environmental impact assessment epc & annuity ... - world...

52
India: Second Karnataka State Highways Improvement Project Executive Summary Environmental Impact Assessment EPC & ANNUITY PACKAGES Prepared by the Government of Karnataka Public Works Department Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: vananh

Post on 28-Mar-2018

228 views

Category:

Documents


1 download

TRANSCRIPT

India: Second Karnataka State Highways

Improvement Project

Executive Summary

Environmental Impact Assessment

EPC & ANNUITY PACKAGES

Prepared by the Government of Karnataka

Public Works Department

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb370910
Typewritten Text
59095

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

i

TABLE OF CONTENTS

E. EXECUTIVE SUMMARY – EPC & ANNUITY PACKAGES .............................................................. 1 E.1 Introduction: .......................................................................................................................................... 1 E.2 Project Background: .............................................................................................................................. 1 E.3 Need and Scope of Environmental Assessment: ................................................................................... 2 E.4 Description of Project: .......................................................................................................................... 2

E.4.1 Description of Project corridors: ................................................................................................. 2 E.4.2 Typical road cross-section types adopted: ................................................................................... 5 E.4.3 Design speed: ............................................................................................................................... 6 E.4.4 Re-alignments/ Horizontal curve improvements: ......................................................................... 6 E.4.5 Major and minor junctions: .......................................................................................................... 8 E.4.6 Treatment of Culverts and Bridges ............................................................................................... 9 E.4.7 Road Furniture and Road Safety Measures................................................................................ 11

E.5 Key Environmental Laws & Policies: ................................................................................................. 12 E.5.1 Clearances required for the project: .......................................................................................... 13

E.6 Description of baseline environment:.................................................................................................. 15 E.7 Stakeholder Consultation: ................................................................................................................... 16 E.8 Analysis of Alternatives: ..................................................................................................................... 18 E.9 Potential Environmental Impacts and Mitigation measures: ............................................................... 18 E.10 Summary of Resettlement and Rehabilitation (R&R): ........................................................................ 25 E.11 Environmental Management Plan: ...................................................................................................... 26 E.12 Conclusion: ......................................................................................................................................... 28

LIST OF TABLES

Table E-1: Details of proposed project roads under EPC and Annuity .................................................................. 2 Table E-2: Typical Road Cross-sections used in designing project roads .............................................................. 5 Table E-3: Details of minor realignments along the project roads ......................................................................... 6 Table E-4: Details of major realignments along the project roads .......................................................................... 8 Table E-5: Number of Major/Minor junctions identified for improvement ............................................................ 8 Table E-6: Treatment proposals for Culverts along project roads .......................................................................... 9 Table E-7: Treatment proposals for Bridges along project roads ......................................................................... 10 Table E-8: No. of Bus Bays proposed for project roads ....................................................................................... 11 Table E-9: Clearances required for the proposed project roads ............................................................................ 13 Table E-10: Details of Public consultation meetings ............................................................................................ 16 Table E-11: Environmental Impact Matrix of the road projects ........................................................................... 21 Table E-12: Summary of Environmental impacts for EPC project roads ............................................................. 21 Table E-13: Summary of Environmental impacts for annuity project roads ........................................................ 22 Table E-14: Summary of proposed Environmental mitigation measures (EPC project roads) ............................. 23 Table E-15: Summary of proposed Environmental mitigation measures (Annuity project roads) ....................... 23 Table E-16 Summary of Impacts .......................................................................................................................... 25 Table E-17: Estimated cost of EMP implementation............................................................................................ 27

LIST OF FIGURES

Figure E-1: Map showing proposed project road locations with respect to notified National Parks and Wildlife

Sanctuaries. ................................................................................................................................................... 4 Figure E-2: Pictures showing completed solid noise barriers on proposed EPC project roads ............................ 24 Figure E-3: Organizational Framework of EMPIU – KSHIP ............................................................................... 48

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

1

KARNATAKA STATE HIGHWAYS IMPROVEMENT PROJECT (KSHIP)

ENVIRONMENT IMPACT ASSESSMENT

E. EXECUTIVE SUMMARY – EPC & ANNUITY PACKAGES

E.1 Introduction:

This report summarizes the Environmental Impact Assessment (EIA) and Environmental

Management Plan (EMP) for the Project, including project background, applicable legal and policy

framework and environmental monitoring standards, significant potential adverse impacts on the

physical, biological and socio-economic attributes of environment along with mitigation measures in

the project area, analysis of alternatives, public consultation programs and environmental

management plan. This Executive Summary prepared for the Karnataka State Highways Improvement

Project II - World Bank funded EPC and Annuity packages serves as a concise environmental report.

E.2 Project Background:

The Karnataka State Highways Improvement Project (KSHIP) is an initiative by the Public Works

Department (PWD) of the Government of Karnataka (GOK), to undertake improvement of State

Highways and Major District Roads.

Under a previous World Bank (WB) assisted KSHIP-I program (2001 to 2007), 2,406 km state roads

covering State Highways (SH) and Major District Roads (MDR) were improved. An updated

Strategic Options Study (SOS), recently performed for the core road network under the control of the

PWD, identified a further 7,094 km of State Highways as potential candidate roads for prioritized

improvement. A techno-economic feasibility study and environmental/social screening of about 4,900

km of SOS and other roads completed in November 2006 evaluated the feasibility of improvement

works and established a priority ranking of 3,411 km of roads. KSHIP-II comprises the subsequent

improvement program of 3,411 km identified through this feasibility study. To facilitate this, the

Government of Karnataka appointed M/s Scott Wilson Kirkpatrick UK with Scott Wilson Kirkpatrick

India as the Project Coordinating Consultants (PCC) to carry out the Detailed Project Report (DPR)

for upgradation of the 3411 km of roads.

From the 3,411km of roads, a total of 832.51 km of roads have been selected for upgradation under

conventional construction contracts (268.59 km) and Annuity concessions (563.92 km). The

conventional construction contracts are referred to as EPC (engineer, procure and construct). The

proposed EPC1 and Annuity

2 projects are grouped into five contract packages (consisting of eight road

links) and four contract packages (consisting of seventeen road links) respectively. None of the EPC

and Annuity road links pass through any protected area including tiger reserves.

The Annuity concessions are structured such that the concessionaire receives a pre-determined

amount of money as part-payment during the construction period and annuity payments every year

during the operation and maintenance period in return for the obligation to develop and maintain the

highway for the duration of the concession period (10 years). The concessionaire is provided with the

designs and drawings (including DPR). However, the concessionaire is allowed to improve upon the

design on the basis of given standards and specifications, with minimum required standards for certain

components such as horizontal & vertical alignment, pavement to be met. The concessionaire shall

1 EPC contracts: Under EPC (engineer, procure and construct), contractors would build roads and hand over to

GOK, and the cost of the project is fully met by GOK from public funds and World Bank assistance. 2 Annuity concessions: In Annuity, the concessionaires would design, finance, build, operate and maintain the

road for a specified period, at the end of which the road would be transferred to GOK. The financing of

construction would be partly met through World Bank assistance. The concessionaires would finance the

balance and recover monies through Annuity payments from GOK.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

2

construct the project within the project site provided by the GOK. No additional land acquisition will

be required during the implementation. The project site is based on the DPR designs, complying with

all the latest environmental guidelines with respect to environmental protection and conservation. The

scope of work of the concessionaire also includes preparation of required Environmental Monitoring

and Management Plans to be implemented for the proposed road construction works.

E.3 Need and Scope of Environmental Assessment:

Under the techno-economic feasibility study of 4,900km, the roads were subjected to Multi

Criteria Analysis (MCA) and environmental screening. Roads that did not qualify in techno-

economic feasibility studies and sensitive corridors passing through wild life sanctuaries and

national parks were screened to avoid negative impacts on eco-sensitive areas to arrive at a

length of 3,411 km of roads for DPRs under KSHIP-II.

The scope of the environmental study during the DPR stage includes screening, scoping, preparation

of an Environmental Impact Assessment (EIA) and Environmental Management Plan reports as per

the guidelines of the Ministry of Environment and Forests (MoEF), Government of India (GoI) and

meet the requirements of Operational Policy 4.01of World Bank.

EIA notification, 2006 by MOEF, GoI covers expansion of state highways greater than 30km,

involving additional right of way > than 20m involving land acquisition and necessitates

preparation of EIA and EMP. Further, the WB OP 4.01 stipulates need for EA and EMP

under WB financing. In line with these guidelines separate Environmental Impact Assessment

reports have been prepared for EPC and Annuity packages including link wise Environmental

Management Plans.

E.4 Description of Project:

E.4.1 Description of Project corridors:

The corridors selected for improvement under EPC and Annuity are spread across the State of

Karnataka along with distance from nearest notified protected area are presented in the Table E-1

below. The locations of proposed project roads with respect to the notified National Parks and

Wildlife Sanctuaries are shown in Figure E-1.

Table E-1: Details of proposed project roads under EPC and Annuity

Contract

Package

Link

ID Description of Link

Districts

traversed

Distance from

nearest notified

Protected Area

(km)

Link

length

(km)

Contract

Package

Length

(km)

EPC Package

WEP-1 67A Hoskote – H Cross (Hindgnala

Cross)

Bangalore

(R) & Kolar

30 km from

Bannerughatta

NP

23.50

52.40

67B H Cross - Chinatmani Bypass Kolar

55 km from

Bannerughatta

NP

28.90

WEP-2 M7D Hangal - Tadasa Haveri

35 km from

Gudavi bird

Sanctuary

43.46

74.26

T8 Haveri (NH4) - Hangal Haveri

35 km from

Ranebennur

Blackbuck

Sanctuary

31.80

WEP-3 21B Dharwad - Saundatti Belgaum &

Dharwad

45 km from

Dandeli WS 38.50 38.50

WEP-4 13A Tinthni - Devadurga Raichur > 100 km from 32.45 73.80

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

3

Daroji Sloth bear

Sanctuary

13B Devadurga - Kalmala Raichur

> 100 km from

Daroji Sloth bear

Sanctuary

41.35

WEP-5 6C Chowdapur - Gulbarga Gulbarga

> 200 km from

Daroji Sloth bear

Sanctuary

28.63 28.63

Total length (km) 268.59

Annuity Package

WAP 1

63A Malavalli – Maddur Mandya 40 km from

Ranganathittu BS 22.803

192.368

63B Maddur – Huliyurdurga Mandya &

Tumkur

45 km from

Ranganathittu BS 27.531

63C Huliyurdurga – Kunigal Tumkur 30 km from

Adichunchanagiri

sanctuary

21.113

63D Kunigal – Tumkur Tumkur 30 km from

Adichunchanagiri

sanctuary

35.017

63E Tumkur – Kortagere Tumkur 60 km from

Adichunchanagiri

sanctuary

27.897

64F Koratagere – Madhugiri Tumkur 75 km from

Adichunchanagiri

sanctuary

20.027

64G Madhugiri – Pavagada Tumkur 90 km from

Adichunchanagiri

sanctuary

37.980

WAP 2

19A Mudhol – Mahalingapura Bagalkot 40 km from

Ghataprabha BS 19.170

107.937

19B Mahalingapura – Kabbur Bagalkot &

Belgaum

15 km from

Ghataprabha BS 42.344

19C Kabbur - Chikodi Belgaum 15 km from

Ghataprabha BS 18.414

19D Chikodi - (NH-4 cross) Nippani Belgaum 30 km from

Ghataprabha BS 23.897

19D Nippani to Maharashtra border Belgaum 04.112

WAP 3

T21 Shikaripura - Anandapuram (on

NH-206) Shimoga

13 km from

Shettihalli WS 32.241

153.665

M7A Shimoga – Shikaripura Shimoga &

Davanagere

7 km from

Shettihalli WS 49.795

M7B Shikaripura – Anavatti Shimoga 15 km from

Gudavi BS 45.414

M7C Anavatti – Hanagal Shimoga &

Haveri

15 km from

Gudavi BS 26.215

WAP 4

10A Managuli - Basavana Bagewadi -

Talikota Bijapur

> 100 km from

Ghataprabha BS 61.300

109.953

10B Talikota - Hunasagi - Devapur Bijapur &

Gulbarga

> 100 km from

Daroji Sloth Bear

Sanctuary

48.653

Total length (km) 563.923

Note: NP – National Park; WS - Wildlife Sanctuary; BS - Bird Sanctuary.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

4

Figure E-1: Map showing proposed project road locations with respect to notified National Parks and

Wildlife Sanctuaries.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

5

E.4.2 Typical road cross-section types adopted:

Based on the analysis of the primary and secondary data on these road links and comparing various

alternatives to avoid, mitigate and compensate the adverse impact on environment and safety for road

users, cross sections presented in Table E-2 have been evolved and recommended in the EMP. Two

different categories of cross-sections have been used in the design - rural cross-sections and urban

cross-sections. The table below includes various cross sections proposed for the project roads.

Table E-2: Typical Road Cross-sections used in designing project roads

C/S-

Type Description

Carriageway

width (m)

Paved

shoulder (m)

Unpaved

shoulder

(m)

Remarks Contract Package

UR1A Rural cross-section 7.00 1.50m both

sides

1.00m

both sides

WEP 1, 2,3,4 & 5

WAP 1, 2, 3 & 4

UR1B Rural cross-section 7.00 Nil 2.50m

both sides

WAP 2, 3 & 4

UR2 Rural cross-section

(through village)

7.00 Varies 2.50m

to 4.50m both

sides

Nil. For parking/

stopping/ bus

bays/ bicycles

WAP 1& 4

UR3 Urban cross-

section in built-up

area (with covered

drain)

7.00 Varies 2.50m

to 4.50m both

sides

Nil 2.0m footpath/

covered drain

on both sides.

WEP 1, 2, 3, 4 & 5

WAP 1, 2, 3 & 4

UR4 Urban dual lane

cross-section in

built-up area (with

covered drain)

Dual 7.50m

with central

median

1.20m

Nil Nil 2.0m footpath/

covered drain

on both sides.

WEP 1 & 2

WAP 1, 2, 3 & 4

UR4A Urban dual lane

cross-section in

built-up area (with

covered drain)

Dual 6.50m

with central

median 0.4m

Nil Nil 2.0m footpath/

covered drain

on both sides.

WEP 1, 2 & 4

WAP 1, 2, 3 & 4

UR4B Urban dual lane

cross-section in

built-up area (with

covered drain)

Dual 6.50m

with central

median 0.4m

Nil 1.5m both

sides

WAP 4

UR4C Urban dual lane

cross-section in

built-up area (with

covered drain)

Dual 6.50m

with central

median 0.6m

Nil Nil 1.0m footpath/

covered drain

on both sides.

WAP 4

UR5 Rural cross-section

in sugarcane belt

7.00 2.50m both

sides

1.0m both

sides

WAP 1

UR6 Rural cross-section

in hilly terrain

7.00 1.00m both

sides

Nil V-type lined

drain on both

sides.

WAP 1

UR7 Rural cross-section

in cutting

7.00 1.50m both

paved with

flexible

pavement and

1.0m both

sides with

ICPB

Nil V-type lined

drain on both

sides.

