Committee.
Local people DoLI/
Consultant/
DCC
EIA of Sardu Khola Bridge Project DoLI
68
Activity Issues Related
adverse
Impacts
Mitigation measures Responsible agencies
Executing agencies Monitoring
agencies
and safety of
bridge
River training works
extending to 150 m
upstream along the left
bank of the Sardu Khola.
Operation of
vehicle
Impact due to
Airand Noise
pollution
Dust, smoke,
noise level,
due to vehicle
movement and
problem to
local
community
Frequent maintenance of
road to reduce air
pollution
Local people/Sub-
Mteropolitan/Wards
DoLI/ DCC
EIA of Sardu Khola Bridge Project DoLI
69
CHAPTER 9: ENVIRONMENTAL MANAGEMENT PLAN
9.1 Environmental Management Plan (EMP) and its Objectives
Environmental Management Plan (EMP) has been prepared for Sardu Khola Bridge Project
to set out environmental management requirements and procedures to ensure that all
mitigation measures and monitoring requirements specified in this EIA study report will be
carried out in subsequent stages of project. It identifies and quantifies the impacts to
formulate the mitigation strategies in order to minimize adverse impacts caused by the
implementation of the project. EMP refers to the documentation pertaining to project
management, monitoring, auditing and execution of mitigation measures and also the
verification of the predicted impacts in the project cycle.
The basic objectives of the EMP are to:
Formulate project environmental management requirements to ensure that all the
mitigation measures, monitoring requirements specified in the report will be carried
out during project construction and operation;
Establish the roles and responsibilities of all parties involved in environmental
management; and
Establish a supervision monitoring auditing and reporting framework.
This EMP has elaborated comprehensive environmental management actions that consist
of the descriptive set of mitigation, monitoring, and institutional measures to eliminate
adverse environmental impacts, offset them, or reduce them to acceptable levels. It clearly
identifies the roles and responsibilities of institutions involved, and define the location of
verification of prescribed measures. The measures are described in following sub-headings.
9.2 Statutory Requirement or Legal and Procedural Bases
Several relevant policies, guidelines, acts and rules applicable to construction and operation
of Sardu Khola Bridge are described in chapter 10. This EMP is based on the experiences
of previously constructed bridges of similar nature, and findings of the EIA study. The
major statutory and legislative requirements reviewed are:
Environment Protection Act, 2053 (1997) and Environment Protection Rules, 2054
(1997) with respective amendments
Public Roads Act, 2031 B.S. (1974 A.D.)
Forest Act, 2050 (1993), its amendments (1995) and Forest Rules (1995)
Local Government Operation Act 2074 BS (2017 A.D)
Soil and Watershed Conservation Act, 2039 (1982)
National Parks and Wildlife Conservation Act, 2029 (1973)
Aquatic Animals Protection Act, 2017 (1961) and first amendment, 1998
Labor Act, 2048 (1991)
Water Resources Act, 2049(1992)
Child Labour (Prohibition and Regulation) Act, 2057 (2000)
Environmental Conservation Standards for Construction and Development in Chure
Region, 2072 B.S. (2015 A.D.)
EIA of Sardu Khola Bridge Project DoLI
70
National Forest Policy, 2075 B.S.
9.3 Institutions and their Roles
The proponent of the Sardu Khola Bridge (DoLI) is primarily responsible to execute the
environmental management plan, however, there are different central level, district level
and local level stakeholders those having different levels of responsibilities at various
stages i.e., design, construction, post construction and operation of the project. Different
institutions involved in the EIA and EMP implementation and their roles are described in
the table below:
Table 31: Institutional Roles and Responsibilities
Institution Roles Responsibility on the Project
Ministry of Forest and
Environment (MoFE)
Mandated to formulate and
implement the environmental
policies, plans and
programmes at the national
level
Final approval of the EIA report
as per the provisions of Act and
Rules
Review of project monitoring
reports during construction and
operation phases and give
comments for corrective actions
Auditing of project general
performance during operation
phase
Ministry of Fedral
Affairs and General
Administration
(MoFAGA)
Executive agency and
concerned Agency
Representation in the EIA review
team,
Forward EIA report to MoFE for
approval after necessary review.
Conduct the environmental
monitoring from the central level
Department of the Local
Infrastructure (DoLI)
Responsible to execute
infrastructure projects under
MoFAGA.
Overall coordination and the
supervision of the LRBP in the
center level.
Bridge Section
(BS/DoLI)
Coordinate and monitor
LRBP activities at Center and
the district
Review, comments and forward
the ToR for EIA and Report to the
MoFAGA for necessary action.
Ministry of Physical
Infrastructure and
Development (MoPID)
Province Ministry
Province no.1
Executive agency and
concerned Agency
at Province level
Province no. 1
Conduct the environmental
monitoring from the Province
level
Infrastructure
Development office
(IDO)
Responsible to execute
infrastructure projects under
MoPID at Province level.
Provides back-up support to
the DCCs/municipalities in
the Technical matters
Supports the DCCs/ Sub-
Metropolitan /Municipalities/
Rural Municipalities to implement
the project activities.
Local Roads Bridge
Project Support Unit
(LRBP-SU)
Technical backstopping and
the Management support to
Center/district
Support capacity building of the
district for the implementation of
the rural infrastructure
considering the environmental
safeguard measures and social
development activities
EIA of Sardu Khola Bridge Project DoLI
71
Institution Roles Responsibility on the Project
Contractors Bridge construction work Building bridge and
implementation of contractor’s
part of environmental
responsibility.
President Chure Terai-
Madesh Conservation
Area Development Board
Planning, Policy, Strategy for
the conservation of Chure
region
Control development works
taking place within CCA; Co-
ordinate, supervise and monitor
whethere the work is undertaking
in compliance with the objective
and targets of CCA
The below figure shows the environment management organization structure.
Figure 8: Environment Management Organization Structure
9.4 Environment Management during Construction and Operation
The ultimate responsibility of management of mitigation measures and monitoring rests on
the proponent (LRBP/DoLI). Since, the project is being executed by the proponent through
contractor and the major impacts of the project will result due to construction activities, the
mitigation measures for the impacts due to activities related to construction contractor will
be implemented thorugh the contractor himself by including the provisions in the tender
document.
In order to deal with the environmental impacts, an extensive set of pre, during and post
construction environment management plans have been prepared for different issues related
with the construction and operation of the project based on the Chapter 6 of this report.
GoN, Ministry of Forests
and Environment
GoN, Ministry of Federal Affairs and
General Administration
Climate and Disaster Management Section
President Chure Terai
Madhesh Conservation
Development Committee
DoLI (Monitoring, Environment and
Technology Promotion Sector)
Bridge Section / DoLI
LRBP/LRBSU
MoPID-IDO/
LRBSU- Province office
Contractor Other Stakeholders
DCC Sunsari, Dharan
sub metropolitan City
EIA of Sardu Khola Bridge Project DoLI
72
These plans identify the actions to be taken to address the particular issue. The timing, costs
and responsibilities have been identified in the Environment Mitigation Management Plan.
The monitoing parameters, methods and frequencies as well as the reporting requirement
have been described in subsequent sections.
9.4.1 Spoil Management Plan
Small volume of reusable earthen materials is expected to be generated from foundation
(pier, abutment, wings walls, river training works and other protection structures)
excavation. Significant volumeof spoil thus generated will be used in backfilling in
foundation pits and trenches. The remaining spoil will be used in fill material for approach
road.
Although, limited quantity of material will be used for construction, and all the spoil will
be used up, there may be some environmental implication of temporary storage of these
materials and will be minimized by adopting following measures:
Material will be stockpiled at fallow landon both banks of the river and covered,
Proper drainage will be arranged around the stockpile area,
Floodways, natural drainage paths, water bodies, farmlands will be avoided, and
Spoil generated from excavation of the abutment and foundations will be used for
backfilling behind structure and approach road embankment formation.
9.4.2 Pollution Abatement Plan (Pertaining to Air Quality, Water Quality and Solid
Waste)
During the construction period water quality of Sardu Khola and air quality of the
surrounding area is likely to deteriorate due to project activities. The objective of the
pollution abatement plan is to avoid or minimize the pollution streams (gaseous, liquid,
solid and acoustic) from the project activities during pre-construction, construction and
operation periods of the project. Both preventive and remedial measures will be
implemented by the project. The preventive measure focus on preventing pollution streams
whereas the remedial measures will focus on the measures to minimize the effects of
pollution through end of the pipe treatment technologies.The regular monitoring of the
water and air quality will be part of pollution abatement plan. The following actions have
been defined under this plan.
To maintain thewater quality following measures will be undertaken:
Teporary diversion will be planned and implemented ensuring minium sediment
load and turbidity to river water;
Discourage washing of construction vehicles in river;
Prevent waste, toxic compound and oil reaching water body including collection
and safe storage of spent oil disposal through reuse and incineration;
Garbage and solid wastes generated from construction camps will be dumped safely
away from water bodies;
Awareness program shall be implemented for the project workers to prevent the
water pollution from project related activities; and
EIA of Sardu Khola Bridge Project DoLI
73
Provision of toilets and septic tanks shall be made in all camps. And the toilet will
be constructed at least 50m away from the water course.
Following measures will be undertaken to maintain the air quality of the project area:
Contractor will be encouraged to purchase and use quality fuel from authorized
vendor in their construction vehicles,
Water will be sprinkled along access road, construction site and public areas like
near settlements to reduce the dust emission from construction vehicles,
Construction equipment and vehicles will be regularly examined and maintained in
proper condition,
Proper fencing will be done at excavation and disposal site, and
Construction materials will be properly covered during haulage.
Solid waste management actions include:
Segregation of waste as per their nature,
Cement bags, metal scarps will be collected and will be sold,
Bio-degradable wastes generated from worker’s camp will be safely disposed in
compost pits,
Other non-degradable wastes are crushed and graded to minimize their volume and
will be disposed in the safe places, and
Hazardous waste is not expected however, in any exception they will be
collectedsafely and transported to the hazardous waste treatment centers and the
project will bear cost for it.
9.4.3 Construction and Temporary Facillity Site Rehabilitation Management Plan
It ensures that all disturbed areas due to construction activities are restored. The major areas
affected by construction of project that require rehabilitation are construction yard,
campsites.
a. Construction yard: Rehabilitation of the construction yard requires all stockpiled material
to be removed and cleaned to significantly resembling previous condition.
b. Campsites: Rehabilitation of the camp site requires dismantling, decommissioning and
removal of all the built-up structure including contractor camp and labour camp. Since the
area would generally be compacted, the area will then be ripped and re-top soiled and
handed back to owner in its original form.
