fets meeting, 1st november 2006 peter savage the front end test stand collaboration 1 the mechanical...
TRANSCRIPT
FETS meeting, 1st November 2006
Peter Savage
1
The Front End Test Stand Collaboration
The mechanical engineering design of the Mk II emittance measurement device.
FETS meeting, 1st November 2006
Peter Savage
2
The Front End Test Stand Collaboration
Mk I Emittance Scanner
_____________________________________________________________________
Isometric view of the Mk I emittance scanner that was designed to fit on the ion source test bench at the Rutherford Appleton Laboratory.
Support rods
The ion source test facility vacuum tank
CameraMoving rod
Window
Head
Mounting flange
FETS meeting, 1st November 2006
Peter Savage
3
The Front End Test Stand Collaboration
_____________________________________________________
The complete assembly mounted on the stainless steel flange.
Mk I Emittance Scanner
FETS meeting, 1st November 2006
Peter Savage
4
The Front End Test Stand Collaboration
Mk I Emittance Scanner – Head Design
Exploded view of the head assembly
Sliced view of the assembled head
10mm thick copper grid with a 25 x 25 array of 2mm diameter holes on a 3mm pitch.
0.3mm thick tungsten grid with 100 micron diameter holes
Scintillator
FETS meeting, 1st November 2006
Peter Savage
5
The Front End Test Stand Collaboration
Vacuum leak due to damage on sealing faces
___________________________________
Damage to the inner rod sealing ring, approx. 0.5mm wide and 0.5mm deep.
___________________________________
The rod has a scratch, approx. 05mm wide, 0.1mm deep, 30mm long.
FETS meeting, 1st November 2006
Peter Savage
6
The Front End Test Stand Collaboration
Mk I was built and used successfully but also has experienced a few problems.
It has been decided that we would benefit from a brand new emittance scanner with improvements made from what we have learned from the MkI. These improvements can be broadly split into three categories:
1) Stiffer support structure – apart from the obvious problems related to movement of the camera when mounted to a weak structure, I believe that the damage shown on the previous slide was due to the moving rod coming into contact with the main flange due to bending of the support structure.
2) Cooled head with a larger grid area – the MkI grid had 625 holes (25 x 25 array) on a 3mm pitch and hence covering 72mm square. This is less than the beam size. Also, damage appeared on the grid due to localised heating by the beam. While beam power is low there is no convection mechanism to cool the grids and so the MkII will have an active cooling system.
3) Improved vacuum seal – before the MkI became damaged the sealing onto the moving rod was working well but an improved vacuum design will be employed for the MkII that will also assist the cooling design.
Mk I Emittance Scanner – Conclusion
FETS meeting, 1st November 2006
Peter Savage
7
The Front End Test Stand Collaboration
The Mechanical Engineering Design of the Mk II emittance measurement
device.
FETS meeting, 1st November 2006
Peter Savage
8
The Front End Test Stand Collaboration
Mk II Emittance Scanner
Light port Handle to be replaced with stepper motor
Bellows mount + window clamp
FETS meeting, 1st November 2006
Peter Savage
9
The Front End Test Stand Collaboration
_____________________________________________________________________
Mk II Emittance Scanner – Head design
Tungsten Grid
Glidcop Grid
(aluminium dispersion strengthened copper)
Copper grid cooling channel closing plate
Scintillator Grid
Moving Rod with keyway
Cooling Rods
End plates
KF50 Flange
FETS meeting, 1st November 2006
Peter Savage
10
The Front End Test Stand Collaboration
_____________________________________________________________________
With this design there are no removable water joints exposed to vacuum and no moving parts sliding through vacuum seals as in the MkI design.
Mk II Emittance Scanner – vacuum seal
KF50 flange to be welded directly onto stainless steel flange
KF50 flanges joined via bellows similar to those shown here from UHV Design
FETS meeting, 1st November 2006
Peter Savage
11
The Front End Test Stand Collaboration
DO WE NEED COOLING AND IF SO, IN WHAT FORM?
FETS meeting, 1st November 2006
Peter Savage
12
The Front End Test Stand Collaboration
First Simple Model
Model parameters:
Beam Power = 36 W
Material: Copper
Block dimensions: L 100mm x W 100mm x H 100mm
Cooling channel radius 10mm
Ambient Temperature = 25C
Cooling water temperature = 20C, forced convection
Radiation ignored
To investigate whether we need active cooling for the MkII emittance measurement device we can use FEA. First we will consider a copper block, being impacted by beam and being cooled by water.
Beam power
Copper block
Cooling water
FETS meeting, 1st November 2006
Peter Savage
13
The Front End Test Stand Collaboration
First Simple Model
Model parameters:
Beam Power = 36 W
Material: Copper
Block dimensions: L 100mm x W 100mm x H 100mm
Cooling channel radius 10mm
Ambient Temperature = 25C
Cooling water temperature = 20C, forced convection
Radiation ignored
n1
n2
n3
n4
e1
e2
e3
The model as shown in figure 1 can be shown in it’s simplest form as in figure 2. This can be modelled using simple link elements and can also be solved using matrices and hence acts as a verification model.
