Experience from India Future Perspectives Prof. Shivanand Swamy Executive Director Centre of Excellence in Urban Transport, CEPT University The 2 nd Asia BRTS Conference September 29 and 30, 2014 Amdavad Abhijit Lokre Associate Professor Centre of Excellence in Urban Transport, CEPT University

Upload: others

Post on 07-Aug-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Experience from India Future Perspectives

Prof. Shivanand SwamyExecutive Director

Centre of Excellence in Urban Transport, CEPT University

The 2nd Asia BRTS Conference

September 29 and 30, 2014Amdavad

Abhijit LokreAssociate Professor

Centre of Excellence in Urban Transport, CEPT University

Page 2: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

BRTS Worldwide India

India initiatives NUTP JnNURM

India issues Future perspectives

Page 3: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Worldwide

Page 4: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Region Number of cities

% Passengers per day

% Total length in 

km

%

Africa 3  1.92 238,000 1 62 1.53

Asia 30 19.23 6,275,622 24.5 1037 25.69

Europe 43 27.56 1,656,966 6.46 688 17.04

Latin America

53 33.97 16,326,783 63.66 1347 33.37

North America

20 12.82 819,685 3.19 576 14.27

Oceania 7 4.48 327,074 1.27 326 8.07

World 156 100 25,644,130 100 4036 100

http://brtdata.org, October 2013

Page 5: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Total length

Before 1990 (16 cities)

1991 - 2000 (19 cities)

2001 - 2010 (103 cities)507 km

1025 km

3707 km

Since 2011 (22 cities)

4119 km

http://brtdata.org, October 2013

Page 6: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

0

25

50

75

100

125

150

175

0

5

10

15

20

25

1970 1975 1980 1985 1990 1995 2000 2005 2010

Cum

ulat

ive

Num

ber o

f Citi

es

New

Citi

es

2008: Ahmedabad (Janmarg), India

2000: Bogotá (TransMilenio),

Colombia

1974/1991*: Curitiba

1972/2010*: Lima

http://brtdata.org, October 2013

Page 7: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

0

200

400

600

800

1000

1200

1400

1972

1974

1976

1978

1980

1982

1984

1986

1988

1990

1992

1994

1996

1998

2000

2002

2004

2006

2008

2010

2012

BRTS N

etwor

k Le

ngth (in km

s)

Time Series

Latin America

North America

Europe

China

India

Page 8: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

India

Page 9: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Delhi

Proposed network of 257 km

City wide coverage

Designed as open system

5.5 km operational in 2008

No addition to network since

Map courtesy: TRIPP, IIT Delhi

Page 10: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

In 2004, the Gujarat government initiated a feasibilitystudy for BRTS in Ahmedabad

In 2005, CEPT University’s feasibility studyrecommended BRTS in Ahmedabad

In 2005 and 2006, two initiatives by the CentralGovernment gave an impetus to BRTS The Jawaharlal Nehru National Urban Renewal Mission

(JnNURM) in 2005 The National Urban Transport Policy (NUTP) in 2006

Page 11: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Main focus on efficiency of urban infrastructure andservice delivery mechanisms

Identified requirement of 28 billion USD investmentin urban infrastructure in 63 cities

Urban infrastructure projects include water supply andsanitation, sewerage, solid waste management, roadnetwork and urban transport

Page 12: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Overarching objective: Safe, reliable, affordable, quick, comfortable, reliable andsustainable access

Key Objectives To incorporate urban transport as an important parameterin urban planning

To bring about more equitable allocation of road spacewith people rather than vehicles as the main focus

To encourage greater use of public transport and non‐motorized modes of transport

Page 13: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Under Implementation (7)

Indore

Surat

Rajkot

Vijaywada

Pimpri Chinchwad

Hubli Dharwad

Bhopal

Naya Raipur

Visakhapatanam DPR under preparation (5)

Chennai

Vadodara

Guwahati

Bangalore

Operational (8)

Pune

Jaipur

Ahmedabad

New Delhi

Bhubaneswar

Amritsar Ludhiana

Kolkata

Page 14: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

City Length km

Sanction date

Amount in Rs crore

Progress Operational km

Indore 11.65 Aug 2006 98.45 complete 11.65

Bhopal 42.19 Nov 2006 247.12 85% 23

Pune 115.67 Aug 2006,Oct 2006Mar 2007Aug 2008

1050.46 95% 17

PimpriChinchwad

41.28 Dec 2007Nov 2008Nov 2008

738.16 70% 0

Ahmedabad 88.5 Aug 2006Oct 2006Aug 2008

981.45 90% 82

Surat 29.9 Mar 2008 469.02 55% 11

Page 15: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

City Length km

Sanction date

Amount in Rs crore

Progress Operational km

Rajkot 10.7 Jul 2007 110 complete 10.7

Vijaywada 15.18 Mar 2007 151 70% 0

Vishakhapatnam

45.2 May 2007 452.93 75% 0

Jaipur 39.45 Jul 2007Dec 2007Nov 2009

479.54 NA 7

Amritsar 30 2013 459 NA 0

Delhi* 257 5.6

HubliDharwad

22.25 452 40 0

Naya Raipur 42.5 1791.93 NA 0

Total 534.47 157* Delhi’s network has not been added

Page 16: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

A total of 534.47 km BRTS network has beensanctioned in India, most of it under JnNURM, sinceAugust 2006

