evaluation of iec 61850 process bus architecture and

245
EVALUATION OF IEC 61850 PROCESS BUS ARCHITECTURE AND RELIABILITY A thesis submitted to The University of Manchester for the degree of Doctor of Philosophy in the Faculty of Engineering and Physical Sciences 2012 UZOAMAKA BENITA ANOMBEM SCHOOL OF ELECTRICAL AND ELECTRONIC ENGINEERING

Upload: others

Post on 18-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

EVALUATION OF IEC 61850 PROCESS BUS ARCHITECTURE AND RELIABILITY

A thesis submitted to The University of Manchester for the degree ofDoctor of Philosophy

in the Faculty of Engineering and Physical Sciences

2012

UZOAMAKA BENITA ANOMBEM

SCHOOL OF ELECTRICAL AND ELECTRONIC ENGINEERING

Table of ContentsLIST OF ABBREVIATIONS USED.....................................................................14LIST OF PUBLICATIONS...................................................................................16ABSTRACT.........................................................................................................17DECLARATION..................................................................................................18COPYRIGHT STATEMENT...............................................................................19ACKNOWLEDGEMENT.....................................................................................20CHAPTER 1INTRODUCTION............................................................................21

1.1. SUBSTATION AUTOMATION..................................................................................211.2. ISSUES AFFECTING THE SUBSTATION..............................................................211.3. COMMUNICATION PROTOCOLS...........................................................................241.4. MOTIVATION............................................................................................................271.5. OBJECTIVES .........................................................................................................281.6. THESIS STRUCTURE.............................................................................................29

CHAPTER 2 LITERATURE REVIEW................................................................312.1. INTRODUCTION......................................................................................................312.2. IEC 61850 DESIGN PROCESS ..............................................................................312.3. IEC 61850 SITE IMPLEMENTATIONS AND TRIALS..............................................322.4. PROPOSED PROCESS BUS ARCHITECTURES..................................................342.4.1. Keeping the Process Bus and Station Bus separate............................................352.4.1.1. Star Topology (Process Bus and Station Bus separate)....................................352.4.1.2. Ring Topology (Process Bus and Station Bus separate)...................................362.4.1.3. Point to point Topology (Process Bus and Station Bus separate).....................372.4.1.4. Parallel Redundancy Protocol, PRP (Process Bus and Station Bus separate).372.4.1.5. High-availability Seamless Redundancy (HSR) (Process Bus and Station Bus separate)..........................................................................................................................382.4.2. Merging the Process Bus and Station Bus ...........................................................392.4.2.1. Star Topology (Merging the Process Bus and Station Bus)...............................392.4.2.2. Ring and Star Topology (Merging the Process Bus and Station Bus)...............402.5. IEC 61850 COMMUNICATION BUS RELIABILITY ANALYSIS METHODS ..........412.5.1. Interface Tables .................................................................................................412.5.2. The Markov state model........................................................................................432.5.3. Fault trees Analysis...............................................................................................452.5.4. Tie sets method.....................................................................................................462.6. SUBSTATION LIFE CYCLE COST ANALYSIS ......................................................472.7. MERGING UNIT TESTS..........................................................................................492.7.1. Interoperability Tests.............................................................................................492.7.2. Merging Unit Accuracy Tests.................................................................................502.7.3. Commercially Available Merging Unit Testing Product - Omicron SV Scout......512.8. SUMMARY................................................................................................................52

CHAPTER 3 FUNDAMENTALS.........................................................................543.1. INTRODUCTION .....................................................................................................54

2

3.2. POWER SYSTEM ...................................................................................................543.3. SMART GRID...........................................................................................................553.4. SUBSTATION...........................................................................................................553.5. IEC 61850 ................................................................................................................583.5.1. Summary of The Parts Making up IEC 61850.......................................................593.5.2. IEC 61850 “Light Edition” (LE)...............................................................................613.5.3. IEC 61850 Edition 2...............................................................................................613.6. BENEFITS OF IEC 61850........................................................................................623.7. IEC 61850 STATION BUS .......................................................................................633.8. IEC 61850 PROCESS BUS .....................................................................................633.9. COMPARISON OF IEC 61850 WITH LEGACY PROTOCOLS...............................643.10. SUMMARY..............................................................................................................66

CHAPTER 4 PROPOSED PROCESS BUS ARCHITECTURE DESIGN..........674.1. INTRODUCTION......................................................................................................674.2. GOLDEN RULES AND ADDITIONAL CRITERIA....................................................674.3. SYSTEM DESCRIPTION.........................................................................................694.3.1. Basic Architecture Concept...................................................................................694.3.1.1. Data Flow (One Bay, Two Bays)........................................................................694.3.1.2. Interbay Process Bus Link .................................................................................714.3.2. High Level Application of Generic Architecture.....................................................714.3.2.1. Generic Architecture Diagram ...........................................................................714.3.2.2. Double Busbar Generic Diagram.......................................................................724.3.2.3. Mesh Substation Generic Diagram....................................................................734.4. DETAILED PROCESS BUS APPLICATIONS.........................................................744.4.1. Double Busbar Applications..................................................................................754.4.1.1. Double Bus Bar Arrangement ............................................................................754.4.1.2. Detailed Double Bus Bar Application ................................................................754.4.2. Mesh Corner Application.......................................................................................814.4.2.1. Mesh Corner Substation Arrangement ..............................................................814.4.2.2. Detailed Mesh Corner Application......................................................................824.5. ARCHITECTURE COMPLIANCE WITH GOLDEN RULES....................................864.6. SUMMARY................................................................................................................88

CHAPTER 5 DETERMINATION OF ARCHITECTURE RELIABILITY..............895.1. INTRODUCTION......................................................................................................895.2. RELIABILITY ANALYSIS METHODOLOGY............................................................895.2.1. Component reliability.............................................................................................895.2.2. System reliability....................................................................................................895.2.2.1. Reliability block diagram (RBD)..........................................................................905.2.2.2. Event Trees.........................................................................................................905.2.2.3. Component Availability.......................................................................................935.2.2.4. System Availability..............................................................................................935.3. RELIABILITY ANALYSIS: CASE STUDY ...............................................................935.3.1. Process Bus Architecture Scenarios.....................................................................935.3.2. Reliability Analysis.................................................................................................975.3.2.1. Component reliability and availability.................................................................975.3.2.2. System reliability and availability........................................................................975.4. ARCHITECTURE RELIABILITY: RESULTS AND DISCUSSION..........................1015.4.1. System Reliability and Availability Comparison..................................................101

3

5.4.2. Sensitivity Analysis - Effects of Device Reliability on System Reliability ..........1065.4.2.1. Double Busbar Feeder Bay (Double Busbar Bus Coupler Bay, Double Busbar Section Bay and Mesh Corner Feeder Bay) Process Bus (Star)..................................1065.4.2.2. Double Busbar Feeder Bay (Double Busbar Bus Coupler Bay, Double Busbar Section Bay and Mesh Corner Feeder Bay) Process Bus (Ring).................................1095.4.2.3. Double Busbar Transformer Bay Process Bus (Star)......................................1115.4.2.4. Double Busbar Transformer Bay Process Bus (Ring).....................................1145.4.2.5. Mesh Corner Mesh Corner Bay Process Bus (Star)........................................1155.4.2.6. Mesh Corner Transformer Bay Process Bus (Star).........................................1175.4.2.7. Mesh Corner Transformer Bay Process Bus (Ring).........................................1195.5. SUMMARY..............................................................................................................121

CHAPTER 6 DETERMINATION OF OPTIMUM ARCHITECTURE ................1236.1.INTRODUCTION.....................................................................................................1236.2. LIFE CYCLE COST ANALYSIS METHODOLOGY................................................1236.3. LIFE CYCLE COST ANALYSIS: CASE STUDY....................................................1266.4. OPTIMUM ARCHITECTURE: RESULTS AND DISCUSSION ............................1296.4.1. Life Cycle Cost Comparison - Double Busbar Feeder Bay (Star)......................1296.5. SUMMARY .............................................................................................................133

CHAPTER 7 DESIGN AND IMPLEMENTATION OF MERGING UNIT PERFORMANCE TEST BED ..........................................................................134

7.1. INTRODUCTION....................................................................................................1347.2. PROTOTYPE AND COMMERCIALLY AVAILABLE MERGING UNITS ...............1347.2.1. Locamation .........................................................................................................1347.2.2. GE .......................................................................................................................1357.2.3. Siemens .............................................................................................................1367.2.4. Mitsubishi.............................................................................................................1377.2.5. Alstom..................................................................................................................1387.2.6. ABB......................................................................................................................1387.3. MERGING UNIT PERFORMANCE TEST BED ....................................................1407.3.1. Real Time Digital Simulator (RTDS)...................................................................1417.3.2. Amplifiers – Omicron Amplifier and Isolation Amplifier.......................................1437.3.2.1. Isolation Amplifier Calibration...........................................................................1437.3.3. National Instruments Digital Acquisition System (DAS)......................................1477.3.4. Endace Network Monitoring Card (NMC)............................................................1487.3.5. Personal Computer (PC).....................................................................................1487.3.6. Fibre optic Ethernet Switch..................................................................................1487.4. DESCRIPTION OF MU PERFORMANCE TESTS................................................1497.4.1. Ethernet Frame Format Check and Sampled Values Recovery Test.................1497.4.2. MU GPS Timestamping Delay Test...................................................................1577.4.3. MU Process Delay Test.......................................................................................1597.4.4. Arrival Time Uniformity Test................................................................................1607.4.5. MU Conversion Error Test...................................................................................1617.4.6. MU Filter Performance Test................................................................................1637.5. DESCRIPTION OF RTDS MODELLING AND MERGING UNIT TEST PROGRAMS .......................................................................................................................................1687.5.1. RTDS Modelling...................................................................................................1687.5.2. Sampled Values Recovery Test Program...........................................................1717.5.3. Data Retrieval program for GPS Timestamping Delay.......................................172

4

7.5.4. Process Delay Test and Arrival Time Uniformity Test Program.........................1747.5.5. Data Retrieval Program for MU Error Test and MU Filter Test...........................1767.6. MERGING UNIT PERFORMANCE TESTS RESULTS.........................................1787.6.1. Ethernet Frame Format Check And Sampled Values Recovery Test................1787.6.2. GPS Timestamping Delay Test...........................................................................1797.6.3. Process Delay Test..............................................................................................1807.6.4. Arrival Time Uniformity Test................................................................................1837.6.5. Conversion Error Test..........................................................................................1867.6.5.1. Voltage Injection...............................................................................................1867.6.5.2. Current Injection...............................................................................................1887.6.6. Filter Performance Test.......................................................................................1917.6.6.1. Voltage Injection...............................................................................................1917.6.6.2. Current Injection...............................................................................................1967.7. SUMMARY..............................................................................................................200

CHAPTER 8 CONCLUSION AND FUTURE WORK........................................2028.1. CONCLUSION........................................................................................................2028.2. KNOWLEDGE CONTRIBUTIONS TO RESEARCH AREA ..................................2068.3. FUTURE WORK.....................................................................................................207

REFERENCES.................................................................................................240

5

Final Word Count: 51339

6

Index of TablesTable 2.1: Interface table for Integration scenario of Fig. 2.11 [58].....................................43Table 3.1:Comparison of IEC 61850 with 2 major protocols: IEC 60870-5 and DNP [21]. .64Table 5.1: Numerical representation of event tree model ...................................................92Table 5.2: Number of Devices in each Scenario (Double Busbar Feeder Bay (Star))........96Table 5.3: Component MTBF, Reliability and Availability....................................................97Table 5.4: Numerical Representation Of Event Tree Model ............................................100Table 5.5 :Process Bus Scenarios (Reliability).................................................................102Table 5.6: Process Bus Scenarios (Availability)................................................................104Table 5.7: Reliability of Different Scenarios For The DBB Feeder Bay (Based On Estimated Reliability figures From Table 5.5)......................................................................................106Table 6.1: Component Investment Cost And Lifetime Data ..............................................126Table 6.2: Investment Cost for Scenario 4 ........................................................................127Table 6.3: Renewal Cost for Scenario 4.............................................................................127Table 6.4: Maintenance Cost for Scenario 4......................................................................127Table 6.5: Replacement Cost for Scenario 4....................................................................128Table 6.6: Penalty Cost for Scenario 4 (Penalty Cost Factor = 0)....................................128Table 6.7: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios (Penalty Cost Factor = 0)....................................................................................................129Table 6.8: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios (Penalty Cost Factor = 400000).........................................................................................130Table 6.9: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios (Penalty Cost Factor = 21000)..........................................................................................................132Table 7.1: Isolation Amplifier Current Calibration..............................................................144Table 7.2: Isolation Amplifier Voltage Calibration..............................................................144Table 7.3: PhsMeas1 Values.............................................................................................154Table 7.4: MX attributes from Table 7.3.............................................................................155Table 7.5: Quality Attribute Type definition........................................................................155Table 7.6: GPS Timestamping Delay (GTD) Test Results...............................................180Table 7.7: Process Delay (PD) Test Results.....................................................................182Table 7.8: Merging Unit Arrival Time Uniformity (ATU) Test Results..............................185Table 7.9: MU Filter Performance Test Results (Voltage).................................................195Table 7.10: MU Filter Performance Test Results (Current)...............................................200Table A.1: Number of Devices in each Scenario (Double Busbar Feeder Bay (Ring)).....210Table A.2: Number of Devices in each Scenario (Double Busbar Transformer Bay (Star))............................................................................................................................................211Table A.3: Number of Devices in each Scenario (Double Busbar Transformer Bay (Ring))............................................................................................................................................211Table A.4: Number of Devices in each Scenario (Mesh Corner Mesh Corner Bay (Star))211Table A.5: Number of Devices in each Scenario (Mesh Corner Transformer Bay (Star)).212Table A.6: Number of Devices in each Scenario(Mesh Corner Transformer Bay (Ring)).212Table B.1: Availability of Different Scenarios For The Double Busbar Feeder Bay (Star) (Based On Estimated Availability figures)..........................................................................213Table B.2: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Star) (Based On Initial Component Reliability Set To 0.999)......................................................213Table B.3: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Estimated Reliability figures)............................................................................213

7

Table B.4: Availability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Estimated Availability figures)..........................................................................214Table B.5: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Initial Component Reliability Set To 0.999)......................................................214Table B.6: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Estimated Reliability figures)..................................................................214Table B.7: Availability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Estimated Availability figures)................................................................214Table B.8: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Initial Component Reliability Set To 0.999)............................................215Table B.9: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Ring) (Based On Estimated Reliability figures).................................................................215Table B.10: Availability of Different Scenarios For The Double Busbar Transformer (Ring) (Based On Estimated Availability figures)..........................................................................216Table B.11: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Ring) (Based On Initial Component Reliability Set To 0.999)...........................................216Table B.12: Reliability of Different Scenarios For The Mesh Corner Mesh Corner Bay (Star) (Based On Estimated Reliability figures)..................................................................216Table B.13: Availability of Different Scenarios For The Mesh Corner Mesh Corner Bay(Star) (Based On Estimated Availability figures)..........................................................217Table B.14: Reliability of Different Scenarios For The Mesh Corner Mesh Corner Bay (Star) (Based On Initial Component Reliability Set To 0.999)............................................217Table B.15: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Star) (Based On Estimated Reliability figures)............................................................................218Table B.16: Availability of Different Scenarios For The Mesh Corner Transformer Bay(Star) (Based On Estimated Availability figures)..........................................................218Table B.17: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Star) (Based On Initial Component Reliability Set To 0.999)............................................218Table B.18: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Ring) (Based On Estimated Reliability figures).................................................................218Table B.19: Availability of Different Scenarios For The Mesh Corner Transformer Bay(Ring) (Based On Estimated Availability figures).........................................................219Table B.20: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Ring) (Based On Initial Component Reliability Set To 0.999)...........................................219Table C.1: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 0)................................................................................220Table C.2: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 400000)......................................................................220Table C.3: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)..........................................................................221Table C.4: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0).........................................................................222Table C.5: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)...............................................................222Table C.6: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)...................................................................223Table C.7: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 0).........................................................................224

8

Table C.8: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 400000)...............................................................225Table C.9: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)...................................................................226Table C.10: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0).........................................................................227Table C.11: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)...............................................................228Table C.12: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)...................................................................229Table C.13: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0).........................................................................230Table C.14: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)...............................................................231Table C.15: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)...................................................................232Table C.16: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 0).........................................................................233Table C.17: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 400000)...............................................................233Table C.18: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)...................................................................234Table D.1: Process Delay (PD) and Arrival Time Results (40 Ethernet Packets)............235Table D.2: GPS Timestamp Delays (5 Injections).............................................................236Table D.3: MU1 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage Injections ranging from 10V – 120V......................................................................236Table D.4: MU2 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage Injections ranging from 10V – 120V......................................................................236Table D.5: MU3 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage Injections ranging from 10V – 120V......................................................................237Table D.6: MU1 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A............................................................................237Table D.7: MU2 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A............................................................................237Table D.8: MU3 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A............................................................................237Table D.9: MU1 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z.......................................................................238Table D.10: MU2 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z.......................................................238Table D.11: MU3 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z.......................................................238Table D.12: MU1 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z.......................................................................238Table D.13: MU2 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z.......................................................................239Table D.14: MU3 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z.......................................................................239

9

List of FiguresFig. 2.1 : Alternative Process Bus Architectures [4].............................................................34Fig. 2.2: Station Bus and Process Bus separate (Star Topology) [30].................................35Fig. 2.3: Station Bus and Process Bus separate (Process Bus Ring Topology).................36Fig. 2.4: Station Bus and Process Bus separate (Process Bus Point to point Topology) [37]..............................................................................................................................................37Fig. 2.5: Station Bus and Process Bus separate (PRP Process Bus) [37]..........................38Fig. 2.6: Station Bus and Process Bus separate (HSR Process Bus) [37]..........................38Fig. 2.7: Station Bus and Process Bus Merged (Star Topology) [30]..................................39Fig. 2.8: Station Bus and Process Bus Merged (Ring Topology) [39]..................................40Fig. 2.9: Hardware model of a computer system [58]..........................................................41Fig. 2.10: Event tree for circuit breaker closure [58].............................................................42Fig. 2.11: Integration scenario containing some circuit breaker closure functions [58].......42Fig. 2.12: Markov modelling - State transition diagram for a restorable one-element system [54] .......................................................................................................................................44Fig. 2.13: Fault tree modelling example...............................................................................46Fig. 2.14: Reliability block diagram, Series – parallel system..............................................46Fig. 2.15: Tie sets for series-parallel system in Fig. 2.14.....................................................47Fig. 2.16 Life Cycle Costing [53].........................................................................................48Fig. 2.17: Relationship between reliability and life cycle cost..............................................49Fig. 2.18: Interoperability Test ABB and Siemens [48]........................................................50Fig. 2.19: Merging unit Accuracy Test [51] ..........................................................................51Fig. 2.20: Validity of sampling accuracy and content test [52] ............................................51Fig. 2.21: Omicron SV Scout Test Arrangement [55]...........................................................52Fig. 3.1: Power System.........................................................................................................54Fig. 3.2: Substations within a power system........................................................................56Fig. 3.3: Part of Double Busbar Transmission Substation...................................................57Fig. 3.4: IEC 61850 modelling [4].........................................................................................58Fig. 4.1: Standard interface applied to a substation.............................................................68Fig. 4.2: Proposed Generic Process Bus Architecture applied to a generic substation bay69Fig. 4.3: Proposed Generic Process Bus Architecture applied across 2 generic bays (Data Flow).....................................................................................................................................70Fig. 4.4: Filter Switch Mechanism........................................................................................71Fig. 4.5: Proposed Generic Process Bus Architecture ........................................................72Fig. 4.6: High-level view of Double Bus Bar Substation Process Bus Architecture ............73Fig. 4.7: High-level view of Mesh Substation Process Bus Architecture .............................74Fig. 4.8: Double Bus Single Breaker with Bus Tie Arrangement ........................................75Fig. 4.9: Feeder Bay for 400 kV Double Busbar Substation with Non-Unit Feeder Protections [65].....................................................................................................................76Fig. 4.10: Bus Section or Bus Coupler Bay for 400 kV Double Busbar Substation (Numbering shown for a bus coupler bay) [65]....................................................................76Fig. 4.11: Transformer Bay for 400 kV Double Busbar Substation With LV........................77Fig. 4.12: Detailed Double Busbar Substation Application..................................................78Fig. 4.13: Detailed Double Busbar Substation Application – Bus Coupler Bay..................79Fig. 4.14: Detailed Double Busbar Substation Application – Bus Section Bay...................79Fig. 4.15: Detailed Double Busbar Substation Application – Feeder Bay...........................80Fig. 4.16: Detailed Double Busbar Substation Application – Transformer Bay..................81Fig. 4.17: Mesh Corner Substation with four independent mesh corner protection scheme arrangements........................................................................................................................81

10

Fig. 4.18: 400kV Mesh corner with feeder and transformer [65]..........................................83Fig. 4.19: Detailed Mesh Corner Substation Application (Filter Switch Shunt Connection) 84Fig. 4.20 : Detailed Mesh Corner Substation Application – Mesh Corner Bay...................85Fig. 4.21: Detailed Mesh Corner Substation Application – Feeder Bay..............................85Fig. 4.22: Detailed Mesh Corner Substation Application – Transformer Bay.....................86Fig. 5.1: Reliability Block Diagram - Series Methodology....................................................90Fig. 5.2: Series Parallel System [58]....................................................................................91Fig. 5.3: Event Tree Model for System shown in Fig. 5.2 [58].............................................91Fig. 5.4: Detailed Double Busbar Application – Feeder Bay................................................94Fig. 5.5: Scenario 1, Introducing the Process Bus, Star Topology......................................95Fig. 5.6: Scenario 1 Feeder Bay 1........................................................................................95Fig. 5.7: Scenario 2 Feeder Bay 1........................................................................................96Fig. 5.8: Scenario 3 Feeder Bay 1........................................................................................96Fig. 5.9: Scenario 4 Feeder Bay 1........................................................................................98Fig. 5.10: Scenario 4 Series-parallel Reliability Block Diagram...........................................99Fig. 5.11: System Reliability ..............................................................................................103Fig. 5.12: System Availability.............................................................................................105Fig. 5.13: Sensitivity analysis of the different scenarios (based on initial estimated component reliability)..........................................................................................................107Fig. 5.14: Sensitivity analysis of the different scenarios (based on initial estimated component availability).......................................................................................................107Fig. 5.15: Sensitivity analysis of the different scenarios (based on all component reliability set to 0.999)........................................................................................................................109Fig. 5.16: Sensitivity analysis of the different scenarios ....................................................111Fig. 5.17: Reliability comparison of the different scenarios................................................113Fig. 5.18: Sensitivity analysis (Double Busbar Transformer Bay)......................................115Fig. 5.19: Reliability comparison of the different scenarios (each component reliability set to 0.999)..............................................................................................................................117Fig. 5.20: Reliability comparison of the different scenarios (each component reliability set to 0.999)..............................................................................................................................119Fig. 5.21: Reliability comparison of the different scenarios (each component reliability set to 0.999)..............................................................................................................................121Fig. 6.1: Life Cycle Cost Determination..............................................................................124Fig. 6.2: Cost Versus Reliability with Penalty Cost factor 0...............................................130Fig. 6.3: Cost Versus Reliability with Penalty Cost factor 400000.....................................131Fig. 6.4: Cost Versus Reliability with Penalty Cost factor 21000.......................................132Fig. 7.1: Locamation Arrangement - Analogue Merging Unit Function..............................135Fig. 7.2: Locamation Arrangement - Digital Merging Unit Function...................................135Fig. 7.3: GE Process Bus Architecture...............................................................................136Fig. 7.4: Siemens Merging Unit Set-Up..............................................................................137Fig. 7.5: Mitsubishi Merging Unit .......................................................................................138Fig. 7.6: Mitsubishi Merging Unit........................................................................................138Fig. 7.7: Mitsubishi Merging Unit........................................................................................138Fig. 7.8: ABB Redundant system for revenue metering using Merging unit for Metering (CP-MUM)...........................................................................................................................139Fig. 7.9: ABB Merging unit for Protection(CP-MUP)..........................................................139Fig. 7.10: Merging unit Test Bed Layout............................................................................140Fig. 7.11: Merging Unit Test Bed Block Diagram...............................................................141Fig. 7.12: RTDS..................................................................................................................141

11

Fig. 7.13: Mesh Corner Substation.....................................................................................142Fig. 7.14: Amplifiers used for merging unit Test Bed.........................................................143Fig. 7.15: Calibration Results for Isolation Amplifier (2A injection)....................................146Fig. 7.16: Calibration Results for Isolation Amplifier (6V injection)....................................147Fig. 7.17: National Instruments Digital Acquisition System................................................147Fig. 7.18: Endace Network Monitoring Card (NMC)...........................................................148 Fig. 7.19: GE Fibre Optic Ethernet Switch........................................................................148Fig. 7.20: Contents of an Ethernet Frame .........................................................................150Fig. 7.21: Structure of the Header MAC.............................................................................150Fig. 7.22: Structure of the tag header ................................................................................151Fig. 7.23: Structure of the Ethertype PDU..........................................................................152Fig. 7.24: Application Protocol Data Unit (APDU), Application Service Data Units (ASDU) and Dataset........................................................................................................................153Fig. 7.25: PhsMeas1 Dataset.............................................................................................154Fig. 7.26: Merging unit GPS Timestamping Delay Test and Process Delay Test.............158Fig. 7.27: Merging unit GPS Timestamping Delay Test.....................................................159Fig. 7.28: Arrival Time Uniformity Plot................................................................................160Fig. 7.29: Merging Unit Conversion Error Test (Voltage) ..................................................162Fig. 7.30: MU Filter Performance Test (Voltage)...............................................................165Fig. 7.31: Squarewave Injection Test: Filter Analysis Curve (MU Magnitude / DAS Magnitude)..........................................................................................................................166Fig. 7.32: Sinewave Injection Test (MU Magnitude / DAS Magnitude)..............................167Fig. 7.33: DAQ Voltage Output based on 50V 50Hz injection...........................................168Fig. 7.34: DAQ and merging unit Voltage Output based on 50V 50Hz injection...............170Fig. 7.35: DAQ and merging unit Current Output based on 3AV 50Hz injection...............171Fig. 7.36: Program flow of sampled values recovery test program...................................172Fig. 7.37: Program flow of data retrieval program for GPS Timestamping Delay.............173Fig. 7.38: Program flow of Process Delay Test and Arrival Time Uniformity Test Program............................................................................................................................................175Fig. 7.39: Program flow of Data Retrieval Program for MU Error Test and MU Filter Test............................................................................................................................................177Fig. 7.40: Ethernet Frame Format Check...........................................................................179Fig. 7.41: MU1 GPS Timestamping Delay Test (400 packets)..........................................181Fig. 7.42: MU2 GPS Timestamping Delay Test (400 packets)..........................................181Fig. 7.43: MU3 GPS Timestamping Delay Test (400 packets)..........................................182Fig. 7.44: Arrival Time Uniformity Plot (400 packets) MU1................................................184Fig. 7.45: Arrival Time Uniformity Plot (400 packets) MU2................................................184Fig. 7.46: Arrival Time Uniformity Plot (400 packets) MU3................................................185Fig. 7.47: MU1 Conversion Error (Voltage)........................................................................186Fig. 7.48: MU2 Conversion Error (Voltage).......................................................................187Fig. 7.49: MU3 Conversion Error (Voltage)........................................................................187Fig. 7.50: MU1, MU2 and MU3 Conversion Error (Voltage)..............................................188Fig. 7.51: MU1 Conversion Error (Current)........................................................................189Fig. 7.52: MU2 Conversion Error (Current)........................................................................189Fig. 7.53: MU3 Conversion Error (Current) .......................................................................190Fig. 7.54: MU1, MU2 and MU3 Conversion Error (Current)...............................................190Fig. 7.55: MU and DAS output from 50V 50Hz square wave injection..............................192Fig. 7.56: MU1 Filter Performance (Voltage)....................................................................193Fig. 7.57: MU2 Filter Performance (Voltage)....................................................................194

12

Fig. 7.58: MU3 Filter Performance (Voltage)....................................................................195Fig. 7.59: MU and DAS output from 1A 50Hz square wave injection ..............................196Fig. 7.60: MU1 Filter Performance (Current)......................................................................197Fig. 7.61: MU2 Filter Performance (Current)......................................................................198Fig. 7.62: MU3 Filter Performance (Current).....................................................................199Fig. A.1: Scenario 4 - Double Busbar Feeder Bay...........................................................209Fig. A.2: Scenario 5 - Double Busbar Feeder Bay...........................................................209Fig. A.3: Scenario 6 - Double Busbar Feeder Bay...........................................................209Fig. A.4: Scenario 7 - Double Busbar Feeder Bay...........................................................209Fig. A.5: Scenario 8 - Double Busbar Feeder Bay...........................................................210Fig. A.6: Scenario 9 - Double Busbar Feeder Bay...........................................................210Fig. A.7: Scenario 10 - Double Busbar Feeder Bay,........................................................210Fig. C.1: Cost Versus Reliability with Penalty Cost factor 0...............................................220Fig. C.2: Cost Versus Reliability with Penalty Cost factor 400000.....................................221Fig. C.3: Cost Versus Reliability with Penalty Cost factor 21000.......................................221Fig. C.4: Cost Versus Reliability with Penalty Cost factor 0...............................................222Fig. C.5: Cost Versus Reliability with Penalty Cost factor 400000.....................................223Fig. C.6: Cost Versus Reliability with Penalty Cost factor 21000.......................................224Fig. C.7: Cost Versus Reliability with Penalty Cost factor 0...............................................225Fig. C.8: Cost Versus Reliability with Penalty Cost factor 400000.....................................226Fig. C.9: Cost Versus Reliability with Penalty Cost factor 21000.......................................227Fig. C.10: Cost Versus Reliability with Penalty Cost factor 0.............................................228Fig. C.11: Cost Versus Reliability with Penalty Cost factor 400000...................................229Fig. C.12: Cost Versus Reliability with Penalty Cost factor 21000.....................................230Fig. C.13: Cost Versus Reliability with Penalty Cost factor 0.............................................231Fig. C.14: Cost Versus Reliability with Penalty Cost factor 400000...................................232Fig. C.15: Cost Versus Reliability with Penalty Cost factor 21000.....................................232Fig. C.16: Cost Versus Reliability with Penalty Cost factor 0.............................................233Fig. C.17: Cost Versus Reliability with Penalty Cost factor 400000...................................234Fig. C.18: Cost Versus Reliability with Penalty Cost factor 21000.....................................234

13

LIST OF ABBREVIATIONS USED1. PB - Process Bus2. M - Metering 3. CBC - Circuit Breaker Control - CB/Disconnector Control Outputs +

Indications/Alarm Inputs4. AMU - Merging Unit - Analogues5. MMU - Merging Unit - Metering High Accuracy6. MP - Main Protection 7. BCU - Bay Control Unit – Substation Control System8. GPS - Global Positioning System9. BP - Backup Protection10. PMU - Phasor Measurement Unit/Substation Monitoring Unit11. WAN - Wide Area Network12. CVT - Capacitive Voltage Transformer 13. CT - Current Transformer14. VT - Voltage Transformer15. SCADA - Supervisory Control and Data Acquisition16. SICAP - Substation Information, Control and Protection17. NICAP - National scheme for Integrated Control and Protection18. CB - circuit breaker 19. IED - Intelligent Electronic Device20. AS3 - Architecture of Substation Secondary System 21. DBB - Double Busbar22. SAS - substation automation system23. SSD - System specification Description24. SCL - Substation Configuration Language25. VLAN - Virtual Local Area Network26. CFE - Comisión Federal de Electricidad27. TVA - Tennessee Valley Authority28. NCIT - Non-Conventional Instrument Transformer29. AEP - American Electric Power30. GE - General Electric31. PRP - Parallel Redundancy Protocol32. HSR - High-availability Seamless Redundancy33. AIS - air insulated substation34. GIS - Gas Insulated Substation35. LCC - Life cycle cost36. EPRI - Electric Power Research Institute

14

37. UCA - Utility Communication Architecture38. IEC TC - International Electrotechnical Commission Technical Committee39. MMS - Manufacturing Message Specification40. ASCI - Abstract Service Communication Interface41. SCSM - Service Communication Service Mapping 42. DER - Distributed Energy Resources43. IRIG-B - Inter-Range Instrumentation Group B44. PTP - Precision Time Protocol45. RMS - Root Mean Square46. RTU - Remote Terminal Unit47. DNP - Distributed Network Protocol48. ASDU - Application Service Data Unit

15

LIST OF PUBLICATIONS

Conferences

1. ANOMBEM, U. B. , LI, H. , CROSSLEY, P. , ZHANG, R., McTAGGART, C., "Flexible IEC 61850 Process Bus Architecture Designs to Support Life-Time Maintenance Strategy of Substation Automation Systems", CIGRE Study Committee B5 Colloquium, Jeju Korea, October 2009.

2. ANOMBEM, U. B. , LI, H. , CROSSLEY, P. , ZHANG, R. , McTAGGART, C. , "IEC 61850 Process bus architecture design and optimisation analysis", International Conference on Advanced Power System Automation and Protection, APAP, Jeju, Korea, October 2009.

3. U.B. ANOMBEM, H.Y. LI, P. CROSSLEY, R. ZHANG and C. McTAGGART; “Process Bus Architectures For Substation Automation With Consideration of Life Cycle Cost”, 10th IET DPSP Conference 2010, Manchester, UK, March 29 - April 1 2010.

4. ANOMBEM, U. B., LI, H., CROSSLEY, P., AN, W., ZHANG, R., McTAGGART, C. , “Merging Unit Interoperability Performance Testing and Assessment Tool”, CIGRE Study Committee B5 Colloquium Lausanne, Switzerland, September 12-17, 2011.

5. ANOMBEM Uzoamaka, LI Haiyu, CROSSLEY Peter, AN Wen, ZHANG Ray & MCTAGGART Craig, “Performance Testing and Assessment of Merging Units using IEC 61850”, International Conference on Advanced Power System Automation and Protection, APAP, Beijing, China October 16- 20, 2011.

Journal

1. Uzoamaka B. Anombem, Haiyu Li, Peter A. Crossley, Wen An, Ray Zhang, Craig McTaggart and David MacLeman , "Process Bus Architecture Design and Optimisation Analysis based on Life Cycle Cost Evaluation", IEEE Trans. on Smart Grid, (1st Revision Submitted May 2012).

16

ABSTRACT

As the use of renewable energy and the implementation of smart grids become more prevalent in Europe, there will be a need to ensure that the quality of power supply is not compromised during the integration of distributed generation to the main grid. Europe’s electricity networks should be flexible, accessible, reliable and economic. In the UK, National Grid has standardised its substation protection and control equipment commissioning and replacement policies, yet issues affecting system long life availability remain, one reason being long outage periods during substation secondary equipment installation, commissioning and maintenance. The present use of direct hardwired point to point connections between the primary power system plant equipment and substation secondary system protection and control devices does not allow for easy upgrading or replacement of these substation secondary devices without an outage of the primary plant or substation.

Outage and the consequent availability problems associated with secondary equipment can be addressed by the open utility communication architecture standard IEC 61850. A well-designed simple, highly reliable, secure, flexible and long-life communication IEC 61850-based architecture can help mitigate the impact of using protection and control IEDs (Intelligent Electronic Devices). Faulty IEDs can be replaced with little or no interruption to the overall operation of the substation. Interoperability is a key feature of the adoption of IEC 61850 in substations. IEC 61850-compliant protection and control devices can communicate with one another, even if they are made by different manufacturers.

This thesis has proposed a simple, long life IEC 61850 based communication architecture which is expected to be flexible and robust enough to cope with both growth and outages. Reliability analyses have been carried out on various hypothetical applications of the proposed process bus architecture to National Grid substation bays. A detailed description of how to determine the optimal process bus architecture using the life cycle cost evaluation technique has been provided. The design and implementation of a test bed used for evaluating the performance characteristics of merging units has been presented. The results of the tests have been fed back to National Grid and the manufacturers, who may then use the data to assist with the drafting of a Merging Unit Test Bed Specification, and also to help the manufacturers to make refinements to the merging units in order to make interoperability more readily achievable.

17

DECLARATION

No portion of the work referred to in the thesis has been submitted in support of an

application for another degree or qualification of this or any other university or other

institute of learning.

18

COPYRIGHT STATEMENT

i. The author of this thesis (including any appendices and/or schedules to this thesis)

owns certain copyright or related rights in it (the “Copyright”) and s/he has given

The University of Manchester certain rights to use such Copyright, including for

administrative purposes.

ii. Copies of this thesis, either in full or in extracts and whether in hard or electronic

copy, may be made only in accordance with the Copyright, Designs and Patents

Act 1988 (as amended) and regulations issued under it or, where appropriate, in

accordance with licensing agreements which the University has from time to time.

This page must form part of any such copies made.

iii. The ownership of certain Copyright, patents, designs, trade marks and other

intellectual property (the “Intellectual Property”) and any reproductions of copyright

works in the thesis, for example graphs and tables (“Reproductions”), which may

be described in this thesis, may not be owned by the author and may be owned by

third parties. Such Intellectual Property and Reproductions cannot and must not be

made available for use without the prior written permission of the owner(s) of the

relevant Intellectual Property and/or Reproductions.

iv. Further information on the conditions under which disclosure, publication and

commercialisation of this thesis, the Copyright and any Intellectual Property and/or

Reproductions described in it may take place is available in the University IP Policy

(see http://www.campus.manchester.ac.uk/medialibrary/policies/intellectual-

property.pdf), in any relevant Thesis restriction declarations deposited in the

University Library, The University Library’s regulations (see

http://www.manchester.ac.uk/library/aboutus/regulations) and in The University’s

policy on presentation of Theses.

