MIS6316 Exam3 Spring 2015 Name: _____________________________ Max Points: 36 Max Time: 60 min TRUE / FALSE 1. A key problem when designing data communications networks is how to adapt to new technologies while organizations change 2. Today, many organizations design networks using the building-block approach. 3. Needs analysis is the final step in the building block approach to network design. 4. The goals in the needs analysis step of network design are exactly the same when designing LANs vs. when designing WANs. 5. The step of understanding current traffic on a network provides a baseline against which future network requirements can be compared. 6. The turnpike effect results when a network is used at a much lower rate than was anticipated when it was designed. 7. Simulation is a tool that can be used in designing networks. 8. Policy-based management allows the network manager to utilize special software to set priority policies for network traffic that take effect when the network becomes busy. HJA 1 7/20/2022

Upload: doe-john

Post on 20-Dec-2015

214 views

Category:

Documents


2 download

DESCRIPTION

Chap 12

TRANSCRIPT

Page 1: Exam3RevMIS6316

MIS6316 Exam3 Spring 2015

Name: _____________________________

Max Points: 36Max Time: 60 min

TRUE / FALSE

1. A key problem when designing data communications networks is how to adapt to new technologies while organizations change

2. Today, many organizations design networks using the building-block approach.

3. Needs analysis is the final step in the building block approach to network design.

4. The goals in the needs analysis step of network design are exactly the same when designing LANs vs. when designing WANs.

5. The step of understanding current traffic on a network provides a baseline against which future network requirements can be compared.

6. The turnpike effect results when a network is used at a much lower rate than was anticipated when it was designed.

7. Simulation is a tool that can be used in designing networks.

8. Policy-based management allows the network manager to utilize special software to set priority policies for network traffic that take effect when the network becomes busy.

9. A SLA specifies the exact type of performance that the common carrier will provide and the penalties if this performance is not provided.

10. The future of network management lies in the management of LANs, BNs, and Internet resources instead of concentrating on mainframe resources.

11. Due to changing communication technologies, most companies have combined voice and data communications functions.

12. One of the least common configuration activities is adding and deleting user accounts.

HJA 1 4/18/2023

Page 2: Exam3RevMIS6316

MIS6316 Exam3 Spring 2015

13. User profiles should enable the network manager to identify the access rights (to particular files and directories) for each user.

14. Trouble tickets are reports produced by a software package that records fault information.

15. Problem statistics are not helpful in determining whether vendors are meeting contractual maintenance commitments.

16. To ensure that critical problems get priority over less important ones, problem prioritizing is needed in a network.

17. Mean Time Between Failures is a statistic that is used to track device reliability.

18. Service level agreements specify the exact type of performance and fault conditions that an organization will accept from a common carrier or Internet service provider.

MULTIPLE CHOICE

19. The traditional network design approach does not work well for _________ networks.

a. slowly evolvingb. rapidly growingc. staticd. modestly growinge. not growing

20. Which of the following is false about staff costs for a network? a. The most expensive part of the network today is the staff who design,

operate, and maintain itb. The emphasis is on network designs that reduce staff time needed to

operate themc. Network staff are often required to learn to operate a variety of devicesd. Network staff are often required to maintain a variety of devicese. When a variety of devices are used in a network, it takes less time to

perform network management activities

HJA 2 4/18/2023

Page 3: Exam3RevMIS6316

MIS6316 Exam3 Spring 2015

21. The building block design approach is sometimes called:a. wide and shallowb. narrow and deepc. wide and deepd. narrow and shallowe. narrow and flat

22. In __________, the network designer attempts to understand the fundamental current and future network needs of the various users, departments, and applications.

a. technology designb. needs analysisc. narrow and deep analysisd. cost assessmente. distribution layering

23. In __________, the network designer examines the available technologies and assesses which options will meet the users’ needs.

a. technology designb. needs analysisc. narrow and deep analysisd. cost assessmente. distribution layering

24. In needs analysis: a. a great deal of the work has probably never been doneb. the goal is to understand what users and applications the network will

supportc. the geographic scope is not an important considerationd. a baseline of current operations is not important e. the rate of growth of network traffic is not an issue

25. Gaining an understanding of the current application system and messages provides a _________ against which future design requirements can be gauged.

a. backplaneb. baselinec. turnpike documentd. wish liste. RFP

HJA 3 4/18/2023

Page 4: Exam3RevMIS6316

MIS6316 Exam3 Spring 2015

26. Which of the following is not a conceptual part, or layer, of the geographic scope of the network?

a. core layerb. application layerc. access layerd. distribution layere. the layer that connects the different distribution layers to each other

27. ________ is used to model the behavior of the planned communication network once the proposed network map is complete.

a. Implementationb. Post-implementation reviewc. Documentationd. Simulation e. Training users

28. One reason that there are technical network integration management issues is the fact that:

a. The more different types of network technology used, the more complex network management becomes.

b. Internet protocols are very similar to traditional mainframe protocols.c. Each LAN was developed by a centralized group.d. All LANs used in an organization all use the same architecture. e. All LANs used in an organization use the same type of technology.

29. To help integrate its network management, a central data communication organization should have a ____________ that defines its purpose and operational philosophy.

a. written charter b. LAN manualc. fault logd. trouble tickete. troubleshooting log

30. ___________ refers to managing and documenting the network’s hardware and software configuration.

a. Visioningb. Troubleshootingc. Firefightingd. Configuration managemente. Implementation

HJA 4 4/18/2023

Page 5: Exam3RevMIS6316

MIS6316 Exam3 Spring 2015

31. ____________ is also called automatic software distribution.a. Electronic Data Interchangeb. Software architecturec. Electronic Software Delivery d. Automatic configuration managemente. Email Software Uploading

32. Which of the following is typically not a part of configuration documentation? a. hardware documentationb. sales brochures for new hardware products being considered by the

organization c. user profilesd. network software documentatione. software documentation

33. ___________ ensures that the network is operating as efficiently as possible.a. Firefightingb. Fault tolerancec. Fault managementd. Performance managemente. Troubleshooting

34. ____________ refers to keeping track of the operation of network circuits to make sure they are working properly.

a. Network monitoring b. Fault tolerancec. Fault managementd. Firefightinge. Downtime

35. Logical network parameter monitoring: a. includes monitoring of the network’s modemsb. can not track the destination of data routed across the networksc. can not provide information about the levels of service provided by the

networkd. includes performance measurement data on traffic volume on a particular

circuit e. can not keep data about user response times

36. ___________ allows the network manager to determine who is responsible for correcting any outstanding problems.

a. Load balancing b. MTBFc. Availabilityd. Reliabilitye. Problem tracking