9.4.4 Terrestrial Ecology: Habitat Protection, Restoration and Management Plan
The objective of terrestrial ecology management plan is to ensure that the terrestrial
resources such as forests/vegetation, and wildlife of the project site and surroundings will
not face adverse impact due to the project implementation. As repeatedly mentioned, the
project has been proposed amidst flood plain and barren land and does not require felling
of any trees. Moreover, the presence of the bridge will avoid the regular change in route
according to the flow condition and destruction of local landscape. However, realizing the
sensitivity of the Chure Region, extra precautionary measures will be adopted by the
proponent to enhance the local habitat.
EIA of Sardu Khola Bridge Project DoLI
74
The cut-bank will be benched and subjected to bio-engneering operation.
Afforestaion with local tree species will be carried out on both banks.
The project will restore all disturbed area due to project activities.
The contractor will be made contractually responsible for provisioning local
employment, supply of kerosene and LPG at the labor camps, for prohibiting the
use of local NTFP and wildlife within the camp etc.
Local people will be made aware about importance of conservation. This will be
carried out in coordination with CCA.
9.4.5 Aquatic Ecology: Habitat Protection, Restoration and ManagementPlan
Aquatic ecology protection restoration and management plan includes the activities that
seek to protect and restore the aquatic habitat around the project area. These activities will
be carrid out in line with the standard formed by President Chure Terai- Madesh
Conservation Development Board. The actions include, but not limited to the following:
Restrict fishing activities by the construction workforce in the Sardu Khola by any
means
Rehabilitate disturbed stream bed and flood plain due to project activities;
Regular monitoring of aquatic lives especially fisheries and macro-invertebrates;
Identify the potential pollution sources and take actions to remove it
(Implementation of Spoil Disposal Plan and Pollution Abatement Plan); and
River training works.
9.4.6 President Chure-Tarai-Madhesh Conservation Area Impact Minimization and
Co- ordination Plan
CCA impact minimization and coordination plan will contain measures to avoid impact on
biodiversityof CCA and overcome the vulnerability of CCA. It will include the following:
Development and implementation of a worker’s code of conduct prohibiting
hunting, fishing and possession of wildlife for human consumption;
Inter-cooperation among CCA office at district, Wards, DCC and DFO will be
established; and
Environmental education and awareness will be imparted in local communities and
the project personnel in coordination with CCA office.
Afforestaion with local tree species will be carried out on both banks in coordination
with CCA office.
9.4.7 Occupational Health and Safety (OHS) Management Plan
As the construction work is associated with diverse types of risk prone activities. The
workers involved in the construction works are exposed to these occupational risks.
Sickness, injuries, and even fatal accidents cannot be ruled out. The increased traffic of
construction vehicles and associated fugitive dust and noise are yet another source of direct
imperative health effects, even fatal to both the project area people and occupational
workers. OHS measures include:
Restriction in access to construction sites to the public by fencing and using guards;
Provision of warning signs and boards near to the construction site;
EIA of Sardu Khola Bridge Project DoLI
75
Provision of personnel protective equipment such as helmets, boots, gloves, and
mask to construction workers, supervisors, and visitors;
Operation of machinery and other heavy equipment by authorized personnel only;
Provision of emergency equipment such as first-aid kits, flash lights, fire
extinguishers, audible warning devices such as a siren, emergency vehicle, and
phone on site at all times with workers well informed about the proper use of such
equipment; and
Provision of adequate lighting and ventilation at all construction sites and camps.
9.4.8 Construction Camp Management Plan
Hiring local people can avoid the necessicity of camp housing for workers. However, the
required manpower may not be sufficed by the area. Timely construction of the project
requires workers from far have housed in camp in the vicinity of the project area till
construction period.The primary responsibility of the construction camp management lies
with the contractor; however, the specifications for preparation of this plan will be
presented in the construction bid. The following measures adopted for camp management:
Camps will be located in relatively stable geological setting, i.e. away from
potential landslide vulnerable zone and flood prone area.
Fencing and prohibition warning signposts will be installed to keep away non
associated personnel.
Two pit latrines with water supply will be provided sufficiently far from the camp.
The camps will be ventilated and with basic amenities like water, electricity and
cooling (fan/for the area has hot and humid climate).
The camps will have waste segregation arrangements.
Camp will be provided with proper drainage management with catch drains.
The camp will have a common dining facility using alternative fuel like LPG or
Kerosene than fuelwood.
Arrangement will be made for disinfectation of camp premise, waste disposal sites
and toilets.
Camp dwellers will undergo regular health checkups.
9.4.9 Construction Traffic Management Plan
This is prepared to ensure the safe and efficient performance of the road network, to
minimize adverse effects on the existing community arising from construction traffic, and
to provide the community with information about specific management method to be
employed during construction of the project. The construction traffic management plan of
the project includes following actions:
Traffic scheduling so that vehicles are operated normally during day time;
Placement of traffic control diagram in different places around project area;
Parking lots will be alloted away from the nearby water sources and critical areas;
Placement of no-horn zone in sensitive areas especially around schools, health posts
and forest.
EIA of Sardu Khola Bridge Project DoLI
76
9.4.10 Emergency Preparedness and Management Plan
It will include evacuation and rescue plan during disasters, hazards and accidents. The plan
includesfollowing arrangements:
Awareness to the workers relating to activities to be performed during emergency;
Arrangement of first aid facility and emergency medicines;
Standby vehicle for running injured into medical facilities available;
Development and communication of evacuation route and bypass
Development of communication system, alarm and siren;
Designation of rescue team; and
Communication facility will be in place for coordination with the local security
offices.
9.4.11 Permits and Approval Plan
There are a number of legislative provisions which require prior permits and approvals
from the concerned government agencies to commence the works. Besides, some activities
would require general consensus of the project area communities or individuals for smooth
operation of certain activities of construction and operation. In these cases, project
management will obtain prior permits and approvals or consensus of the affected
communities and general public before the start of activities.
Approval of Environmental Impact Assessment from the Ministry of Population
and Environment is due on the proponent,
Likewise, permission and coordination for undertaking mitigative activities for
using public land for site clearance will be acquired from CCA and DCC, and
Approval will be obtained from the DCC for sourcing the riverbased construction
materials.
9.4.12 Public Health and Safety Management Plan
The project development sites are areas of high human concentration. High human
concentration at one location is always associated with high pollution loads to the
environment, particularly sanitary and solid waste. Normally, the project development sites
in the rural areas are thinly populated and the population is not exposed to high pollution
loads of diverse types. This increased pollution, in an infrastructure deficient area to treat
the pollution, becomes the primary cause of public health degradation. Apart from this,
people from different places and with different diseases come in the area as project workers
or economic opportunity seekers. They may also act as carriers of the communicable
diseases which are otherwise alien to the local population of the project area. Moreover,
safety issue of general visitor is of another concern. Following actions will be carried out
under this plan:
Regular health check-up in the construction camp,
Awareness using pamphlets, boards and browsers,
Encouragement to keep the camp clean and tidy,
Arrangement of toilet with water supply,
Disinfectation arrangement,
EIA of Sardu Khola Bridge Project DoLI
77
Restriction of general public into construction area by warning signs and guards,
and
Imformation to local about potentially dangerous areas and activities.
9.4.13 Public Grievance Redress and Management Plan
As the project follows existing road alignment, no disputes related to ownership of property
is expected. However, grievances may arise due to various reasons besides that. A
grievance redress mechanism will be established to allow individual or community to
appeal against any disagreeable decisions, practices and activities; technical and general
project-related disputes. It will consist of four levels of authorities in order of increasing
hierarchy. First one is local level authority consisting of Contractor and Site Representative
of the Proponent; second is the central level authority consisiting of Central Office of the
Proponent. At the third level, Grievance Redress Committee is envisaged consisting
rerpesentatives of local and central level authorities as well as affected person. The last one
is legal redress from the court of law for the grievance that could not be redressed at first
three levels. The site engineer will record the detail of the compalints and its fate.
Rule 45 of the EPR 1997 has given authority to the Chief District Officer (CDO) for
grievance handling and redress. Affected party (AP) has to mention the type of loss suffered
as a result of Sub-project activities and the amount of compensation sought. The CDO will
conduct an investigation into it as well as into the actual situation prevailing at the
concerned place, as required, and also seek the opinion and suggestion from the concerned
officer who would investigate the loss and send the report to CDO within 30 days from the
date of receipt of the application. The CDO will take a decision in respect to payment of
compensation within 15 days from the date of receipt of suggestion from the concerned
officer. The amount of the compensation determined by the CDO under this rule should be
appropriate and reasonable. Rule 46 of EPR states that the proponent shall pay the
compensation amount to the concerned individual or institution within 30 days from the
date of determination of the amount of compensation.
9.4.14 Project Information Management Plan
Proponent’s Engineer at site shall be responsible for maintenance of records and
information received from the contractor and proponent, dissemination of information to
the project stakeholders and co-ordinate with the different line agencies.
9.4.15 Environmental Impacts Mitigation Management Plan
The environmental mitigation measures described in previous Chapter 6 will be
implemented in different phases of proposal implementation. The Impact Mitigation
Management Plan briefly describes impacts, description of mitigation action required,
individual or agency responsible, timing of actions, responsible authority. The following
table summarizes the environmental impacts management plan for the project.
EIA of Sardu Khola Bridge Project DoLI
78
Table 32: Environmental Impacts Mitigation Management Plan.
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
Beneficial Impacts
Construction Phase
Employment
opportunities
Priority to socially
excluded, disadvantaged,
marginalized people and
women
No
additional
cost
Construction
Phase
Contractor/
Proponent
DoLI/LRBSU/
Supervision
Consultant
Enhancement
of technical
skill
On the job training in
construction technique
and river training works
to local laborers
including OHS
NRs
50,000
Once during
construction
DoLI/LRBSU DoLI/LRBSU
Increased
Trade and
Business
opportunities
Priority to local
products, local market
and local contractors
No
additional
cost
Regularly
during
construction
Contractor&
DoLI/LRBSU
DoLI/ LRBSU
Operation Phase
Reduced
traffic
disruption
Regular maintenance of
bridge and approach
road whenever necessary
Budget as
needed
During
operation
DoLI DoLI/LRBSU
Improvement
of
transportation
services
Regular bridge and
approach maintenance
Allocation of budget for
regular inspection and
maintenance of the
bridge.
Budget as
needed
During
operation
DoLI DoLI/LRBSU
Promotion of
agro-
enterprise
No augmentation
measure within the
scope contractor or
proponent
NA Sub-Metropolitan /Wards/NGOs/
CBOs
DoLI/LRBSU
Access over
public
services and
basic utilities
Timely implementation
of the project
Regular maintenance of
the bridge
NA During
Operation
DoLI / LRBSU DoLI/LRBSU
Adverse Impact
Pre-Construction Phase
Physical Environment
Process and
reliability of
detail survey
and design
The bridge design will
follow the standard
methods.
All provision proposed
in the EMP of EIA
document will be
properly reflected in the
design.
