![Page 1: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/1.jpg)
FINAL DESIGN PRESENTATION 13th St N – Kirkwood Rd to N. Johnson St
(Lyon Village Neighborhood)Angela Marshall, Neighborhood Conservation Planner
Community Planning, Housing, & Development
Neighborhood Conservation Program
![Page 2: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/2.jpg)
Final DesignN560 13th Street N
(N Kirkwood Rd to N Johnson St)
![Page 3: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/3.jpg)
Agenda:
1. Overview of the Project
2. Street Improvement Design Plan
3. Sign and Pavement Markings Plan
4. Landscape Plan
![Page 4: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/4.jpg)
Presentation Purpose:
Present final design to property owners in preparation for
construction of the street improvement project on 13th St N,
Kirkwood Rd to N. Johnson St.
Project Goal:
Pedestrian Safety project to include a 5-foot wide sidewalk, curb and gutter on the south-side, and curb and gutter only on the north-side of 13th St N between Kirkwood Rd to N. Johnson St and a retaining wall at one property. All improvements within existing right-of-way; ADA compliant accessible curb ramps at the intersection of 13th Street N and N Kirkwood Rd. Parking on either side of 13th St N will not be permitted.
![Page 5: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/5.jpg)
![Page 6: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/6.jpg)
![Page 7: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/7.jpg)
![Page 8: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/8.jpg)
![Page 9: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/9.jpg)
Temporary Easements
• Temporary easements and construction agreements allow the County contractor to access private yards to perform construction-related work, including the relocation of fences, replacement of disturbed sod, and making grade adjustments.
• The County agrees to restore the disturbed area on and adjacent to the Temporary Easement Area as nearly as practicable to its original condition.
• Temporary easements become null and void at the end of the project.
![Page 10: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/10.jpg)
Next steps
1. Questions and comments
• Relative to the overall project design
• Relative to individual lots
2. Final design plan 90%→100%
3. Temporary easements complete
4. Utility relocation complete
5. On-call contractor/Prepare for construction
![Page 11: FINAL DESIGN PRESENTATION › wp-content › uploads › sites … · Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement](https://reader033.vdocuments.net/reader033/viewer/2022060401/5f0e42767e708231d43e60c5/html5/thumbnails/11.jpg)