The simple 1D model from figure 2 was then expanded to the 2D form as shown in figure 3 to better illustrate the effect of the beam power and the cooling.
Figure 1. A simple model with symmetry
Figure 2. A 1D model with link elements.
Figure 2. A 2D model using PLANE55 elements
FETS meeting, 1st November 2006
Peter Savage
14
The Front End Test Stand Collaboration
Calculating convection coefficient for cooling
FETS meeting, 1st November 2006
Peter Savage
15
The Front End Test Stand Collaboration
Calculating convection coefficient for cooling
FETS meeting, 1st November 2006
Peter Savage
16
The Front End Test Stand Collaboration
Nodal temperatures
After 1 minute:
Tmax = 24.8°C
Tmin = 23.6°C
Nodal temperatures
After 10 minutes:
Tmax = 22.7°C
Tmin = 21.8°C
Nodal temperatures
After 30 hours:
Tmax = Tmin = 1198°C
First Simple Model – cooled, radiation ignored
For a beam power of 36W, cooling water temperature of 20°C, initial temperatures of 25°C throughout (and convection coefficient of 3000W/m2.K). After about 6 minutes the block cooling reaches a thermal equilibrium with the beam power. With cooling switched off, after about 30 hours the OFC block will exceed the melting temperature of 1082°C.
Water cooled @ 20°C Water cooled @ 20°C No cooling
Temperature change with time for nodes along the right hand edge (representing the centre of the 2D model).
FETS meeting, 1st November 2006
Peter Savage
17
The Front End Test Stand Collaboration
Emittance Measurement Device – 36W for one hour
Conclusion: A cooled rod or grid allows a thermal equilibrium to be reached. It is recommended that for either cooled solution a time of approx 2000 seconds / 30 minutes is
allowed to elapse before taking data to let the grid stabilise.
No cooling Rod water cooling alone Grid water cooling alone
Tmax = 60.0°C
Tmin = 43.7°C
Tmax = 37.0°C
Tmin = 25.0°C
Tmax = 22.2°C
Tmin = 20.2°C
FETS meeting, 1st November 2006
Peter Savage
18
The Front End Test Stand Collaboration
Displacement due to heating - cooled grid
Maximum displacement
in X direction = 0.018mm
Maximum displacement
in Y direction = 0.041mm
FETS meeting, 1st November 2006
Peter Savage
19
The Front End Test Stand Collaboration
THE RESULTS FROM THE THERMAL CALCULATIONS HAVE PROMPTED THE
DEVELOPMENT OF A NEW DESIGN
FETS meeting, 1st November 2006
Peter Savage
20
The Front End Test Stand Collaboration
Simplified cooling scheme
Mk II Emittance Scanner – revised
Improved camera mount
Rod mounts optimised for strength versus size to allow for motor to be mounted close to the main flange
Tip / tilt stage
Translation stage
The combination of the tip / tilt stage with translation stages for X and Z and a custom translation adjustment for Y creates a system that is adjustable for all six degrees of freedom.
Z
Y
X
FETS meeting, 1st November 2006
Peter Savage
21
The Front End Test Stand Collaboration
UHV Design
_____________________________________________________________________
The search for a long travel edge welded vacuum bellows led me to this company called UHV design.
FETS meeting, 1st November 2006
Peter Savage
22
The Front End Test Stand Collaboration
LSML64/35 700SD Linear Shift Mechanism
_____________________________________________________________________
Side and end elevations of the LSML64 from UHV Design
FETS meeting, 1st November 2006
Peter Savage
23
The Front End Test Stand Collaboration
Quote From UHV Design
_____________________________________________________________________
UHV design will also be quoting for cooling using their support tube and for electrical feed-throughs for strain gauges.
Item
Qty Part Number Description Price Each £
A 1 LSML64/35-700-SD
Long travel linear shift mechanism mounted on a CF64 (4-1/2" OD CF) flange with a CF35 (2-3/4” OD CF) travelling flange. Both flange have metric tapped boltholes. 700mm stroke. 38mm bore bellows (this is reduced with the support tube fitted). Price includes a bellows support tube, demountable bellows assembly, a side-mounted DC motor and timing belt cover. Price also includes pre-wired bakeable limit switches.
£7,573.00
B 1 SADC Bench-mounted DC motor controller for Item A.
£404.00
C 1 EWB-3044-1 316L bellows assembly with CF35 (2-3/4” OD CF) flanges. 700mm stroke. 39mm ID x 59mm OD. Bellows length = 154.0-854.0mm plus flanges and tubes. 10,000 cycle lifetime.
£1,628.00
FETS meeting, 1st November 2006
Peter Savage
24
The Front End Test Stand Collaboration
New design with LSML
_____________________________________________________________________
The new design showing just the bellows from the LSML.
FETS meeting, 1st November 2006
Peter Savage
25
The Front End Test Stand Collaboration
Conclusions:
•Purchasing the LSML from UHV Design will reduce the manufacturing effort and will provide a proven working system that will reduce ‘fine tuning’ time dramatically.
•The cost of the LSML purchase may not prove to be significantly less than the cost to manufacture my design.
•The remaining design work and manufacture for the main flange, the camera mount and grid + grid mount can proceed in parallel with the manufacture of the LSML.