fawaz miro

7
KAR Pipeline LTD, HKN RETM, Piping (from 28/Nov/2018 to 01-Dec-2019), Working as Mechanical Supervisor Engineer in piping construction, was in charge of pipe welding map mark, site construction quality check (delivery checklist of pipes, welding, sandblasting, coating, painting). Prepare hydro-test Package and relevant certificates (such as the mechanical complete certificates, Provisional Acceptance certificate, Commissioning Certificate, Ready to Start-up Certificate, Start-up Certificate, etc.) Material checking with certificate for piping in RETM HKN Materials. hydrostatic test of piping. KAR Pipeline LTD, GKPI (PF1,RETM) and pipeline 16'' (from 01/Nov/2018 to 01-Dec-2019), Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding map mark, site construction quality check (delivery checklist of pipes, stringing, bending, welding, coating, lowering) 12.850 Km. Material checking with certificate for piping in PF1. Torqueing the flanges and valves. Experiences FAWAZ MIRO Supervisor Mechanical Engineer at KAR GROUP Duhok, Iraq +964-7508359100 [email protected] LinkedIn: Fawaz Miro Personal Information Nationality: Syrian Sex: Male Family status: Married, I have two children Date of Birth: 20\12\1983 Scientific Certification University: Damascus University, the Faculty of Mechanical and Electrical Engineering. Department: Mechanical Engineering / Mechanical Power Department Graduation Project: Economic Survey of the Feasibility at Spinning and Textile factory in Damascus, Syria. Degree: Good Rate: (62, 43 %) 2011

Upload: others

Post on 16-Oct-2021

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: FAWAZ MIRO

• KAR Pipeline LTD, HKN RETM, Piping (from 28/Nov/2018 to 01-Dec-2019),

➢ Working as Mechanical Supervisor Engineer in piping construction, was in charge of pipe

welding map mark, site construction quality check (delivery checklist of pipes,

welding, sandblasting, coating, painting).

➢ Prepare hydro-test Package and relevant certificates (such as the mechanical

complete certificates, Provisional Acceptance certificate, Commissioning Certificate,

Ready to Start-up Certificate, Start-up Certificate, etc.)

➢ Material checking with certificate for piping in RETM HKN Materials.

➢ hydrostatic test of piping.

• KAR Pipeline LTD, GKPI (PF1,RETM) and pipeline 16'' (from 01/Nov/2018 to 01-Dec-2019),

➢ Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding

map mark, site construction quality check (delivery checklist of pipes, stringing,

bending, welding, coating, lowering) 12.850 Km.

➢ Material checking with certificate for piping in PF1.

➢ Torqueing the flanges and valves.

Experiences

F A W A Z M I R O

Supervisor Mechanical Engineer at KAR GROUP

Duhok, Iraq

+964-7508359100

[email protected]

LinkedIn: Fawaz Miro

Personal Information

Nationality: Syrian Sex: Male Family status: Married, I have two children Date of Birth: 20\12\1983

Scientific Certification

University: Damascus University, the Faculty of Mechanical and Electrical Engineering.

Department: Mechanical Engineering /

Mechanical Power Department

Graduation Project: Economic Survey of the

Feasibility at Spinning and Textile factory in Damascus, Syria.

Degree: Good Rate: (62, 43 %) 2011

Page 2: FAWAZ MIRO

➢ hydrostatic test of piping.

➢ Prepare hydro-test Package and relevant certificates (such as the mechanical

complete certificates, Provisional Acceptance certificate, Commissioning

Certificate, Ready to Start-up Certificate, Start-up Certificate, etc.)

• KAR Pipeline LTD, KPS2 (KURDISTAN PUMP STATION 2) PIPELINE EXPORT SYSTEM OIL and GAS

(February2018- to 01/Nov/2018) SHEKHAN, KURDISTAN, IRAQ.

Main Duties:

➢ Working as Mechanical engineer in Pipeline (Piping)construction, was in charge of pipe

welding map mark, site construction quality check.

➢ Punch list incorrect item of piping installation, close the punch list items.

