Farmington Public Schools Bid Package #1 & #2 Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools Brian Smilnak – Wakely Associates/A/E Paul Wills- Plante Moran CRESA Scott Smith- Plante Moran CRESA Rich Griffin – McCarthy & Smith Project Superintendent Leo Cartier- McCarthy & Smith Project Superintendent Ryan Black – McCarthy & Smith Project Engineer Aaron Phillips – McCarthy & Smith Project Manager

Upload: others

Post on 02-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Farmington Public Schools Bid Package #1 & #2

Forest Elementary and East Middle School Construction Progress Report

Monday May 16, 2016

Jon Riebe- Farmington Public Schools Brian Smilnak – Wakely Associates/A/E

Paul Wills- Plante Moran CRESA Scott Smith- Plante Moran CRESA

Rich Griffin – McCarthy & Smith Project Superintendent Leo Cartier- McCarthy & Smith Project Superintendent

Ryan Black – McCarthy & Smith Project Engineer Aaron Phillips – McCarthy & Smith Project Manager

Page 2: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Current Status

Shoreview Electric installing temporary hanger wires on lights and mobilizing in gymnasium for over head piping.

East Middle School

Page 3: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Current Status

East Middle School gymnasium

Overhead piping

Page 4: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Current Status

Forest Elementary

Set up and layout for new footings.

Page 5: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Current Status

Forest Elementary

Rebar installation

Page 6: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Packing up books at Forest Elementary.

Page 7: Farmington Public Schools Bid Package # 1 & #2€¦ · Forest Elementary and East Middle School Construction Progress Report Monday May 16, 2016 Jon Riebe- Farmington Public Schools

Plan Ahead

CEI Electric mobilized at Lanigan Elementary to start overhead piping and data piping. Shoreview Electric mobilized at Farmington High on 5/12/16 and will start overhead piping this week. McCarthy & Smith plans on setting up the job site trailers at each school by the end of May.