A total of 157 km of BRTS is operational in 2013, half ofwhich is in Ahmedabad

The first projects to be sanctioned were in Aug 2006(Indore, Pune and Ahmedabad) and the last in 2013(Amritsar)

Page 17: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

0.0

20.0

40.0

60.0

80.0

100.0

120.0

140.0

160.0

0.0

5.0

10.0

15.0

20.0

25.0

30.0

BRTS km Lau

nche

d

AhmedabadPune

Ahmedabad

Bhopal

Page 18: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

City Operations PopulationKm 

operationalDaily 

ridership

Ahmedabad 2009 5,726,000  82 150,000Pune 2008 5,010,000  17 96,750Bhopal 2013 1,843,000  24 70,000New Delhi 2008 17,015,000  5 53,500Indore 2013 11 22,200Rajkot 2009 11 7,500Jaipur 2010 3,136,000  7 6,622Surat 2013 4,500,000 11 8,000

Total 157 396,572

Page 19: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Issues

Page 20: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Except Ahmedabad, no other city has increasednetwork after initial operations

PILs were filed against Delhi, Indore and Ahmedabadsystems In Delhi, the High Court (HC) initially allowed cars to use bus

lanes and asked CRRI to evaluate situation before and after.Finally, the HC ruled that only buses can be allowed inside

In Indore, the HC allowed cars to use bus lanes, leading tooperations, management and safety issues

In Ahmedabad, the HC refused to admit the PIL, citing theprerogative of the AMC to take the final decision

Page 21: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Delhi BRTS after cars were allowed inside bus lanes

Page 22: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Structural NUTP and JnNURMwere central government initiatives Urban transport is a state subject Public Transport is not an obligatory function of ULB

Policy and plan non‐integration There is no attempt to disincentivise private transport. On

the contrary, cities are funding road projects (widening,flyovers) through internal budgets

A pre‐condition to JnNURM funding was that citiesimplement parking policies. No city has a comprehensiveparking policy

Development plans do not take into account specific needs ofBRTS projects

Page 23: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Political Very few leaders are ready to weather criticism Rail based systems are considered more likely to please voters Bus priority removes parking spaces

Bus image Deteriorated over last 40 years; very difficult to change

Capacity Lack of trained personnel to plan, design and implement as

well as operate BRTS

Page 24: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Bus supply Few bus manufacturers Very high demand from cities, especially after bus funding

scheme Tax issues with bus procurement Quality BRTS bus – It took AMC 5 long years to convince

manufacturers to make quality buses We still don’t have an Articulated Bus manufactured in India

Page 25: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

We have made big strides in the last decade inbuilding infrastructure

However, maintenance is missing Infrastructure is crumbling There is no maintenance regime Budget for maintenance is minimal

Page 26: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18
Page 27: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Our cities may build metros, they may even benecessary

However, buses will always remain the backbone ofour PT systems

Buses and metros must co‐exist, complement andsupport each other

Page 28: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18
Page 29: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Hubli to Dharwad

40.14

43.15

60.60

29.89 35.11

39.03

32.62

30.48 35.40

39.10

33.27

30.14 35.10

38.19

31.25

0.005.00

10.0015.0020.0025.0030.0035.0040.0045.0050.0055.0060.0065.00

Bike Car Regular Bus Express Bus

Existing Network BRT as per DFR 2 Lane at Midblock ElevatedBuses get the highest benefit

BRTS reduces journey times for all modes

Page 30: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

05001000150020002500300035004000450050005500600065007000750080008500900095001000010500110001150012000125001300013500140001450015000155001600016500170001750018000185001900019500200002050021000215002200022500230002350024000

1802

1996

2190

2384

2578

2772

2966

3160

3354

3548

3742

3936

4130

4324

4518

4712

4906

5100

5294

5488

5682

5876

6070

Distanc

e Tr

avelled

Distance Travelled

05001000150020002500300035004000450050005500600065007000750080008500900095001000010500110001150012000125001300013500140001450015000155001600016500170001750018000185001900019500200002050021000215002200022500230002350024000

1802

1930

2058

2186

2314

2442

2570

2698

2826

2954

3082

3210

3338

3466

3594

3722

3850

3978

4106

4234

4362

4490

4618

4746

Distance Travelled

No BRT Scenario BRT scenario

Sample size: 10 BusesBunching of buses in no BRT scenario leads to higher journey time.

