1
Spring Creek SouthHazard Mitigation Grant Program (HMGP) Update
Presentation to Jamaica Bay Task ForceState of the Bay Meeting
Venetia LannonR2 Regional DirectorOctober 29, 2015
2
FEMA Hazard Mitigation Grant
Federal Funds: 75% Local Funds: 25%
Goal: Reduce future disaster damages
3
Project Area: National Park Service Gateway National Recreation Area Jamaica Bay Unit – Spring Creek
4
Project Area: Spring Creek
5
Project Goals
• Natural/nature-based features to manage coastal storm risk
• Improve sustainability and resilience of area
• Integrated approach to provide storm protection and ecosystem restoration benefits
• Consistent with NPS management goals
6
HMGP Award: Two Phases
Phases• I: Engineering & DesignTotal: $3.3M (Share: $2.5M + $0.8M)
• II: ConstructionTotal: $65.8M (Share: $49.3M + $16.5M)Schedule: 18-month build
7
Phase 1 Status Progress
• Agreements between USACE and NYSDEC executed and sampling permits obtained• Scope of Work and contract awarded to Consultant TeamPrinceton HydroParsons BrinckerhoffHDR
• Field work for Baseline Conditions and Concept Design development over the next 2-3 months
8
Baseline Data CollectionOctober- November
Wetland Delineation
Bathymetry
9
Baseline Data Collection: Geotechnical Investigation - Soil BoringsNovember-December
Delivery of ATV Rig and Water Truck to remain on-site
Work Hours: 7AM-3PM +/- One Pick-up Truck on 165th
Street (at 7AM and 3PM) Duration: 2-3 weeks from
start
10
Baseline Data Collection: Contaminant Characterization - Soil SamplingNovember-December
Delivery of Geoprobe and brush hog on-site
Operational hours and traffic same as Geotech
Duration: 5-6 weeks from start
11
Baseline Data Collection: October-December
Biological surveys
Aerial surveys
Tide gauges and current meters
12
Previous USACE Ecosystem Restoration Conceptual Design
Concept Plan Development
13
Conceptual Designs
14
Concept Designs Evaluated
Coastal Storm Modeling Cost Estimates
Concept Plan Selected Designs National Environmental Policy Act (NEPA) Environmental Assessment
15
Detailed Designs and Cost Estimates and NEPA Compliance
Cost Benefit Analysis Detailed designs Detailed cost estimates Plans and specifications Updated NEPA Environmental Assessment
and Compliance
16
Complementary Projects: USACE Rockaway Reformulation Study
17
Complementary Projects: Spring Creek North and New York Rising
Spring Creek North (USACE/NYC Parks Restoration Project)
NY RisingPriority Projects
18
Community and Partner Input
Adjacent landowner requirements Partner agencies considerations Complementary projects Public access & amenities Community Involvement:
Information sessions Draft Environmental Assessment Review/Comment Potential outreach portals (webpage, library, press, signage, info sheets, email updates)
19
FEMA Approval of Phase 1
Advancement to Phase 2 Final plans and specifications for construction Construction
20
21
Thank You
Lisa BaronProject Manager, USACE [email protected]
Joanna FieldMarine Resources BiologistRegion 2, [email protected]
Connect with us:Facebook: www.facebook.com/NYSDECTwitter: twitter.com/NYSDECFlickr: www.flickr.com/photos/nysdec