environmental impact assessment project brief for dolerite mining intro
DESCRIPTION
Mining document that is required by most of the government environmental ministries before you can be granted mining rights.TRANSCRIPT
Environmental impact assessment project brief for dolerite mining / quarrying at Thaba- Phechela, Tsakholo , Mafeteng
EXECUTIVE SUMMARY
Mining and quarrying of natural resources, such as, clay diamonds dolerite and river sand, dominate Lesothos mining industry, and their extraction is exclusively by opencast mining. The mineral recovery and subsequent production of finished products entail mainly physical processes. Therefore, environmental impacts of mining are predominantly physical in nature. These includes enhanced soil erosion from removal of top soil to expose the required material underneath, mining effluent ,dust ,permanent change of topography and landscape (resulting in visual impact) and disturbance of aquatic life through water pollution. Air pollution from the mining and crushing dust is more prevalent during the windy periods, which is August. Erosion from abandoned opencast mines and mining effluent contribute to an increased suspended matter in water streams.
Quarrying often involves the use of explosives to break the rock, therefore processing it to the required final product. The blasting operation may at times cause seismic vibrations, dust, and noise. The crushing process will result in emission of dust. Trucks and earthmoving machinery driving along the gravel roads will cause noise, dust and emits exhaust fumes. Water will be sprayed on the gravel roads and parts of the crusher plant will either be fitted with mist sprayers to suppress dust or enclosed in a corrugated iron sheet housing. Exhaust fumes emissions will be minimized by ensuring that all earthmoving machinery trucks inclusive, are maintained in good running conditions through regular servicing and adopting preventive maintenance.
Erosion of stripped topsoil also represents a serious environmental impact .Compacting the stripped overburden and/or revegetating it will reduce loss of soil due to erosive forces. The impact associated with overburden soils will be minimal, as the project site has poor soil coverage.
Based on the findings of this study, the proposed mitigation measures will certainly reduce predicted impacts to acceptable levels, and the social impacts associated with the project will be insignificant and outweighed by the benefits to be derived from the project establishment. Potential benefits to be obtained by the local community include employment of, electricity supply, provision of potable water, road maintenance, provision of other temporary jobs etc. The economic spin-offs of the mine will be in the form of taxes paid to the government of Lesotho. Economic upliftment of the local community will also result in creation of other business opportunities.
Table of Contents
2EXECUTIVE SUMMARY
7CHARPTER ONE INTRODUCTION
71.1Introduction
71.2Report Structure
81.3Purpose, nature and the objective of the project
91.4Scope of work and terms of reference of the consultant
101.5 Supporting Reports
101.6Approach to the study and methodology
101.7Limitations and assumption
111.7.1General background
111.7.2Thaba-Phechela Dolerite Quarry
111.7.3Choice of Tsakholo Thaba-Phechela mountain
111.7.4Zero option
121.9 Planning policy, legal and administrative requirements
121.9.1Planning requirements
131.9.2 Legal and administrative requirements
151.9.3 International environmental agreements
151.10Permits, Plans and Notifications required for the mining operation
151.10.1Mining Right
151.10.2Environmental permit/license
151.10.3Water abstraction permit
161.10.4Permit to store explosives
161.10.5Notifications
161.11Environmental standards and technical regulations
161.11.1Water quality standards / regulations
161.11.2Emission standards
18CHAPTER TWO: LOCATION AND DESCRIPTION OF THE PROJECT AREA
182.1 Basic information
182.1.1 Project Proponent
182.1.2 Project location
192.1.3 History of the project site
192.2 Description of the project area
192.2.1 Cultural, conservation, protected and historical sites
192.2.2 Fauna
202.2.3 Flora
202.2.4 Forecasts and agricultural land
212.2.5 Hydrology ground and surface water system
252.2.6 Land use- Current
272.2.7 Local geology
282.2.9 Socio-economic environment and settlement areas.
292.2.10 Soil cover
292.2.11
302.2.12 Topography and landscape
302.2.13 Wind pattern
312.3 Major elements of the surrounding environment
312.3.1 Components of the environment susceptible to the pollution from the mine
322.3.2 existing surrounding pollution sources
33CHAPTER THREE PROJECT ACTIVITIES
333.1 Description of the project
333.1.1 Equipment and infrastructure
333.1.2 Concrete aggregate quarrying process
383.1.3 Production inputs.
393.1.4 Labour requirements
423.1.5 Ablution facilities
423.1.6 General Waste
423.1.7 Projected output capacity and lifespan
423.1.8 Working hours and days
433.1.9 Project phase-out
433.2 Ancillary project facilities
433.2.1 Internal network
433.2.3 Information and communication facilities
433.2.4 Sewage works and handling facilities
433.2.5 Accommodation
433.2.6 Administration office
443.2.7 Ablution facilities
443.3 Wastewater treatment system
443.3.1 Septic tank
443.3.2 Drainfield
453.3.3 Location of the septic tank
453.3.4 Septic system management
463.4 Mining effluent management
463.4.1 Settlement ponds
473.4.2 Silt management
473.5 Project cost estimate
48CHARPTER FOUR: ELECTRICAL SUPPLY
484.1 General Background
494.2 Analysis of alternative routes for the power line
494.2.1 Alternative route
504.2.2 Recommended route
504.3 Description of the environment of the proposed route
504.3.1 Temperature rainfall and wind pattern
504.3.2 Landscape and topography
504.3.3 Vegetation
514.3.4 Socio-economic environment
514.4 Environmental issues/impacts
514.4.1 Impacts on biophysical environment
534.4.2 Socio-economic impacts
54CHAPTER FIVE: ENVIRONMENTAL IMPACTS
545.1 Key environmental issues and impacts identified
545.1.1 Pre-construction phase
545.1.2 Construction Phase
555.1.3 Operation phase
58B. Socio-Economic impacts
59C. Positive impacts
SUBMITTED TO
National Environmental Secretariat Ministry of Tourism, Culture and Environment
SUBMITTED BY
March 22 Mining and Civil Engineering (Pty) Ltd
SEPTEMBER 2014
Prepared by
Relebohile Khatibe
P.O. Box 1393
Maseru 100
Cell: +26658540973/ +26662747316
Email: HYPERLINK "mailto:[email protected]/" [email protected]/ HYPERLINK "mailto:[email protected]/" [email protected]/
Environmental impact assessment project brief for dolerite mining / quarrying at Thaba- Phechela, Tsakholo , Mafeteng
PREPARED IN FULFILMENT OF Environmental Act of 2001, Sections 27(1), 28(1), and 2
v | Page