financial analysis for a 50 mw power project

26
Kristján B. Ólafsson [email protected] 1 28.5.2014 Fjármálagreining jarðhitavirkjana Kristján B. Ólafsson WORKSHOP FOR GEOTHERMAL DEVELOPMENT DONORS Reykjavik Iceland May 2014 Financial analysis for a 50 MW power project Case Study: Africa and Iceland Investment, O&M, Risk, IRR, ROE, LCOE, Tariff, Financing, etc. Kristján B. Ólafsson Senior Financial Analyst [email protected]

Upload: yadavmihir63

Post on 01-Oct-2015

218 views

Category:

Documents


2 download

DESCRIPTION

Financial Analysis for a 50 Mw Power Project

TRANSCRIPT

  • Kristjn B. lafsson [email protected] 128.5.2014Fjrmlagreining jarhitavirkjanaKristjn B. lafsson

    WORKSHOP FOR GEOTHERMAL DEVELOPMENT DONORSReykjavik Iceland May 2014

    Financial analysis for a 50 MW power projectCase Study: Africa and Iceland

    Investment, O&M, Risk, IRR, ROE, LCOE, Tariff, Financing, etc.

    Kristjn B. lafsson Senior Financial Analyst [email protected]

  • Kristjn B. lafsson [email protected] 2

    Kristjan B Olafsson

    Senior Financial Analyst

    Economist from the University of Iceland.

    MBA from Copenhagen Business School.

    Tel. + 354 892 9200 e-mail: [email protected]

    Consent Energy LLC Washington DC - partner

    Consultancy and energy project development

    www.consentenergy.com

    Geothermal experience from Reykjavik Energy and Reykjavik Energy Invest:

    Hellisheidi power plant

    Nesjavellir power plant

    Hverahlid 90 MW geothermal project

    Djibouti Assal geothermal project (2008-2010): REI and Djibouti

    A. Financial analysis

    B. Operational analysis

    C. Risk analysis and risk mitigation

    D. Project Finance

    E. Corporate Finance

    F. Contract structure

    G. Pre-feasibility and Feasibility studyH. PA and PPA I. Tender for drillingJ. JDA

    Consultancy for: MFA (Ministry for Foreign Affairs / Benedikt Hskuldsson), Mannvit, Verkis, NEA (National Energy Authority / Orkustofnun), Icelandic Power Companies, Banks, Investors, etc.

    Kristjan B Olafsson

  • Kristjn B. lafsson [email protected] 3

    Nesjavellir CHP 300 MW thermal and 120 MW electricity = 420 MW

    Separation station, steam, gas and effluent water.

    Steam vent station:

    Steam pipelines:

    Two phase flow from wells (steam and liquid):

    Power Plant:Cooling towers:

    Turbine and generator: Wells:

    Nesjavellir

  • Kristjn B. lafsson [email protected] 4

    Iceland: The power system totals 2.637 MW and its 100% renewable from hydro and geothermal

    The Icelandic power system totals 2.637 MW and its 100% renewable from hydro and geothermal resources

    Transmission cost in Iceland:

    Example:50 MW and 98% utilization

    Cost: 0,6 cent/kWh

    National Power Company

    12.838.23671%

    Reykjavik Energy;

    3.421.772; 19%

    HS Energy; 1.349.743; 7%

    Total Generation 201318.116.099 MWh

    National Power Company Reykjavik Energy HS Energy A B C D E F G

    Hydro12.862.843

    71%

    Geothermal5.245.021

    29%

    Wind5.485

    0%

    Fossil2.750

    0%

    Total Generation 201318.116.099 MWh

    Hydro Geothermal Wind Fossil

  • Kristjn B. lafsson [email protected] 5

    Iceland: Installed Power Plants 1960-2014

    It was a political decision in 1961 to seek ways how Iceland could best use its energy resources and what kind of power intensive industry could be build in the country. The National Power Company (Landsvirkjun) was formed in 1965 and the first new power plant, Burfell, was commissioned 1969.

