Education Graduate of Versailles High School Pursuing Bachelors Degree in Mechanical Engineering at Wright State
University (Currently at Lake Campus) Graduation Date: May 2018
Previous Work Experience Emerson Climate Technologies Crown Lift Equipment
Agenda
Co-Op Expectations
Projects
Midmark Experience
Future Goals
What I Gained
Conclusion
Questions
Co-op Expectations
Work in a friendly yet focused environment
Learn the day to day functions of an engineer at Midmark and further my knowledge in the field
Be committed to my work and contribute in an impactful way
Have the opportunity to work from different angles on projects
Learn as much as possible
Projects
Generating Future UPT Line Format and Sequence
Near Miss Resolution
630 Foot and Back Assembly Cart Project
Kaizen Event
Other Small Projects
Power Line > Hi-Low & UPT Lines
Current Power Line
Future Power LinesUPT/SCP Line & Hi-Low Line
Generating Future UPT Line Format and Sequence
Collected cycle times on current seven station across all UPT and SCP models
Developed cycle times per station based on the current build mix to compress UPT tables from a seven station build to a three station build
Balanced and combined work sequence to meet identified target times
Finalized new work instruction in Winsequence
Change request #C3813
Resolved Near Miss Incident
Modified a current part basket design to replace unfit wood part basket
This project was completed after a wood basket broke while being handled
Purchasing > Processing > Weld > Finished Product
630 Assembly Cart Project Eliminated the use of the large assembly cart used to attach the foot and
back sections to a 630 unit Able to eliminate cart by developing a hoisting method and new work
sequence New sequence will create much needed space on the new UPT Line and
will allow for a faster assembly time
630 Assembly Cart Project
Run base downReceive components
Assemble back and foot to seat
Link actuator using brace Hoist entire assembly Secure assembly to scissor top
Future Sequence:
Spring Kaizen Event
Kaizen Event on April 20th and 21st Casework Line, Station 2 Theme: Save 600 seconds of fluctuation through three stations on the
Casework line Outcome: Saved just over 200 seconds of fluctuation Implemented 4 Kaizens
• Tool accessibility • Tool interference/disruptance• Reducing Red Zone Work
Other Small Projects
Nutsert Testing
Construction of New Line Components
Battery Exchange Cart Waterspider Battery Charging Station
Battery Tray/Holder
New Station Development
Midmark Experience
Positives Work environment Co-op trust and reliance Interaction between
manager and mentor Introduction to the
company and the department functions
Hands on experiences
Improvements Increase work experience
to include Creo More involvement with
work groups outside current department
Future Goals
Continue to attend school at Wright State
Co-op as much as possible based on school schedule
Continue to further my engineering skills and knowledge in the classroom as well as gaining real work experience through co-op opportunities
Graduate from Wright State in May of 2018
Obtain a position in Mechanical Engineering at a place where I can further my learning as well as make a contribution within a company that impacts society
What I Gained
Furthered communication skills• Conversed with team leaders and line teammates daily• Created connections among teammates at all plants to assist in completing
projects
Knowledge of manufacturing methods• Emphasis on efficiency and ergonomics • Documentation protocols and requirements
Learning by doing is best• Making mistakes leads to more impactful learning
Don’t underestimate the power of asking questions• Understand purposes of projects fully• Become as well-rounded as possible in all business efforts• Be adaptable
<footer>
Conclusion
Special thanks to:
Brad Beyke
Scott Denman and Eric Harshbarger
Entire Medical Ops team
Brent Pepple and Andy Knapke
Questions???