    FDOT UTILITY RELOCATION SCHEDULE

    MANUAL

    June 12th, 2001

  • 5/24/2018 FDOT Utility Production Rate Manual

    2/31

    FDOT UTILITY RELOCATION

    SCHEDULE MANUAL

    Dr. Ralph D. Ellis Jr., P.E. Principal Investigator

    [email protected]

    Jennifer W. Shannon, E.I. Research Assistant

    Michael Shane Johnson Research Assistant

    Benjamin S. Yang, E.I. Research Assistant

    Barry D. Guertin, E.I. Research Assistant

    Department of Civil & Costal Engineering

    College of Engineering

    UNIVERSITY OF FLORIDAGainesville

  • 5/24/2018 FDOT Utility Production Rate Manual

    3/31

    INTRODUCTION

    The researchers at the University of Florida would like to thank John Shriner of the Florida

    Department of Transportation for allowing them to work on this project. It is hoped that thismanual will be a helpful guide to professionals who are interested in the duration of utility

    relocation and installation operations. Although this manual is not the final word in utilities

    scheduling it is hoped that you will find it useful and that it will provide you with a betterunderstanding of the time requirements for utilities operations.

    Respectfully:

    Ralph D. Ellis Jr. P.E.

    Jennifer W. Shannon, E.I.Michael Shane Johnson

    Benjamin Yang, E.I.Barry D. Guertin, E.I.

  • 5/24/2018 FDOT Utility Production Rate Manual

    4/31

    BACKGROUND

    FDOT scheduling engineers need a reliable reference for estimating the duration of different

    utility relocations encountered on FDOT construction projects. The type of utility work involved

    on a project may vary considerably. FDOT projects can involve everything from fiber optic

    systems to conventional storm drainage, often with many different utility systems involved in asingle project. This manual is intended to be the beginning of a comprehensive information base

    for estimating utility production rates and activity duration.

    The University of Florida was under contract with the FDOT to create this Utility Production

    Rate Scheduling Reference for FDOT Construction Projects. The research team used the

    following research approach:

    Approached members of the utility industry to develop a list of common utility activities. Developed list of common utility activities from FDOT utility relocation schedules Verified the list of common utility activities with FDOT district utility engineers Obtained low, average, and high durations and influencing factors for items on the list of

    common utility activities from different utility companies and means manuals Compared the information from the utility companies with the data from the utility

    relocation schedules and means manuals

    For more information on the research process, please see the document Development of a UtilityProduction Rate Scheduling Reference for FDOT Construction Projects.

    This estimating reference presents production rates for utility work activities within the contextof FDOT projects. The range of times and influencing factors for the activities can serve as

    adjustment factors for a scheduling engineer. However, anyone who uses this manual must note

    that the durations for the activities included in this manual are on-site construction times only!The time necessary to acquire permits and to design a utility relocation is not included in this

    manual. The focus of this research was to find construction times and that is what is included inthis manual.

  • 5/24/2018 FDOT Utility Production Rate Manual

    5/31

    Table of Contents

    CABLE ........................................................................................................................................... 1Activity CA01 Adjust or replace one fiber optic aerial cable..................................................... 1

    Activity CA02 Place and pull new coaxial cable through a four-inch duct................................ 1

    Activity CA03 Splice and activate new coaxial cable. ............................................................... 1

    Activity CA04 Directional bore 100 feet for a four-inch duct.................................................... 2Activity CA05 Relocate three fiber overhead cables to new poles. ........................................... 2

    Activity CA06 Remove one existing underground amplifier and power supply........................ 2

    Activity CA07 Remove existing overhead cable per 100-feet. .................................................. 3Activity CA08 Remove existing cable crossing per span........................................................... 3

    ELECTRIC ..................................................................................................................................... 4

    Activity OE01 Relocate per span one 13kV line. ....................................................................... 4Activity OE02 Relocate one pole for 12.47 kV line................................................................... 4

    Activity OE03 Remove one overhead electric crossing for a 13.2 kV line................................ 5

    ActivityOE04 Remove fifty feet of aerial cable. ........................................................................ 5ActivityOE05 Provide service for street light load center (480 V). ........................................... 5