    13 17 1 0

    105

    3 1 3570

    4 8 0 8 6 2 3050

    2 1

    100

    670

    140

    0 450

    3 0

    100

    5 540 30 20

    600

    60 30 260 30 45 45 0 1 3 30

    9010033

    690

    19 1 1 0 30 690

    3 2

    90

    0 0

    95

    0

    1.500

    3.000

    Stei

    ngr

    mss

    t

    196

    0

    1961

    1962

    raf

    oss

    19

    63

    ve

    r 1

    964

    Mr

    ar

    196

    5

    B

    rfel

    l 196

    9 1

    972

    Nm

    afja

    ll 19

    69

    Smyr

    lab

    jarg

    a 1

    969

    1970

    B

    rfel

    l 197

    1

    B

    rfel

    l 197

    2

    An

    dak

    ll 1

    973

    Lax

    19

    73

    1974

    Bl

    vard

    als

    197

    5

    Laga

    rfo

    ss 1

    975

    Mj

    lk

    197

    5

    Skei

    sf

    oss

    19

    76

    Kra

    fla

    197

    7

    Siga

    lda

    1977

    Svar

    tsen

    gi 1

    977

    Sn

    gurf

    oss

    19

    77

    Siga

    lda

    1978

    1979

    Svar

    tsen

    gi 1

    980

    Hra

    un

    eyja

    foss

    198

    1

    Hra

    un

    eyja

    foss

    198

    2

    Bl

    vard

    als

    198

    3

    1984

    1985

    1986

    1987

    1988

    Svar

    tsen

    gi 1

    989

    1990

    Bla

    nd

    a 1

    991

    Lax

    19

    91

    Rei

    h

    jalli

    199

    1

    Bla

    nd

    a 1

    992

    Svar

    tsen

    gi 1

    993

    Lax

    19

    94

    1995

    1996

    B

    rfel

    l 199

    7

    Kra

    fla

    199

    7

    B

    rfel

    l 199

    8

    Nes

    jave

    llir

    199

    8

    Rey

    kjan

    es 1

    998

    Sult

    arta

    ngi

    19

    99

    Svar

    tsen

    gi 1

    999

    H

    sav

    k 20

    00

    Sult

    arta

    ngi

    20

    00

    Nes

    jave

    llir

    200

    1

    Vat

    nsf

    ell 2

    001

    Vat

    nsf

    ell 2

    002

    ve

    r 2

    002

    2003

    Smv

    irkj

    anir

    200

    4

    M

    lavi

    rkju

    n

    Nes

    jave

    llir

    200

    5

    Hel

    lish

    ei

    i 200

    6

    Rey

    kjan

    es 2

    006

    G

    ngu

    skar

    s

    200

    7

    Hel

    lish

    ei

    i 200

    7

    Kr

    ahn

    jka

    virk

    jun

    200

    7

    Laga

    rfo

    ss 2

    007

    Lin

    d

    200

    7

    Lj

    s 2

    007

    Sel

    rvir

    kju

    n 2

    007

    Svar

    tsen

    gi 2

    007

    Bj

    lfsv

    irkj

    un

    200

    8

    Hel

    lish

    ei

    i 200

    8

    G

    lsvi

    rkju

    n 2

    009

    Mj

    lk

    201

    0

    Hel

    lish

    ei

    i 201

    1

    Bre

    iad

    alsv

    irkj

    un

    201

    2

    Sk

    garg

    er

    i 20

    12

    2013

    B

    ar

    hl

    s 20

    14

    Installed power plants in Iceland 1960-2014 Hydro 1972 MW (75%) and Geothermal 665 MW (25%) = 2.637 MWTotal generation: 18.116.099 MWh = 18,1 TWh Utilization 78,4%

  • Kristjn B. lafsson [email protected] 6

    Iceland: Geothermal power plants and electricity generation

    330 30

    2

    6 4 5

    30 30

    60

    30 30

    2

    100

    90

    33 90 90

    0,0

    3,0

    6,0

    0

    150

    300

    19

    69

    19

    70

    19

    71

    19

    72

    19

    73

    19

    74

    19

    75

    19

    76

    19

    77

    19

    78

    19

    79

    19

    80

    19

    81

    19

    82

    19

    83

    19

    84

    19

    85

    19

    86

    19

    87

    19

    88

    19

    89

    19

    90

    19

    91

    19

    92

    19

    93

    19

    94

    19

    95

    19

    96

    19

    97

    19

    98

    19

    99

    20

    00

    20

    01

    20

    02

    20

    03

    20

    04

    20

    05

    20

    06

    20

    07

    20

    08

    20

    09

    20

    10

    20

    11

    20

    12

    20

    13

    20

    14

    20

    15

    Electricity gen. per year in TWh Bjarnarflag 3,2 MW 1969 National Power Company

    Krafla 2x30=60 MW 1977-1997 National Power Company Svartsengi several units 76,4 MW 1997-2007 HS Energy

