farahpour-harvard-final presentation-for publication-july ... · 1.verify vfd fiv for ahu-13 is...
TRANSCRIPT
High-containment LaboratoryDesign & Construction
Part 3 - Engineering and Commissioning .Engineering and Commissioning .
Presented by:Babak (Bob) Farahpour, P.E.
Harvard School of Public Health Center for Continuing Professional EducationJuly 14 - 25, 2008 Boston, Massachusetts
Engineering and CommissioningEngineering and Commissioning
• Commissioning• Common Engineering issues during
design, construction and commissioning.
• Certification• Challenges of Commissioning and
maintenance in the developing countries.
Commissioning-1
Definition:
“ Commissioning is a systematic process, through documented verification, that all building
systems perform interactively according to the documented design intent and owner’s
operational needs.”
Commissioning-2
• Identifying and documenting the owner’s needs and the requirements of the facility.
• Ensuring that the designed systems are in accordance with the owner’s needs.
• Ensuring that the systems installed are operable and maintainable.
• Testing of the systems to ensure that they are interacting and performing optimally.
• Ensuring that the design intent, the installations and the O&M requirements are clearly and thoroughly documented
• Training of the operators and the facility staff to ensure they operate and maintain the facility per the design intent .
• The Commissioning Authority oversees and coordinates the Commissioning efforts although all parties play a vital role in Commissioning.
1
1-NIH Website: http://des.od.nih.gov/eWeb/research/farhad2/Commissioning/nih_cx_guide/cxplan/plan/hh_start.htm
Commissioning-3
Building an effective commissioning teamWho should be involved in commissioning:
•Commissioning authority
•Owner project manager
•Users
•Biosafety
•Design team
•Contractor/subcontractor
•Security
Commissioning-4
Our experience for successful commissioning:1. Scope of Work:• Understanding what systems need to be commissioned.• Making sure the owner, user and contractor have the
same expectation from the scope of commissioning.• Independent commissioning agent.• Provide specific requirement:
* Involvement during design.-Peer review* Acceptance criteria.* Field installation verification* Developing Function Performance Tests (FPT)* Developing integrated testing protocols*Training.
Commissioning-5
Our experience for successful commissioning:2. Communication:
– Communication between the users, design team, commissioning agent (Cx) and contractors is essential to ensure successful commissioning.
– Communication between Cx and the rest of the team starts at the design phase-Suggest bringing Cx at 15% design for high containment facilities.
– Commissioning activities should be communicated with the contractor and be integrated into the schedule.
– Lack of communication causes delays translating to higher cost.
Commissioning-6
Notes:
YES NO N/A
YES NO N/A
YES NO N/A1.Verify power panel FIV for AHU-13 is complete and approved.
YES NO N/A1.Verify VFD FIV for AHU-13 is complete and approved.
YES NO N/A1.Verify TAB is completed and approved.
YES NO N/A1.Verify AHU-13 ductwork leak testing FIV is complete and approved.
YES NO N/A1.Verify AHU-13 FIV and AHU-13 ATC FIV are complete and approved.
NoteCACMcCompliancePre-Requisite
TEST PRE-REQUISITE’S2.0
FPT Sample:
Commissioning-7
FPT Sample:
YES NO N/A
Steam control valve actuates to full close position.
Verify if associated preheat coil control valve actuates to full close position when commanded by BAS
3.1.7
YES NO N/A
Steam control valve actuates to full open position.
Verify if associated preheat coil control valve actuates to full open position when commanded by BAS system.
3.1.6
YES NO N/AAHU inlet isolation damper goes to full open position.
Verify AHU inlet isolation damper goes to full open position when commanded by BAS system.
3.1.5
YES NO N/AAHU inlet isolation damper goes to full closed position.
Verify AHU inlet isolation damper goes to full closed position when commanded by BAS system.
3.1.4
YES NO N/AVFD will be able to maintain desired air flow.
Verify AHU supply fan VFD operation from maximum to minimum air flow.
3.1.3
YES NO N/ASupply fan rotates in the right direction.
Verify supply fan correct rotation.3.1.2
YES NO N/AAir handling unit fan starts and stops as commanded by BAS system.
Verify air handling unit fan can be started and stopped by BAS system.
3.1.1
NoteCACMcComplianceExpected ResponseProcedureSeq #
Normal Operating Conditions3.1
TEST PROCEDURES3.0
Commissioning-8
Cost
• It needs to be looked at on a project by project basis.• Average cost: 1% to 2% of the total construction cost.
Commissioning-9
Lessons learned during commissioning:• Hire the Cx early on during design.• Have Cx involved during design reviews.• Review the interlocks-sequence of operation.• Integrated Schedule.• Have Biosafety & security involved during testing
and commissioning. Validated SOPs.• Have the local Fire Marshal involved.
Commissioning-10
Lessons learned during commissioning:
• Have building engineer present during commissioning.
• Have all the Functional Performance Tests (FPTs) and Integrated Systems Test (ISTs) prepared well in advance.
Commissioning-11
Lessons learned during commissioning:
• Field coordination• Each zone(BSL-3, BSL-2,etc.)
to have it’s ownredundant system.Combining the back up system for different zones creates control complications.
Commissioning-13
Problems identified during commissioning:
• Design: incorrect duct and equipment size.• Installation: construction debris blocking pipes
and ventilation pathways.• Component failure: faulty electronics in BAS.• Start-Up: ATS not functioning properly, air in the
water system, etc.
