establishing the performance measurement baseline (v4)

34
Thank you all for coming to the work shop today. The title of the Work Shop title speaks about the Performance Measurement Baseline. This may be a new term for some of you. After our four hours today, I’m hoping it will be a term you'll be using back on your own projects. Let’s define what we mean at this point in the work shop. At the first slide. The Performance Measurement Baseline is a time-phased budget plan for accomplishing work, against which the project performance is measured. It includes the budgets assigned to scheduled work , their budget spreads, and the applicable indirect budgets. This budget plan is derived from a resource loaded Master Schedule. These resource loads, along with other information, are contained in Work Packages. You’ll hear many times the phrase “cost and schedule.” I want you to start thinking about what it sounds like when you say “schedule and cost.” It’s the schedule – the sequence of the Work Packages that is the basis of the cost. AACE Symposium, April 16th, 2011 1/34 Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Upload: glen-alleman

Post on 18-May-2015

2.104 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Establishing the performance measurement baseline (v4)

Thank you all for coming to the work

shop today.

The title of the Work Shop title speaks

about the Performance Measurement

Baseline.

This may be a new term for some of

you. After our four hours today, I’m

hoping it will be a term you'll be using

back on your own projects.

Let’s define what we mean at this point

in the work shop. At the first slide.

The Performance Measurement

Baseline is a time-phased budget plan

for accomplishing work, against which

the project performance is measured.

It includes the budgets assigned to

scheduled work , their budget spreads,

and the applicable indirect budgets.

This budget plan is derived from a

resource loaded Master Schedule.

These resource loads, along with other

information, are contained in Work

Packages.

You’ll hear many times the phrase

“cost and schedule.” I want you to start

thinking about what it sounds like when

you say “schedule and cost.”

It’s the schedule – the sequence of the

Work Packages – that is the basis of

the cost.

AACE Symposium, April 16th, 2011

1/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 2: Establishing the performance measurement baseline (v4)

There are four words that we’ll connect

together today. These words – when

they are connected, will describe how

to increase the probability of success

for your projects.

Any project, doesn’t matter the

domain, the context in that domain, the

methods used to manage the project,

the specific technology of the products

in the projects.

If you don’t have these four words in

your vocabulary, you’re going to

reduce the probability of success.

This doesn’t mean the project will fail.

This doesn’t mean the project will be

challenged.

All it means is the Probability of

Project Success will be reduced.

These four words are here in front of

us.

Credible

Performance

Measurement

Baseline

The title of this talk puts the words

together. But they also stand alone.

Let’s look at one as a standalone word

first.

AACE Symposium, April 16th, 2011

2/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 3: Establishing the performance measurement baseline (v4)

Credible.

What does it mean to be credible.

Well Jiminy Cricket here can tell the

difference between credible and not

so credible.

It’s harder for us to do that on a

project. But we have some methods

that you’ll see today that can be used

to test the credibility of a project’s

ability to successfully be completed.

These methods are probabilistic in

mature. They ask and answer

probability questions, using simple

statistics.

AACE Symposium, April 16th, 2011

3/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 4: Establishing the performance measurement baseline (v4)

When we speak of performance, we

should only be speaking in terms of

deliverables, percent complete,

tangible evidence of completion of our

planned work.

Not in terms of cost and schedule. The

consumption of resources, the

expenditure of money or the passage

of time.

So our Performance Measurement

Baseline needs to use units of measures

that are tangible.

These units of measure must also be

meaningful to the decision makers as

well.

AACE Symposium, April 16th, 2011

4/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 5: Establishing the performance measurement baseline (v4)

Measuring means measuring against

the plan, on the day the plan says

there is an expected deliverable.

The units of measure are predefined in

the work package that is going to be

on baseline.

The measure is always some tangible

evidence. A milestone met, a

deliverable produced, a count of some

kind.

The measure is never an opinion of the

owner of the measurement.

AACE Symposium, April 16th, 2011

5/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 6: Establishing the performance measurement baseline (v4)

The word baseline in Performance

Measurement Baseline, means the cost

of the scheduled program activities

that have been approved for

execution.

Management of the baseline is a

change control process once the

Performance Measurement Baseline

goes on baseline.

We’re going to see today there are

actually three baselines.

