euradwaste´04 large-scale experiments in underground research laboratories experience in ebs...

12
EURADWASTE´04 Large-scale Experiments in Underground Research Laboratories Experience in EBS Engineering Development and Handling Feasibility Christer Svemar, Fernando Huertas and Roland Pusch

Upload: jamel-longyear

Post on 14-Dec-2015

215 views

Category:

Documents


2 download

TRANSCRIPT

EURADWASTE´04

Large-scale Experiments in Underground Research Laboratories

Experience in EBS Engineering Development and Handling Feasibility

Christer Svemar, Fernando Huertas and Roland Pusch

EURADWASTE´04

The two projectsFEBEX

Prototype Repository

EURADWASTE´04

Horizontal vs vertical emplacement modes

EURADWASTE´04

Excavation of drifts and holes

Prototype Repository

FEBEX

EURADWASTE´04

Excavation Damaged Zone (EDZ)

EDZ HOLE 3

0,0

0,2

0,4

0,6

0,8

1,0

1,2

0 20 40 60 80distance (mm)

po

ros

ity

(%

)

3:1A

3:1B

3:2A

3:2B

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0 1 2 3 4 5 6 7

distance (cm)

po

rosi

ty (

%)

FEBEX

Prototype Repository

EURADWASTE´04

Emplacement of bentonite blocks (liner) and pelletsPrototype Repository

FEBEX

EURADWASTE´04

Canister emplacementFEBEX

Prototype Repository

EURADWASTE´04

Retrieval

Horizontal emplacement mode Vertical emplacement mode

EURADWASTE´04

Results and conclusions 1(2)

• TBM excavation of drifts is a proven technology• Vertical boring of deposition holes has been shown possible to do with a

higher accuracy than assumed• Bentonite blocks can be pre-compacted to the size needed• Installation of brick-size bentonite blocks and liner in the horizontal mode

can be done in the assumed way, but the humidity in a drift puts time constraint on the installation

• Vertical installation of large blocks can meet accuracy requirements, but humidity in the air and, even more, dripping water demands protection of the bentonite blocks

• Both horizontal and vertical emplacement of canisters meet the high requirement on alignment

• In situ compaction of backfill can meet quality requirements with 30/70 mixtures of bentonite and crushed rock

• Retrieval of emplaced canisters is technically feasible

EURADWASTE´04

Results and conclusions 2 (2)

• Main technical difficulty in horizontal emplacement was the alignment of the canister, and

• the water inflow in the vertical emplacement mode, both into holes and into the drift

• In both projects were practical manufacturing and emplacement methods simulated with good result, including measures taken to overcome the difficulties mentioned above

• Further development can be directed toward optimisation of concepts

EURADWASTE´04

The futureTesting of horizontal emplacement techniques at Aspo HRL

Objectives

• To continue the technical development of practically applicable techniques

• To provide the basis for PA of the KBS-3H concept

• To demonstrate technical feasibility in field test in ÄHRL

EURADWASTE´04

Thank you for your attention