    Activity OE06 Remove poles for an aerial crossing................................................................... 6Activity OE07 Provide service for traffic signal (120 V)........................................................... 6

    Activity UE01 Remove three buried cables per fifty feet........................................................... 6Activity UE02 Place duct bank X by Y of Z-inch conduit per fifty feet. ................................... 7

    ActivityUE03 Remove 3-100 mm conduits for fifty feet. .......................................................... 7

    Activity UE04 Adjust existing electric conduits. ....................................................................... 8ActivityUE05 Place pre-cast manhole. ....................................................................................... 8

    GAS................................................................................................................................................. 9

    Activity GA01 Protect and support ten linear feet of one low-pressure gas line. ...................... 9Activity GA02 Adjust one two-inch steel pipe........................................................................... 9

    Activity GA03 Lower one service line in place.................................................................... 9

    Activity GA04 Install one new two-inch gas line per fifty linear feet...................................... 10Activity GA05 Install one bottom-out connection for one four-inch gas main........................ 10

    Activity GA06 Place out of service one four-inch gas line per fifty linear feet. ...................... 10Activity GA07 Lower one high-pressure gas line. ................................................................... 11

    Activity GA08 Encase one high-pressure gas line. .................................................................. 11

    PHONE ......................................................................................................................................... 12

    Activity PA01 Install and splice 100 linear feet of buried copper cable. ................................. 12Activity PA02 Install and splice 100 linear feet of buried fiber cable...................................... 12

    Activity PA03 Install and splice 100 linear feet of aerial copper cable.................................... 12

    Activity PA04 Install and splice 100 linear feet of aerial fiber cable....................................... 13Activity PA05 Install and splice 100 linear feet of copper cable in conduit. ........................... 13

    Activity PA06 Install and splice 100 linear feet of fiber cable in conduit................................ 13Activity PA07 Place fifty feet of X-pair cable out of service................................................... 14Activity PA08 Place (1) 4 sched. 40 PVC conduit out of service........................................... 14

    Activity PA09 Place (1) 4 sched. 40 PVC conduit in service................................................. 15

    Activity PA10 Lower fifty linear feet of X-pair cable.............................................................. 15Activity PA11 Install and connect one handhole and duct system........................................... 15

    Activity PA12 Adjust one telephone handhole to final grade. ................................................. 16

    Activity PA13 Adjust frame and cover for one manhole. ........................................................ 16

  • 5/24/2018 FDOT Utility Production Rate Manual

    6/31

    Activity PA14 Splice one 900-pair cable.................................................................................. 16

    SEWER......................................................................................................................................... 17Activity SA01 Furnish, install, and connect fifty linear feet of X-inch PVC SDR. ................. 17

    Activity SA02 Furnish, install, and connect fifty linear feet of X-inch PVC FM. ................... 17

    Activity SA03 Remove and replace fifty linear feet of X-inch PVC FM................................. 18

    Activity SA04 Plug and place out of service one eight-inch sanitary sewer main. .................. 18Activity SA05 Re-route fifty linear feet of X-inch PVC FM. .................................................. 19

    Activity SA06 Grout fill one X-inch sanitary sewer lateral for fifty linear feet....................... 19

    Activity SA07 Furnish and install one manhole. ...................................................................... 20Activity SA08 Adjust ring and cover to grade for one manhole. ............................................. 20

    WATER ........................................................................................................................................ 21

    Activity WA01 Furnish, install, and connect fifty linear feet of Type K copper pipe. ............ 21ActivityWA02 Cut and plug one X-inch pipe. ......................................................................... 21

    Activity WA03 Adjust one water valve box to grade............................................................... 22

    Activity WA04 Adjust one X-inch WM................................................................................... 22Activity WA05 Remove and replace fifty linear feet of X-inch WM. ..................................... 23

    ActivityWA06 Furnish and install one fire hydrant assembly.................................................. 23Activity WA07 Remove and replace one fire hydrant assembly.............................................. 24

    Activity WA08 Remove and replace one water meter. ............................................................ 24Activity WA09 Relocate one water meter. ............................................................................... 25

  • 5/24/2018 FDOT Utility Production Rate Manual

    7/31

    Cable Page # 1

    CABLE

    Adjustment or replacement one fiber optic aerial cable.