1. The technical baseline

2. The cost baseline

3. The schedule baseline

AACE Symposium, April 16th, 2011

6/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 7: Establishing the performance measurement baseline (v4)

Here’s how we are going to build our

Performance Measurement Baseline.

It’s a simple process in principle. But of

course in practice, it’s always harder in

practice.

We’ll use the exercises to pull out

these practices from the principles, but

let’s have a quick look first at the

principles.

1. Build a Work Breakdown

Structure.

2. Define the Work Packages that

produce the deliverables at the

terminal nodes of the WBS.

3. Arrange these Work Packages in

some logical sequence.

4. Assign the resources needed to

complete the Work Packages in a

timely manner.

5. Turn this whole collection of

information into a credible

Performance Measurement

Baseline (PMB).

One final step is to perform the

continuous risk management processes

inside these five (5) steps, so we

actually increase our probability of

success.

The key here is “increasing the

probability of success.” We need to

remember this phrase. It’s the inverse

of many of the efforts made to

manage projects.

Connecting actions with outcomes is the

Critical Success Factor.

AACE Symposium, April 16th, 2011

7/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 8: Establishing the performance measurement baseline (v4)

Let’s look at a broader context of the

five (5) essential process areas for

managing any project.

Other project management paradigms

have even other process areas –

Prince2 for example.

But the process areas here have

emerged over the course of several

decades of managing defense, large

construction, and enterprise IT projects.

These five (5) processes are:

Identify the needed capabilities – this

is commonly missing from many

projects. A capability is not the same

as a requirements. One way to think of

this in the Enterprise IT is the ask “if I

had the system, it was free, it worked

on Monday, what would I do with it?

Once you’ve defined the needed

capabilities, you need to identify the

technical and operation requirements

needed to enable these capabilities.

Then comes establishing the

Performance Measurement Baseline.

And then the execution of the PMB.

At each process, we must apply

continuous risk management in place

and operational.

The other 4 processes areas are work

shops unto themselves, so for today,

we’ll concentrate on building the PMB

and assume the other 4 areas are in

place.

AACE Symposium, April 16th, 2011

8/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 9: Establishing the performance measurement baseline (v4)

The term “baseline” has an important

role here. It is a “controlled” document

that contains the agreed on

information about the future

performance of the project.

When we say “baseline,” we really

mean three baselines.

The Technical Baseline is the

agreed on set of technical

requirements. These can be changing

or they can be frozen, or any place

in between.

From the technical requirements

baseline, we have the work needed

to implement them in the Schedule

Baseline.

From this work we can establish the

Cost Baseline.

All three baselines are connected in an

inseparable relationship, change one

and the other two are impacted.

This is sometimes called the “iron

triangle.”

Trying to make tradeoffs between the

three variables can be done early in

the project.

Once underway, trade offs between

these three baselines and the belief

that there will be no negative impacts

is a Ponzi scheme.

AACE Symposium, April 16th, 2011

9/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 10: Establishing the performance measurement baseline (v4)

What we’re here for today is to build

the Performance Measurement

Baseline. The core elements of the PMB

are Work Packages.

Work Packages are “lumps of work,”

that produce a single outcome. The

idea of the single outcome has

important attributes.

If we have multiple outcomes, it’s hard

to measure progress with 0% or 100%

completion criteria.

If we have multiple outcomes who’s

accountable for each outcome?

Try as hard as possible to have a

single outcome for each Work

Package.

Once we’ve connected the Work

Package with an outcome, we can ask

other questions:

How long will it take?

How much will it cost?

Who’s accountable for delivering the

outcome?

What are the risks involved in

delivering this outcome?

What dependencies are there for

this Work Package or other Work

Packages or external items?

We need to answer these questions, if

we ever have a chance at having a

credible PMB. By credible I mean

“believable.” It doesn’t have to be

“right,” there are few “right” answers.

It has to be feasible and it has to be

credible.

AACE Symposium, April 16th, 2011

10/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 11: Establishing the performance measurement baseline (v4)

So let’s look at an example of building

a bio lab to BSL Level 4 specifications.

BSL Level 4 is REALLY bad stuff.

AACE Symposium, April 16th, 2011

11/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 12: Establishing the performance measurement baseline (v4)

Here’s a page from our Deliverables

Based Planning ® method handbook.