    Nesjavellir 4x30=120 MW 1998-2005 Reykjavik Energy Husavk 2 MW 2000

    Reykjanes 2x50=100 MW 2006 HS Energy Hellisheidi 6x45+33=303 MW 2006-2011 Reykjavik Energy

    Installed geothermal capacity: 665 MW electricity. Utilization 90% and yearly generation 5,2 TWh

    The main causes of rapid geothermal growth in electricity generation: New Electricity Act 2003: Its main objective was to liberalize the market for generation of electricity and retail. Nordural Grundartangi aluminum production. PPA contracts with HS Energy and Reykjavik Energy. Nesjavellir 120 MW, Reykjanes 100 MW and Hellisheidi 303 MW. Most of the energy goes to the aluminum smelter.

    MW TWh

  • Kristjn B. lafsson [email protected] 7

    14,60

    11,63

    4,90

    2,584,21

    0,6

    30,00

    0

    20

    40

    ReykjavikEnergy:

    Householdincl. 25,5%

    VAT.

    ReykjavikEnergy:

    Householdexcluding

    25,5% VAT.

    NationalPower

    Company:Heavy Industry

    includingtransmission.

    NationalPower

    Company:Heavy

    Industry, oldcontracts,

    partlyincluding

    transmission.

    EstimatedTariff from a

    newgeothermal

    power plant.

    Transmissioncost

    Household inCountry X:Estimatedtariff 30

    cent/kWh oreven higher.

    Electricity tariffs in IcelandCalculated to cent/kWh (US$)

    Transmission and distribution

    4,9234%

    Fixed charge2,1815%

    Energy price4,4230%

    Energy tax0,111%

    Value Added Tax2,9720%

    Reykjavik Energy Household 14,60 cent/kWh including VAT

    Per year: 4.800 kWh x 14,60 cent/kWh = 700 US$

    Electricity Tariffs in Iceland calculated to cent/US$

    ISK/US$: 115,00

  • Kristjn B. lafsson [email protected]

    Well 1 Well 2 Well 3 Well 4 Well 5 Well 6

    MW per drilled well 6 0 7 17 20 0

    Accumulated MW 6 6 13 30 50 50

    6 6

    13

    30

    50 50

    0

    30

    60

    Figures from a drilling project in Iceland

    8

    Drilling is the primary risk factor in geothermal projects

    The figure shows real figures from a drilling project in Iceland. 6 wells have been drilled and estimated 50 MW have been secured. Average 50/6 = 8, 3 MW/Well The first three wells yield a total of 13 MW. Then there are two robust wells and finally well 6 with 0 MW. This case clearly describes the situation that may arise during drilling for a new plant, one the management of the project should be aware of. This may be analysed further in a decision tree analysis.

    MW

  • Kristjn B. lafsson [email protected] 9

    Geosciences

    Legal and institutional framework

    Finance

    Engineering

    Cooperation between disciplines

  • Kristjn B. lafsson [email protected] 10

    A: PPPublic project

    ICELAND

    C: IPPThe private sector

    B: PPPPublic Private Partnership

    D: Separation of

    steam collection and power generation

    Financial Models

  • Kristjn B. lafsson [email protected] 11

    OperatorReykjavik Energy

    Operations and Maintenance Contract

    LendersFinancing Agreements

    IFC and MDBs

    ContractorReykjavik Energy

    Construction Contract

    Sponsors / InvestorsEquity

    Reykjavik Energy Invest, IFC and MDBs

    Project Finance model: REI Djibouti model 2008

    PPA

    & PA

    Project Company Djibouti

    Off-takerEDD Djibouti

    InsurersRisk Mitigation

  • Kristjn B. lafsson [email protected] 12

    The Icelandic Approach in Development of Geothermal Projects

    Geothermal development

    R & D Exploration Drilling Confirmation Engineering Construction O & M +25 Y

    ISOR Icelandic Geothermal Companies (*)

    Iceland Drilling Mannvit

    Verkis

    Efla

    Worldwide: Only a few companies cover all phases of geothermal development

    (*) Not using EPC contracting approach. EPC: Engineering, procurement and construction.