19

ACKNOWLEDGEMENT

I would like to thank God for everything He has done for me.

I would like to acknowledge the great advice, guidance and support that my supervisor,

Dr. Haiyu Li has provided me throughout this project.

I would also like to thank Wen An, Ray Zhang, John Fitch, Peter Holliday (from National

Grid), Craig McTaggart (from Scottish Power), Zheng Luo, Feng Zhang and Senpeng Zhao

and my advisor Prof. Peter Crossley (from the University of Manchester) for all the help

they provided me with at different stages of the project.

To my parents, brothers, sisters, Felix and everyone who has had a positive impact on my

life, I say thank you.

I am very grateful to National Grid, Scottish Power and SSE (Scottish and Southern

Energy) for their financial support.

20

CHAPTER 1 INTRODUCTION

1.1. SUBSTATION AUTOMATIONA digital substation is an electrical substation which is managed by distributed Intelligent

Electronic Devices (IEDs) interconnected by communication networks [1]. It is the result of

technological changes made in substation communication. Substation devices were made

to incorporate the use of microprocessors, thus providing increased functionality of the

devices, and improving their accuracy and stability. Also, as substation communication

capabilities were improved it became possible to connect the substation devices to

Supervisory Control and Data Acquisition (SCADA) equipment. Substation personnel

could have access to relevant information via user interfaces using specialized software

running on personal computers. As computing power became greater and cheaper, it

became possible to use fewer devices to carry out the same functions as before. Due to

the integration of functions and communications within the devices, the traditional divisions

between protection, monitoring and control have become blurred and these three areas

now fall within one broad area called substation automation.

1.2. ISSUES AFFECTING THE SUBSTATIONOne of the main challenges facing the energy Industry over the coming years will be the

need to meet the global demand for electric services, which shall grow significantly, while

players in the industry seek to produce more and more energy using environmentally

sensitive and sustainable sources, and in an efficient and cost-effective manner. This is

because the global demand for energy services shall increase primarily due to population

growth, and climate change will still be a very important factor to be considered. There will

need to be an emphasis on cutting down greenhouse gas emissions arising from

generation utilising traditional fossil fuel sources, while making renewable energy

technologies more competitive. In addition, as the use of renewable energy and the

implementation of smart grids become more prevalent, there shall be more instances of

decentralised (distributed) means of power generation. The effects of distributed

21

Chapter 1 - Introduction

generation will thus play a more important role during power system planning – as the

model continues to move away from the purely central power generation, there will be a

need to ensure that the quality of power supply is not compromised during the integration

of the distributed generation model to the main grid. In the UK, a number of power stations

are scheduled to close within the next 10 years and 20GW of generation will be needed by

2020 to meet the continued demand; however, the UK must also meet the targets of

reducing greenhouse gas emissions and addressing climate change. In response to these

needs, the UK Government has adopted an energy policy promoting energy efficiency, and

a range of energy sources, including renewable energy and gas. The consequent activities

include replacements and upgrades of ageing assets, as well as construction of new

overhead power lines and substations.

In order to adapt to these activities it is thus becoming increasingly necessary to ensure

that they can be carried out with minimum outage in order to maintain life system

availability.

Substation equipment can be broadly classified into 2 categories - the primary equipment

(for example, transformers and circuit breakers), and secondary equipment (for example,

protection and control devices). National Grid has standardised its substation protection

and control equipment commissioning and replacement policies by adopting the SICAP

(Substation Information, Control and Protection) and NICAP (National scheme for

Integrated Control and Protection) philosophies. However, the issues affecting system long

life availability remain due to the following reasons:

a) Long outage periods during substation secondary equipment installation,

commissioning and maintenance

Key substation secondary equipment includes relays and control devices. Traditionally

electromechanical relays have been used in substations to gather analogue data from

Current and Voltage Transformers (CTs and VTs). An electomechanical relay is highly

reliable with a long useful lifetime (about 30 years [2] but requires one or two long outage

periods during which costly, high-risk maintenance would be carried out. It also requires

long outage periods for installation and commissioning. Advances in electronics allowed for

the advent of microprocessor-based relays, which are types of IEDs capable of performing

22

Chapter 1 - Introduction

more protection and monitoring functions than the traditional electromechanical relay. Also,

an IED, unlike an electromechanical relay, is capable of undergoing software upgrades, so

that additional functions and features can be programmed into the IED, thus keeping it up

to date without having to replace it. These software upgrades however take place every 3-

5 years, thus still leading to frequent outages involving costly, risky maintenance.

b) High cost, high risk and long outage time during hardware I/O interface

replacement

A complex network of copper cables links the CTs/VTs to the relays. The relays would

then be able to use this information provided via the cables to determine whether or not to

trip the relevant circuit breakers (CBs). Replacement of any of these cables is an

expensive risky process which would require long outage periods.

c) Short life and replacement cycle in microprocessor based electronic devices

One disadvantage of IED-type relays is that they have a shorter useful lifetime than

electromechanical relays [3]. This implies that they would require more frequent

replacements than the traditional electromechanical relays.

d) Risk of equipment spare part obsolescence and unavailability of equipment

technical support

By the time a piece of substation equipment requires the replacement of spare parts, the

company producing those types of spare parts may no longer be producing them or

providing technical support for them. Newer models of those spare parts may not be

compatible with the original substation equipment. The manufacturer may not even be in

business anymore.

In order to address the issues hindering long-term system availability, the National Grid

Architecture of Substation Secondary System (AS3) project was commissioned. The aims

of the project are to form a new policy for substation light current systems aimed at

maintaining high availability and reliability of the transmission network by balancing the

whole life-cycle risk, performance and cost of assets and develop a new architecture for

substation secondary system targeting a quicker, safer and easier approach for the

23

Chapter 1 - Introduction

installation and replacement of protection and control equipment beyond 2011. This new

architecture may be realisable if it is implemented in accordance with IEC 61850.

1.3. COMMUNICATION PROTOCOLSCommunication protocols are necessary for proper communications and data exchange

between IEDs. A communication protocol is a set of conventions governing the treatment

and especially the formatting of data in an electronic communications system [4]. These

protocols provide the translation or common language for IEDs to communicate and

exchange data with one another. There are many protocols that one can use in integration

applications, ranging from vendor-specific (proprietary) to standard protocols. Some major

power system automation protocols are IEC 60870-5 and DNP3. Others include Modbus,

Profibus and Profinet.

IEC 60870-5 IEC 60870-5 is part 5 of the IEC 60870 set of standards [5] which define systems used for

telecontrol (supervisory control and data acquisition or SCADA) in power system

automation applications. IEC 60870-5 itself has many parts such as IEC 60870-5-101

(which defines the most important user functions and actual communication functions for

the telecontrol equipment, and also defines Application Service Data Units, or ASDUs, with

time tags which could be applied in scenarios such as the temporary failure of a network),

IEC 60870-5-103 (which presents specifications for the informative interface of protection

equipment and describes 2 methods of information exchange - one based on explicitly

specified ASDUs and application procedures for transmission of “standardized” messages,

and the second which uses generic services for transmission of nearly all possible

information) and IEC 60870-5-104 (which applies to telecontrol equipment and systems

with coded bit serial data transmission for monitoring and controlling geographically

widespread processes and which enables interoperability among compatible telecontrol

equipment). The specifications of IEC 60870-5-104 present a combination of the

application layer of IEC 60870-5-101 and the transport functions provided by a TCP/IP

(Transmission Control Protocol/Internet Protocol). Within TCP/IP, various network types

can be utilized, including X.25, FR (Frame Relay), ATM (Asynchronous Transfer Mode)

and ISDN (Integrated Service Data Network). Using the same definitions, alternative

24

Chapter 1 - Introduction

ASDUs specified in other IEC 60870-5 companion standards may be combined with

TCP/IP.

DNP3 DNP [6] stands for Distributed Network Protocol. DNP3 has been adopted as an IEEE

standard (IEEE 1815).

It was developed between 1992 and 1994 by Westronic Incorporated (now GE-Harris

Canada) based on the early parts of IEC 60870-5. It is an open, non-proprietary protocol

maintained by the DNP Users Group (a users group of vendors and end users), rather than

a proprietary protocol maintained by just one vendor.

DNP was specifically developed for use in electrical utility SCADA Applications. Although a

primary focus for DNP3 was on the electric utility industry, other industries that deliver

energy, transportation services and water are also using DNP3.

DNP3 is an intelligent, robust, and efficient modern SCADA protocol which can [7]

• request and respond with multiple data types in single messages,

• segment messages into multiple frames to ensure excellent error detection and

recovery,

• include only changed data in response messages,

• assign priorities to data items and request data items periodically based on their

priority,

• respond without request (unsolicited),

• support time synchronization and a standard time format,

• allow multiple masters and peer-to-peer operations,

• and allow user definable objects including file transfer.

Modbus Modbus [8] is a messaging structure developed by Modicon (now Schneider Electric) in

1979. It is used to establish master-slave/client-server communication between intelligent

devices as well as seniors and instruments. It is also used to monitor devices using HMIs

and also to program them. Modbus is also used in RTU applications where wireless

25

Chapter 1 - Introduction

communication is required, such as in gas and oil and substation applications. It has also

been used for building, infrastructure and transportation applications. It has been

implemented by hundreds of vendors on thousands of different devices to transfer

discrete/analog I/O and register data between control devices.

Different transmission protocols exist for implementing the Modbus protocol [9]:

• Asynchronous Serial Transmission: for serial connections (over wire RS-232, 422 or 485,

fibber or radio). Two different transmission modes exist, Modbus RTU, a compact, binary

representation of the data, which is faster and is used for normal operation (hex); and

Modbus ASCII, which is human readable, and more verbose, and is used for testing

purposes.

• TCP/IP over Ethernet

• Modbus Plus: also referred to as Modbus+ or MB+ which is currently proprietary to

Modicon (Schneider Electric).

The major advantage of Modbus is its simplicity for small devices as well as the very large

range of devices that have some sort of Modbus interface. Modbus does not however

support time-stamped data.

Profibus and ProfinetProfibus (Process Fieldbus) is the fieldbus-based automation standard for Profibus and

Profinet International (PI). Profibus [10] is currently available in two forms: Profibus DP

(Decentralized Periphery) and Profibus PA (Process Automation). Profibus DP

incorporates a master-slave based polling system. The mater (for instance a PC) sends a

request message to each of the connected slaves (for example input/output devices) and

then each slave answers the prompting master with a response message. Profibus is

standardized in accordance with the IEC 61158 and IEC 61784 standards. Profibus is not

as widely used as Profibus DP. It is used for the transmission of data and power in

accordance with the IEC 61158-2 standard.

26

Chapter 1 - Introduction

Profinet [11] is the communication standard for Profibus and Profinet International (PI).

Profinet is also standardized in accordance with IEC the IEC 61158 and IEC 61784

standards. It is an open standard for Industrial Ethernet. The Profinet concept has two

perspectives: Profinet CBA (Component Based Automation) and Profinet IO (Input Output).

Profinet CBA is used for component-based machine to machine communication via

TCP/IP. It is also used for real-time communication and is applicable to modular plant

design. Profinet IO is used for real-time and isochronous real time communication between

distributed IO devices. Profinet IO follows a provider/consumer model for data exchange. A

plant implements at least one IO Controller and one or more IO Devices. The IO Controller

is usually a Programmable Logic Controller or PLC and serves as a provider of output data

to the IO Devices and serves as a consumer of input data provided by the IO Devices. The

IO Device is usually a distributed IO device. Data can be exchange in a cyclic or acyclic

manner.

1.4. MOTIVATIONOutage and the consequent availability problems associated with secondary equipment

can to an extent be addressed by the open utility communication architecture set of

standards for communication networks, IEC 61850 [5]. With the traditional protection

scheme arrangement, replacing a relay or copper cable would lead to a considerable

interruption to the substation. One of the key advantages of IEC 61850 is that it makes it

possible to replace the faulty devices without relatively little or no interruption to the overall

operation of the substation. With IEC 61850, a well-designed simple, highly reliable,

secure, flexible and long-life process bus architecture can thus help mitigate the impact of

using IEDs which have a shorter lifetime than traditional electomechanical relays. IEDs can

be linked to CTs/VTs through a 'plug and play' arrangement as described below.

An IED is connected to a device called a merging unit (MU) via a process bus. The MU,

which is hardwired to the CTs/VTs, digitizes the analogue current/voltage signals from the

CT/VTs, and sends this digitized data in a standard format to the IED through the process

bus. The use of fibre optic cables for the process bus eliminates the cost of providing

electromagnetic interference shielding for these cables. The IED can also trip a circuit

breaker via a circuit breaker Controller (CBC) connected to both the IED and CB. Some

IEDs may require information from multiple CTs/VTs. Replacing the intricate connections

27

Chapter 1 - Introduction

from such IEDs to each individual CT/VT with simpler connections to a process bus leads

to an overall use of fewer cables. The use of fewer cables means that IED disconnection

and reconnection time is reduced. IEC 61850 also supports interoperability meaning that

IEC 61850-compliant IEDs from different manufacturers would be able to communicate

with the MU, CBC, and each other, without needing any protocol converter. Utilities will not

then be restricted to using protection and devices from only one manufacturer in a

substation, and a 'plug and play' environment can be more readily achieved. The use of a

modular process bus means that it will be easier to add a new relay during expansion of

the bay.

Although some initial work has been carried out in terms of proposing different process bus

architectures and evaluating process bus reliability/availability, there is still need for a

process bus architecture that can cope with the data requirements within a bay while still

simultaneously catering for the data requirements between bays. There is a need to be

able to select an optimum process bus architecture based on specified criteria when faced

with a range of possible process bus architectures. Finally, although some previous work

on merging unit testing has been carried out, there are some additional characteristics not

currently being tested for that need to be addressed, in order to further facilitate

interoperability between relays and merging units from different manufacturers. One key

characteristic for example is the bandwidth of the Merging Unit. This characteristic is

important because the data sent tot he relay needs to be accurate enough even when the

input frequency of the analogue voltage/current signal is of the order of many kilohertz.

1.5. OBJECTIVES The objectives of this thesis are

1. To propose a simple, long life process bus architecture and to carry out detailed

reliability analyses on detailed applications of process bus architectures on the

bays of different types of substations: Double Busbar (DBB) and Mesh Corner (MC)

Substations.

28

Chapter 1 - Introduction

2. To propose an initial optimum process bus architecture based on reliability and life

cycle costing.

3. To develop a merging unit test platform that is able to evaluate the performance of

IEC 61850-9-2 Light Edition (LE) merging units made by different manufacturers.

1.6. THESIS STRUCTUREChapter 1 provides the background for the research topic as well as the motivation and

objectives.

Chapter 2 presents a description of IEC 61850-related and in particular process bus-

related work that has been carried out by others. It provides a detailed description of

reliability analysis methods currently being used to determine IEC 61850 communication

bus reliability and in particular the process bus reliability. Existing merging unit test

methodologies are also described.

Chapter 3 presents a detailed description of power systems, the smart grid and the IEC

61850 standard.

In Chapter 4, a proposed process bus architecture and its hypothetical applications to both

National Grid double busbar and mesh corner substations are described. The architecture

has been proposed based on a set of golden rules for substation protection and control

systems.

In Chapter 5, the methodology for evaluating the reliability of the individual devices making

up the process bus system, and the system as a whole is introduced. This methodology is

then applied to a case study and the results are discussed for different types of bays in the

double busbar and mesh corner substations.

In Chapter 6, the methodology for evaluating the optimum process bus architecture using

the life cycle cost methodology is discussed. This methodology is then applied to a case

29

Chapter 1 - Introduction

study and the results are discussed. The methodology is also applied to the different

double busbar and mesh corner substation bays.

Chapter 7 presents the design and implementation of a test bed used for evaluating the

performance characteristics of merging units. The currently available vendor merging units

shall be described. The results of performance tests carried out on merging units from 3

different vendors are discussed.

In Chapter 8, the conclusions, contributions and suggestions for future work are presented.

30

CHAPTER 2 LITERATURE REVIEW

2.1. INTRODUCTIONThis chapter presents a detailed description of reliability analysis methods currently being

used to determine IEC 61850 communication bus reliability and in particular the process

bus reliability. These methods include reliability block modelling, the Markov state model,

event trees, interface tables tie sets and fault tree analysis. The concept of life cycle

costing is also introduced in this chapter. Existing merging unit test methodologies are

also discussed.

2.2. IEC 61850 DESIGN PROCESS In [13], a recommended process of designing IEC 61850 substation automation systems

(SASs) is described. The design process may begin with the functional specification in the

form of a System specification Description (SSD). The next step is to select IEDs which

support the required functions. Factors such as safety, reliability and availability should be

taken into account when designing the communication architecture. To address the

problem of single point of failure for the process bus, redundancy is provided – for

instance, one process bus is connected to the Main 1 protection while a separate process

bus is connected to the Main 2 protection. The IEDs will be able to provide a Substation

Configuration Language (SCL) based description in a standardized file which can be read

and written using the appropriate system engineering tools. IEC 61850 leads to open

communication across devices [14] and this makes a robust system design even more

important. The robustness of the system can be improved by decoupling IED critical

functions from distributed functions, storing redundant configuration databases in each

IED, and using system management tools that can automatically update separate IEDs.

Recommendations are made in [15] for selecting IEC 61850 compliant equipment and

service vendors. These can be useful for utilities when designing new highly integrated

protection and control systems. In [16] it is suggested that a single network using the IEEE

1588 Precision Time Synchronisation Protocol can provide clock synchronisation.

31

Chapter 2 - Literature Review

According to [15], time-synchronized devices, if used, are typically isolated from other

zones of protection. This is to ensure that their failure or maintenance will have limited

impact on the overall substation protection system. It is possible for IEDs to provide backup

protection for other protection zones. Redundant IEDs may be assigned to the same zone.

Using redundant IEDs means it is possible for one IED to undergo maintenance while the

other IED is protecting the primary equipment. The optimum design also depends on the

geography of the substation and the cost of resulting communication equipment such as

switches, cables and plugs [17]. In [18], the use of a Virtual Local Area Network (VLAN) at

the process bus level is mentioned. A VLAN makes it possible for an Ethernet switch to

deliver data to only those switch ports/IEDs that have subscribed to the data.

2.3. IEC 61850 SITE IMPLEMENTATIONS AND TRIALSIn November 2004, the world’s first IEC 61850-based substation was installed [23] and

since then numerous installations have been carried out in different parts of the world. For

instance, in Switzerland the successful refurbishment of a 380kV Laufenburg substation

was carried out, based on IEC 61850 [24]. A stepwise (bay by bay) approach was used to

retrofit a number of bays within the substation. The IEC 61850 Main 1 and Main 2

protection devices were supplied by different manufacturers. The Main 2 protection was

installed and integrated with the existing substation automation system (SAS). There were

a few bugs discovered in the first two months of implementation, but these were eventually

resolved. In [25] the successful implementation of IEC 61850 in Mexico on a Comisión

Federal de Electricidad (CFE) integrated transmission protection and control network is

described. Use was made of IEC 61850 devices from different vendors. Suggestions were

made about points which could be considered at the different project stages (design,

communication interface testing, and functional testing). The first IEC 61850-based multi-

vendor project in the United States was carried out at a Tennessee Valley Authority (TVA)

substation [26]. In this multi-vendor project, GOOSE interoperability was successfully

achieved between IEDs from different vendors.

The previous installations mentioned above have been station bus based implementations,

mainly involving IEC 61850 based protection and control IEDs located in bays

communicating with the station control centre devices. Process bus based

implementations are not as prevalent, but more and more trials are being carried out. In the

32

Chapter 2 - Literature Review

UK, for instance, at least two ‘piggy-back’ trials [27] have been installed and commissioned

at National Grid substations. A piggy-back trial is one in which a trial system is installed in

parallel with the existing protection and control system. The controls and trips of the trial

system are however disabled. In the Areva (now Alstom) piggy back trial, a Non-

Conventional Instrument Transformer (NCIT) was installed in one substation (Osbaldwick)

and a conventional instrument transformer was installed in the other remote substation

(Thornton). Metering and Feeder protection devices were connected to these instrument

transformers according to IEC 61850 9-2 ”Light Edition” (LE) via merging units. Another set

of metering and feeder protection devices was installed using conventional connections for

reference purposes. In the Siemens piggy back trial, switchboxes (used for isolation

purposes), feeder distance and backup protection devices were installed at the National

Grid 400kV Radcliffe substation for 3 main reasons. The first reason was to assess the

performance of process IEDs with IEC 61850-9-2 LE, and investigate switchbox installation

issues. The second reason was to explore the implementation of different Ethernet

switches, using the switchbox for simulated replacement to investigate outage reduction.

The third reason was to examine the Siemens time synchronized Ethernet, again using the

switchbox for simulated replacement to confirm outage reduction benefits.

[28] describes the installation in China of a smart 110/10kV Air Insulated Substation which

included the process bus implementation together with synchronization based on IEEE

1588 time synchronization. [69] describes a pilot process bus installation commissioned in

2009, running in parallel with a conventional control and protection system in order to

enable the collection of long-term real-life experience as well as comparison of behaviour.

On the primary side a combined and fully redundant ABB CP-3 current and voltage sensor

(with merging units for protection and metering) was installed. On the secondary side were

an ABB line distance protection IED, an energy meter and an ABB busbar protection

system with three bay units. For supervision and easy access, a station bus was also

installed. [68] describes ABB's proposed refurbishment of a substation first commissioned

in 1999 in Queensland, Australia an upgrade that would include the world’s first

commercial implementation of IEC 61850-9-2 LE. The ABB merging units for the project

are tailor-made for a specific type of Non-Conventional Instrument Transformer (NCIT)

and hence are not designed to be used with other types of transformers, including

conventional Current Transformers and Voltage Transformers. [29] describes the

33

Chapter 2 - Literature Review

installation of an evaluation retrofit project for an American Electric Power (AEP) substation

in Ohio, USA, based on the General Electric (GE) HardFiber process bus solution.

2.4. PROPOSED PROCESS BUS ARCHITECTURESDifferent types of process bus architectures have been proposed in literature. The IEC

61850 standard does not specify a mandatory communication architecture for the station or

process bus; neither does it specify what type of topology should be used when applying

the station or process bus architecture (for instance, whether it should be a ring, star, point

to point or meshed topology). It however does provide examples of alternative process bus

architectures as can be seen in Fig. 2.1.

Fig. 2.1 : Alternative Process Bus Architectures [4]

With architecture 1, each bay has its own process bus segment. To allow for protection

and control equipment that require data from more than one segment, a separate station-

wide communication bus is installed, with switches or routers to each bay segment to

transmit the required data streams. With architecture 2, each process bus segment covers

more than one bay, and data streams required by more than one segment are transferred

by switches or routers. With architecture 3, all devices are connected to a single station-

wide communications bus. This requires a very high data rate on the bus, but eliminates

the need for routers. Architecture 4 operates based on a function oriented bus structure. In

34

Chapter 2 - Literature Review

this case, the bus segments are set up to correspond to protection zones. Although routers

are required, the segments can be arranged to minimize the data to be transferred

between segments.

Process bus architectures can vary depending on factors such as distance (location of

MUs and protection/control IEDs), communication capabilities (the number of ports

available in the merging units and IEDs, as they may have single ports or multiple ports),

available network bandwidth, availability considerations or communication topologies, such

as point-to-point, star or ring configurations.

2.4.1. Keeping the Process Bus and Station Bus separate[17], [30], [31], [32], [33], [34] and [37] suggest that the process bus is kept separate from

the station bus. The types of topologies proposed for the process bus in particular include

a star, ring and point to point topology.

2.4.1.1. Star Topology (Process Bus and Station Bus separate)

Fig. 2.2 below shows a proposed architecture where the process bus and station bus are

kept separate. The station bus is implemented based on a star topology. The process bus

in each of the 2 bays is also based on a star topology. In a star topology, every device has

a dedicated cable that is connected to a centralized point - the Ethernet switch.

HMI

Main Protection

Ethernet Switch

Substation Control

Backup Protection

Bay Control

Main Protection

Backup Protection

Bay Control

Ethernet Switch

Feeder 2 Feeder 2 Feeder 2Feeder 1 Feeder 1 Feeder 1

Ethernet Switch

Merging Unit

Feeder 1

Breaker IED Merging Unit

Feeder 2 Feeder 2Breaker IED

Feeder 1

Station Bus

Process Bus

Fig. 2.2: Station Bus and Process Bus separate (Star Topology) [30]

35

Chapter 2 - Literature Review

A network based on a star topology is straightforward and easy to maintain. It is also easy

to carry out troubleshooting and fault isolation tasks within a star topology. A fault may be

detected by a switch that incorporates management software, and it will be possible to spot

errors at the port level. Take the example shown in Fig. 2.2. If the Feeder 1 merging unit

fails, the switch port that it is connected to on the Ethernet Switch will indicate that

connection to the device has been lost. A star topology based network is a flexible one. A

device may be added without necessarily requiring the entire substation to be shut down.

In terms of data transfer between the merging unit and the bay level IED(s) (also

connected to the switch) , the destination device is no more than two nodes away from the

sending device - for data to reach its intended device it just passes through the switch and

then reaches the destination device, it does not go to any other device.

2.4.1.2. Ring Topology (Process Bus and Station Bus separate)

Fig. 2.3 below shows an example of a process bus implemented based on a ring topology.

Each Ethernet Switch is connected to the next and the last one is connected back again to

the first to form a ring. There is a logical gap maintained between two switches to ensure

that the data does not flow continuously in a ring. If a single cable fault occurs, the logical

gap will be closed to ensure network continuity.

Fig. 2.3: Station Bus and Process Bus separate (Process Bus Ring Topology)

A ring topology can allow for a single cable or device failure. Ring networks are relatively

easy to troubleshoot. This is because a device will become aware that a connection has

36

Chapter 2 - Literature Review

been broken when it no longer receives messages from its neighbouring device.

Maintenance is easy to carry out using this topology because a device can be isolated

while it is undergoing any upgrade/repair. It is possible to carry out expansion activities,

because a segment can be isolated while a new switch is being added to the Ethernet ring.

Data transfer between any two devices depends on the number of the devices between

them in the ring. If there are three devices between the sending and the destination device,

the data will have to pass through each of the three devices before getting to the intended

device.

2.4.1.3. Point to point Topology (Process Bus and Station Bus separate)

Fig. 2.4 below shows an example of a process bus implemented based on a point to point

topology. Each device is directly connected to relevant device(s), and no Ethernet Switch is

used.

Fig. 2.4: Station Bus and Process Bus separate (Process Bus Point to point Topology) [37]

This type of network is not easily scalable. Adding or removing a device would lead to the

addition or removal each separate cable linking that device to other devices that require

information from it. However it has the least number of nodes required for data transfer, as

the destination device is just one node away from the sending device.

2.4.1.4. Parallel Redundancy Protocol, PRP (Process Bus and Station Bus separate)

PRP is a protocol which implements redundancy in devices. It can be applied to switched

Local Area Networks (LANs) implementing any type of topology such as a ring or meshed

topology. Fig. 2.5 below shows an example of a process bus implemented based on the

Parallel Redundancy Protocol (PRP). It requires two independent networks and PRP-

compliant IEDs.

37

Chapter 2 - Literature Review

Fig. 2.5: Station Bus and Process Bus separate (PRP Process Bus) [37]

Merging Unit 1 multicasts sampled values frames to both networks. Relays 1 and 2 are

connected to both networks. Every time the Merging Unit sends a sampled value frame,

each Relay receives the same sampled value frame from both networks and discards one

of the frames. This type of connection ensures lossless transmission of critical data over

the network.

2.4.1.5. High-availability Seamless Redundancy (HSR) (Process Bus and Station Bus separate)

HSR is an application of PRP which allows for the approximate halving of the network

infrastructure or bandwidth depending on the initial protocol used (for instance if it was

PRP or RSTP (Rapid Spanning Tree Protocol) that was initially used). It is in particular

applicable to the topologies made up of rings, or rings of rings. Fig. 2.6 below shows an

example of a process bus implemented based on High-availability Seamless Redundancy

(HSR). Each device is connected to the next and the last one is connected back again to

the first to form a ring.

Fig. 2.6: Station Bus and Process Bus separate (HSR Process Bus) [37]

38

Chapter 2 - Literature Review

A sending device (for instance Merging Unit 1) sends sampled value frames over each of

its 2 ports. Every time the Merging Unit sends a sampled value frame, a destination device

(for instance Relay1) receives two identical frames from each its own 2 ports within a

certain interval and discards one of the frames. If Merging Unit 1 receives the frame that it

injected into the ring, it will not forward it. This type of connection also ensures lossless

transmission of critical data over the network.

2.4.2. Merging the Process Bus and Station BusMerging the station and process bus has been suggested in [16], [17], [30], [35], [36], [38],

and [39]. The types of topologies proposed for the merged station and process bus include

star and ring topologies.

2.4.2.1. Star Topology (Merging the Process Bus and Station Bus)

Fig. 2.7 shows an architecture similar to the one shown above in Fig. 2.2 where the station

bus is implemented based on a star topology, and the process bus in each of the 2 bays is

also based on a star topology. However, in this case [30], the station bus has been

connected to each of the bay process buses.

Fig. 2.7: Station Bus and Process Bus Merged (Star Topology) [30]

39

Chapter 2 - Literature Review

2.4.2.2. Ring and Star Topology (Merging the Process Bus and Station Bus)

Fig. 2.8 below [39] shows an example of an architecture in which the process bus and

station bus have been merged based on a ring topology. The process level and bay level

devices are connected to a bay level switch in a star topology. The bay level switches and

the station level switches are then connected to form a ring.

Fig. 2.8: Station Bus and Process Bus Merged (Ring Topology) [39]

Merging the station and process bus is possible because IEC 61850 uses the same

communication technology (Ethernet) for the process bus and the station bus. One

possible reason for merging the process and station bus together is to reduce the number

of switches used. This reduction in hardware may have a positive impact on the acquisition

cost. Keeping the process bus and station bus physically separate may however be more

useful. One main reason is that it may be easier to carry out maintenance or repair on a

particular bus, without affecting the activity on the other bus. However, the decision to use

either a fully separated process bus or a merged station and process bus would depend on

factors such as the actual application requirements and IED limitations.

40

Chapter 2 - Literature Review

2.5. IEC 61850 COMMUNICATION BUS RELIABILITY ANALYSIS METHODS

Reliability can be defined as a measure of a component or system to perform its intended

function under specified conditions for a specified period of time. It is a probability figure,

based on failure data and length of operating time [5]. The different methods of estimating

the process bus and/or station bus reliability shall now be described.

2.5.1. Interface Tables Event trees have been used together with system hardware models to show the

interdependency between the functions present in a substation control system [40, 41] or

substation automation system [42]. Such substation functions include switchgear control,

interlocking, and indications. An interface table is a reliability model that links a system

hardware model with its functional models. The hardware model provides a modular

representation of the physical modules of the system. The interface table models the

functions that are lost due to the failure of each system hardware module. Fig. 2.9 shows

an example of the hardware model of a computer system .

Fig. 2.9: Hardware model of a computer system [58]

Fig. 2.10 shows a function model of one of the many actions that occurs in a substation -

circuit breaker closure. The function model is implemented using event trees. The 3

functions to be considered for this model are substation control, synchronising, and

substation indicators.

41

Chapter 2 - Literature Review

Fig. 2.10: Event tree for circuit breaker closure [58]

There are 3 possible outcomes for each function combination:

S—Success: All functions involved in the required action are fully available and the action

is completed successfully.

MF—Manageable Failure: Although some of the functions involved are unavailable, it is

possible to complete the required action with some limitations.

F—Failure: The unavailable functions make it impossible to safely complete the required

action.

A circuit breaker closure integration scenario is shown in Fig. 2.11 (showing how the

functions are integrated in the hardware), and this is expanded in the interface table shown

in Table 2.1.

Fig. 2.11: Integration scenario containing some circuit breaker closure functions [58]

42

Chapter 2 - Literature Review

Table 2.1: Interface table for Integration scenario of Fig. 2.11 [58]

In order to determine the system reliability based on this interface table:

1. The hardware modules are represented from a reliability point of view by their

availability.

2 All possible combinations of hardware module failures are considered. For each

hardware failure combination:

a) the probability of its occurrence is calculated

b) the resulting failed functions will be obtained from the interface table.

c) The event tree then shows the system outcome (S, MF, F) resulting from

the failed functions and the probability calculated in (a) is assigned to that

outcome.

3 The system reliability is the sum of the successful outcome probabilities obtained in

2c above.

2.5.2. The Markov state modelReference [17] proposes different architectures at the station level and at the process level

and some reliability analysis is carried out on these architectures, based on the Markov

43

Chapter 2 - Literature Review

state model. The positive effect reducing the error recovery time has on improving the

safety integrity is discussed. According to [53], Markov modelling is a probabilistic method

that allows for the statistical dependence of the failure or repair characteristics of individual

components to be adapted to the state of the system. It can capture the effects of both

order-dependent component failures and changing transition rates resulting from stress or

other factors. Markov analysis is thus a method suitable for the dependability evaluation of

functionally complex system structures and complex repair and maintenance strategies.

An example of Markov modelling is illustrated Fig. 2.12 below [54], which shows the

transition diagram of a one-element system. It is assumed that there are only two states -

the up state 0 and the down state 1. λ represents the transition rate called failure rate (the

rate at which the element moves from the up state to the down state) and µ represents the

transition rate called repair rate (the rate at which the system moves from the down state to

the up state).

Fig. 2.12: Markov modelling - State transition diagram for a restorable one-element system

[54]

The reliability metric Mean Time to system Failure, is obtained using the following 2

equations

(1)

where

MTTFSi = Mean Time to System Failure, when starting with the system in state i at t = 0

(2)

qi = departure rate from state i.

44

Chapter 2 - Literature Review

qij = transition rate from state i to state j, j≠i

m = total number of states

j is also a member of the set UP (for up states)

The steady state availability is obtained using the following 2 equations

(3)

where

As = steady state availability

j is a member of the set UP (for up states)

(4)

where

Pj = steady-state probability of finding the system in state j at time t

2.5.3. Fault trees Analysis[43] makes use of fault tree analysis techniques in comparing different digital protection

schemes, one of which incorporates the use of a merging unit. A fault tree is a logic

diagram that describes what combination of component failures will cause a top event

(unwanted or undesirable event) to occur. It provides a top down modelling approach from

the top event to the individual component failure.

Shown below in Fig. 2.13 is an example of fault tree modelling:

TE = Top Event

IE = Intermediate event

D, E and F = basic events

45

Chapter 2 - Literature Review

Fig. 2.13: Fault tree modelling example

If either event F occurs or both events D and E occur, then it will lead to top event TE

occurring.

P(TE) = P(IE) + P(F) – P(IE)P(F) (5)

= P(D)P(E) + P(F) – P(D)P(E)P(F) where P(N) = probability of even N occurring

2.5.4. Tie sets methodIn [16], the protection system reliability in the process bus environment is modelled with

the use of reliability block diagrams and evaluated using the series methodology. [44]

uses reliability block diagrams to model a number of process bus architecture scenarios

and the system reliability is evaluated using the minimal tie sets method. A tie set is a set

of components connected in series representing a minimum path for system success. In a

system, a number of tie sets are effectively connected in parallel. This means that for the

system to fail all the tie sets must fail. For a tie set to fail, at least one of its components

must fail. An example of a tie set shall now be described. Fig. 2.14. shows a reliability

block diagram of four components A, B C and D. A and B are in parallel, as are C and D.

The A and B parallel combination is in series with the C and D parallel combination.

Fig. 2.14: Reliability block diagram, Series – parallel system

46

Chapter 2 - Literature Review

It can be seen from the above Fig. 2.14 that for the system to fail either A and B must both

fail, or C and D must both fail. Hence there are two tie sets. In tie set 1, T1, A and B are

modelled in series since they both need to fail for system failure. Similarly, C and D are

modelled in series since they also need to both fail for the system to fail and are

represented in tie set T2. This is illustrated in Fig. 2.15 below.

Fig. 2.15: Tie sets for series-parallel system in Fig. 2.14

The system reliability, Rs is obtained using the following equation

Rs = P(T1 …..U Tn ) (6)

where Tn = nth tie set

P(Tn) = the probability of the occurrence of Tn

2.6. SUBSTATION LIFE CYCLE COST ANALYSIS Life Cycle Costing is a useful tool in determining the optimum configuration when faced

with a range of configurations to choose from. [45], [46] and [47], apply different models

for estimating the Life Cycle Costs in substations. However, the common costs that feature

among them are the investment cost, maintenance cost and failure cost. In [45], the life

cycle costs (LCCs) are determined for an overhead transmission grid with air insulated

substations. The genetic algorithm is applied in order to minimize the LCC of a substation.

The algorithm iteratively changes the components making up the substation layout, varying

both the technology and the type of redundancy used. In each iteration step the algorithm

calculates the LCC for the current substation layout and for the next iteration step the

algorithm improves the substation layout. Every component is defined with its LCC

parameters, and then put in a component specific file card. After a certain number of

iteration steps the algorithm provides the optimal composition of the substation layout.