WEP 4

WAP 1 & 3

UR8 Urban cross-

section with

parking bays

7.00 2.50m both

sides

Nil 6m parking

bays on either

sides

WAP 2

UR9 Rigid pavement

rural cross-section

(through village)

7.00 Varies 2.50m

to 4.50m both

sides

Nil RCC uncovered

drains on both

sides

WEP 1, 2 & 4

WAP 1, 2 & 3

UR10 Rural cross-section

in hilly terrain

7.00 1.50m both

sides

1.00m

both sides

Open V-type

drain in cutting

side and W-

beam crash

barrier in valley

WEP 5

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

6

C/S-

Type Description

Carriageway

width (m)

Paved

shoulder (m)

Unpaved

shoulder

(m)

Remarks Contract Package

side.

UR11 Rural cross-section

at bridge approach

7.00 Nil 2.50m

both sides

Provision of

retaining wall

to reduce the

toe width.

WEP 5

UR12 Rural cross-section

with lime

stabilization

technique

7.00 Nil 2.50m

both sides

WEP 4

UR13 Rural cross-section

with retaining wall

on both side

7.00 Nil Nil Provision of

retaining wall

to reduce the

toe width on

both the sides

WEP 3

UR14 Urban cross-

section with

overlay

7.00 Nil Nil Lined cover

drain in both

the sides.

WAP 1

UR15 Rural cross-section 7.00 1.50m both

sides

1.00m

both sides

Lined

uncovered

drains on both

sides (V-Type)

WAP 1

UR16 Rural cross-section 7.00 1.50m both

sides

1.00m

both sides

Retaining wall

and open drain

proposed in

tank bund area.

WAP 1

UR17 Urban dual lane

cross-section in

built-up area (with

un covered drain)

Dual 7.50m

with central

median 1.2m

Nil 1.00m

both sides

Retaining wall

and open drain

in the built up

area.

WAP 3

UR18 Rural cross-section

in lake location

7.00 Nil 2.50m

both sides

Retaining wall

in the lake side.

The cross-sectional details adopted are consistent with IRC guidelines.

E.4.3 Design speed:

Design speeds have been selected in compliance with the relevant IRC Guidelines. A

minimum design speed of 80 kph is considered for the project roads in line with the type of

terrain traversed. However, a target design speed of 100 kph has been adopted for all rural

sections in plain terrain. In village areas/built up areas, a posted speed of 50 kph has been

adopted from safety considerations.

E.4.4 Re-alignments/ Horizontal curve improvements:

Re-alignments are generally considered to avoid stretches of road that have significant constraints on

improvement – such as heavily built up areas with restricted width where the R&R costs would be

very high. There are 3 major re-alignments required on these roads. Also, to provide for safe

operation, minor re-alignments were carried out at sharp curves with inadequate sight distance, in

line with geometrical standards as set out in IRC guidelines.

Table E-3: Details of minor realignments along the project roads

Link ID. Start Chainage End Chainage Length of

realignment (m)

EPC road links

67A 1.250 1.600 350

67B No realignments

M7D 3.980 4.020 40

13.660 13.850 190

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

7

Link ID. Start Chainage End Chainage Length of

realignment (m)

17.980 18.460 480

42.200 42.339 139

T8

6.920 7.040 120

7.550 7.720 170

11.540 11.620 80

21B 8.820 8.950 130

31.700 31.950 250

13A

0.720 0.800 80

1.350 1.520 170

8.670 8.900 230

13B No realignments

6C

9.900 10.280 380

18.560 19.070 510

23.180 23.200 20

Annuity road links

63A

1150 1250 100

13980 14180 200

18610 18700 90

63B 21860 21950 90

63C

2500 2700 200

4520 4620 100

6400 6720 320

9800 10000 200

63D

12950 13100 150

21500 21850 350

28240 28340 100

33240 33280 40

33920 34050 130

63E

900 1170 270

14720 14820 100

16920 17320 400

19580 20120 540

64F

10250 10600 350

11520 11740 220

12870 13430 560

13600 13920 320

11420 14540 120

64G

1510 1850 340

2350 2630 280

3180 3260 80

17970 18130 160

18730 19040 310

20340 20460 120

24950 25460 510

25680 26040 360

44640 45380 740

51720 51820 100

19B

3590 3860 270

9460 9890 430

12420 12660 240

13410 13960 550

17800 18160 360

29700 30170 470

37740 38050 310

41260 41400 140

19C 690 810 120

1020 1170 150

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

8

Link ID. Start Chainage End Chainage Length of

realignment (m)

10360 10560 200

14490 14810 320

19D

2930 3630 700

7740 8500 760

11860 12220 360

17950 18180 230

21500 21770 270

T21

4180 4300 120

8720 8860 140

12765 13050 285

22800 22930 130

29800 30200 400

31200 31520 320

M7A 32150 32350 200

32510 32710 200

M7B

2580 2800 220

3370 3630 260

4000 4700 700

14080 14730 650

20700 20820 120

24770 25100 330

25500 25800 300

30550 30800 250

36900 37400 500

38700 38900 200

41000 41200 200

M7C

10140 10260 120

22770 22930 160

23150 23260 110

10A 25920 26200 280

29840 30130 290

10B 32150 32350 200

32510 32710 200

Table E-4: Details of major realignments along the project roads

Link ID. Start Chainage End Chainage Length of

realignment (m)

Realignment

location

63B 23.600 27.300 3700 Huliyurdurga

63E 22.635 27.200 4565 Koratagere

64F 14.900 22.627 7727 Madhugiri

E.4.5 Major and minor junctions:

In order to carryout geometric improvement at junctions, it was decided to categorise them

under Major junctions and Minor junctions. Major junctions involved are those with NHs,

SHs and MDRs that carry higher traffic volumes. Village roads and other roads with lower

traffic volumes were typically considered under minor junctions. The number of junctions

identified for improvement is presented in the table below. The improvements would provide

for higher capacity and safe operation.

Table E-5: Number of Major/Minor junctions identified for improvement

Link

ID Description

No. of Junctions

Major Minor

EPC project roads

67A Hoskote - Hindgnala Cross 5 15

67B Hindgnala Cross - Chintamani Bypass 4 21

M7D Hangal – Tadasa 6 17

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

9

Link

ID Description

No. of Junctions

Major Minor

T8 Haveri (NH4) - Hangal 4 20

21B Dharwad - Saundatti 2 16

13A Tinthni - Chinchodi - Jalhalli - Karegud - Devadurga 2 6

13B Devadurga - Masarkal - Gabbur - Kalmala 4 8

6C Chowdapur - Gulburga 1 12

Total 28 115

Annuity project roads

63A Malavalli – Maddur 1 26

63B Maddur – Huliyurdurga 2 27

63C Huliyurdurga – Kunigal 1 15

63D Kunigal – Tumkur 3 31

63E Tumkur – Kortagere 4 26

64F Koratagere – Madhugiri 2 17

64G Madhugiri – Pavagada 1 29

19A Mudhol – Mahalingapura 2 8

19B Mahalingapura – Kabbur 5 19

19C Kabbur - Chikodi 4 3

19D Chikodi - (NH-4 cross) Nippani 3 13

19D Nippani to Maharashtra border 0 2

T21 Shikaripura - Anandapuram (on NH-206) 0 11

M7A Shimoga – Shikaripura 3 21

M7B Shikaripura – Anavatti 5 20

M7C Anavatti – Hanagal 3 13

10A Managuli - Basavana Bagewadi - Talikota 6 17

10B Talikota - Hunasagi - Devapur 5 14

Total 50

E.4.6 Treatment of Culverts and Bridges

The treatment proposals for culverts, depending on their condition, include maintenance, widening,

increasing the vent size, replacement of structurally distressed culverts and replacement of bridges by

culverts. The treatment proposals for culverts are summarized in the Table E-6 below.

Table E-6: Treatment proposals for Culverts along project roads

Co

ntr

act

Pa

cka

ge

Lin

k R

ef

Description of Link

Treatment Proposals

Total

Do

No

thin

g

Ma

inte

na

nce

Wid

enin

g

Rep

lace

men

t o

f su

per

stru

ctu

re

Rep

lace

men

t w

ith

la

rger

dia

met

er

pip

e

Rep

lace

men

t o

f d

istr

esse

d c

ulv

erts

Rep

lace

men

t d

ue

to c

han

ge

in

Ali

gn

men

t (H

A /

VA

)

Ad

dit

ion

al

culv

erts

/ C

ulv

erts

pro

po

sed

on

By

pa

ss

Ab

an

do

n

EPC project roads

WEP-1 67A Hoskote - H Cross

(Hindgnala Cross) - 7 2 - 1 8 1 2 - 21

67B H Cross - Chinatmani Bypass - 2 2 - 3 21 1 4 - 33

WEP-2 M7D Hangal - Tadasa - 4 18 - 53 10 2 4 3 94

T8 Haveri (NH4) - Hangal 3 9 9 - 15 29 2 - - 67

WEP-3 21B Dharwad - Saundatti - 3 5 - 1 18 4 10 - 41

WEP-4 13A Tinthni - Devadurga - 6 7 - 21 14 1 3 - 52

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

10

13B Devadurga - Kalmala - 14 1 - 8 20 5 2 - 50

WEP-5 6C Chowdapur - Gulbarga - 1 4 - 5 26 1 3 1 41

Total 3 46 48 0 107 146 17 28 4 399

Annuity project roads

WAP 1

63A Malavalli – Maddur - 10 10 - 5 14 8 - 2 49

63B Maddur – Huliyurdurga - 5 12 - 13 11 2 9 3 55

63C Huliyurdurga – Kunigal - 4 2 - 13 14 5 - - 38

63D Kunigal – Tumkur 2 1 9 - 6 35 4 2 - 59

63E Tumkur – Kortagere - 12 4 - 8 15 9 9 2 59

64F Koratagere – Madhugiri - 2 1 - 4 28 - 16 - 51

64G Madhugiri – Pavagada - 17 9 - 2 59 4 2 - 93

WAP 2

19A Mudhol – Mahalingapura - - 2 - 21 24 - - - 47

19B Mahalingapura – Kabbur - 1 4 - 23 36 2 - - 66

19C Kabbur - Chikodi - - - - 8 28 - - - 36

19D Chikodi - (NH-4 cross)

Nippani - 3 5 - 9 28 2 - 6 53

WAP 3

T21 Shikaripura -

Anandapuram ( NH-206) - 6 13 - 23 20 9 1 - 72

M7A Shimoga – Shikaripura - 15 37 - 17 32 9 1 - 111

M7B Shikaripura – Anavatti - 5 18 - 42 24 5 1 - 95

M7C Anavatti – Hanagal - 5 4 - 15 9 1 7 - 41

WAP 4

10A Managuli - Basavana

Bagewadi - Talikota - 5 11 - 2 33 1 4 - 56

10B Talikota - Hunasagi -

Devapur - 10 3 - 23 23 - 3 - 62

2 101 144 0 234 433 61 55 13 1043

A summary of the proposals for the bridges is given in the Table E-7 below. The 3 major bridges in

the EPC packages are 138 m long Varada River bridge on link T8, 128 m long Hirehalla bridge on

link 13A, and a 60 m bridge on link 6C. There are 3 major bridges in Annuity packages as well. A

major bridge having a length of 162 m is proposed at Kunigal tank on road link 63D and two major

bridges each having of length of 63 m across road link 63E.

Table E-7: Treatment proposals for Bridges along project roads

Co

ntr

act

Pa

cka

ge

Lin

k R

ef

Description of Link

New Bridges

Rep

lace

men

t o

f

Su

per

stru

ctu

re

Wid

enin

g

Ma

inte

na

nce

Do

No

thin

g

Co

nv

erte

d t

o

Cu

lver

ts

Total

6m

to

30m

30m

to 6

0m

> 6

0m

EPC project roads

WEP-1 67A Hoskote - H Cross (Hindgnala Cross) 2 - - - - 5 - - 7

67B H Cross - Chinatmani Bypass 6 - - - - 6 - - 12

WEP-2 M7D Hangal - Tadasa 1 1 - - - - - - 2

T8 Haveri (NH4) - Hangal - - 1 - - - - - 1

WEP-3 21B Dharwad - Saundatti 4 2 - - 1 1 - 1 9

WEP-4 13A Tinthni - Devadurga 12 2 1 - 2 - - 3 20

13B Devadurga - Kalmala 6 2 - 2 11 - 4 25

WEP-5 6C Chowdapur - Gulbarga 5 - 1 - - 1 - - 7

Total 36 7 3 0 5 24 0 8 83

Annuity project roads

WAP 1

63A Malavalli – Maddur 1 - - - - 4 - - 5 63B Maddur – Huliyurdurga - - - - 3 2 - - 5 63C Huliyurdurga – Kunigal - - - - - 4 - - 4

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

11

Co

ntr

act

Pa

cka

ge

Lin

k R

ef

Description of Link

New Bridges

Rep

lace

men

t o

f

Su

per

stru

ctu

re

Wid

enin

g

Ma

inte

na

nce

Do

No

thin

g

Co

nv

erte

d t

o

Cu

lver

ts

Total

6m

to

30m

30m

to 6

0m

> 6

0m

63D Kunigal – Tumkur 2 - 1 - 1 7 - - 11 63E Tumkur – Kortagere 4 - 2 - 3 7 - - 16 64F Koratagere – Madhugiri 5 2 - 1 - 2 - - 10 64G Madhugiri – Pavagada 8 2 - 4 2 9 - - 25

WAP 2

19A Mudhol – Mahalingapura 4 3 - - - - - - 7

19B Mahalingapura – Kabbur 11 4 - - - 1 - 2 18

19C Kabbur - Chikodi 2 1 - - - 1 - - 4 19D Chikodi - (NH-4 cross) Nippani 12 - - - - - 2 - 14

WAP 3

T21 Shikaripura - Anandapuram (on NH-

206) 2 - - - - 3 1 - 6

M7A Shimoga – Shikaripura 4 - - - - 2 2 - 8

M7B Shikaripura – Anavatti 5 - - - 1 - 5 - 11

M7C Anavatti – Hanagal 1 - - - - 3 - - 4

WAP 4 10A

Managuli - Basavana Bagewadi -

Talikota 5 1 - - 3 4 - 3 16

10B Talikota - Hunasagi - Devapur 10 4 - - - 1 - 1 16

76 17 3 5 13 50 10 6 180

Other details of the project discussed under this section include, present and projected traffic details

by vehicle type pertaining to the project roads; road construction materials such as rock, gravel, sand,

embankment fill, asphalt; the major material sources for aggregates, murrum and sand in the project

area; etc,.

E.4.7 Road Furniture and Road Safety Measures

Road furniture and safety measures include road markings, cautionary, mandatory and informatory

signs, kilometer stones, hectometer stones and boundary stones, delineators and object markers, guard

posts and crash barriers, road humps & rumble strips, Reflective Pavement Markers (RPM) and

chevron signs, median barriers, bus bays and truck lay byes. Table E-8 below gives the number of bus

bays provided on each of the proposed project roads.