Common Engineering Issues During Design, Construction & Commissioning
• Redundancies.• Room pressurization.• Canopy hood design.• Air device locations.• Decontamination.• Back flow prevention devices.
Redundancy Design-1
• Ideal design: 100% redundant or N+1:– N= number of equipments to have 100% capacity.– 1=one independent backup equipment to ensure
system functionality continues in the event of a system failure
• Keep the laboratory and the vivarium systems separate.
• Exhaust to have min. N+1 for each zone (BSL-3, ABSL-3, BSL-4, ABSL-4)
• A common back up for two different systems.
Redundancy Design-2
BSL-2-EF 1&2
BSL-3-EF 3&4
BSL-2 AHU
Standby AHU
BSL-3 AHU
NC
NC
NORMAL OPERATION:
Room Pressurization-1
CONTROL OF AIRFLOW OFFSETS FOR HIGH CONTAINMENT FACILITIES:
• Passive method
• Active method
Room Pressurization-2
CONTROL OF AIRFLOW OFFSETS:
Passive method:• Not well defined.• Generally constant volume approach• Lower initial cost.• Simpler controls• No/minimal wiring required.• May need rebalancing.• More difficult to commission• Keeping pressurization.
Room Pressurization-3
CONTROL OF AIRFLOW OFFSETS:Active method:• Variable Air Volume Approach (VAV)• Reactive to pressure loss.• Energy efficient.• Easier to commission.• More controllability.• Complicated controls.• Higher initial cost.
Room Pressurization-4
PRESSURE DECAY TESTING:• Done for BSL-4 or ABSL-4, (BSL-3 AG)• Basic principals:
– Charging the room to test pressure – Allowing the pressure to stabilize – Measuring the drop in pressure during testNIH’s Criteria: 2”/20min/50%
Room Pressurization-5
Issues during testing, balancing and Commissioning:
– Room tightness• Door sweeps• Gasketed doors• Transfer ducts.
– Using Fume hoods as exhaust.– Serving more than one room with a single box.
Canopy Hood Design
• Can have a large impact in small places.• Humidity and temperature issues.• Odor control.• Effect on room finishes.• Design to correct capture velocity: 50FPM.• Drain.• Don’t oversize it.
Air Device Locations
• Location of supply air diffusers.• Location of the Exhaust registers.• Animal holding room:
– Ceiling and high level exhaust causes lower room temperature when compared to low level exhaust.
– Ceiling level exhaust provides a better environment for the Scientists.
– Low-level exhaust provides a better environment for the Cages.
Decontamination-1
WHAT NEEDS TO BE DECONTAMINATED?– The laboratory/vivarium area itself.– Any material leaving the high containment
laboratory:• Exhaust Air• Liquid waste• Solid waste• Lab material
Decontamination-2
Laboratory/Vivarium area decontamination:
Most commonly used for Gaseous decontamination:– Formaldehyde (HCHO)– Hydrogen peroxide (H2O2), VHP (Vaporized Hydrogen Peroxide)– Chlorine dioxide (ClO2)
Decontamination-3
Laboratory/Vivarium decontamination:HVAC issues related to decontamination:– There are no standards.– Leaks could create problems:
• Gas dilution• Over pressurizing
– Room preparation issues• Bioseal/Bubble tight dampers:
– Very effective– costly
Decontamination-5
LIQUID DECONTAMINATION SYSTEMS:(Effluent Decontamination System-EDS)
• Batch-type Heat treatment. (Cook Tanks)• Chemical Treatment.• Microwave
Decontamination-6LIQUID DECONTAMINATION SYSTEM:
Batch-type Heat treatment.(Cook Tanks)– Steam injected:
» Quicker kill time» Uniform temperature» More waste» Less commonly used
– Steam Jacketed:» More commonly used
now» Longer kill time.» Cleaner heat transfer
– Steam Coils:» Not allowed.
Decontamination-8
LIQUID DECONTAMINATION SYSTEM:Issues During Commissioning:
• Piping to Cook tanks.• Uniform temperature in tank.• Discharge temperature too high.• No sampling ports.• Sizing.
Decontamination-10
SOLID WASTELab Material
• Autoclave:» Most Commonly used.
• Irradiation:» Gamma irradiation.» Microwave irradiation» Ultraviolet irradiation.
Decontamination-11
SOLID WASTEAnimal Carcasses:– Autoclave
• Protocol driven• Timing is very critical
– Tissue Digesters:• Either for decon or disposal• Manufacturers• Sizing• Cycles• Installation• Commissioning issues
– Incineration:• Availability
Back Flow Prevention Devices-1
Issues with BFP Devices:• Lack of understanding
of the containment barrier.
• Improper use of the BFP devices.
Back Flow Prevention Devices-2
Issues with BFP Devices:
• Incorrect installation of BFP devices.
• Required testing criteria.
Lab Certification
– What is Lab Certification?• Differentiate between Lab and equipment.
– Certification Vs. Commissioning– Is it required?– Having a successful certification
process.
Challenges and Limitation of Commissioning & Maintenance in the
Developing Countries
• Finding the right equipment.• Finding the right contractor.• Understanding of high containment facilities.• Finding the right maintenance staff. • Training facility staff.• Availability of equipment and parts.
[email protected]@niaid.nih.gov
Part 3 - Engineering and Commissioning Engineering and Commissioning issuesissues