No extra
cost
Prior
Construction
LRBSU DoLI/LRBSU
Construction Phase
Socio-Economic and Cultural Environment
EIA of Sardu Khola Bridge Project DoLI
79
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
Impact on the
social
services and
community
infrastructure
Building consensus with
local people for using
community
infrastructures and
resources and provision
of basic utilities within
camp perimeter
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Any damage to existing
road in project location
like formation of ditches
shall be controlled and
rehabilitated.
Budget as
needed
During
construction
Contractor/Propo
nent
DoLI/Consultant
Occupation
Health and
Safety
measures
Provision of First Aid
Kit Box and standby
medicine for workforce
for emergency.
NRs
25,000
During
construction
Contractor
/Proponent
DoLI/Consultant
Provision of PPE
(helmet, boots, globe,
mask and safety belts
etc.)
NRs
75,000
During
construction
Contractor/
Proponent
DoLI/Consultant
Sign and barricading to
restrict public access to
construction site.
NRs
100,000
During
construction
Contractor/
Proponent
DoLI/Consultant
Communicabl
e diseases
Regular health check-up
in the construction camp.
NRs
60,000 for
health
camp
arrangeme
nt
Twice During
construction
Contractor/
Proponent
DoLI/Consultant
Awareness using
pamphlets, boards and
browsers.
Encouragement to keep
the camp clean and tidy.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/Consultant
Arrangement of 2 toilets
with water supply 50 m
away from river.
NRs
50,000
Throughout
construction
Contractor/
Proponent
DoLI/Consultant
Disinfectant will be
sprayed regularly in the
toilets and garbage
collection pits.
NRs 5,000 Throughout
construction
Contractor/
Proponent
DoLI/Consultant
Conflict
between
locals and
outside
workers and
public
grievance
Informing worker about
general norms and
values of local
community; instructing
them to respect local
culture and tradition
with humility; gambling
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/Consultant
EIA of Sardu Khola Bridge Project DoLI
80
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
and alcoholism will be
discouraged.
Job opportunities to
local people will be
maximized.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/Consultant
Grievance Redress
Mechanism will be
formed and locals will
be informed about its
existence and procedure
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/Consultants
Gender
discriminatio
n
Enforcement of non-
discriminatory policy;
Positive discrimination,
empowerment and social
mobilization; related
trainings/programs
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/Consultant
Child labour
issue
Prohibition of use of
child labour in the force
through agreement with
contractor to avoid use
of children below 18 yrs
of age.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Physical Environment
Sediment
load in river
water
Proper drainage
arrangement in stockpile
area
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Balancing cut and fill
approach; Excavated
materials will be used
for filling and river
training works.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Immediate clearance of
the river path in case of
blockade; Pumping out
mud slurry.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Stockpiling,
spoil/waste
disposal,
Transport of
construction
materials
Material will be
stockpiled at fallow land
on the right bank of the
river and will be
covered. Floodways,
natural drainage paths,
water bodies, farmlands
will be avoided.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Proper drainage will be
arranged around the
stockpile area.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
EIA of Sardu Khola Bridge Project DoLI
81
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
Excavated materials will
be used for filling and
river training works.
No extra
cost
Throughout
construction
Contractor/
Proponent
DoLI/ Consultant
Bank stability Due consideration of
existing slope and
minimal excavation
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Construction of river
training works with
gabion (150 m u/s and
50 m d/s) to minimize
bank cutting.
Included in
the design
After bridge
construction
Contractor/Propo
nent
DoLI/Consultant
Impacts on
air quality
due to
operation of
equipments
and vehicles
Construction equipments
and vehicles will be
regularly examined and
maintained in proper
condition.
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Water will be sprinkled
along access road at least
two times a day to
reduce the dust emission.
Included in
the design
During
construction
Contractor/
Proponent
DoLI/Consultant
Construction materials
will be properly covered
during conveyance.
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Enforcing vehicle speed
limit
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Impact on
water quality
Disposal of the soil,
sludge and the other
wastes directly into the
water body will be
avoided
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Prohibition of the open
urination and defecation
by workers.
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Pit toilets will be
provided at the work
sites 50 m away from the
river.
Cost
already
addressed
During
construction
Contractor/
Proponent
DoLI/Consultant
Restriction of the vehicle
washing in the river
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Safe storage and the
wise use of the
chemicals.
No extra
cost
During
construction
Contractor/
Proponent
DoLI/Consultant
Impact of
noise and
vibration
from
operation of
equipments
and vehicles
Concrete mixer, vibrator,
etc. will be used with
possible sound
minimizing applications.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Sound producing
equipments will be
preferred to use only in
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
EIA of Sardu Khola Bridge Project DoLI
82
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
day time and will be
kept at area away from
settlement.
Earplug will be provided
to the worker involved in
equipment operations.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Impact due to
solid waste
generation
Solid waste will be
segregated at source and
managed following 3 R
principle.
NRs 5,000
for waste
collection
and
separation
bins
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Degradable waste will
be disposed in a separate
pit away from the water
bodies.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Sellable wastes like
metals, bottles, drums,
bags, etc will be stored
and sold to vendors.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Biological Environment
Impact on
Aquatic
ecology
Due care during
temporary diversion and
channeling water
towards the diversion;
Diversion channel
assuming natural flow.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Construction crew will
be prohibited from illicit
fishing activities through
awareness
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Waste and spills will be
managed properly
avoiding water bodies.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Impacts on
rare,
endangered,
threatened
and endemic
species
Prohibiting construction
crew from hunting and
poaching; Putting
restriction on
construction workers
from entering into the
local forest areas and
enforcing this provision
as punishable offense;
Putting restriction on the
use of wildlife meat in
the construction camps
and treating breaching as
punishable offense
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/ CCA/
Consultant
EIA of Sardu Khola Bridge Project DoLI
83
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
Enforcing speed limit
and traffic regulation for
transport vehicles
No extra
cost
Construction
period
Contractor/
Proponent
DoLI/Consultant
Maximizing numbers of
locals in construction
crew
No extra
cost
Construction
period
Contractor/
Proponent
DoLI/Consultant
Hoarding board on
importance of wildlife
and conservation and
sensitivity of the area.
NRs
25,000
Construction
period
Contractor/
Proponent
DoLI/Consultant
/CCA
Chemical Environment
Impacts of
construction
wastes
(spillage of
fuels, grease
and other
chemicals
and
consequent
land and
water
pollution)
Chemicals, oils and fuels
will be stored in the
impervious floor in such
a way that no leakage or
spillage will occur to
drainage system.
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Leakage and spillage
will be monitored and
controlled; accidental
spillage will be captured
immediately
No
additional
cost
Throughout
construction
period
Contractor/
Proponent
DoLI/Consultant
Operation Phase
Socio-Economic and Cultural Environment
Ribbon
settlement
along the
project
alignment
Appropriate planning
and enforcement of law;
Installation of sign of
road safety.
Cost under
road safety
Operation
phase
DoLI/DCC/ Sub-
Metropolitan/
Wards
CDO/DCC/ Sub-
Metropolitan/Wards
Bridge and
road safety
issues
Awareness by
Signboards and traffic
signs at critical places &
bridge site
NRs
10,000
Operation
Phase
Contractor/
Proponent
DoLI/Consultant
Adopting 3Es:
Engineering,
Enforcement and
Education. Education
will be imparted to the
local people on bridge
safety issue,
afforestation and
biodiversity
conservation as a whole
NRs.
60,000
Operation
Phase
Contractor/
Proponent
DoLI/Consultant
Physical Environment
Bank
instability
and failure
River training works
extending to 150 m
upstream and 50 m
downstream along the
Cost
addressed
already
Operation
and
maintenance
DoLI/DCC DoLI/Consultant/
DCC
EIA of Sardu Khola Bridge Project DoLI
84
Issues Mitigation/Augmentati
on Measures
Mitigation
Cost
Time &
Duration
Individuals/Age
ncy Responsible
Competent
Authority/ Agency
and River
shifting
both banks of the Sardu
Khola .
Restriction of extraction
of soil and aggregates to
500m upstream and
downstream of the
bridge location;
Enforcement of
protective provision
through Bridge User
Committee.
No
additional
cost
Operation
and
maintenance
DoLI/DCC Sub-
Metropolitan/
Wards
DoLI/DCC Sub-
Metropolitan/Wards
Bioengineering
operation and
afforestation along the
bank with locally
suitable tree species.
NRs
2,50,000
Operation
stage
DoLI/DCC DoLI/DCC
Impact due to
Airand Noise
pollution
Frequent maintenance of
road to reduce air
pollution.
Budget as
per need.
Operation
and
maintenance
DoLI/DCC DoLI/DCC
9.5 Cost of Implementation of Mitigation and Augmentation Measures
The design and cost estimation of various activities of mitigation measure such as slope
stabilization, spoil disposal, supply of the PPE, accidental insurances, river training, bio-
engineering measures etc. shall be incorporated in the design and cost estimates. Therefore,
most of the mitigation measure suggested would be a part of the bridge design and
construction without additional cost. All proposed mitigation measures will be an
integrated part of the project design during construction and operation phases. A total of
NRs 7,65,000 has been allocated for implementation of mitigation and augmentation
measures.
The proponent will cover all the environment management costs in addition to the legal
liabilities of the contractors and its environmental focal person. Similarly the proponent
will cover the cost related to the legal role that the governmental institution will have to
play.
EIA of Sardu Khola Bridge Project DoLI
85
Table 33: Cost for Impact Mitigation and Augmentation
SN Particular Amount (NRs) Remark
1 Job related training including construction
technique, sensitivity of the region and OHS
{Table 35 (1)}
50,000 Two days workshop
2 OHS Measures
I First Aid Kit and Standby Medicine 25,000
II PPE for workers 75,000
III Sign and Barricading of Construction Yard
with Guard
1,00,000
3 Health Camps (2 camps during
construction)
60,000 Two camps with a
general physician and
team
4 Two pit toilets with water supply
arrangements
50,000
5 Waste collection bins 5,000
6 Arrangement for spraying disinfectant 5,000
7 Hoarding board on sensitivity of area and
conservation of wildlife
25,000
8 Traffic awareness and safety signpost 10,000
9 Bioengineering and Plantation along the
Bank
2,50,000
10 Reinstatement of Construction Site 50,000
11 Awareness program on bridge safety and
biodiversity conservation including others.
{Table 35 (2)}
60,000 Two days training to
the local people related
to bridge safety and
biodiversity
conservation, with the
close coordination with
CCA Authority.