Table E-8: No. of Bus Bays proposed for project roads

Contract

Package

Link

ID Description

Number of Bus

Bays

LHS RHS

EPC project roads

WEP1 67A Hoskote - Hindgnala Cross 6 6

67B Hindgnala Cross - Chintamani Bypass 5 5

WEP2 M7D Hangal – Tadasa 12 12

T8 Haveri (NH4) – Hangal 3 5

WEP3 21B Dharwad – Saundatti 2 2

WEP4 13A Tinthni - Chinchodi - Jalhalli - Karegud – Devadurga 8 8

13B Devadurga - Masarkal - Gabbur - Kalmala 7 8

WEP5 6C Chowdapur – Gulburga 3 3

Total 46 49

Annuity project roads

WAP 1 63A Malavalli – Maddur 1 1

63B Maddur – Huliyurdurga 5 5

63C Huliyurdurga – Kunigal 6 6

63D Kunigal – Tumkur 11 11

63E Tumkur – Kortagere 9 9

64F Koratagere – Madhugiri 4 4

64G Madhugiri – Pavagada 8 8

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

12

Contract

Package

Link

ID Description

Number of Bus

Bays

LHS RHS

WAP 2 19A Mudhol – Mahalingapura 2 2

19B Mahalingapura – Kabbur 7 7

19C Kabbur - Chikodi 3 2

19D Chikodi - (NH-4 cross) Nippani 9 9

WAP 3 T21 Shikaripura - Anandapuram (on NH-206) 8 8

M7A Shimoga – Shikaripura 3 3

M7B Shikaripura – Anavatti 7 7

M7C Anavatti – Hanagal 8 8

WAP 4 10A Managuli - Basavana Bagewadi - Talikota 10 10

10B Talikota - Hunasagi – Devapur 12 12

Total 113 112

E.5 Key Environmental Laws & Policies:

The Constitutional Provisions like Article 48 and 51-A (g) and 74th Amendment to the Constitution

serve as principle guidelines of environmental protection. Further Regulations, Acts, Policies

applicable to sustainability and environmental protection as listed in chapter 3 of EIA report have

been reviewed for their applicability. Guidelines and norms related to road construction by Indian

Road Congress that help for environmental protection include, IRC: 104-1988, IRC: 36-1974, IRC:

10-1961, IRC: 36-1970, IRC: 43-1972, IRC: 72-1978, IRC: 33-1982, etc.

EIA Notification of September 20063 - As per the Notification, it is necessary to take prior

Environmental clearance for the road expansion projects from Expert Appraisal Committee (EAC) for

Category „A‟4 projects and State Environmental Appraisal Committee (SEAC) for Category „B‟

5

projects. Interpretation and applicability of the EIA Notification dated 14th September 2006, for EPC

and annuity road links is as follows. Proposed road links have been grouped as follows with respect to

prior Environmental clearance under EIA Notification, 2006.

Group I: Expansion of State Highways having length > 30 km length and located within 10 km

distance from the boundary of Protected Areas notified under the Wild Life (Protection) Act, 1972 and

interstate boundaries are grouped under Category „A‟. These projects require prior environmental

clearance from the Expert Appraisal Committee (EAC).

Link ID Description of the links Length in km Remarks

64G Madhugiri - Pavagada 35.80 AP Border

M7A Shimoga – Shikaripura 50.10 Shettihalli wildlife sanctuary

3 EIA Notification of September 2006

3 under sub-rule (3) of rule 5 of the Environment (Protection) Rules, 1986

for imposing certain restrictions and prohibitions on new projects or activities, or on the expansion or

modernization of existing projects or activities based on their potential environmental impacts as indicated in the

schedule to the notification.

4 Category „A‟ projects - All projects or activities included as Category „A‟ in the Schedule, including expansion

and modernization of existing projects or activities and change in product mix, shall require prior environmental

clearance from the Central Government in the Ministry of Environment and Forests (MoEF) on the

recommendations of an Expert Appraisal Committee (EAC) to be constituted by the Central Government for the

purposes of this notification.

5 Category „B‟ projects - All projects or activities included as Category „B‟ in the Schedule, including expansion

and modernization of existing projects or activities as specified in sub paragraph (ii) of paragraph 2, or change

in product mix as specified in sub paragraph (iii) of paragraph 2, but excluding those which fulfill the General

Conditions (GC) stipulated in the Schedule, will require prior environmental clearance from the State/Union

territory Environment Impact Assessment Authority (SEIAA). The SEIAA shall base its decision on the

recommendations of a State or Union territory level Expert Appraisal Committee (SEAC) as to be constituted

for in this notification. In the absence of a duly constituted SEIAA or SEAC, a Category „B‟ project shall be

treated as a Category „A‟ project

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

13

Group II: Expansion of State Highways greater than 30 km involving additional right of way

greater than 20m involving land acquisition are grouped under Category „B‟. These projects

require prior environmental clearance from the State Environmental Impact Assessment Authority

(SEIAA).

Link ID Description of the links Length in km

M7D Hangal – Tadasa 43.46

T8 Haveri (NH-4) – Hangal 31.80

21B Dharwad – Saundatti 38.50

13A Thinthini – Chinchodi – Jalhalli – Karegud – Devadurga 32.45

13B Devadurga – Masarkal – Gabbur – Kalmala 41.35

63D Kunigal – Tumkur 35.20

19B Mahalingapura – Kabbur 42.27

T21 Shikaripura – Anandapuram (on NH-206) 32.20

M7B Shikaripura – Anavatti 46.00

10A Managuli - Basavana Bagewadi - Talikota 61.04

10B Talikota - Hunasagi – Devapur 48.56

Group III: Project roads having length < 30 km are not under the purview of EIA Notification 14th

September 2006.

Link ID. Description of the links Length in km

67A Hoskote - H (Hindgnala) Cross 23.50

67B H Cross - Chinatmani bypass 28.90

6C Chowdapur – Gulbarga 28.63

63A Malavalli – Maddur 22.80

63B Maddur – Huliyurdurga 27.50

63C Huliyurdurga – Kunigal 21.10

63E Tumkur – Koratagere 27.90

64F Koratagere – Madhugiri 20.00

19A Mudhol – Mahalingapura 19.06

19C Kabbur – Chikodi 18.38

19D Chikkodi - Nippani (NH4) 23.90

M7C Anavatti Hanagal 26.30

However, recent amendment (dated November, 2009) to EIA Notification, 2006 states that “All state

highway projects; and state highway expansion projects in hilly terrine (above 1,000 m AMSL) and or

ecologically sensitive areas” require pre environmental clearances from EAC for Category „A‟

projects and from SEAC for Category „B‟ projects.

E.5.1 Clearances required for the project:

After reviewing the various applicable acts and statutes, as mentioned above, it is proposed that

clearances and permission are required for corridors of the project. A summary of clearances required

for the proposed projects is shown in the Table E-9.

Table E-9: Clearances required for the proposed project roads

Sl.

No. Subject

Authority

granting

clearance

When

required

Corridors

requiring

clearances

Responsibility and Status

of Clearance

1 Prior environmental

clearance

Karnataka State

Environmental

Appraisal

Committee

Before

Construction

M7D, T8, 21B,

13A & 13B

(EPC) 63D,

19B, T21,

M7B, 10A &

10B (Annuity).

KSHIP‟s responsibility

Environmental clearance

has given vide letter no.

SEIAA/80/ind/2008 dated

18.11.2008 and

SEIAA/7/ind/2009 dated

01.10.2009.

MoEF, New Delhi Before

Construction

64G & M7A

(Annuity)

Environmental clearance

has given vide letter no. 5-

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

14

Sl.

No. Subject

Authority

granting

clearance

When

required

Corridors

requiring

clearances

Responsibility and Status

of Clearance

13/2008-IA-III dated

13.01.2009 and letter no 5-

6/2009-IA.III dated

22.01.2010.

2 Forest Clearance Karnataka State

Forest

Department.

Before

Construction

67A, 13A &

M7D (EPC)

63C, T21, M7A

& M7B

(Annuity)

KSHIP‟s responsibility

Applications for forest land

diversion – submitted.

3 Cutting tress and

transporting

Department of

Forests.

Before

Cutting

All road links. KSHIP‟s responsibility

Application for tree cutting

clearance has been

submitted for EPC road

links and is in progress for

Annuity road links.

4 Consent for

Establishment

(under Water

(Control and

prevention of

pollution) Act and

Air (Control and

prevention of

pollution) Act)

Karnataka State

Pollution Control

Board (KSPCB),

Bangalore

Before

Construction

All road links. KSHIP‟s responsibility

Consents have been

obtained vide letter no.

PCB/439/CFE/08/H.551

dated 22.07.2008 and vide

letter no.

PCB/05/CNP/09/558 dated

29.01.2010.

5 Permit for

installation of

crusher

KSPCB Before

Construction

All road links. Contractor‟s responsibility.

6 No Objection

Certificate (NOC)

for batching plant

KSPCB, inspector

of Factories.

Before &

during

construction.

All road links. Contractor‟s responsibility.

7 Asphalt Plant

Clearance

KSPCB Before

Construction

All road links. Contractor‟s responsibility.

8 Traffic

Management and

regulation during

operation

Police Department During

Construction

All road links. Contractor‟s responsibility.

9 Installation of

Generators

Karnataka

Electricity

company of

respective regions

Before

Installation

All road links Contractor‟s responsibility.

10 Clearance for

excavation &

transporting soil

Department of

Mines / Local

Bodies

Before

Quarrying

All road links. Contractor‟s responsibility.

11 Permission for

extraction of sand

and boulder

Department of

Mines &

Geology.

Government of

Karnataka

Before

Quarrying

All road links. If the extraction of boulder

is being procured from the

existing quarry/supplier, it

shall be ensured that,

requisite license/ lease has

been obtained from the

concerned Authority.

12 License for storing

diesel

Commissioner of

Explosives &

KSPCB

During

Construction

All road links. Contractor‟s responsibility.

13 Labour camps District Health

Officer

During

Construction

All road links. Contractor‟s responsibility.

14 Clearance for

crossing other

waterways

Irrigation

Department, GoK.

During

Construction

T8 Contractor‟s responsibility.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

15

Sl.

No. Subject

Authority

granting

clearance

When

required

Corridors

requiring

clearances

Responsibility and Status

of Clearance

15 If water has to be

taken from river /

Reservoir

Irrigation

Department, GoK.

During

Construction

Where ever the

necessity arises.

Contractor‟s responsibility.

E.6 Description of baseline environment:

Information on baseline environment was collected from secondary source of data for the macro

environmental parameters like climate, physiography (Geology and geomorphology), biological and

socio-economic environment of the project influence area. The micro-environmental details within the

Corridor of Impact (CoI) have been collected from Primary source of data such as base maps prepared

by reconnaissance survey, extrapolation of environmental features on the proposed design, tree

enumeration, Analysis for environmental parameters such as Air, Water, Noise and Soil quality on the

project road.

The proposed road links proposed for improvements are spread across the state of Karnataka. Road

links 6C, 21B, 19A, 19B, 19C & 19D are on the Northern Karnataka Plateau; road links 10A, 10B,

13A, 13B, T8, M7D, T21, M7A, M7B & M7C are on the Central Karnataka Plateau and road links

67A, 67B, 63A, 63B, 63C, 63D, 63E, 64F and 64G are on the Southern Karnataka Plateau.

Topography of the project areas varies from mixture of flat to undulating terrain to gently undulating

terrain with residual hills.

The mean maximum temperature of the project area varies from 36.48 0C to 44.62

0C and mean

minimum temperature from 9.73 0C to 12.58

0C. The annual normal rainfall of the project area varies

from 383 mm to 821 mm.

Air quality, noise levels, water quality and soil characteristics for the proposed project roads have

been monitored at representative locations.

Proposed project road links 6C, 13A, 13B, 21B, 19A, 19B, 19C, 19D, 10A and 10B are distributed in

the Krishna river basin; links M7D, T8, T21, M7A, M7B and M7C are distributed in the Tungabhadra

river basin; road links 63A, 63B, 63C and 63D are distributed over the Kaveri river basin and road

links 67A, 67B, 63E, 64F and 64G are distributed over the Penneru and Palar river basins of

Karnataka state. The water contours and ground water yields in the project area varies from 400 – 500

(6C) to 800 - 1000 (67B) m above MSL and <1 (67B) to 5 – 25 (13 A&B) respectively.

The geological history of Karnataka is largely confined to the two oldest eras – the Archaean and the

Proterozoic. Deccan Trap covers the substantial part of North Karnataka. The bulk of the rocks of

Karnataka are Archaean in age. Major part of project area is covered with rock types of Granite,

Grano-diorite, Pegmatite, unclassified crystalline rocks (mainly Gneisses) Schist, Phyllites, Shale,

Limestone and Slates and distributed with minerals such as Red ochre, Feldspar, Gypsum, China

Clay, Manganese, Limestone and Magnesite, etc.

Project areas have different types of soils. Corridor 67 is over red loamy to red gravel type of soils

suitable for growing ragi, paddy, mulberry, mango and oil seeds; M7 corridor and T8 project road is

over red loamy, red sandy and mixed red & black soils suitable for growing sun flower, paddy and

cotton; 21B is over mixed red & black suitable for growing sun flower, wheat, ground nuts and

cotton; road links 6C, 13A, 13B, 10A and 10B are on Black Cotton medium and red gravel soils

which are suitable for growing pulses, maize, jowar, grapes and cotton; 63 and 64 corridors are in red

loamy, red sandy and red gravel type of soils suitable for growing ragi, paddy, mulberry, ground nuts

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

16

and oil seeds and major part of corridor 19 is through black cotton soils suitable for growing wheat,

tobacco, pulses, oil seeds and sugar cane.

The project road links 67A, M7D, T8, 63C, M7A, M7B and T21 requires some forest land diversion.

None of the project roads pass through the protected areas such as National Parks and Wildlife

Sanctuaries. Details of EPC and Annuity project roads along with distance from nearest notified

protected area are presented in Table E-1.

The project roads run mainly through cultivable land growing verities of crops connecting many

human habitations such as villages and towns. Public institutions like schools, hospitals, banks,

religious, community and commercial structures are located along the road side which facilitates the

general public with good service. Some of the major urban settlements with commercial activities

along the proposed project corridors are Hosakote, Hanagal, Haveri, Dharwad, Saundatti, Devadurga,

Gulbarga, Malavalli, Maddur, Kunigal, Tumkur, Madhugiri, Mudhol, Chikkodi, Shimoga, Shikaripura

and Talikota. The basic features of demography along the study corridors have been studied

and indicated in the report. The figures of 2001 census of population have been used.

E.7 Stakeholder Consultation:

Consultations during pre-feasibility, feasibility and environmental assessment stage have been

conducted with the objective of involving local communities in the project planning (participatory

planning). The follow up consultations have been held at project roads as a part of disclosure to

highlight the salient features of the project. The stakeholders of the project included affected

communities (within the corridor of impact) and other institutional stakeholders. The details of public

consultations are presented in the Table E-10.

Table E-10: Details of Public consultation meetings

Link

ID

Description of

link Details of consultation meetings Details of follow-up consultations

Annuity project roads

67A Hoskote – H

Cross (Hindgnala

cross)

Date: 18.01.2008; Place: Hindgnala;

No. of Participants: 43, covering 8

villages.

Date: 14-7-2010 ; Place: Hindignal

No. of Participants: 75

67B H Cross -

Chintamani

Bypass

Date: 18.01.2008; Place:

Perumanchanahalli;

No. of Participants: 39, covering 15

villages.

T8 Haveri – Hanagal Date: 20.12.2007; Place: Adur;

No. of Participants: 65, covering 8

villages.