In [46], life cycle costing is applied as part of distribution network planning. The studied

network is 110 kV fed by a 380 kV system via 380/110 kV transformers, and consists of air

insulated substations (AIS) and is assumed to be newly built. It was seen from a study of

accumulated non delivered energy for all loads that overhead lines were responsible for 39

47

Chapter 2 - Literature Review

percent of the interruptions but only 10 percent of the non delivered energy. That was due

to the fact that most of the loads are supplied by two lines in parallel (in accordance with

the n-1 reliability criterion). Power transformers however were only responsible for 28

percent of the interruptions but accounted for 52 percent of the non delivered energy

because they were not executed in accordance with the n-1 reliability criterion.

In [47], life cycle costs of three different substation schemes are carried out. These three

schemes are: a single busbar in two sections (using Air Insulated Substation (AIS)), a

single busbar in two sections (using Gas Insulated Substation (GIS) hybrid, where the

busbar is air insulated and the circuit breaker bays are gas insulated), and a double circuit

breaker system (using AIS). The life cycle costs are compared based on two types of

networks: partially radial network and meshed network. For the partially radial network, in

which some power backup is available from surrounding stations, the single busbar

schemes are likely to be more economic. In a more pronounced radial network, with higher

outage costs, the double circuit breaker scheme (which is the most redundant station with

the lowest outage costs) is likely to be more economic. In the meshed network where the

outage costs are less significant, the single busbar scheme (using AIS) which has the

lowest investment costs and the lowest LCC is likely to be more economic.

There is still a need for a study that focuses on the IEC 61850 process bus in terms of

applying life cycle costing for the purpose of illustrating the effect of the penalty cost factor

on the optimum process bus architecture reliability.

Life cycle costing is the process of economic analysis to assess the total cost of

acquisition, ownership and disposal of a product. It provides important inputs in the

decision-making process in product design, development, use and disposal [53]. Fig. 2.16

shows the life cycle phases of a product. Life cycle costing can be applied to the whole life

cycle of a product or to parts or combinations of different life cycle phases.

Fig. 2.16 Life Cycle Costing [53]

48

Chapter 2 - Literature Review

Fig. 2.17 shows a relationship between reliability and life cycle cost. According to [53], with

increasing reliability, (all other factors held constant), the acquisition costs will generally

increase but maintenance and support costs will decrease. At a certain point, an optimum

product reliability, which corresponds to the lowest life cycle cost, is achieved.

Fig. 2.17: Relationship between reliability and life cycle cost.

2.7. MERGING UNIT TESTSThe merging unit tests that have been carried out can be divided into different categories,

such as interoperability tests and accuracy tests. There is also a commercially available

merging unit test package which shall be described.

2.7.1. Interoperability TestsOne of the key advantages that IEC 61850 offers is interoperability – the ability of IEDs

made from different manufacturers to communicate with each other without the use of

protocol converters. A number of tests have been carried out to prove the interoperability of

IEC 61850-compliant devices. In [48], two manufacturers ABB and Siemens were able to

demonstrate interoperability between their devices. They each developed their own

merging unit and distance protection relay. In addition, Siemens developed a billing meter.

These devices were connected as shown in Fig. 2.18.

49

Chapter 2 - Literature Review

Fig. 2.18: Interoperability Test ABB and Siemens [48]

The current/voltage signals from an Omicron Test Set were fed to the merging units via

sensor simulators. The MUs then converted these signals to IEC 61850 9-1 messages

which were delivered to the protection devices and meter via an Ethernet Switch. The ABB

relay received the messages from the Siemens MU while the Siemens meter and relay

both received data from the ABB MU. The Omicron Test set simulated a single phase short

circuit which led to both the ABB and Siemens relays tripping. This communication was

however based on the IEC 61850 9-1 standard.

[49] describes interoperability evaluation tests performed on three different all digital

protection systems based on an IEC-61850-9-2 process bus. These protection systems

were assembled in the Texas A&M Protection and Control Lab. A compatibility index was

applied as a means of quantifying the level of interoperability. The tested protection

systems were seen to be compatible and interoperable.

2.7.2. Merging Unit Accuracy TestsSome work on merging unit accuracy testing has also been carried out. [51] proposes a

test bed that is able to test for the accuracy of up to 2 merging units simultaneously. Fig.

2.19 shows the MU accuracy test bed setup. A GPS receiver provides synchronization to

all required devices. A signal generator generates the test scenarios. Amplifiers produce

realistic voltage/current signals. Instrument transformers step down the realistic

50

Chapter 2 - Literature Review

voltage/current signals to low level current/voltage signals. Digital measurement systems

measure and store the measured current/voltage data. Merging units produce IEC 61850

9-2 output from the low level current/voltage signals. Use is also made of a media

converter which converts optical fibre based signals to twisted pair based signals.

Fig. 2.19: Merging unit Accuracy Test [51]

The aim of the test in [52] was to verify the sampling accuracy. AC signals were fed to the

merging unit and the MU Ethernet output was compared with the analogue values

measured by a reference instrument (Fig. 2.20). It was concluded that the MU which was

tested would be able to satisfy the demands of digital substation protection units.

Fig. 2.20: Validity of sampling accuracy and content test [52]

2.7.3. Commercially Available Merging Unit Testing Product - Omicron SV Scout

A manufacturer - Omicron - has developed a commercially available measurement and

testing tool called SV Scout [55]. This tool is capable of testing merging units. Fig. 2.21

shows how it used to test merging units. The CMIRIGB synchronises the CMC Test set,

merging unit and computer running SV Scout. The CMC Test set generates analogue

51

Chapter 2 - Literature Review

voltages and currents which are accurately defined in magnitude and phase. SV Scout

captures the Sampled Values from the merging unit for a detailed assessment of the

conversion performance. For a comparison of the generated and measured values, SV

Scout can also subscribe to the Sampled Values of the test set and display them as a

reference.

Fig. 2.21: Omicron SV Scout Test Arrangement [55]

SV Scout recovers and plots the current/voltage waveforms from the sampled values

embedded in the Ethernet packets. It is also able to display phasor angle information. SV

Scout provides information about the individual samples such as decoded quality

information, zero crossings, voltage/current magnitudes, time distribution and jitter.

2.8. SUMMARYThis chapter has provided a description of IEC 61850 and in particular process bus related

work that has been carried out by others. The process bus deployment is still at a relatively

early stage when compared with station bus deployment. A number of different substation

communication (process bus and station bus) architectures have been proposed, yet there

is still a need for an architecture that can cope with the critical current, voltage and circuit

breaker data exchange required within a bay while still being able to transmit critical

process level data across adjacent bays.

Detailed descriptions of reliability analysis methods (the Markov state model, interface

tables, tie sets and fault tree analysis) have been provided. These methods have been

applied in different substation configurations in order to determine the reliability of the

52

Chapter 2 - Literature Review

station bus, process bus or a combination of both. Out of the existing methodologies,

reliability block diagram modelling together with event trees (which are described in more

detail in Chapter 5) shall be used to evaluate the reliability for the process bus architecture

scenarios introduced in this thesis. Varying levels of redundancy shall be introduced until a

process bus architecture scenario where there is full topology duplication, and the reliability

of all the architecture scenarios will be compared.

There is also still a need to be able to compare process bus architecture scenarios with the

goal of determining an optimum one. Thus, the life cycle costs of different hypothetical

process bus architecture scenarios shall also be obtained for the architecture scenarios

introduced in this thesis. The architecture with the lowest life cycle cost shall be deemed

the optimal architecture.

There is a need to test merging units prior to when they are connected to a relay, a need

for a test system that can independently assess the performance characteristics of the

merging units, as this can help promote interoperability among relays and merging units

from different manufacturers. It would also be beneficial to be able to carry out additional

tests not currently being carried out on merging units. Such tests include the GPS

Timestamping delay test (which would determine the delay that occurs when the MU

timestamps the digitized signal) and Filter performance assessment (which would check

how much of the original signal the MU is able to recover at different frequencies). In this

thesis, the design and development of a merging unit test bed which can be used to carry

out these additional tests shall be discussed.

53

CHAPTER 3 FUNDAMENTALS

3.1. INTRODUCTION

This chapter presents a description of fundamental topics, most of which shall be

periodically referred to in subsequent chapters. The topics to be described are power

systems, smart grids, the IEC 61850 standard, the station bus and the process bus.

3.2. POWER SYSTEM A power system serves to generate and deliver electrical energy to consumers and it is

expected to do so in a reliable, safe and economic manner. Fig. 3.1 shows a high level

example depicting the UK power system.

Fig. 3.1: Power System

In the example depicted above, electrical energy is produced at 22kV by generators

located in a generating station (G). Step up transformers are then used to increase the

energy voltage level to 400kV for onward transmission via transmission lines. Busbars

connect different parts of the system together. For example large industrial consumers

(such as steel mills) can be served directly via the transmission busbars. In addition, the

54

Chapter 3 - Fundamentals

22kV/400kV step up transformer is connected to the 400kV transmission lines via the

transmission busbars. The 400kV part of the power system falls under national

transmission. When the voltage is stepped down to 132kV it then falls under regional

substransmission. The voltage is stepped down to 33kV and then the distribution system is

used to connect to large commercial customers (at 11kV) or domestic and commercial

customers (400V).

3.3. SMART GRIDA smart grid is an electricity network that can intelligently integrate the actions of all users

connected to it – generators, consumers and those that do both – in order to efficiently

deliver sustainable, economic and secure electricity supplies [50]. It is a power grid which

has incorporated connectivity and automation between the different parts making up the

grid. Implementation of smart grids include the transmission and distribution grids that

undergo modernization such as increased use of variable energy resources (for example

renewable energy sources) as well as automation are monitoring capabilities for

continental bulk transmission. Advanced sensors and distributed computing technology are

expected to improve the efficiency, reliability and safety of power delivery and use, while

new or improved services can be implemented such as fire monitoring and alarms which

can automatically shut off power and constant emergency services. Analogue meters are

replaced with digital 'smart' meters which can record power usage in real time.

3.4. SUBSTATIONA substation is a node in the power system. Substations play many roles in the ultimate

delivery of power to end users [66]. The roles could include switching generators,

equipment, and AC voltages form one level to another, and/or changing AC to DC or DC to

AC. Substations vary in size, construction, cost and complexity according to voltage,

location and function. Two types of substations, the transmission substation and

distribution substation are highlighted in Fig. 3.2 below.

55

Chapter 3 - Fundamentals

Fig. 3.2: Substations within a power system

Some substations may be small, with little more than a transformer and associated

switches. Other substations may be large, with several transformers and dozens of

switches and other equipment. Although not all substations are designed to function

exactly alike, most substations perform the following functions:

• Change the voltage from one level to another

• Regulate voltage to compensate for system voltage changes

• Switch transmission and distribution circuits into and out of the grid system

• Measure electric power qualities flowing in the circuits

• Connect communication signals to the circuits

• Eliminate lightning and other electrical surges from the system

• Connect electric generation plants to the system

• Make interconnections between the electric systems of more than one utility

• Control reactive kilovolt-amperes supplied and the flow of reactive kilovolt-amperes

in the circuits

The functions above broadly fall within 2 main substation functions, protection and control.

Protection is required to identify and remove from the power system any item of plant that

suffers a fault. This ensures that a fault does not adversely affect the secure and economic

operation of the power system. Protection is typically implemented using relays. Protection

56

Chapter 3 - Fundamentals

relays read current/voltage signals from CTs, VTs and ‘trip’ (open) circuit breakers if the

readings fall outside a desired range. Control is required to facilitate manual or automatic

reconfiguration of the power system, and data acquisition. It also allows the system to be

reconfigured in response to changing conditions such as maintenance, or unexpected

changes in power demand or outage due to a fault. Part of the transmission substation

(which has been highlighted in Fig. 3.2) is expanded in Fig 3.3 below.

Fig. 3.3: Part of Double Busbar Transmission Substation

The Fig. above shows part of the components making up the transformer bay of a double

busbar transmission substation: the supergrid power transformer, the circuit breakers,

disconnectors, CT and VT. In a double busbar substation, there is a main busbar and a

backup or reserve busbar which can be used if for instance the main busbar needs to

undergo maintenance. Circuit breakers are used to make/break load and fault current (to

make current is to connect to a circuit which has some current passing through it, while to

break current is to disconnect from a circuit which has some current flowing through it).

They are used to switch generation and transmission circuits in and out of service as

required. In terms of protection, they may be used in emergencies requiring the shutdown

of power to a circuit (such as when there is a fault current in the circuit). In terms of

control, they may be used to connect or disconnect a part of the network for the redirection

of power. Circuit breakers are types of switchgear. Two other types of switchgear are

switches, which can make (but not break) fault current and make/break load current and

disconnectors, which provide physical isolation within a substation. The scope of this

project falls mainly within the transmission substation.

57

Chapter 3 - Fundamentals

3.5. IEC 61850 IEC 6I850 is a set of standards developed with the main goal of providing interoperability

between all devices in substations. Interoperability means that devices from different

manufacturers are able to effectively communicate with one another, without the need for

complex and costly protocol converters. IEC 61850 is designed to support any allocation of

functions to substation automation system devices. The flexibility in the allocation of

functions is necessary to cater for different user requirements and advances in

communication technology. The Electric Power Research Institute (EPRI) began work on a

Utility Communication Architecture (UCA) Version 1 in the early 1990s. The UCA was

developed in order to produce a consensus in the industry about device interoperability.

This work was developed further to UCA Version 2 which showed that interoperability was

indeed achievable. The UCA2 was developed further by International Electrotechnical

Commission Technical Committee (IEC TC) 57, and as a result IEC 61850 was produced.

Fig. 3.4 provides an example of how IEC 6150 is used to model substation equipment.

Fig. 3.4: IEC 61850 modelling [4]

58

Chapter 3 - Fundamentals

On the right is the picture of the type of actual equipment modelled, the circuit breakers

(labelled as the real devices in any substation). To the left of this picture is the virtual

model of the circuit breakers. All known functions in a substation automation system have

been identified and split into subfunctions (logical nodes). Many logical nodes make up a

logical device. In this example there are 3 logical nodes that make up a logical device

(Bay). One of the logical nodes is expanded. It is the logical node XCBR1, representing

one specific circuit breaker. The logical node names are standardized and XCBR

represents the common information of a real circuit breaker. The XCBR logical node

contains about 20 data classes, but 2 are shown in Fig. 3.4, Switch Position and Mode.

Each data class is made up of individual attributes. For instance, the Position data class

has data attributes (not shown in Fig. 3.4) such as ctlVal (the controllable information,

which can be set to ON or OFF), and stVal (the position of the actual circuit breaker, which

could be in intermediate-state, off, on or a bad-state). Each data class has a structure and

well-defined semantic (meaning in the context of substation automation systems).

The information represented by the data classes and their attributes are exchanged by

services according to rules and performance requirements. These services are then

mapped and implemented by a specific and concrete communication means. In this case

the mapping is implemented via the Manufacturing Message Specification (MMS) over a

TCP/IP network. The configuration language used for the data is the Substation

Configuration Language (SCL).

3.5.1. Summary of The Parts Making up IEC 61850a) Parts 1 - 6

IEC 61850 is divided into 10 main parts. Part 1 provides an introduction and overview of

IEC 61850. It provides a summary of the contents of the other parts of IEC 61850. Part 2

contains the glossary of the terminology used in the parts of the standard. Part 3 describes

the general (and in particular, quality) requirements of the communications network. It also

provides the guidelines for environmental conditions and auxiliary services. Part 4

describes the requirement of the system and project management process. It deals with

the system and IED lifecycle, quality assurance, and supporting tools for the engineering

process. Part 5 describes the communication requirements of the substation automation

59

Chapter 3 - Fundamentals

system functions. The emphasis is on identifying the communication requirements

between technical services and the substation. Part 6 specifies a Substation Configuration

Language (SCL), which is to be used for the configuration of IEDs.

b) Parts 7 - 8

Part 7 is itself made up of 4 parts. Part 7-1 provides an introduction of modelling methods,

communication principles, and information models. Part 7-2 describes the services used

for the exchange of information for different kinds of functions. It describes the Abstract

Communication Service Interface (ACSI), a virtual interface which provides abstract

information modelling methods. This interface is independent of the actual underlying

protocol stacks used. Part 7-3 deals with the abstract definitions of Common Data Classes

(CDCs) related to substation applications. It provides a list of commonly used information.

Part 7-4 makes use of the CDCs defined in part 7-3 to specify compatible data classes for

communication between IEDs. It defines specific information models for substation

automation functions.

Part 8-1 describes the Specific Communication Service Mapping (SCSM) of the ACSI

defined in IEC 61850-7-2 to Manufacturing Message Specification (MMS) and ISO/IEC

8802-3 (Ethernet) frames. It specifies a method of exchanging time-critical and non-time-

critical data through local area networks by mapping the ACSI to MMS and Ethernet

frames.

c) Parts 9- 10

Part 9 is further divided into 2 parts. Part 9-1 introduces the connection of current and

voltage transformers with a merging unit. Part 9-2 defines the Specific Communication

Service Mapping (SCSM) for the transmission of Sampled Values over Ethernet. It is an

extended mapping specification of IEC 61850-9-1 and IEC 61850-8-1 to cover sampled

value transmission over ISO/IEC 8802-3.

Part 10 defines the methods and abstract test cases for conformance testing of devices

used in substation automation systems, and the metrics to be measured within devices

according to the requirements defined in Part 5.

60

Chapter 3 - Fundamentals

3.5.2. IEC 61850 “Light Edition” (LE)A document called “Implementation Guideline for Digital Interface to Instrument

Transformers Using IEC 61850-9-2” (popularly referred to as IEC 61850 9-2 “Light Edition”

(LE) [16]) was prepared in order to support a fast market introduction and implementation

of IEC 61850 9-2. IEC 61850 does not specify logical devices, but allows for logical

devices to be described using the Substation Configuration Language (SCL). In order to

reduce the first implementations to a minimum of required services without losing

interoperability, IEC 61850 9-2 LE defines a merging unit logical device which includes a

dataset used for the transmission of sampled values. It specifies operation modes: “ON”

(when the merging unit is in normal operation mode and transmits the Ethernet packets),

“TEST” (where the merging unit transmits the Ethernet packets, but these packets are

flagged with a test indicator bit), and “OFF” (when the merging unit does not transmit any

Ethernet packet). IEC 61850 9-2 LE also provides recommendations for synchronisation

accuracy, and how the merging unit should behave when it is synchronised or if it has lost

its synchronisation signal.

3.5.3. IEC 61850 Edition 2Many parts of IEC 61850 (parts 4, 6, 7-1 to 7-4, 8-1 and 9-2) have been revised. The

revisions [20] include new concepts, models, functional extensions, clarifications,

corrections and enlarging the scope from substation automation systems to all utility

automation systems. The name of the IEC 61850 series has also been changed. It had

previously been “Communication networks and systems in substations”. The new name of

the series is “Communication networks and systems for power utility automation”, since the

scope of IEC 61850 is no longer limited to substations. IEC 61850 has been updated so

that it is also applicable to other areas such as wind turbines and hydro power plants and

distributed energy resources. The new series includes 4 new parts: parts 7-410, 7-420, 80-

1 and 90-1.

Part 7-410 specifies additional common data classes, logical nodes and data objects

required for the use of IEC 61850 in a hydro power plant.

61

Chapter 3 - Fundamentals

Part 7-420 defines IEC 61850 information models to be used in the exchange of

information with distributed energy resources (DER), which comprise dispersed generation

devices and dispersed storage devices, including reciprocating engines, fuel cells,

microturbines, photovoltaics, combined heat and power, and energy storage.

Part 80-1 is a technical specification which provides a guideline on how to exchange

information from a Common Data Class based data model using IEC 60870-5-101 or IEC

60870-5-104 between substation(s) and control centre(s).

Part 90-1 is a technical report which provides a comprehensive overview on the different

aspects that need to be considered while using IEC 61850 for information exchange

between substations.

3.6. BENEFITS OF IEC 61850IEC 61850 offers several benefits, some of which are described below:

• Devices are able to communicate with one another without the need for costly

protocol converters, hence reducing the cost of procuring such converters. In

addition, utilities are not restricted to using devices from only one manufacturer.

• Previously, for an IED to have been able to communicate with two other IEDs, a

dedicated connection between that IED and each of the other IEDs would have

been required. With IEC 61850, IEDs can be connected to different IEDs via a

single connection to a Local Area Network (LAN). It reduces the complexity of such

connections as well as installation costs associated with wiring, trenching and

ducting.

• A current or voltage transducer (via a merging unit and process bus) can

communicate with more IEDs than before, leading to reduced transducer costs. [1]

• Since naming conventions are standardized, it will be easier to migrate to new

equipment. Also, IEC 61850 makes it possible for new applications to be

developed and implemented since all the main data required for such application is

readily available and this data is presented in a standard form

62

Chapter 3 - Fundamentals

• IEC 61850 is flexible enough to allow for easy expansion, so if the network grows

and requires more IEDs, this will have little impact on the existing devices. Faulty

devices can be replaced without little or no interruption to the overall operation of

the substation. This leads to a reduction of maintenance and expansion costs.

3.7. IEC 61850 STATION BUS

The station bus is used for the complete information exchange between the station and

bay levels in a substation. At the station level, the following devices may be located – a

gateway (such as a router) which enables remote access/control, and the Station

Computer which provides the Human Machine Interface (HMI) functionality. The HMI is a

graphic screen showing alarms and switch positions, and which logs historical data that

can be used for future analysis. At the bay level, the following devices may be located - a

bay controller IED (for forwarding information and control commands between the station

and bay level), and main and backup protection devices (for sending trip commands to

open the required circuit breaker).

3.8. IEC 61850 PROCESS BUS

The process bus is used for the complete information exchange between the process and

bay levels. As mentioned above, the following devices may be located at the bay level - a

bay controller IED (for forwarding information and control commands between the station

and bay level), main and backup protection devices (for sending trip commands to open

the required circuit breaker). At the process level, the following devices may be located -

the Current Transformer (CT), Voltage Transformer (VT), merging unit (MU), Breaker IED,

and circuit breaker (CB). The MU samples the analogue signals from the CT and VT and

sends these sampled signals in a standardized format via the process bus to the protection

and control IED(s). When needed, the Protection or Control IED(s) send(s) trip commands

via the process bus to the Breaker IED which then trips the circuit breaker. The

connections between the CT, VT and the MU are proprietary; they are specific to the MU

manufacturer. Similarly, the connections between the Breaker IED and the circuit breaker

are proprietary.

A common time reference, such as a GPS, is required in order to ensure that the sampling

carried out by every merging unit located throughout the substation is synchronised. This

63

Chapter 3 - Fundamentals

will ensure that protection and control devices will have accurately timestamped

information about the voltage and current in different parts of the substation, important

when the protection and control device algorithms that are fed these current/voltage

sampled values need to determine whether or not the measured magnitude and/or phase

values are outside prescribed limits. According to [22], interpolation can also be used to

predict what the value of a sample would be at a particular time based on known time

delays.

The maturity of the process bus is not considered to be at the same level as the station

bus. A possible reason for this is that the process bus requires time critical digitized data,

whereas the station bus can cope with a delayed response time.

3.9. COMPARISON OF IEC 61850 WITH LEGACY PROTOCOLS

IEC 61850 is often referred to as a more advanced communication protocol However it

tends to be more than just a protocol in the traditional sense. IEC 61850 defines an

interface (Application Communication Service Interface - ASCI) which is independent of

the communication protocols. The ACSI services and objects can then be mapped onto a

particular protocol stack. IEC 61850 references existing protocols (such as MMS, TCP, IP

and Ethernet).

The table below shows a comparison of IEC 61850 with 2 major protocols IEC 61870-5

and DNP:

Table 3.1:Comparison of IEC 61850 with 2 major protocols: IEC 60870-5 and DNP [21]

IEC 61850 IEC 60870-5 DNPSCADA Applications:Standardized file transfer of data including quality information and timestamp data

Supported Supported

The process bussignificantly reduces wiring and EMC by connecting Circuit Breakers and

Relies on analog data which is not digitized close to source with more EMC requirements.

Relies on analog data which is not digitized close to source with more EMC

64

Chapter 3 - Fundamentals

IEC 61850 IEC 60870-5 DNPVoltage/Current Transformers to Merging Units which will digitize the analog data relatively close to source.

requirements.

Standardization: IEC Standard

Standardization: IEC Standard Standardization: IEEE Standard

Substation Configuration Language (SCL) based on XMLComplete description of device configuration

Paper documentation Paper documentation

Support for vendor independent engineering systems

Not supported or Limited support

Not supported or Limited support

Using the info from the Logical node classes, data and common data classes

Not supported Not supported

Automatic verification of online and offline configuration: Complete model can be retrieved online and authentically compared with the offline configuration XML file

Not supported Not supported

Feature-rich and optimized for LAN/WAN based (high bandwidth) applications

Used for low-bandwidth serial links and Wide Area Networks (WAN).

Byte-efficient optimized for low bandwidth applications.

IEC 61850 is relatively young, untested and hasn’t had time to evolve.

IEC 60870-5 has had more time to evolve

DNP3 has had more time to evolve

It is more complicated than the legacy protocols, and its solution is based on a whole system concept, implying a relatively steeper learning curve so it may take some time to be fully adopted by the industry.

- -

65

Chapter 3 - Fundamentals

3.10. SUMMARYIn this chapter an overview of power systems, substations, smart grids, the IEC 61850

standard, the station bus and the process bus has been provided. The crucial nature of

power grid cannot be overemphasized. Whether it is to a small or large extent, the model

of the power grid will change and the many benefits of IEC61850 over other previous

substation communication implementations (using solutions such as DNP3 for instance)

along with its 'future proof' nature should make it suitable for use at the substation and

even beyond, where there opportunities for the standard to be used in wind turbine, hydro

power, and distributed energy resource applications.

IEC 61850 is increasingly being adopted in substations at the region connecting the

secondary equipment (such the Human Machine Interface and IEDs) for critical monitoring

and control purposes, but is yet to be as extensively adopted at the extremely critical

region where the primary equipment is directly connected to the secondary equipment

using complex analogue copper cable connections. The proposed replacement of most of

these existing analogue cable connections with a fibre optic network based on IEC 61850

shall be described in the following chapter. This project mainly focuses on the connections

between the Current Transformers, Voltage Transformers, disconnectors, Circuit breakers

and the Protection and Control Intelligent Electronic Devices in a transmission substation.

66

CHAPTER 4 PROPOSED PROCESS BUS ARCHITECTURE DESIGN

4.1. INTRODUCTIONIn this chapter, a proposed IEC 61850 process bus architecture and its applications to both

the double busbar and mesh corner substation are described. The proposed architecture

was largely based on a set of golden rules for substation protection and control systems,

which any potential process bus architecture is expected to comply with.

4.2. GOLDEN RULES AND ADDITIONAL CRITERIAThe aims of designing the National Grid Architecture of Substation Secondary System

(AS3) Architectures are to:

1. Allow for the replacement of faulty IED(s) with minimum outage requirements

2. Allow for secondary bay refurbishment with minimum outage requirement

3. Simplify isolation procedures between primary and secondary systems

4. Reduce risk of maloperation

In response to this, a process bus architecture which can be applied to different types of

substations such as the double busbar and mesh corner shall be proposed. A set of

golden rules for substation protection and control systems were taken into consideration

during the design of this architecture. These golden rules were agreed on by National Gird

experts from the fields of protection, control, equipment commissioning/decommissioning,

and also by relay manufacturers including Alstom and Siemens. Although the architecture

is for National Grid, it is generic and should be readily adaptable to Scottish Power and

SSE requirements). These golden rules are:

1. All trip signals shall be received by the breakers within 10ms excluding inter-trip

send.

2. No single activity on the main 1 system shall affect the main 2 system.

3. No single failure shall result in the loss of control of more than one bay.

4. Physical facilities shall be available to isolate a bay for testing (Protection &

Control).

5. The Protection and Control application/philosophy shall be functionally identical to

the current solution.

67

Chapter 4 - Proposed Process Bus Architecture Design

6. Design of AS3 scheme standard for all bays – DBB feeder, DBB Bus Section, DBB

Bus Coupler, MC Mesh Corner, MC Transformer and MC Feeder.

7. The switching box should be located as close as possible to the primary

equipment.

The AS3 project was divided into different streams each with different objectives. One of

the objectives of AS3 Stream 1 was to develop simple, long life, reliable and standard

interfaces between the primary equipment and the secondary equipment. The standard

interfaces in substation secondary systems may be divided into critical (Station Bus and

Control bus) and extremely critical (Process Bus and GOOSE Messages). In view of this,

the following IEC 61850 architecture design rules were suggested (Fig. 4.1):

8. These interfaces connecting the station level to the bay level, (as well as the bay

level to the process level) of the substation should be vendor independent

solutions. For example, standard Ethernet switches or hubs shall be used to

configure the standard interface without the need for any special software.

IED: Intelligent Electronic Device MU: merging unit CBC: circuit breaker Controller SB: Switch Box

Fig. 4.1: Standard interface applied to a substation

9. Due to critical and extremely critical requirements, as well as security

implementation issues, the separation between the station/control buses and

process buses is necessary.

68

Chapter 4 - Proposed Process Bus Architecture Design

4.3. SYSTEM DESCRIPTION

4.3.1. Basic Architecture Concept

4.3.1.1. Data Flow (One Bay, Two Bays)Based on the above golden rules (1-7) and standard interface design rules (8-9), Fig. 4.2

shows the proposed generic architecture applied to a generic substation bay where the

• Station Bus is mainly used for the configuration, monitoring and control of the

substation secondary system equipment.

• Control Bus is mainly used for high accuracy measurement equipment, such as

metering equipment and high resolution voltage sample values across bays for

busbar protection and the

• Duplicate Interbay Process Buses are mainly used for protection equipment IEDs.

Fig. 4.2: Proposed Generic Process Bus Architecture applied to a generic substation bay

69

Chapter 4 - Proposed Process Bus Architecture Design

Each CT and VT is connected to a merging unit (MU) while each circuit breaker (CB) is

connected to a circuit breaker Controller (CBC). The CBCs and MUs are connected to the

bay process buses (PB1 and PB2). Between each CT/VT and MU (and between each CB

and CBC) is a Switch Box (SB), which is used for isolation purposes. The protection

devices (Main Protection - MP1, MP2 and Backup protection BP) are connected to the

process bus and the station bus. The dashed arrows show the bay level IED process bus

connections which are not dedicated. The Bay Control Unit (BCU) and Metering (M)

devices are connected to the control bus and station bus, while the Phasor Measurement

Unit (PMU) is connected to the Wide Area Network (WAN), as well as the control bus. The

interfaces connecting the station level to the bay level, (as well as the bay level to the

process level) are expected to be fixed, while the deployment of the bay level IEDs,

merging units and the CBC can depend on the manufacturer.

Fig. 4.3 shows the concept applied to 2 basic bays (with 1 bay highlighted), with only 1 bay

process bus (PB) in each bay. The PBs in the different bays are connected to each other

with an optional interbay process bus link. The process bus link is used within an Interbay

Process Bus to connect or isolate bays wherever necessary .

Fig. 4.3: Proposed Generic Process Bus Architecture applied across 2 generic bays (Data Flow)

70

Chapter 4 - Proposed Process Bus Architecture Design

4.3.1.2. Interbay Process Bus Link The interbay process bus link can be implemented by using a filter switch mechanism. This

filter switch mechanism is further illustrated in Fig. 4.4 below:

PB1PB1Process Bus Link

a - Series Connection

Process Bus Link

PB1PB1

b - Shunt Connection

Fig. 4.4: Filter Switch Mechanism

In Fig. 4.4a, the filter switches are connected in a series manner. The filter switch located

at the end of a bay process bus is connected to the filter switch at the beginning of the next

bay process bus. 8-1 GOOSE messaging traffic is allowed to pass through to

neighbouring bay process buses. In Fig. 4.4b, the filter switch is connected to the interbay

process bus in a shunt manner.

4.3.2. High Level Application of Generic Architecture

4.3.2.1. Generic Architecture Diagram Fig. 4.5 shows the proposed generic architecture applied to “n” number of bays.

71

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.5: Proposed Generic Process Bus Architecture

4.3.2.2. Double Busbar Generic DiagramFig. 4.6 shows a high-level view of the application of this architecture to a double bus bar

substation. The double bus bar substation shown below is made up of Bus Coupler Bay

(BCs) 1 and 2, Feeder Bays (FBs) 1 and 2 and the Bus section Bay (BS).

72

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.6: High-level view of Double Bus Bar Substation Process Bus Architecture

It can be seen that the bays are decoupled - the protection scheme for each bay operates

independently. The protection devices in one bay do not require voltage/current information

from another bay, neither do they need to be able to trip circuit breakers located in other

bays. The filter switches are therefore not used to link bays together.

4.3.2.3. Mesh Substation Generic DiagramFig. 4.7 shows a high-level view of the application of this architecture to a mesh substation.

The mesh substation consists of four independent mesh corners. Each mesh corner has

three or more bays (such as mesh corner bay, transformer bay and feeder bay).

73

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.7: High-level view of Mesh Substation Process Bus Architecture

Within each mesh corner the protection devices in one bay may need to be able to trip

circuit breakers located in other bays. The bays are thus linked by the filter switches. If any

refurbishment in a single bay is required, the other bays making up the mesh corner will

still be able to communicate with one another.

4.4. DETAILED PROCESS BUS APPLICATIONSAs mentioned in Section 4.1., CTs and VTs are connected to merging units (MUs), while

circuit breakers are connected to circuit breaker Controllers (CBCs). These connections to

MUs and CBCs are all made via Switch Boxes. The detailed applications below also

include disconnectors which are also connected to CBCs. Most of the CTs are connected

to a merging unit each, while there are some CTs that are connected to 2 merging units.

Most of the VTs are connected to 3 merging units each, and these merging units are

usually also connected to CTs. Each merging unit is then connected to either PB1, PB2 or

the Control Bus. Each circuit breaker is connected to 4 CBCs. 2 CBCs are connected to

PB1 and PB2 and the other 2 are connected to the Control Bus. Each disconnector is

74

Chapter 4 - Proposed Process Bus Architecture Design

connected to 2 CBCs. Each of these CBCs is then connected to either PB1 or the Control

Bus. In the different bays, MP1 is connected to PB1, while BP is connected to PB2. In the

case of the feeder bay, which has 3 projection IEDs (MP1, MP2 and BP), MP1 and BP are

connected to PB1, while MP2 is connected to PB2. The dashed arrows show the bay level

IED process bus connections which are not dedicated.

4.4.1. Double Busbar Applications

4.4.1.1. Double Bus Bar Arrangement A typical double bus bar substation with single breaker bus tie arrangement is shown in

Fig. 4.8 below. According to the high-level view of double busbar substation process bus

architecture in Fig. 7.6, no filter switches are required between neighbouring bays. This is

because the protection schemes for the bus coupler bay, bus section bay, feeder bay and

transformer bay are independent of one another.

Fig. 4.8: Double Bus Single Breaker with Bus Tie Arrangement

4.4.1.2. Detailed Double Bus Bar Application Figs. 4.9 - 4.11 [65] show the Feeder Bay, Bus Section, Bus Coupler Bay and Transformer

Bay of a National Grid 400kV substation prior to the introduction of the process bus. The

Figs. show the original copper connections between the current transformers, voltage

transformers and their corresponding protection and control devices.

75

Bus section

Reserve bar disconnector

Bus coupler

Feeder

Tranformer

Source

Bus coupler

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.9: Feeder Bay for 400 kV Double Busbar Substation with Non-Unit Feeder

Protections [65]

It can be seen in Fig. 4.10, that there is no VT used in the bus coupler and bus section

bays, and thus the merging units for these bays will only receive current signal inputs.

Fig. 4.10: Bus Section or Bus Coupler Bay for 400 kV Double Busbar Substation

(Numbering shown for a bus coupler bay) [65]

76

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.11: Transformer Bay for 400 kV Double Busbar Substation With LV

Connected Mechanically Switched Capacitor [65]

These diagrams do not take into account other details such as the length of the cables.

Also the connections to the CB aren't shown but there would in reality be wires linking the

protection and control equipment to the circuit breakers.

A detailed application of the proposed process bus architecture to a the National Grid

double bus bar substation is shown in Fig. 4.12. These diagrams (unlike the original hard-

wired connections) include the connection between the protection/control devices and the

relays and control devices. Unlike the generic double bus bar substation described in

section 4.3.2.2., which had 5 bays (2 bus section bays, 2 feeder bays and one bus coupler

bay), the detailed application shows 4 bays (1 feeder bay, one bus section bay, one bus

coupler bay and one transformer bay).

77

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.12: Detailed Double Busbar Substation Application

Figs. 4.13 – 4.22 show the individual bays – the Bus Coupler Bay, Bus Section Bay,

Feeder Bay and the Transformer Bay. In the Bus Coupler Bay, there are 5 Current

Transformers, (C1 – C5), 1 circuit breaker (X130) and 2 disconnectors (X134 and X136).

In total 6 MUs and 8 CBCs have been used.

78

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.13: Detailed Double Busbar Substation Application – Bus Coupler Bay

In the Bus Section Bay, as in the Bus Coupler Bay, there are 5 Current Transformers, (C13

– C18), 1 circuit breaker (X120) and 2 disconnectors (X124 and X126). Also, 6 MUs and 8

CBCs have been used in total.

Fig. 4.14: Detailed Double Busbar Substation Application – Bus Section Bay

79

Chapter 4 - Proposed Process Bus Architecture Design

In the Feeder Bay, there are 5 Current Transformers, (C7 – C11), 1 circuit breaker (X105),

3 disconnectors (X103, X104 and X106) and 1 Voltage Transformer V1. 6 MUs and 10

CBCs have been used in total.