    Adjustment

    Current

    Activity CA01 Adjust or repl

    one fiber optic aerial cable.

    Lowest Duration: 4 hoursAverage Duration: 5 hours

    Highest Duration: 6 hours

    Influencing Factors:

    type of pole energized or de-energiz

    cable

    drilling time

    Place & pull new coax cable through 4" conduit

    4"

    Activity CA02 Place and pullcoaxial cable through a four-

    duct.

    Lowest Duration: 5 daysAverage Duration: 6 days

    Highest Duration: 10 days

    Influencing Factors:

    Soil conditions Location of other utiliti

    Splice & activate new coax cable

    Activity CA03 Splice and acti

    new coaxial cable.

    Lowest Duration: 5 daysAverage Duration: 6 days

    Highest Duration: 10 days

    Influencing Factors: Location of coaxial cab Location of other utiliti Number of people on cr Available equipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    8/31

    Cable Page # 2

    Activity CA04 Directional bo

    100 feet for a four-inch duct.

    Lowest Duration: 1 day

    Average Duration: 2 daysHighest Duration: 4 days

    Influencing Factors:

    Soil conditions Known or unknown util

    locations

    Any failed attempts for successful directional b

    Relocate 3 fiber optic aerial cables to new poles Activity CA05 Relocate threeoverhead cables to new poles.

    Lowest Duration: 6 hours

    Average Duration: 12 hoursHighest Duration: 18 hours

    Influencing Factors:

    Type of pole Number of attachments

    pole

    Energized or de-energizcable

    Remove on e exisiting underground amplifier & power supply

    Activity CA06 Remove one

    existing underground amplifi

    and power supply.

    Lowest Duration: NA

    Average Duration: 1 day

    Highest Duration: NA

    Influencing Factors:

    Soil conditions Location of other utiliti

  • 5/24/2018 FDOT Utility Production Rate Manual

    9/31

    Cable Page # 3

    Remove existing OH cable per 100 ft.

    100 L.F. 100 L.F.

    Activity CA07 Remove existin

    overhead cable per 100-feet.

    Lowest Duration: 0.4 hours

    Average Duration: 0.5 hoursHighest Duration: 0.7 hours

    Influencing Factors:

    Traffic Energized or de-energiz

    cable

    Location of other utiliti Street crossings

    Remove existing OH per crossing span

    Roadway

    Activity CA08 Remove existincable crossing per span.

    Lowest Duration: 0.8 hours

    Average Duration: 1.0 hour

    Highest Duration: 1.4 hours

    Influencing Factors:

    Traffic Energized or de-energiz

    cable

    Location of other utiliti Street crossings

  • 5/24/2018 FDOT Utility Production Rate Manual

    10/31

    ELECTRICAL Page # 4

    ELECTRIC

    Relocate per span one 13 kV line.

    Activity OE01 Relocate per sp

    one 13kV line.

    Lowest Duration: 0.5 days

    Average Duration: 1 dayHighest Duration: 10 days

    Influencing Factors:

    Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination

    Activity OE02 Relocate one p

    for 12.47 kV line.

    Lowest Duration: 0.5 days

    Average Duration: 2 daysHighest Duration: 5 days

    Influencing Factors:

    Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination

  • 5/24/2018 FDOT Utility Production Rate Manual

    11/31

    ELECTRICAL Page # 5

    Remove 50 ft. Aerial cable.

    50 '

    Activity OE03 Remove one

    overhead electric crossing for

    13.2 kV line.

    Lowest Duration: 1 dayAverage Duration: 2 days

    Highest Duration: 4 days

    Influencing Factors:

    Crew availability Truck access Type of pole Pole mounted equipmen Outage coordination req MOT coordination

    Remove 50 ft. Aerial cable.

    50 '

    ActivityOE04 Remove fifty fe

    aerial cable.

    Lowest Duration: 0.5 days

    Average Duration: 1 day

    Highest Duration: 2 days

    Influencing Factors:

    Crew availability Truck access Outage coordination req MOT coordination

    Provide service for Street light load center (480 V)

    street light load center

    Activity OE05 Provide servic

    street light load center (480 V

    Lowest Duration: 1 day

    Average Duration: 3 days

    Highest Duration: 10 days

    Influencing Factors:

    Crew availability Truck access Type of line work requi MOT coordination

  • 5/24/2018 FDOT Utility Production Rate Manual

    12/31

    ELECTRICAL Page # 6

    Remove poles for aerial crossing

    Activity OE06 Remove poles

    an aerial crossing.

