FDOT UTILITY RELOCATION SCHEDULE
MANUAL
June 12th, 2001
-
5/24/2018 FDOT Utility Production Rate Manual
2/31
FDOT UTILITY RELOCATION
SCHEDULE MANUAL
Dr. Ralph D. Ellis Jr., P.E. Principal Investigator
Jennifer W. Shannon, E.I. Research Assistant
Michael Shane Johnson Research Assistant
Benjamin S. Yang, E.I. Research Assistant
Barry D. Guertin, E.I. Research Assistant
Department of Civil & Costal Engineering
College of Engineering
UNIVERSITY OF FLORIDAGainesville
-
5/24/2018 FDOT Utility Production Rate Manual
3/31
INTRODUCTION
The researchers at the University of Florida would like to thank John Shriner of the Florida
Department of Transportation for allowing them to work on this project. It is hoped that thismanual will be a helpful guide to professionals who are interested in the duration of utility
relocation and installation operations. Although this manual is not the final word in utilities
scheduling it is hoped that you will find it useful and that it will provide you with a betterunderstanding of the time requirements for utilities operations.
Respectfully:
Ralph D. Ellis Jr. P.E.
Jennifer W. Shannon, E.I.Michael Shane Johnson
Benjamin Yang, E.I.Barry D. Guertin, E.I.
-
5/24/2018 FDOT Utility Production Rate Manual
4/31
BACKGROUND
FDOT scheduling engineers need a reliable reference for estimating the duration of different
utility relocations encountered on FDOT construction projects. The type of utility work involved
on a project may vary considerably. FDOT projects can involve everything from fiber optic
systems to conventional storm drainage, often with many different utility systems involved in asingle project. This manual is intended to be the beginning of a comprehensive information base
for estimating utility production rates and activity duration.
The University of Florida was under contract with the FDOT to create this Utility Production
Rate Scheduling Reference for FDOT Construction Projects. The research team used the
following research approach:
Approached members of the utility industry to develop a list of common utility activities. Developed list of common utility activities from FDOT utility relocation schedules Verified the list of common utility activities with FDOT district utility engineers Obtained low, average, and high durations and influencing factors for items on the list of
common utility activities from different utility companies and means manuals Compared the information from the utility companies with the data from the utility
relocation schedules and means manuals
For more information on the research process, please see the document Development of a UtilityProduction Rate Scheduling Reference for FDOT Construction Projects.
This estimating reference presents production rates for utility work activities within the contextof FDOT projects. The range of times and influencing factors for the activities can serve as
adjustment factors for a scheduling engineer. However, anyone who uses this manual must note
that the durations for the activities included in this manual are on-site construction times only!The time necessary to acquire permits and to design a utility relocation is not included in this
manual. The focus of this research was to find construction times and that is what is included inthis manual.