Total 7,65,000/-
9.5.1 Tree Plantation Plan (Bio-engineering)
Although the construction of the proposed project does not require tree cutting, tree
plantation is mainly done to minimize river bank cutting and erosion. Tree plantation will
be carried along both banks of the river, outside the river training structures. Altogether
200 saplings will be planted (including both banks) for this purpose. Species recommended
for tree plantation includes Sisso, Simal, Bakaino and Khayer. The detail break down of
tree plantation program is presented in following table:
EIA of Sardu Khola Bridge Project DoLI
86
Table 34: Cost for Bio-engineering
SN Activities Amount
(NRs)
Remarks
1 Plantation of 200 sapling along the bank
including site preparation,
50,000 NRs 250/sapling
2 Replacement of 60 dead saplings at the rate of
NRs 150 per sapling
9,000 Assuming 10%
mortality
3 Bamboo guard around the sapling to prevent
grazing
80,000 NRs 400/guard
4 Benching and landscaping along banks 50,000 sqm
5 Grass and shrub plantation over fresh cut 20,000 Nos.
6 Tools 20,000 LS
7 Trending and maintenance for five years
(personpower)
37,000 LS
Total 2,66,000/-
9.5.2 Cost for Training and Awareness
A sum of NRs 1,10,000 has been allocated to train and aware workers and local people on
different subjects as described below:
Table 35: Cost associated with training and awareness
SN Activities Amount
(NRs)
Remarks
1 Two Days Training to Workers on Following
Subjects:
a) Construction Techniques by supervising
engineer
b) OHS measures by Environmental Officer of
Proponent
c) Sensitivity of Region (Chure) and general
conservation awareness by Environmental
Officer of Proponent
50,000/- Cost includes
remuneration and
logistics for trainers
and lunch for
trainees
2 Awareness and Education to Local People on
following subjects
a) Bridge safety measures by engineer of
proponent
b) Environmental Sensitivity of the region and
biodiversity conservation by CCA
Personnel or Environmental Officer of
Proponent
60,000/- Two days workshop
in close coordination
with CCA Autority;
Cost includes
remuneration and
logistics for trainers
and lunch for
trainees
Total 1,10,000/-
EIA of Sardu Khola Bridge Project DoLI
87
CHAPTER 10: REVIEW OF RELEVANT ACTS, RULES,
REGULATIONS AND GUIDELINES
GoN has adopted various policies, acts, rules, regulations and guidelines to ensure the
integration of the development and conservation of environment. The policies and
legislative provisions of Nepal that have a direct relevance to proposed project are given in
Table 36 below.
Table 36: Review of Relevant Acts, Rules, Regulations and Guidelines
Constitution
Constitution of Nepal The article 30 (1) of constitution has granted
‘every person shall have the right to live in clean
and healthy environment’ as a fundamental right
for the people. The victim shall have the right to
obtain compensation, in accordance with law, for
any injury caused from environmental pollution or
degradation
Article 51 of the constitution mentions about
pursuing policies to develop balanced,
environment friendly, quality and sustainable
physical infrastructures, while according priority
to the regions lagging behind from development
perspective. The article also mentions about
sustainable development
Policies and Plans
Fourteenth Three Year
Plan 2073/74-2075/76 B.S
The plan centers on increasing domestic
production by transforming the agricultural sector
and expanding tourism, industry and small and
medium enterprises. The plan also aims on
developing infrastructure related to energy, road,
air travel and information and communications
besides strengthening the country’s social security
and social protection systems. Besides,
introducing reforms in the economic and social
sectors, ensuring sound and accountable public
finance, delivering quality public services in a
transparent manner and promoting good
governance by protecting and promoting human
rights are other objectives. Focus has also been
laid on cross-cutting issues such as gender
equality, inclusive society, environmental
protection and capacity development of different
institutions.
EIA of Sardu Khola Bridge Project DoLI
88
President Chure-Tarai Madhesh
Conservation Master Plan, 2074
B.S.
The Master Plan has been prepared for 20-year
period. This plan incorporates overall image of the
conservation of chure. It initially analyses the
existing scenario and finally discuss about
management of the Chure-Tarai Madhesh
landscape. Again, the integrated river system
management plan, of the 64 river systems that will
be implemented in the first complementary section
of the plan. Similarly, the district- wise plan of the
36 districts touched by the Chure region habe been
included in its second complimentary section.
National Forest Policy, 2075 B.S. This policy focuses on sustainable management of
forest in Nepal. It emphasizes for green economy,
employment generation, tourism development,
carbon sequestration, biodiversity, conservation
and watershed management, to contribute for
country’s propesrity as national goal. This policy
is related to overall management of forest for
development of user’s group, coopearatives, forest
enterpreneurs, medicinal plants and NTFPs
enterpreneurs. As country is newly structured in
three federal system with three type of
government. This policy also defines roles and
responsibilities and resource mobilization of forest
by three type of governments.
Policy Document, Environmental
Assessment in the Road Sector of
Nepal (2000 A.D)
The Policy Document ensures that development
improves the way of life of the affected people
without damaging the natural surroundings. The
policy document suggested five types of
environmental assessment activities viz.
Screening, Initial Environmental Examination,
Scoping, Environmental Impact Assessment and
Monitoring. Environmental mitigation measures
appropriate to the Nepal Road Sector are outlined
in this document
20 Year Road Plan, 2059 –2079
B.S. (2002-2022 A.D.)
With main objectives of development of Strategic
Road Networks (SRN), the implementation
strategies include all weather road connection to
the District Headquarters (DHQ) and provision of
road linkages from the DHQ to the adjacent road
network of the neighboring districts and countries
Acts and Rules
EIA of Sardu Khola Bridge Project DoLI
89
Environment Protection Act, 2053
BS (1997 A.D)
Any development project, before implementation,
to pass through environmental assessment, which
may be either IEE or an EIA depending upon the
location, type and size of the projects. As per
Article 3 of EPA, 1997, IEE study is prerequisite
for construction of road. Article 4 prohibits
implementing the proposal without getting the
IEE/EIA approved from the concerned authority.
Article 6 deals on the approval procedures. Article
18 has provisions for punishment.
Environment Protection Rules,
2054 BS (1997 A.D) (with
amendments)
Rule 3 schedule 1 lists project that have to conduct
IEE and schedule 2 list projects that has to conduct
EIA before implementation. Rule 5 guides for
preparing ToR and rule 7 guides for preparing
IEE/EIA report. Rule 10, suggests submitting
recommendations received from affected
municipalities/rural municipalities along with the
IEE/EIA report. Rule 13 deals with environmental
monitoring. According to this rule, the concerned
ministry is responsible for such monitoring.
Schedule 3 and 4 are the ToR format for IEE and
EIA respectively. Matters to be covered in IEE and
EIA are given in schedule 5 and 6 respectively.
Forest Act, 2049 BS (1993 A.D) Section 68 of the Act states that “notwithstanding
anything contained in this Act, in case there is no
alternative except to use the forest area for
implementation of the plan of national priority and
if there shall be no significant adverse effect on the
environment while conducting such plan, GoN
may give assent to use any part of the government
managed forests, community forests, leasehold
forests, or religious forests, for the implementation
of such plan”. Further, the sub-section (2) states
for compensatory arrangements if any damage of
the person or community is occurred.
Forest Rules, 2051 BS (1995 A.D) According to Rule 65 (1) of Forest Rules, “if there
is loss of anything of local people during
implementation of the national prioritized plan,
the plan implementer has to pay compensation.”
Rule 65 (2) states that, “the proponent has to pay
all the costs incurred in clearing and managing
trees and bushes.
EIA of Sardu Khola Bridge Project DoLI
90
Local Government Operation Act
2074 BS (2017 A.D)
Para 3 section 11 (2) Subclause 1(chha) and (yna)
has shorted out the rights of municipalities and
rural municipalities in which municipalities and
rural municipalities are responsible for
environment protection at local level.
Para 3 section 11 (4) Subclause 3 (nga) also
mentions about protection of local level forest,
wildlife, birds, water use, environment and
biodiversity.
Similarly, para 3 section 12(2) subclause 1(ga)
mentions about environment friendly
development works.
Soil and Watershed Conservation
Act, 2039 BS (1982 A.D)
Soil and Watershed Conservation Act, 1982 attract
as and when slide or erosion within road is
surfaced up significantly.
Labour Act, 2074 BS (2017 A.D) Where 20 or more employees are engaged,
employer shall constitute a Safety and Health
Committee as per sec 74
Where 10 or more employees are engaged in the
entity, employer shall also constitute the
Collective Bargaining Committee as per sec 116
Sec 80 mentions about provision of controlling
communicable diseases
Sec 82 mentions about occupational health and
treatment
Labour Rules 2075 BS (2018 A.D) Rule 7 is concern with occupational safety and
health policy. Employers are required to maintain
an occupational health and safety policy including
provisions related to arrangements Employee’s
safety and security, Employee’s health, probable
accident in workplace, precautions to be taken
while operating devices and machines in
workplace and precautions to be taken while using
chemical substances.
The Labor Rules has provided the detail safety
measures to be followed by Employer.
Child Labor (Prohibition and
Regulation) Act, 2056 BS (2000
A.D)
As per section 3 of this act, no child having not
attained the age of 14 years shall be engaged in
works as a laborer. However, clause 2 states that it
is prohibited to engage children below 16 years in
works in risk-prone sectors such as public
transportation and construction related works. In
other words, any employment of children below
EIA of Sardu Khola Bridge Project DoLI
91
the age of 16 is to be excluded from becoming
contracted in any of the road and bridge’
construction works.
Solid Waste Management Act,
2068 BS (2011 A.D)
The objectives of the act include maintaining a
clean and healthy environment by minimizing the
adverse effects of solid waste on public health and
the environment. The act mandates local bodies to
take the necessary steps to promote reduce, reuse,
and recycle (3R), including segregation of MSW
at source. It also authorizes the local bodies to
formulate rules, by-laws, and guidelines.
Solid Waste Management Rules
2070 BS (2013 A.D)
Rule 3 mentions about segregation and
management of solid waste, rule 4 about discharge
of solid waste and rule 5 about discharge and
management of harmful and chemical waste
Public Road Act 2031 B.S. (1974
A.D)
The Public Road Act is the governing legislation
for construction and operation of roads in Nepal.
The Act prohibits the construction of permanent
structures (buildings) in a defined distance from
the rural road, i.e., the road agency has the
authority over everything within the right of way.
The act makes provision for cases where road
projects temporarily require land and/or other
properties during construction, rehabilitation and
maintenance. A Compensation Fixation
Committee CFC determines compensation in case
of loss of assets, business or production.
Provisions are also detailed for compensation for
the extraction of construction materials. Article 19
of the Act mandates requirement of permission
from the Department of Roads to carry out
activities within the limits of the road boundaries.
As per Article 29, local governmental offices have
to give notice to the DoR prior to the start of
activities in the limits of the public roads.
Water Resource Act, 2049 B.S.
(1992 A.D)
The Act strives to minimize environmental
damage to water bodies, especially lakes and
rivers through environmental impact assessment
studies.
Under Section 19, it is clearly mentioned that No
one shall pollute water resource by way of using
or putting any litter, industrial wastes, poison,
chemical or toxicant to the effect that the pollution
EIA of Sardu Khola Bridge Project DoLI
92
tolerance limit of the water resource as prescribed
pursuant to Sub-section (1) is exceeded.