    Lowest Duration: 1 dayAverage Duration: 2 days

    Highest Duration: 4 days

    Influencing Factors:

    Crew availability Truck access MOT coordination Type of pole Disposal of pole

    Provide Service for traffic Siginal (120 V)

    Traffic control device

    Activity OE07 Provide servic

    traffic signal (120 V).

    Lowest Duration: 1 day

    Average Duration: 3 daysHighest Duration: 10 days

    Influencing Factors:

    Crew availability Truck access Line work required MOT coordination

    Remove 3 buried cable per 50 L.F.

    50 L.F.

    Activity UE01 Remove three

    buried cables per fifty feet.

    Lowest Duration: 1 day

    Average Duration: 2 daysHighest Duration: 5 days

    Influencing Factors:

    Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin

    required

  • 5/24/2018 FDOT Utility Production Rate Manual

    13/31

    ELECTRICAL Page # 7

    Place duct bank X by Y of Z inch conduit for 50 L.F.

    50 L.F. X

    Conduits width

    Y tall Z inches

    Activity UE02 Place duct ban

    by Y of Z-inch conduit per fif

    feet.

    Lowest Duration: 1 day

    Average Duration: 2 daysHighest Duration: 5 days

    Influencing Factors:

    Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin

    required

    Remove 3 buried cable per 50 L.F.

    50 L.F.

    ActivityUE03 Remove 3-100 m

    conduits for fifty feet.

    Lowest Duration: 1 day

    Average Duration: 2 days

    Highest Duration: 5 days

    Influencing Factors:

    Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin

    required

  • 5/24/2018 FDOT Utility Production Rate Manual

    14/31

    ELECTRICAL Page # 8

    Adjust existing electrical conduits.Activity UE04 Adjust existing

    electric conduits.

    Lowest Duration: 1 day

    Average Duration: 2 daysHighest Duration: 5 days

    Influencing Factors:

    Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin

    required

    Ability to switch cable

    Adjust frame & cover for one m anhole

    ActivityUE05 Place pre-cast

    manhole.

    Lowest Duration: 2 days

    Average Duration: 5 days

    Highest Duration: 10 days

    Influencing Factors:

    Crew availability Site conditions Ground water level Quality of soil Outage or MOT coordin

    required

    Location of manhole Number of surrounding

    utilities

    Placement into pavemengrass

  • 5/24/2018 FDOT Utility Production Rate Manual

    15/31

    Gas Page # 9

    GAS

    Protect & Support 10 L.F. of one low pressure gas line

    10 L.F.

    Trench

    Activity GA01 Protect and

    support ten linear feet of one

    pressure gas line.

    Lowest Duration: 0.5 days

    Average Duration: 1 dayHighest Duration: 2 days

    Influencing Factors:

    Open excavation Providing temporary su Site conditions Weather conditions Type of material Shoring equipment

    Adjust one 2" steel pipe

    2"

    Activity GA02 Adjust one tw

    inch steel pipe.

    Lowest Duration: 1 day

    Average Duration: 2 daysHighest Duration: 4 days

    Influencing Factors:

    Length to move Pressure Need to make stops and

    in pipe

    Lower one 3/4" steel pipe

    3/4"

    Activity GA03 Lower one

    service line in place.

    Lowest Duration: 1 dayAverage Duration: 1 day

    Highest Duration: 2 days

    Influencing Factors:

    Site conditions Restoration of service Involvement of road cro

  • 5/24/2018 FDOT Utility Production Rate Manual

    16/31

    Gas Page # 10

    Activity GA04 Install one new

    two-inch gas line per fifty line

    feet.

    Lowest Duration: 0.5 daysAverage Duration: 1 day

    Highest Duration: 2 days

    Influencing Factors:

    Open trench Site conditions Type of pipe

    Bottom OutDerby.

    90 Ell.

    New lin e.

    Line being tappedor stopped.