-
5/24/2018 FDOT Utility Production Rate Manual
5/31
Table of Contents
CABLE ........................................................................................................................................... 1Activity CA01 Adjust or replace one fiber optic aerial cable..................................................... 1
Activity CA02 Place and pull new coaxial cable through a four-inch duct................................ 1
Activity CA03 Splice and activate new coaxial cable. ............................................................... 1
Activity CA04 Directional bore 100 feet for a four-inch duct.................................................... 2Activity CA05 Relocate three fiber overhead cables to new poles. ........................................... 2
Activity CA06 Remove one existing underground amplifier and power supply........................ 2
Activity CA07 Remove existing overhead cable per 100-feet. .................................................. 3Activity CA08 Remove existing cable crossing per span........................................................... 3
ELECTRIC ..................................................................................................................................... 4
Activity OE01 Relocate per span one 13kV line. ....................................................................... 4Activity OE02 Relocate one pole for 12.47 kV line................................................................... 4
Activity OE03 Remove one overhead electric crossing for a 13.2 kV line................................ 5
ActivityOE04 Remove fifty feet of aerial cable. ........................................................................ 5ActivityOE05 Provide service for street light load center (480 V). ........................................... 5
Activity OE06 Remove poles for an aerial crossing................................................................... 6Activity OE07 Provide service for traffic signal (120 V)........................................................... 6
Activity UE01 Remove three buried cables per fifty feet........................................................... 6Activity UE02 Place duct bank X by Y of Z-inch conduit per fifty feet. ................................... 7
ActivityUE03 Remove 3-100 mm conduits for fifty feet. .......................................................... 7
Activity UE04 Adjust existing electric conduits. ....................................................................... 8ActivityUE05 Place pre-cast manhole. ....................................................................................... 8
GAS................................................................................................................................................. 9
Activity GA01 Protect and support ten linear feet of one low-pressure gas line. ...................... 9Activity GA02 Adjust one two-inch steel pipe........................................................................... 9
Activity GA03 Lower one service line in place.................................................................... 9
Activity GA04 Install one new two-inch gas line per fifty linear feet...................................... 10Activity GA05 Install one bottom-out connection for one four-inch gas main........................ 10
Activity GA06 Place out of service one four-inch gas line per fifty linear feet. ...................... 10Activity GA07 Lower one high-pressure gas line. ................................................................... 11
Activity GA08 Encase one high-pressure gas line. .................................................................. 11
PHONE ......................................................................................................................................... 12
Activity PA01 Install and splice 100 linear feet of buried copper cable. ................................. 12Activity PA02 Install and splice 100 linear feet of buried fiber cable...................................... 12
Activity PA03 Install and splice 100 linear feet of aerial copper cable.................................... 12
Activity PA04 Install and splice 100 linear feet of aerial fiber cable....................................... 13Activity PA05 Install and splice 100 linear feet of copper cable in conduit. ........................... 13
Activity PA06 Install and splice 100 linear feet of fiber cable in conduit................................ 13Activity PA07 Place fifty feet of X-pair cable out of service................................................... 14Activity PA08 Place (1) 4 sched. 40 PVC conduit out of service........................................... 14
Activity PA09 Place (1) 4 sched. 40 PVC conduit in service................................................. 15
Activity PA10 Lower fifty linear feet of X-pair cable.............................................................. 15Activity PA11 Install and connect one handhole and duct system........................................... 15
Activity PA12 Adjust one telephone handhole to final grade. ................................................. 16
Activity PA13 Adjust frame and cover for one manhole. ........................................................ 16
-
5/24/2018 FDOT Utility Production Rate Manual
6/31
Activity PA14 Splice one 900-pair cable.................................................................................. 16
SEWER......................................................................................................................................... 17Activity SA01 Furnish, install, and connect fifty linear feet of X-inch PVC SDR. ................. 17
Activity SA02 Furnish, install, and connect fifty linear feet of X-inch PVC FM. ................... 17
Activity SA03 Remove and replace fifty linear feet of X-inch PVC FM................................. 18
Activity SA04 Plug and place out of service one eight-inch sanitary sewer main. .................. 18Activity SA05 Re-route fifty linear feet of X-inch PVC FM. .................................................. 19
Activity SA06 Grout fill one X-inch sanitary sewer lateral for fifty linear feet....................... 19
Activity SA07 Furnish and install one manhole. ...................................................................... 20Activity SA08 Adjust ring and cover to grade for one manhole. ............................................. 20
WATER ........................................................................................................................................ 21
Activity WA01 Furnish, install, and connect fifty linear feet of Type K copper pipe. ............ 21ActivityWA02 Cut and plug one X-inch pipe. ......................................................................... 21
Activity WA03 Adjust one water valve box to grade............................................................... 22
Activity WA04 Adjust one X-inch WM................................................................................... 22Activity WA05 Remove and replace fifty linear feet of X-inch WM. ..................................... 23
ActivityWA06 Furnish and install one fire hydrant assembly.................................................. 23Activity WA07 Remove and replace one fire hydrant assembly.............................................. 24
Activity WA08 Remove and replace one water meter. ............................................................ 24Activity WA09 Relocate one water meter. ............................................................................... 25
-
5/24/2018 FDOT Utility Production Rate Manual
7/31
Cable Page # 1
CABLE
Adjustment or replacement one fiber optic aerial cable.