    Icelandic Power Companies 2014: Landsvirkjun: State ownership Reykjavik Energy: City of Reykjavik and municipalities HS Energy: Privatized 2007

  • Kristjn B. lafsson [email protected] 13

    Africa: Estimated investment 4 MUS$/MW vs Iceland 3 MUS$/MW

    45

    25

    76

    19

    5

    150

    30

    75

    100

    176

    195200

    0

    150

    300

    Pre-feasibility and 4exploration &

    production wells

    Additional Productionwells

    Re-injection wells Power plant, turbines,rotor, etc.

    Piping, substation,etc.

    Start up andcommissioning

    Iceland Total 150MUS$

    Estimate for Africa: 4 MUS$/MW x 50 MW = 200 MUS$ (Estimates from 3-7 MUS$/MW)Estimate for Iceland: 3 MUS$/MW x 50 MW = 150 MUS$ (Estimates from 3-4 MUS$/MW)

    Project cost heavily depending on the total cost of drilling

    MUS$ Iceland Accumulated cost

    MUS$

    Page 41:Low estimate: 2,8 MUS$/MWMedium estimate: 3,9 MUS$/MWHigh estimate: 5,5 MUS$/MW

  • Kristjn B. lafsson [email protected] 14

    0,25

    0,50

    0,25 0,25

    0,75

    2,00

    0,00

    1,50

    3,00

    Fixed Cost:Supervision of

    machines

    Fixed Cost:Maintenance

    work

    Variable Cost:Superv. ofReservoir

    Variable Cost:Operational

    supplies

    Variable Cost:Make-up or

    maintenancedrilling

    Estimated operating expenses, including make-up, from 0,85 - 2,00 cent/kWh

    O&M cent/kWh Accumul. cent/kWh

    0,2512%

    0,5025%

    0,2512%

    0,2513%

    0,7538%

    Estimated operating expenses 2,00 cent/kWh

    Fixed Cost: Supervision ofmachines

    Fixed Cost: Maintenancework

    Variable Cost: Superv. ofReservoir

    Variable Cost: Operationalsupplies

    Variable Cost: Make-up ormaintenance drilling

    O&M including make-up

    Cent/kWh

  • Kristjn B. lafsson [email protected] 15

    6,0 12,0

    40,224,0

    48,0

    19,8

    140,0

    30,0

    60,0

    0,0

    60,0

    140,0

    0

    100

    200

    First drilling and scientificwork

    Financial Close: 75% of power Grant 0% Equity Debt

    50 MW Geothermal Project: 200 MUS$: Grant 0%IPPs and Investors not willing to taka 100% risk to prove the resource

    Example: Djibouti 2008-2010

    IPP Company Multiple Donors MDBs Equity 30% Debt 70% Total

    A: First step B: Second step C: Total financing

    Project finance model without Grant

    MUS$

  • Kristjn B. lafsson [email protected] 16

    15,0

    34,230,0

    30,0

    30,0

    15,0

    16,8

    119,0

    30,0

    60,0

    30,0

    51,0

    119,0

    0

    100

    200

    First drilling and scientificwork

    Financial Close: 75% of power Grant 15% Equity Debt

    50 MW Geothermal Project: 200 MUS$: Grant 15% or 30 MUS$Example: Djibouti with WB/Multidonors support

    IPP Company Multiple Donors Others MDBs Equity 30% Debt 70% Total

    Project finance model including grant 15% or 30 MUS$

    MUS$

    A: First step B: Second step C: Total financing

  • Kristjn B. lafsson [email protected] 17

    45,0

    105,0

    0,0

    45,0

    105,0

    0

    100

    200

    First drilling and scientificwork

    Financial Close: 75% ofpower

    Grant 0% Equity Debt

    50 MW Geothermal Project: 150 MUS$Public Power Companies: Understanding and accepting the geothermal risk

    Power Company MDBs and Commercial Banks Total

    Corporate Finance model for Iceland

    MUS$

    A: First step B: Second step C: Total financing

  • Kristjn B. lafsson [email protected] 18

    30 30 30 30

    3051 51

    19

    119

    2 5

    30

    60

    100

    200

    0

    50

    100

    150

    200

    250

    Pre-feasibility Pre-feasibility andFeasibility Study

    Feasibility Study and firstdrilling

    Drilling and to reachFinancial Close

    Total drilling and re-injection

    Power plant, equipment,steam supply system, etc.