This method is applied in a variety of

domains and contexts in those

domains.

The critical success factor for

Deliverables Based Planning® is to

focus on the deliverables.

Not on the effort, the technology, the

resources.

These items are important. But the

customer paid for the deliverables. By

customer I mean the general notion of

a customer. A business customer, a

government customer, an internal

customer.

The units of measure for these

deliverables must be meaningful to the

customer. This is the reason to start with

the Capabilities Based processes

shown in slide 4.

We’ll assume these have been

defined, and the technical and

operational requirements defined.

Now we’re taking those requirements

and building the Performance

Measurement Baseline that will make

them appear.

These 6 steps are “immutable” in that

they are all needed and they need to

be performed in the proper order.

This doesn’t mean they not iterative

and incremental, but each step takes

information for the previous step.

AACE Symposium, April 16th, 2011

12/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 13: Establishing the performance measurement baseline (v4)

Let’s start with the Work Breakdown

Structure (WBS). We all know about

the WBS right?

We should all also know there is a

new specific for the WBS MIL-STD-

881C that will be coming in June of

this year. For us in the defense business

the STD part has replaced the HDBK

part of the title. It is no longer a

suggested approach, it is a mandated

approach.

AACE doesn’t have a specific WBS

13

Page 14: Establishing the performance measurement baseline (v4)

Here’s a “notional” starting point.

Using the WBS paradigm, we need to

capture the Products and the Services

that produce those products.

The WBS does NOT describe the

functional roles of the project. Design,

construct, inspect, develop, test, install

are not WBS elements.

The focus is on “deliverables,” the end

item deliverables of the work efforts.

So for this example we have.

The design basis. While the word

design is here, it is the document that

is the deliverable.

The processing document is the other

deliverable. This document

described how the BSL Lvl-4

materials handling processes will be

performance for this lab. That is

critical to FDA certification before

construction starts, so it’s a

deliverable.

Each of these deliverables has two

sub deliverables – the elements that

make up the actual deliverable.

Notice here with well formed structure.

Each parent has proper children. It is a

well formed tree.

All the children only go to one parent.

No step-parents.

AACE Symposium, April 16th, 2011

14/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 15: Establishing the performance measurement baseline (v4)

Let’s connect the dots between the

WBS and the Work Packages that

guide the activities that produce the

artifacts of the WBS.

These Work Packages are derived

from the terminal nodes of the WBS.

This picture shows where the Work

Package lives in this process.

We take our notional WBS and for

each terminal node make a Work

Package.

The Work Package contains many

things, but the first thing it contains is

the list of work needed to produce the

deliverable.

This might be called a schedule, but

let’s not go there yet.

Let’s just get the list of work activities,

maybe their sequencing.

And most of all the list of “named”

deliverables produced by the Work

Package.

AACE Symposium, April 16th, 2011

15/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 16: Establishing the performance measurement baseline (v4)

With the WBS and the Work

Packages defined, let’s define who is

going to do the work.

16

Page 17: Establishing the performance measurement baseline (v4)

Just a reminder that the “owner” of the

Work Package this person is

accountable for.

It’s always about the deliverables.

There are other activities of course, but

the deliverables are what the customer

bought.

This is why the planning and scheduling

process stops at the Work Package.

With the Work Package manager

being accountable for the

deliverables, “how” the work package

is executed must be the role of the

Work Package Manager and her

team.

Within the project governance guides,

you want to push down the

accountability to those doing the work.

They can’t do this work in any

arbitrary way, but they must be

accountable for the outcomes.

On our large projects, Work Packages

have a period of performance (start-

end), assigned resources, and a

budget profile. The Work Package

Manager may have a detailed

schedule, or just a bunch of notes stuck

to the wall.

This is called a “supplemental

schedule.” The details are not on

baseline. The Work Package is.

Below this level detailing out the work

is the role of the Work Package

manager.

AACE Symposium, April 16th, 2011

17/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 18: Establishing the performance measurement baseline (v4)

Here’s a real world example of the

Responsibility Assignment Matrix

(RAM).

The first approach is to just put in the

“accountable” connections.

Once those who are accountable for

the deliverables are defined, it’s all

down hill from there.

18

Page 19: Establishing the performance measurement baseline (v4)

The next step is to lay out these work

packages in their order of execution.