Adjustment
Current
Activity CA01 Adjust or repl
one fiber optic aerial cable.
Lowest Duration: 4 hoursAverage Duration: 5 hours
Highest Duration: 6 hours
Influencing Factors:
type of pole energized or de-energiz
cable
drilling time
Place & pull new coax cable through 4" conduit
4"
Activity CA02 Place and pullcoaxial cable through a four-
duct.
Lowest Duration: 5 daysAverage Duration: 6 days
Highest Duration: 10 days
Influencing Factors:
Soil conditions Location of other utiliti
Splice & activate new coax cable
Activity CA03 Splice and acti
new coaxial cable.
Lowest Duration: 5 daysAverage Duration: 6 days
Highest Duration: 10 days
Influencing Factors: Location of coaxial cab Location of other utiliti Number of people on cr Available equipment
-
5/24/2018 FDOT Utility Production Rate Manual
8/31
Cable Page # 2
Activity CA04 Directional bo
100 feet for a four-inch duct.
Lowest Duration: 1 day
Average Duration: 2 daysHighest Duration: 4 days
Influencing Factors:
Soil conditions Known or unknown util
locations
Any failed attempts for successful directional b
Relocate 3 fiber optic aerial cables to new poles Activity CA05 Relocate threeoverhead cables to new poles.
Lowest Duration: 6 hours
Average Duration: 12 hoursHighest Duration: 18 hours
Influencing Factors:
Type of pole Number of attachments
pole
Energized or de-energizcable
Remove on e exisiting underground amplifier & power supply
Activity CA06 Remove one
existing underground amplifi
and power supply.
Lowest Duration: NA
Average Duration: 1 day
Highest Duration: NA
Influencing Factors:
Soil conditions Location of other utiliti
-
5/24/2018 FDOT Utility Production Rate Manual
9/31
Cable Page # 3
Remove existing OH cable per 100 ft.
100 L.F. 100 L.F.
Activity CA07 Remove existin
overhead cable per 100-feet.
Lowest Duration: 0.4 hours
Average Duration: 0.5 hoursHighest Duration: 0.7 hours
Influencing Factors:
Traffic Energized or de-energiz
cable
Location of other utiliti Street crossings
Remove existing OH per crossing span
Roadway
Activity CA08 Remove existincable crossing per span.
Lowest Duration: 0.8 hours
Average Duration: 1.0 hour
Highest Duration: 1.4 hours
Influencing Factors:
Traffic Energized or de-energiz
cable
Location of other utiliti Street crossings
-
5/24/2018 FDOT Utility Production Rate Manual
10/31
ELECTRICAL Page # 4
ELECTRIC
Relocate per span one 13 kV line.
Activity OE01 Relocate per sp
one 13kV line.
Lowest Duration: 0.5 days
Average Duration: 1 dayHighest Duration: 10 days
Influencing Factors:
Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination
Activity OE02 Relocate one p
for 12.47 kV line.
Lowest Duration: 0.5 days
Average Duration: 2 daysHighest Duration: 5 days
Influencing Factors:
Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination
-
5/24/2018 FDOT Utility Production Rate Manual
11/31
ELECTRICAL Page # 5
Remove 50 ft. Aerial cable.
50 '
Activity OE03 Remove one
overhead electric crossing for
13.2 kV line.
Lowest Duration: 1 dayAverage Duration: 2 days
Highest Duration: 4 days
Influencing Factors:
Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination
Remove 50 ft. Aerial cable.
50 '
ActivityOE04 Remove fifty fe
aerial cable.