    Installation of bottom out connection.

    Activity GA05 Install one botout connection for one four-in

    gas main.

    Lowest Duration: 0.5 daysAverage Duration: 2 days

    Highest Duration: 4 days

    Influencing Factors:

    Site conditions Weather Welding Material and supplies

    Place out of service one 4" ga s line per 50 ft.

    4"

    50 L.F.

    Activity GA06 Place out of se

    one four-inch gas line per fift

    linear feet.

    Lowest Duration: 0.5 days

    Average Duration: 2 days

    Highest Duration: 4 days

    Influencing Factors:

    Length of main to purge Type of material for ma Involvement of custome Installation of stoppers

    each end

  • 5/24/2018 FDOT Utility Production Rate Manual

    17/31

    Gas Page # 11

    Lower one high pressure gas line.Activity GA07 Lower one hig

    pressure gas line.

    Lowest Duration: 1 day

    Average Duration: 3 daysHighest Duration: 6 days

    Influencing Factors:

    Type of material for lin Open excavation Location of other utiliti

    Encase one high-pressure gas line

    Activity GA08 Encase one hig

    pressure gas line.

    Lowest Duration: 6 days

    Average Duration: 8 days

    Highest Duration: 10 days

    Influencing Factors:

    Open excavation Installation of casing

  • 5/24/2018 FDOT Utility Production Rate Manual

    18/31

    Phone Page # 12

    PHONE

    Install & splice 100 L.F. of buried copper cab le.

    100 L.F.

    B B B B B B

    Activity PA01 Install and spli

    100 linear feet of buried copp

    cable.

    Lowest Duration: 2 days

    Average Duration: 3 daysHighest Duration: 5 days

    Influencing Factors:

    Special conduit cut-ove Ground conditions

    Activity PA02 Install and spli100 linear feet of buried fiber

    cable.

    Lowest Duration: 2 days

    Average Duration: 3 daysHighest Duration: 5 days

    Influencing Factors:

    Special conduit cut-ove Ground conditions

    Install & splice 100 L .F. of aerial copper cable.

    100 L.F.

    Activity PA03 Install and spli

    100 linear feet of aerial coppe

    cable.

    Lowest Duration: 2 days

    Average Duration: 3 daysHighest Duration: 5 days

    Influencing Factors:

    Special conduit cut-ove Ground conditions

  • 5/24/2018 FDOT Utility Production Rate Manual

    19/31

    Phone Page # 13

    Install & splice 100 L .F. of aerial fiber cable.

    100 L.F.

    Activity PA04 Install and spli

    100 linear feet of aerial fiber

    cable.

    Lowest Duration: 2 daysAverage Duration: 3 days

    Highest Duration: 5 days

    Influencing Factors:

    Special conduit cut-ove Ground conditions

    Install & splice 100 L.F. of copper cable in condu it.

    100 L.F.

    Activity PA05 Install and spli

    100 linear feet of copper cablconduit.

    Lowest Duration: 2 days

    Average Duration: 3 days

    Highest Duration: 5 days

    Influencing Factors:

    Special conduit cut-ove Ground conditions Manhole access Traffic

    Install & splice 100 L .F. of fiber cable in conduit.

    100 L.F.

    Activity PA06 Install and spli

    100 linear feet of fiber cable i

    conduit.

    Lowest Duration: 2 daysAverage Duration: 3 days

    Highest Duration: 5 days

    Influencing Factors: Special conduit cut-ove Ground conditions Manhole access Traffic

  • 5/24/2018 FDOT Utility Production Rate Manual

    20/31

    Phone Page # 14

    Place 50 L.F. x-pair cable out of service.

    50 L.F.

    B X B B B BX X X

    Activity PA07 Place fifty feet

    pair cable out of service.

    Lowest Duration: 2 days

    Average Duration: 3 daysHighest Duration: 5 days

    NOTE: The time for this activ

    included in the splicing work.

    Influencing Factors:

    Special conduit cut-ove Ground conditions Manhole access Traffic

    Place (1) 4" schedule 40 PVC con duit out of service.

    4"

    Activity PA08 Place (1) 4 sch

    40 PVC conduit out of service

    Lowest Duration: 2 days

    Average Duration: 3 days

    Highest Duration: 5 days

    NOTE: The time for this activ

    included in the splicing work.

