final chapter 5 live cases

Upload: mina-safwat-oosa

Post on 03-Apr-2018

226 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Final Chapter 5 Live Cases

    1/12

    Chapter 5 live cases

    Page 45

    CHAPTER 5

    LIVE CASES

  • 7/28/2019 Final Chapter 5 Live Cases

    2/12

    Chapter 5 live cases

    Page 46

    In this chapter we will present few live cases of damaged concrete structures

    which require a serial of repair and strengthening procedures these structures

    includes residential building, hotels and bridges and it have different levels of

    damages varies between major and minor damages.

    Figure5- 1 Building that need's repair

    5.1. Repair of residential building

    5.1.1. Structure

    Three storing residential building located in New Cairo district, the building is still

    under-construction, it is still in the skeleton form.

    5.1.2. Material used

    The material used are; cement of high compressive strength (higher than the one

    previously used in construction) and reinforcing steel bars.

  • 7/28/2019 Final Chapter 5 Live Cases

    3/12

    Chapter 5 live cases

    Page 47

    5.1.3. Project scope

    In this building damages are detected after the removal of the wooden forms the

    damage was presented as (figure2, 3, and 4)

    5.1.3.1Causes of repair

    Figure5- 2longitudinal crack Figure5-3spalling of concrete coversAnd appearof RFT

    Figure5- 4 longitudinal crack due to construction and structural defects

  • 7/28/2019 Final Chapter 5 Live Cases

    4/12

    Chapter 5 live cases

    Page 48

    Figure5- 5 Figure5- 6Buckling of column due to high

    compressive forces

    5.1.4.Repair procedures

    Splitting cracks due to buckling of column

    5.1.4.1.Repair of column by using (concrete jacket)

    1. The slab is lifted up by wooden sections to remove the load from column

    Figure5- 7 First step lifting up the slab with wood to be able to remove concrete cover

  • 7/28/2019 Final Chapter 5 Live Cases

    5/12

    Chapter 5 live cases

    Page 49

    2. Cover is removed and steel bars have been inserted into old slab by epoxy to

    welded thenew additional RFT to it (fig5-7)

    Figure5- 8 Bonded steel bars

    3. Creating voids in the slab to insert new RFT of the column into the slab to

    increase the bond between the columns and to make the process of purring

    concrete into shutter easier.

    Figure5- 9 Breaking the slab to insert new RFT into it

  • 7/28/2019 Final Chapter 5 Live Cases

    6/12

    Chapter 5 live cases

    Page 50

    4. After cleaning the surface insert new additional RFT and additional

    stirrups that preferred to be box stirrup to increase the bond then make

    the new shutter of the column from one or more sides according to

    repair design then pure the new concrete into column jacket.

    Figure5- 10 Concrete jacket from one or more sides

    Figure5- 11 Increase in the section dimensions of column after repair

  • 7/28/2019 Final Chapter 5 Live Cases

    7/12

    Chapter 5 live cases

    Page 51

    5.1.4.2. Strengthening of the first slab using section enlargement

    Some elements were not in need to repair such as first floor it has small deflection

    thats not critical; we insert new top RFT then cover it with a layer of concrete.

    Figure5- 12 slab of first floor before and after adding additional top RFT

    5.1.4.3. Reconstruction of the second and third floor slabs

    1. Lift up the repaired slab by wooden sections to avoid slab collapse.

    Figure5- 13 Slab lifted by wooden sections

  • 7/28/2019 Final Chapter 5 Live Cases

    8/12

    Chapter 5 live cases

    Page 52

    2. Remove base concrete and prepare the connection between slabs and columns

    Figure5- 14Removing old concrete

    3. Make sure of Cleaning RFT from old concrete and ducts of electric wires.

    Figure5- 15 Clean the main RFT of embedded beam from concrete

  • 7/28/2019 Final Chapter 5 Live Cases

    9/12

    Chapter 5 live cases

    Page 53

    4. Build up the new shutter of the slab in the same level of floor then insert electric

    ducts

    Figure5- 16 Wooden forms from in and out sides

    5. Pour concrete into shutter then remove wooden forms after harden of reinforced

    concrete.

    Figure5- 18 Curing surface of new concrete slab

  • 7/28/2019 Final Chapter 5 Live Cases

    10/12

    Chapter 5 live cases

    Page 54

    5.2. Repair of Hotel Concrete Balcony Columns

    Concrete can crack and experience vertical stress under the most unexpected

    circumstances affecting the structural building integrity and requiring immediaterepair. When these situations occur in buildings used by the public, such as

    restaurants and hotels, repairs must be aesthetically pleasing and not raise public

    concern related to the buildings safety. In this case, concrete columns were pulling

    away from the balconies.

    5.2.1. Structure

    Grande Shores Ocean Resort, Myrtle Beach, South Carolina this is a 7-story resorthotel on the Atlantic beachfront. It is constructed using standard concrete skeleton

    method.

    5.2.2. Material Used

    Pre-cured Pre-preg w/peel-ply column wrap vacuum laminated; Designed by

    layout of job scope; Laminated with (#4020) Epoxy.

    5.2.3. Project Scope

    Concrete columns faade were pulling away from the balconies. Challenge was to

    strap and reinforce columns, yet make reinforcement aesthetically pleasing.

    Figure5 - 19 Repair of hotel column

  • 7/28/2019 Final Chapter 5 Live Cases

    11/12

    Chapter 5 live cases

    Page 55

    5.2.4. SolutionPre-preg column wraps allowed for fast installation, completing project with

    minimal disruption and prior to hotels busy season. With this method they werestill able to function with only a small area of rooms closed off to public

    Original design was to install 200 lb steel plates that would have added significant

    weight, would not have been aesthetically pleasing and would have closed a large

    area of the hotel losing them revenue.

    Figure 5- 20 side view of concrete balcony columns

    Figure5- 21 Elevation of concrete balcony columns

  • 7/28/2019 Final Chapter 5 Live Cases

    12/12

    Chapter 5 live cases

    Page 56

    5.3.Highway-Bridge, Support Column RepairConcrete bridge columns are an integral part of the integrity of highway bridges

    that may be damaged by various physical forces including earthquakes and vehicleaccidents. Vertical effects on these bridge columns lead to significant variations in

    axial force demand which can result in fluctuations in moment demands at the face

    of the bent cap, amplification of moment demands at the girder mid-span, and

    changes to moment and shear capacity of the column.

    In this case, concrete columns were deemed to be fatigued due to deterioration of

    steel reinforcement.

    5.3.1. Material UsedFortec 600 gsm unidirectional carbon fiber fabric w/ #4550 Epoxy Saturant and

    (#590) Epoxy paste.

    5.3.2. Project Scope

    Concrete Columns were deemed to be fatigued due to deterioration of steel

    reinforcement. Repair was to wrap columns using 600 gsm carbon fiber wrap

    utilizing onsite impregnator of epoxy saturate.

    Figure5- 22 Wrapping column with FRP sheets

    5.3.3. Conclusion

    Wrapping column with Fortec carbon fiber fabric allowed for minimal road closure

    as would have been needed with old method of teardown and replacement of

    column. The #4550 epoxy allowed contractor to cure out in field under difficult

    weather conditions. With highs in the 60's and lows dipping into the 40's a night

    curing was a challenge.