Lowest Duration: 0.5 days
Average Duration: 1 day
Highest Duration: 2 days
Influencing Factors:
Crew availability Truck access Outage coordination req MOT coordination
Provide service for Street light load center (480 V)
street light load center
Activity OE05 Provide servic
street light load center (480 V
Lowest Duration: 1 day
Average Duration: 3 days
Highest Duration: 10 days
Influencing Factors:
Crew availability Truck access Type of line work requi MOT coordination
-
5/24/2018 FDOT Utility Production Rate Manual
12/31
ELECTRICAL Page # 6
Remove poles for aerial crossing
Activity OE06 Remove poles
an aerial crossing.
Lowest Duration: 1 dayAverage Duration: 2 days
Highest Duration: 4 days
Influencing Factors:
Crew availability Truck access MOT coordination Type of pole Disposal of pole
Provide Service for traffic Siginal (120 V)
Traffic control device
Activity OE07 Provide servic
traffic signal (120 V).
Lowest Duration: 1 day
Average Duration: 3 daysHighest Duration: 10 days
Influencing Factors:
Crew availability Truck access Line work required MOT coordination
Remove 3 buried cable per 50 L.F.
50 L.F.
Activity UE01 Remove three
buried cables per fifty feet.
Lowest Duration: 1 day
Average Duration: 2 daysHighest Duration: 5 days
Influencing Factors:
Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin
required
-
5/24/2018 FDOT Utility Production Rate Manual
13/31
ELECTRICAL Page # 7
Place duct bank X by Y of Z inch conduit for 50 L.F.
50 L.F. X
Conduits width
Y tall Z inches
Activity UE02 Place duct ban
by Y of Z-inch conduit per fif
feet.
Lowest Duration: 1 day
Average Duration: 2 daysHighest Duration: 5 days
Influencing Factors:
Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin
required
Remove 3 buried cable per 50 L.F.
50 L.F.
ActivityUE03 Remove 3-100 m
conduits for fifty feet.
Lowest Duration: 1 day
Average Duration: 2 days
Highest Duration: 5 days
Influencing Factors:
Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin
required
-
5/24/2018 FDOT Utility Production Rate Manual
14/31
ELECTRICAL Page # 8
Adjust existing electrical conduits.Activity UE04 Adjust existing
electric conduits.
Lowest Duration: 1 day
Average Duration: 2 daysHighest Duration: 5 days
Influencing Factors:
Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin
required
Ability to switch cable
Adjust frame & cover for one m anhole
ActivityUE05 Place pre-cast
manhole.
Lowest Duration: 2 days
Average Duration: 5 days
Highest Duration: 10 days
Influencing Factors:
Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin
required
Location of manhole Number of surrounding
utilities
Placement into pavemengrass
-
5/24/2018 FDOT Utility Production Rate Manual
15/31
Gas Page # 9
GAS
Protect & Support 10 L.F. of one low pressure gas line
10 L.F.
Trench
Activity GA01 Protect and
support ten linear feet of one
pressure gas line.
Lowest Duration: 0.5 days
Average Duration: 1 dayHighest Duration: 2 days
Influencing Factors:
Open excavation Providing temporary su Site conditions Weather conditions Type of material Shoring equipment
Adjust one 2" steel pipe
2"
Activity GA02 Adjust one tw
inch steel pipe.
Lowest Duration: 1 day
Average Duration: 2 daysHighest Duration: 4 days
Influencing Factors:
Length to move Pressure Need to make stops and
in pipe
Lower one 3/4" steel pipe
3/4"
Activity GA03 Lower one
service line in place.
Lowest Duration: 1 dayAverage Duration: 1 day
Highest Duration: 2 days
Influencing Factors:
Site conditions Restoration of service Involvement of road cro
-
5/24/2018 FDOT Utility Production Rate Manual
16/31
Gas Page # 10
Activity GA04 Install one new
two-inch gas line per fifty line
feet.
Lowest Duration: 0.5 daysAverage Duration: 1 day
Highest Duration: 2 days
Influencing Factors:
Open trench Site conditions Type of pipe
Bottom OutDerby.
90 Ell.
New lin e.
Line being tappedor stopped.
Installation of bottom out connection.
Activity GA05 Install one botout connection for one four-in
gas main.