Date: 06-7-2010 ; Place: Hangal

town

No. of Participants: 60

M7D Anavatti –

Hanagal – Tadas

Date: 13-01-2009; Place: Hanagal;

No. of Participants: 185, covering 15

villages.

21B Dharwad –

Saundatti

Date: 23.01.2008 ; Place: Aminabhavi;

No. of Participants: 121, covering 5

villages.

Date: 07-7-2010 ; Place:

Aminbhavi village No. of

Participants: 65

13A Thinthini Bridge

– Devadurga

Date: 13.11.2008; Place: Jalahalli;

No. of Participants: 31, covering 8

villages..

Date: 08-7-2010 ; Place: Deodurga

town

No. of Participants: 34

13B Devadurga -

Kalmal cross

Date: 14.11.2008 ; Place: Masarkal;

No. of Participants: 20, covering 8

villages.

6C Chowdapur –

Gulbarga

Date: 31.12.2007; Place: Sharan

Sirasangi;

No. of Participants: 62, covering 4

villages.

Date: 09-7-2010 ; Place: Gabbur B

village

No. of Participants: 53

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

17

Link

ID

Description of

link Details of consultation meetings Details of follow-up consultations

Annuity project roads

63A Malavalli-

Maddur

Date: 20.02.2008; Place: K M Doddi;

No. of Participants: 31, covering 6

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

63B Maddur-

Huliyurdurga

Date: 20.02.2008; Place:

Mallankuppe;

No. of Participants: 113, covering 10

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

63C Huliyurdurga-

Kunigal

Date: 19.02.2008; Place: Dodda

Mavathur;

No. of Participants: 57, covering 7

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

63D Kunigal-Tumkur Date: 19.02.2008; Place: Kothagere;

No. of Participants: 91, covering 7

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

63E Tumkur-

Koratagere

Date: 18.02.2008; Place: Beladara;

No. of Participants: 67, covering 6

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

64F Koratgere to

Madhugiri

Date: 18.02.2008; Place:

Keregalapalya;

No. of Participants: 83, covering 4

villages..

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

64G Madhugiri to

Pavagada

Date: 18.02.2008; Place: Hoskere;

No. of Participants: 92, covering 12

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

19A Mudhol-

Mahalingapur

Date: 21.11.2008; Place: Ranna

Belagali;

No. of Participants: 53, covering 6

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

19B Mahalingapur-

Kabbur

Date: 21.11.2008; Place: Kankanawadi;

No. of Participants: 58, covering 7

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

19C Kabbur-Chikodi Date: 21.11.2008; Place: Nagar Munnoli

No. of Participants: 32, covering 7

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

19D Chikkodi-(NH 4

Cross) Nippani

Date: 19.12.2007; Place: PAttankudi;

No. of Participants: 113, covering 6

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

T21 Shikaripura-

Anandapuram

(NH 206)

Date: 07.01.2009; Place: Anandapuram;

No. of Participants: 35, covering 8

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

M7A Shimoga –

Shikaripura

Date: 07.01.2009; Place: Shimoga;

No. of Participants: 180, covering 10

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

M7B Shikaripura –

Anavatti

Date: 12. 01.2009; Place: Thogarsi;

No. of Participants: 80, covering 9

villages.

Follow up consultations will be

conducted prior to the construction of

annuity project roads.

M7C Anavatti -

Hanagal

Date: 13.01.2009; Place: Hanagal;

No. of Participants: 185, covering 15

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

10A Managuli-

Basavana

bagewadi-

Talikota

Date: 13.11.2008; Place: Huvina

Hipparagi;

No. of Participants: 25, covering 6

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

10B Talikota-

Hunasagi-

Devapur

Date: 13.11.2008; Place: Hunasagi;

No. of Participants: 25, covering 10

villages.

Follow up consultations will be

conducted prior to the start of

construction of annuity project roads.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

18

During the consultations, specific suggestions, issues, and concerns were sought from the local

communities and stakeholders. Some of the issues discussed during consultation process are provision

for parking areas; public comfort station; bus bays; bypasses and realignments; drainage; road user

safety; road side (avenue) tree planting; solid noise barriers to alleviate noise generated from the

traffic near schools and hospitals; provision of foot paths; speed breakers; sign boards; crash

barriers/parapet; dust control measures; proper compensation paid to the PAPs; availability of water

for construction; minimizing tree cutting; compensatory tree plantation and conservation of natural

water sources, etc.

E.8 Analysis of Alternatives:

The objective of this section is to highlight some of the salient issues considered for exercising

options such as “project with alternative”, “project with mitigations” and “no project scenario”. The

alignment alternatives of constituent road links were selected after finalization of these alternatives.

An analysis of various alternatives is attempted to arrive at the technically and

environmentally best-fit alternative. Alternatives in terms of realignments, bypasses, different

cross-section types have been considered to avoid the places of congestion and human settlements,

significant old trees, religious and community assets and environmentally sensitive areas (forest lands,

erosion prone areas, flood regions, etc). KSHIP is an upgradation project of existing State Highways.

No new alignments are being proposed except realignments and bypasses to improve the road

geometrics and avoid congested human settlements. Hence, the scope for project alternatives in terms

of alignment alternatives is limited. There are no bypasses proposed along the EPC project roads.

Similarly alternative route analyses for annuity links were carried. Based on this analysis, three major

shifts in alignments at Huliyardurga (63B), Koratgere (63E) and Madhugiri (64F) have been

proposed.

E.9 Potential Environmental Impacts and Mitigation measures:

Some of the significant environmental impacts of proposed road projects on the natural environment

and nearby communities are discussed in the section. The identified impacts could be largely

mitigated through engineering designs, good construction practices accompanied by a site specific

mitigation measures. Largely these mitigation measures have been made part of civil works contract.

Other mitigation/enhancement measures such construction of solid and vegetative noise barriers

across sensitive receptors and compensatory avenue tree plantation have been suggested for

implementation separately by KSHIP and involving other governmental agencies.

No significant change in the macro-climatic parameters (precipitation, temperature and wind) is

envisaged due to the project but cutting of roadside trees, laying of paved surface and other

construction activities temporarily modify the microclimate. Avenue plantations shall be taken up

under the compensatory plantation programme on either side of the road to counter the indicated

impacts on the physical environment.

There would be an increase in daytime temperature near the newly paved surfaces of the road due to

increase in the surface area of blacktop of widened road. This impact shall be mitigated by planting

rows of avenue plantations.

Surface runoff may be increased due to increase in the paved surface of the project roads overloading

the existing drainage facilities seldom causing floods at low lying areas. Raising of embankment

height and improvement of both longitudinal and cross drainage shall be done to avoid flooding of

flood prone section. Run off water recharge pits shall be constructed to facilitate the infiltration of

runoff water into the ground.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

19

Air quality along the project road alignment, major settlement locations like Hosakote (WEP 1),

Hanagal and Haveri (WEP 2), Dharwad and Saundatti (WEP 3), Devadurga (WEP 4) and Gulbarga

(WEP 5), Malavalli, Maddur, Kunigal, Tumkur and Madhugiri (WAP 1), Mudhol and Chikkodi

(WAP 2), Shimoga and Shikaripura (WAP 3) Talikota (WAP 4) and at construction establishments

(batching plants, hot mix plants, crushers, etc) will be impacted temporarily during construction

activities. To counter the impact on the air quality in the project area asphalt plants, crushers and

batching plants shall be sited at least 1 km in the downwind direction from the nearest human

settlement. Vehicles delivering loose and fine materials like sand and fine aggregates shall be covered

with tarpaulin covers to reduce spills on existing roads. Water shall be sprayed on earthworks,

temporary haulage and detour roads on a regular basis. The hot mix plants will be installed with dust

extraction units and cyclones/scrubbers to reduce exhaust gases.

There will be gradual enhancement of air pollution due to increase in number of vehicles on the

improved roads. Avenue and median plantation along the road sides and medians respectively should

help to control dust and fugitive emissions by operating vehicles from reaching the receptors.

The noise impact due to the project will be of significance both during construction as well as

operation stages. The community abutting project road and construction establishments will be

adversely affected by increase in noise level due to operating equipments and construction activities

of project road. Mitigation measures such as use of enclosures, walls, installation of mufflers around

noisy equipment; substituting quieter equipment or construction methods; timing of noisier

construction and demolition activities; providing Personnel Protective Equipments (PPE) to the

workers; locating construction establishments away from sensitive receptors; construction of noise

barriers at sensitive receptors; etc shall be taken up to reduce the impact of noise.

Soil compaction and contamination is envisaged at construction camps, labour camps, concrete

batching plants, hot mix plants, borrow areas, quarries and along access roads to these construction

establishments. Soil erosion is anticipated at bridge and culvert construction sites. As part of

mitigation measures top soil shall be preserved and back filled after the rehabilitation of

quarry/burrow areas Natural geographical contours and natural landscape shall be preserved and

maintained. If haulage roads are inevitable on productive agricultural land, it shall be reclaimed to the

original nature after the completion of construction activity. All construction establishments such as

construction camps, labour camps, and material storage areas shall be rehabilitated to the original

condition after the completion of construction work.

The major land use in the project area is agriculture and some stretches of the project constitutes built

up areas /settlements having active commercial and economic activity along the roadside. Agricultural

and commercial activities will be disturbed temporarily during construction phase.

Domestic solid waste from construction and labour camps shall be segregated into biodegradable and

non biodegradable before being sent to treatment. Biodegradable wastes are treated by composting

and non biodegradable wastes are either recycled or disposed off to an authorised land fill site.

Untreated waste water from construction camps and labour camps will pollute the surface water

bodies. Liquid wastes generated from the construction camps and labour camps shall be treated to the

prescribed norms before disposal.

There are two tributaries of minor river Tupari (flowing across 21B); two tributaries of major river

Krishna (flowing across 13B) and rivers Dharma and Varada (flowing across M7D & T8 respectively)

are in the impact zone and river Krishna (near 13A road link) is in the influence zone EPC corridors.

There are two minor rivers Varada, Dharma (M7C) and river Dona (10A) in the Impact zone. There

are no major rivers except few canals and other streams in the influence zone of Annuity corridors.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

20

These streams might be temporarily impacted during construction of road embankments, cross

drainage structures and cut and fill activities, by temporary increase in the silt inflow. These impacts

shall be mitigated by constructing cross drainage structures during the lean flow periods of summer;

provision for silt traps at regular intervals, especially at major cross drainage structures to trap the silt

before it reaches the water bodies. Some of the water supply units adjacent to project road within

proposed ROW will be impacted. Water supply resources such as bore wells, taps, water cisterns,

pipelines, etc. being impacted shall be relocated before the construction starts.

Total of 39,607 (EPC - 17,311 and Annuity – 22,296) trees are impacted due to the project and

aproximately 1,66,502 (EPC - 53,718 and Annuity - 1,12,784) avenue trees shall be planted on both

sides of the project roads.

A variety of utilities serving the regional needs like electric poles, electric transformers, telephone

poles, telephone junction boxes which are within impact zone shall be impacted. Some of the religious

structures (such as temples, mosque, church, shrines, arali kattes) and community structures (such as

schools, hospitals, bus shelters, etc.) by the sides of the project roads are impacted directly or

indirectly. Mitigation measures include shifting of all utilities and relocation of religious and

community structures in consultation with the public before the start of construction.

There are several locally important cultural properties – religious as well as community structures that

may be impacted by the project. The project includes adequate measures to ensure that the impacts on

these are managed properly. Chance-find procedures are also included in the contracts to handle any

such situations.

Road project requires materials such as aggregate stone metal, murrum and sand for the construction.

Procuring these materials from stone quarries, borrow pits and sand quarries leaves scars on the land,

increase the soil erosion and leads to loss of productive soil. These impacts shall be mitigated by

suitably rehabilitating the quarries, murrum borrow pits after the extraction of required material is

complete. Quarries shall be opened only after obtaining all the required statutory clearances from the

respective authorities. Borrow area management plan shall be prepared to rehabilitate the borrow pits.

The topsoil in the borrow area shall be stored separately and used to cover the area after rehabilitation.

Sourcing of the sand shall be made from leased sand mines only.

Major or minor accidents are envisaged during construction of roads by lack of knowledge on

handling of new equipments, workers functioning without proper personal protective equipment.

Injuries get worsen if first aid facilities are not there at construction sites. Injuries and accidents to

workers at construction shall be avoided by providing required training on using the equipments and

provision of personal protective equipments along with first aid facilities at construction sites.

Periodical health check-ups shall be arranged for the workers to ensure good health. Preparation and

implementation of road safety plans during project implementation is an important mitigation

measure. Labour camps shall not be located within 1000m of major habitations to avoid outbreak of

communicable diseases. Arrangement for storage and supply of potable water shall be made to the

workers.

It is usual that nearby public and commuting transportation will suffer from inconveniences,

additional time, cost and distance during construction period. Contractor shall prepare Traffic

Management Plan to ensure least interference to the free flow of traffic and local public.

On the positive aspect, the proposed road project will improve the connectivity between urban centers

and nearby rural areas and economic and social wellbeing of rural communities by improved access to

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

21

markets, jobs, education canters and health care services. Tourism in the project area will boost the

local economic activities. Good roads also reduce travel time, fuel consumption and pollutants emitted

by the operating vehicles.

Significant negative and positive impacts due to project are summarized in the following impact

matrix (Table E-11).

Table E-11: Environmental Impact Matrix of the road projects

Environmental Attributes

Physical

Environment

Biological

Environment Geology

Topo-

graphy Air Water Noise Flora Fauna

Natural

Drainage Soil

I. Construction Phase

Labour Camp Activities -ve/t

Quarrying -ve/t -ve/t -ve/t -ve/t -ve/p -ve/p

Material Transport & Storage -ve/t -ve/t -ve/t -ve/t -ve/t -ve/t

Drilling and Blasting -ve/t -ve/t -ve/t -ve/p

Pavement works -ve/t -ve/t -ve/t -ve/t -ve/t -ve/p -ve/t -ve/p

Use of Construction Equipment -ve/t -ve/t -ve/t

Cutting of Trees -ve/p

Plantation +ve/p +ve/p +ve/p +ve/p

Culvert and Bridge Construction -ve/t -ve/t -ve/p

Stripping of Topsoil -ve/t -ve/t -ve/t

Debris Generation -ve/t -ve/t -ve/t -ve/t

Oil and Grease -ve/t -ve/t

II. Operational Phase

Vehicular Movement +ve/p +ve/t +ve/t -ve/p

Note: t – Temporary; p- Permanent; Impacts indicated in bold letters are Significant Impacts.

Summary of environmental impacts for the proposed EPC and annuity project roads are given in the

following Tables E-12, E-13.