➢ Prepare hydro-test Package and relevant certificates (such as the mechanical

complete certificates, Provisional Acceptance certificate, Commissioning Certificate,

Ready to Start-up Certificate, Start-up Certificate, etc.)

➢ Construction coordination with Client for pre-commission and hand over working.

➢ Be familiar with sand blasting, Coating, And Welding.

➢ Installing pumps with motor skid in the Foundation, pre- alignment, final alignment. Install

3 pumps, alignment, hot commissioning.

➢ Install 3 pumps, alignment, hot commissioning.

➢ Prepare hydro-test Package and relevant certificates (such as the mechanical

complete certificates, Provisional Acceptance certificate, Commissioning Certificate,

Ready to Start-up Certificate, Start-up Certificate, etc.)

• KAR Pipeline LTD, GULF KEYSTONE BESAT PIPELINE EXPORT SYSTEM OIL and GAS (PF2) (October 2017 –

February 2018) BESAT TO ATRUSH PIPELINE, Kurdistan, Iraq

Main Duties:

➢ Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding

map mark, site construction quality check.

➢ Punch list incorrect item of piping installation, close the punch list items.

➢ Prepare hydro-test Package and relevant certificates (such as the mechanical

complete certificates, Provisional Acceptance certificate, Commissioning Certificate,

Ready to Start-up Certificate, Start-up Certificate, etc.)

➢ Construction coordination with Client for pre-commission and hand over working.

➢ Be familiar with sand blasting, Coating, And Welding.

➢ Install 3 pumps, alignment, hot commissioning.

• KAR Pipeline LTD, ATRUSH PIPELINE EXPORT SYSTEM oil and gas (March 2017- October 2017)- ATRUSH TO SHEKHAN, Kurdistan, Iraq

Main Duties:

Page 3: FAWAZ MIRO

➢ Working as Mechanical engineer in Pipeline construction, was in charge of pipe welding

map mark, site construction quality check.

➢ Punch list incorrect item of piping installation, close the punch list items.

➢ Be familiar with sand blasting, Coating, And Welding.

• KAR Group LTD, Khormala Power Plant (1000 MW) (January 2013- Febriwary-2017) - Erbil, Kurdistan, Iraq

Field Engineer

Main Duties:

➢ Supervising the installation of the 5000 CUBIC METERS Tank Farm (Erection,

hydrostatic test, commissioning).

➢ Supervising the installation of the 400 KV switchyard towers.

➢ Supervising the installation of the central air-conditioning HVAC in (Project administration building, social building, control building, reception building and firefighting building).

➢ Supervising the Welding processes and installing the pipes within the project (Erection,

Blowout, Hydrostatic test, flashing).

➢ Arranging the working sheets that satisfy the work demand of the contractor

(SIEMENS, ABB & ACCORU) and sub-contractor (SEC, Power China, and NYCO).

➢ Arranging the Notification Sheets that report the issues occur during work. ➢ QA/QC completion that related to the NDT Company (NYCO). ➢ Electrical ECC (Erection Clearance Certificate) & FQP (Field Quality Plan) for all power

plant units. ➢ Placing all KKS labels regarding the power plant elements according to P&ID diagrams.

➢ Work in commissioning of fuel gas supply system and fuel oil supply system. ➢ Embedded part (install anchor bolts, plats and H-beam) in the foundation in power

plant, phase one (four units) and phase three (two units).

➢ Supervising the installation of the power island, SIEMENS part (turbine, generator, air intake, exhaust stack, and auxiliary), phase three (two units).

➢ Cold commissioning and hot commissioning of the power plant with SIEMENS teams in Khormala power plant.

➢ Commissioning of Demin water System Capacity 10 m3 per day.

• Avro City (Duhok / Kurdistan / Iraq), (April 2012- December 2012).

Main Duties:

➢ Installation and maintenance of air conditioners individual, multilateral and central air conditioning with VRV system.

➢ Expertise in engineering drawing more than four years in Damascus. ➢ Installation, Welding, and insulation of the brass pipes. ➢ Work in Electricity car workshop for three Years. ➢ A member of Association of Engineers in Syria.

➢ Kurdish: Native Language.

➢ Arabic: Excellent Read and write.