Lowest Duration: 0.5 daysAverage Duration: 2 days
Highest Duration: 4 days
Influencing Factors:
Site conditions Weather Welding Material and supplies
Place out of service one 4" ga s line per 50 ft.
4"
50 L.F.
Activity GA06 Place out of se
one four-inch gas line per fift
linear feet.
Lowest Duration: 0.5 days
Average Duration: 2 days
Highest Duration: 4 days
Influencing Factors:
Length of main to purge Type of material for ma Involvement of custome Installation of stoppers
each end
-
5/24/2018 FDOT Utility Production Rate Manual
17/31
Gas Page # 11
Lower one high pressure gas line.Activity GA07 Lower one hig
pressure gas line.
Lowest Duration: 1 day
Average Duration: 3 daysHighest Duration: 6 days
Influencing Factors:
Type of material for lin Open excavation Location of other utiliti
Encase one high-pressure gas line
Activity GA08 Encase one hig
pressure gas line.
Lowest Duration: 6 days
Average Duration: 8 days
Highest Duration: 10 days
Influencing Factors:
Open excavation Installation of casing
-
5/24/2018 FDOT Utility Production Rate Manual
18/31
Phone Page # 12
PHONE
Install & splice 100 L.F. of buried copper cab le.
100 L.F.
B B B B B B
Activity PA01 Install and spli
100 linear feet of buried copp
cable.
Lowest Duration: 2 days
Average Duration: 3 daysHighest Duration: 5 days
Influencing Factors:
Special conduit cut-ove Ground conditions
Activity PA02 Install and spli100 linear feet of buried fiber
cable.
Lowest Duration: 2 days
Average Duration: 3 daysHighest Duration: 5 days
Influencing Factors:
Special conduit cut-ove Ground conditions
Install & splice 100 L .F. of aerial copper cable.
100 L.F.
Activity PA03 Install and spli
100 linear feet of aerial coppe
cable.
Lowest Duration: 2 days
Average Duration: 3 daysHighest Duration: 5 days
Influencing Factors:
Special conduit cut-ove Ground conditions
-
5/24/2018 FDOT Utility Production Rate Manual
19/31
Phone Page # 13
Install & splice 100 L .F. of aerial fiber cable.
100 L.F.
Activity PA04 Install and spli
100 linear feet of aerial fiber
cable.
Lowest Duration: 2 daysAverage Duration: 3 days
Highest Duration: 5 days
Influencing Factors:
Special conduit cut-ove Ground conditions
Install & splice 100 L.F. of copper cable in condu it.
100 L.F.
Activity PA05 Install and spli
100 linear feet of copper cablconduit.
Lowest Duration: 2 days
Average Duration: 3 days
Highest Duration: 5 days
Influencing Factors:
Special conduit cut-ove Ground conditions Manhole access Traffic
Install & splice 100 L .F. of fiber cable in conduit.
100 L.F.
Activity PA06 Install and spli
100 linear feet of fiber cable i
conduit.
Lowest Duration: 2 daysAverage Duration: 3 days
Highest Duration: 5 days
Influencing Factors: Special conduit cut-ove Ground conditions Manhole access Traffic
-
5/24/2018 FDOT Utility Production Rate Manual
20/31
Phone Page # 14
Place 50 L.F. x-pair cable out of service.
50 L.F.
B X B B B BX X X
Activity PA07 Place fifty feet
pair cable out of service.
Lowest Duration: 2 days
Average Duration: 3 daysHighest Duration: 5 days
NOTE: The time for this activ
included in the splicing work.
Influencing Factors:
Special conduit cut-ove Ground conditions Manhole access Traffic
Place (1) 4" schedule 40 PVC con duit out of service.
4"
Activity PA08 Place (1) 4 sch
40 PVC conduit out of service
Lowest Duration: 2 days
Average Duration: 3 days
Highest Duration: 5 days
NOTE: The time for this activ
included in the splicing work.