सङकाापनन िरजत तथा िनसपमत
अतरामसिर वयपार मनरनतरण ऐन 2073
B.S (2017 A.D)
This Act was enforced for the enactment of
Convention on International Trade in Endangered
Species of Wildlife Fauna and Flora (CITES,
1973) being Nepal a party country of Convention.
This acts states about the regulation and control of
international trade of such endangered flora and
fauna species
Manuals/Guidelines/Directives
BatabaranParichhyan - Resource
Booklet - 2070 B.S. (2013 A.D.)
It provides guidance for local body to prepare
environmental assessment reports of different
projects; construction materials extraction and
local roads, on their own.
Batabaraniya Nirdesika (Nepali),
2057 B.S. (2000 A.D.)
Focuses in the practical implementation of small
rural infrastructures through the minimization of
environmental impacts and outlines simple
methods of environmental management in the
different phases of the project cycle. More
emphasis is given to prevention rather than cure.
Occupational Safety and Health
Guidelines, (DoLIDAR 2017 A.D)
This guideline guides all projects under DoLIDAR
with basic principals for working safely on
construction sites and for ways for Contractors and
managers to manage the safety and health on site.
Environment Friendly Local
Governance Framework (EFLG)
2070 B.S (2013 A.D.)
This framework is prepared to promote
environmental conservation through local
institutions to materialize environment friendly
local development concept. There are different
level of environment friendly indicators like basic,
advanced and special indicators at household,
tole/settlement, ward, VDC, Municipality and
District level. Main objectives of this framework
are (1) Main streaming the environment, climate
change, disaster management issues in local
development planning process; (2) Making
environment friendly local governance
mechanism; (3) Strengthening basic level to make
environment friendly sustainable development;
(4) Promoting coordination and cooperation
within environment and development; and (5)
Strengthening local organization to enhance local
EIA of Sardu Khola Bridge Project DoLI
93
ownership for the sustainable development of
environment.
Environmental and Social
Management Framework (ESMF)
Geo-DoR, GoN (2008 A.D) and
addendum 2013 A.D.
The framework contains public consultation
framework and compendium of environmental
and social impacts with mitigation measures that
needs to be adopted during road design,
construction and operation. Addendum is focused
for bride related cases.
Environmental Management
Guidelines, Geo Environmental
Unit, DoR, (1997 A.D)
This guideline assists to integrate environmental
consideration in each phase of project cycle. The
guideline consists of environmental mitigation
measures to be incorporated into Road projects,
procedures for public participation, and socio-
economic consideration.
National Environmental Impact
Assessment Guidelines 2050 BS
(1993 A.D)
The guideline assists mechanisms for conducting
Environmental Assessment. This guideline guides
in project screening, scoping, identifying project
impacts, adopting mitigation measures,
monitoring, evaluating impacts, community
participation, and report preparation.
Roadside Bio-engineering
Reference Manual, DoR, GoN
(1999 A.D)
This Reference Manual provides a theoretical
concept for the use of vegetation with engineering
structures.
Roadside Bio-engineering Site
Handbook, DoR, GoN (1999 A.D)
This handbook provides information needed to
design, plan, implement and maintain roadside
bio-engineering works. It also covers the
establishment and maintenance of bio-engineering
nurseries.
Roadside Geotechnical Problems:
A Practical Guide to their
Solutions (2007 A.D)
This document provides practical guidance on
how to deal with geotechnical problems that affect
roads. This document guides in problem
identification, site investigation and risk
assessment and possible engineering solutions.
Guidelines on Use of National
Forest Area for Operation of
National Prioritized Project (रामिर
पराथमिकता परापत आरोजनाको लामग रामिर
िन कषतर पररोग गन समबमित कारयमबिी
२०७४ (2017)
The guideline addresses the conditions to make
forest land avail to the loss of forest land use and
forest products. Has provision of compensatory
plantation of 1:25 tree, it also suggests the
mitigation measures to apply for the conservation
of forest.
Environmental Standards
EIA of Sardu Khola Bridge Project DoLI
94
Chure Environmental Standards for
Developmental Activities 2072
B.S.
The sector 2 clause road sub sector 2.4 first clause
Major bridge to be constructed where
Environment Protection Act 2053, and
Environment Protection Rule 2054 would be
followed while conducting EIA.The second
clause states that Environment Social
Management Framework (ESMF), 2000 would be
followed. The third clause states that massive
sediment load that might came from chure region
will be analysed and done on the basis of it while
making structural design. The fourth clause states
that there should not be any extracatation of river
bed materials from direct impacted zone and right
and left (both) sides of the bridge. The fourth
clause states about the screening work to be
carried out on the basis of annex three, placed on
the document of chure standard 2072.
Nepal Bridge Standards 2067 B.S Department of Roads (DOR) has formulated these
standards with a view to establish a common
procedure for design and construction of road
bridges in Nepal. All permanent bridges shall be
designed for a design life of minimum 50 years.
Traffic projections shall be made for a period of
30 years and designed for a desig discharge of 100
yrs return period.
Nepal Vehicle Mass Emission
Standard 2069 BS (2012 A.D)
The emission standard is enforced for vehicles
operated on petrol and diesel as per ignition
engines, type approval and conformity of
production and seat/weight/number of wheels of
vehicles. The proponent using these vehicles
during and after the project should comply the
standards.
National Ambient Air Quality
Standards for Nepal 2060 B.S
(2003 A.D)
The construction and operation of the proposal
should comply limit of the ambient air quality
standards. The construction fugitive and
combustion shall not deteriorate the ambient air
quality following limits on; Total Suspended
Particles (TSP), PM10, Sulphur Dioxide, Nitrogen
Dioxide, Carbon Monoxide, lead, Benzene.
National Drinking Water Quality
Standard of Nepal 2062 BS (2005
A.D)
Drinking water to be provided to the construction
crews should be within the limits of National
Drinking Water Quality Standards.
EIA of Sardu Khola Bridge Project DoLI
95
Noise Level Standard of Nepal
2069 BS (2012 A.D)
Government of Nepal has formulated noise level
standard for different area for day and night time.
Project Activities should be within the prescribed
limit of noise level. No equipment or activities
exceeding limit is allowed.
National Diesel Generator
Emission Standard 2069 BS (2012
A.D)
The GoN has introduced the National Diesel
Generator Emission Standard (NDGES) for new
and in-use diesel generators with a capacity of 8
kW-560 kW. The emissions limits are set for four
major pollutants: CO, HC, NOx, and PM.
Generators used for the project should comply
with the emissions limit.
International Conventions and Treaties
Convention on Biological
Diversity, 2049 BS (1992 A.D)
The objectives of this Convention, to be pursued
in accordance with its relevant provisions, are the
conservation of biological diversity, the
sustainable use of its components and the fair and
equitable sharing of the benefits arising out of the
utilization of genetic resources, including by
appropriate access to genetic resources and by
appropriate transfer of relevant technologies,
considering all rights over those resources and to
technologies, and by appropriate funding.
Convention on International Trade
in Endangered Species of Wild
Fauna and Flora (CITES), 2053
BS, amended, 2059 BS (1973 A.D,
amended 1979 AD)
The convention classifies species according to
criteria where access or control is important (e.g.
I-species threatened with extinction; II-species
which could become endangered; III-species that
are protected; E-Endangered; V-Vulnerable, R–
Rare (CITES, 1983). The project will have to
minimize impacts to the CITES species as far as
possible.
SIACM Conventation (2006) A.D. The achievement of the sound management of
chemicals throughout their life cycyle so that the
chemicals used in ways that minimize significant
adverse impacts on the environment and human
health as appropriate, by stakeholders, according
to their applicability.
EIA of Sardu Khola Bridge Project DoLI
96
CHAPTER 11: ENVIRONMENTAL MONITORING
Environmental monitoring is an integral part of the Environmental Management Plan.
Environmental monitoring process generates meaningful information and improves the
implementation of mitigation measures. Besides this, it also provides early warning for
significant environmental damages so that additional actions may be taken. The aims of
Environmental Monitoring Plan are:
To ensure that project baseline conditions were adequately documented; so that a
comparative assessment of the project baseline before and after the project could be
made objectively for impact evaluation,
To ensure that the mitigation commitments to minimize the predicted adverse
impacts and maximize the beneficial impacts including the environmental
enhancement programmes were actually complied and implemented sincerely in
time by the project and,
To verify that the project impacts were either within the limits of the environmental
impact prediction or some unforeseen impacts also occurred during project
development and what measures were taken to minimize the unforeseen impacts.
As per EPR 1997, project proponent should be responsible for monitoring. The information
obtained from these activities shall be presented on regular basis and made available to all
the concerned agencies. The project proponent shall appoint a team of monitoring experts
and mitigation officer. The project proponent shall be primarily responsible for all the
proposed environmental monitoring plans with proper consultation and involvement of
local people in the process. However, the agencies like MoFE, MoFAGA, and other
relevant agencies like President Chure Terai- Madesh Conservation Development Board
shall be consulted during monitoring.
11.1 Matter to be monitored while implementing the Proposal
Monitoring of the implementation of environmental protection measures provides a basis
for logical comparison for the predicted and actual impacts of a proposal. Environmental
monitoring will involve the systematic collection of data to determine the actual
environmental impacts of the sub-project, compliance of the sub-project with regulatory
standards, and the degree of implementation and effectiveness of the environmental
protection. Monitoring will be an integral part of the implementation of the mitigation
measures during project construction, and will generate important information. It will
improve the quality of sub-project implementation. The EIA Guidelines (1990) and EPR
(1997) also require monitoring plans and indicators, schedules and responsibilities be
identified in the EIA report. The National EIA Guidelines for the Forestry sector, 1995 has
proposed three stages of the monitoring i.e. baseline monitoring, compliance monitoring
and impact monitoring.
EIA of Sardu Khola Bridge Project DoLI
97
11.1.1 Baseline Monitoring
Baseline monitoring aims to determine the baseline condition of the environmental
resources. It is carried out if significant time elapse between preparation of the EIA report
and the construction stage or change in the environmental quality is noticeable. This project
will proceed for the immediate construction after the approval of this EIA report and hence
baseline monitoring is not necessary.
11.1.2 Compliance Monitoring
Compliance monitoring is essential in order to ensure that environmental protection
measures recommended by this study and other requirements set forth during the approval
of the sub-project are complied with. This monitoring is not concerned with determining
the actual effect of the project activities on the environment.
The proponent will ensure compliance of activities such as; inclusion of mitigation
measures in the design and tender documents, budget allocation for mitigation measures
and monitoring, compensation arrangements and other compliances spoil disposal, storage
sites, arrangement of construction activities etc.
11.1.3 Impact Monitoring
This monitoring detects environmental changes and estimates inherent variation within the
environment, establishes long term trends in the natural system, and derives conclusion by
making comparison against standard or targets.