Table E-12: Summary of Environmental impacts for EPC project roads

Project road link ID 67A 67B M7D T8 21B 13A 13B 6C

High School (Nos.) 0 0 1 1 0 0 0 1

Primary School (Nos.) 0 0 0 0 1 0 0 0

Temple (Nos.) 3 2 3 1 4 5 4 5

Shrine (Nos.) 2 8 0 3 3 1 0 4

Arali katte (Nos.) 6 5 0 6 2 3 2 5

Bus shelter (Nos.) 3 2 9 8 4 6 8 6

Hand pump (Nos.) 2 0 9 7 1 17 16 6

MWS tank (Nos.) 10 4 4 10 4 7 2 5

Samadhi (Nos.) 0 0 0 0 2 1 1 0

Anganawadi (Nos.) 0 0 0 0 1 0 0 0

Mosque (Nos.) 0 0 1 0 1 0 0 0

Grazing land (Nos.) 0 0 0 0 0 0 0 0

Well (Nos.) 0 0 0 0 0 2 1 0

Hospital (Nos.) 0 0 0 0 0 0 0 0

Others (Nos.)* 12 15 57 47 21 23 20 25

No. of trees to be felled (Nos.)** 1,556 2881 4753 2870 320 1397 1370 2164

Forest land to be acquired (Ha) 0.2400 - 0.6085 0.1316 - - - -

Electric Poles to be shifted (No.) 410 152 370 339 225 249 266 277

Transformers to be shifted (No.) 20 9 18 11 11 4 7 7

Telephone Poles to be shifted (No.) 36 23 28 11 12 1 19 67 * Others include Basement, Bore well, Compound wall, Fence, Flag pole, Govt. Land, Public toilet, Pump house, School

toilet, Water tank, Water tap, Sign board, Grave yard, Statues, APMC check points.

* * No of trees to be felled indicates trees measuring > 30 cm girth. Details of actual trees to be felled will be updated after

joint verification of PIU and Forest Dept.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC and Annuity Packages

and Associated Safeguard Instruments – EPC and Annuity Packages Funded by World Bank

22

Table E-13: Summary of Environmental impacts for annuity project roads

Project road link ID 63A 63B 63C 63D 63E 64F 64G 19A 19B 19C 19D T21 M7A M7B M7C 10A 10B

High School (Nos.) 0 1 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0

Primary School (Nos.) 0 2 0 0 1 1 2 0 1 0 1 0 3 0 0 0 0

Temple (Nos.) 5 5 7 10 5 6 8 9 11 4 0 5 12 7 3 9 6

Shrine (Nos.) 1 2 1 4 0 3 6 1 0 0 4 1 0 0 0 0 0

Arali katte (Nos.) 4 7 7 12 5 7 14 0 2 0 1 3 2 3 0 5 8

Bus shelter (Nos.) 6 6 6 16 5 7 16 1 6 6 10 7 15 8 4 5 13

Hand pump (Nos.) 8 9 10 23 7 5 8 6 19 2 2 10 12 6 11 6 19

MWS tank (Nos.) 8 18 23 35 11 7 11 4 5 4 5 7 3 8 1 2 2

Samadhi (Nos.) 2 1 0 1 0 0 0 0 0 0 0 1 0 0 0 0 0

Anganawadi (Nos.) 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0

Mosque (Nos.) 0 0 0 1 0 1 0 0 0 0 0 2 0 0 0 0 0

Grazing land (Nos.) 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Well (Nos.) 0 1 0 2 0 0 2 0 0 0 0 2 0 0 0 0 0

Hospital (Nos.) 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0

Others (Nos.)* 42 68 39 83 28 30 63 16 21 10 12 21 23 26 15 10 21

No. of trees to be felled (Nos.)** 521 1404 1128 1264 1052 373 755 1194 1823 605 604 918 1939 2433 670 3781 1832

Forest land to be acquired (Ha) No No Yes No No No No No No No No Yes Yes Yes No No No

Electric Poles to be shifted (No.) 389 366 385 629 611 254 460 133 252 160 225 407 562 562 462 117 177

Transformers to be shifted (No.) 33 24 18 46 21 11 34 2 2 2 17 13 42 34 17 0 1

Telephone Poles to be shifted (No.) 49 35 10 51 62 37 47 31 53 31 54 3 73 81 58 22 2 * Others include Basement, Bore well, Compound wall, Fence, Flag pole, Govt. Land, Public toilet, Pump house, School toilet, Water tank, Water tap, Sign board, Grave yard, Statues, APMC

check points.

* * No of trees to be felled indicates trees measuring > 30 cm girth. Details of actual trees to be felled will be updated after joint verification of PIU and Forest Dept.

Summary of impact mitigation measures proposed are given in the following Table E-14.

Table E-14: Summary of proposed Environmental mitigation measures (EPC project roads)

Project

road

link ID

Silt fencing

(No.)

Recharge

pits (No.)

Debris re-

utilisation

(Cum)

Compensatory

tree plantation

(No.)

Noise Barrier

locations

(No.)

Enhancement

of water

bodies (No.)

67A 7 7 5360 4700 6 1

67B 10 10 5200 5780 5 1

M7D 8 8 3060 8692 14 1

T8 13 13 5360 6360 10 1

21B 6 6 6720 7700 5 1

13A 14 14 1920 6490 9 -

13B 17 17 4720 8270 9 1

6C 18 18 2000 5726 8 -

Total 93 93 34340 53718 66 6

Table E-15: Summary of proposed Environmental mitigation measures (Annuity project roads)

Project

road

link ID

Silt fencing

(No.)

Recharge

pits (No.)

Debris re-

utilisation

(Cum)

Compensatory

tree plantation

(No.)

Noise Barrier

locations

(No.)

Enhancement

of water

bodies (No.)

63A 15 15 1,013 4,560 10 1

63B 18 18 1,125 5,506 10 1

63C 9 9 478 4,222 9 1

63D 15 15 1,181 7,003 17 1

63E 11 11 1,238 5,579 8 1

64F 9 9 759 4,005 5 1

64G 18 18 1,041 7,596 19 1

19A 9 9 422 3,834 8 -

19B 16 16 1,041 8,468 9 -

19C 8 8 506 3,682 6 1

19D 32 32 816 5,601 6 -

T21 11 11 422 6,448 11 1

M7A 18 18 1,013 9,959 14 1

M7B 16 16 1,097 9,082 21 1

M7C 12 12 675 5,243 12 1

10A 19 19 984 12,260 7 -

10B 16 16 928 9,730 4 -

Total 252 252 14,739 112,778 176 12

Construction of solid noise barriers

Construction of solid noise barriers for identified sensitive noise receptors for road links

under all EPC and Annuity contract packages is in progress – procured under local shopping

procedures (Figure E-2). These noise barriers serve as the mitigation measure for the

anticipated increase in ambient noise and the transmission of dust towards the sensitive

receptor, not only for the operation phase but also during construction phase of the project.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity packages

and Associated Safeguard Instruments – EPC Packages Funded by World Bank

24

Figure E-2: Pictures showing completed solid noise barriers on proposed EPC project roads

Solid noise barrier under construction for a hospital building on road link 21

Solid noise barrier constructed for a Govt. School on road link 21

Solid noise barrier under construction for a Govt. School on road link M7D

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity packages

and Associated Safeguard Instruments – EPC Packages Funded by World Bank

25

E.10 Summary of Resettlement and Rehabilitation (R&R):

The GOK will adopt a R&R Policy for KSHIP II to address the adverse social impacts of the project

on the line of National Policy of Resettlement and Rehabilitation 2007. The policy adopted is

consistent with the World Bank‟s Involuntary Resettlement Policy. The Resettlement Action Plan

(RAP) is prepared in accordance with the stipulations and guidelines provided in Karnataka Public

Works Departmental Code; Resettlement and Rehabilitation - Principles and Policy Framework for

the Karnataka State Highways Improvement Project; The National Resettlement Policy, 2007 and the

World Bank‟s Operational Policy 4.12.

Census socio- economic surveys were conducted on the up-gradation roads, for a Corridor of Impact

between 16 m and 22 m keeping in view the design requirements. The matrix depicting the summary

of impacts is as follows.

Table E-16 Summary of Impacts

Contract

Package

Land

Acquisition-

Private (ha)

Land Transfer

– Government

(ha)

Major

Impact

- PAFs

Minor

impact

- PAFs

Community

Assets

(Nos)

PAFs PAPs

WEP1 0.82 0.26 28 44 74 72 337

WEP2 25.56 3.03 85 688 168 773 4695

WEP3 4.38 0.36 32 147 44 179 997

WEP4 0.08 0 147 65 117 212 715

WEP5 1.12 0 28 26 57 54 301

WAP1 78.43 5.68 349 406 736 755* 3349

WAP2 33.42 0 343 130 165 473* 1690

WAP3 70.35 0 215 325 223 540* 1706

WAP4 1.77 0.03 249 106 106 355 1174

TOTAL 215.93 9.36 1476 1937 1690 3413 14964

* Include estimate for land losers and actual for structure losers.

KPWD, GOK has decided to acquire the land under the Karnataka Highways Act, 1964. The GOK

has already initiated the process of establishing the Negotiation Committee to negotiate the price of

land with the beneficiaries on the basis of guidance value for the land.

Some of the entitlements include payment of compensation through negotiation according to the

KHA; additional assistance for those becoming marginal farmers; eligibility of bagar hukum land

losers; grant for replacement of cattle shed; alternative house or developed plot including construction

cost for those losing house; additional 25% compensation for partially affected structures towards

reconstruction; income generating assets up to Rs.75,000 for those losing commercial structures;

rental allowance for tenants; non-titleholders to get alternate house or developed plot + construction

cost, for commercial structures alternate shop or income generating asset; employees losing livelihood

will be given a one time payment; vulnerable groups including physically challenged and those above

60 years will be given a lump sum amount as assistance; and all community assets will be replaced

and reconstructed.

The RAP will be implemented by Karnataka PWD-PIU Social Development Resettlement Cell with

the support of NGOs. The Special DC, LA will be responsible for land acquisition activities and the

Chief Administrative Officer will be responsible for all resettlement and rehabilitation works. A

grievance redressal cell will be constituted for registering and addressing complaints including appeal

mechanisms. The RAP provides the implementation schedule which is linked to the commencement

of civil works. The RAP will be implemented over a period of 3 years starting from the date of

approval. The estimated total budget for the implementation of RAP is Rs. 147.83 Crore.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity packages

and Associated Safeguard Instruments – EPC Packages Funded by World Bank

26

E.11 Environmental Management Plan:

Environmental Management Plan (EMP) deals with the implementation procedure of the guidelines

and mitigation measures recommended to avoid, minimize and mitigate foreseen environmental

impacts of the project. The implementation of environmental management plan needs a suitable

organization set up and the success of any environmental management plan depends on the efficiency

of the group responsible for implementation of the programme. It is proposed to carryout regular

environmental monitoring to provide information to the management for periodic review and

alternation of the environmental management plan as necessary so as to ensure that environmental

protection is optimized at all stages of the project implementation. Link wise Environmental

Management Plans have been prepared for both EPC and annuity links. For annuity links,

Concessionaire will prepare EMPs incorporating the proposed design changes and corresponding

environmental management and mitigation measures for the identified impacts.

Environmental monitoring is an essential component for sustainability of any developmental project.

It is an integral part of any environmental assessment process. The monitoring programme consists of

performance indicators, reporting formats and necessary budgetary provision. For each of the

environmental condition indicators, the monitoring plan specifies the parameters to be monitored,

location of the monitoring sites, frequency and duration of monitoring. The monitoring plan also

specifies the applicable standards, implementation and supervising responsibilities. The monitoring

will be carried out by PIU through the approved agency and will be supervised by the Environmental

Experts of the Construction Supervision Consultants and PIU.

Environmental Management Plan Implementation Unit (EMPIU) established under KSHIP I has been

continued for KSHIP II. This EMPIU with the assistance of the Environmental Specialist of Project

Design and Environmental Officer (EO) of the CSC (for EPC) and Independent Engineer (for

annuity) will be responsible for implementing all environmental monitoring and management works

and ensure that all statutory requirements are met during the project implementation. Organizational

setup for PIU and EMPIU is illustrated in the Figure E.2.

The engineering staff of PIU, Construction Supervision Consultancy (for the EPC contracts),

Independent Engineer (for the Annuity concessions) and the contractor/concessionaire who would be

responsible for the implementation of the EMP, need to be trained on environmental issues of specific

road development project. Looking into the potential requirements of each of the target groups,

several training modules have been planned. The training would cover the basic principles and

postulates of environmental assessment and mitigation plans; implementation techniques; monitoring

and management methods and tools.

The budgetary provision for the implementing EMP of the road project has been made in 2 parts

based on responsibility for the execution.

The Part „A‟ works to be undertaken has been quantified and quantities included in the respective

BOQ items in the civil works contract packages. These cover items such as safe disposal of

unserviceable materials with suitable top soil treatment; dust mitigation during construction phase;

recharge pits; silt fencing; sign boards for tourist and ecologically sensitive areas if any; safe disposal

of scarified bitumen in clay lined pits; construction of noise barriers for silent receptors; monitoring of

air, water, noise and soil characteristics; provision of oil interceptors; provision of personal protective

equipments for labourers; provision for two health checkup; utilisation of unserviceable material and

enhancement of roadside water bodies.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity packages

and Associated Safeguard Instruments – EPC Packages Funded by World Bank

27

Part „B‟ works of redevelopment of oxbow lands and other leftover lands; raising median plantations;

compensatory plantation; compensatory provisions in terms of Net Present Value (NPV) for diverted

forest lands, if any; providing environmental management training at all levels are discussed under

mandatory works to be implemented by Government Departments or other agencies as per the

regulatory requirements.

In addition to the above, water bodies (max. of one per link) along the project roads both under EPC

and EPA will be developed.

Cost for Part A & B works of EMP implementation are estimated and given in the Table E-17.

Table E-17: Estimated cost of EMP implementation.

Link

ID Name of the road

Length

(km)

Estimated cost for EMP

execution (Crores)

Part A Part B Total

EPC Project roads

67A Hoskote – H (Hindgnala) Cross 23.50 1.33 0.71 2.04

67B H Cross - Chinatmani Bypass (cor 65 F –Jn) 28.90 1.73 0.94 2.67

M7D Hanagal – Tadasa 43.46 1.22 1.15 2.37

T8 Haveri (NH-4) – Hangal 31.80 1.90 1.05 2.95

21B Dharwad – Saundatti 38.50 1.76 0.71 2.47

13A Thinthini – Chinchodi – Jalhalli – Devadurga 32.45 1.16 0.82 1.98

13B Devadurga – Masarkal – Gabbur – Kalmala 41.35 1.28 0.91 2.19

6C Chowdapur – Gulbarga 28.63 1.02 0.96 1.98

Total EMP cost in Crores 268.59 11.4 7.25 18.65

Annuity Project roads

63A Malavalli – Maddur 22.803 1.29 0.52 1.81

63B Maddur – Huliyurdurga 27.531 1.82 0.71 2.53

63C Huliyurdurga – Kunigal 21.113 1.62 0.58 2.20

63D Kunigal – Tumkur 35.017 1.85 0.81 2.66

63E Tumkur – Koratagere 27.897 1.32 0.66 1.98

64F Koratagere – Madhugiri 20.027 0.87 0.45 1.32

64G Madhugiri - Pavagada 37.980 2.68 0.73 3.41

19A Mudhol - Mahalingapura 19.170 0.65 0.56 1.21

19B Mahalingapura - Kabbur 42.344 1.18 0.98 2.16

19C Kabbur - Chikodi 18.414 1.04 0.47 1.51

19D Chikkodi - Nippani (NH4) – MH Border 28.009 1.18 0.60 1.78

T21 Shikaripura - Anandapuram (NH206) 32.241 2.94 1.84 4.78

M7A Shimoga - Shikaripura 49.795 3.23 1.42 4.65

M7B Shikaripura - Anavatti 45.414 3.47 1.15 4.62

M7C Anavatti - Hanagal 26.215 1.82 0.59 2.41

10A Managuli - Basavana Bagewadi - Talikota 61.300 1.54 1.53 3.07

10B Talikota - Hunasagi - Devapur 48.653 1.01 1.07 2.08

Total EMP cost in Crores 563.923 29.51 14.67 44.18

E.12 EMP Implementation

Details of various mitigation measures to be implemented during Pre-construction,

construction and operational phases for a general EPC are presented in the EMAP Table E-

18. In case of Annuity packages the EMP will be supervised by Independent Engineer.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity packages

and Associated Safeguard Instruments – EPC Packages Funded by World Bank

28

E.12 Conclusion:

The up-gradation of existing State Highways, involves less significant environmental impacts and

most of these adverse impacts of road project are temporary and local in nature. Most of these impacts

can be minimized through engineering solutions incorporated into the project design and by

implementing adequate and timely mitigation measures as included in the Environmental

Management Plan. Therefore the overall findings of the EIA are that the proposed improvement to

above mentioned roads are unlikely to cause significant adverse environmental impacts.