    Influencing Factors:

    Special conduit cut-ove Ground conditions Manhole access Traffic

  • 5/24/2018 FDOT Utility Production Rate Manual

    21/31

    Phone Page # 15

    Place (1) 4" schedule 40 PVC cond uit in service.

    4"

    Activity PA09 Place (1) 4 sch

    40 PVC conduit in service.

    Lowest Duration: 0.8 days

    Average Duration: 1 dayHighest Duration: 1.2 days

    Influencing Factors:

    Rocks

    Lower 50 L.F. of x-pair cable

    Activity PA10 Lower fifty lin

    feet of X-pair cable.

    Lowest Duration: 1 day

    Average Duration: 2 days

    Highest Duration: 8 days

    Influencing Factors:

    Rocks Must expose 150 of ca

    lower 50

    Install & connect one handhole & duct system.

    L

    Activity PA11 Install and con

    one handhole and duct system

    Lowest Duration: 2 days

    Average Duration: 3 daysHighest Duration: NA

    Influencing Factors:

    Availability of labor anequipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    22/31

    Phone Page # 16

    Adjust one telephone handho le to final grade.

    HH

    Activity PA12 Adjust one

    telephone handhole to final g

    Lowest Duration: 0.5 days

    Average Duration: 1 dayHighest Duration: 2 days

    Influencing Factors:

    Need road surveyor to sgrade

    Adjust frame & cover for one m anhole

    Activity PA13 Adjust frame a

    cover for one manhole.

    Lowest Duration: 0.5 days

    Average Duration: 1 day

    Highest Duration: 2 days

    Influencing Factors:

    Need road surveyor to sgrade

    Splice one 900 pair cableActivity PA14 Splice one 900-

    cable.

    Lowest Duration: 2 days

    Average Duration: 3 days

    Highest Duration: 5 days

    Influencing Factors:

    Need two people for thiactivity

    Special cut-over

  • 5/24/2018 FDOT Utility Production Rate Manual

    23/31

    Sewer Page # 17

    SEWER

    Furnish, install & correct 50 L.F. of X-inch PVC F M.

    4"

    Activity SA01 Furnish, instal

    connect fifty linear feet of X-i

    PVC SDR.

    Lowest Duration: 1 day

    Average Duration: 14 daysHighest Duration: 20 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather

    Furnish, install & correct 50 L.F. of X-inch PVC F M.

    4"

    Activity SA02 Furnish, instal

    connect fifty linear feet of X-i

    PVC FM.

    Lowest Duration: 1 day

    Average Duration: 14 days

    Highest Duration: 20 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather

  • 5/24/2018 FDOT Utility Production Rate Manual

    24/31

    Sewer Page # 18

    Remove & replace 50 L.F. of X-inch PVC FM .

    50 L.F. 50 L.F.X-inch

    Conduit

    Activity SA03 Remove and re

    fifty linear feet of X-inch PVC

    FM.

    Lowest Duration: 3 daysAverage Duration: 28 days

    Highest Duration: 40 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather Preparation of trench fo

    installation

    Disposal point for oldmaterials

    Sometimes removal canmore time than installat

    Plug & place out of service one 8" sanitary sewer main.

    8"

    Activity SA04 Plug and place

    of service one eight-inch sanitsewer main.

    Lowest Duration: 2 daysAverage Duration: 4 days

    Highest Duration: 30 days

    Influencing Factors:

    Depth of pipe Soil conditions Permitting Weather Availability of labor an

    equipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    25/31

    Sewer Page # 19

    Re-route 50 L.F. of X-inch PVC FM.

    X-inchConduit

    50 L.F.

    Activity SA05 Re-route fifty l

    feet of X-inch PVC FM.

    Lowest Duration: 1 day

    Average Duration: 14 daysHighest Duration: 20 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather

    Grout & fill one X-inch sanitary sewer lateral for 50'.

    X-inchConduit

    50 L.F.

    Activity SA06 Grout fill one X

    inch sanitary sewer lateral fo

    fifty linear feet.