Impact monitoring is generally carried out to access the effectiveness of the environmental
mitigation measures and provides the actual level of the impact in the field. Hence, an
impact monitoring evaluation study is proposed by the end of project construction phase or
within 2 years of the project implementation. Impact monitoring will focus on each
predicted impact and effectiveness of environmental protection measures.
11.2 Monitoring Indicators
Monitoring will be carried out in a transparent and credible manner by using established
indicators. To ensure that the monitored parameters are replicable, i.e. they do not depend
on the person or specific methodology used, the selected indicators are easy to be verified
and controlled by the agencies where the final monitoring and supervision responsibility
remains.
Use of standard checklists and formats is sought to be used by the monitoring staff both for
site surveys and in the subsequent reports. Much of the monitoring is related to quantifying
the observed impacts, and to verify the nature and extent of impacts, photographs,
parameter tests, collect local accounts of stakeholders and technical experts. The
monitoring will also include specific cause-effect analyses for the impacts observed.
Following Table 37 specifies the set of verifiable indicators that will be used for
monitoring.
EIA of Sardu Khola Bridge Project DoLI
98
Table 37: Parameters selected for monitoring
Monitor sector Parameter selected for the monitoring
Flooding, Bank Cutting,
Sedimentation,
Waste Management
Sites
No., location and the extent of the bank failure
Cause analysis for such failure, nature and man-made
Area (ha) of the land, forest and the properties affected
No. and the extent of gully erosions and the pavement failure,
Sites and the suitability of the safe disposal of garbage and
wastes.
Bioengineering/river training Nos and types of structures constructed for river training, their
suitability for the proposed project,
No. of plants species selected for the bio-engineering,
disaggregated by the protective function,
Effectiveness of river training works.
Seismicity Nos and magnitude of local seismic activities and respective
damage to structures.
Water pollution, water
resources and their uses,
surface water, Irrigation
water & Drinking water
No. and extent of the water logging at oppressive and /or
decommissioned construction site,
Incidents and trends in development of waterborne diseases,
Nos of days and nature of traffic delays due to water logging and
inundation,
Blockage of waterways-extent and secondary impacts,
Water pollution incidents due to unsafe disposal of waste and
spoil, analyzing effects on local fisheries,
Observations on car washing practices in rivers, and analysis
ofpotential environmental effects.
Air and noise level in relation
to the traffic volume
End of pipe measurement of vehicle exhaust,
Point measurement of noise near the construction site,
Qualitative analysis of wind borne dust particles during the
construction stage of the project,
Qualitative assessment of vibrations sensed around the nearby
households of the project construction site,
Traffic volume count.
Bridge and Road Safety Speed measurement at both sides of the bridge
Nos and type of accidents recorded by the Traffic Police Office
and local health service centres that occurred around the bridge
Effectiveness of safety signs
Aquatic Ecology Use of fish diet in camp and identificiation of their source,
Practice of disposal of solid and liquid waste,
Change in local catch of fish.
Wildlife habitat disturbance
and impacts on forest
resources and its mitigation
Nos and extent of accidents inflicting wildlife,
CCA records on illegal medicinal plant, wildlife exploitation and
trade,
Nos, extents and causes of forest fires,
Observations and handling of invasive species,
Success/failure/effectiveness of roadside plantation.
Socio-economic development
in road alignment
Demographic, economic and education data,
No. and the extent of new settlements/types and ethnic groups,
No. and extent of new business,
No. and extent of new service and utilities,
No. of employment opportunities created,
No. of workers received training on the enhancement of technical
skill including women,
Change in transportation cost and time,
EIA of Sardu Khola Bridge Project DoLI
99
Number and type of the enterprises, cottage industries established,
Change in the status of basic services and utilities in ZoI for
access to services,
Rate of the involvement of female populace in activities other
than households and agricultures,
Condition of affected infrastructures,
Occupation health and safety measures provided to workers,
Increase in the number of people receiving social services
facilities (schools and health post),
No. accidents related to bridge structure and approach road,
State of accidents related to bridge structures and approach road
State of settlement condition (no. of houses, shops, sanitation
condition),
Number and status of porter’s livelihood,
Wage of women,
No. of Children below 18 years of age in workforce.
As baseline environment of the project area is grossly known and also documented in this
EIA report, the DoLI/LRBP together with district bodies will carry out compliance and
impact monitoring of the project construction and operation period. The monitoring
management plan for compliance and impact monitoring presented in Table 38 and Table
39 respectively.
Table 38 identifies the specific compliance monitoring activities. Phase-
wise/chronological details are provided for the methods, schedules, responsible
implementing agency and the responsible monitoring agency. The compliance monitoring
refers primarily to the pre- construction and the construction stage of the project. Table 39
shows the impact and the effect of monitoring activities envisaged as in the previous table
and provide the applied methods, location and schedule along with responsible
implementing & monitoring agencies.
EIA of Sardu Khola Bridge Project DoLI
100
Table 38: Compliance Monitoring for Sardu Khola Bridge Project
Parameters/Issues
Responsible
Implementing
Agency
Verifiable
Indicators
Verification
Methods
Schedule
Responsible
Monitoring
Agency
Final Site and alignment
selection as per EIA /EMP
recommendation
Consultant Incorporation of EIA/ EMP
recommendations into Site and alignment
selection process and design document
Walkthrough along final Bridge site and
approach road alignment, verifying
sensitive areas
Initial stage of
surveying
Proponent
Public land acquisition Proponent Cadastral records, Recommendation from
President Chure Terai-madhesh
Conservation Development- Committee,
ward offices for use of public land
Consultation and observation of
recommendation letters
Initial stage of
surveying and
alignment selection
CCA / PCU /
DoLI/ MoFAGA
Site selection and preparation of
construction logistics
Contractors Project’s arrangement for materials
storage, and construction activities
Site observation, geo-referencing and
photographic documentation
Beginning of
construction period
Proponent/
Consultants
Use of local labour, particularly
vulnerable groups and women
Contractors Specifications which obligate the
contractors to observe certain quotas for
employing local labour, specially
vulnerable groups and women, use of
child labour
Records that facilitates and coordinates
the process for local people’s
employment, interviews
During the entire
period where labour
work is contracted
Proponent
Awareness and on-the-job
training on bridge / approach
road construction to
technicians, and locally
employed labourers
Contractors Training programmes for skill
development, occupational safety and
environmental protection associated with
bridge and road construction works
Specifications; Training records, check
training programme reports, assess
feedback from participants
Beginning of
construction and
during construction
Proponent/
Consultants
Compliance to Occupational
health and safety matters
Contractor
Health and safety regulations, first aid and
medical arrangements, contingency plan,
number and type of safety equipments
such as mask, helmet, glove, safety belt
Spot checks at work sites, photos, accident
records, interviews
Monthly throughout
construction activities
Proponent/
Consultants
Compliance to Environmental
Protection Measures, including
pollution prevention, water and
soil management, slope
stabilisation, cut and fill, waste
management, spoils, sensitive
habitats and critical sites,
protection of fauna and flora
Contractor
Arrangement specified in the Code of
Practice and in Manuals relating to
environmental protection; records and
observations on pollution, waste
management, spoil deposit.
Site inspection, discussion with Project
management, consultants, and local
people. Quantifying site-specific impacts,
photos, laboratory tests where required.
Existing patrol, control and enforcement
mechanisms, enforcement records, Air
and noise quality measurement water
quality test
Before and during
construction period
Proponent/
Consultants/FUGs/
CCA
Site clearance Contractor Amount of vegetation removed during
construction works
Record, inspection and interview with
local people and CFUGs
After detail design and
before construction
work
CFUGs /
DFO/CCA
Proponent
Measures to avoid pressure on
forest and wildlife
Contractor Use of firewood or fossil fuel by
construction crew, events of hunting and
killing of wildlife/fishes
Inspection, interview with local people
and CFUGs
Once a month during
construction
CFUGs /
Proponent/
Consultants
Measures to protect
environment from air & noise
pollution
Contractor Measurement of vehcle exhausht
Dust level and noise level at work sites,
major settlements and sensitive spots like
health centres and schools
Testing, Observation of good construction
practices anddiscussion with residents
andworkers
Once in a month
during construction
Proponent
/Consultants
Measures to protect water
bodies from pollution
Contractor Visual observation, observation of open
defecation and waste disposal around
water sources near construction sites ;
Parameters like pH, hardness, DO etc.
Site inspection, test of site-selected
samples of water at laboratory
Once in a six months
during construction;
Upon demand for
testing with field kit
Proponent
/Consultants
Restoration, rehabilitation,
reconstruction of all
infrastructure services disrupted
or damaged by the proposal
activities
Contractor Continued services by the facilities and
functional public life
Site observation; Wards/DCC records;
Public Consultation Meetings; Photos
Once in a month
during construction
Proponent
/Consultants
Adequate technical and
environmental supervision
Consultant Adequate number of technicians regularly
at site
Check number and type of technicians
available at site;
Skill of work carried out;
Discussion
Twice a month during
construction
Proponent
Clean up and reinstatement of
the construction sites (camps,
stockpiling yard)
Contractor Decommissioned sites indicate no
adverse/residual environmental impacts,
and are rehabilitated to the satisfaction of
the supervisor and land owners
Site observation; Comparing photos;
Consultation with land owners and CBOs
At end of construction
period
Proponent
/Consultants
EIA of Sardu Khola Bridge Project DoLI
101
Table 39: Impact / Effect Monitoring for the Sardu Khola Bridge Project
Parameters
/Issues
Verifiable
Indicators VerificationMethods Location Schedule
Responsible
Monitoring Agency
Bank /Slope
stability and
erosion
Inclination,
Bank/ slope
failures, causes;
Drainage
facilities such as
catch drain, side
drains and
functionality of
cross drainage
structures; Fresh
gullies and
erosion;
Success/failure
of bio-
engineering/river
training
solutions
Site observation,
photos
Discussion with
technicians
Near steep
slopes and at
river bank
cutting areas
Continuously
during
construction
and
operation
Proponent/
Consultants
Disposal of
Spoils and
construction
wastes
Affected
aesthetic value,
affected forest
and agriculture,
initiated land
erosion by local
blocked
drainage, hazard
to downstream
slope residents
and agricultural
lands
Site observation and
interviews, photos,
geo-referencing sites
At specific
locations
where such
sites occur
During
construction
Proponent/Consultants
Disruption of
drainage system
Status of
rehabilitation
Service status of
irrigation and
water supply
system;
Operation and
maintenance
requirement
Observation and
interviews, photos,
fisheries data,
wildlife records;
Records of Sunsari-
Morang Irrigation
Office
Disrupted
aquatic
system,
irrigation
schemes
During
construction
Proponent/Consultants
Loss or
degradation of
farmland ,
community
forest area
Status of road
side land;
Production /
yield;
Observation, data
collection and
analysis and
interview with
stakeholders
Road side
land and
houses
During
construction
Proponent/Consultants
EIA of Sardu Khola Bridge Project DoLI
102
Parameters
/Issues
Verifiable
Indicators VerificationMethods Location Schedule
Responsible
Monitoring Agency
Status of road
side houses;
Status of
standing crop
along alignment
Water quality observation of
open defecation
and waste
disposal around
water sources
near
construction
sites ;
Parameters like
pH, hardness,
DO etc.