Sample size: 12 BusesSegregated bus lanes reduce bunching by increasing reliability

Average Journey Time: 38 mins & 31 mins

Average Journey Time: 60 mins

Page 31: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved : 150Area occupied – 84 sq. mQueue length – 24 m.

People moved :77Area occupied – 486 sq. m.Queue length ‐ 54  m.Phase Time – 40 SecondsCycle Length – 120 Seconds

Page 32: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved – 150Area occupied – 84 sq. mQueue length – 24 m.

People moved ‐45(Reduction from 77)Area occupied – 486 sq. m.Queue length ‐ 54  m.

Page 33: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved – 150Area occupied – 84 sq. mQueue length – 24 m.

People moved ‐77Queue length ‐ 183  m.(Increase from 54 meters)Phase time – 70 SecondsCycle Length – 180 Seconds

Page 34: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved ‐240Queue length ‐ 165 m.(Increase from 54 meters)Phase time – 180 SecondsCycle Length > 180 Seconds (Not Desirable)

Page 35: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved ‐610Queue length ‐ 630 m.(Increase from 210 meters)Phase time – 200 + Seconds (At‐grade operation impossible)

Total ‐Section length –537m

Page 36: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18
Page 37: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

People moved – 280Area occupied – 135 sq. mQueue length – 37 m.

People moved ‐155Queue length – 210 m.Phase time – 70 SecondsCycle Length – 180 Seconds

18 M ARTICULATED BUS CAPACITY‐ 140 

Page 38: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Planned On site situation

Element Width % covered Width % covered

Footpath 2.25m 15 % 2.25m 15 %

Carriageway 9.25m 50% 7m  22%

BRT lane 3.65m 25 %

3.65m 25 %

BRT Stop 1.9m  1.9m 

Parking 2.25  8 % 6m  36%

How do we use our roads?

Page 39: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Segregation is critical; stretches of mixed runningBRTS affect performance and efficiency

Bus stations are critical; segregated busways with nobus stations is as good as not having a BRTS!

Level alighting and boarding are critical;mismatched levels increase dwell times and havesafety implications

Page 40: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Experience suggests ‘supply’ of high quality BRTSneeds to be complemented by demand management Cities need to focus on parking restrictions (less on streetparking, time restrictions) and charging for parking

Cities need to balance their priorities. Public transit,NMT facilities should get higher share in municipalbudgets

Page 41: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Dearth of trained professionals to operate bussystems Frequent training programs for in‐service officers Education programs

BRTS Design is not a traffic engineering exercise Dearth of consultants who understand BRTS and are not‘usual’ traffic engineering consultants

Page 42: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18
Page 43: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

If we consider 25 km of BRT network per million population (and that is a conservative estimate!)

and

If we consider our top 50 cities,

We need 3500 km of BRT network in the next 10 years

Which means 350 km of BRT network every year

And these are base year estimates!!

Page 44: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

So,what are the next steps?

1. We need huge investments to build BRT systems Can the private sector invest in infrastructure? How can government make it viable for them? (especially with issues

in private sector participation in metro projects) How can government regulate such participation?

Page 45: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

So,what are the next steps?

2. We need to create consultants and advisors to work withgovernment Can we create more institutes that offer post graduate programs in

urban transport? Can we create more dedicated training programs across India for in‐

service professionals?

Page 46: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

BRTS is inexpensive to build. (That does not mean itis cheap!)

But, BRTS is difficult to implement and operate(That does not mean it is not possible to build)

Hard decisions! Given Population Density and Area under Roads,BRTS is also inevitable

AND…..DO WE REALLY HAVE A CHOICE?

Page 47: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

IS THIS IS A CHOICE?

Page 48: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18
Page 49: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

This is quality Public Transport

Centre of Excellence in Urban Transport, CEPT University, Ahmedabad, India

Page 50: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Centre of Excellence in Urban Transport, CEPT University, Ahmedabad, India

Page 51: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Centre of Excellence in Urban Transport, CEPT University, Ahmedabad, India

Page 52: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

No RoadsBefore BRTS ‐ No Roads…2008This is what it was

Centre of Excellence in Urban Transport, CEPT University, Ahmedabad, India

Page 53: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Today…–With BRT (2014) 

Transforming Constraints into OpportunitiesBRTS to be operational on this corridor by 2014.

BRTS bus lane

Existing Canal

Mixed traffic lanes

Pedestrian pathPedestrian path

BRTS bus laneMixed traffic lanes

No RoadsThis is what you can make

Centre of Excellence in Urban Transport, CEPT University, Ahmedabad, India

Page 54: Experience Future Perspectives · 2020. 12. 18. · City Length km Sanction date Amount in Rs crore Progress Operation al km Rajkot 10.7 Jul 2007 110 complete 10.7 Vijaywada 15.18

Thank you…