Further, Environmental Impact Assessment and Environmental Management Plans for EPC and

Annuity projects are being reviewed by independent reviewer as a part of World Bank‟s requirement.

The review for EPC contract packages is about to be completed and for Annuity packages the review

is in progress. The comments from the independent reviewer will be addressed and incorporated in the

respective reports.

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

29

Table E- 18: ENVIRONMENTAL MANAGEMENT ACTION PLAN

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

PRE-CONSTRUCTION STAGE

Pre-construction activities by Karnataka state Highways Improvement Project (KSHIP)

P 1 Land Acquisition

(If required)

The acquisition of land and private properties shall be carried out in accordance

with the RAP and entitlement framework of the Project.

KSHIP has to ascertain that acquisition of land in the post design phase are

addressed and integrated into the EMP and relevant contract documents.

Karnataka State

Highways Act

1964

KSHIP,

Revenue Dept,

Collaborating

Agencies

KSHIP

P 2

Clearance of

Encroachment/Squa

tters (change in land

use)

Advance notice, as per RAP shall be given to the encroachers & squatters present

in the Corridor of Impact, who need to be relocated. All R&R activities shall be

undertaken. Entitlements as per KSHIP entitlement framework shall be completed

before construction starts.

RAP documents

KSHIP and

Revenue

Authority

KSHIP

P 3 Tree Cutting

Trees shall be removed from the Corridor of Impact before the actual

commencement of the work with the permission from the state Forest Department.

Cutting shall not start until the implementation of the project in that particular

location of cutting 100% confirmed.

Stacking, transport and storage of the wood shall be done as per the relevant

norms.

MoRTH 201.6

Contractor/Age

ncy engaged by

KSHIP

CSC and /

KSHIP

P 4 Preservation of

Trees

All efforts shall be made to preserve trees including evaluation of minor design

adjustments/alternatives (as applicable) to save trees. Specific attention shall be

given for protecting giant trees, green tunnels and locally important trees

(religiously important etc.). Detail of the trees affected due to the proposed project

road in given in (Appendix – 10)

Tree cutting is to proceed only after all the legal requirements including attaining

of In-principle and Formal Clearances form the Forest Dept./MoEF are completed

and subsequently a written order is issued to the Contractor.

Particular species declared as “protected” by the State‟s Forest Dept. in the private

land shall be felled only after due clearance from the Forest Dept. is obtained.

In the event of design changes, additional assessments including the possibility to

save trees shall be made.

Systematic corridor level documentation for the trees cut and those saved shall be

maintained by the KSHIP

Appendix-10

Contractor/Age

ncy engaged by

KSHIP

CSC and /

KSHIP

P 5

Relocation of

Community

Utilities and

All community utilities and properties i.e., hand pumps, open wells, water supply

lines, sewer lines, telephone cables, buildings and health centers shall not be

relocated before construction starts in the project road. Details of the community

RAP document

KSHIP, other

Agencies /

Contractor

KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

30

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Common Property

Resources

properties affected are provided in Chapter-2 Summary of Impacts.

P 6

Relocation of

affected Cultural

and Religious

Properties

All religious property resources such as shrines, temples and mosques within the

project road shall relocated. A list of cultural properties affected is given in the

Chapter-2 Summary of Impacts.

If there is any relocation of the religious structures may happen then it shall be

identified in accordance with the choice of the community. KSHIP in consultation

with local people shall finalize those.

The entire process (i.e. selection of relocation sites and design) shall be under

supervision of Environmental Specialist of CSC, during the construction stage by

the Contractor. The relocation shall be completed before the construction starts in

these sites.

Chapter-2

Summary of

Impacts

KSHIP/

Contractor

CSC/

KSHIP

Pre-construction activities by the Contractor/Environmental Specialist of CSC

P 7 Field Verification and Modification of the Contract Documents

P.7.1 Joint Field

Verification

The Environmental Specialist of CSC and the Contractor shall carry out joint field

verification to ascertain any possibilities of saving trees, environmental and

community resources, & these activities are to be taken up by the construction

Contractor.

Contractor/

Environmental

Specialist of

CSC

KSHIP

P.7.2

Assessment of

Impacts due to

Changes/Revisions/

Additions in the

Project Work

The Environmental Specialist of CSC shall assess impacts and revise/modify the

EMP and other required sections of the project document/s in the event of

changes/revisions (including addition or deletion) in the project‟s scope of work.

Contractor/

Environmental

Specialist of

CSC

KSHIP

P.7.3

Crushers, Hot-mix

plants and Batching

Plants Location

All construction plants shall be sited sufficiently away from settlements and

agricultural operations or any commercial establishments. Such plants shall be

located at least 100m away from the nearest dwelling preferably in the downwind

direction.

The Contractor shall submit a detailed layout plan for all such sites and approval of

Environmental Specialist of CSC shall be necessary prior to the establishment.

Arrangements to control dust pollution through provision of windscreens, water

sprinklers, and dust extraction systems shall have to be provided at all such sites.

Specifications for crushers, hot mix plants and batching plants shall comply with

the requirements of the relevant emission control legislations. Consent for the

Establishment and Operation from KSPCB shall be obtained before establishment

and operation respectively and a copy should be submitted to the CSC and KSHIP.

MoRTH 111.1,

Air Pollution

Control Act, and

Noise Rules

Contractor/

Environmental

Specialist of

CSC

KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

31

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Wherever there is extremely water scarcity areas exist the Water sprinkling shall be

limited to one time in the morning. To balance this deficient information boards

shall be erected at appropriate locations with a message to “Dust prone area take

precautions.

P.7.4

Other Construction

Vehicles,

Equipment and

Machinery

All vehicles, equipment and machinery to be procured for construction shall

confirm to the relevant Bureau of India Standard (BIS) norms. The discharge

standards promulgated under the Environment Protection Act, 1986 and Motor

Vehicles Act, 1988 shall be strictly adhered to.

The silent/quiet equipment available in the market shall be used in the Project.

The Contractor shall maintain a record of PUC for all vehicles and machinery used

during the contract period which shall be produced to EO, KSHIP /PWD‟s

verification whenever required.

Air pollution

Control Act, and

Noise Rules and

Motor Vehicle

Act, 1988

Contractor/

Environmental

Specialist of

CSC

KSHIP

P 8 Identification and Selection of Material Sources

P.8.1 Borrow Areas

Finalizing soil borrowing earth and all logistic arrangements as well as compliance

to environmental requirements, as applicable, shall be the sole responsibility of the

Contractor. (Appendix-17).

The Contractor shall not start borrowing earth from selected borrow area until the

formal agreement is signed between landowner and Contractor and a copy is

submitted to the CSC.

Locations finalized by the Contractor shall be reported to the Environmental

Specialist of CSC and he shall submit the report to KSHIP.

Planning of haul roads for accessing borrows areas shall be undertaken during this

stage. The haul roads shall be routed to avoid agricultural areas as far as possible

and shall use the existing village roads wherever available.

The environmental personnel of the CSC shall be required to inspect every borrow

area location prior to approval. The CSC should include the Request for Inspection

form for borrow area approval from the environmental point of view.

Appendix-16, 17

Contractor/

Environmental

Specialist of

CSC

KSHIP

P.8.2 Quarry

Contractor shall finalize the quarry for procurement of construction materials after

assessment of the availability of sufficient quantity of materials, quality and other

logistic arrangements.

In case the Contractor decides to use quarries other than recommended by DPR

consultant, then the Contractor should give substantiation.

Contractor shall also work out haul road network and report to Environmental

Specialist of CSC and CSC shall inspect and in turn report to KSHIP before

MoRTH 111.3 &

Appendix-17, 19

Contractor

Environmental

Specialist of

CSC

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

32

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

approval.

P.8.3 Arrangement for

Construction Water

In view of the special situation in Karnataka, Contractor shall prepare and

implement the approved Water Management Plan in accordance with the

Appendix-16, Appendix-24 and BOQ Environment mitigation works

The contractor shall use ground/surface water as a source of water for the

construction and may set up own bore well facility for construction work.

Contractor may take surface water from the Irrigation Canal with the written

consent from the Irrigation Department.

To avoid disruption/disturbance to other water users, the Contractor shall extract

water from fixed locations and consult Environmental Specialist of CSC before

finalizing the locations.

The Contractor shall provide a list of locations and type of sources from where

water for construction shall be extracted.

The Contractor shall need to comply with the requirements of the State Ground

Water Department for the extraction and seek their approval for doing so and

submit copies of the permission to CSC and KSHIP.

Appendix-15 and

Appendix-16 Contractor

Environmental

Specialist of

CSC

P 9 Sand

The Sand shall be procured from identified sand mines as far as possible. If the

Contractor want to obtain from source other than listed in EMP, substitution shall

be provided. has the details of the aggregates source and lead distance.

The Contractor shall obtain copy of the Lease Agreement of the supplier and

submit to CSC before procuring the sand.

Chapter-2

Summary of

Impacts

All riverbeds

recommended

for sand

extraction for

the project.

P 10 Labour

Requirements

The Contractor preferably shall use unskilled labour drawn from local communities

to give maximum benefits to the local community. Copy of Contract

Document Contractor

Environmental

Specialist of

CSC

P 11

Construction Camp

Locations –

Selection, Design

and Layout

Siting of the construction camps shall be as per the guidelines below and details of

layout to be approved by CSC Resident Engineer and environment specialist.

Construction camps shall not be proposed within 500m from the nearest

settlements to avoid conflicts and stress over the infrastructure facilities with the

local community.

Location for stockyards for construction materials shall be identified at least 300m

away from watercourses.

The sewage TP and solid waste treatment for the camp shall be designed, built and

operated.

Contractor‟s camps shall be identified at least 2km away from the Forest Reserves.

Appendix-13, 21 Contractor

Environmental

Specialist of

CSC

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

33

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

P 12

Arrangements for

Temporary Land

Requirement

The Contractor as per prevalent rules shall carry out negotiations with the

landowners for obtaining their consent for temporary use of lands for construction

camp/construction/borrow areas etc.

Temporary land arrangements shall not be from the forest reserves except under

special permission circumstances where it is un avoidable due to the vast forest

reserves in the PIA.

Appendix-13, 16,

17 Contractor

Environmental

Specialist of

CSC

P 13

Orientation of

Implementing

Agency and

Contractors

The KSHIP shall organize Orientation Sessions and regular training sessions at all

stages of the project. This shall include on-site training (general as well as in the

specific context of a sub-project). These sessions shall involve all staff of KSHIP

involved in the implementation of EMP, Environmental Specialists of CSC and

Contractors.

EMP and other

training plan

developed by

KSHIP

Contractor/

CSC and

KSHIP

KSHIP

CONSTRUCTION STAGE

Activities to be Carried Out by the Contractor

C 1 Site Clearance

C.1.1 Clearing and

Grubbing

If required vegetation shall be removed from the construction zone before

commencement of construction. All works shall be carried out such that the

damage or disruption of flora other than those identified for cutting is minimum.

Only ground cover/shrubs that impinge directly on the permanent works or

necessary temporary works shall be removed with prior approval from the

Environmental Expert of CSC.

The Contractor, under any circumstances shall not cut or damage trees and forest

reserves (refer Appendix-13). Trees identified under the project shall be cut only

after receiving clearance from the Forest Dept./DoEF/MoEF (as applicable) and

after the receipt of KSHIP‟s written permission in this regard.

Vegetation only with girth size of over 30 cm shall be considered as trees and shall

be compensated, in the event of KSHIP‟s instruction to undertake tree cutting.

MoRTH 201 &

Appendix-10, 20 Contractor

Environmental

Specialist of

CSC, KSHIP

C.1.2

Disposal of Debris

from dismantling

structures, road

surface and hill

ward side

excavation for

widening of the

road

Appendix-1 provides guidelines for the preparation of the contractors Debris

disposal plan. This is mainly to deal with surplus debris materials that would be

available after adjusting for all insitu applications.

Other debris generated due to dismantling of the existing road shall be suitably

reused in the proposed construction zone, subjected to the structure suitability of

the materials and approval of the Resident Engineer and Environmental Expert of

CSC as follows:

For filling and leveling of School grounds and proposed parking areas.

The sub grade of the existing pavement shall be used as embankment fill material.

MoRTH 202

Appendix-1 Contractor

Environmental

Specialist and

Resident

Engineer of

CSC, EC,

KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

34

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Existing base and sub-base material shall be recycled as sub-base of the haul road

or access roads.

The existing bitumen surface may be utilized for the paving of cross roads, access

roads and paving works in construction sites and campus, temporary traffic

diversions, haulage routes etc.

The Contractor shall suitably dispose off unutilized debris materials either through

filling up of borrows areas located in wasteland or at pre-designated disposal

locations, subject to the approval of the Environmental Expert of CSC.

At locations identified for disposal of bituminous wastes, the disposal shall be

carried out over a 30 mm thick layer of rammed clay so as to eliminate the

possibility of scarified percolation of leachate into the ground water. The

Contractor shall ensure that the surface area of such disposal pits is covered with a

layer of soil & subsequent turfing.

All arrangements for transportation during construction including provision,

maintenance, dismantling and clearing debris, shall be considered incidental to the

work and shall be planned and implemented by the Contractor as approved and

directed by the Environmental Expert of CSC.

The pre-designed disposal locations shall be a part of Waste Disposal Plan in

consultation and with approval of Environmental Expert of CSC.

Debris generated from pile driving or other construction activities shall be

disposed such that it does not flow into the surface water bodies or for mud

puddles in the area.

The Contractor shall identify dumping sites as per the Debris Disposal Plan

prepared using the Guidelines provided in the Appendix 1; The identified locations

shall be reported to the Environmental Expert of CSC. These locations shall be

checked on site and accordingly approved by Environmental Expert of CSC prior

to any disposal of waste materials.

C.1.3 Other Construction

Wastes Disposal

The pre-identified disposal location shall be part of Comprehensive Waste

Disposal Plan Solid Waste Management Plan to be prepared by the Contractor in

consultation and with approval of Environmental Specialist of CSC.

Location of disposal sites shall be finalized prior to initiation of the works on any

particular section of the road.

The Environmental Specialist of CSC shall approve these disposal sites after

conducting a joint inspection on the site with the Contractor.