Visual observation,
water sample test
River water
Drinking
water at
Camps
During
construction;
Upon
demand for
testing
Proponent/Consultants
Air quality Dust level in
ambient air
Test by portable Air
Sampler.
At
construction
sites and at
sensitive spots
(schools,
health spots,
major
settlements)
During
construction
Proponent/Consultants
Forest and
vegetation
Numbers of
trees, presence
of ground
vegetation, signs
of illicit logging
and extraction of
NTFPs
Observations, photos;
interview with
CFUGs members
In and around
the
construction
sites, firewood
use in local
restaurants
During
construction
and
operation
CFUGs during
construction;
Wildlife/Aquatic
Life
Wildlife hunting
trapping and
poaching by
work force, trade
of wildlife,
biological
survey on
selected biota,
road accidents
inflicting
wildlife
Interview with local
people / CFUGs/
photos,
observations
Forest areas at
roadside/River
Twice a year
during
construction
and routine
during
operation
Proponent
CFUGs/Consultants
Change in
economy
Numbers of
people employed
Records kept by the
Project management,
Project Area Trimester
during
Proponent/Consultants
EIA of Sardu Khola Bridge Project DoLI
103
Parameters
/Issues
Verifiable
Indicators VerificationMethods Location Schedule
Responsible
Monitoring Agency
by the Project
during
construction
Numbers of
women in work
forces
discussion with
stakeholders
construction
phase
Trade and
commerce
Numbers of
shops increased
or decreased,
rental of houses
and land spaces
Records, interviews,
observations, photos
Project Area Throughout
Project, once
in a year
Proponent/Consultants
Cottage
industries
Establishment of
industries in the
vicinity of
Project Area
Records and
interviews, photos
Project Area/
zone of
influence
Throughout
Project
Proponent/Consultants
Occupational
safety and
hazard
Type and
number of
accident
occurred during
construction;
Adequacy of
occupational
safety measured
provided;
Compensation
provided in case
of fatal accidents
or invalidity
Observations, photos,
spot checks,
contractors’ and
health centre records
interview with
labourers
Project Camps During
construction
Proponent/Consultants
Change in socio-
economic
structure
No and extent
of new
settlements /
types and ethnic
groups; Nos and
extent of new
businesses; Nos
and extent of
new services
and utilities,
social conflicts
Observations,
interview with local
people, DCC, Police
and Wards records
Project Area During
construction
Proponent/Consultants
Ribbon
settlement
Congestions to
road users
Nos. of
accidents, RoW
encroachment
Records, observations Project Area During
construction
Proponent/Consultants
EIA of Sardu Khola Bridge Project DoLI
104
11.3 Record Keeping, Reporting and Corrective Actions
EPR 1997 entitles the monitoring responsibilities to the proponent. The proponent will
develop in-built monitoring mechanism to show its additional commitment for
environmental improvement and mitigate undesirable changes, if any during construction
and operation stage. During construction, District Implementation Team in district and
Environmental specialist for LRBSU will conduct environmental monitoring with the
support of DoLI. Beside this, it is recommended that an external team hired by DoLI will
take the responsibility for the monitoring. At least one monitoring in each construction
season is necessary. Trimester EMP compliance report will be prepared and submitted to
the DoLI by the monitoring consultant.
To demonstrate compliance with the environmental management, the proponent will
instruct the contractors through engineer to maintain daily records of mitigation
implementation works in retrievable forms at its office during the construction phase.
Contractors will keep records of the employment of the local people, and will submit those
records to the engineers every three month. Similarly, records of occupational safety and
health will also be documented in retrievable forms and submitted to engineer in every
three month. Besides, records of instructions, trainings and land area rented with
agreements will also be submitted to the engineers regularly or when it is demanded by the
engineer.
Contract document will categorically include provision of the environmental protection,
health and safety, waste management and other environmental mitigation measures
identified during the EIA study. It will spell out clearly the measures that will be taken in
case on non compliance. This will make them comply with the provisions.
The monthly reports will be based on recurrent site inspections and will report on the
effectiveness of the mitigation measures;
The Contractor's compliance with the environmental specifications;
Measures recommended in the events of non-compliance and
Recommendations for any other remedial actions, etc
In the operation phase, DoLI/LRBP will keep records of the mitigation and monitoring as
required in the retrievable forms. Central level monitoring will be conducted once by the
MoFE as suggested by the EPR 1997.
11.4 Costs of Environmental Monitoring
The cost of environmental monitoring of Sardu River Bridge Project has been itemized in
Table 40.
Table 40: Estimated Cost for Environmental Monitoring
Description Duration Rate NRs. Amount (NRs.)
Environmental Specialist 1 80,000 80,000
Engineer 0.5 60,000 30,000
Socio-economist 0.5 60,000 30,000
EIA of Sardu Khola Bridge Project DoLI
105
District Focal Person 0.5 40,000 20,000
Support staff 1 25,000 25,000
Transportation costs LS 60,000
Report preparation LS 15,000
Laboratory and Equipments LS 25, 000
Sub-total 2,85,000
Central level monitoring (monitoring by MoFE)
Monitoring cost 50,000
Total 3,35,000
11.5 Environmental Auditing
Environmental Audit enables us to check back and examine how well the environmental
instruments have worked and enabled to assess the actual environmental impacts, accuracy
of prediction, effectiveness of environmental mitigation measures adopted and functioning
of monitoring mechanism. EPR 1997 suggests conduction of environmental examination
by MoFE after two (2) years of commencement of the project.
11.5.1 Agencies Responsible for Examination
On behalf of Government of Nepal, MoPE is responsible for Examination of the projects.
The Audit will be carried out as specified as in National EIA Guideline (1993). This
guideline specifies that the result obtained from EIA should be made available to the
project proponent and concerned agencies.
11.5.2 Elements to Environmental Examination/Audit report
Main elements in the audit report include:
Predicted impacts in EIA report for defined activities in the project development
Mitigation measures in EIA report to minimize impacts of the defined activities in
the project cycle
Implementation status of the mitigation measures in the project as per EMP
Effectiveness of the employed mitigation measures to minimize the impact of the
defined activities
Any residual impact due to construction activities
Any corrective actions suggested or undertaken to mitigate the impacts of the
defined activities
Compliance or non-compliance with EMP
Compliance of EMP with the national environmental standards
Experience gained to strengthen impact prediction in future project for the defined
activities
Environmental Impact Audit of the project is performed after two years following its
operation and its facilities to assess the actual environmental and health impacts, the
accuracy of predictions, and the effectiveness of mitigation measures and the functioning
of monitoring mechanisms. The framework for Environmental auditing of this project is
presented in the Table 41:
EIA of Sardu Khola Bridge Project DoLI
106
Table 41: Environmental Auditing Framework for Sardu Khola Bridge Project
Parameters Indicators Location Methods Sources
Physical Environment
i. Air Quality
Quality of Air TSP, PM10,
PM2.5, SOx,
NOx, dust
accumulation
from
construction
activities in
houses,
vegetation,
surrounding
areas
Around the
bridge and
along the road
access
Low-volume sampler,
visual inspection,
measurement, and
their comparison with
ambient standards
Analysis of
data,
information for
local people,
observation
ii. Noise and Vibrations
Noise Noise levels
and their
comparison
with ambient
standards
Around the
bridge and
along the road
access
Decibel meter Measurement
and
information
from local
people
Vibration of
Structures
Any case of
hearing
impairment
Cracks existed
in houses, and
compensation
Construction
sites,
locations of
cracked
buildings
Interview, observation Local people,
observation
iii. Water Quality
Water Quality Temperature,
pH, turbidity
TSS, TDS,
sodium
chloride, oil
and grease
Sardu River
stream-flow
below bridge
site
Water samples
collection and testing
Analytical data
iv. Disposal of Spoils and Construction Wastes
Disposal for
construction
spoils
Initiated
erosion
Affected the
aesthetic value
Designated
sites
Observation/interview Local people
and
observation
v. Bank Cutting and Stability
Bank stability Cut and
unstable areas
on natural
slopes,
collected data
Abutments,
its u/s and d/s
for 150 m
Observation,
measurement
Local
information
photographs,
observation
EIA of Sardu Khola Bridge Project DoLI
107
Plantation and
bioengineering
along the bank
Afforestation
of the bank and
conditions of
bank revetment
structures
150 m u/s and
50 d/s of
bridge site
along the
bank
Visual observation,
photographs
Local
information,
observation
Biological Environment
i. Forest and vegetation
Loss of Trees
from nearby
forest
Volume of fuel
wood trade,
location of
timber depots
and firewood
sale in the
project
construction
area
Project site,
checkpoints
and
settlement
areas
Records, observation Local people,
available
information,
observation,
CCA
Number of
stumps of cut
trees in nearby
forest
Forest area
nearby
Examination of forest Local people,
observation
Alternative
energy for
cooking for
labour force
Volume and
type of fuel
used in the
project area
Project sites Record from the
contractors
Local people.
observation
Harvesting and
trade of medical
plants
Sales of
medical herbs
increased
Project site
and the
market
Information from the
local people and
market
Local people
Physical
condition of the
forest
General
condition of
forest nearby
Forest near
project site
Observation Information
available from
local people,
CCA
ii. Wildlife
Wildlife Wildlife
hunting,
trapping and
poaching by
workforce
Forest area
near the
project site
Interview with local
people and
photographs
Local people,
observation,
CCA
Trading of
wildlife
products(dried
meats, hides,
furs)
Project sites
and market
Observation,
interview and
photographs
Local people,
observation,
CCA
Frequency of
the birds and
mammals seen
in the projects
sites before
Project area Observation,
interview
Local people,
CCA
EIA of Sardu Khola Bridge Project DoLI
108
and after the
project
Socio-economic and Cultural Environment
i. Employment Opportunity
Employment
Opportunity
Number of
local laborers
employed in
the Project
Construction
Project site Analysis of records,
interview
Records from
contractor and
local people
Number of
women in
workforce
Project sites Records Local people
records of
contractor
Use of children Project site Records Records, local
people
ii. Trade, Commerce and Industry
Trade,
Commerce and
Industry
Number of
business
enterprise in
the vicinity of
project area
Project area
and the
surroundings
Records, interview Records and
local people
Rentals of
houses and
land space,
before, during
and after the
project
Local area Inquiries, interview Local tenants
and local
people
iii. Occupational and safety Hazard
Occupational and
Safety Hazard
Types and
numbers of
accidents
occurred
during
construction
Project sites Records, interview Records from
contractors and
local people
Adequacy of
occupational
safety
measures
provided by
the project
Project sites Records, interview Records from
contractors and
local people
Facility of first
aid emergency
services
provided
Project sites Records, interview Records of
office and local
people
Compensation
to the loss of
life or
disability
Project sites Records, interview Records of
contractor,
office of
project
EIA of Sardu Khola Bridge Project DoLI
109
management
and local
people
v. Public Health
Public Health Cases of
communicable
diseases as
compared to
the number
and types of
disease, which
existed before
the project.