This can be done in a variety of ways,

sticky notes on the wall is one.

Fancy electronic tools is another.

The sticky notes provides much more

flexibility early in the project.

19

Page 20: Establishing the performance measurement baseline (v4)

Here’s a picture of “real” Work

Packages being arranged by “real”

Work Package managers, on a “real”

project.

This is a simple process. Brown paper,

sticky notes, hand written Work

Package descriptions.

This process is called Product

Development Kaizen.

The critical idea is to have collective

ownership of the arrangement of the

Work Packages, while having single

accountability of the contents of each

Work Package by the Work Package

Manager.

Arranging the Work Packages is a full

contact sport.

When complete, leave the sticky notes

on the wall for all to see.

You will move these into a project

scheduling tool of course, but even then

you should have a “plot” of these

Work Packages.

20

Page 21: Establishing the performance measurement baseline (v4)

With the Work Packages in place,

documented to some level of detail,

the estimated durations, and work

efforts, it’s time to lay them out in some

order of execution.

We need to identify the predecessors

and successors of the “lumps of work.”

Note the tasks – that’s an issue for the

Work Package Manager.

The order needs to be logical in the

sense that the products produced by

the Work Packages can be consumed

by the next Work Package.

With this sequence, we can ask

questions about the flow of value, the

impacts on resources, the general logic

of how the work progresses toward

DONE.

At this level of granularity, the

emerging Master Schedule comes out.

This is then the basis of the Work

Authorization process.

The authorization of work is not used

to prevent work from being

performed, but to assure the work is

performed in the agreed on order.

Performing work “out of order,”

creates lots of problems, not the least

of which is outcomes sit idle while

others are waiting for materials.

This is a “work flow” issue and needs

to be addressed to ensure the best

effectiveness from the resources.

AACE Symposium, April 16th, 2011

21/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 22: Establishing the performance measurement baseline (v4)

Let’s take a short diversion here for a

critically important concept.

Leads and Lags in the schedule are

restricted in most defense projects.

NAVAIR, the Navy’s aviation arm,

allows 5 days lead or lag in the

Integrated Master Schedule between

any two Work Packages. On a 5 year

project 5 days might as well be zero

(0) days.

The reason to restrict leads and lags is

the follow on work activity then uses

partially complete products. This is the

source of “rework.”

When the predecessor activities finally

complete, there is likely more work

done and likely changes in that work.

The successor work then has to readjust

for these changes.

If there is intermediate output needed

by successor work, split the Work

Package and produce 100% of the

maturity for the intermediate output.

By “thinking” in terms of “increasing

maturity,” leads and lags can be

removed.

The project is a work flow of

increasing maturity. We want to

maximize this value within the

constraints of schedule and cost.

AACE Symposium, April 16th, 2011

22/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 23: Establishing the performance measurement baseline (v4)

Now that we’ve got the Work

Packages in some kind order – not the

final order – but something that’s

starting to look like a plan, let’s see

what resources and costs are going to

be needed.

23

Page 24: Establishing the performance measurement baseline (v4)

Putting budget to Work Packages at

this point is real simple.

We’ve got definitions of the

deliverables, the needed resources

assigned – at least in lumps – to the

Work Packages.

Now it’s simple to budget.

From the head count, assign a labor

rate, possibly forward adjusted for all

the changes – and see what number

comes out for each Work Package.

In Earned Value terms – which we’ve

avoided so far – this is the Budgeted

Cost for Work Schedule – BCWS.

No matter what cost performance

management system we are using,

we’ve now got the “budget spreads”

defined for each Work Package.

Put this number back into the document

that describes the Work Package. This

is one advantage of building the

Work Packages in Excel, you can now

do math on the budget numbers.

AACE Symposium, April 16th, 2011

24/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 25: Establishing the performance measurement baseline (v4)

We don’t have a lot of time today to

take deep dived into building the

PMB, but this topic is critically

important to any credible PMB.

We must have a probabilistic

understanding of how cost, schedule,

and technical performance all interact.

Here’s a notional example of using a

Monte Carlo simulator to answer the

question – what’s the probability of

complete on or before a date and

spending an amount of money or less?

25

Page 26: Establishing the performance measurement baseline (v4)

Now we reach the end and the hard

part.