Influencing Factors:
Special conduit cut-ove Ground conditions Manhole access Traffic
-
5/24/2018 FDOT Utility Production Rate Manual
21/31
Phone Page # 15
Place (1) 4" schedule 40 PVC cond uit in service.
4"
Activity PA09 Place (1) 4 sch
40 PVC conduit in service.
Lowest Duration: 0.8 days
Average Duration: 1 dayHighest Duration: 1.2 days
Influencing Factors:
Rocks
Lower 50 L.F. of x-pair cable
Activity PA10 Lower fifty lin
feet of X-pair cable.
Lowest Duration: 1 day
Average Duration: 2 days
Highest Duration: 8 days
Influencing Factors:
Rocks Must expose 150 of ca
lower 50
Install & connect one handhole & duct system.
L
Activity PA11 Install and con
one handhole and duct system
Lowest Duration: 2 days
Average Duration: 3 daysHighest Duration: NA
Influencing Factors:
Availability of labor anequipment
-
5/24/2018 FDOT Utility Production Rate Manual
22/31
Phone Page # 16
Adjust one telephone handho le to final grade.
HH
Activity PA12 Adjust one
telephone handhole to final g
Lowest Duration: 0.5 days
Average Duration: 1 dayHighest Duration: 2 days
Influencing Factors:
Need road surveyor to sgrade
Adjust frame & cover for one m anhole
Activity PA13 Adjust frame a
cover for one manhole.
Lowest Duration: 0.5 days
Average Duration: 1 day
Highest Duration: 2 days
Influencing Factors:
Need road surveyor to sgrade
Splice one 900 pair cableActivity PA14 Splice one 900-
cable.
Lowest Duration: 2 days
Average Duration: 3 days
Highest Duration: 5 days
Influencing Factors:
Need two people for thiactivity
Special cut-over
-
5/24/2018 FDOT Utility Production Rate Manual
23/31
Sewer Page # 17
SEWER
Furnish, install & correct 50 L.F. of X-inch PVC F M.
4"
Activity SA01 Furnish, instal
connect fifty linear feet of X-i
PVC SDR.
Lowest Duration: 1 day
Average Duration: 14 daysHighest Duration: 20 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather
Furnish, install & correct 50 L.F. of X-inch PVC F M.
4"
Activity SA02 Furnish, instal
connect fifty linear feet of X-i
PVC FM.
Lowest Duration: 1 day
Average Duration: 14 days
Highest Duration: 20 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather
-
5/24/2018 FDOT Utility Production Rate Manual
24/31
Sewer Page # 18
Remove & replace 50 L.F. of X-inch PVC FM .
50 L.F. 50 L.F.X-inch
Conduit
Activity SA03 Remove and re
fifty linear feet of X-inch PVC
FM.
Lowest Duration: 3 daysAverage Duration: 28 days
Highest Duration: 40 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather Preparation of trench fo
installation
Disposal point for oldmaterials
Sometimes removal canmore time than installat
Plug & place out of service one 8" sanitary sewer main.
8"
Activity SA04 Plug and place
of service one eight-inch sanitsewer main.
Lowest Duration: 2 daysAverage Duration: 4 days
Highest Duration: 30 days
Influencing Factors:
Depth of pipe Soil conditions Permitting Weather Availability of labor an
equipment
-
5/24/2018 FDOT Utility Production Rate Manual
25/31
Sewer Page # 19
Re-route 50 L.F. of X-inch PVC FM.
X-inchConduit
50 L.F.
Activity SA05 Re-route fifty l
feet of X-inch PVC FM.
Lowest Duration: 1 day
Average Duration: 14 daysHighest Duration: 20 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather
Grout & fill one X-inch sanitary sewer lateral for 50'.
X-inchConduit
50 L.F.
Activity SA06 Grout fill one X
inch sanitary sewer lateral fo
fifty linear feet.