    Operation period

    Accumul. GRANT 30 MUS$

    Accumul. Equity 51 MUS$

    Accumul. Debt 119 MUS$

    Accumul. Capex 200 MUS$

    Risk profile from high to low

    50 MW Geothermal Power ProjectRisk profile and major steps in financing

    Financial Close: 60 MUS$

    Risk profile: From high to low

    2) Financial Close 60 MUS$

    1) First drilling 30 MUS$

    4) CapEx 200 MUS$

    3) Total drilling 100 MUS$

    Steps in financing a geothermal project and project risk

    MUS$

  • Kristjn B. lafsson [email protected] 19

    13,27

    8,78

    4,21

    25,0%

    20,0%

    11,0%

    0,0%

    12,5%

    25,0%

    0,00

    10,00

    20,00

    A: Africa: No grantTariff 13,27 cent/kWh

    Project Finance.

    B: Africa: Grant 30 MUS$Tariff 8,78 cent/kWh

    Project Finance

    C: Iceland: No grantTariff 4,21 cent/kWh

    Corporate Finance

    Return on equity, Grant and Tariff

    Tariff cent/kWh ROE

    Key findings

    Cent/kWh ROE %

    Transmission cost:0,6 cent/kWh.

  • Kristjn B. lafsson [email protected] 20

    CASE STUDY: Financial assumptions and conclusions

    Corpor. Fin.

    1 A B C

    2 Plant size MW 50 50 50

    3 Capital expenditures: CAPEX over six years MUS$ 200 200 150

    4 Capital expenditures: Capex per MW MUS$/MW 4,0 4,0 3,0

    5 Exploration and production wells Nr. 12 12 9

    6 Average well productivities (success rate included in calculation) MWe 4,2 4,2 5,6

    7 Re-injection wells Nr. 6 6 6

    8 Financing of first drilling & scientific work MUS$ 30 309 Financial Close in Project finance reached at MUS$ 60 60

    10 Total scientific work, drilling and re-injection MUS$ 100 100 5811 Power plant, turbines, steamfield, etc. 100 100 9312 A B C13 Equity: 30% MUS$ 60 51 4514 Debt: 70% MUS$ 140 119 10515 Loan guarantee Project finance Project finance State/Municipality16 Grant MUS$ 0 30 017 Grant % of CAPEX 0% 15% 0%18 Interest on debt: % in real terms % 6% 6% 3%19 Required rate of return on equity % 25% 20% 11,0%20 WACC: Before tax % 11,7% 10,2% 5,4%21 WACC: After tax % 10,9% 9,4% 5,0%22 A B C23 Plant capacity factor % 90% 90% 92,5%24 Maintenance and internal power consumption % 10% 10% 7,5%25 Generation (MW x capacity x 365 x 24) GWh/Year 394,2 394,2 405,226 Annual revenues MUS$ 52,3 34,6 17,027 A B C28 OPEX incl. Make-up. Annual prod. decline 2-3%. cent/kWh 2,0 2,0 0,8529 OPEX incl. Make-up. Annual prod. decline 2-3%. % of CAPEX 3,9% 3,9% 2,3%30 OPEX incl. Make-up. Annual prod. decline 2-3%. MUS$/Year 7,9 7,9 3,431 5. Tax, depreciation and years in calculation A B C32 Income tax % 20% 20% 20%33 Depreciation, straight line Years 25 25 2534 Loan maturity period Years 25 25 2535 Operating life time Years 25 25 2536 A B C37 Tariff cent/kWh 13,27 8,78 4,2138 Project IRR (from free cash flow to firm: FCFF) % 15,3% 9,3% 5,7%39 Project NPV MUS$ 53,9 -1,3 9,740 Equity IRR (from free cash flow to equity: FCFE) % 25,0% 20,0% 11,0%41 Equity NPV MUS$ 0,0 0,0 0,042 Pay-Back Years 6,0 9,1 13,143 Discounted Pay-Back (disc. at WACC) Years 11,0 22,144 Levelized Cost of Energy cent/kWh 5,15 5,00 2,8245 Levelized Cost of Energy after Grant cent/kWh 5,15 4,34 2,8246 a) LCOE Capital cent/kWh 3,95 3,72 2,1647 b) LCOE O&M cent/kWh 1,19 1,28 0,6748 No resource tax, tax holidays or carbon credit revenues.