Let’s start with an understanding that

measures of progress on in units of

“tangible evidence.”

No opinion, no guesses, no “well I think

well be OK, we’re probably 60%

done with the work to date.”

Nope, tangible evidence of progress

to plan is the only acceptable measure

of progress.

26

Page 27: Establishing the performance measurement baseline (v4)

The first thing to do when defining the units of measure of DONE is to agree that they must be “objective.”

Tangible Evidentiary Materials is the formal word.

They have to be tangible. Something you can touch, see, smell, look at.

A simple example can be around drawings.

Our Work Package produces 10 drawings for our workshop example toaster.

We say the period of performance for these drawings is 2 weeks.

Assuming a linear production of work, we should see 5 drawings at the close of business Friday for the first week.

We defined this Measure of Performance (MoP) in the Work Package. On the Friday afternoon, you can walk over to the drafting area and ask to see the 5 drawings that are planned to be completed.

If you see the 5 hanging in the stick-file, then you are 100% complete for the planned 50% completion point in the Work Package. The Estimate to Complete is now 50% - the other 5 drawings – and with the past performance of “on time,” you can naively assume you’ll get the next 5 at COB next Friday.

It may serve you better if you went to visit the drafting department over lunch on Wednesday to see if 2 ½ drawings are done – this answers the question how long are you willing to wait before you find out you’re late?

AACE Symposium, April 16th, 2011

27/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 28: Establishing the performance measurement baseline (v4)

In the file that contains all the project

information, we need to write down

what these success criteria or exit

criteria are, so no one forgets what we

agreed to when we planned out the

Work Packages.

The term “earned value method” is on

this slide and we haven’t mentioned its

use – and we won’t go there for now.

But EV is a critically important

measurement tool for any type of

project.

This is a topic for another workshop,

but I want to plant the seed around

EV.

EV measures physical percent

complete against planned percent

complete in ways no other project

management performance

measurement process can.

Agile’s story points are Uncalibrated,

Lean and Critical Chain’s “value flow”

is Uncalibrated.

EV measures progress to plan in units

of “money.” And money is what project

management is all about.

AACE Symposium, April 16th, 2011

28/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 29: Establishing the performance measurement baseline (v4)

With all this data collected in one

place – the Integrated Master

Schedule – we need to actually put it

on baseline.

29

Page 30: Establishing the performance measurement baseline (v4)

So why all these words about “setting

the baseline?”

The baseline is the “contract” between

the people doing the work, the people

managing the work, and the people

receiving the results of that work.

It is a “contract” about “how long,”

“how much,” “when,” sometimes “why,”

and most importantly “what.”

It’s an agreement of how to get to

DONE.

Like all good agreements, making

changes to the agreement is only done

with the full consent of all the parties

involved.

So where do we go to look at what we

agreed to?

The Baseline.

AACE Symposium, April 16th, 2011

30/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 31: Establishing the performance measurement baseline (v4)

This list comes from guidance in the

defense program management

business. While some of the statement

may not be appropriate for the

commercial world, every statement has

some applicability to every project –

not matter what the domain. Whether

formal or informal the programmatic

risk assessment of a project needs to

ask or answer these statements.

The actions needed to close any gaps

from these statements are outside the

scope of this presentation.

But the next step is to have the project

management team start to answer

these questions.

31

Annual Rocky Mountain Project Management SymposiumRisk Management in Five Easy PiecesDenver Colorado April 11, 2008

Glen B. AllemanLewis & Fowler, 8310 South Valley Highway, Englewood CO80112www.lewisandfowler.com

Page 32: Establishing the performance measurement baseline (v4)

Thank you for investing your time

today.

With the time we have left, let’s open

this up to questions.

If we run out of time, please drop a

card with my colleague and we’ll

make direct contact.

AACE Symposium, April 16th, 2011

32/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 33: Establishing the performance measurement baseline (v4)

AACE Symposium, April 16th, 2011

33/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved

Page 34: Establishing the performance measurement baseline (v4)

Here’s my contact information if you

have any questions later, want a soft

copy of this presentation with the

speaker notes, or any other items

AACE Symposium, April 16th, 2011

34/34Copyright ©, 2011, Lewis & Fowler, All Rights Reserved