Fig. 4.15: Detailed Double Busbar Substation Application – Feeder Bay

In the Transformer Bay, there are 13 Current Transformers, (C19 - C31), 2 circuit breakers

(X110 and X180), 3 disconnectors (X113, X114 and X116) and 1 Voltage Transformer V1.

14 MUs and 14 CBCs have been used in total.

80

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.16: Detailed Double Busbar Substation Application – Transformer Bay

4.4.2. Mesh Corner Application

4.4.2.1. Mesh Corner Substation Arrangement A typical mesh corner substation with 4 independent mesh corner protection scheme

arrangements is shown in Fig. 4.17 below.

Fig. 4.17: Mesh Corner Substation with four independent mesh corner protection scheme

arrangements

81

Chapter 4 - Proposed Process Bus Architecture Design

According to the high-level overview of Mesh Corner substation Architecture in Fig. 4.7, no

filtering switches are required between neighbouring mesh corner protection schemes.

Hence, each mesh corner application is considered independently. It is assumed that each

mesh corner is identical.

4.4.2.2. Detailed Mesh Corner ApplicationIn the feeder, mesh corner and transformer bays, the hard wired connections between the

CTs, VT and the Protection devices shall be replaced with process bus connections.

There will be a hard wired connection between the CT/VT and the merging unit, and an

Ethernet connection between the MU and the Switch (SW). Finally there will be an

Ethernet connection between the SW and the protection device. It is assumed that the

circuit breaker is hardwired to a circuit breaker Controller (CBC). Fig. 4.18 [65] shows the

detailed 400kV Mesh Corner substation with the mesh corner, feeder and transformer bay.

82

Fig. 4.18: 400kV Mesh corner with feeder and transformer [65]

83

Chapter 4 - Proposed Process Bus Architecture Design

A detailed application of the proposed process bus architecture to the 400kV National Grid

Mesh corner substation is shown in Fig. 4.19. It shows that the filter switch mechanism is

applied in a shunt manner to the each of bays making up the mesh corner.

Fig. 4.19: Detailed Mesh Corner Substation Application (Filter Switch Shunt Connection)

Figs. 4.20 – 4.22 show the individual bays – the Mesh Corner Bay, Feeder Bay, and the

Transformer Bay. In the Mesh Corner Bay, there are 6 Current Transformers, 2 circuit

breakers (X120 and X420), and 3 disconnectors (X124, X126 and X428). 106 MUs and 14

CBCs have been used in total.

84

Chapter 4 - Proposed Process Bus Architecture Design

Fig. 4.20 : Detailed Mesh Corner Substation Application – Mesh Corner Bay

In the Mesh Corner Feeder Bay, there are 3 Current Transformers, 1 disconnector and 1

Voltage Transformer V1. 5 MUs and 2 CBCs have been used in total.

Fig. 4.21: Detailed Mesh Corner Substation Application – Feeder Bay

85

Chapter 4 - Proposed Process Bus Architecture Design

In the Mesh Corner Transformer Bay, there are 6 Current Transformers, 1 disconnector, 1

circuit breaker X110 and 2 Voltage Transformers V2 and V3. 9 MUs and 6 CBCs have

been used in total.

Fig. 4.22: Detailed Mesh Corner Substation Application – Transformer Bay

4.5. ARCHITECTURE COMPLIANCE WITH GOLDEN RULESIn this subsection, the proposed architectures will be assessed based on the golden rules

which have been introduced earlier in Section 4.2:

1. All trip signals shall be received by the breakers within 10ms excluding inter-

trip send.

It is believed that this can be implemented; however this rule is not being assessed by this

current project.

2. No single activity on the main 1 system shall affect the main 2 system.

86

Chapter 4 - Proposed Process Bus Architecture Design

This is the case with the proposed architecture. The Main 1 and Main 2 systems have links

to both process buses, however the back up links are non-dedicated. Main 1 and Main 2

are thus sufficiently isolated from one another.

3. No single failure shall result in the loss of control of more than one bay.

In the Double Busbar Substation, the bays are already decoupled, therefore the failure in

one bay will not affect the operation of other bays.

In the Mesh Corner substation, a single BCU failure will not result in the loss of control of

more than one bay. In addition, a fault-tolerant Control Bus will ensure that no single failure

results in the loss of control of more than one bay.

4. Physical facilities shall be available to isolate a bay for testing (Protection &

Control).

The filter switches and Switch boxes are able to isolate a bay for testing

5. The Protection and Control application/philosophy shall be functionally

identical to the current solution.

The Protection and Control IEDs will be able to gather the same required CT and VT data

as the current solution. They will also have access to the same required circuit breakers as

they are currently to. To prevent common mode failure, the merging units/circuit breaker

controllers used for Main 1 and Main 2 may be supplied by different manufacturers, and as

mentioned in Rule 2 above, they are sufficiently isolated from one another.

6. Design of AS3 scheme standard for all bays – DBB feeder, DBB Bus Section,

DBB Bus Coupler, MC Mesh Corner, MC Transformer, MC Feeder.

As can be seen in the previous sections, the generic architecture has been consistently

applied to a DBB Feeder, DBB Bus Section, DBB Bus Coupler, MC Mesh Corner, MC

Transformer, and MC Feeder.

7. The switching box should be located as close as possible to the primary

equipment.

It is believed that this can be implemented during installation.

87

Chapter 4 - Proposed Process Bus Architecture Design

4.6. SUMMARY

A generic process bus architecture has been introduced based on National Grid protection

and control equipment application golden rules and proposed standard interface design

rules. The architecture has been largely seen to comply with these golden rules and

interface design rules. The proposed architecture has been applied to different types of

bays that may be found in double busbar and mesh corner substations. The outcomes of

these applications indicate that although the proposed generic architecture concept is quite

simple and basic, its application ranges from simple to very complex substation

arrangements. The architecture has thus been seen to be adaptable to different types of

substation configurations. The use of switchboxes provide a means of completely

separating the primary equipment from the secondary equipment and the use of filter

switches make it possible to isolate one bay from another bay. Another important point is

that the Circuit Breaker Controllers, Merging Units, Protection and Control IEDs do not all

have to be produced by the same manufacturer.

These different characteristics help ensure that there is less overall interruption to the

substation operation if maintenance work needs to be carried out, or during an expansion

of a bay.

88

CHAPTER 5 DETERMINATION OF ARCHITECTURE RELIABILITY

5.1. INTRODUCTIONThe methodology for evaluating the reliability of the individual devices/components making

up the process bus system, and then of the system as a whole shall be introduced in this

chapter. This methodology is then applied to a case study and the results are discussed

for different types of bays in the double busbar and mesh corner substations.

5.2. RELIABILITY ANALYSIS METHODOLOGY

5.2.1. Component reliabilityComponent (or device) reliability, r, is estimated using the following equation [56].

( ) exp tr tMTBF

− = ÷ (7)

where

MTBF= Mean Time Between Failure (years). MTBF is the Mean Time Between Failure

(years). It is the reciprocal of the failure rate, when it is assumed that the failure rate is

constant. For example, an MTBF of 400 years is the reciprocal of the failure rate, 1/400

failures/year [57]. It means that in a statistical population of 400 components, on average

one component is expected to fail each year.

It is assumed that the period under consideration is the 1st year, thus t = 1.

5.2.2. System reliabilityParts of the system will be modelled using a reliability block diagram. Other parts will be

modelled using an event tree.

89

Chapter 5 – Determination of Architecture Reliability

5.2.2.1. Reliability block diagram (RBD)A reliability block diagram is the graphical representation of a system’s logical structure in

terms of sub-systems and/or components. This allows the system success paths to be

represented by the way in which the blocks (sub-systems/components) are logically

connected. Though in reality a component may be made up of one of more different

components, for the purpose of the reliability analysis carried out throughout this thesis, a

component will an indivisible entity. For the same reason, devices may also be referred to

as components. The reliability blocks may be connected in series, parallel, a series/parallel

combination or in an even more complex manner.

An example of reliability block diagram modelling is illustrated in Fig. 5.1 below. It shows

the reliability diagram for a system made up of 3 components A, B and Z connected in

series.

When all components making up a system need to be working for system success, the

components are said to be in series. components A, B and Z need to be working for the

system to be operational.

Fig. 5.1: Reliability Block Diagram - Series Methodology

The reliability metric Mean Time Between Failure (MTBF) for a system in series is obtained

using the following equation

(8)

where n = nth component;

N = number of components.

5.2.2.2. Event TreesEvent trees represent a number of possible sequences of events following an initiating

event or a system failure in the form of a tree made up of different paths. The probability

90

Chapter 5 – Determination of Architecture Reliability

associated with occurrence of a specific path (sequence of events) represents a product of

conditional probabilities of all events in that path.

An example of event tree modelling is illustrated below. Figs. 5.2 and 5.3 respectively

show the reliability block diagram and event tree model of a system made up of a

series/parallel combination of components A, B and C. The components can either be

working (UP), or not working (DN). For system success, either components A and B must

be working or components A and C must be working. For the 3 components being

considered there are 8 (i.e. 23) different individual paths. The system outcome caused by

the occurrence of each path implies either success (S) or Failure (F).

Fig. 5.2: Series Parallel System [58]

DN: component has failed F: Failure, Unsuccessful OutcomeUP: component is working S: Success, Successful Outcome

Fig. 5.3: Event Tree Model for System shown in Fig. 5.2 [58]

91

Chapter 5 – Determination of Architecture Reliability

There may also be an outcome implying a degree of manageable failure (MF), but for the

example below, only outcomes implying success or failure are illustrated. The system

reliability is the sum of all the successful outcomes.

Table 5.1 below is the mathematical representation of the event tree model shown in Fig.

5.3. For each outcome, the component failure (DN) has been replaced by the probability of

competent failure q, while the component working (UP) has been replaced by the

probability that the component is working, r.

reliability of component N, rN, is the probability that component N is working

unreliability of component N, qN, is the probability that component N has failed.

rN and qN are related by the following equation

qN = 1 – rN (9)

P(Oi) is the probability of occurrence of Outcome i

Table 5.1: Numerical representation of event tree model

OutcomeNumber A B C

Outcome :Success (S)

or Failure (F)

Probability of

Outcome1 qA qB qC F P(O1)2 qA qB rC F P(O2)3 qA rB qC F P(O3)4 qA rB rC F P(O4)5 rA qB qC F P(O5)6 rA qB rC S P(O6)7 rA rB qC S P(O7)8 rA rB rC S P(O8)

System Reliability, R is the sum of successful outcome probabilities

From Table 5.1,

R = P(O6)+ P(O7) + P(O8) = (rA x qB x rC) + (rA x rB x qC) x (rA x rB x rC) (10)

92

Chapter 5 – Determination of Architecture Reliability

5.2.2.3. Component AvailabilityThe component availability a, is the probability that a component will be functioning at any

point in time [59]. It is estimated using the following equation [60].

a =1 - MTTRMTBF

(11)

where

MTTR = Mean Time to Repair, the time taken to detect and repair each component failure.

It is the average downtime per failure (years)

MTBF is as described above (in the component reliability section)

5.2.2.4. System AvailabilityBy replacing the figures for component reliability with the corresponding figures for

component availability, the system availability will be estimated using event trees and

reliability block diagrams.

5.3. RELIABILITY ANALYSIS: CASE STUDY The reliability analysis for the proposed double bus bar process bus architecture

applications shall be carried out. A combination of reliability block diagram and event tree

modelling methods shall be applied. An introductory reliability analysis has also been

carried out in [61].

5.3.1. Process Bus Architecture ScenariosFig. 5.4 shows the architecture that will be used for the case study. It is the detailed

process bus architecture applied to the feeder bay of a double busbar substation as

previously described in Chapter 4.

93

Chapter 5 – Determination of Architecture Reliability

Fig. 5.4: Detailed Double Busbar Application – Feeder Bay

Fig. 5.4 is redrawn (Fig. 5.5) to show the primary equipment connections that are

considered for this analysis. Fig. 5.5 is the first architecture scenario and includes the

Ethernet switches that are used to implement the process bus. Ethernet Switch 1(SW1)

represents Process Bus 1, Ethernet Switch 2 (SW2) represents Process Bus 2 while

Ethernet Switch 3 (SW3) represents the Control Bus. The bay level IEDs are shown – their

connections to the process bus (the fibre optic cables) are included in the reliability

analysis, but not the bay level IEDs themselves. The IED P1 incorporates the functions of

Main Protection device. P2 incorporates the functions of Main Protection 2 and the backup

protection. Control IED C incorporates control functions such as Fault recording, and

delayed auto reclosure. Each current and voltage transformer is connected to a merging

unit (MU) and each circuit breaker is connected to a circuit breaker Controller (CBC). The

merging units and circuit breaker Controllers are connected to the Ethernet Switches. The

copper cables connecting the merging units to the CTs/VT and the circuit breaker

Controllers to the circuit breakers are not considered in this reliability analysis.

94

Chapter 5 – Determination of Architecture Reliability

Fig. 5.5: Scenario 1, Introducing the Process Bus, Star Topology

Scenario 1 is redrawn without the feeder (Fig. 5.6). Also, to make it easier to show

increasing levels of redundancy, the connections have been grouped according to the

corresponding Protection or Control IED(s) and process bus connection. For instance in

the first group showing the Process Bus 1 (PB1) connections, Protection IED P1 is shown

with the connections to SW1, C1, V1 and X105. Note that X105 is shown 3 times because

it is connected to the CBCs 1 – 3. Similarly, V1 is shown 3 times because it is connected to

MUs 4 – 6. In this scenario, there are 12 Fibre optic cables (FIOCs), 3 switches, 6 merging

units and 3 circuit breaker Controllers.

Fig. 5.6: Scenario 1 Feeder Bay 1

In Scenario 2 (Fig. 5.7), redundancy is introduced in the Control Bus connections. Control

IED C is now connected to MU3 via 2 switches SW3 and SW4. There are now 14 fibre

optic cables, 4 switches, 6 merging units and 3 circuit breaker controllers.

95

Chapter 5 – Determination of Architecture Reliability

Fig. 5.7: Scenario 2 Feeder Bay 1

In order to increase the redundancy, C is also connected via the 2 switches to CBC3 in

Scenario 3 ((Fig. 5.8). This redundancy is gradually increased until each process bus has 2

Ethernet Switches, and each IED, MU and CBC is connected to the 2 Ethernet Switches in

the corresponding process bus connection group.

Fig. 5.8: Scenario 3 Feeder Bay 1

There are in total 10 scenarios, and Scenario 4 is shown below in the subsequent

subsection, and Scenarios 5-10 can be seen in APPENDIX A. In Scenario 4, there is full

star topology duplication for the control bus. In Scenarios 5 - 7, varying levels of

redundancy are further added until there is a full star topology duplication in bay process

bus 1, and in Scenarios 8 - 10, varying levels of redundancy are further added until there is

a full star topology duplication in bay process bus 2. Table 5.2 lists the number of

components used for each architecture scenario:

Table 5.2: Number of Devices in each Scenario (Double Busbar Feeder Bay (Star))

Scenario Number of DevicesSW MU CBC FIOC

1 3 6 3 122 4 6 3 143 4 6 3 154 4 6 3 16

96

Chapter 5 – Determination of Architecture Reliability

Scenario Number of DevicesSW MU CBC FIOC

5 5 6 3 186 5 6 3 197 5 6 3 208 6 6 3 229 6 6 3 2310 6 6 3 24

The tables listing the number of components used for each architecture scenario (for the

other Double Busbar substation bays and also for the Mesh Corner substation bays) can

be seen in APPENDIX A. It is important to note that the analysis for the double busbar bus

coupler bay, double busbar section bay and mesh corner feeder bay will be identical to that

of the double busbar feeder bay since the number of considered components as well as

the connections are identical.

5.3.2. Reliability Analysis

5.3.2.1. Component reliability and availabilityIt is assumed that the period under consideration for the reliability evaluation is the 1st

year, thus t = 1.

The MTTR for each component is assumed to be 48 hours

Table 5.3 shows the component MTBF based on the data presented in [60], and

engineering judgement and it also shows the corresponding reliability and availability

figures based on equations (7) and (11).

Table 5.3: Component MTBF, Reliability and Availability

Item MTBF (hours)

MTBF (years) Reliability Availability

SW 928845 106 0.9906 0.9999CBC 500000 57 0.9826 0.9999MU 500000 57 0.9826 0.9999

FIOC 30 0.9672 1

5.3.2.2. System reliability and availabilityThe system reliability will now be obtained for architecture scenario 4. Fig. 5.9 shows

Scenario 4 and as can be seen the fibre optic cables are also labelled (F1 – 16).

97

Chapter 5 – Determination of Architecture Reliability

Fig. 5.9: Scenario 4 Feeder Bay 1

In this study, it is assumed that the protection should be able to trip the circuit breaker in

the case of a fault and the control system should be able to open or close the circuit

breaker when a re-configuration of the substation is required, Both protection and control

should have access to the current and voltage measurement information. There are thus 2

requirements for system success.

1) Protection Device P1 must be connected to C1, V1 and X105 or Protection Device

P2 must be connected C2, V1 and X105.

2) Control Device C must be connected to C3, V1 and X105

In order to satisfy requirement 1, either a or b below must be true

a. SW1, MU1, CBC1 and MU4 must be functioning. Also the fibre optic cables

connecting SW1 to P1, MU1, CBC1 and MU4 must be functioning.

b. SW2, MU2, CBC2 and MU5 must be functioning. Also the fibre optic cables

connecting SW2 to P2, MU2, CBC2 and MU5 must be functioning.

In order to satisfy requirement 2, SW3, MU3, CBC3 and MU6 must be functioning. Also the

fibre optic cables connecting SW3 to P3, MU3, CBC3 and MU6 must be functioning.

Fig. 5.10 shows the resulting reliability block diagram for Scenario 4. it is a series parallel

combination made up of 3 subsystems, A, B and C. It can be seen that subsystem A is

made up of the following components connected in series: Fibre optic cables F1-4, SW1,

CBC1, MU1 and MU4. Similarly, subsystem B is made up of the following components

connected in series: Fibre optic cables F5-8, SW2, CBC2, MU2 and MU5. Subsystem C is

made up components MU3, CBC and MU6 in series with subsystem X.

98

Chapter 5 – Determination of Architecture Reliability

Fig. 5.10: Scenario 4 Series-parallel Reliability Block Diagram

The components making up subsystem A are in series, thus based on equation (I) and the

data in Table 5.3, the reliability of A is

0.9672 x 0.9906 x 0.9672 x 0.9826 x 0.9672 x 0.9826 x 0.9672 x 0.9826 ≈ 0.8225 (12)

Since B has identical components connected in an identical manner, the reliability of this

subsystem ≈ 0.8225.

Subsystem X is made up of the following components

SW1, F1, F3, F4, F5, SW2, F2, F6, F7 and F8,

SW1 and FI are in series and be replaced by a subsystem SW1*

Similarly, SW2 and F2 are in series and be replaced by a subsystem SW2*

For the system success of subsystem X, at least one of the following groups of

components/subsystems must be functioning:

1. SW1* F3 F4 F5 2. SW1* F4 F5 SW2* F6 3. SW1* F3 F5 SW2* F7 4. SW1* F3 F4 SW2* F8 5. SW1* F5 SW2* F6 F7 6. SW1* F4 SW2* F6 F8

99

Chapter 5 – Determination of Architecture Reliability

7. SW1* F3 SW2* F7 F8 8. SW2* F6 F7 F8 9. SW1* F3 SW2* F7 F8 10. SW1* F4 SW2* F6 F8 11. SW1* F5 SW2* F6 F7 12. SW1* F4 F5 SW2* F6 13. SW1* F3 F5 SW2* F7 14. SW1* F3 F4 SW2* F8

For the 8 components/subsystems being considered there are 256 (i.e. 28) different

individual paths. These paths are numerically (partially) represented in part in Table 5.4.

Table 5.4: Numerical Representation Of Event Tree Model

(O/C : Outcome; O/C Prob: Outcome Probability)

O/C

No. SW1* F3 F4 F5 SW2* F6 F7 F8

Outcome:Success (S) or

Failure (F)

O/C

Prob.

1 qSW1* qF3 qF4 qF5 qSW2* qF6 qF7 qF8 F 02 qSW1* qF3 rF4 qF5 qSW2* qF6 qF7 rF8 F 03 qSW1* qF3 qF4 qF5 qSW2* qF6 rF7 qF8 F 04 qSW1* qF3 qF4 qF5 qSW2* qF6 rF7 rF8 F 0....

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.

.254 rSW1* rF3 rF4 rF5 rSW2* rF6 qF7 rF8 S 0.0255255 rSW1* rF3 rF4 rF5 rSW2* rF6 rF7 qF8 S 0.0255256 rSW1* rF3 rF4 rF5 rSW2* rF6 rF7 rF8 S 0.7515

Based on the data in Table 5.4

rSW1* = 0.9906 x 0.9672= 0.9581rF3 = 0.9672rF4 = 0.9672rF5 = 0.9672rSW2* = 0.9906 x 0.9672 = 0.9581rF6 = 0.9672rF7 = 0.9672rF8 = 0.9672

Reliability of subsystem X is the sum of successful outcome probabilities. Use was made

of an event tree program developed in Java to derive the reliability of subsystem X.

100

Chapter 5 – Determination of Architecture Reliability

rX = 0.98764

Since Subsystem C is made up components MU3, CBC and MU6 in series with subsystem

X,

The reliability of subsystem C = 0.9826 x 0.9826 x 0.9826 x 0.98764 ≈ 0.9370 (13)

A and B are in parallel thus based on equation (i) the reliability of the A-B parallel

combination

= 1- ( (1- 0.8225) x (1- 0.8225 ) ) ≈ 0.9685 (14)

Therefore the system reliability for architecture Scenario 4

= 0. 9685 x 0.98764 ≈ 0.9076 (15)

The system availability is derived in exactly the same manner as the system reliability

described above.

5.4. ARCHITECTURE RELIABILITY: RESULTS AND DISCUSSION

5.4.1. System Reliability and Availability ComparisonTable 5.5 shows the reliability figures obtained for all the proposed scenarios of the double

busbar and mesh corner substation bays, based on the event tree and series parallel

methodology introduced in the previous section. As mentioned in section 5.3.1., the

analysis for the double busbar bus coupler bay, double busbar section bay and mesh

corner feeder bay will be identical to that of the double busbar feeder bay since the number

of considered components as well as the connections are identical. The reliability results

for the double busbar coupler, bus section and mesh corner feeder bays will thus be the

same as that of the double busbar feeder bay.

101

Chapter 5 – Determination of Architecture Reliability

Table 5.5 :Process Bus Scenarios (Reliability)

(note DBB: Double Busbar, MC: Mesh Corner, xf: Transformer * DBB Feeder bay results identical to DBB Bus Section, DBB Bus Coupler and MC Feeder

bay results)

Scenario

DBB Feeder

Bay(star)

*

DBB Feeder

Bay(ring)

*

DBB xf Bay(star)

DBB xf Bay(ring)

MC Mesh

Corner Bay

(star)

MC xf Bay(star)

MC xf Bay(ring)

1 0.7967 0.7858 0.7486 0.7594 0.8500 0.8243 0.81252 0.8216 0.8349 0.7721 0.8068 0.9128 0.8502 0.86333 0.8475 0.9028 0.7963 0.8724 0.9187 0.8760 0.87334 0.9076 0.9116 0.8528 0.8778 0.9249 0.8810 0.87835 0.9119 0.9238 0.8604 0.8838 0.9304 0.8859 0.88326 0.9163 0.9300 0.8680 0.8898 0.9363 0.8913 0.88897 0.9266 0.9312 0.8755 0.8958 0.9421 0.8964 0.89188 0.9281 - 0.8831 0.8962 0.9453 0.8991 0.89469 0.9297 - 0.8907 0.8990 0.9487 0.9017 -10 0.9334 - 0.8912 0.9020 0.9517 0.9046 -11 - - 0.9012 0.9051 0.9549 0.9073 -12 - - 0.9041 0.9082 0.9581 - -13 - - 0.9071 0.9113 - - -14 - - 0.9100 - - - -15 - - 0.9129 - - - -16 - - 0.9158 - - - -

Fig.s 5.11 a and b show the plot of the reliability figures against the architecture scenarios

based on the data presented in Table 5.5. As expected, the reliability improves as the

redundancy is increased, with the most reliable architecture scenario for each bay being

the one which has the highest level of redundancy. It can also be seen that for each bay,

the reliability of the most reliable ring architecture is slightly lower than that of the most

reliable star architecture. The Mesh Corner Mesh Corner Bay only had the star

architecture, as there were not enough components to be hypothetically considered for a

ring architecture

102

Chapter 5 – Determination of Architecture Reliability

a. DBB Feeder bay (star and ring), MC xf bay (star and ring)

(note DBB: Double Busbar, MC: Mesh Corner, xf: Transformer DBB Feeder bay results identical to DBB Bus Section, DBB Bus Coupler and MC Feeder

bay results)

0.74

0.79

0.84

0.89

0.94

0.99

0 2 4 6 8 10 12 14 16 18Scenario Number

Rel

iabi

lity

DBB xf ring DBB xf star MC mc star

b. DBB xf bay (star and ring), MC MC bay (star)

(note DBB: Double Busbar, MC: Mesh Corner, xf: Transformer)

Fig. 5.11: System Reliability

Table 5.6 shows the availability figures obtained for all the proposed scenarios of the DBB

and Mesh Corner substation bays.

103

Chapter 5 – Determination of Architecture Reliability

Table 5.6: Process Bus Scenarios (Availability)(note MC: DBB: Double Busbar, Mesh Corner, xf: Transformer

* DBB Feeder bay results identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

Scenario

DBB Feeder

Bay(star)

*

DBB Feeder

Bay(ring)

*

DBB xf Bay(star)

DBB xf Bay(ring)

MC Mesh

Corner Bay

(star)

MC xf Bay(star)

MC xf Bay(ring)

1 0.99893 0.99888 0.99893 0.99888 0.99948 0.99921 0.999162 0.99911 0.99924 0.99911 0.99924 0.99990 0.99939 0.999523 0.99929 0.99971 0.99929 0.99971 0.99990 0.99957 0.999524 0.99971 0.99971 0.99971 0.99971 0.99990 0.99957 0.999525 0.99971 0.99971 0.99971 0.99971 0.99990 0.99957 0.999526 0.99971 0.99971 0.99971 0.99971 0.99990 0.99957 0.999527 0.99971 0.99971 0.99971 0.99971 0.99990 0.99957 0.999528 0.99971 - 0.99971 0.99971 0.99990 0.99957 0.999529 0.99971 - 0.99971 0.99971 0.99990 0.9995710 0.99971 - 0.99971 0.99971 0.99990 0.9995711 - - 0.99971 0.99971 0.99990 0.9995712 - - 0.99971 0.99971 0.9999013 - - 0.99971 0.99971 - - -14 - - 0.99971 - - - -15 - - 0.99971 - - - -16 - - 0.99971 - - - -

Fig.s 5.12 a and b show the plot of the availability figures against the architecture

scenarios based on the data presented in Table 5.6. Again the system availability

improves across the bays as the redundancy is increased, although it gets to a point where

the increase in availability is not as steep when compared with reliability. Also, especially

for the double busbar feeder bay and transformer bay, the difference in availability

between the most available ring and the star is much less than that seen in the case of

reliability.

104

Chapter 5 – Determination of Architecture Reliability

0.9988

0.9990

0.9992

0.9994

0.9996

0.9998

0 2 4 6 8 10 12 14 16 18

Scenario Number

Ava

ilabi

lity

DBB fdr ring MC xf ring MC xf star DBB fdr star

a. DBB Feeder bay (star and ring), MC xf bay (star and ring)

(note MC: DBB: Double Busbar, Mesh Corner, xf: Transformer DBB Feeder bay results identical to DBB Bus Section, DBB Bus Coupler and MC Feeder

bay results)

0.99880

0.99900

0.99920

0.99940

0.99960

0.99980

1.00000

0 2 4 6 8 10 12 14 16 18

Scenario Number

Ava

ilabi

lity

DBB xf ring DBB xf star MC mc star

b. DBB xf bay (star and ring), MC MC bay (star)

(note MC: DBB: Double Busbar, Mesh Corner, xf: Transformer)

Fig. 5.12: System Availability

The reliability of the feeder bay process bus architecture has however been seen to be less

than that of the hardwired copper-based connections (prior to the introduction of the

process bus). Taking the double busbar feeder bay as an example, the estimated reliability

of the most reliable feeder bay process bus architecture was 0.9334. The reliability of the

105

Chapter 5 – Determination of Architecture Reliability

hardwired copper-based connection was 0.9994. It has to be taken into consideration that

these system reliability figures have been based on estimated component reliability figures.

If it is assumed that the component reliability figures are equally set to 0.9999 then the

system reliability will be greater than that of the hardwired copper-based connections.

5.4.2. Sensitivity Analysis - Effects of Device Reliability on System Reliability

5.4.2.1. Double Busbar Feeder Bay (Double Busbar Bus Coupler Bay, Double Busbar Section Bay and Mesh Corner Feeder Bay) Process Bus (Star)

Table 5.7 shows the results of the sensitivity analysis carried out based on the process bus

reliability figures in Table 5.5. The Scenario Column lists the scenario numbers. It is

followed by 5 reliability columns. The 1st reliability column lists the initial reliability figures.

The 2nd reliability column lists the reliability figures obtained when the reliability of only the

Ethernet Switches (SW) is increased to 0.9999. Similarly the next 3 reliability columns list

the reliability figures obtained when the reliability of the CBCs, MUs and FIOCs

respectively are increased to 0.9999. Fig. 5.13 shows the effect of these reliability

improvements on each scenario in terms of percentage increase in reliability. A similar

analysis has been carried out based on availability and the plot (based on Table B.1,

APPENDIX B) can be seen in Fig. 5.14.

Table 5.7: Reliability of Different Scenarios For The DBB Feeder Bay (Based On Estimated Reliability figures From Table 5.5)

(note DBB: Double Busbar, MC: Mesh CornerDBB Feeder bay results identical to DBB Bus Section, DBB Bus Coupler and MC Feeder

bay results)Scenarios Initial Only SW

set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.7967 0.8064 0.8148 0.8330 0.93612 0.8216 0.8319 0.8403 0.8591 0.93623 0.8475 0.8583 0.8668 0.8861 0.93634 0.9076 0.9121 0.9282 0.9490 0.94525 0.9119 0.9163 0.9323 0.9528 0.94526 0.9163 0.9206 0.9365 0.9568 0.94527 0.9266 0.9295 0.9463 0.9660 0.9458

106

Chapter 5 – Determination of Architecture Reliability

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

8 0.9281 0.9310 0.9475 0.9668 0.94589 0.9297 0.9325 0.9487 0.9676 0.9458

10 0.9334 0.9357 0.9515 0.9694 0.9462

Fig. 5.13: Sensitivity analysis of the different scenarios (based on initial estimated component reliability)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

Fig. 5.14: Sensitivity analysis of the different scenarios (based on initial estimated component availability)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

107

Chapter 5 – Determination of Architecture Reliability

It can be seen that increasing the reliability of the fibre optic cables in the first 3 scenarios

leads to the highest increases in system reliability. With each subsequent scenario, as the

system reliability increases, the impact of the fibre optic cables on reliability improvement is

reduced. The same can be said of the Ethernet Switches, though the reduction of the

impact on reliability is not as steep as that of the fibre optic cables. The increase in system

reliability is higher in MUs than that of the CBCs. Also the system reliability improvement

due to the increase in MU and CBC reliability are almost constant throughout all scenarios.

The latter can be attributed to the fact that in all scenarios, it is only the MUs and CBCs

which do not vary in number. The same is true of the availability analysis in Fig. 5.14.

However the influence due to improvements in the individual component categories is

much less, indeed the highest impact seen is in Scenario 1 where the improvement is

approximately 0.07% when compared with approximately 18% in the reliability analysis.

This is due to the fact that the initial availability of the components is already much higher

than the initial reliability of the components. The trends are still similar as the impact of

fibre is much higher for the less available scenarios (1 – 3) and then tends to be negligible

for the more available scenarios (4 - 10). The MUs and CBCs had a consistent impact

across all the scenarios and finally the improvements in switch reliability had the least

impact overall.

The results in Table 5.5 do not take into account the fact that apart from the MUs and

CBCs, the reliability of the devices are different. Increasing the reliability of a device to

0.9999 would increase the reliability of that device by a higher percentage than for another

device, and hence affect their relative increase in system reliability. Also these reliability

figures are estimates and the actual reliability may be higher than what was estimated. For

these reasons mentioned above, the sensitivity analysis was repeated, this time with the

reliability of all devices set to 0.999 after which the reliability of each device category was

in turn increased to 0.9999 (Table B.2, APPENDIX B). Fig. 5.15 shows the new plot based

on the new analysis.

108

Chapter 5 – Determination of Architecture Reliability

Fig. 5.15: Sensitivity analysis of the different scenarios (based on all component reliability set to 0.999)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

It is seen that the actual percentage increases have generally dropped when compared

with Fig. 5.13, but there are still similarities between Figs 5.13 and 5.15. The impact of the

fibre cable is still the greatest in the 1st 3 scenarios and this impact drops steeply in

subsequent scenarios. Also the MU and CBC reliability increase still have a constant

impact on the system reliability improvement, with the MUs’ still being higher than that of

the CBCs’.

The sensitivity analysis for the other bays shall now be discussed and the tables used for

the plots can be found in APPENDIX B.

5.4.2.2. Double Busbar Feeder Bay (Double Busbar Bus Coupler Bay, Double Busbar Section Bay and Mesh Corner Feeder Bay) Process Bus (Ring)

Fig. 5.16a-c show the effect of system reliability (or availability) improvements on each

scenario in terms of percentage increase in reliability, availability and the reliability (when

the reliability of all individual devices is set to the same value) respectively for the Ring-

topology based Process Bus architecture applied to the Double Busbar Feeder Bay. The

109

Chapter 5 – Determination of Architecture Reliability

results are identical to the Double Busbar Bus Coupler Bay, Double Busbar Section Bay

and Mesh Corner Feeder Bay .

a. Comparison of percentage increase in system reliability due to increase in component category reliability (based on initial estimated component reliability)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

b. Comparison of percentage increase in system availability due to increase in component category availability (based on initial estimated component availability)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

110

Chapter 5 – Determination of Architecture Reliability

c. Comparison of percentage increase in system reliability due to increase in component category reliability (each component reliability set to 0.999)

(note DBB: Double Busbar, MC: Mesh CornerResults identical to DBB Bus Section, DBB Bus Coupler and MC Feeder bay results)

Fig. 5.16: Sensitivity analysis of the different scenarios

There are fewer proposed scenarios (7) than for the star based architecture. However the

trend is the same as that of the star based architecture: the fibre has the highest impact for

the less reliable scenarios and then this impact drastically reduces as the architecture

becomes more reliable. Both the MU and CBC have a consistent impact across all

scenarios and the Ethernet switch has the lowest overall impact on system reliability. With

the reliability of all components set to 0.999 (c), the impact of the switches and the fibre is

seen to be negligible for more reliable scenarios. The same can be said of the availability

(b). In terms of consistency, an increase in the MU reliability is seen to have the greatest

impact on the system reliability.

5.4.2.3. Double Busbar Transformer Bay Process Bus (Star)Fig. 5.17a-c show the effect of reliability (or availability) improvements on each scenario in

terms of percentage increase in reliability, availability and the reliability (when the reliability

of all individual devices is set to the same value) respectively for the double busbar bay

(star based architecture).

111

Chapter 5 – Determination of Architecture Reliability

a. Comparison of percentage increase in system reliability due to increase in component category reliability (based on initial estimated component reliability)

b. Comparison of percentage increase in system availability due to increase in component category availability (based on initial estimated component availability)

112

Chapter 5 – Determination of Architecture Reliability

c. Comparison of percentage increase in system reliability due to increase in component category reliability (each component reliability set to 0.999)

Fig. 5.17: Reliability comparison of the different scenarios

In Fig. 5.17a it can be seen that there are more proposed scenarios (16) than for the feeder

bay process bus architecture The impact trend is the same as that of the feeder bay

process bus architecture: the fibre has the highest impact on the less reliable scenarios

and then this impact drastically reduces as the architecture becomes more reliable. The

MU and CBC have a consistent impact across all scenarios and the Ethernet switch has

the lowest overall impact on system reliability. The availability trends (Fig. 5.17b) are also

similar as the impact of fibre is much higher for the less available scenarios (1 – 3) and

tends to be negligible for the more available scenarios (4 -10). The MUs and CBCs had a

consistent impact across all the scenarios and finally the improvements in switch reliability

had the least impact overall. With the reliability of all devices set to 0.9999 (Fig. 5.17c), the

impact of the fibre is more pronounced in the less reliable scenarios. (Scenarios 1 -2 ). it

has the highest impact on reliability, but in the more reliable scenarios 4 – 16, it mostly ties

with the MU in terms of having the highest impact on reliability. The component with the

next highest impact is the CBC followed by the switch.

113

Chapter 5 – Determination of Architecture Reliability

5.4.2.4. Double Busbar Transformer Bay Process Bus (Ring)

Fig. 5.18a-c show the effect of reliability (or availability) improvements on each scenario in

terms of percentage increase in reliability, availability and the reliability (when the reliability

of all individual devices is set to the same value) respectively for the double busbar

transformer bay (ring based architecture).

a. Comparison of percentage increase in system reliability due to increase in component category reliability (based on initial estimated component reliability)

114

Chapter 5 – Determination of Architecture Reliability

b. Comparison of percentage increase in system availability due to increase in component category availability (based on initial estimated component availability)

c. Comparison of percentage increase in system reliability due to increase in component category reliability (each component reliability set to 0.999)

Fig. 5.18: Sensitivity analysis (Double Busbar Transformer Bay)

It can be seen from Fig.s 5.18a-c the SWs make their highest impact on only the 1st 2

scenarios, after which their impact reduces, even in Fig. 5.18a and even more drastically

so in Fig. 5.18b and c. the same trend is also seen with the fibre. As usual, the impact of

MU and CBC on the reliability is steady throughout. The MU has the highest overall impact

on the availability and reliability, followed by the CBC, fibre and finally the switches.