Project site,
health posts
and hospitals
Records, interview Medical
records from
local health
post/hospital,
interview
vi. Undesirable Activities (Social Problems/Crimes)
Alcohol and
Drug Abuse
Liquor
production and
consumption
and
comparison
with levels
before the
project
Project site Survey, in-depth
interview
Local people,
observation
Law and Order Level of
disputes and
crimes
Project site Survey, interview Local people,
police, project
management
office
Clean-up Temporary
workforce sites
cleaned and
restored to
original
condition
Project area Visual inspection,
interview with
relevant people
Contractors,
local people
observation
vii. Damages and Complaints
Damage and
Compensation
Type of
damages made
on personal
properties
Project site
and its
vicinities
Survey, interview,
observation
Observation,
records
Damage to
local
infrastructure
such as roads,
bridges,
culverts, etc
Within the
periphery of
project area
Survey, interview,
observation
Concerned
agencies, local
people
Compensation
for
maintenance
and
Project area Interview, records Concerned
agencies,
project
management
EIA of Sardu Khola Bridge Project DoLI
110
rehabilitation
of
infrastructure
and local
people
Losses caused
by vibration
and noise and
compensation
paid
Project area
and its
vicinity
Record, interview Local people
and project
management
viii. Coordination and Communication
Coordination and
Communication
Coordination
among district
administration,
CCA,
Municipality,
Wards,
politicians,
project
management,
contractors,
laborers and
local people
Office of
Authorities,
District
headquarters
and project
site
Record and interview Office of
Authorities,
project
management,
local people,
Sub-
Metropolitan/
Ward officials,
local leaders,
contractors and
labour
representatives
Information
dissemination
to workers and
local people
about the
project
Project site
and vicinity
Mass meetings, public
notices
Local people,
project staff
and laborers
ix. Economic Condition
Socio-Economic
Changes
Change in
local economy
(standards of
living)
Project area /
Sub-
Metropolitan
/Wards
Interview, survey,
observation
Local people,
business
community,
observation
Price Rise Rise in the
price in
essential
commodities
as compared to
the price of
these goods
before
construction
and adjusted
for inflation
Local Market Market survey Local people,
shop keepers
EIA of Sardu Khola Bridge Project DoLI
111
CHAPTER 12: PARTICULAR OF THE COST AND
RETURNS OF THE PROPOSAL
Measurement of the actual benefit of the proposed project on environmental and social
domain in monetary term is difficult and beyond the scope of this level of project and study.
However, a summary of cost assessment has been made in different terms in this section.
12.1 Summary of Cost
The total environmental and social costs are summarized in Table 42. Total environmental
cost includes the cost of implementation of mitigation measures and the cost of monitoring.
Table 42: Environmental Management Cost
S.N. Measures/Activities Costs NRs. Remarks
1 Mitigation Cost 7,65,000/-
2 Environmental monitoring including central level monitoring 335,000/-
Total 11,00,000/-
12.2 Comparision of Costs
Since, it is difficult to estimate the return o the project in monetary terms, comparasion has
been made with the total project cost only. The comparison is presented in the Table 43.
Table 43: Cost and Returns of the Proposal
S.N. Measures/Activities Costs NRs. Remarks
1 Mitigation Cost and Enhancement Cost 765,000
2 Environmental monitoring including central level monitoring 335,000
3 Total Enviornmetal Cost 11,00,000
4 Total Project Cost 13,98,20,483.33
5 Percentage of Total Environmental Cost to the Total Project
Cost
0.78%
EIA of Sardu Khola Bridge Project DoLI
112
CHAPTER 13: CONCLUSION
The proposed Sardu Khola Bridge is essential for the development of rural road network to
enhance the connectivity of people living in the region. After the completion of the project,
access to the social services will be easier for people of the remote areas of this region
alongside important religious place of Bishnu paduka. It will have long-term impact on the
development of local and regional areas. Besides these, implementation of this proposal is
expected to bring several immediate short term benefits like employment generation,
increase in the local economy and enhancement of the technical skills, especially during
operation phase.
Moreover, the project has been expected to have minimal detrimental effect on the physical,
biological, socioeconomic and cultural environment of area. This project does not falls on
any environmentally, historically and culturally sensitive areas. Most of the adverse
impacts (identified and predicted) are short and medium term in nature as well as reversible
in nature. Similarly, identified environmental adverse impacts are locally confined and
limited mainly to the period of construction. No acquisition of private land and resettlement
will be required and no stands of trees to be felled only some common ground vegetations
will be cleared. With set of the proposed mitigation measures, most of impacts can be
minimized or even set off. In addition, proposed bridge work do not exceed any of the
prescribed thresholds by EPA, 1997 and EPR, 1997 (First amendment, 1999) and other
relevant acts and rule.For this time, EIA is sufficient for implementation of project.
To implement the proposal, adopting the safeguard measures described in Environmental
Management and Monitoring Plan is essential.Similarly, all the social and environmental
issues related to project should be settled down before implementation of project works.
EIA of Sardu Khola Bridge Project DoLI
113
References
APHA, AWWA &WEF (1998): Standard Methods for examination of Water and Waste
water, American Public Health Association, Washington DC, 20th edition.
Baral. H.S and Shah K.B. (2064): Wild Mammals of Nepal. Himalayan Nature, Kathmandu,
Nepal
Central Bureau of Statistics (2012): National Population and Housing census 2011,
National Report Vol 1, National Planning Commission (NPC), Kathmandu, Nepal
Central Bureau of Statistics (2014): National Population and Housing census 2014,
National Report Vol 5, part III National Planning Commission (NPC), Kathmandu, Nepal
Field Survey (2018): Field survey conducted from 2075-06-20 to 2075-06-29, Public
consultation held in 2075-06-23. Public Consultations with CFUG member 2076-2-29
Public Hearing held in 2076-3-10 Dharan, Sunsari, Nepal.
Fleming, R Sr. and Jr. and Bangdel, L.S. (1976): Birds of Nepal. R.C. Fleming (Sr. and Jr.)
Kathmandu, Nepal.
GoN: Constitution of Nepal 2072, Ministry of Law, Justice and Parliamentary Affairs, Law
Books Management Board, Kathmandu, Nepal.
GoN: DoR 2003, Reference manual for the Environmental and Social aspects of the
Integrated Road Development. Ministry of the Physical Planning and works Department of
the Road, Kathmandu.
GoN: DoR 2007, Environmental and Social Management Framework, a guideline to the
environmental and social issues associated with new road construction and upgrading.
Ministry of the Physical Planning and Works, Department of Road, Kathmandu.
GoN: DoR 2067, Nepal Bridge Standard, 2067
GoN: DoR, 2013, Nepal Road Standard, 2070
GoN (1997): Environment Protection Act, 1997 (with amendments), Ministry of
Environment, Science and Technology, Kathmandu, Nepal.
GoN (1997): Environment Protection Rules, 1997 (with amendments), Ministry of
Environment, Science and Technology, Kathmandu, Nepal
GoN (1999): Approach for development of Agricultural and Rural roads.
GoN (2004): DoR Bridge Policy and Strategy.
GoN: Labor Act, 1991, Ministry of Law, Justice and Parliamentary Affairs, Law Books
Management Board, Kathmandu.
GoN (2074): Local Government Operation Act 2074 B.S (2017 A.D), Ministry of Federal
Affairs and Genereal Administration, Kathmandu, Nepal.
GoN: Ministry of water resources. Land Water development Committee 2009, National
Water Quality Standard. Smarika.Ministry of Water Resources. Land Water development
Committee, 30th Anniversary and land Water day.
EIA of Sardu Khola Bridge Project DoLI
114
GoN: National Environmental Impact Assessment Guidelines, 1993, Nepal Gazette
Volume, 45 Number 19 Kathmandu
GoN: Solid Waste Management and Resource Mobilization Act 2011, Ministry of Law,
Justice and Parliamentary Affairs, Law Books Management Board, Kathmandu.
GoN: Solid Waste Management and Resource Mobilization Regulation 2012, Ministry of
Law, Justice and Parliamentary Affairs, Law Books Management Board, Kathmandu.
GoN: Water Resources Act 1992, Ministry of Law, Justice and Parliamentary Affairs, Law
Books Management Board, Kathmandu.
GoN: Water Resources Regulation 1993, Ministry of Law, Justice and Parliamentary
Affairs, Law Books Management Board, Kathmandu.
Inskipp, C. and Inskipp, T. 1985. A guide to birds of Nepal.Croom Helm, London, England.
IUCN (2014): IUCN red list of threatened species, version 2012.2, www.iucnredlist.org
Jnwali, S.R., Baral, H.S., Lee, S., Acharaya, K.P., Upadhyay, G.P., Pandey, M., Shrestha,
R., Joshi, D., Laminchhane, B.R., Griffiths, J., Khatiwada, A.P., Subedi, N., and Amin, R.
(2011): The Status of Nepal Mammals: The National Red List Series, Department of
National Parks and Wildlife Conservation Kathmandu, Nepal
Martin, G.J. (1995): Ethnobotany, A People and Plant Conservation Manual. Chapman
and Hall, London.
MoHP (2011): National Population report 2011, Ministry of Health and Population,
Kathmandu.
MoPE (2016): National Population Report 2016, Ministry of Population and Environment,
Kathmandu, Nepal.
MoPE (2017): National Population Report 2017, Ministry of Population and Environment,
Kathmandu, Nepal.
Shrestha, K. (1985): A Field Guide to Nepali Names for Plants.Natural History Museum,
Institute of Science and Technology, T.U., Kathmandu, Nepal.
Singh, A.P. (2001): Flowering Plants of Nepal (Phanerogams).Bulletin of Department of
Plant Resources No. 18.HMG/N, MoFSC, Dept. of Plant Resources, National Herbarium
and Plant Laboratories, Godavary, Lalitpur, Nepal.
Uprety, B.K. (2003): Safeguarding the resources Environmental Impact Assessment
process and Practice. Utara Uprety, Kathmandu.
www.cbs.gov.np : Official website of Central Bureau of Statistics, data of National
Population and Housing Census, 2011
www.dor.gov.np : Safety guidelines for working on Bridge, Guidelines for Inspection and
maintenance of Bridge, Volume, 1, accessed in June 15, 2015.
www.dharan.gov.np : Official website of Dharan Sub-metropolitan city.
www.lrbpnepal.org. Official website of Local Road Bridge Programme (LRBP).