Contractor shall of ensure that any spoils or material unsuitable for embankment

fill shall not be disposed off near any water course or agricultural land, Orchards

MoRTH:202.5

MoRTH:301.11

(Apendix-1)

Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

35

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

and Natural Habitats like Grasslands. Such spoils from excavation can be used to

reclaim borrow pits and low-lying areas located in barren lands along the project

road (if it so desired by the owner/community and approved by the Environmental

Specialist, CSC).

Non-bituminous wastes shall be dumped in borrow pits covered with a layer of

30cm soil to ensure that borrow pit is restored to original use. No new disposal site

shall be created as part of the project, except with prior approval of the

Environmental Specialist of CSC.

All waste materials shall be completely disposed and the site shall be completely

cleaned and certified by Environmental Specialist of CSC before handing over.

The Contractor at his cost shall resolve any claim, arising out of waste disposal or

any non-compliance that may arise on account of lack of action on his part.

C.1.4

Stripping, stocking

and preservation of

top soil

The topsoil from all areas of cutting and all areas to be permanently covered shall

be stripped off to a specified depth of 150 mm and stored in stockpiles. A portion

of the temporarily acquired area and/or Right of Way shall be earmarked for

storing topsoil. The locations for stock piling shall be pre-identified in consultation

and with approval of Environmental Specialist of CSC. The following

precautionary measures shall be taken to preserve them till they are used:

(a) Stockpile shall be designed such that the slope does not exceed

1:2(Vertical to horizontal), and height of the pile is restricted to 2 m.

To Retain soil and to allow percolation of water, silt fencing shall protect

the edges of the pile.

(b) Stockpiles shall not be surcharged or otherwise loaded and multiple

handling shall be kept to a minimum to ensure that no compaction shall

occur. The stockpiles shall be covered with gunny bags or vegetation.

(c) It shall be ensured by the Contractor that the topsoil shall not be

unnecessarily trafficked either before stripping or when in stockpiles.

Such stockpiled topsoil shall be utilized for –

Covering all disturbed areas including borrow areas, only in

case where they are to be rehabilitated.

Dressing of slopes of road embankment > Agricultural fields of

farmers acquired temporarily land.

MoRTH:301.3.2

MoRTH:301.7

MoRTH:305.3.3

and

MoRTH:305.3.9

Contractor

Environmental

Specialist of

CSC, KSHIP

C.1.5 Accessibility

The Contractor shall provide safe and convenient passage for vehicles, pedestrians

and livestock to and from roadsides and property access connecting the project

road, providing temporary connecting road.

Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

36

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

The Contractor shall also ensure that the existing accesses shall not be undertaken

without providing adequate provisions.

The Contractor shall take care that the cross roads are constructed in such a

sequence that construction work on the adjacent cross roads are taken up one after

one so that traffic movement in any given area not get affected much.

C.1.6

Planning for Traffic

Diversions And

Detours

Temporary diversions shall be constructed with the approval of the Resident

Engineer and Environmental Specialist of CSC. Detailed Traffic Control Plans

shall be prepared by the Contractor and approved by Environmental Specialist and

Resident Engineer of CSC for approval, seven days prior to commencement of

works on any section of road. The Traffic Control Plans shall contain details of

temporary diversions, traffic safety arrangements for construction under traffic,

details of traffic arrangement after cessation of work each day, safety measures for

night time traffic and precaution for transportation of hazardous materials and

arrangement of flagmen.

The contractor shall ensure that the diversion/detour is always maintained in

running condition, particularly during the monsoon to avoid disruption to traffic

flow.

The Contractor shall also inform local community of changes to traffic routes,

conditions and pedestrian access arrangements with assistance form CSC and

KSHIP. The temporary traffic detours shall be kept free of dust by sprinkling of

water three times a day and as required under specific conditions (depending on

weather conditions, construction in the settlement areas and volume of traffic).

MoRTH:112 and

its Amendments

(Appendix-14)

Contractor

Environmental

Specialist and

Resident

Engineer of

CSC, EO,

KSHIPF

C.2 Procurement of Construction Material

C.2.1

Earth from Borrow

Areas for

Construction

No borrow area shall be opened without permission of the Environmental

Specialist of CSC. The location, shape and size of the designated borrow areas

shall be as approved by the Environmental Specialist of CSC and in accordance to

the IRC recommended practice for borrow pits for road embankments (IRC: 10:

1961). The borrowing operations shall be carried out as specified in the guidelines

for siting and operation of borrow areas.

The unpaved surfaces used for the haulage of borrow materials, if passing through

the settlement areas or habitations; shall be maintained dust free by the Contractor.

Sprinkling of water shall be carried out twice a day to control dust along such

roads during their period of use.

During dry seasons (winter and summer) frequency of water sprinkling shall be

increased in the settlement areas and Environmental Specialist of CSC shall decide

MoRTH:305.2

(Appendix-16 and

17)

Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

37

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

the sprinkling time depending on the local requirements.

Contractor shall rehabilitate the borrow areas as soon as borrowing of soil is over

from a particular borrow area in accordance with the approved Borrow Area

Redevelopment Plan.

C.2.2 Quarry Operations

Crushers

The Contractor shall obtain materials from quarries only after consent of the

Department of Mines & Geology and District Administration. In view of special

situation of excavation of the ward hill side, Contractor shall get an opportunity to

use the same material for road construction. This shall require establishment of a

number of crushers along the roadsides. The crushers and all related activities shall

be under taken as per the Appendix-19 Policy guidelines for installation of stone

Crushers.

MoRTH: 111.3

Appendix-19 Contractor

Environmental

Specialist of

CSC, KSHIP

C.2.3 Blasting

Except as may be provided in the contract or ordered or authorized by the

Engineer, the Contractor shall not use explosives.

Where the use of explosives is so provided or ordered or authorized, the

Contractor shall comply with the requirements of the following Sub-Clauses of

MoRTH 302 besides the law of the land as applicable.

The Contractor shall at all times take every possible precaution and shall comply

with appropriate laws and regulations relating to the importation, handling,

transportation, storage and use of explosives. The contractor shall at all times

when engaged in blasting operations, post sufficient warning flagmen, to the full

satisfaction of the Engineer.

The Contractor shall at all times make full liaison with and inform well in advance

and obtain such permission as is required from all Government Authorities, public

bodies and private parties whomsoever concerned or affected or likely to be

concerned or affected by blasting operations.

Blasting shall be carried out only with permission of the Engineer. All the

statutory laws, regulations, rules etc., pertaining to acquisition, transport, storage,

handling and use of explosives shall be strictly followed.

Blasting shall be carried out during fixed hours (preferably during mid-day) or as

permitted by the Engineer. The timing should be made known to all the people

within 1000m (200m for pre-splitting) from the blasting site in all directions.

Appendix-19 MoRTH:302.4 301.9 (i)

304.5

C.2.4

Transporting

Constructing

Materials and Haul

Road Management

Contractor shall maintain all roads (existing or built for the project), which are

used for transporting construction materials, equipment and machineries as

précised. All vehicles delivering fine materials to the site shall be covered to avoid

spillage of materials.

Appendix-16 Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

38

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

All existing roads used by vehicles of the Contractor or any of his subcontractor or

suppliers of materials and similarly roads, which are part of the works, shall be

kept clear of all dust/mud or other extraneous materials dropped by such vehicles.

Contractor shall arrange for regular water sprinkling as necessary for dust

suppression of all such roads and surfaces.

C.2.5 Construction Water

Contractor need to implement the finally approved contractors Construction Water

Management Plan as per the guidelines provided in Appendix 15. This is linked to

the contractor‟s work plan.

Contractor shall arrange adequate supply and storage of water for the whole

construction period at his own cost. The contractor shall submit a list of source/s

from where water shall be used for the project to CSC and KSHIP.

The Contractor shall source the requirement of water preferentially by conjuctive

use of Surface water and groundwater but with prior permission from the

Groundwater Authority. A copy of the permission shall be submitted to CSC and

KSHIP prior to initiation of construction.

The Contractor shall take all precaution to minimize the wastage of water in the

construction process/operation.

Appendix-15 Contractor

Environmental

Specialist of

CSC, KSHIP

C.3 Construction Work

C.3.1

River Training and

Disruption to Other

Users of Water

While working across or close to any perennial water bodies, Contractor shall not

obstruct/prevent the flow of water.

Construction over and close to the non-perennial streams shall be undertaken in

the dry season. If construction work is expected to disrupt users of community

water bodies, notice shall be served well in advance to the affected community.

MoRTH:304.3.2 Contractor

Environmental

Specialist of

CSC, KSHIP

C.3.2 Drainage and Flood

Control

Contractor shall ensure that no construction materials like earth, stone, or

appendage disposed off in a manner that block the flow of water of any water

course and cross drainage channels.

Contractor shall take all necessary measures to prevent any blockage to the water

flow. In addition to the design requirements, the Contractor shall take all required

measures as directed by the Environmental Specialist of CSC to prevent temporary

or permanent flooding of the site or any adjacent area.

MoRTH:305.3.7

MoRTH:306

Appendix 1

Contractor

Environmental

Specialist of

CSC, KSHIP

C.3.3

Siltation of Water

Bodies and

Degradation of

Water Quality

The Contractor shall not excavate beds of any stream/canals/any other water body

for borrowing earth for embankment construction.

Contractor shall construct silt fencing at the base of the embankment construction

for the entire perimeter of any water body (including springs and wells) adjacent to

the project road and around the stockpiles at the construction sites including

MoRTH:306

(Silt Fencing)

Appendix-3

Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

39

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

ancillary sites close to water bodies. The fencing shall be provided prior to

commencement of earthwork and continue till the stabilization of the embankment

slopes, on the particular sub-section of the road.

Contractor shall ensure that construction materials containing fine particles are

stored in an enclosure such that sediment-laden water does not drain into nearby

watercourse.

C.3.4

Slope Protection

and Control of Soil

Erosion

The Contractor shall construct slope Protection works as per design, or as directed

by the Environmental Specialist of CSC to control soil erosion and sedimentation

through use of Breast walls, Retaining Walls, Plot Bioengineering methods, dykes,

sedimentation chambers, basins, fibber mats, mulches, grasses, slope, drains and

other devices.

All temporary sedimentation, pollution control works and maintenance thereof

shall be deemed as incidental to the earth work or other items of work and as such

no separate payment shall be made for them.

Contractor shall ensure the following aspects:

After construction of road embankment, the side slopes shall be covered with

grass and shrubs (refer Appendix-10 and 18) as per design specifications.

Turfing works shall be taken up as soon as possible provided the season is

favorable for the establishment of grass sods. Other measures of slope

stabilization shall include mulching netting and seeding of batters and drains

immediately on completion of earthworks.

In borrow pits, the depth shall be so regulated that the sides of the excavation

shall have a slope no steeper than 1 vertical to 2 horizontal, from the edge of

the final section of the bank.

Along sections abutting water bodies, pitching as per design specification

shall protect slopes.

MoRTH:305.2.2.2

MoRTH:306.2

& Appendix 10

and 18

Contractor

Environmental

Specialist of

CSC, KSHIP

C.4 Pollution

C.4.1 Water Pollution

C.4.1.1

Water Pollution

from Construction

Wastes

The Contractor shall take all precautionary measures to prevent entering of

wastewater into streams, water bodies or the irrigation system during construction.

Contractor shall avoid construction works close to the streams or water bodies

during monsoon.

Contractor shall not wash his vehicles in river water and shall not enter riverbed

for that purpose.

MoRTH:111.4

MoRTH:111.1 Contractor

Environmental

Specialist of

CSC, KSHIP

C.4.1.2 Water Pollution The Contractor shall ensure that all construction vehicle parking locations, MoRTH:111.4 Contractor Environmental

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

40

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

from Fuel and

Lubricants

fuel/lubricants storage sites, vehicle, machinery and equipment maintenance and

refueling sites shall be located at least 500 m away from rivers and irrigation

canal/ponds.

The Contractor shall submit all locations and layout plans of such sites prior to

their establishment and shall be approved by the Environmental Specialist of CSC.

Contractor shall ensure that all vehicle/machinery and equipment operation,

maintenance and refueling shall be carried out in such a manner that spillage of

fuels and lubricants does not contaminate the ground. Wastewater from vehicle

parking, fuel storage areas, workshops, wash down and refueling areas shall be

treated in an oil interceptor before discharging it on land or into surface water

bodies or into other treatment system.

In all, fuel storage and refueling areas, if located on agricultural land or areas

supporting vegetation, the topsoil shall be stripped, stockpiled and returned after

cessation of such storage.

Contractor shall arrange for collection, storing and disposal of oily wastes to the

pre-identified disposal sites (list to be submitted to CSC and KSHIP) and approved

by the Environmental Specialist of CSC. All spills and collected petroleum wastes

shall be disposed off in accordance with Petroleum Rules and PCB guidelines.

MoRTH:111.1

(Oil Interceptors)

Petroleum Act

and Rules

MoEF/CPCB

Notifications

(Appendix-8)

Specialist of

CSC, KSHIP

C.4.2 Air Pollution

C.4.2.1 Dust Pollution

The Contractor shall take every precaution to reduce the level of dust from

construction plants, construction sites involving earthwork by sprinkling of water,

encapsulation of dust source.

Due to the acute water scarcity in certain areas, Contractor should limit water

sprinkling once in the early morning hours. Contractor should erect warning

boards on dust nuisance to the road users.

The Contractor shall procure the construction plants and machinery, which shall

conform to the pollution control norms specified by MoEF/CPCB/KSPCB.

The concentration of suspended particulate matter at a distance of 40m from a

construction plant located in a cluster of industries should be less than 500 µg. The

environmental monitoring is to be conducted as per the monitoring plan.

Alternatively, only crushers licensed by the KSPCB shall be used. The

Environmental Specialist, EO and KSHIP through the Engineer shall submit

required certificates and consents.

MoRTH:111.1

MoRTH:111.5

MoRTH:111.9

MoRTH:111.10

Contract

Agreement

(Appendix-7 and

Appendix-16)

Contractor

Environmental

Specialist of

CSC, EO,

KSHIP

through

Engineer

C.4.2.2 Emission from

Construction

Contractor shall ensure that all vehicles, equipment and machinery used for

construction are regularly maintained and confirm that pollution emission levels

Appendix-16 Contractor

Environmental

Specialist of

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

41

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Vehicles,

Equipment and

Machineries

comply with the relevant statutory requirements of CPCB and/Motor Vehicles

Rules.

The Contractor shall submit PUC certificates for all vehicles/equipment/machinery

used for the Project.

CSC, KSHIP

C.4.3 Noise Pollution

C.4.3.1

Noise Pollution:

Noise from

Vehicles, Plants and

Equipments

The Contractor shall confirm the following:

All Construction plants and equipment used in construction shall strictly

conform to the MoEF/CPCB noise standards.

All Vehicles and equipment used in construction shall be fitted with exhaust

silencers.

Servicing of all construction vehicles and machinery shall be done regularly

and during routine servicing operations, the effectiveness of exhaust silencers

shall be checked and if found defective shall be replaced.

The equipment available in the market should be procured, if the Contractor

plans to purchase new equipment. For the old equipment, necessary or

possible alterations must be carried out to reduce the noise levels to the

possible extent.

Maintenance of vehicles, equipment and machinery shall be regular and up to

the satisfaction of the Environmental Specialist of CSC to keep noise levels at

the minimum.