5.4.2.5. Mesh Corner Mesh Corner Bay Process Bus (Star)Fig. 5.19a-c show the effect of reliability (or availability) improvements on each scenario in

terms of percentage increase in reliability, availability and the reliability (when the reliability

of all individual devices is set to the same value) respectively for the mesh corner mesh

corner bay (star based architecture).

115

Chapter 5 – Determination of Architecture Reliability

a. Comparison of percentage increase in system reliability due to increase in component

category reliability

b. Comparison of percentage increase in system availability due to increase in component

category availability

116

Chapter 5 – Determination of Architecture Reliability

c. Comparison of percentage increase in system reliability due to increase in component category reliability

Fig. 5.19: Reliability comparison of the different scenarios (each component reliability set to 0.999)

In Fig. 5.19a, it can be seen that unlike with the other previously mentioned bays, the fibre

has overall the highest impact. Its impact is consistently higher than the other devices

impact until the top 2 reliable scenarios (11 – 12). The MU and the CBCs have almost an

equal impact. The component with the lowest impact is the switch. In terms of availability,

(Fig. 5.19b) the fibre only has the highest impact in Scenario 1, (the least available

scenario), and a negligible impact in more available scenarios. The switch has a relatively

small impact in Scenario 1, and a negligible impact in the more available scenarios. The

MU has virtually no impact on all the scenarios, while the CBC has the highest overall

impact, being the only device to have an impact in all scenarios. When the reliability of all

devices is set to 0.9999 (Fig. 5.19c), the results are similar to that shown in Fig. 5.19b

obtained for the availability.

5.4.2.6. Mesh Corner Transformer Bay Process Bus (Star)Fig. 5.20a-c show the effect of reliability (or availability) improvements on each scenario in

terms of percentage increase in reliability, availability and the reliability (when the reliability

of all individual devices is set to the same value) respectively for the Mesh Corner

Transformer bay (star architecture).

117

Chapter 5 – Determination of Architecture Reliability

a. Comparison of percentage increase in system reliability due to increase in component

category reliability

b. Comparison of percentage increase in system availability due to increase in component

category availability

118

Chapter 5 – Determination of Architecture Reliability

c. Comparison of percentage increase in system reliability due to increase in component

category reliability

Fig. 5.20: Reliability comparison of the different scenarios (each component reliability set to

0.999)

In Fig. 5.20a the fibre has the highest impact on reliability followed by the MU, CBC and

the switch respectively. In terms of availability, (Fig. 5.20b), and when the reliability of

components is set to 0.9999 (Fig. 5.20c), the fibre and switch only have an impact on the

less reliable/available scenarios (1 and 2), while the MU has the highest overall impact

followed by the CBC.

5.4.2.7. Mesh Corner Transformer Bay Process Bus (Ring)

Fig. 5.21a-c show the effect of reliability (or availability) improvements on each scenario in

terms of percentage increase in reliability, availability and the reliability (when the reliability

of all individual devices is set to the same value) respectively for the Mesh Corner

Transformer bay (Ring architecture).

119

Chapter 5 – Determination of Architecture Reliability

a. Comparison of percentage increase in system reliability due to increase in component

category reliability

b. Comparison of percentage increase in system availability due to increase in component

category availability

120

Chapter 5 – Determination of Architecture Reliability

c. Comparison of percentage increase in system reliability due to increase in component

category reliability

Fig. 5.21: Reliability comparison of the different scenarios (each component reliability set to

0.999)

For the Mesh Corner Transformer bay (ring architecture), the fibre (Fig. 5.21a) has the

highest impact on reliability followed by the MU, the switch and the CBC respectively. In

terms of availability, (Fig. 5.21b), the fibre also has the highest impact, but this time the

switch, MU and CBC are tied for the next highest impact on availability. Finally when the

reliability is set to 0.9999, the switch now has the overall highest impact on system

reliability while the CBC, MU and fibre are tied for the next highest impact except Scenario

1, while the fibre has the highest impact.

5.5. SUMMARYIn this chapter, the methodology for evaluating the reliability of the process bus has been

described. A combination of reliability block diagram and event tree modelling methods

have been applied to the proposed double bus bar and mesh corner process bus

architecture scenarios. By using estimated component reliability and cost data, the

reliability, availability of these architecture scenarios have been evaluated and compared.

The impact of certain types of devices on the process bus system reliability has been

studied. It has been seen that in all bays with a star or ring alternative (the mesh corner

mesh corner bay had the sole option of using a star based architecture, but other bays

could incorporate either a star based or ring based architecture) the reliability figure of the

121

Chapter 5 – Determination of Architecture Reliability

most reliable star architecture scenario was higher than that of the most reliable ring based

architecture scenario.

From the sensitivity analysis carried out, it could be seen that the system reliability was

overall most likely to improve when the merging units' reliability was increased, although

there were a few times when the greatest system reliability improvement was due to an

improvement in the reliability of the fibre optic cables, switches or the circuit breaker

controllers. Also it was seen that on most occasions, in the first one or two scenarios when

the system was less reliable/available, the fibre optic cables had a higher impact on system

reliability.

122

CHAPTER 6 DETERMINATION OF OPTIMUM ARCHITECTURE

6.1. INTRODUCTIONThe process bus Life cycle cost Methodology as a means of selecting the optimum

architecture is introduced in this chapter.

6.2. LIFE CYCLE COST ANALYSIS METHODOLOGYLife cycle costing is the methodology used in determining the optimal process bus

architecture. The Life cycle cost of a high voltage (HV) Substation is made up [45] of Cost

of Investment CI(t), Cost of operation CO(t) and renewal cost CR(t), as can be seen in Fig.

6.1 and equation (16). The Cost of Operation is divided into maintenance and failure cost.

A system failure results in a penalty cost for undelivered energy (including profit losses) as

well as the component replacement cost. The costs are calculated for the expected

duration of the substation designed lifetime. The life cycle cost (LCC) is estimated as

follows:

LCC (t) = CI(t) + CR(t) + CO(t) (16)

where

CI is the investment cost - the cost of acquiring the components

CR is the renewal cost - the cost of replacing the components at the end of their designed

lifetimes

CO is the cost of operation - the cost of using the components during their designed

lifetimes

t is the expected substation duration lifetime

123

Chapter 6 - Determination Of Optimum Architecture

Fig. 6.1: Life Cycle Cost Determination

The investment cost CI is estimated as follows

1 =

n

ii

CI(t) Inv=

∑ (17)

where

n = number of components

Invi = investment cost of the ith component

The renewal cost CR is estimated as follows

CR(t) = 1

n

i ii

Nren Inv=

×∑ (18)

where

n = number of components

Invi = investment cost of the ith component

Nreni = number of times the ith component will be renewed

The operation cost CO is estimated as follows

124

Chapter 6 - Determination Of Optimum Architecture

CO(t) = CM(t) + CF(t) (19)

where

CM = maintenance cost

CF = failure cost

The maintenance cost CM is estimated as follows

CM(t) = 1 1

n m

iji j

C= =

∑ ∑ (20)

where

n = number of components

m = number of maintenance activities for a particular component

Cij = cost of carrying out the jth maintenance activity on the ith component.

The failure cost CF is estimated as follows

CF(t) = CCR(t) + CP(t) (21)

where

CCR = replacement cost - the cost of replacing the components in the event of a failure

CP = penalty cost - the cost of undelivered service as a result of the downtime

The replacement cost CCR is estimated as follows

CCR(t) = 1

* ( )n

iCrepi Fi t

=∑ (22)

where

Crepi = component replacement price

Fi = ith component failure probability

The penalty cost CP is estimated as follows

CP (t) = kp * Fs * tsRep (23)

where

125

Chapter 6 - Determination Of Optimum Architecture

kp = penalty cost factor

Fs = system failure probability

tsRep = system repair time

Some assumptions were made during the estimation of the life cycle cost:

a) All component prices are estimated and relative.

b) All component designed lifetimes are estimated.

c) System repair time tsRep = Period of consideration * system unavailability.

d) Reliability and availability figures are constant during the useful lifetime of the

components.

e) Net Present Value is not considered.

6.3. LIFE CYCLE COST ANALYSIS: CASE STUDYIn the previous chapter, Section 5.3. described how the reliability analysis methodology

was applied to a process bus architecture scenario which served as a case study. The life

cycle cost will now be obtained for that same architecture scenario. Introductory life cycle

cost analyses have also been carried out in [70] and [71].

Some assumptions were made during the estimation of the life cycle cost:

• Maintenance cost is 1% of investment cost

• Maintenance is carried out every 5 years

• Penalty cost factor is applied in factors of 24hrs

• Period under consideration = 40 years

• Maintenance is carried out every 5 years

Table 6.1 shows the component Investment Cost and lifetime estimates.

Table 6.1: Component Investment Cost And Lifetime Data

Device Investment Cost Lifetime (Years)SW 1000 15MU 3500 15

CBC 3500 15

126

Chapter 6 - Determination Of Optimum Architecture

Device Investment Cost Lifetime (Years)FIOC 200 25

Investment cost CI has been estimated based in equation 17 and the results are shown

in Table 6.2

Table 6.2: Investment Cost for Scenario 4

Component Unit Investment

Cost

Quantity Inv[Unit Investment Cost x Quantity]

SW 1000 4 4000MU 3500 6 21000

CBC 3500 3 10500FIOC 200 16 3200

System Investment cost 38700

The renewal cost CR has been estimated based in equation 18 and the results are

shown in Table 6.3.

Table 6.3: Renewal Cost for Scenario 4

Component Npur: No. of times component will be

purchased over 40yr period

Nren: No. of times component will be

renewed[Npur - 1]

Nren x Inv[Nren x Unit

Investment Cost x Quantity]

SW 8 7 28000MU 3 2 42000

CBC 3 2 21000FIOC 2 1 3200

System Renewal cost 94200

The maintenance cost CM has been estimated based in equation 20 and the results are shown in Table 6.4.

Table 6.4: Maintenance Cost for Scenario 4

Component Uman: Unit Maintenance

Cost

Nman: No. of maintenance

activities

Component Maintenance Cost [Quantity x Uman x

Nman]SW 10 0 0MU 35 5 1050

127

Chapter 6 - Determination Of Optimum Architecture

Component Uman: Unit Maintenance

Cost

Nman: No. of maintenance

activities

Component Maintenance Cost [Quantity x Uman x

Nman]CBC 35 5 525FIOC 2 6 192

System maintenance Cost 1767

The replacement cost CCR has been estimated based in equation 22 and the results are

shown in Table 6.5.

Table 6.5: Replacement Cost for Scenario 4

Component Urep: Unit Replacement

Cost

Crep: Component

Replacement Cost [Quantity x

Urep]

F: component Failure

probability[1 - component

reliability]

Crep * F * period under consideration

SW 1000 4000 0.0094 1504MU 3500 10500 0.0174 14616

CBC 3500 21000 0.0174 7308FIOC 200 3200 0.0328 4198.4

System Replacement Cost 27626.4

The Penalty cost CP has been estimated based in equation 23 and the results are shown

in Table 6.6.

Table 6.6: Penalty Cost for Scenario 4 (Penalty Cost Factor = 0)

Kp: penalty

cost factor

Fs: System Failure

probability[1 - System reliability]

U: System Unavailability

[1 - System Availability]

Period under consideration

(yrs)

tsRep: System repair time

(hrs)[U x period

under consideration]

Penalty cost

[Kp * Fs * tsRep/24]

0 0.09 0 40 101.45 0

Operational Cost CO(t) = Maintenance Cost + Failure Cost (24)

CO(t)= 1767 + (27626.4 + 0.00) = 29393.4 (25)

128

Chapter 6 - Determination Of Optimum Architecture

Life Cycle Cost for Scenario 4 = CI(t) + CR(t) + CO(t)

= 38700 + 94200 + 29393.4 ≈ 162293.4 (26)

Alternatively,Life Cycle Cost for Scenario 4 = CIRM (t) + CF(t) (27)

where CIRM(t) is the sum of CI(t), CR(t) and CM(t)

LCC = ( 38700 + 94200 + 1767) + 27626.4 ≈ 162293.4 (28)

6.4. OPTIMUM ARCHITECTURE: RESULTS AND DISCUSSION The results of the process bus reliability analysis carried on the double bus bar feeder bay

shall now be discussed. As noted in the reliability analysis, the results for the double

busbar feeder, DBB Feeder bay, DBB Bus Section, DBB Bus Coupler and MC Feeder bay

are identical. The effects of device reliability on the process bus system reliability are also

studied. The penalty cost factor is varied and its impact on the life cycle cost and

subsequent optimum process bus architecture reliability is discussed.

6.4.1. Life Cycle Cost Comparison - Double Busbar Feeder Bay (Star)

Table 6.7 shows the (investment, failure and life cycle) costs for each process bus scenario

for the feeder bay, using a penalty cost factor of 0. As the penalty is 0, the resulting failure

cost is low and it can be seen (Fig. 6.2) that the failure cost has little or no impact on the

life cycle cost and naturally the life cycle cost will increase as reliability increases. In this

situation the optimum will automatically be the scenario which had the lowest investment

cost, which is Scenario 1. The optimum process bus architecture reliability is 0.797.

Table 6.7: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios

(Penalty Cost Factor = 0)

129

Chapter 6 - Determination Of Optimum Architecture

Scenario Reliability Investment Renewal andMaintenance

Cost

Failure Cost Life Cycle Cost

1 0.7967 125019 26201 1512202 0.8216 133843 27102 1609453 0.8475 134255 27364 1616194 0.9076 134667 27626 1622935 0.9119 143491 28527 1720186 0.9163 143903 28790 1726937 0.9266 144315 29052 1733678 0.9281 153139 29953 1830929 0.9297 153551 30215 18376610 0.9334 153963 30478 184441

Fig. 6.2: Cost Versus Reliability with Penalty Cost factor 0

If the penalty cost factor is extremely high (for instance 400000 as shown in Table 6.8 and

Fig. 6.3), the failure cost has a much greater impact on the LCC, thus the optimum

architecture will be the one with the highest reliability (Scenario 10). The optimum process

bus architecture reliability is now 0.933

Table 6.8: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios

(Penalty Cost Factor = 400000)

130

Chapter 6 - Determination Of Optimum Architecture

Scenario Reliability Investment Renewal andMaintenance

Cost

Failure Cost Life Cycle Cost

1 0.7967 125019 1297856 14228752 0.8216 133843 953028 10868713 0.8475 134255 656265 7905204 0.9076 134667 183911 3185785 0.9119 143491 177466 3209576 0.9163 143903 170133 3140367 0.9266 144315 152788 2971038 0.9281 153139 151105 3042449 0.9297 153551 148692 30224310 0.9334 153963 142742 296705

IRM Cost: Investment, Renewal and Maintenance Cost

Fig. 6.3: Cost Versus Reliability with Penalty Cost factor 400000

The penalty cost factor may fall in between these extremely low or high values (say 21000,

as shown in Fig. 6.4 and Table 6.9) and the resulting optimum architecture reliability would

lie in between the minimum or maximum reliability. In this example, the optimum

architecture reliability - 0.908 - corresponds to Scenario 4. It can thus be seen that the

penalty cost factor influences the optimum process bus architecture reliability.

131

Chapter 6 - Determination Of Optimum Architecture

Table 6.9: Reliability And Cost Data For Mesh Corner Bay Process Bus Scenarios (Penalty

Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance

Cost

Failure Cost Life Cycle Cost

1 0.7967 125019 92963 2179822 0.8216 133843 75713 2095563 0.8475 134255 60381 1946364 0.9076 134667 35831 1704985 0.9119 143491 36346 1798376 0.9163 143903 36210 1801137 0.9266 144315 35548 1798638 0.9281 153139 36313 1894529 0.9297 153551 36435 18998610 0.9334 153963 36372 190335

IRM Cost: Investment, Renewal and Maintenance Cost

Fig. 6.4: Cost Versus Reliability with Penalty Cost factor 21000

The tests were repeated for the Double Busbar Feeder Bay (Ring), Double Busbar

Transformer Bay (Star and Ring), Mesh Corner Mesh Corner Bay (Star), Mesh Corner

Transformer Bay (Star and Ring). The results can be seen in APPENDIX C. The trends

were seen to be similar to that observed for the Double Busbar Feeder Bay (Star): the

132

Chapter 6 - Determination Of Optimum Architecture

higher the penalty cost factor, the higher the impact that failure cost has on the Life cycle

cost. In addition, the higher the penalty cost factor, the higher the optimum process bus

architecture scenario reliability.

6.5. SUMMARYIn this chapter the process bus Life cycle cost methodology has been introduced and

applied to different process bus architecture scenarios. It has been shown how Life Cycle

Costing can be used as an optimum process bus architecture selection methodology. As

the quantities which have been used in determining the Life Cycle Cost are estimates, it

may be better utilized as one of many tools that can be used in the decision making

process. It has also been suggested that the reliability increases as the architecture

becomes more redundant. It is important to note that this is not always the case, as there

would be occasions where increasing the redundancy may adversely affect reliability.

There also has to be a good balance between redundancy and simplicity so that in an

effort to make the system more reliable by introducing redundancy, the system does not

end up becoming too complex.

It has also been shown how the penalty cost factor (for outage periods) influences the

optimum process bus architecture reliability. It was seen that when the penalty cost factor

was extremely high, then the optimum architecture reliability was that of the most reliable

architecture. When the penalty was extremely low, the optimum architecture reliability was

that of the least reliable architecture. This has shown that although it is always desirable to

select the most reliable architecture, that architecture may not be the optimum one when

other factors (such as the penalty for outage) are taken into account.

133

CHAPTER 7 DESIGN AND IMPLEMENTATION OF MERGING UNIT PERFORMANCE TEST BED

7.1. INTRODUCTIONThere are a number of prototype and commercially available merging units currently

available. Merging units from different manufacturers though capable of producing

Ethernet packets that are IEC 61850-compliant, may vary in their performance

characteristics, such as delay, dynamic range and conversion error. Presently there is no

particular MU specification; hence, there is a need to test MU performance characteristics,

as this may be useful in promoting interoperability.

In this chapter, the design and implementation of a MU performance test bed shall be

discussed. This test bed can be used for carrying out performance tests such as the

sampled values recovery test, process delay test, GPS Timestamping delay test, arrival

time uniformity test, conversion error test and filter performance assessment. It is able to

test up to 4 MUs simultaneously.

7.2. PROTOTYPE AND COMMERCIALLY AVAILABLE MERGING UNITS

7.2.1. Locamation Figs. 7.1 and 7.2 illustrate how the Locamation MU606 Merging unit functions as an

Analogue Merging Unit (AMU) and Digital Merging Unit (DMU) [72].

Analogue Merging Unit (AMU) functionCurrent and Voltage transformers are connected to a Current Interface Module (CIM) and

Voltage Interface Module (VIM) respectively. The CIM and VIM deliver the raw data of

measured current and voltage samples respectively to the MU. The resulting sampled

values (based on IEC 61850-9-2 LE) are then sent to the external Protection device by

134

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

using 100Base-FX (optical fibre based) Ethernet communication. The merging unit can be

synchronised by an external GPS system based on Pulse per second (PPS) signals.

Fig. 7.1: Locamation Arrangement - Analogue Merging Unit Function

Digital Merging Unit (DMU)GOOSE control messages are sent from the external Protection device to the MU, which is

then able to trip a circuit breaker via the Breaker Interface Module (BIM).

Fig. 7.2: Locamation Arrangement - Digital Merging Unit Function

7.2.2. GE Fig. 7.3 shows the Process Bus system Architecture for the GE HardFiber solution [63].

The Bricks convert copper signals to and from digital optical signals. Copper signals

include CTs, VTs, contact inputs, and contact outputs. Bricks implement the concept of an

IEC 61850 merging unit, expanded to optically connect relays with all types of input and

output signals in the switchyard, not just instrument transformers. A relay can also work

with duplicated bricks. The Brick receives a GOOSE Ethernet frame sent by a relay. It then

uses the GOOSE message to sample the measured (CT, VT) values. Each brick can work

with different relays.

135

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

STATIONLAN

RELAY 1 RELAY 2 RELAY 3

21 65

CROSSCONNECTPANEL 1

CROSSCONNECTPANEL 2

3

4

BrickL-1

CT-1 CT-2CB-1 CT-3 CB-2

VT-1

CT-4

Outdoor Fibrecables

Indoor Fibrecables

Control House

Fig. 7.3: GE Process Bus Architecture

Copper cables (not shown in Fig. 7.3) make the connections between the copper

terminals inside the power equipment to the Bricks mounted in the switchyard, typically on

the outside of the equipment. Outdoor fibre cables make the optical connection between

the Bricks in the switchyard and the Cross Connect Panels in the control house. They are

also used to supply power to the Brick internal electronics via an embedded copper wire

pair. Cross Connect Panels are where individual fibres in the outdoor cables are

patchcorded to individual fibres of indoor cables, completing the associations between the

relays and the Bricks for a given station topology. Also, the panels distribute DC to the

Bricks via the outdoor fibre cables. Indoor fibre cables make the optical connection

between the process bus ports of the relays and the Cross Connect Panel.

The GE HardFiber System does not require external clocks. Components called Process

Cards convert Brick digital optical signals so they can be used by GE relays.

7.2.3. Siemens A prototype Siemens merging unit setup [73] is shown in Fig. 7.4. A conventional current

transformer (CT) and a conventional voltage transformer (VT) are connected to the

136

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

merging unit. An interphase open/Interphase close (IPO/IPC) relay is connected to a circuit

breaker IED. The merging unit and circuit breaker controller are connected via a process

bus to a feeder protection IED and Gateway switch. A data logger is connected to the

process bus via the gateway switch. The setup also incorporates an isolation scheme. If

procedures such as testing, maintenance or commissioning need to be carried out, an

isolation box is used in conjunction with the merging unit. The merging unit can be

synchronised by an external GPS system using fibre-optic based Pulse per second (PPS)

signals.

Fig. 7.4: Siemens Merging Unit Set-Up

7.2.4. MitsubishiThe Mitsubishi MMU-H100A prototype merging unit [74] is shown in Fig. 7.5. A current

transformer (CT) and a voltage transformer (VT) are connected to the merging unit which

broadcasts the output Ethernet packets according to IEC 61850 9-2 LE. The merging unit

can be synchronised by an external GPS system based on Inter-Range Instrumentation

Group B (IRIG -B) signals.

137

CT VT IPO/IPCRELAY

ISOLATION BOXNORMAL

MERGING UNIT

IEC 61850 9-2 LE BUS

FEEDERPROTECTION

DATALOGGER

9-2 GATEWAYSWITCH

CIRCUIT BREAKER IED

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.5: Mitsubishi Merging Unit

7.2.5. AlstomThe Alstom COSI-NXMU commercially available merging unit is shown in Fig. 7.6 [75]. It

accepts optical CT and analogue VT signals and is able to sample signals based on 80

and 256 samples/cycle. The output can be sent to metering and protection devices.

Fig. 7.6: Mitsubishi Merging Unit

There is also the Alstom IMU prototype merging unit which accepts conventional CT and

VT signals (Fig. 7.7).

Fig. 7.7: Mitsubishi Merging Unit

7.2.6. ABBABB has 2 different types of merging units. They are the Merging unit for Measurement

(CP-MUM) [67] and the Merging unit for Protection (CP-MUP) [68]. These merging units

are designed to be used in conjunction with an ABB product, ELK-CP3, which is a

Combined Non-Conventional Instrument Transformer (NCIT) for current and voltage.

Figure 7.8 shows how the ELK-CP3 is connected to 2 merging units for Metering thus

providing 2 independent measuring systems. A CP-MUM has one sensor input (one sensor

138

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

input means three individual phases). It provides 1 Pulse Per Second (PPS) output. The

Ethernet output stream from the merging unit is IEC 61850 9-1 transmitted using 10BaseT.

Fig. 7.8: ABB Redundant system for revenue metering using Merging unit for Metering

(CP-MUM)

The ABB Merging unit for Protection (CP-MUP) (Fig. 7.9) is a Merging unit with three

sensor inputs, five Ethernet ports based on IEC 61850 9-2 LE and a freely configurable

Ethernet switch. It can be synchronized by a 1 PPS signal and provides 5 1PPS outputs. It

provides 5 Ethernet streams transmitted using 100BaseFX.

Fig. 7.9: ABB Merging unit for Protection(CP-MUP)

139

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.3. MERGING UNIT PERFORMANCE TEST BED The MU test bed basic layout is illustrated in Fig. 7.10 and introductory descriptions of the

test bed have been provided in [76] and [77]. A Real Time Digital Simulator (RTDS) shall

be used to model instrument transformers within a substation. The RTDS output is then

amplified using an Omicron amplifier, producing analogue signals which mirror the voltage

and current signals from instrument transformers. Further amplification is required by an

isolation amplifier before the signal is fed to the DAS. Throughout the chapter, voltage

signals will be mentioned more often, but a similar analysis would apply to current signals.

Two analogue voltage signals of equal magnitude, phase and frequency shall be

simultaneously fed into the merging unit (MU), and the National Instruments Digital

Acquisition System (DAS). The MU samples its input analogue voltage signal and sends

the output in the form of Ethernet packets (also referred to as Ethernet frames). The DAS

also samples its analogue voltage signals. The sampling of the MU and DAS is

synchronized by GPS signals connected to both of them. A PC is able to capture the output

from the A/D converter and also receive the Ethernet packets from the MU via an Ethernet

Switch (not shown). The output is stored and analysed. The MU test bed is able to test up

to 4 MUs simultaneously. The MU generic Test bed block diagram is shown in Fig. 7.11.

Fig. 7.10: Merging unit Test Bed Layout

140

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

RTDS: Real Time Digital SimulatorDAS: National Instruments Digital Acquisition SystemNMC: Endace Network Monitoring CardPC: ComputerMU: Merging UnitIs Amp: Isolation Amplifier

Fig. 7.11: Merging Unit Test Bed Block Diagram

7.3.1. Real Time Digital Simulator (RTDS)RTDS software is used to model the circuits which provide the current and voltage injection

signals for the merging unit. The RTDS device is shown below in Fig. 7.12.

Fig. 7.12: RTDS

For instance RTDS can be used to model one of the mesh corner substations highlighted

in Fig. 7.13a. The mesh corner substation is made up of 3 circuit breakers (CB1, CB4, and

CB5) and a transformer (T1). T1 is a 400kV/132kV step-down transformer, CB5 is a 132kV

141

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

circuit breaker, while CB1 and CB4 are 400kV circuit breakers. Fig. 7.13b shows how

RTDS is used to model this substation.

a: High Level View of Mesh Corner

b: Mesh Corner Modelled using RTDS

Fig. 7.13: Mesh Corner Substation

142

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.3.2. Amplifiers – Omicron Amplifier and Isolation AmplifierThe Omicron amplifier (shown in Fig 7.14a together with an oscilloscope measuring its

output voltage) amplifies the analogue signals produced by RTDS and produces output

analogue signals that mirror the output of voltage (and current) instrument transformers.

This output is then simultaneously fed to the MU directly and to the Digital Acquisition

System via the Isolation Amplifier (Fig. 7.14b). The Omicron analogue output is scaled

down with the isolation amplifier before it is fed to the DAS.

a. Omicron Amplifier b. Isolation Amplifier

Fig. 7.14: Amplifiers used for merging unit Test Bed

The Omicron amplifier produces 50V for every 1V input it receives, while it produces 5A for

every 1V input it receives. The isolation amplifier provides 20V for every 1V input, and 1V

for every 1A input it receives from the Omicron amplifier. The Digital Acquisition System

(DAS) samples the analogue voltage outputs from the isolation amplifier and then rescales

the digital output so that this output represents the original voltage (and current) signals

produced by the Omicron Amplifier. The input and output voltages are measured using the

oscilloscope.

7.3.2.1. Isolation Amplifier CalibrationThe methodology for the calibration of the isolation amplifier is as follows. For the current

calibration, 2A(RMS) signals ranging from 50Hz to 5kHz are fed into the current ports of

the amplifier. The input current is measured by:

143

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

a) using a clamp placed across the incoming input cable (this cable is connected to

the incoming input port. The other input cable, the outgoing input cable, is connected to the

outgoing input port). The output of the current clamp is a voltage output which is measured

by using the oscilloscope;

b) using an ammeter as part of the connections;

c) measuring the voltage across the current input ports, using the oscilloscope.

The output of the amplifier is a voltage signal which has a 1:1 ratio with the current input.

This output is measured using an oscilloscope.

For the voltage calibration, 6V (RMS) signals are fed into the voltage ports of the amplifier.

Only the voltage across the input voltage ports are used for comparison with the output

voltage (measured using the oscilloscope).

Tables 7.1 and 7.2 show the isolation amplifier calibration data for the voltage and current.

Table 7.1: Isolation Amplifier Current Calibration

Freq(Hz)

Input current

(ammeter) (A)

Input voltage(clamp)

(mV)

VIPR = Input

voltage(parallel resistor across input

terminals)

(mV)

Input voltage (parallel resistor)normalized/converted to Amps (A)

(VIPR x 2/60)

Output voltage

(oscilloscope)

converted to Amps

(1V represents

1A)

Current Ratio

Error (%)

50 2 201 60 2 2.02 1.010 11000 1.96 205 460 2 2.02 1.010 12000 1.89 199 452 1.965 1.99 1.013 1.2615000 1.46 164 390 1.696 1.70 1.003 0.200

Table 7.2: Isolation Amplifier Voltage Calibration

144

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Freq(Hz)

VIPR = Input voltage

(parallel resistor across input

terminals)(mV)

Input voltage (parallel resistor)

normalized/converted to Actual Input Voltage

(V) (VIPR x 6/300)

Output voltage

(oscilloscope) converted to Amps (1V represents

1A)

Current Ratio

Error (%)

50 300 6 6 1 01000 300 6 6 1 02000 300 6 6 1 05000 299 5.980 6 1.003344 0.334

The ratio of the voltage output to the current input is plotted against the corresponding

frequencies (Fig. 7.15a). Out of the current input measurements, the one used for the

“current” ratio calculated was the one based on the voltage across the input ports. This is

because it was the most consistent out of the 3 measurements, and also the ammeter

accuracy greatly diminished at higher frequencies. The output error is also shown in Fig.

7.15b. it is seen that at 50Hz the error is approximately 1%. it rises to 1.2% and then the

error drops as the frequency increases. This graph is taken as an initial estimate due to the

absence of an ammeter which is capable of maintaining its accuracy even at higher

frequencies.

a. Current Ratio

145

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

b. Current Error

Fig. 7.15: Calibration Results for Isolation Amplifier (2A injection)

The voltage ratio and error can be seen in Fig. 7.16. The error is seen to be approximately

zero percent while it gets to 0.33% when the input frequency is 5kHz.

a. Voltage Ratio

146

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

a. Voltage Error

Fig. 7.16: Calibration Results for Isolation Amplifier (6V injection)

7.3.3. National Instruments Digital Acquisition System (DAS)The National Instruments Digital Acquisition System (DAS), shown in Fig. 7.17 below, is

made up of different modules that enable the accurate sampling of the analogue voltage

signals from RTDS.

Fig. 7.17: National Instruments Digital Acquisition System

It is connected to the PC and serves as a reference. The DAS system is housed in an 8-

slot quiet chassis (PXI 1042Q). The DAS includes a GPS-synchronizable high precision

timing and digital I/O module (PXI 6608) which has a frequency timebase of up to 80MHz,

eight 32-bit counters/timers and 32 digital I/O lines. The DAS also includes a dynamic

signal acquisition module (PXI-4472B) which can sample up to 8 analogue inputs

simultaneously at a sampling rate of up to 102,400 samples per second. The Analogue to

Digital Converter within the PXI-4472B has a resolution of 24 bits.

147

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.3.4. Endace Network Monitoring Card (NMC)The Endace Network Monitoring Card (NMC) shown in Fig. 7.18 below, timestamps the

arrival of the incoming Ethernet packets sent from the MU. It has a resolution of 7.5ns.

Fig. 7.18: Endace Network Monitoring Card (NMC)

It is installed in the PC. It provides precise packet stamping, 100% packet capture

capability and can be synchronized with a GPS.

7.3.5. Personal Computer (PC)The DAS is connected to the Personal Computer (PC). The NMC is installed in the PC. A

program running on the PC has been developed based on Wireshark, (network analysis

software). At the desired time, the program triggers the simultaneous capture of Ethernet

packets sent by the MU, and the sampling of the analogue signals by the DAS saves and

analyses the stored data.

7.3.6. Fibre optic Ethernet SwitchThe GE MultiLink Fibre Optic Ethernet Switch illustrated in Fig. 7.19 below has fibre optic

ports and RJ45 Ethernet ports.

Fig. 7.19: GE Fibre Optic Ethernet Switch

148

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

It connects the merging unit to the PC. The PC is thus able to retrieve the Ethernet packets

that are sent by the merging unit.

7.4. DESCRIPTION OF MU PERFORMANCE TESTS

7.4.1. Ethernet Frame Format Check and Sampled Values Recovery Test

Aim: To check if the Ethernet frames/packets sent from the MU are of the format specified

by IEC 61850 9-2 “Light Edition” (LE). Also, to check if sampled values can be successfully

recovered from the merging unit.

Methodology: Analogue current and voltage signals are sent via the RTDS and Omicron

amplifiers to the MU. The frequency and magnitude of the analogue signals are recorded.

The Ethernet packet output from the MU is saved. The saved Ethernet packets are then

retrieved and checked for compliance with IEC 61850 9-2 (LE), and the sampled values

are then extracted from the packets.

Fig. 7.20 shows the expected structure of an Ethernet packet/frame sent by a merging unit.

The Ethernet frame is made up of a number of data fields represented by bits. If a data

field is made up of one byte (octet), then the field shall be represented by having the least

significant bit (lsb) on left and the most significant bit (msb) on the right. If a data field is

made up of more than one bit, then the lsb shall be on the lower right hand corner and the

msb on the upper left corner (see the Preamble data field in Fig. 7.20 The contents of the

Ethernet frame are described in detail in the sections below, beginning with the Header

Media Access Controller (MAC):

(a) HEADER MAC Fig. 7.21 shows the structure of the MAC. In order to increase the overall performance of

multicast message reception, it is preferable to have the MAC hardware perform the

filtering. The multicast addressing should be based upon the MAC IC’s hash algorithms.

The hash algorithms in the various integrated circuits vary. The impact of these algorithms

149

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

need to evaluated when destination multicast addresses are being assigned. A unique

ISO/IEC 8802-3 source address shall be used. One recommended addressing scheme for

the destination address is outlined below:

The multicast addresses (octet string of size 6) used will have the following structure:

• The first three octets are assigned by IEEE with 01-0C-CD.

• The fourth octet will be 04 for multicast sampled values.

• The last two octets will be used as individual addresses assigned by range 00-00 to

01-FF.

Octets123456789

101112131415161718192021222324252627282930313233343536......

8 7 6 5 4 3 2 1

Preamble

Start of Frame

HeaderMAC

Priority Tagged

EthertypePDU

Pad bytes if neededFrame check

sequence

lsb

msb

Octets123456789

101112

8 7 6 5 4 3 2 1

HeaderMAC

Destination Address

Source Address

Fig. 7.20: Contents of an Ethernet Frame Fig. 7.21: Structure of the Header MAC

(b) PRIORITY TAGGING/VIRTUAL LAN

150

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Priority tagging according to IEEE 802.1Q is used to separate time critical and high priority

bus traffic for protection relevant applications from low priority busload. Fig. 7.22 below

shows the structure of the tag header:

8 7 6 5 4 3 2 1

TPID 0 x 8100

VIDTCI VIDCFIUser Priority

Fig. 7.22: Structure of the tag header

(a) TPID (Tag Protocol Identifier) Field: This indicates the Ethernet Type assigned for

802.1Q Ethernet encoded frames. This value shall be 0x8100.

(b) TCI (Tag Control Information) Fields: These are the User priority, CFI and VID

fields.

i. User Priority: This value should be configured to separate sampled values from

low priority busload. If the priority is not configured then the default value is 4. The higher

priority frames should have a priority of 4 to 7 and the lower priority should have a priority

of 1 to 3. The value 1 is the priority of untagged frames thus 0 should be avoided as it may

cause unpredictable delay due to normal traffic.

ii. CFI (Canonical Format Indicator): This is a single bit flag value. The CFI bit

value shall be “reset” (value = 0). If the CFI bit value is “set” (value = 1), an Embedded

Resource Identification Field (E-RIF) follows the Length/Type field in the ISO/IEC 8802-3

tagged frame.

iii. VID (VLAN Identifier): Virtual LAN support is optional. If this mechanism will be

used, the VID shall be set by configuration, and if it is not used, it shall be set to 0. Since

Sampled Values need to have potentially their own bandwidth allocation, the configured

VID for Sampled Values will be different from GOOSE and GSE.

(c) ETHERTYPE PDU

An Ethertype based on ISO/IEC 8802-3 MAC – Sublayer is registered by the IEEE

Authority Registration. Fig. 7.23 below shows the structure of the Ethertype Protocol Data

Unit (PDU).