    3. Plant capacity factor and annual generation (+/-)

    High temperature reservoir single flash geothermal project Africa IcelandProject finance

    1. Capital expenditures, wells and steps in financing (+/-)

    2. Capital structure, interest, return on equity and WACC (+/-)

    4. Operation and Maintenance costs including make-up (+/-)

    6. Financial calculations: Tariff, IRR, Payback and LCOE

    7. Other assumptions:

    Iceland: No direct grant Loan guarantee from owner No resource tax Return on equity 11% WACC after tax 5%

  • Kristjn B. lafsson [email protected] 21

    2,00

    2,03

    0

    5

    10

    15

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    O&M incl. Make-up Depreciation Interest Net Income Income tax

    Tariff per year calculated to cent/kWhTariff 8,78 cent/kWh

    O&M incl. Make-up

    2,0022,8%

    Interest1,25

    14,3%

    Income tax0,708,0%

    Depreciation2,03

    23,1%

    Net Income2,79

    31,8%

    Tariff in cent/kWh and %Tariff 8,78 cent/kWh

    Tariff 8,78 cent/kWh

  • Kristjn B. lafsson [email protected] 22

    Levelized Cost

    2,00

    0,00

    1,250,70

    2,03

    2,79

    8,78

    5,00

    4,34

    0,0

    5,0

    10,0

    15,0

    O&M & M-up

    Royalties Interest Income tax Depreciation Net Income Tariff LevelizedCost

    LC afterGrant

    Tariff 8,78 cent/kWhLCOE 5,00 cent/kWh

    LCOE after Grant 4,34 cent/kWh

    cent/kWh

    3,72

    0,510,77

    5,00

    0,0

    5,0

    10,0

    15,0

    LCOE Capital LCOE O&M Fixed 40% LCOE O&M Variable 60% LCOE Total

    LCOE 5,00 cent/kWhCapital: 3,72 cent/kWh

    O&M Fixed: 0,51 cent/kWhO&M Variable: 0,77 cent/kWh

    cent/kWh

  • Kristjn B. lafsson [email protected] 23

    Project IRR 9,26% and Equity IRR 20%

    -1,3

    9,26%

    -20%

    0%

    20%

    -150

    0

    150

    1 2 3 4 5 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Free Cash Flow to Project, accumulated Project IRR and accumulated NPV: Tariff 8,78 cent/kWh

    Equity Debt

    GRANT Free Cash Flow to Project

    Acc. Cash Flow at WACC a.tax Acc. Project IRR

    Million US$ and %

    WACC after tax: 9,4%Iceland: WACC 5,0%

    20,00%

    -20%

    0%

    20%

    -150

    0

    150

    1 2 3 4 5 6 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

    Free Cash Flow to Equity, accumulated Equity IRR and accumulated NPV: Tariff 8,78 cent/kWh

    Equity Debt

    GRANT Free Cash Flow to Equity

    Acc. Disc. Cash Flow to Equity Acc. Equity IRR

    Million US$ & %

    ROE 20%Iceland: ROE 11%

  • Kristjn B. lafsson [email protected] 24

    1. Favorable geothermal conditions, strong infrastructure and local support.

    2. Power plants located close to transmission lines and market.

    3. Years of experience from geothermal central heating projects.

    4. New Electricity Act 2003 and increased demand from aluminum industry willing to sign long term PPA.

    5. High utilization (90%) lowering the Levelized Cost of Electricity.

    6. State and municipal ownership of power companies.

    7. A loan guarantee from owners.

    8. Power companies understanding and accepting the risk in geothermal projects.

    9. Corporate Finance and access to finance.

    10. Local geothermal capacity building (UNU, ISOR, NEA (Orkustofnun), Engineering companies, etc.) and a local geothermal drilling company.

    Iceland would be facing a different geothermal picture without State/Municipal Power Companies, Corporate Finance instead of Project Finance, local know-how, local drilling company, experience from central heating projects and increased demand from aluminum industry.

    Key success factors for rapid geothermal development in Iceland

  • Kristjn B. lafsson [email protected] 25

    Long term PPA

    Long operational life cycle

    Renewable energy

    No reliance on fossil fuel, rain, wind or sun

    Reliable

    energy

    Generation capacity factor > 90%

    Tariff 8,78-13,27 cent/kWh

    Financing is a difficult step

    African Rift Valley and Geothermal Energy

    Estimate for Africa:

    10 x Iceland installed geothermal capacity in the coming years.

  • Kristjn B. lafsson [email protected] 26

    Kristjan B OlafssonSenior Financial AnalystReykjavik IcelandE-mail: [email protected]: +354 892 9200