    Lowest Duration: 3 daysAverage Duration: 4 days

    Highest Duration: 6 days

    Influencing Factors: Depth of pipe Soil conditions Permitting Weather Availability of labor an

    equipment

    Contractor availability

  • 5/24/2018 FDOT Utility Production Rate Manual

    26/31

    Sewer Page # 20

    Re-route 50 L.F. of X-inch PVC FM.

    X-inchConduit

    50 L.F.

    Activity SA07 Furnish and in

    one manhole.

    Lowest Duration: 1 day

    Average Duration: 4 daysHighest Duration: 8 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather

    Adjust frame & cover to grade one manhole. Activity SA08 Adjust ring an

    cover to grade for one manho

    Lowest Duration: 0.5 days

    Average Duration: 1 dayHighest Duration: 2 days

    Influencing Factors:

    Soil conditions Permitting Weather Availability of labor an

    equipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    27/31

    Sewer Page # 21

    WATER

    Furnish, install, & conn ect 50 L.F. of type K cop per pipe.

    Activity WA01 Furnish, insta

    and connect fifty linear feet o

    Type K copper pipe.

    Lowest Duration: 1 day

    Average Duration: 5 daysHighest Duration: 20 days

    Influencing Factors:

    Clearing and grubbing Ordering the

    material/Fabrication

    Availability of labor anequipment

    Soil conditions DOT permits Weather

    Cut & plug one x-inch pipe.ActivityWA02 Cut and plug o

    X-inch pipe.

    Lowest Duration: 0.5 days

    Average Duration: 2 days

    Highest Duration: 8 days

    Influencing Factors:

    Depth of pipe Soil conditions Permitting Weather Availability of labor an

    equipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    28/31

    Sewer Page # 22

    Adjust one water valve box to grade.Activity WA03 Adjust one wa

    valve box to grade.

    Lowest Duration: 0.25 days

    Average Duration: 0.5 daysHighest Duration: 2 days

    Influencing Factors:

    Soil conditions Permitting Weather Availability of labor an

    equipment

    X-inchConduit

    Adjust one X-inch water main. Activity WA04 Adjust one X-WM.

    Lowest Duration: 0.25 days

    Average Duration: 1 day

    Highest Duration: 4 days

    Influencing Factors:

    Clearing and grubbing Availability of labor an

    equipment

    Soil conditions DOT permits Weather Length of adjustment Vertical or horizontal

    adjustment

  • 5/24/2018 FDOT Utility Production Rate Manual

    29/31

    Sewer Page # 23

    Activity WA05 Remove and

    replace fifty linear feet of X-i

    WM.

    Lowest Duration: 0.5 daysAverage Duration: 1 day

    Highest Duration: 5 days

    Influencing Factors:

    Soil conditions Permitting Weather Availability of labor an

    equipment

    Remove & replace one fire hydrant assembly.ActivityWA06 Furnish and in

    one fire hydrant assembly.

    Lowest Duration: 0.5 days

    Average Duration: 3 daysHighest Duration: 10 days

    Influencing Factors: Availability of assembli Perpendicular or paralle

    water main

    Permitting Weather

    Availability of labor and equip

  • 5/24/2018 FDOT Utility Production Rate Manual

    30/31

    Sewer Page # 24

    Remove & replace one fire hydrant assembly.Activity WA07 Remove and

    replace one fire hydrant assem

    Lowest Duration: 1 day

    Average Duration: 6 daysHighest Duration: 16 days

    Influencing Factors:

    Availability of assembli Perpendicular or paralle

    water main

    Permitting Weather Availability of labor an

    equipment

    Removal time Removal of concrete bl

    the elbow

    Remove & replace one water meter

    Activity WA08 Remove and

    replace one water meter.

    Lowest Duration: 1 dayAverage Duration: 3 days

    Highest Duration: 4 days

    Influencing Factors:

    Soil conditions Permitting Weather Availability of labor an

    equipment

  • 5/24/2018 FDOT Utility Production Rate Manual

    31/31

    Sewer Page # 25

    Relocate one water meter

    Activity WA09 Relocate one w

    meter.

    Lowest Duration: 1 day

    Average Duration: 3 daysHighest Duration: 4 days

    Influencing Factors:

    Soil conditions Permitting Weather Availability of labor an

    equipment