➢ English: good Read and write.

Relative Skills:

Languages:

Page 4: FAWAZ MIRO

➢ Turkish: good conversation.

➢ Proficient in Microsoft Office, Data Base (ICDL) and Computer Maintenance in

Software and Hardware.

➢ Proficient in Mechanical Desktop and AutoCAD Desktop.

➢ Knowledgeable in operating Mechanical Desktop and AutoCAD for HVAC Planning

➢ ASNT – Level I & II (VT, PT & MT).

SAMI ABDULZAHRA ALI,

Project Manager at KAR Group, Erbil-Iraq.

Phone No: +964-7508230860, Email [email protected]

Computer: Skills

References

Page 5: FAWAZ MIRO

-6-6 !,%r"9.@""tyf"n

,9r, 9/Drt"t4Magnetic Particle Testing- MT

Level II

.//lat'

Fawoz Miro

Hqs Met the Requirements as Per Guidelines of American Societyfor NonDestructive Testing Document SNT-TC-IA as

Examination Result:Average: 80%Fundamental: 80okCode: 80%Practical: 8A%

Certification DeptManaging Director

Issue Date: July. 3 1 .2019Expiration Date: July. 31 .2022

Certificate Number:

QAL-266874-19-256230

Vision ExaminationLeft: JI Right: JlNear Vision: NormalColor Vision: Normal

Issued By:Mr. Shamaghdari

ASNT III No. :1

*rt

Applicable SpecificatiAWS Dl.l (2015) & ASME Sec. v & VIII (2017), ASME 831.1 (2016), ASME 83l.l (2016)

www.qalcert.co.uk

ALUKLIMITED

-

.,!A

7

Page 6: FAWAZ MIRO

(9r02) r'rts s'.,rsv '(9t02) t r ts ansv '( 0z) IA a A 'tes ahrsv ? (s r0z) I IC s,,r\v

--16-a6i

.L

6t.ON

III IA^A'I INSVrrepqSPueqs 'rr{

:Ig panssl

lotlttoN :uorsu toloSlDuloN :uolsu fiaN

It:ry8!tr If :{aT

E€qs'It[

6ZZ9 97,- 6r -n 18992-TVb

:JequnN elBcglueS

ZZ0Z' IE ',(1ng:e1eg uorleldxg610Z' lE '.(1n1 :e1eq enssl

ropalq Sur8eueylldag uopuegp.ra3

% 08 :lorlpDrd% 08 :apoJ9%08 : loluzuopunc

% 0g :a8ota,tyuolDutaoxg uolsll :qnsaf, uououtuoxg

II PM7Jd -Sulsal tuD,Uauad prublT

//r?"1316 ":%: ,r

sD 7I1J-JNS tuawrucoq Suttsal atlpnusaeuoTJ totilalcog uon"tawylo saulpplng "od sD suaua"4nba[ aqt pIA[ sDH

ottru zDtADl

va{taag/r-%; trtr

In' o J' ua J Ieb',u,,r,r.,r,t

:(s) uosecgrcadg alqecqddy

ClfI'In.I

T r

L"

I

Page 7: FAWAZ MIRO

Fawaz Mtro

Has Met the Requirements as Per Guidelines of American Societyfor NonDestructive Testing Document SNT-TC-IA as

-{",',%,!,,XGl"rt4Yisual Testing - W

Level IIExamination Result:

Average: 80 %Fundamental: 8096Code: 80%Practical: 80%

Certification DeptManaging Director

Vision ExqminationLefi: Jl Right: JlNear llision: NormalColor Vision: Normal

Issue Date: July. 3l .2019Expiration Date: July. 31 .2022

Certificate Number;

QN--266874-19-2s6228

lssued By:Mr. Shamaghdari

ASNT III No.

Applicable SpecificatiAwS Dl,l (2015) & ASME Sec. V & VIll (2017), ASME 83l.l (2016), ASME 83l.l (2016)

9

www.qalceft.co.uk

n

I

UKL

-% -% !%:,*9, C"rgf"d %r,

!

I

/

t

ASN'a i : Irlf/T. t:'! M'i' r;