151

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Octets123456789

10

. . . . . . . . .m + 10

Ethertype

APDU

APPIDLength

Reserved 1Reserved 2

Eth

erty

pe

PDU

Fig. 7.23: Structure of the Ethertype PDU

i. Ethertype - The registered Ethertype value is 88-BA (hexadecimal). The sampled

analogue value buffer update is directly mapped to the reserved Ethertype and the

Ethertype PDU.

ii. APPID (Application identifier): The APPID is used to select ISO/IEC 8802-3

frames containing sampled value (SV) messages and to distinguish the application

association. The value of APPID is the combination of the APPID type, defined as the two

most significant bits of the value (“01” for sampled values), and the actual ID. The reserved

value range for sampled values is 0x4000 to 0x7FFF. If no APPID is configured, the

default value shall be 0x4000. The default value is reserved to indicate lack of

configuration. It is strongly recommended to have unique, source orientated SV APPID

within a system. This should be enforced by the configuration system.

iii. Length: This is the number of octets including the Ethertype PDU header starting

at APPID, and the length of the APDU (Application Protocol Data Unit). Therefore, the

value of Length shall be m+8, where m is the length of the APDU and m is less than

1492. Frames with inconsistent or invalid length field shall be discarded.

iv. Reserved1, Reserved2: These are reserved for future standardized applications

and shall be set to 0 as default.

v. APDU (Application Protocol Data Unit): An APDU is made up of one or more

Application Service Data Units (ASDUs). It is possible to concatenate “n” number of

ASDUs into one APDU before the APDU is posted into the transmission buffer. The

number of ASDUs which will be concatenated into one ASDU is defined with a

configuration parameter and related to the sample rate. The concatenation of ASDUs is not

dynamically changeable in order to reduce the implementation complexity. When

152

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

concatenating several ASDUs into one frame, the ASDU with the oldest samples is the first

one in the frame.

Fig. 7.24 shows a high level view of an APDU made up of “n” ASDUs. One of the ASDUs

is expanded. It is made of a sequence of bits which can be converted to obtain the “tag”

information, the “length” of the actual data, and the actual data. For instance svID is the

unique sample value ID. There must be a tag value of 80, this will let one know that one is

about to retrieve the sample value ID. Following that is the “length” which can be a value of

10 – 34, and so a value of 10 means that the sample value ID is 10 bytes in length and

finally the actual ID will follow, and it must be exactly 10 bytes in length. Similarly there

must be a tag of 82 to represent the sample count (smpCnt), 83 for configuration revision

(confRev), 85 for sample synchronized (smpSynch) and then 87 for the actual dataset

which shall be described shortly. According to IEC 61850 9-2 LE, there are 2 possible

values of “n”, and the sampling frequency, depending on which type of Multicast Sampled

Value Control Block (MSVCB) is to be used for transmission. There are 2 types of

MSVCBs defined - MSVCB01 and MSVCB02. At least one must be used. If type 1

(MSVCB01) is used, then n=1 and 80 samples per nominal cycle will be transmitted. If type

2 (MSVCB02) is used, then n = 8 and 256 samples per nominal line cycle will be

transmitted.

Fig. 7.24: Application Protocol Data Unit (APDU), Application Service Data Units (ASDU)

and Dataset

The attributes making up the APDU are described below:

1) noASDU: The number of ASDUs that make up the APDU.

153

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

2) svID: The attribute svID shall be a unique identification of the sampled value buffer

related to the update of the sampled values.

3) smpCnt: The parameter smpCnt contains the values of a counter, which is

incremented each time a new sample of the analogue value is taken. The sample values

shall be kept in the right order. If the counter is used to indicate time consistency of various

sampled values, the counter shall be reset by an external synchronization event.

4) ConfRev: The attribute ConfRev represents a count of the number of times that the

datset configuration has been changed. However, the datasets used for the transmission

of sampled values have been defined. The MSVCB has also been defined. Hence, this

attribute has a fixed value of 1.

5) smpSynch: The parameter smpSynch indicates whether the sampled analogue

values sent by the MSVCB are synchronized by clock signals. It shall be set to TRUE if the

merging unit is synchronized.

6) DataSet: Within each ASDU is a dataset. The dataset contains the data to be

transmitted. The name of the dataset for IEC 61850 9-2 LE is “PhsMeas1”. The section

“value1” within the “PhsMeas1” dataset is expanded in Fig. 7.24. The expected format of

this DataSet is shown in Fig. 7.25 and the relevant values are shown in the Table 1. The

MX attributes are listed in Table 7.5.

Fig. 7.25: PhsMeas1 Dataset

Table 7.3: PhsMeas1 Values

No Attribute name Value Comment1 DSMemberRef InnATCTR1.Amp[MX]

InnBTCTR2.Amp[MX]Inn and TCTR(1 - 4) are for the identification of the Current Sensors;

154

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

No Attribute name Value CommentInnCTCTR3.Amp[MX]InnNTCTR4.Amp[MX]UnnATVTR1.Vol[MX]UnnBTVTR2.Vol[MX]UnnCTVTR3.Vol[MX]UnnNTVTR4.Vol[MX]

Unn and TVTR(1 - 4) are for the identification of the Voltage Sensors;

A, B C and N are for phase identification.

Amp/Vol are the Current/Voltage sampled values. The MX attributes of these sampled values are listed in the table below.

Table 7.4: MX attributes from Table 7.3

No. Attribute name Attribute Type1. instmag.i IINT322. q Quality3. sVC.scaleFactor FLOAT324. sVC.offset FLOAT32

The MX attributes listed in the table above are described below:

1) instmag.i : This is the magnitude of the instantaneous value of a measured value.

“.i” means that the value returned would be an integer.

2) q (Quality): This provides more information about the sampled value that was just

obtained. It includes an indication of whether the value is derived or based on a real

sensor, if further update of the value has been blocked by an operator, if it is a test flag, the

nature of the source or origin of the value, data validity information (and for invalid or

questionable data, the reasons for the questionability/invalidity).

For example, InnATCTR1.Amp.instmag.q.derived = 1 means that phase A current sampled

value has been calculated, and not actually measured. The quality type attributes are listed

in the table below and then the attributes are further described.

Table 7.5: Quality Attribute Type definition

(Note: M = mandatory; O = optional; C = conditional)

No. Attribute Name Attribute Type Value/Value Range M/O/CPACKED LIST

I. validity CODED ENUM good | invalid | questionable MII. detailQual PACKED LIST M

a overflow BOOLEAN Mb outOfRange BOOLEAN Mc badReference BOOLEAN Md oscillatory BOOLEAN M

155

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

No. Attribute Name Attribute Type Value/Value Range M/O/Ce failure BOOLEAN Mf oldData BOOLEAN Mg inconsistent BOOLEAN Mh inaccurate BOOLEAN M

III. source CODED ENUM process | substitutedDEFAULT process

M

IV. test BOOLEAN DEFAULT FALSE MV. operatorBlocked BOOLEAN DEFAULT FALSE MVI. derived BOOLEAN DEFAULT FALSE M

I validity: The validity is either good, questionable or invalid:

• good: This is when no abnormal condition of the acquisition function or the

information source is detected.

• invalid: This is when an abnormal condition of the acquisition function or

the information source (missing or non-operating updating devices) is

detected. It is used to indicate to the client that the value may be incorrect

and shall not be used.

• questionable: This is when a supervision function detects an abnormal

behaviour, however the value could still be valid. The client shall be

responsible for determining whether or not values marked "questionable"

should be used.

II detailQual: This represents the detailed quality identifiers. The reason for an

invalid or questionable value of an attribute may be specified in more detail with further

quality identifiers. If one of these identifiers is set then validity shall be set to invalid or

questionable. The 8 detailed quality identifiers are described below:

• overflow: The value of the attribute to which the quality has been

associated is beyond the capability of being represented properly.

• outOfRange :The attribute to which the quality has been associated is

beyond a predefined range of values. The server shall decide if validity

shall be set to invalid or questionable.

• badReference: The value may not be a correct value due to a reference

being out of calibration. The server shall decide if validity shall be set to

invalid or questionable.

• oscillatory : A signal oscillation has occurred : the signal has changed in a

defined time twice in the same direction.

156

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

• failure : A supervision function has detected an internal or external failure.

• oldData: An update has not been made during a specific time interval.

• inconsistent : An evaluation function has detected an inconsistency.

• inaccurate : The value does not meet the stated accuracy of the source.

III source: This gives information related to the origin of a value. The value may be

acquired from the process or be a substituted value.

• process: the value is provided by an input function from the process

input/output (I/O) or is calculated from some application function.

• substituted: the value is provided by input of an operator or by an automatic

source.

IV test : This may be used to classify a value being a test value and not to be used for

operational purposes.

V operatorBlocked: This is set if further update of the value has been blocked by an

operator.

VI derived: This is TRUE if the value is not based on a real sensor, but is derived

from the values of other real sensors. It is set to FALSE if the value is based on a real

sensor.

3) sVC.scaleFactor and sVC.offset : These are used to convert the integer value of

instmag.i to a floating point value. sVC.scaleFactor is 0.001 for current, and 0.01 for

voltage. sVC.offset is 0. This implies a fixed scaling. (sVC stands for ScaledValueConfig).

For the current, the scale has been fixed so that each bit stands for 0.001A = 1mA.

The length of instmag.i is 32 bits (4 bytes). Take for instance InnATCTR1.Amp.instmag.i

A value of “1” in the InnATCTR1.Amp.instmag.i field means the current is 1mA.

A value of “11” means the current is 3 x 1mA. = 3mA.

For the voltage, the scale has been fixed so that each bit stands for 0.01V = 10mV.

A value of “1” in the UnnATVTR1.Vol.instmag.i field means the voltage is 10mV.

A value of “11” means the voltage is 3 x 10mV = 30mV.

7.4.2. MU GPS Timestamping Delay Test

157

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Aim: The aim of the MU GPS Timestamping Delay Test is to determine the delay that

occurs when the MU timestamps the digitized signal.

Methodology: A voltage signal is sent to both the MU and the DAS (See Fig. 7.26). timeA

reflects the timestamp of a voltage value, part of analogue voltage signal produced by the

signal generator. timeB corresponds to the time when the MU sampled and timestamped

the analogue voltage value produced at timeA. That sample is called dataA1. timeC

corresponds to the time that a similar value (dataB1) was obtained by the DAS. The

dataA1 is then converted to an Ethernet packet pcktA1 and sent to the PC. pcktA1 arrives

at timeD.

Fig. 7.26: Merging unit GPS Timestamping Delay Test and Process Delay Test

Fig. 7.27 below provides a further description of how timeA, timeB and timeC are

measured. timeA is measured by the oscilloscope as the time between a GPS pulse input,

and the end of a voltage dip period. timeB is calculated based on the MU GPS sample

count attached to the sampled value of the point indicated by the oscilloscope at timeA.

The sample count ranges from 0 to 3999, and the sample count value is divided by 4000 to

get the sub second timestamp for that sampled value. Similarly, timeC is the sub second

timestamp value extracted from the DAS. The GPS Timestamping delay is estimated using

the following equation:

Estimated GPS Timestamping Delay = GTD = T0 = timeB – timeA. (29)

158

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.27: Merging unit GPS Timestamping Delay Test

7.4.3. MU Process Delay TestAim: The aim of the MU Process Delay test is to determine the delay resulting from factors

such as the MU encapsulating the sampled values into Ethernet frames and then

transmitting these Ethernet frames to the receiving device.

Methodology: As shown in Fig. 7.26 above, timeD is the arrival timestamp of the sampled

value that was sampled at timeB. The MU Process delay is estimated using the following

equation:

Estimated MU Process delay = PD = T1 + T2 + T3 = timeD – timeB (30)

where

T1: the estimated time required for the merging unit to prepare and transmit the Ethernet

packet

T2: the estimated time required for the network to deliver the Ethernet packet,

T3: the estimated time required for the PC timestamping hardware to deliver the value to

its process logic.

159

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.4.4. Arrival Time Uniformity TestAim: The aim of the MU Arrival Time Uniformity Test is to check how regular the Ethernet

frames are at arriving at the receiving device.

Methodology: The difference between the arrival timestamps of successive sampled

values is calculated (Fig. 7.28).

Fig. 7.28: Arrival Time Uniformity Plot

Assuming a frequency of 50Hz and 80 samples per cycle

Number of samples per second = 80 x 50 = 4000 For uniform spacing between packets,

the time between successive packets = (1/4000) seconds = 250 μs

∆t = 250 μs .

t1: time that the first packet has arrived, time t2 is the time the second packet has arrived

and similarly t3, when packet 3 has arrived.

∆t1 = t2 – t1 (31)

∆t2 = t3 – t2 (32)

Ideally ∆t1 - ∆t should be = 0. If ∆t < ∆t1 then ∆t1 - ∆t will be positive. Similarly if ∆t > ∆t2,

then ∆t2 - ∆t will be negative.

160

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.4.5. MU Conversion Error Test

Aim: The aim of the MU Conversion Error Test is to determine the amplitude error of a MU

when it converts an analogue signal to sampled values.

Methodology: For the MU Voltage Conversion Error Test, voltage sine waves with a

frequency of 50Hz are fed to the DAS and MU (Fig. 7.29). The output signals from the

merging unit and DAS are aligned so that samples falling within the same periods can be

compared. 10 cycles from the MU and 10 corresponding, aligned cycles from the DAQ are

selected and the RMS (Root Mean Square) values of these 10-cycle sinewaves are

derived.

The RMS magnitude =

2

1

n

ii

M

n=

∑ (33)

where i = the ith sample number

Mi = the magnitude of the ith sample number

n = total number of samples

The MU amplitude conversion error (%) =

(MU RMS magnitude – DAS RMS magnitude) x 100 (34)

DAS RMS magnitude

161

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

a. ANALOGUE INPUT (Voltage)

DAS Output MU Output

Fig. 7.29: Merging Unit Conversion Error Test (Voltage)

After the voltage error is derived, the voltage sinewave injection at that particular

magnitude is repeated and the error is derived again. The injections are repeated and then

the average error is derived. The magnitude of the voltage sinewave injection is then

increased, and the average error is derived based on repeated injections at that increased

voltage magnitude. The test ends after the average error has been derived based on a

120V input injection.

162

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

The methodology for the current conversion error is exactly the same as that for the

voltage conversion error test, only this time, current injections are used instead of voltage

injections.

7.4.6. MU Filter Performance Test

Aim: The aim of the MU Filter Performance Test is to check how much of the original

signal the MU is able to recover at different frequencies. A square wave has been initially

used because theoretically it is a sum of an infinite number of sine wave signals at different

frequencies. Since a MU samples at 4kHz, ideally it should be able to recover the original

signal up to 2kHz, if there is an antialiaisng filter.

However, there were cases where the cut-off frequency point did not appear within the

2kHz frequency range. It may have been due to one or more reasons such as FFT

leakage, or the MU may not be using a filter, or the filter may not be attenuating signals at

more than 2kHz (half the 4kHz assumed sample rate), leading to aliasing. To reduce or

rule out errors due to FFT leakage, a sine wave injection test was carried out.

Methodology: The DAS serves as a reference, since it has been set to have a sampling

rate of 16kHz (4 times that of the MU). It has also been calibrated by the manufacturer, and

has an Analogue to Digital Converter with a resolution of 24 bits. The DAS can thus be

assumed to accurately represent the input analogue signals.

The initial methodology for the filter performance was based on a Fourier Analysis. For the

voltage square wave test, a Fourier Analysis was carried out on the DAS and MU output

after both had simultaneously received 50V, 50Hz, square wave input signals (Fig. 7.30a

-c) . A square wave is theoretically a sum of an infinite number of sine wave signals at

different frequencies. The frequencies selected for the Fourier analysis plot were based on

odd harmonics of the fundamental input frequency, 50Hz (odd harmonics starting from

50Hz, and including 150Hz, 250Hz, up to 1950Hz) (Fig. 7.30 d-e). For each selected

frequency, the derived MU Fourier magnitude output was divided by the corresponding

DAS Fourier magnitude output. The results of these calculations were then plotted (Fig.

7.30 f).

163

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

The cut-off frequency is the frequency at which the merging unit output divided by the

reference = √2 /2

Cut-off frequency = freq (MU magnitude/ DAS magnitude = √2 /2 = 0.707) (35)

a. 50V, 50Hz Square Wave Injection

b. DAS Output c. MU Output

d. DAS Fourier Analysis (16kHz sampling) e. MU Fourier Analysis (4kHz sampling)

164

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

1.1

0 200 400 600 800 1000 1200 1400 1600 1800 2000

freq f (Hz)

MU

/DA

S

CUT-OFF FREQUENCY

f. Filter Analysis Curve (MU Magnitude / DAS Magnitude)

Fig. 7.30: MU Filter Performance Test (Voltage).

Fig. 7.30f is the filter analysis curve for the merging unit from one manufacturer. The Fig.

shows a clear cut-off frequency of approximately 250Hz to the nearest 50Hz.

These results were consistent when repeated. However Fig. 7.31 shows the result of a

square wave injection test carried out on the merging unit from a different manufacturer. It

can be seen that the cut-off frequency point does not appear within the 2kHz frequency

range. In addition to this, the results were not consistent when the test was repeated.

There were instances when the cut-off frequency would appear within the 2kHz. The

inconsistent results may have been due to one or more reasons: FFT leakage, or the MU

may not be using a filter, or the filter may not be attenuating signals at more than 2kHz

(half the 4kHz assumed sample rate), leading to aliasing, or the MU and DAS samples

used for comparison had not been aligned.

165

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.31: Squarewave Injection Test: Filter Analysis Curve (MU Magnitude / DAS

Magnitude)

In order to reduce or rule out errors due to FFT leakage and non-alignment, a data capture

methodology similar to that used for the MU Conversion Error (section 7.4.5.) was applied.

For the Filter Performance Voltage test, voltage sine waves with an initial frequency of

50Hz were fed to the DAS and MU (Fig. 7.29). The output signals from the merging unit

and DAS were aligned so that samples falling within the same periods could be compared.

10 cycles from the MU and 10 corresponding, aligned cycles from the DAS were selected

and the RMS values of these 10-cycle sinewaves were derived. The voltage ratio was

derived using the following equation:

Voltage ratio, Vout/Vin = merging unit Output Voltage Magnitude/DAS Output Voltage

Magnitude (36)

After the voltage ratio had been derived, the voltage sinewave injection at that particular

frequency was repeated and the voltage ratio was derived again. The injections were

repeated and then the average ratio was derived. The frequency of the voltage sinewave

injection was then increased, and the average ratio was derived based on repeated

injections at that increased frequency. The frequencies used for the voltage sinewave

injections were the same as those initially used for the Fourier analysis (50Hz, 150Hz,

250Hz, up to 1950Hz).

166

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

The output can be seen in Fig 7.32. The test results were consistent when repeated and

are discussed in detail in Section 7.6.6..

Fig. 7.32: Sinewave Injection Test (MU Magnitude / DAS Magnitude)

For the Filter Performance current test the methodology is identical to that used for the

voltage test, but it is based on 2A injections rather than 50V injections.

According to [78], most protection functions need to filter the fundamental components of the

analogue values and analyses of current and voltages at frequencies of up to 1kHz is

considered sufficient. For evaluation of power quality, frequencies up to the 50th harmonic are

expected to be measured and for a 50Hz system, this corresponds to 2.5kHz. IEC 61850

specifies a sampling rate of 4kHz or 12.8kHz for a 50Hz system, which means that the Merging

Unit will be only able to correctly sample signals with frequencies up to 2kHz or 6.4kHz based on

the Nyquist theorem. The Merging Unit is thus limited by its sampling frequencies and will not

be able to be correctly used for transient earth fault current detection which may require input

frequencies of up to 12kHz. MU may also not be able to correctly detect higher frequency

transient signals relevant to transient based protection for Extremely High Voltage (EHV)

transmission lines, which are of the magnitude of hundreds of many kHz or higher

167

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.5. DESCRIPTION OF RTDS MODELLING AND MERGING UNIT TEST PROGRAMS

7.5.1. RTDS Modelling

Fig. 7.33 below shows the model of the RTDS circuit used to produce the analogue voltage

for the MU Conversion Error and MU Filter Performance Tests. A similar circuit was used

for the current injections. Another similar circuit was used for the GPS Timestamp Delay

Tests.

Fig. 7.33: DAQ Voltage Output based on 50V 50Hz injection

The top part of the Fig. shows a 2V source that has an internal resistance of 1 ohm. It is in

parallel with 2 resistor branches, one 1ohm and the other 0.5 ohms. In the second branch,

there is a circuit breaker which is normally open, and when it is closed, it has a resistance

of 0.001 ohms. As the circuit breaker normally open, the voltage source is normally in

series with the 1 ohm resistor in the first branch.

The bottom part of the Fig. shows the GPS triggered pulse arrangement. Every second, a

GPS pulse is sent to the digital input port, and this sends a pulse with a duration of 0.030s

168

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

or 30ms to the circuit, breaker, thus triggering the circuit breaker and causing it to close for

approximately 30ms. During that period, the 0.5 ohm resistor in the second branch will then

be connected in parallel with the source and the 1 ohm resistor. This connection will cause

a voltage dip across the measurement node (N1) for approximately 30ms. This has been

displayed in the oscilloscope output window shown in Fig. 7.29a in the previous section.

The dip is introduced in order to assist with the alignment of the MU and DAQ output (Fig.

7.34). The beginning of the dip occurs around the time that the GPS pulse has been

received by RTDS and since the DAQ and MU are both GPS synchronized, they will

capture the dip at roughly the same period, (when their GPS subsecond timestamp

counters have been reset to zero by the GPS pulse). From there a point is selected,

usually the second instance when the sampled value changes from a negative value to a

positive value (capture count 4028 in the DAQ, Fig. 7.34a and capture count 1204 in the

MU, Fig. 7.34b ). Beginning from that point, 10 cycles are then selected and then the RMS

value of the cycles is obtained and used for further analysis. (Note that as stated in section

7.3.2., the Omicron Amplifier amplified the RTDS output signals in order to provide the

actual signals that were sent to the MU and DAQ (the latter via the isolation amplifier) ).

a. DAQ Voltage Output

169

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

b. Merging Unit Voltage Output

Fig. 7.34: DAQ and merging unit Voltage Output based on 50V 50Hz injection

This alignment was seen to be especially useful when comparing the current output (Fig.

7.35).

a. DAQ Current Output

170

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

b. Merging Unit Current Output

Fig. 7.35: DAQ and merging unit Current Output based on 3AV 50Hz injection

(notice the 90deg phase shift between the MU and the DAQ output)

It can be seen that when the current output from the merging unit is aligned with that of the

DAQ, there is an approximately 90 degree phase shift between them, hence in order to

compare the corresponding samples the starting instance for the DAQ was when the

sampled values had changed from a negative to a positive value (Capture count 8451 in

Fig. 7.35a) while for the MU, the same instance would be when the sampled values

changed from a positive to a negative value (Capture count 2083 in Fig. 7.35b).

7.5.2. Sampled Values Recovery Test ProgramFig. 7.36 shows the program flow of the sampled values recovery test program. The

program captures the samples sent by the merging unit over the Ethernet network. The

Ethernet based samples are captured and saved in an MU data file.

171

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.36: Program flow of sampled values recovery test program

The phase voltage (or current if it the current test) is extracted from the MU data file and

plotted on the program window. A new set of samples and then captured, processed and

plotted and this continues until the user clicks stop or the steps have been repeated a

predetermined number of times.

7.5.3. Data Retrieval program for GPS Timestamping Delay

Fig. 7.37 shows the program flow of the data retrieval program for GPS Timestamping

Delay. The program captures the samples sent by the merging unit over the Ethernet

network. The Ethernet based samples are captured an saved in an MU data file. The user

is then prompted to view the captured data and if selected, an Excel file is then opened

172

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

and when updated, it retrieves the latest voltage/current sampled values and plots these

values. The user can then refocus the plot so that the event of interest is within view.

Fig. 7.37: Program flow of data retrieval program for GPS Timestamping Delay

In order to complete the analysis, the user locates the MU samplecount data

corresponding to the event of interest and then this samplecount is converted to seconds

by dividing it by 4000. this result is the timestamp of the event in the form of a decimal

number (timeB). The GPS timestamping delay is then deduced by subtracting timeB from

timeA which is the oscilloscope timestamp of the same event.

173

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.5.4. Process Delay Test and Arrival Time Uniformity Test Program

Fig. 7.38 shows the program flow of the Process Delay Test and Arrival Time Uniformity

Test Program. The program captures the samples sent by the merging unit over the

Ethernet network. When each sample arrives it is timestamped by the high accuracy

Endace Network Monitoring Card. The Ethernet based samples are saved together with

the accurate and corresponding arrival timestamp data in an MU data file. The MU

current/voltage and samplecount data is retrieved from the MU data file and saved in a 2 nd

MU data file. The MU arrival timestamp data represents the time the sample arrived at the

network Monitoring card. It is retrieved from the 1st MU data file and saved in a 3rd MU data

file. It is then extracted from the 3rd MU data file and the time is converted into seconds. It

is now in the form of a large number made up of integers and decimals and it is the

decimal part that is used for comparison with the MU samplecount. For this reason, the

decimal part of the arrival timestamp number is separated from the integer part of the

number and saved in a 4th MU data file.

The user is then presented with the option of viewing the process delay, and if this is

selected, an Excel file is then opened, and when it is updated, the MU samplecount is

extracted from the 2nd MU data file and converted into seconds in the form a decimal

number (timeB) by dividing it by 4000. The corresponding arrival timestamp second data is

(in the form of a decimal) is designated as timeD. The MU process delay is then deduced

by subtracting timeB from timeD (as described in equation 31).

After the MU Process Delay test has been carried out, the user is also able to carry out the

Arrival Time Uniformity test and is presented with the option to view the Arrival Time

Uniformity. If this option is selected, an Excel file is opened and when it is updated, the

arrival timestamp data for is extracted and the arrival time uniformity difference is derived

as described in Section 7.4.4.. The uniformity difference is then plotted.

174

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.38: Program flow of Process Delay Test and Arrival Time Uniformity Test Program

175

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.5.5. Data Retrieval Program for MU Error Test and MU Filter Test

Fig. 7.39 shows the program flow of the data retrieval program for MU Error Test and MU

Filter Test. The program captures the samples sent by the merging unit over the Ethernet

network. The Ethernet based samples are captured an saved in an MU data file. Almost

simultaneously, the DAQ begins sampling the same analogue voltage/current signals as

the MU and it also acquires the corresponding timestamp for each sample. The samples

and corresponding timestamps are saved in a DAQ data file. The user is then presented

with an option of viewing the captured data and if this is selected, an Excel file is then

opened and when updated, it retrieves the latest voltage/current sampled values for both

the MU and DAQ and plots these values. The user can then refocus the plots so that the

event of interest is within view in both the MU and DAQ window.

The user then specifies where the MU voltage/current RMS analysis should begin, as well

the number of samples that will be used for the RMS analysis. The same is done for the

DAQ. The beginning point should coincide with the point that was specified for the MU.

Also the number of samples should be consistent with the number of samples specified for

the MU. The MU samples at 4kHz and for a 50Hz signal the MU would thus have 4000/50

samples per cycle or 80 samples per cycle. For this analysis, the equivalent 10 cycles for

a 50Hz input signal were specified. 10 cycles for a 50 Hz signal equals 80 x 10 or 800

samples (Fig. 7.34a). Since the DAQ was set to capture at 16kHz, the equivalent of 10

cycles for a 50Hz input signal equals 800 x 4 or 3200 samples(Fig. 7.34b).

176

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.39: Program flow of Data Retrieval Program for MU Error Test and MU Filter Test

177

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

For the MU conversion error, the frequency of all input signals was 50Hz. The Filter

performance however involved input signals of varying frequencies, up to 1950Hz. At

50Hz, 10 cycles correspond to a 200ms window. This 200ms window was consistently

used for all frequencies, hence an 800 sample RMS analysis was maintained for the MU

while a 3200 sample RMS analysis was maintained for the DAQ.

7.6. MERGING UNIT PERFORMANCE TESTS RESULTSThe results of the performance tests carried out on merging units from 3 different

manufacturers shall be discussed. These tests include the sampled values recovery test,

process delay test, GPS Timestamping delay test, arrival time uniformity test, conversion

error test and filter performance assessment. More of the merging unit performance test

result data can be seen in APPENDIX D.

7.6.1. Ethernet Frame Format Check And Sampled Values Recovery Test

Ethernet Frames of MUs 1- 3 adhere to the IEC 61850 9-2 (LE) format. Fig. 7.40 shows

part of an Ethernet frame that has been recovered from a merging unit. This part is the

Application Protocol Data Unit (APDU).

178

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.40: Ethernet Frame Format Check

The sampled values have been successfully recovered from the merging unit. As can be

seen in Fig. 7.40, the hexadecimal bits “ff ff f9 ba” have been converted to a decimal

number to represent the phase B current sampled value at that instant (-1606mA).

7.6.2. GPS Timestamping Delay TestThe table below shows the GPS Timestamping Delay results of repeated tests carried out

on MUs 1 - 3.

179

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Table 7.6: GPS Timestamping Delay (GTD) Test Results

Measure of Dispersion

Result (microseconds)MU1 MU2 MU3

Average 410 -70 131Standard Deviation 65.19 83.67 81.73Variance 4.25E-003 7.00E-003 6.68E-003Maximum 500 0 200Minimum 350 -200 5Range 150 200 195

It is seen from Table 7.6 that in the case of MU2, the average GTD is negative, which

would imply that the MU timestamped the analogue signal before the analogue signal was

sent, and this is not expected to be the case. The accuracy of the results depends on a

number of different factors. The timestamp timeA from the oscilloscope was measured to

the nearest 10th of a millisecond (100μs). The timestamp timeB from a merging unit is

measured to the nearest 250μs (that is 1/4000 s). Also, it is possible that MU2 possesses a

method of determining exactly when the analogue signal was sent, and then time-stamping

the corresponding sampled value using that time. Thus, MU2 may be able to compensate

for any actual delay when timestamping the sampled values, while MU1 and MU3 may not

presently be able to compensate for such a delay. Another factor to take into account is the

possible reading error that may occur while taking measurements from the oscilloscope.

7.6.3. Process Delay TestFig. 7.41 below shows the process delay in microseconds for 400 packets captured from

MU1.

180

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

405

410

415

420

425

430

435

440

445

450

455

400 450 500 550 600 650 700 750 800

Capture Count

Del

ay (μ

s)

Fig. 7.41: MU1 GPS Timestamping Delay Test (400 packets)

It can be seen from Fig. 7.41 that the delay pattern is quite steady and after approximately

every 50 samples, the delay sharply increases and then reduces until it gets to being

relatively steady again.

Fig. 7.42 below shows the process delay in microseconds for 400 packets captured from MU2.

Fig. 7.42: MU2 GPS Timestamping Delay Test (400 packets)

181

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

It can be seen from Fig. 7.42 that the delay pattern for MU2 is relatively inconsistent and

rises and falls sharply throughout the sample view. The lowest delay is higher than the

higher than the highest delay observed in MU1.

Fig. 7.43 below shows the process delay in microseconds for 400 packets captured from

MU3.

Fig. 7.43: MU3 GPS Timestamping Delay Test (400 packets)

It can be seen from Fig. 7.43 that the delay pattern in MU3 falls in between that of MU1

and MU2. Its lowest value is still higher than the highest value of MU1, but its highest value

is still lower that the lowest value of MU2. The pattern is not as steady as that of MU1, yet

the delays do not rise and fall as sharply as that of MU2.

The table below shows the MUs 1-3 Process Delay results after repeated Ethernet packet

captures.

Table 7.7: Process Delay (PD) Test Results

Measure of Dispersion

Result (microseconds)MU1 MU2 MU3

Average 416.85 1170.49 521.71Standard Deviation 5.67 271.57 6.49Variance 3.21E-005 7.38E-002 0.00Maximum 474.00 2254.00 561.00Minimum 411.00 633.00 501.00

182

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Measure of Dispersion

Result (microseconds)MU1 MU2 MU3

Range 63.00 1621.00 60.00

Based on these results MU1 has the lowest process delay of 417µs followed by MU3

(522µs) and then MU2 (1170µs). It is seen that the overall average process delay for MU2

is about 2.8 times as much as that of MU1, while the process delay of MU3 is 1.25 times

as much as that of MU1. The standard deviation of MU1 is the lowest (5.7 μs) followed by

MU3 (6.5 μs) and with that of MU2 being much (271.6 μs). MU1 and MU3 have roughly the

same range of 60 μs while MU2 also has a much larger range of 1620 μs.

As in section 7.6.2., a number of factors need to be taken into account when considering

the accuracy of the results shown in Table 7.7. The previously discussed accuracy of the

MU is to the nearest 0.250ms (or 250µs) and the Ethernet packet arrival timestamp timeD

has a resolution of 7.5ns and also depends on the accuracy of the supplied GPS used for

synchronizing the Endace Network Monitoring Card. The GE Fibre Optic Ethernet switch

also introduces a very small delay. The GE switch has a latency of 5 μs + the packet time.

The packet time for an IEC 61850 9-2 LE packet is approximately 13.12 μs, hence the total

latency due to the Ethernet Switch is = 5 μs + 13.12 μs = 18.12 μs.

7.6.4. Arrival Time Uniformity Test

The results below show the difference between the arrival timestamps of successive

packets differ from 250 μs. Due to the fact that the Arrival Time Uniformity is directly

derived from the Process Delay, the patterns obtained for the ATU are very similar to that

observed in the Process Delay patterns.

Fig. 7.44 below shows the arrival time uniformity test results for 400 packets captured from

MU1.

183

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

-50

-40

-30

-20

-10

0

10

20

30

40

50

400 450 500 550 600 650 700 750 800

n

Δtn

- Δ

t (μ

s)

Fig. 7.44: Arrival Time Uniformity Plot (400 packets) MU1

It can be seen from Fig. 7.44 that the delay pattern is quite steady and after approximately

every 50 samples, the delay sharply increases and then reduces until it gets to being

relatively steady again.

Fig. 7.45 below shows the arrival time uniformity test results for 400 packets captured from

MU2.

Fig. 7.45: Arrival Time Uniformity Plot (400 packets) MU2

It can be seen from Fig. 7.45 that the delay pattern for MU2 is relatively inconsistent and

rises and falls sharply throughout the sample view. The lowest delay is higher than the

higher than the highest delay observed in MU1.

184

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.46 below shows the arrival time uniformity test results for 400 packets captured from

MU3.

Fig. 7.46: Arrival Time Uniformity Plot (400 packets) MU3

It can be seen from Fig. 7.46 that the delay pattern in MU3 falls in between that of MU1

and MU2. Its lowest value is still higher than the highest value of MU1, but its highest value

is still lower that the lowest value of MU2. The pattern is not as steady as that of MU1, yet

the delays do not rise and fall as sharply as that of MU2.

The table below shows the MUs 1-3 Process Delay results after repeated Ethernet packet

captures.

Table 7.8: Merging Unit Arrival Time Uniformity (ATU) Test Results

Measure of Dispersion

Result (microseconds)MU1 MU2 MU3

Average 0.00 0.22 0.01Standard Deviation 6.76 270.33 6.91Variance 4.57E-005 7.31E-002 4.77E-005Maximum 57.00 1045.00 28.00Minimum -55.00 -238.00 -32.00Range 112.00 1283.00 60.00

185

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Based on these results MU1 and MU3 can be said to be on average extremely uniform

with an overall Arrival Time Uniformity (ATU) difference of 0 μs and 0.01 μs respectively.

They both have a standard deviation of less than 7 μs, but the range of MU1 is almost

twice (112 μs ) that of MU3 (60 μs). The ATU of MU2 is on average very uniform with an

ATU of 0.22μs . Its standard deviation is the highest (270 μs) as is the range (1283 μs).

7.6.5. Conversion Error Test

The results of the conversion error tests shall now be shown. It may be important to note

that for the current and voltage outputs provided by RTDS, the GPS synchronized dip

duration varied slightly each second, and the actual magnitude provided by RTDS may

also have changed slightly each second. This provided an even stronger reason to repeat

the tests and derive the average error values for each approximate magnitude injection

(10V – 120V for voltage and 1A – 5A for current). For each MU conversion error plot, the

overall average error is displayed, as is the range.

7.6.5.1. Voltage Injection

Fig. 7.47 shows the MU1 Conversion Error (%) plotted against the input voltages ranging

from 10V to 120V.

Fig. 7.47: MU1 Conversion Error (Voltage)

186

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

From Fig. 7.47 it can be seen that the error largely reduces as the voltage is increases.

The error range is approximately 0.22%, and the average error is -1.16%. Fig. 7.48 shows

the MU2 Conversion Error (%) plotted against the input voltages ranging from 10V to 120V.

Fig. 7.48: MU2 Conversion Error (Voltage)

Fig. 7.48 shows that the error appears to alternatively increase and decrease. However, as

in MU1, the error range is 0.22%. It has a slightly higher average value of 1.28%. Fig. 7.49

shows the MU3 Conversion Error (%) plotted against the input voltages ranging from 10V

to 120V.

Fig. 7.49: MU3 Conversion Error (Voltage)

187

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.49 shows that the error decreases with and increased voltage injection, with a range

of 0.04% and an average value of -0.951%. Fig. 7.50 shows the Conversion Error (%) of

the 3 MUs plotted together with input voltages ranging from 10V to 120V.