At the construction sites within 150 m of the nearest habitation, noisy construction

work such as crushing, operation of DG sets, use of high noise generation

equipment shall be stopped during the night time between 10.00 pm to 6.00 am.

Working hours of the construction activities shall be restricted around educational

institutions/Health Centers (silent zones) up to a distance of 100 m from the

sensitive receptors i.e., School, Health Centers and Hospitals etc.

Contractor shall provide noise barriers to the suggested locations of select Schools.

List of locations for noise barriers is given in (Appendix-6).

Noise monitoring shall be carried out at the locations specified in Table 5.2 by the

KSHIP and the Engineer through the approved monitoring agency.

Noise Rules

Published by

MoEF

Appendix-6

&

Appendix-7

Contractor

Environmental

Specialist of

CSC, KSHIP

C.5 Safety

C.5.1

Personnel Safety

Measures for

Labour

Contractor shall provide:

Protective footwear, protective goggles and nose masks to the workers

employed in asphalt works, concrete works, crusher etc.

Welder‟s protective eye-shields to workers who are engaged in welding works

Appendix-9 Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

42

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Earplugs to workers exposed to loud noise, and workers working in crushing

or compaction

The Contractor shall comply with all regulations regarding safe scaffolding,

ladders, working platforms, gangway, stairwells, excavations, trenches and

safe means of entry and egress.

The Contractor shall comply with all the precautions as required for ensuring the

safety of the workmen as per the International Labour Organization (ILO)

Convention No. 62 as far as those are applicable to this contract.

The Contractor shall make sure that during the construction work all relevant

provisions of Building and other Construction Workers (regulation of Employment

and Conditions of Services) Act, 1996 are adhered to.

The Contractor shall not employ any person below the age of 14 years for any

work and no woman shall be employed on the work of painting with products

containing lead in any form

The Contractor shall also ensure that paint containing lead or lead products is used

except in the form of paste or readymade paint.

C.5.2 Traffic and Safety

The Contractor shall take all necessary measures for the safety of traffic during

construction and provide erect and maintain such barricades, including signs,

markings, flags, lights and flagmen as proposed in the Traffic Control

Plan/Drawings and as required by the Environmental Expert of CSC for the

information and protection on traffic approaching or passing through the section of

any existing cross roads.

The Contractor shall ensure that all signs, barricades, pavement markings are

provided as per the MoRTH specifications. Before taking up of construction on

any section of the existing lanes of the highway, a Traffic Control Plan shall be

devised and implemented to the satisfaction of the Environmental Expert of CSC.

MoRTH: 112.4

MoRTH: 112.1

IRC: SP:55

Appendix-9 & 14

Contractor

Environmental

Specialist of

CSC, KSHIP

C.5.3 Risk from Electrical

Equipments

The Contractor shall take all required precautions to prevent danger from electrical

equipment and ensure that –

No material shall be so stacked or placed as to cause danger or inconvenience

to any person or the public.

All necessary fencing and lights shall be provided to protect the public in

construction zones.

All machines to be used in the construction shall conform to the relevant Indian

Contractor

Environmental

Expert of SC,

PIU

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

43

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

Standards (IS) codes, shall be free from patent defect, shall be kept in good

working order, shall be regularly inspected and properly maintained as per IS

provision and to the satisfaction of the Environmental Expert of CSC.

C.5.4 Risk Force Measure

Contractor shall take all reasonable precautions to prevent danger to the workers

and public from fire, flood etc. resulting due to construction activities.

Contractor shall make required arrangements so that in case of any mishap all

necessary steps can be taken for prompt first aid treatment. Construction Safety

Plan prepared by the Contractor shall identify necessary actions in the event of an

emergency.

Contract

Agreement

Appendix-9

Contractor

Environmental

Specialist of

CSC, KSHIP

C.5.6 First Aid

The Contractor shall arrange for –

A readily available first aid unit including an adequate supply of sterilized dressing

materials and appliances as per the Factories Rules in every work zone.

Availability of suitable transport at all times to take injured or sick person(s) to the

nearest hospital.

Equipment and trained nursing staff at construction camp.

Contract

requirement

Appendix-9

Contractor

Environmental

Specialist of

CSC, KSHIP

C.5.7 Informatory Signs

and Hoardings

The Contractor shall provide, erect and maintain informatory/safety signs,

hoardings written in English and local language (Kannada), wherever required or

as suggested by the Environmental Specialist of CSC.

MoRTH:801

MoRTH:802

&

Appendix-4

Contractor

Environmental

Specialist of

CSC, KSHIP

C.6 Flora and Fauna: Plantation/Preservation/Conservation Measures

C.6.1 Road side

Plantation Strategy

The Contractor shall do turfing on embankment slopes, plantation of shrubs as

specified in the Contract.

The compensatory forestation shall be carried out by the State Forest Department.

Minimum 80 percent survival rate of the saplings shall be acceptable otherwise the

Contractor/Forest Department shall replace dead plants at his own cost.

The Environmental Specialist of CSC shall inspect regularly the survival rate of

the trees planted by the Contractor in accordance with the plantation strategy

suggested.

Appendix-10 Contractor

Environmental

Specialist of

CSC, KSHIP

C.6.2 Flora and chance

found Fauna

The Contractor shall take reasonable precaution to prevent his workmen or any

other persons form removing and damaging any flora (plant/vegetation) and fauna

(animal) including fishing in any water body and hunting of any animal. If any

animal is found near the construction site at any point of time, the Contractor shall

immediately upon discovery thereof acquaint in the Environmental Specialist of

CSC and carry out his instructions for dealing with the same.

Environmental Specialist of CSC shall report to the near by forest office (range

Appendix-13 Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

44

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

office or divisional office) and shall take appropriate steps/measures, if required in

consultation with the forest officials.

C.6.3

Chance Found

Archaeological

Property

All fossils, coins, articles of value of antiquity, structures and other remains of

archaeological interest discovered on the site shall be the property of the

Government and shall be dealt with as per provisions of the relevant legislation.

The Contractor shall take reasonable precautions to prevent his workmen or any

other persons from removing and damaging any such article or thing. He shall,

immediately upon discovery thereof and before removal acquaint the

Environmental Specialist of CSC of such discovery and carry out the CSC‟s

instructions for dealing with the same, waiting which all work shall be stopped.

The CSC shall seek direction from the Archaeological Survey of India (ASI)

before instructing the Contractor to recommence the work in the site.The

Archaeological structures identified along the road sides should be protected/

preserved or enhanced as per the law.

Appendix-11

Contractor

Environmental

Specialist of

CSC, KSHIP

C.7.1 Accommodation

Contractor shall follow all relevant provisions of the Building and the other

Construction Workers (Regulations of Employment and Conditions of Service)

Act, 1996 for construction and maintenance of labour camp.

The location, layout and basic facility provision of each labour camp shall be

submitted to CSC and KSHIP prior to their construction.

The Construction shall commence only upon the written approval of the

Environmental Specialist of CSC.

The Contractor shall maintain necessary living accommodation and ancillary

facilities in functional and hygienic manner and as approved by the CSC.

Contract

Agreement

Appendix-21

Contractor

Environmental

Specialist of

CSC, KSHIP

C.7.2 Potable Water

The Contractor shall construct and maintain all labour accommodation in such a

fashion that uncontaminated water is available for drinking, cooking and washing.

The Contractor shall also provide potable water facilities within the premises of

every camp at an accessible place, as per standards set by the Building and other

Construction Workers (Regulation of Employment and Conditions of Service) Act,

1996.

The Contractor shall also guarantee the following:

a) Supply of sufficient quantity of Potable Water (as per IS) in every

workplace/labour camp (Site at suitable and easily accessible places and

regular maintenance of such facilities.

b) If any water storage tank is provided that shall be kept such that the

bottom of the tank at least 1 m above the surrounding ground level.

Appendix-21

Contractor

Environmental

Specialist of

CSC, KSHIP

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

45

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

c) If water is drawn from any existing well, which is within 30 m proximity

of any toilet, drain or other source of pollution, the well shall be

disinfected before water is used for drinking.

d) All such wells shall be entirely covered and provided with a trap door,

which shall be dust proof and water proof.

e) A reliable pump shall be fitted to each covered well. The trap door shall

be kept locked and opened only for cleaning or inspection, which shall be

done at least once in a month.

f) Analysis of water shall be done every month as per parameters prescribed

in IS 10500-1991.

Environmental Specialist of CSC shall be required to inspect the labour camp once

in a week to ensure the compliance of the EMP

C.7.3 Sanitation and

Sewage System

The Contractor shall ensure that –

The Sewage system for the camp are designed, built and operated in such a

manner that no health hazards occurs and no pollution to the air, ground water

or adjacent water courses take place

Separate toilets/bathrooms, wherever required, Screened from those form men

(marked in vernacular) are to be provided for women

Adequate water supply is to be provided in all toilets and urinals

Night soil can be disposed of with the help of local municipal extractor or

disposed of by putting layer of it at the bottom of a permanent tank prepared

for the purpose and covered with 15 cm layer of waste or refuse and then

covered with a layer of earth for fortnight.

MoRTH:114.14

Appendix-21 Contractor

Environmental

Specialist of

CSC, KSHIP

C.7.4 Waste Disposal

The Contractor shall provide garbage bins in the camps and ensure that these are

regularly emptied and disposed off in a hygienic manner as per the Comprehensive

Solid Waste Management Plan approved by the Environmental Specialist of CSC.

Appendix-21 Contractor

Environmental

Specialist of

CSC, KSHIP

C.8 Contractor’s Demobilization

C.8.1 Environmental

Conditions

The KSHIP shall undertake seasonal monitoring of air, water, and noise and soil

quality through an approved monitoring agency. The parameters to be monitored,

frequency and duration of monitoring as well as the locations to be monitored shall

be as per the Monitoring Plan prepared. National Standard of Air, Noise and Water

given in Appendix-7.

Appendix-7 and

Appendix-12 Contractor

Environmental

Specialist of

CSC and

KSHIP, NHAI

C.8.2

Continuous

Community

Participation

The Environmental Specialist of CSC shall have continuous interactions with local

people around the project area to ensure that the construction activities are not

causing undue inconvenience to the locals residing in the vicinity of project site

Appendix-16

Environmental

Specialist of

CSC

Environmental

Specialist of

CSC and

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

46

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

under construction due to noise, dust or disposal of debris etc. KSHIP, NHAI

C.8.3

Clean-up

Operations,

Restoration and

Rehabilitation

Contractor shall prepare site restoration plans, which shall be approved by the

Environmental Specialist of CSC. The clean-up and restoration operations are to

be implemented by the Contractor prior to demobilization. The Contractor shall

clear all temporary structures; dispose all garbage, night soils and POL (Petroleum,

Oil and Lubricants) wastes as per Comprehensive Waste Management Plan and as

approved by CSC.

All disposal pits or trenches shall be filled in and effectively sealed off. Residual

topsoil, if any shall be distributed on adjoining/proximate barren land or areas

identified by the Contractor and approved by the Environmental Specialist of CSC

in a layer of thickness of 75 mm – 150 mm.All construction zones and facilities

including culverts, road side areas, camps, Hot Mix plant sites, Crushers, batching

plant sites and any other area used/affected due to the project operations shall be

left clean and tidy, at the Contractor‟s expense, to the entire satisfaction to the

Environmental Specialist of CSC.

Appendix-1 and

Appendix-21 Contractor

Environmental

Specialist of

CSC, KSHIP

C.9 Construction Activities by KSHIP/PWD

C.9.1 Tree Plantation

The plantation at the following locations shall be implemented by the KSHIP

through the State Forest Department;

3. Road side

4. Enhancement sites

5. Forest land

6. Community Forestation

A forest area management plan is provided in Appendix-13 & 11 is the list of

various enhancements sites included in the project.

Appendix-13

Appendix-11

State Forest

Department KSHIP

C.9.2

Oxbow lands and

other left over

portions of the

existing project

road

Development of the enhancement sites identified where PWD land is already

available are provided in Appendix-11.

Appendix-11 State PWD KSHIP

OPERATION STAGE

Activities to be Carried Out by the KSHIP/PWD

O.1

Monitoring

Operation

Performance

The KSHIP shall monitor the operational performance of the various

mitigation/enhancement measures carried out as a part of the project.

The indicators selected for monitoring include the survival rate of trees; utility of

enhancement provision made under the project; status of rehabilitation of borrow

Appendix-12 KSHIP/PWD KSHIP/PWD

Karnataka State Highways Improvement Project - II Executive Summary Report

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

47

Sl. No. Environmental

Issue Management Measures

Reference

Document

Responsibility

Planning and

Execution *

Supervision/

Monitoring **

areas; and effectiveness of noise barriers.

O.2 Maintenance of

Drainage

PWD shall ensure that all drains (side drains, median drain and all cross drainages)

are periodically cleared especially before monsoon season to facilitate the quick

passage of rainwater and avoid flooding.

Appendix-12 KSHIP/PWD KSHIP/PWD

O.3 Pollution

Monitoring

The periodic monitoring of the ambient air quality, noise level, water (both ground

and surface water) quality, soil quality in the selected locations as suggested in

pollution monitoring plan through the KSPCB or its approved monitoring agency.

Appendix-12

Pollution

Monitoring

Agency

KSHIP/PWD

O.4

Soil Erosion and

Monitoring of

Borrow Areas

Visual Monitoring and inspection of soil erosion at borrow areas, quarries (if

closed and rehabilitated), embankments and other places expected to be affected,

shall be carried out once in every three months as suggested in monitoring plan.

Appendix-12 KSHIP/PWD KSHIP/PWD

O.5

Public awareness

on Noise levels and

Health Affects

However the public shall be advised to construct the noise barriers such as walls,

double glazed windows and tree plantation between the roads and their property.

The public awareness is necessary regarding the human health through the news

papers and consultations and distribution of pamphlets during the operation stage.

Appendix-6 KSHIP KSHIP

Note: For Annuity Packages:

* Planning and Execution will be by Concessionaire, and

** Supervision and Monitoring will be by Independent Engineer and KSHIP/PWD.

Karnataka State Highways Improvement Project - II Executive Summary

Consultancy Services for Preparation of DPR, Bid Documents EPC & Annuity Packages

and Associated Safeguard Instruments – Funded by World Bank

EIA Report 48 Scott Wilson

Figure E-3: Organizational Framework of EMPIU – KSHIP

PROJECT IMPLEMENTATION UNIT (PIU)

Project Director

Superintendant Engineer

Asst. Exe. Engineer (Envt.)

Documentation and Training

supervision Consultants

Environmental Engineer Assistant Conservator of Forest

Executive Engineers KSHIP Divisions Raichur, Belgaum, Shimoga & Tumkur

Asst. Engineer (Envt.)

Supervision Consultants/

Independent

Engineer

Executive Engineer (Environment)

Assistant Conservator of Forest

Range Forest Officer

Assistant Executive Engineers (Environment) each at Gulbarga,

Dharwar, Raichur, Chinthamani, Belgaum, Shimoga & Tumkur,

Forester

Chief Project Officer

ENVIRONMENTAL MANAGEMENT PLAN IMPLEMENTATION UNIT (EMPIU)

Range Forest Officers each at Gulbarga, Dharwar, Raichur,

Chinthamani, Belgaum, Shimoga & Tumkur,