Forest Elementary and East Middle School Construction Progress Report
Monday May 16, 2016
Jon Riebe- Farmington Public Schools Brian Smilnak – Wakely Associates/A/E
Paul Wills- Plante Moran CRESA Scott Smith- Plante Moran CRESA
Rich Griffin – McCarthy & Smith Project Superintendent Leo Cartier- McCarthy & Smith Project Superintendent
Ryan Black – McCarthy & Smith Project Engineer Aaron Phillips – McCarthy & Smith Project Manager
Current Status
Shoreview Electric installing temporary hanger wires on lights and mobilizing in gymnasium for over head piping.
East Middle School
Current Status
East Middle School gymnasium
Overhead piping
Current Status
Forest Elementary
Set up and layout for new footings.
Current Status
Forest Elementary
Rebar installation
Packing up books at Forest Elementary.
Plan Ahead
CEI Electric mobilized at Lanigan Elementary to start overhead piping and data piping. Shoreview Electric mobilized at Farmington High on 5/12/16 and will start overhead piping this week. McCarthy & Smith plans on setting up the job site trailers at each school by the end of May.