Fig. 7.50: MU1, MU2 and MU3 Conversion Error (Voltage)

Comparing the results from the 3 MUs (Fig. 7.50) it can be seen that MU3 has the lowest

error followed by that of MU1 and then MU2. It can be seen that the MU3 error is the

steadiest again followed by MU1 and then MU2.

7.6.5.2. Current InjectionThe Fig.s below illustrate the average error results based on repeated current injections

fed to MUs 1 – 3. It was seen that only the MU2 output introduced a 90 degree phase shift

for current injections (Fig. 7.35) and the samples were aligned accordingly for comparison.

Fig. 7.51 shows the MU1 Conversion Error (%) plotted against the input currents ranging

from 1A to 5A.

188

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.51: MU1 Conversion Error (Current)

Fig. 7.51 shows that the error decreases with an increased current injection, with a range

of 0.82% and an average value of 1.27%. Fig. 7.52 shows the MU2 Conversion Error (%)

plotted against the input currents ranging from 1A to 5A.

Fig. 7.52: MU2 Conversion Error (Current)

Fig. 7.52 shows that the error decreases with and increased current injection, with a higher

range (1.01%) than that of MU1 but with a lower average value (0.94%) than MU1. Fig.

7.53 shows the MU3 Conversion Error (%) plotted against the input currents ranging from

1A to 5A.

189

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.53: MU3 Conversion Error (Current)

Fig. 7.53 shows that the error drops when it increases up to 2A and then it increases with a

slight dip at 5A. It has the lowest range (0.65%) and highest average (1.64%). Fig. 7.54

shows the Conversion Error (%) of the 3 MUs plotted together with input current ranging

from 1A to 5A.

Fig. 7.54: MU1, MU2 and MU3 Conversion Error (Current)

190

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Comparing the current error results from the 3 MUs, it can be seen that for MU1 and MU2

the error reduces as the current increases while in the case of MU3, the error drops,

increases and then slightly dips.

7.6.6. Filter Performance Test

The results of the filter performance tests shall now be shown. As in the Conversion Error

Test, it may be useful to note that for the current and voltage outputs provided by RTDS,

variations of the GPS synchronized dip durations were observed, and the actual

magnitude provided by RTDS may have changed slightly each second, hence the need to

repeat the tests at a particular frequency and derive the average voltage and current ratios

at the approximate magnitude (50V or 2A) injection.

7.6.6.1. Voltage InjectionFig. 7.55 shows the output of the DAS and merging units from a 50V, 50Hz square wave

injection. It can be seen the DAS and MU3 are able to faithfully reproduce the square wave

shape, however in the case of MU1, and MU2, there are some slight variations from a

square wave shape.

a. 50V, 50Hz Square Wave Injection b. DAS Output

c. MU1 Output d. MU2 Output

191

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

e. MU3 Output

Fig. 7.55: MU and DAS output from 50V 50Hz square wave injection

Fig. 7.56 shows one MU1 Filter Analysis curve after a 50V 50Hz square wave injection. It

can be seen from Fig. 7.56 that the cut-off frequency is well below 2kHz. The test was

repeated using the sinewave injection test and the average of the voltage ratios obtained at

different frequencies can be seen in Fig. 7.56 b below. The cut-off frequencies were seen

on average to be consistent after repeated square wave and sinewave voltage injections.

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

1.1

0 200 400 600 800 1000 1200 1400 1600 1800 2000freq f (Hz)

MU

/DA

S

CUT-OFF FREQUENCY

a. Filter Analysis Curve, square wave injection, MU1

192

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

b. Filter Analysis Curve, sine wave injection, MU1

Fig. 7.56: MU1 Filter Performance (Voltage)

It can also be seen that the result of the sinewave injection test is largely consistent with

the result of the square wave injection test. The results for MU2 were quite different. Fig.

7.57a shows the MU2 Filter Analysis curve after a 50V 50Hz square wave injection. It can

be seen that the cut-off frequency point does not appear within the 2kHz frequency range,

and though it is not shown, there were instances where the cut-off would appear within the

2kHz range. The 50V sine wave is thus injected at different frequencies and the voltage

ratio is plotted as can be seen in Fig. 7.57b.

a. Filter Analysis Curve, square wave injection, MU2

193

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

b. Filter Analysis Curve, sine wave injection, MU2

Fig. 7.57: MU2 Filter Performance (Voltage)

It can be seen that even with repeated sinewave injection tests, the cut-off frequency

appears to be greater than 2000Hz. This bandwidth is higher than anticipated, since if the

sampling rate is 4kHz, then the maximum bandwidth is expected to be no more than half of

that frequency.

Fig. 7.58a shows the MU3 Filter Analysis curve after a 50V 50Hz square wave injection,

and the cut-off frequency point also does not appear within the 2kHz frequency range, and

as with MU2, the results varied during different square wave voltage injections. A 50V

sine wave is then injected at different frequencies and the voltage ratio is plotted as can be

seen in Fig. 7.58b.

0

0.2

0.4

0.6

0.8

1

1.2

0 200 400 600 800 1000 1200 1400 1600 1800 2000freq f (Hz)

MU

/DA

S

194

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

a. Filter Analysis Curve, square wave injection, MU3

b. Filter Analysis Curve, sine wave injection, MU3

Fig. 7.58: MU3 Filter Performance (Voltage)

It can be seen that this time the cut-off frequency point does appear within the 2kHz

frequency and it is approximately 1700Hz.

Table 7.9 lists the cut-off frequencies based on the voltage injection tests carried out on

MUs1-3 (accurate to the nearest 50Hz).

Table 7.9: MU Filter Performance Test Results (Voltage)

merging unit

Average cut-off Freq

(Hz)MU1 250MU2 >2000MU3 1700

The results show that MU3 has a cut-off frequency (1700Hz) which is greater than that of

MU1 (250Hz). MU2 on the other hand, appears to have a cut-off frequency which is greater

than 2000Hz.

195

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

7.6.6.2. Current InjectionFig. 7.59 shows the output of the DAS and merging units from a 1A, 50Hz square wave

injection. It can be seen the DAS and MU3 and in this case MU2 are able to faithfully

reproduce the square wave shape, however the output of MU1 still has some variation from

a square wave shape.

-1.5

-1

-0.5

0

0.5

1

1.5

71 271 471 671 871

Capture CountA

a. 1A, 50Hz Square Wave Injection b. DAS Output

c. MU1 Output d. MU2 Output

e. MU3 Output

Fig. 7.59: MU and DAS output from 1A 50Hz square wave injection

196

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

Fig. 7.60a shows one of the MU1 Filter Analysis curves after a 1A 50Hz square wave

injection, while Fig. 7.60b shows the MU1 Filter Analysis curve, based on the average of

repeated 2A sine wave injections at different frequencies. The cut-off frequencies were

seen on average to be consistent after repeated square wave and sinewave current

injections.

00.10.20.30.40.50.60.70.80.9

11.11.21.31.4

0 200 400 600 800 1000 1200 1400 1600 1800 2000

freq f (Hz)

MU

/DA

S

CUTOFF FREQUENCY

a. Filter Analysis Curve, square wave injection, MU1

b. Filter Analysis Curve, sine wave injection, MU1

Fig. 7.60: MU1 Filter Performance (Current)

197

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

It again be can be seen from Fig.s 7.60a and 7.60b that the cut-off frequency is well below

2kHz, the result of the sinewave injection test is largely consistent with the result of the

square wave injection test. The cut-off frequency for the current injection (approximately

400Hz) is higher than that of the voltage injection (approximately 250Hz).

Fig. 7.61a shows the MU2 Filter Analysis curve after a 1AV 50Hz square wave injection

while the average current ratio after sine wave injections of 2A at different frequencies is

plotted in Fig. 7.61b.

0

0.2

0.4

0.6

0.8

1

1.2

1.4

0 200 400 600 800 1000 1200 1400 1600 1800 2000

freq f (Hz)

MU

/DA

S

a. Filter Analysis Curve, square wave injection, MU2

b. Filter Analysis Curve, sine wave injection, MU2

Fig. 7.61: MU2 Filter Performance (Current)

198

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

As with the voltage injections, the MU2 Filter Analysis test results based on the square

wave injections were not consistent, and as is shown in Fig. 7.61a, the cut-off frequency

point sometimes did not appear within the 2kHz frequency range. With repeated current

sinewave injection tests, the cut-off frequency is once again seen to be apparently greater

than 2000Hz (Fig. 7.61b) . Fig. 7.62a shows one MU3 Filter Analysis curve after a 1AV

50Hz square wave injection while the average current ratio after repeated 2A sine wave

injections at different frequencies is plotted as can be seen in Fig. 7.62b.

0

0.2

0.4

0.6

0.8

1

1.2

1.4

0 200 400 600 800 1000 1200 1400 1600 1800 2000

freq f (Hz)

MU

/DA

S

a. Filter Analysis Curve, square wave injection, MU3

b. Filter Analysis Curve, sine wave injection, MU3

Fig. 7.62: MU3 Filter Performance (Current)

The current filter analysis curve based on repeated square injections gave different results

including instances where the cut-off frequency did not appear within the 2kHz range.

199

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

However, as can be seen in Fig. 7.62b, with repeated sinewave injections, the cut-off

frequency was slightly more (1750Hz) than that obtained for the voltage injection (1700Hz).

Table 7.10 lists the cut-off frequencies based on the current sinewave injection tests

carried out on MUs1-3 (accurate to the nearest 50Hz).

Table 7.10: MU Filter Performance Test Results (Current)

merging unit

Average cut-off Freq

(Hz)MU1 400MU2 >2000MU3 1750

The results show that, as with the voltage injections, MU3 has a cut-off frequency (1750Hz)

which is greater than that of MU1 (400Hz). MU2 again appears to have a cut-off frequency

which is greater than 2000Hz, which is higher than expected for a 4kHz sampling

frequency.

7.7. SUMMARYThe prototype and commercially available merging units have been listed in this chapter.

The design of a merging unit performance test bed has also been discussed.

The results of the performance tests carried out on merging units made by 3 different

manufacturers have been discussed. These tests include the Ethernet Frame Format

check, sampled values recovery test, process delay test, GPS Timestamping delay test,

arrival time uniformity test, conversion error test and filter performance assessment. The

main similarity between the merging units was that it was possible to indeed recover the

sampled values from the Ethernet packets. In other tests, their characteristics were seen to

vary relatively widely. Also no one merging unit was seen to perform consistently better

than others in all tests. For example MU3 had the lowest voltage conversion error, but the

other 2 merging units performed better during the current conversion error tests at higher

current inputs (above 3A). MU1 had the lowest process delay, but also had the lowest

200

Chapter 7 - Design and Implementation of Merging Unit Performance Test Bed

bandwidth in both voltage and current injection tests. MU1 had the lowest GPS

timestamping delay but had the highest process delay.

As these merging units are mostly prototypes being developed and there is not yet a

merging unit specification, the merging units may need to be modified to meet the utility

requirement (for instance, if the utility specifies that the merging unit should be able to

recover samples up to 2kHz, or if the GPS Timestamping delay must be less than 250 μs,

or if the conversion error must be less than +/- 1 %, or the desired bandwidth). The results

of each individual merging unit set of tests have been fed back to the corresponding

vendor, as well as to National Grid.

201

CHAPTER 8 CONCLUSION AND FUTURE WORK

8.1. CONCLUSIONThe IEC 61850 standard has been implemented in varying degrees in substations around

the world, and has the potential to extend its impact beyond substations. While there is a

need for some refinement so that a major goal of interoperability among different devices

can be achieved, the immediate and long term benefits of IEC 61850 are not in question.

The immediate benefits of an IEC 61850 based architecture include the flexibility to adapt

to changes as the technology and processes associated with smart grids and renewable

energy systems mature. Such changes include growth in the communication network due

to the addition of a new substation bay, or upgrades of existing bays to ensure that they

can keep up with the latest technology advances. In the long term, the architecture the

technology and processes associated with renewable energy and smart grids are expected

to have matured, but maintenance would still need to be carried out, and it would still be

important to be able to continue to provide the communication services to the other bays in

the substation while one part of the substation has to be taken out in order to undergo

maintenance.

In response to these needs, the design of a simple, long life IEC 61850 based

communication architecture has been presented in this Thesis. The architecture is

expected to be modular, flexible and robust enough to cope with growth, outages and even

shrinkage that may occur in transmission substations. This architecture design has taken

into account golden rules which have been outlined by protection and control experts from

National Grid and device manufacturers. As part of the architecture design, the security

implementation issues were also taken into account and as a result of this, it was proposed

that the critical substation wide information should be kept separate from the extremely

critical relatively fast information concentrated within the bay. The process bus architecture

has been applied to the following bays within a Double Busbar (DBB) substation: DBB

Feeder bay, DBB transformer bay, DBB Bus coupler/Bus coupler bay. The architecture

has also been applied to the following bays within a Mesh Corner (MC) substation: MC MC

bay, MC feeder bay and MC transformer bay. It has been seen that the architecture

202

Chapter 8 - Conclusion and Future Work

concept is simple and basic, yet adaptable to complex situations, such as can be found in

the Mesh Corner substation.

Extensive reliability analyses have been carried out on various scenarios which are

detailed applications of this proposed process bus architecture to the bays of different

Double Busbar and Mesh Corner substation bays. The reliability block diagram (RBD) was

useful because it provided an overall model of the system in terms of components and

subsystems and the RBD was used to represent the high level success path of the system

from which the system reliability was derived. For the less complex scenarios, subsystems

could be readily broken down into basic series/parallel combinations from which the

subsystem and resulting system reliability could be derived. For the more complex

scenarios, event trees were used to model the subsystems which could not readily be

broken down into basic series/parallel combinations. The event tree allowed for the

specification of requirements for the successful operation of the subsystem and based on

this list of requirements, the subsystem reliability could then be derived. This resulting

subsystem reliability could then be fed into the reliability block diagram and the system

reliability could be derived using a series/parallel combination. From the analyses carried

out on the different bays it was seen that the system was more likely to be reliable when

based on a star architecture than when based on a ring architecture. The most reliable

architecture scenarios were duplicated star connections. From the sensitivity analysis

carried out, it could be seen that the system reliability was overall most likely to improve

when the merging units' reliability was increased. However this was seen to depend on

how reliable the system was because on most occasions, during the first one or two

scenarios when the system was less reliable/available, the fibre optic cables had a higher

impact on system reliability. After the Merging Unit, the Circuit Breaker Controllers had the

next highest overall reliability impact followed by the fibre optic cables and finally the

Ethernet switch. These results were based on estimated reliability figures and in practice

the devices may be more reliable than initially estimated.

Life cycle costing has been used to illustrate how an optimum architecture scenario can be

selected from a range of architecture scenarios. As the reliability, availability and life cycle

cost parameters have been estimated, the methodology has been essentially used to

illustrate how the optimum architecture can be determined. The penalty factor has been

203

Chapter 8 - Conclusion and Future Work

varied between extremely low and high values, and the actual penalty is most likely to fall

in between these 2 extremes. The penalty factor has been varied to show its impact on the

resulting optimum architecture and the corresponding optimum reliability.

Security means the security against “unwanted commands“. It is a measure of the degree

of certainty that a relay will not operate incorrectly”, Dependability is a measure of the

degree of certainty that a relay system will operate correctly

The primary focus of this project has been on the dependability, in particular the

dependability of the communication architecture itself. The dependability assessment has

been in the form of estimating the probability that the protection and control devices would

be able to receive adequate information form the current/voltage transformers and circuit

breakers via this communication architecture, and in turn send trip commands to the circuit

breakers when required.

The reliability (in terms of dependability) of the architecture, based on the analysis that has

been carried out, has been seen to be somewhat reduced, compared with the original

hardwired configuration, or indeed when compared the other communication protocols.

This may be in some measure be attributed to the overall increased part count, and the

use of components/devices which are not as reliable as the copper cables. This decrease

can be mitigated by improving the reliability of the individual components/devices and

applying proper redundancy. However, the use of a Merging Unit to send digital data to the

relay would make it possible to incorporate additional features in the relay which would

improve the security and availability. Features such as continuous internal self testing and

data-integrity mechanisms will make it possible for personnel to solve faults with more

precision and with less down time. Failures which may have been undetected in traditional

hardwired configurations may now be detected more easily as a result of this digital

communication. The rectification of these failures would ensure that the protection

equipment operates properly when required, thus enhancing its security. The continuous

self monitoring may also reduce the human errors which could cause the maloperation of

the protection systems during testing and maintenance tasks.

The use of fibre optic cables for the process bus means that personnel would not be

exposed to potentially lethal voltage/current when they need to replace the relays, hence

204

Chapter 8 - Conclusion and Future Work

this is expected to reduce the downtime and have a positive impact on availability. In terms

of Life Cycle Cost depending on the penalty for downtime, the LCC for the new architecture

may prove less as a result of the overall downtime that may occur during maintenance of

upgrades.

Finally, a Merging Unit performance test bed has been developed for testing these crucial

devices which send current and voltage data to the protection and control devices. The

results of the tests have been fed back to National Grid and the manufacturers, who may

then use the data to assist with the drafting of a merging unit Test Bed Specification, and

also to help the manufacturers to make refinements to the merging units in order to make

interoperability more readily achievable.

This test bed has been used to test the following features of merging units:

• Ethernet frame format check and sampled values recovery test (To check if the

Ethernet frames/packets sent from the MU are of the format specified by IEC

61850 9-2 “Light Edition” (LE). Also, to check if sampled values can be successfully

recovered from the merging unit)

• MU GPS Timestamping Delay (To determine the delay that occurs when the MU

timestamps the digitized signal)

• Process Delay (To determine the delay resulting from factors such as the MU

encapsulating the sampled values into Ethernet frames and then transmitting these

Ethernet frames to the receiving device)

• Arrival Time Uniformity (To check how regularly the Ethernet frames arrive at the

receiving device).

• MU Conversion Error Test (To determine the amplitude error of a MU when it

converts an analogue signal to sampled values) and

• MU Filter Performance (To check how much of the original signal the MU is able to

recover at different frequencies)

The main similarity between the merging units was seen in the Ethernet frame format

check and sampled values recovery test were it was possible to indeed recover the

sampled values from the Ethernet packets. In other tests, their characteristics were seen to

vary relatively widely. Also no one merging unit was seen to perform consistently better

205

Chapter 8 - Conclusion and Future Work

than others in all tests. For example MU1 had the lowest process delay and the highest

arrival time uniformity, but also had the lowest bandwidth in both voltage and current

injection tests. MU2 had the lowest GPS timestamping delay but had the highest process

delay. MU3 had the lowest voltage conversion error, but the other 2 merging units

performed better during the current conversion error tests at higher current inputs (above

3A). A key benefit of this test bed is that it has been used to show that it is flexible enough

to assess the performance of merging units irrespective of who manufactured them and as

a result, it has been able to provide a range of key performance metrics which can be

useful to both National Grid and the manufacturers in achieving a major goal of IEC 61850,

which is interoperability.

8.2. KNOWLEDGE CONTRIBUTIONS TO RESEARCH AREA Based on the conclusion described in the above section, the highlights of the contributions

made by this thesis are:

✔ The design of a simple, long life IEC 61850 based process bus architecture which

is modular, flexible and robust. This architecture has been designed to cope with

shrinkage, growth, or outages which may occur in transmission substations;

✔ The application of this architecture to different National Grid Double Busbar and

Mesh Corner Bays leading to a variety of process bus architecture scenarios;

✔ The application of existing reliability analysis methodologies in order to evaluate

the reliability of the process bus architecture scenarios;

✔ The application of existing life cycle costing methodologies in order to select an

optimum scenario from a range of process bus architecture scenarios;

✔ The design of a performance test bed for testing Merging Units, the crucial devices

which send sampled current and voltage data to the protection and control

devices; and

206

Chapter 8 - Conclusion and Future Work

✔ The implementation of the Merging Unit performance test bed. 3 actual Merging

Units made from different manufacturers have been tested, leading to the

generation of performance test data that can help facilitate interoperability.

8.3. FUTURE WORKIt may be useful to scale the reliability analysis so that it is carried out for the substation –

a combination of the different bays. Busbar Protection was not considered in this analysis

so it may be beneficial to incorporate busbar protection in the reliability analysis.

The proposed architecture has been applied hypothetically to a substation. Carrying out an

actual implementation of the architecture, even in a laboratory setting may help with the

identification of the quantifiable strengths and disadvantages of the architecture.

The merging unit performance test results shown in this thesis were based on tests that

were carried out separately on one merging unit at a time. It is however possible that

testing more merging units simultaneously may have an effect on characteristics such as

the MU process delay, since the presence of additional MUs on the network will increase

the traffic. It may thus be useful to explore this option of testing the merging units

simultaneously. Also the merging unit tests were based on only single phase injection.

There would be some benefits in carrying out the tests based on 3 phase injections. The

comparisons were made mainly based on magnitude of the current and voltage signals.

While the GPS timestamp delay has provided the delay in terms of microseconds, future

upgrades of the test bed may also be able to incorporate instantaneous conversions of the

delay results from seconds to phase angle differences.

The MU test analyses were based on cycles of pure sinewaves. Future work could

incorporate analysis of the signals generated under fault conditions.

The merging units tested so far have been able to accept an external synchronising signal

mostly based on a 1 pulse per second (pps) input which goes to the merging units' clocks.

One merging unit was synchronised using an external synchronizing signal based on IRIG-

B inputs. It is expected that the merging unit samples should be time stamped with an

207

Chapter 8 - Conclusion and Future Work

accuracy of +/- 4 microseconds. However, each timestamp based on the sample count

field located in the merging unit Ethernet packet had a resolution of 250 microseconds, and

the oscilloscope currently used for the project has a resolution of 100 microseconds, thus it

is not currently possible to test the accuracy of the synchronisation to the nearest

microsecond. However, it may become possible to do so if the refrTm Refresh Time field in

the Ethernet packet is used and if oscilloscopes used for future tests are accurate to the

nearest 0.5 microseconds. The Refresh Time field allows for extremely accurate

timestamps, much more accurate than 1 microsecond. The IEEE 1588 time

synchronization standard defines the Precision Time Protocol (PTP) and allows sub-

microsecond synchronization of real-time clocks becomes and is expected to be applicable

to local area networks supporting multicast communications (including but not limited to

Ethernet). It is being considered for time synchronization in future distributed recording

systems, including such applications as wide area monitoring and recording.

Synchronization based on IEEE 1588 may become more widely available and may

warrant more study.

208

APPENDIX A

Figs. A.1 - A.7 below show the Process Bus Architecture Scenarios 4 – 10 for the Double Busbar Feeder Bay Process Bus (star).

Fig. A.1: Scenario 4 - Double Busbar Feeder Bay

Fig. A.2: Scenario 5 - Double Busbar Feeder Bay

Fig. A.3: Scenario 6 - Double Busbar Feeder Bay

Fig. A.4: Scenario 7 - Double Busbar Feeder Bay

209

Appendix A

Fig. A.5: Scenario 8 - Double Busbar Feeder Bay

Fig. A.6: Scenario 9 - Double Busbar Feeder Bay

Fig. A.7: Scenario 10 - Double Busbar Feeder Bay,

Table A.1: Number of Devices in each Scenario (Double Busbar Feeder Bay (Ring))

Scenario Number of DevicesSW MU CBC FIOC

1 6 6 3 182 8 6 3 233 8 6 3 244 10 6 3 295 10 6 3 306 12 6 3 357 12 6 3 36

210

Appendix A

Table A.2: Number of Devices in each Scenario (Double Busbar Transformer Bay (Star))

Scenario Number of DevicesSW MU CBC FIOC

1 3 13 3 192 4 13 3 213 4 13 3 224 4 13 3 235 5 13 3 256 5 13 3 267 5 13 3 278 5 13 3 289 5 13 3 2910 5 13 3 3111 6 13 3 3312 6 13 3 3413 6 13 3 3514 6 13 3 3615 6 13 3 3716 6 13 3 38

Table A.3: Number of Devices in each Scenario (Double Busbar Transformer Bay (Ring))

Scenario Number of DevicesSW MU CBC FIOC

1 6 13 3 252 8 13 3 303 8 13 3 314 10 13 3 365 10 13 3 376 10 13 3 387 10 13 3 398 10 13 3 419 12 13 3 4610 12 13 3 4711 12 13 3 4812 12 13 3 4913 12 13 3 50

Table A.4: Number of Devices in each Scenario (Mesh Corner Mesh Corner Bay (Star))

Scenario Number of DevicesSW MU CBC FIOC

1 3 8 3 142 4 8 3 163 5 8 3 184 5 8 3 195 5 8 3 20

211

Appendix A

Scenario Number of DevicesSW MU CBC FIOC

6 5 8 3 217 5 8 3 228 6 8 3 249 6 8 3 2510 6 8 3 2611 6 8 3 2712 6 8 3 28

Table A.5: Number of Devices in each Scenario (Mesh Corner Transformer Bay (Star))

Scenario Number of DevicesSW MU CBC FIOC

1 3 7 3 122 4 7 3 153 4 7 3 164 5 7 3 185 5 7 3 196 5 7 3 207 5 7 3 218 6 7 3 239 6 7 3 2410 6 7 3 2511 6 7 3 26

Table A.6: Number of Devices in each Scenario(Mesh Corner Transformer Bay (Ring))

Scenario Number of DevicesSW MU CBC FIOC

1 6 7 3 192 8 7 3 243 10 7 3 294 10 7 3 305 10 7 3 316 12 7 3 367 12 7 3 378 12 7 3 38

212

APPENDIX BTable B.1: Availability of Different Scenarios For The Double Busbar Feeder Bay (Star)

(Based On Estimated Availability figures)Scenarios Initial Only SW

set to 0.99999Only CBC

set to 0.99999Only MU

set to 0.99999Only Fibre set

to 0.999991 0.99893 0.99897 0.99902 0.99910 0.999622 0.99911 0.99915 0.99920 0.99928 0.999633 0.99929 0.99933 0.99938 0.99947 0.999644 0.99971 0.99971 0.99980 0.99988 0.999715 0.99971 0.99971 0.99980 0.99988 0.999716 0.99971 0.99971 0.99980 0.99988 0.999717 0.99971 0.99971 0.99980 0.99988 0.999718 0.99971 0.99971 0.99980 0.99988 0.999719 0.99971 0.99971 0.99980 0.99988 0.99971

10 0.99971 0.99971 0.99980 0.99988 0.99971

Table B.2: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Star) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9920 0.9929 0.9929 0.9938 0.99562 0.9930 0.9939 0.9939 0.9948 0.99573 0.9939 0.9949 0.9949 0.9958 0.99584 0.9969 0.9969 0.9978 0.9987 0.99705 0.9969 0.9969 0.9978 0.9987 0.99706 0.9969 0.9970 0.9978 0.9988 0.99707 0.9970 0.9970 0.9979 0.9988 0.99708 0.9970 0.9970 0.9979 0.9988 0.99709 0.9970 0.9970 0.9979 0.9988 0.997010 0.9970 0.9970 0.9979 0.9988 0.9970

Table B.3: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Estimated Reliability figures)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.7858 0.8051 0.8038 0.8220 0.92622 0.8349 0.8562 0.8541 0.8734 0.92643 0.9028 0.9116 0.9235 0.9444 0.94394 0.9116 0.9200 0.9320 0.9524 0.94395 0.9238 0.9292 0.9436 0.9635 0.94516 0.9269 0.9322 0.9460 0.9651 0.94517 0.9312 0.9355 0.9493 0.9673 0.9459

213

Appendix B

Table B.4: Availability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Estimated Availability figures)

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.99888 0.99896 0.99896 0.99905 0.999572 0.99924 0.99933 0.99933 0.99941 0.999593 0.99971 0.99971 0.99980 0.99988 0.999714 0.99971 0.99971 0.99980 0.99988 0.999715 0.99971 0.99971 0.99980 0.99988 0.999716 0.99971 0.99971 0.99980 0.99988 0.999717 0.99971 0.99971 0.99980 0.99988 0.99971

Table B.5: Reliability of Different Scenarios For The Double Busbar Feeder Bay (Ring) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9910 0.9928 0.9919 0.9928 0.99462 0.9929 0.9948 0.9938 0.9948 0.99483 0.9969 0.9969 0.9978 0.9987 0.99704 0.9969 0.9970 0.9978 0.9987 0.99705 0.9969 0.9970 0.9979 0.9988 0.99706 0.9970 0.9970 0.9979 0.9988 0.99707 0.9970 0.9970 0.9979 0.9988 0.9970

Table B.6: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Estimated Reliability figures)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.7486 0.7589 0.7679 0.7913 0.93712 0.7721 0.7830 0.7920 0.8161 0.93723 0.7963 0.8078 0.8169 0.8418 0.93734 0.8500 0.8584 0.8748 0.9014 0.94625 0.8604 0.8660 0.8824 0.9099 0.94636 0.8680 0.8736 0.8900 0.9183 0.94637 0.8755 0.8812 0.8976 0.9267 0.94638 0.8831 0.8888 0.9051 0.9351 0.94639 0.8907 0.8964 0.9127 0.9436 0.946310 0.8912 0.8979 0.9132 0.9438 0.946311 0.9012 0.9072 0.9225 0.9547 0.939112 0.9041 0.9099 0.9252 0.9565 0.939113 0.9071 0.9127 0.9279 0.9583 0.939114 0.9100 0.9154 0.9306 0.9602 0.939115 0.9129 0.9183 0.9333 0.9620 0.939216 0.9158 0.9208 0.9360 0.9639 0.9392

Table B.7: Availability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Estimated Availability figures)

214

Appendix B

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.99893 0.99897 0.99901 0.99910 0.999622 0.99911 0.99915 0.99920 0.99928 0.999633 0.99929 0.99933 0.99938 0.99946 0.999644 0.99971 0.99971 0.99979 0.99988 0.999715 0.99971 0.99971 0.99979 0.99988 0.999716 0.99971 0.99971 0.99979 0.99988 0.999717 0.99971 0.99971 0.99980 0.99988 0.999718 0.99971 0.99971 0.99980 0.99988 0.999719 0.99971 0.99971 0.99980 0.99988 0.9997110 0.99971 0.99971 0.99980 0.99988 0.9997111 0.99971 0.99971 0.99980 0.99988 0.9997112 0.99971 0.99971 0.99980 0.99988 0.9997113 0.99971 0.99971 0.99980 0.99988 0.9997114 0.99971 0.99971 0.99980 0.99988 0.9997115 0.99971 0.99971 0.99980 0.99988 0.9997116 0.99971 0.99971 0.99980 0.99988 0.99971

Table B.8: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Star) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9919 0.9928 0.9928 0.9937 0.99562 0.9929 0.9938 0.9938 0.9947 0.99573 0.9938 0.9948 0.9948 0.9957 0.99584 0.9968 0.9968 0.9977 0.9987 0.99885 0.9968 0.9969 0.9978 0.9987 0.99886 0.9968 0.9969 0.9978 0.9987 0.99887 0.9969 0.9969 0.9978 0.9987 0.99888 0.9969 0.9969 0.9978 0.9987 0.99889 0.9969 0.9969 0.9978 0.9987 0.9988

10 0.9969 0.9969 0.9978 0.9987 0.998811 0.9969 0.9969 0.9978 0.9988 0.998712 0.9969 0.9969 0.9978 0.9988 0.998713 0.9969 0.9969 0.9978 0.9988 0.998714 0.9969 0.9969 0.9978 0.9988 0.998715 0.9969 0.9969 0.9978 0.9988 0.998716 0.9969 0.9969 0.9978 0.9988 0.9987

Table B.9: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Ring) (Based On Estimated Reliability figures)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.7594 0.7795 0.7782 0.8097 0.91962 0.8068 0.8289 0.8268 0.8603 0.91983 0.8724 0.8826 0.8940 0.9302 0.93724 0.8778 0.8881 0.8994 0.9348 0.93725 0.8838 0.8939 0.9053 0.9399 0.9372

215

Appendix B

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

6 0.8898 0.8998 0.9112 0.9449 0.93727 0.8958 0.9057 0.9171 0.9500 0.93728 0.8962 0.9061 0.9175 0.9502 0.93729 0.8990 0.9087 0.9201 0.9520 0.9372

10 0.9020 0.9115 0.9230 0.9541 0.937211 0.9051 0.9143 0.9258 0.9561 0.937212 0.9082 0.9171 0.9287 0.9582 0.937213 0.9113 0.9199 0.9316 0.9602 0.9372

Table B.10: Availability of Different Scenarios For The Double Busbar Transformer (Ring) (Based On Estimated Availability figures)

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.9989 0.9990 0.9990 0.9990 0.99962 0.9992 0.9993 0.9993 0.9994 0.99963 0.9997 0.9997 0.9998 0.9999 0.99974 0.9997 0.9997 0.9998 0.9999 0.99975 0.9997 0.9997 0.9998 0.9999 0.99976 0.9997 0.9997 0.9998 0.9999 0.99977 0.9997 0.9997 0.9998 0.9999 0.99978 0.9997 0.9997 0.9998 0.9999 0.99979 0.9997 0.9997 0.9998 0.9999 0.999710 0.9997 0.9997 0.9998 0.9999 0.999711 0.9997 0.9997 0.9998 0.9999 0.999712 0.9997 0.9997 0.9998 0.9999 0.999713 0.9997 0.9997 0.9998 0.9999 0.9997

Table B.11: Reliability of Different Scenarios For The Double Busbar Transformer Bay (Ring) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9909 0.9927 0.9918 0.9927 0.99452 0.9928 0.9947 0.9938 0.9947 0.99473 0.9968 0.9969 0.9977 0.9987 0.99694 0.9968 0.9969 0.9977 0.9987 0.99695 0.9968 0.9969 0.9978 0.9987 0.99696 0.9969 0.9969 0.9978 0.9987 0.99697 0.9969 0.9969 0.9978 0.9987 0.99698 0.9969 0.9969 0.9978 0.9987 0.99699 0.9969 0.9969 0.9978 0.9987 0.996910 0.9969 0.9969 0.9978 0.9987 0.996911 0.9969 0.9969 0.9978 0.9987 0.996912 0.9969 0.9969 0.9978 0.9987 0.996913 0.9969 0.9969 0.9978 0.9988 0.9969

Table B.12: Reliability of Different Scenarios For The Mesh Corner Mesh Corner Bay (Star) (Based On Estimated Reliability figures)

216

Appendix B

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.8505 0.8617 0.8715 0.8730 0.96482 0.9128 0.9174 0.9354 0.9369 0.97403 0.9187 0.9232 0.9411 0.9419 0.97404 0.9249 0.9290 0.9473 0.9472 0.97415 0.9304 0.9348 0.9526 0.9519 0.97416 0.9363 0.9406 0.9584 0.9568 0.97417 0.9421 0.9465 0.9642 0.9618 0.97418 0.9453 0.9495 0.9671 0.9637 0.97419 0.9487 0.9526 0.9703 0.9658 0.9741

10 0.9517 0.9556 0.9730 0.9675 0.974111 0.9549 0.9587 0.9760 0.9695 0.974112 0.9581 0.9617 0.9789 0.9714 0.9741

Table B.13: Availability of Different Scenarios For The Mesh Corner Mesh Corner Bay(Star) (Based On Estimated Availability figures)

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.99948 0.99953 0.99957 0.99949 0.999832 0.99990 0.99990 0.99999 0.99990 0.999903 0.99990 0.99990 0.99999 0.99990 0.999904 0.99990 0.99990 0.99999 0.99990 0.999905 0.99990 0.99990 0.99999 0.99990 0.999906 0.99990 0.99990 0.99999 0.99990 0.999907 0.99990 0.99990 0.99999 0.99990 0.999908 0.99990 0.99990 0.99999 0.99990 0.999909 0.99990 0.99990 0.99999 0.99990 0.9999010 0.99990 0.99990 0.99999 0.99990 0.9999011 0.99990 0.99990 0.99999 0.99990 0.9999012 0.99990 0.99990 0.99999 0.99990 0.99990

Table B.14: Reliability of Different Scenarios For The Mesh Corner Mesh Corner Bay (Star) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9959 0.9968 0.9968 0.9959 0.99782 0.9988 0.9989 0.9998 0.9989 0.99903 0.9989 0.9989 0.9998 0.9989 0.99904 0.9989 0.9989 0.9998 0.9989 0.99905 0.9989 0.9989 0.9998 0.9989 0.99906 0.9989 0.9989 0.9998 0.9990 0.99907 0.9989 0.9989 0.9998 0.9990 0.99908 0.9989 0.9989 0.9998 0.9990 0.99909 0.9989 0.9989 0.9998 0.9990 0.999010 0.9989 0.9989 0.9998 0.9990 0.999011 0.9989 0.9990 0.9998 0.9990 0.999012 0.9989 0.9990 0.9999 0.9990 0.9990

217

Appendix B

Table B.15: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Star) (Based On Estimated Reliability figures)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.8243 0.8347 0.8439 0.8533 0.95062 0.8502 0.8612 0.8704 0.8801 0.95073 0.8760 0.8877 0.8969 0.9069 0.95084 0.8810 0.8926 0.9017 0.9112 0.95085 0.8859 0.8975 0.9064 0.9155 0.95086 0.8913 0.9029 0.9117 0.9202 0.95087 0.8964 0.9079 0.9167 0.9246 0.95088 0.8991 0.9104 0.9190 0.9263 0.95089 0.9017 0.9129 0.9214 0.9279 0.950810 0.9046 0.9157 0.9240 0.9298 0.950811 0.9073 0.9183 0.9264 0.9315 0.9508

Table B.16: Availability of Different Scenarios For The Mesh Corner Transformer Bay(Star) (Based On Estimated Availability figures)