Lowest Duration: 3 daysAverage Duration: 4 days
Highest Duration: 6 days
Influencing Factors: Depth of pipe Soil conditions Permitting Weather Availability of labor an
equipment
Contractor availability
-
5/24/2018 FDOT Utility Production Rate Manual
26/31
Sewer Page # 20
Re-route 50 L.F. of X-inch PVC FM.
X-inchConduit
50 L.F.
Activity SA07 Furnish and in
one manhole.
Lowest Duration: 1 day
Average Duration: 4 daysHighest Duration: 8 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather
Adjust frame & cover to grade one manhole. Activity SA08 Adjust ring an
cover to grade for one manho
Lowest Duration: 0.5 days
Average Duration: 1 dayHighest Duration: 2 days
Influencing Factors:
Soil conditions Permitting Weather Availability of labor an
equipment
-
5/24/2018 FDOT Utility Production Rate Manual
27/31
Sewer Page # 21
WATER
Furnish, install, & conn ect 50 L.F. of type K cop per pipe.
Activity WA01 Furnish, insta
and connect fifty linear feet o
Type K copper pipe.
Lowest Duration: 1 day
Average Duration: 5 daysHighest Duration: 20 days
Influencing Factors:
Clearing and grubbing Ordering the
material/Fabrication
Availability of labor anequipment
Soil conditions DOT permits Weather
Cut & plug one x-inch pipe.ActivityWA02 Cut and plug o
X-inch pipe.
Lowest Duration: 0.5 days
Average Duration: 2 days
Highest Duration: 8 days
Influencing Factors:
Depth of pipe Soil conditions Permitting Weather Availability of labor an
equipment
-
5/24/2018 FDOT Utility Production Rate Manual
28/31
Sewer Page # 22
Adjust one water valve box to grade.Activity WA03 Adjust one wa
valve box to grade.
Lowest Duration: 0.25 days
Average Duration: 0.5 daysHighest Duration: 2 days
Influencing Factors:
Soil conditions Permitting Weather Availability of labor an
equipment
X-inchConduit
Adjust one X-inch water main. Activity WA04 Adjust one X-WM.
Lowest Duration: 0.25 days
Average Duration: 1 day
Highest Duration: 4 days
Influencing Factors:
Clearing and grubbing Availability of labor an
equipment
Soil conditions DOT permits Weather Length of adjustment Vertical or horizontal
adjustment
-
5/24/2018 FDOT Utility Production Rate Manual
29/31
Sewer Page # 23
Activity WA05 Remove and
replace fifty linear feet of X-i
WM.
Lowest Duration: 0.5 daysAverage Duration: 1 day
Highest Duration: 5 days
Influencing Factors:
Soil conditions Permitting Weather Availability of labor an
equipment
Remove & replace one fire hydrant assembly.ActivityWA06 Furnish and in
one fire hydrant assembly.
Lowest Duration: 0.5 days
Average Duration: 3 daysHighest Duration: 10 days
Influencing Factors: Availability of assembli Perpendicular or paralle
water main
Permitting Weather
Availability of labor and equip
-
5/24/2018 FDOT Utility Production Rate Manual
30/31
Sewer Page # 24
Remove & replace one fire hydrant assembly.Activity WA07 Remove and
replace one fire hydrant assem
Lowest Duration: 1 day
Average Duration: 6 daysHighest Duration: 16 days
Influencing Factors:
Availability of assembli Perpendicular or paralle
water main
Permitting Weather Availability of labor an
equipment
Removal time Removal of concrete bl
the elbow
Remove & replace one water meter
Activity WA08 Remove and
replace one water meter.
Lowest Duration: 1 dayAverage Duration: 3 days
Highest Duration: 4 days
Influencing Factors:
Soil conditions Permitting Weather Availability of labor an
equipment
-
5/24/2018 FDOT Utility Production Rate Manual
31/31
Sewer Page # 25
Relocate one water meter
Activity WA09 Relocate one w
meter.
Lowest Duration: 1 day
Average Duration: 3 daysHighest Duration: 4 days
Influencing Factors:
Soil conditions Permitting Weather Availability of labor an
equipment