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.99921 0.99925 0.99929 0.99929 0.999732 0.99939 0.99943 0.99948 0.99948 0.999743 0.99957 0.99961 0.99966 0.99966 0.999754 0.99957 0.99961 0.99966 0.99966 0.999755 0.99957 0.99961 0.99966 0.99966 0.999756 0.99957 0.99961 0.99966 0.99966 0.999757 0.99957 0.99961 0.99966 0.99966 0.999758 0.99957 0.99961 0.99966 0.99966 0.999759 0.99957 0.99961 0.99966 0.99966 0.9997510 0.99957 0.99961 0.99966 0.99966 0.9997511 0.99957 0.99961 0.99966 0.99966 0.99975

Table B.17: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Star) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9939 0.9948 0.9948 0.9949 0.99672 0.9949 0.9958 0.9958 0.9959 0.99683 0.9959 0.9968 0.9968 0.9968 0.99694 0.9959 0.9968 0.9968 0.9969 0.99695 0.9959 0.9968 0.9968 0.9969 0.99696 0.9959 0.9968 0.9968 0.9969 0.99697 0.9959 0.9969 0.9969 0.9969 0.99698 0.9959 0.9969 0.9969 0.9969 0.99699 0.9960 0.9969 0.9969 0.9969 0.996910 0.9960 0.9969 0.9969 0.9969 0.996911 0.9960 0.9969 0.9969 0.9969 0.9969

Table B.18: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Ring) (Based On Estimated Reliability figures)

218

Appendix B

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.8125 0.8334 0.8320 0.8417 0.94032 0.8633 0.8862 0.8840 0.8943 0.94053 0.8733 0.8960 0.8937 0.9030 0.94054 0.8783 0.9010 0.8986 0.9074 0.94055 0.8832 0.9059 0.9034 0.9117 0.94056 0.8889 0.9111 0.9086 0.9156 0.94057 0.8918 0.9136 0.9112 0.9176 0.94058 0.8946 0.9162 0.9138 0.9196 0.9406

Table B.19: Availability of Different Scenarios For The Mesh Corner Transformer Bay(Ring) (Based On Estimated Availability figures)

Scenarios Initial Only SW set to 0.99999

Only CBC set to 0.99999

Only MU set to 0.99999

Only Fibre set to 0.99999

1 0.99916 0.99924 0.99924 0.99924 0.999672 0.99952 0.99960 0.99961 0.99961 0.999693 0.99952 0.99960 0.99961 0.99961 0.999694 0.99952 0.99960 0.99961 0.99961 0.999695 0.99952 0.99960 0.99961 0.99961 0.999696 0.99952 0.99960 0.99961 0.99961 0.999697 0.99952 0.99960 0.99961 0.99961 0.999698 0.99952 0.99960 0.99961 0.99961 0.99969

Table B.20: Reliability of Different Scenarios For The Mesh Corner Transformer Bay (Ring) (Based On Initial Component Reliability Set To 0.999)

Scenarios Initial Only SW set to 0.9999

Only CBC set to 0.9999

Only MU set to 0.9999

Only Fibre set to 0.9999

1 0.9929 0.9947 0.9938 0.9938 0.99572 0.9949 0.9967 0.9958 0.9958 0.99593 0.9949 0.9967 0.9958 0.9958 0.99594 0.9949 0.9967 0.9958 0.9959 0.99595 0.9949 0.9967 0.9958 0.9959 0.99596 0.9949 0.9968 0.9958 0.9959 0.99597 0.9949 0.9968 0.9959 0.9959 0.99598 0.9950 0.9968 0.9959 0.9959 0.9959

219

APPENDIX C

Table C.1: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost

Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7900 151491 28903 1803942 0.8349 169551 30967 2005183 0.9028 169963 31230 2011934 0.9116 188023 33294 2213175 0.9238 188435 33556 2219916 0.9269 206495 35620 2421157 0.9312 206907 35882 242789

Fig. C.1: Cost Versus Reliability with Penalty Cost factor 0

Table C.2: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost

Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7900 151491 1433298 15847892 0.8349 169551 761702 9312533 0.9028 169963 195621 3655844 0.9116 188023 182515 3705385 0.9238 188435 161899 3503346 0.9269 206495 158719 3652147 0.9312 206907 151743 358650

220

Appendix C

Fig. C.2: Cost Versus Reliability with Penalty Cost factor 400000

Table C.3: Reliability And Cost Data For Double Busbar Feeder Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.7900 151491 102634 2541252 0.8349 169551 69331 2388823 0.9028 169963 39860 2098234 0.9116 188023 41128 2291515 0.9238 188435 40294 2287296 0.9269 206495 42083 2485787 0.9312 206907 41965 248872

Fig. C.3: Cost Versus Reliability with Penalty Cost factor 21000

221

Appendix C

Table C.4: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7486 202628 45090 2477182 0.7721 211452 45990 2574423 0.7963 211864 46253 2581174 0.8528 212276 46515 2587915 0.8604 221100 47416 2685166 0.8680 221512 47678 2691907 0.8755 221924 47941 2698658 0.8831 222336 48203 2705399 0.8907 222748 48466 27121410 0.8912 223572 48990 27256211 0.9012 232396 49891 28228712 0.9041 232808 50154 28296213 0.9071 233220 50416 28363614 0.9100 233632 50678 28431015 0.9129 234044 50941 28498516 0.9158 234456 51203 285659

Fig. C.4: Cost Versus Reliability with Penalty Cost factor 0

Table C.5: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7486 202628 1621357 18239852 0.7721 211452 1232059 14435113 0.7963 211864 889234 11010984 0.8528 212276 297700 5099765 0.8604 221100 285317 5064176 0.8680 221512 272336 4938487 0.8755 221924 259392 4813168 0.8831 222336 246486 4688229 0.8907 222748 233618 456366

222

Appendix C

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

10 0.8912 223572 233312 45688411 0.9012 232396 216990 44938612 0.9041 232808 212227 44503513 0.9071 233220 207468 44068814 0.9100 233632 202713 43634515 0.9129 234044 197963 43200716 0.9158 234456 193218 427674

Fig. C.5: Cost Versus Reliability with Penalty Cost factor 400000

Table C.6: Reliability And Cost Data For Double Busbar Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7486 202628 127844 3304722 0.7721 211452 108259 3197113 0.7963 211864 90509 3023734 0.8528 212276 59702 2719785 0.8604 221100 59906 2810066 0.8680 221512 59473 2809857 0.8755 221924 59042 2809668 0.8831 222336 58613 2809499 0.8907 222748 58186 28093410 0.8912 223572 58667 28223911 0.9012 232396 58664 29106012 0.9041 232808 58662 29147013 0.9071 233220 58661 29188114 0.9100 233632 58660 29229215 0.9129 234044 58659 29270316 0.9158 234456 58659 293115

223

Appendix C

Fig. C.6: Cost Versus Reliability with Penalty Cost factor 21000

Table C.7: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.7594 229100 47792 2768922 0.8068 247160 49856 2970163 0.8724 247572 50118 2976904 0.8778 265632 52182 3178145 0.8838 266044 52445 3184896 0.8898 266456 52707 3191637 0.8958 266868 52970 3198388 0.8962 267692 53494 3211869 0.8990 285752 55558 34131010 0.9020 286164 55821 34198511 0.9051 286576 56083 34265912 0.9082 286988 56346 34333413 0.9100 287400 56608 344008

224

Appendix C

Fig. C.7: Cost Versus Reliability with Penalty Cost factor 0

Table C.8: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.7594 229100 1627410 18565102 0.8068 247160 906440 11536003 0.8724 247572 266877 5144494 0.8778 265632 259465 5250975 0.8838 266044 249364 5154086 0.8898 266456 239286 5057427 0.8958 266868 229231 4960998 0.8962 267692 229109 4968019 0.8990 285752 226346 51209810 0.9020 286164 221320 50748411 0.9051 286576 216299 50287512 0.9082 286988 211283 49827113 0.9100 287400 206326 493726

225

Appendix C

Fig. C.8: Cost Versus Reliability with Penalty Cost factor 400000

Table C.9: Reliability And Cost Data For Double Busbar Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.7594 229100 130722 3598222 0.8068 247160 94827 3419873 0.8724 247572 61498 3090704 0.8778 265632 63065 3286975 0.8838 266044 62783 3288276 0.8898 266456 62503 3289597 0.8958 266868 62223 3290918 0.8962 267692 62714 3304069 0.8990 285752 64525 35027710 0.9020 286164 64509 35067311 0.9051 286576 64495 35107112 0.9082 286988 64480 35146813 0.9100 287400 64468 351868

226

Appendix C

Fig. C.9: Cost Versus Reliability with Penalty Cost factor 21000

Table C.10: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.85049 148017 32122 1801392 0.91281 156017 32498 1885153 0.91868 164841 33399 1982404 0.92493 165253 33662 1989155 0.93040 165665 33924 1995896 0.93626 166077 34186 2002637 0.94212 166489 34449 2009388 0.94532 175313 35350 2106639 0.94873 175725 35612 21133710 0.95172 176137 35874 21201111 0.95492 176549 36137 21268612 0.95812 176961 36399 213360

227

Appendix C

Fig. C.10: Cost Versus Reliability with Penalty Cost factor 0

Table C.11: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.85049 148017 482234 6302512 0.91281 156017 82814 2388313 0.91868 164841 80191 2450324 0.92493 165253 76726 2419795 0.93040 165665 73730 2393956 0.93626 166077 70530 2366077 0.94212 166489 67351 2338408 0.94532 175313 66391 2417049 0.94873 175725 64677 24040210 0.95172 176137 63209 23934611 0.95492 176549 61626 23817512 0.95812 176961 60047 237008

228

Appendix C

Fig. C.11: Cost Versus Reliability with Penalty Cost factor 400000

Table C.12: Reliability And Cost Data For Mesh Corner Mesh Corner Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.85049 148017 55753 2037702 0.91281 156017 35140 1911573 0.91868 164841 35856 2006974 0.92493 165253 35922 2011755 0.93040 165665 36014 2016796 0.93626 166077 36094 2021717 0.94212 166489 36176 2026658 0.94532 175313 36979 2122929 0.94873 175725 37138 21286310 0.95172 176137 37309 21344611 0.95492 176549 37475 21402412 0.95812 176961 37641 214602

229

Appendix C

Fig. C.12: Cost Versus Reliability with Penalty Cost factor 21000

Table C.13: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.82427 135694 28637 1643312 0.85016 144930 29800 1747303 0.87605 145342 30062 1754044 0.88097 154166 30963 1851295 0.88590 154578 31226 1858046 0.89133 154990 31488 1864787 0.89643 155402 31750 1871528 0.89906 164226 32651 1968779 0.90170 164638 32914 19755210 0.90460 165050 33176 19822611 0.90733 165462 33438 198900

230

Appendix C

Fig. C.13: Cost Versus Reliability with Penalty Cost factor 0

Table C.14: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.82427 135694 842668 9783622 0.85016 144930 564230 7091603 0.87605 145342 340083 4854254 0.88097 154166 328485 4826515 0.88590 154578 316265 4708436 0.89133 154990 302805 4577957 0.89643 155402 290197 4455998 0.89906 164226 284455 4486819 0.90170 164638 278080 44271810 0.90460 165050 271038 43608811 0.90733 165462 264447 429909

231

Appendix C

Fig. C.14: Cost Versus Reliability with Penalty Cost factor 400000

Table C.15: Reliability And Cost Data For Mesh Corner Transformer Bay (Star) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost

Life Cycle Cost

1 0.82427 135694 71373 2070672 0.85016 144930 57858 2027883 0.87605 145342 46338 1916804 0.88097 154166 46583 2007495 0.88590 154578 46190 2007686 0.89133 154990 45732 2007227 0.89643 155402 45319 2007218 0.89906 164226 45871 2100979 0.90170 164638 45785 21042310 0.90460 165050 45664 21071411 0.90733 165462 45566 211028

Fig. C.15: Cost Versus Reliability with Penalty Cost factor 21000

232

Appendix C

Table C.16: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 0)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.8125 162578 31602 1941802 0.8633 180638 33666 2143043 0.8733 198698 35730 2344284 0.8783 199110 35992 2351025 0.8832 199522 36254 2357766 0.8889 216758 37794 2545527 0.8918 217994 38581 2565758 0.8946 218406 38843 257249

Fig. C.16: Cost Versus Reliability with Penalty Cost factor 0

Table C.17: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 400000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.8125 162578 956670 11192482 0.8633 180638 416905 5975433 0.8733 198698 390670 5893684 0.8783 199110 376732 5758425 0.8832 199522 362957 5624796 0.8889 216758 348374 5651327 0.8918 217994 341065 5590598 0.8946 218406 333319 551725

233

Appendix C

Fig. C.17: Cost Versus Reliability with Penalty Cost factor 400000

Table C.18: Reliability And Cost Data For Mesh Corner Transformer Bay (Ring) Process Bus Scenarios (Penalty Cost Factor = 21000)

Scenario Reliability Investment Renewal andMaintenance Cost

Failure Cost Life Cycle Cost

1 0.8125 162578 80168 2427462 0.8633 180638 53786 2344243 0.8733 198698 54364 2530624 0.8783 199110 53881 2529915 0.8832 199522 53406 2529286 0.8889 216758 54099 2708577 0.8918 217994 54461 2724558 0.8946 218406 54303 272709

Fig. C.18: Cost Versus Reliability with Penalty Cost factor 21000

234

APPENDIX D

Table D.1: Process Delay (PD) and Arrival Time Results (40 Ethernet Packets)

No. Process Delay (microseconds)

Arrival Time Uniformity (microseconds)

MU1 MU2 MU3 MU1 MU2 MU31 414 1163 518 2.80E-011 -142 62 414 1021 524 -2.75E-011 -159 -13 414 862 523 1 151 -34 415 1013 520 -1 -53 -45 414 960 516 2.80E-011 555 66 414 1515 522 -2.75E-011 -50 47 414 1465 526 2.80E-011 -141 -2.75E-0118 414 1324 526 1 -159 -69 415 1165 520 -1 -141 -2.75E-01110 414 1024 520 -2.75E-011 -160 411 414 864 524 2.80E-011 153 112 414 1017 525 27 -48 -1113 441 969 514 -24 -40 1314 417 929 527 -4 -142 -2.75E-01115 413 787 527 -2 230 -416 411 1017 523 6 -48 -417 417 969 519 -2 -142 218 415 827 521 -1 442 -2.75E-01119 414 1269 521 -3 -49 320 411 1220 524 2.80E-011 -142 -621 411 1078 518 -2.75E-011 -146 322 411 932 521 2.80E-011 -142 623 411 790 527 -2.75E-011 229 -324 411 1019 524 2.80E-011 -43 -225 411 976 522 -2.75E-011 -142 -426 411 834 518 2.80E-011 438 727 411 1272 525 -2.75E-011 -48 328 411 1224 528 2.80E-011 -141 229 411 1083 530 -2.75E-011 -155 -330 411 928 527 2.80E-011 -141 131 411 787 528 6 236 -432 417 1023 524 -3 -40 -833 414 983 516 -3 -141 1134 411 842 527 2.80E-011 435 -235 411 1277 525 -2.75E-011 -51 -136 411 1226 524 -2.75E-011 -141 -837 411 1085 516 8.35E-011 -150 538 411 935 521 6 -141 539 417 794 526 -2.75E-011 233 -140 417 1027 525 8.35E-011 -50 -10

235

Appendix D

Table D.2: GPS Timestamp Delays (5 Injections)

No. GPS Timestamp Delay (microseconds)MU1 MU2 MU3

1 350 0 2002 400 0 2003 450 -100 1504 350 -50 1005 500 -200 5

Table D.3: MU1 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage

Injections ranging from 10V – 120VInput

Voltage (V)Average

(%)Standard

Deviation (%)Variance

(%)Maximum

(%)Minimum

(%)Range

(%)10 -1.300 0.006 0.000 -1.288 -1.304 0.01620 -1.206 0.003 0.000 -1.204 -1.211 0.00730 -1.177 0.000 0.000 -1.175 -1.178 0.00240 -1.156 0.010 0.000 -1.146 -1.169 0.02250 -1.146 0.018 0.000 -1.124 -1.163 0.03960 -1.104 0.003 0.000 -1.100 -1.107 0.00870 -1.126 0.020 0.000 -1.105 -1.153 0.04880 -1.185 0.013 0.000 -1.164 -1.196 0.03290 -1.174 0.027 0.001 -1.136 -1.201 0.065100 -1.073 0.014 0.000 -1.062 -1.094 0.033110 -1.150 0.032 0.001 -1.106 -1.183 0.078120 -1.139 0.035 0.001 -1.087 -1.175 0.088

Table D.4: MU2 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage Injections ranging from 10V – 120V

Input Voltage (V)

Average(%)

Standard Deviation (%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

10 -1.269 0.081 0.007 -1.195 -1.361 0.16620 -1.368 0.024 0.001 -1.342 -1.393 0.05230 -1.429 0.026 0.001 -1.396 -1.455 0.06040 -1.228 0.025 0.001 -1.196 -1.265 0.06950 -1.356 0.043 0.002 -1.296 -1.398 0.10260 -1.205 0.005 0.000 -1.199 -1.212 0.01470 -1.336 0.038 0.001 -1.288 -1.383 0.09480 -1.225 0.016 0.000 -1.208 -1.250 0.04290 -1.305 0.026 0.001 -1.269 -1.330 0.061100 -1.307 0.013 0.000 -1.290 -1.322 0.032110 -1.161 0.023 0.001 -1.141 -1.195 0.055120 -1.151 0.053 0.003 -1.103 -1.234 0.132

236

Appendix D

Table D.5: MU3 Conversion Error Measures of Dispersion based on repeated 50Hz Voltage Injections ranging from 10V – 120V

Input Voltage (V)

Average(%)

Standard Deviation (%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

10 -0.980 0.000 0.000 -0.975 -0.983 0.00720 -0.955 0.001 0.000 -0.955 -0.957 0.00230 -0.953 0.001 0.000 -0.951 -0.954 0.00340 -0.956 0.000 0.000 -0.955 -0.956 0.00150 -0.952 0.000 0.000 -0.952 -0.953 0.00160 -0.953 0.001 0.000 -0.952 -0.953 0.00170 -0.951 0.002 0.000 -0.949 -0.953 0.00480 -0.948 0.001 0.000 -0.947 -0.948 0.00190 -0.944 0.001 0.000 -0.944 -0.945 0.001

100 -0.943 0.001 0.000 -0.941 -0.943 0.000110 -0.940 0.001 0.000 -0.939 -0.941 0.003120 -0.937 0.001 0.000 -0.936 -0.939 0.000

Table D.6: MU1 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A

Input Current

(A)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

1 1.599 0.015 0.000 1.625 1.585 0.0412 1.546 0.023 0.001 1.574 1.515 0.0593 1.348 0.103 0.011 1.508 1.252 0.2564 1.083 0.097 0.009 1.238 0.989 0.2495 0.776 0.148 0.022 1.025 0.653 0.372

Table D.7: MU2 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A

Input Current

(A)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

1 1.374 0.071 0.005 1.458 1.268 0.1902 1.222 0.034 0.001 1.263 1.192 0.0703 1.069 0.072 0.005 1.178 0.990 0.1884 0.668 0.111 0.012 0.811 0.521 0.2905 0.364 0.119 0.014 0.566 0.276 0.290

Table D.8: MU3 Conversion Error Measures of Dispersion based on repeated 50Hz Current Injections ranging from 1A – 5A

Input Current

(A)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

1 1.494 0.012 0.000 1.511 1.485 0.0262 1.342 0.038 0.001 1.402 1.305 0.0973 1.489 0.076 0.006 1.621 1.433 0.1884 1.989 0.109 0.012 2.165 1.893 0.2725 1.904 0.116 0.013 2.101 1.819 0.282

237

Appendix D

Table D.9: MU1 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 0.989 0.00 0.00 0.989 0.988 0.00150 0.941 3.48E-005 1.21E-009 0.941 0.941 8.20E-005250 0.671 1.26E-005 1.60E-010 0.671 0.671 2.59E-005350 0.407 1.46E-005 2.14E-010 0.407 0.407 3.83E-005550 0.173 6.09E-006 3.71E-011 0.173 0.173 1.52E-005

1150 0.040 3.45E-005 1.19E-009 0.040 0.040 7.04E-0051950 0.014 2.36E-005 5.57E-010 0.014 0.014 6.35E-005

Table D.10: MU2 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 0.986 0 1.86E-007 0.987 0.986 0150 0.983 9.73E-005 9.46E-009 0.983 0.983 0550 0.974 9.56E-005 9.15E-009 0.974 0.974 0950 0.954 3.62E-005 1.31E-009 0.954 0.954 8.46E-005

1150 0.939 9.77E-005 9.55E-009 0.939 0.939 01350 0.922 1.67E-005 2.78E-010 0.922 0.922 3.91E-0051750 0.882 0 2.83E-008 0.882 0.882 01950 0.859 0 9.48E-006 0.863 0.860 0.01

Table D.11: MU3 Filter Analysis Measures of Dispersion based on repeated 50V Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 0.990 3.70E-006 1.37E-011 0.990 0.990 8.89E-006150 0.988 5.00E-006 2.50E-011 0.988 0.988 1.01E-005250 0.959 6.67E-005 4.45E-009 0.959 0.959 0550 0.898 3.24E-005 1.05E-009 0.898 0.897 7.78E-005

1150 0.856 4.59E-005 2.11E-009 0.856 0.856 01550 0.754 0 1.36E-005 0.755 0.747 0.011650 0.727 8.65E-005 7.48E-009 0.727 0.727 01750 0.697 0 3.63E-008 0.698 0.697 01850 0.667 6.79E-005 4.60E-009 0.667 0.667 01950 0.635 0 1.99E-008 0.636 0.635 0

Table D.12: MU1 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 1.020 0.000 5.41E-008 1.016 1.015 0.001150 1.314 0.001 4.92E-007 1.316 1.314 0.002250 1.267 0.000 1.72E-007 1.268 1.267 0.001350 0.797 0.445 0.2 0.997 0.001 0.996

238

Appendix D

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

550 0.624 0.000 8.73E-008 0.625 0.624 0.0011150 0.261 0.000 2.76E-008 0.262 0.261 0.0001950 0.115 0.000 1.72E-007 0.116 0.115 0.001

Table D.13: MU2 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 1.012 0.000 1.15E-007 1.013 1.012 0.001150 1.000 0.000 1.31E-007 1.001 1.000 0.001550 0.989 0.000 5.16E-008 0.989 0.989 0.001950 0.969 0.000 6.72E-008 0.970 0.969 0.001

1150 0.956 0.000 1.85E-007 0.956 0.955 0.0011350 0.940 0.000 7.01E-008 0.940 0.940 0.0011750 0.902 0.000 1.28E-007 0.903 0.902 0.0011950 0.881 0.002 6.06E-006 0.883 0.878 0.005

Table D.14: MU3 Filter Analysis Measures of Dispersion based on repeated 2A Injections at frequencies ranging from 50Hz to 1950z

Input Frequency

(Hz)

Average(%)

Standard Deviation

(%)

Variance(%)

Maximum(%)

Minimum(%)

Range(%)

50 1.013 0.000 1.46E-007 1.014 1.013 0.001150 1.010 5.93E-005 3.52E-009 1.010 1.010 0.000250 1.000 0.013 0 1.006 0.977 0.029550 0.979 0.000 4.89E-008 0.980 0.979 0.001

1150 0.871 0.000 1.67E-008 0.871 0.871 0.0001550 0.765 0.000 6.03E-008 0.766 0.765 0.0011650 0.735 0.000 8.35E-008 0.736 0.735 0.0011750 0.704 0.001 3.44E-007 0.705 0.703 0.0021850 0.672 0.000 4.35E-008 0.673 0.672 0.0011950 0.640 0.000 2.03E-007 0.640 0.639 0.001

239

REFERENCES

1 Alstom Grid, “Network Protection & Automation Guide”, Edition May 2011.

2 D. Novosel, “Upgrading and Retrofitting Utility Protective Relaying Systems

Benefits of Upgrading Protective Relaying Systems”, Power Systems Conference

and Exposition, PSCE, October 29, 2006 - November 1, 2006.

3 P. Montignies, P. Basu, F. Gruffaz, “Digital Protective Relays Are Designed For

Long Life”, 4th European Conference on Electrical and Instrumentation

Applications in the Petroleum & Chemical Industry, PCIC Europe, June 2007.

4 Merriam-Webster Dictionary, “http://www.merriam-webster.com”.

5 IEC 60870 Standard, “Telecontrol equipment and systems”.

6 IEEE Standard for Electric Power Systems Communications-Distributed Network

Protocol (DNP3), IEEE Std 1815.

7 DNP3 Overview - Triangle MicroWorks, “http://www.trianglemicroworks.com”.

8 The Modbus Organization, “http://www.modbus.org”.

9 S. Mohagheghi, J. Stoupis and Z. Wang, "Communication protocols and networks

for power systems-current status and future trends," Power Systems Conference

and Exposition, 2009. PSCE '09. IEEE/PES , vol., no., pp.1-9, 15-18 March 2009.

10 PROFIBUS System Description Technology and Application,

“http://www.profibus.com”.

11 PROFINET System Description Technology and Application, www.profibus.com.

12 Communication networks and systems in substations, IEC Standard 61850 Parts 1

- 10, first parts published in 2002.

13 K.P. Brand, C. Brunner, W. Wimmer, “Design Of IEC 61850 Based Substation

Automation Systems According To Customer Requirements”, CIGRE Study

Committee B5 - 103, Paris, August - September 2004.

14 L. Hossenlopp, “Engineering perspectives on IEC 61850”, IEEE Power and Energy

Magazine, May/June 2007, pages 45– 50.

15 Bogdan Kasztenny, James Whatley, Eric A. Udren, John Burger, Dale Finney and

Mark Adamiak; “IEC 61850 Practical Application Primer for Protection Engineers”,

Annual Georgia Tech Protective Relaying Conference, Atlanta, Georgia, May 2006

240

16 V. Skendzic, I. Ender and G. Zweigle, Schweitzer Engineering Laboratories, Inc.,

“IEC 61850-9-2 Process Bus and Its Impact on Power System Protection and

Control Reliability”, 9th Annual Western Power Delivery Automation Conference,

Spokane, Washington, April 2007.

17 Andersson, K.-P. Brand, C. Brunner, and W. Wimmer, “Reliability investigations for

SA communication architectures based on IEC 61850”, in Conf. Rec. Power Tech,

IEEE Russia, 2005, pp. 1 - 7.

18 D. Baigent, M. Adamiak and R. Mackiewicz, “IEC 61850 Communication Networks

and Systems in Substations: An Overview for Users”, SIPSEP, Monterrey, Mexico,

November 2004.

19 IEC 61850 9-2 “Light Edition” - “Implementation Guideline for Digital Interface to

Instrument Transformers using IEC 61850 9-2”.

20 Communication networks and systems for power utility automation, IEC Standard

61850.

21 K. Schwartz, “Comparison of IEC 60870-5-101/-103/-104, DNP3, and IEC 60870-6-

TASE.2 with IEC 61850”, version 3, 2008-10-03.

22 IEC 60044 Standard, “Instrument transformers”, Part 8.

23 Siemens Press Release, “Siemens commissions the world’s first substation control

system based on IEC 61850”, Reference number: PTD EA 200412.357 e, Siemens

AG 2002.

24 S. Laederach, W. Baass, K.P. Brand and P. Reinhardt, “Experience with IEC

61850 in the refurbishment of an important European 380 kV substation”, CIGRE

B5-109, Paris, 2006.

25 V.M. Flores, D. Espinosa, J. Alzate, D. Dolezilek, “Case Study: Design and

Implementation of IEC 61850 From Multiple Vendors at CFE La Venta II” 60th

Annual Conference for Protective Relay Engineers, March 2007.

26 J. Holbach, C. Wester, L. Frisk, S. Kunsman, L. Hossenlopp , “Status On The First

IEC 61850 Based Protection And Control, Multi-Vendor Project In The United

States”, 60th Annual Conference for Protective Relay Engineers, March 2007.

27 R. Zhang and B. Gwyn, “Architecture of Substation Secondary Systems,

Protection, Automation and Control (PAC) World Magazine”, September 2010.

241

28 J. McGhee and M. Goraj, “Smart High Voltage Substation based on IEC 61850

Process Bus and IEEE 1588 Time Synchronization”, First IEEE International

Conference on Smart Grid Communications (SmartGridComm), 2010.

29 J. F. Burger, D. A. Krummen and J. R. Abele, “AEP Process Bus Replaces

Copper”, Transmission & Distribution World magazine, March 2009.

30 D. Dolezilek, “IEC 61850: What you Need to Know about Functionality and

Practical Implementation”, Power Systems Conference: Advanced Metering,

Protection, Control, Communication, and Distributed Resources, 2006.

31 J.-C.Tournier and T. Werner, “A quantitative evaluation of IEC 61850 process bus

architectures”, in Conf. Rec. IEEE Power and Energy Society General Meeting,

2010, pp. 1 - 8.

32 M. Schumacher, “Process bus communication in High Voltage Substations based

on IEC 61850”, CIGRE Study Committee B3 Colloquium, Berlin, September 2007,

Presentation PS1-105.

33 R.E. Mackiewicz, “Overview of IEC 61850 and benefits”, Power Engineering

Society General Meeting, IEEE, June 2006.

34 A. Apostolov and D. Tholomier, “Impact of IEC 61850 on Power System

Protection”, Power Systems Conference and Exposition, IEEE PES

October/November 2006, pages 1053 – 1058.

35 L. Andersson, C. Brunner and F. Engler, “Substation Automation based on IEC

61850 with new process-close Technologies”, Power Tech Conference

Proceedings, IEEE Bologna June 2003.

36 K. Brand and W. Wimmer, "Investigations of different Function Allocations in SA

Systems enabled by IEC 61850", IEEE Lausanne PowerTech Conference,

Lausanne, July 2007, pages 720 – 725.

37 J. Mo, J. C. TAN, P. A. Crossley, Z. Q. Bo and A. Klimek, “Evaluation of Process

Bus Reliability”, in Conf. Rec. Managing the Change, 10th IET Int. Conf. on

Developments in Power System Protection (DPSP), 2010, pp. 1 - 5.

38 R. Midence and D. Iadonisi, “Ethernet Networks Redundancy with Focus on IEC

61850 Applications”, in Conf. Rec. 20th Int. Conf. on Electricity Distribution, 2009,

pp. 1 - 4.

242

39 M.S. Thomas and I. Ali, “Reliable, Fast, and Deterministic Substation

Communication Network Architecture and its Performance Simulation,” IEEE

Trans. on Power Delivery, vol. 25, no. 4, pp. 2364 - 2370, Oct. 2010.

40 L. R. Castro Ferreira, P. A. Crossley and R.N. Allan , “The impact of functional

integration on the reliability of substation protection and control systems,” IEEE

Trans. on Power Delivery, vol. 16, no. 1, pp. 83-88, Jan. 2001.

41 L. R. Castro Ferreira, P. A. Crossley and R.N. Allan , “Reliability evaluation of

substation control systems,” in IEE Proc. Generation, Transmission and

Distribution, vol. 146, no. 6, pp. 626-632.

42 H. Hajian-Hoseinabadi, “Impacts of Automated Control Systems on Substation

Reliability,” IEEE Trans. on Power Delivery, vol. 26, no. 3, pp. 1681 -1691, Jul.

2011.

43 B. Morris, R. Moxley, and C. Kusch, Then Versus Now: A Comparison of Total

Scheme Complexity, 62nd Annual Conference for Protective Relay Engineers,

2009.

44 L. Yang, P. A. Crossley, J. Zhao, H. Li, and W. An, Impact Evaluation of IEC 61850

Process Bus Architecture on Numerical Protection Systems, International

Conference on Sustainable Power Generation and Supply, SUPERGEN 2009.

45 M. Hinow, M. Waldron, L. Müller, H. Aeschbach and K. Pohlink, “Substation Life

Cycle Cost Management Supported by Stochastic Optimization Algorithm”, in Conf.

Rec. CIGRÉ Session 42, paper no. B3-103, Paris 2008.

46 I. Jeromin, G. Balzer, J. Backes and R. Huber, “Life cycle cost analysis of

transmission and distribution systems” , in Conf. Rec. Power Tech, IEEE

Bucharest, 2009, pp. 1 - 6.

47 D. Karlsson, L. Wallin, H.-E. Olovsson and C.-E.Solver, “Reliability and life cycle

cost estimates of 400 kV substation layouts ” , IEEE Transactions on Power

Delivery, Oct 1997 Volume 12, Issue 4, pp : 1486 - 1492.

48 P. Erni, “Successful demo of IEC 61850-9-1”, “http://www.nettedautomation.com”,

2002.

49 Z. Djekic, L. Portillo and M. Kezunovic, “Compatibility and Interoperability

Evaluation of All-digital Protection Systems Based on IEC 61850-9-2

Communication Standard”, IEEE Power and Energy Society General Meeting -

Conversion and Delivery of Electrical Energy in the 21st Century, 2008.

243

50 IET smart grids briefing July 2010 www.iet.org.

51 M. Gurbiel, P. Komarnicki, Z. A. Styczynski, F.W. Gatzen,. C. Dzienis, “merging

unit Accuracy Testing”, IEEE Power & Energy Society General Meeting, PES,

2009.

52 L. Xiaobin, Z. Jie, Y. Yongbiao, S. Jian, X, L1, Z. Bin, “Development of New Kind of

merging unit Based on IEC 61850”, International Conference on Electricity

Distribution CICED, 2008, China.

53 IEC 60300 Standard, “Dependability management”.

54 IEC 61165 Standard, “Application of Markov techniques”.

55 Omicron SVScout Product Brochure, September 2011.

56 C. M. Torres-Ortolaza and A. A. Irizany-Rivera, “Reliability of Intelligent Power

Routers”, presented at the 8th Int. Conf. On Probabilistic Methods Applied to Power

Systems, Iowa, September 2004.

57 E. O. Schweitzer III, B. Fleming, T.J. Lee and P. M. Anderson, “Reliability Analysis

of Transmission Protection Using Fault Tree Methods”, presented at the 24th

Annual Western Protective Relay, Spokane, Washington, 1997.

58 L. Rafael de Castro Ferreira, “Reliability Assessment of Integrated Protection and

Control System”, Ph.D. Thesis, University of Manchester, May 1999.

59 M. L. Shooman, “Reliability of computer systems and networks: fault tolerance,

analysis and design,” John Wiley and Sons, 2002, pp. 14.

60 G. W. Scheer and R. E. Moxley, “Digital Communications Improve Contact I/O

Reliability,” presented at the Power Systems Conf. Advanced Metering, Protection,

Control, Communication, and Distributed Resources, March 2006.

61 U.B. Anombem, H. Li, P. Crossley, R. Zhang and C. McTaggart, “Flexible IEC

61850 Process Bus Architecture Designs to Support Life-Time Maintenance

Strategy of Substation Automation Systems”, CIGRÉ Study Committee B5

Colloquium paper no. 102, Jeju 2009.

62 S. Robinson. “Total Value Concepts in the Contract Definition Phase”, IEEE

Transactions on Aerospace and Electronic Systems, pp. 402-408 (1966).

63 GE, “Hard Fiber Process Bus System”, GE HardFiber Reference Manual, 2008.

64 IEEE 1588 Standard, “Standard for a Precision Clock Synchronization Protocol for

Networked Measurement and Control Systems”.

65 National Grid Technical Specification NGTS 2.6 Issue 3, November, 2008.

244

66 D. Warkentin-Glenn, “Electric Power Industry In Nontechnical Language”, 2006

PennWell Corporation.

67 “Experiences with Non-Conventional Instrument Transformers (NCITs)”, D.

Füchsle, M. Stanek, GCC Power Conference 2009.

68 S. Meier, “Sharing Values”, ABB Review Issue 1/2011.

69 “IEC 61850 at work”, ABB Review Special Report IEC 61850, August 2010.

70 U. B. Anombem, H. Li, P. Crossley, R. Zhang and C. McTaggart, “IEC 61850

Process Bus Architecture Design and Optimisation Analysis” , presented at the Int.

Conf. on Advanced Power System Automation and Protection (APAP), Jeju 2009,

Paper APAP2009-P151.

71 U. B. Anombem, H. Li, P. Crossley, R. Zhang and C. McTaggart, “Process bus

architectures for substation automation with life cycle cost consideration”, in Conf.

Rec. Managing the Change, 10th IET Int. Conf. on Developments in Power System

Protection (DPSP), Manchester, 2010, pp. 1 – 5.

72 Locamation MU606 merging unit Series Manual Release 5.9, version 01, 2010.

73 D. Meadows, "WG13 Siemens Trial Proposal", National Grid AS3 Project, October

2008.

74 Mitsubishi MMU-H100A Merging Unit Manual, 2008.

75 Alstom COSI-MU merging unit Product Brochure, 2012.

76 U.B. Anombem, H. Li, P. Crossley, W. An, R. Zhang, C. McTaggart, “Merging Unit

Interoperability Performance Testing and Assessment Tool“ CIGRE Study

Committee B5 Annual Meeting and Colloquium, Lausanne, Switzerland,

September 2011.

77 U.B. Anombem, H. Li, P. Crossley, W. An, R. Zhang, C. McTaggart, “Performance

Testing and Assessment of Merging Units using IEC 61850”, The International

Conference on Advanced Power System Automation and Protection (APAP),

Beijing, October 2011.

78 M. Kleemann,. K. Gorner, and C. Rehtanz, “Concept and requirements of a

simulator for substation automation systems”, Innovative Smart Grid Technologies

Conference Europe (ISGT Europe), 2010 IEEE PES.

245