Introduction
Project preparation should be geared towards the requirements of financial and economic evaluation.
Once all the elements of a feasibility study are prepared, the next step is to compile the total investment costs.
Financial evaluation should preferably rely on discounting methods and incorporate sensitivity analysis.
Projects should also be, evaluated from the aspect of their direct and indirect effects on the national economy.
![Page 3: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/3.jpg)
Total Investment Costs
Investment costs are defined as the sum of fixed capital (fixed investments plus production capital costs) and net working capital.
Fixed capital constitutes the resource referred for constructing and equipping an investment project and working capital corresponding to the resources needed to operate the project totally or partially.
![Page 4: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/4.jpg)
Fixed Assets (Capital)
Fixed assets (capital) comprise fixed investments and pre-production capital costs
i) Fixed Investments: include the following. Land and site preparation. Building and civil works. Plant machinery and equipment including
auxiliary equipment. Certain incorporate fixed assets such as
industrial property rights.
![Page 5: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/5.jpg)
ii) Pre-production Capital Expenditure: This expenditure, which has to be capitalized, includes a number of items that originated during the various stages of project formulation and implementation. These include: Preliminary and capital issue expenditures. Consultant fees for preparing studies, Travel expensesPreparatory installations such as camps,
temporary offices, stores, etc.Training costs, including fees, travel and living
expenses; salaries and stipends of the trainees.
Interest on loan during construction.
![Page 6: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/6.jpg)
Working Capital
Working capital indicates the financial means required to operate the project according to its production program.
It is defined as the current assets minus current liabilities
Current assets comprise receivables, inventories (raw material, auxiliary material, supplies packaging materials, spares and small tools), work in progress, finished products and cash.
Current liabilities consist mainly of accounts payable (creditors) and are free of interest.
![Page 7: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/7.jpg)
Project Financing
The financing of new projects continued to be a problem, since corporate guarantees would usually be required for loans to finance projects.
Companies were therefore risking to the extent of their total assets if a project failed.
Development of project financing, therefore, emerged from the need for companies to shield themselves from such risks.
This has led to non-recourse or limited recourse financing.
![Page 8: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/8.jpg)
In this financing, creditors provide financing to a
project solely based on the merits of the project
itself, with limited or no recourse to the
companies sponsoring the project.
The project implementation demands the
establishment of a separate project company by
the project sponsors.
They also need to carefully analyze the financial
feasibility of projects, in the light of the risks
involved and their proposed distribution.
![Page 9: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/9.jpg)
Types of Capital
There are, in principle, three types of capital available to all projects: equity, debt and mezzanine capital.
Each plays a specific role in project financing and has its own risk characteristics.
The return on each type of capital is determined largely by its risk characteristics.
![Page 10: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/10.jpg)
i) Equity Capital: It represents the funds provided by the owners and is the lowest-ranking capital of all in terms of its claims on the assets of a project. Normally, any distributions that can be made to
equity investors is done after all other project obligations are satisfied.
If a project fails, therefore, all other claims must be met before any claims can be made by equity investors.
Equity investors therefore bear a higher degree of risk than any other providers of capital.
Moreover, if after all other obligations are met, the value of the remaining assets is less than the initial equity capital of the project; the investors will bear the loss.
Equity capital is also referred to as risk capital.
![Page 11: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/11.jpg)
ii) Debt Capital: Senior debt has first claim over all the assets of a project and must be repaid first, according to a predetermined schedule. In contrast to equity capital, a project’s senior
debt has the highest ranking of all capital. The claims of others can be considered only
after the claims of senior debt are satisfied. It bears the lowest risk of all capital and correspondingly, the returns are usually limited to just the interest payments on the loans, irrespective of how successful the project may be.
Equity investors would prefer a debt-equity ratio as high as possible.
![Page 12: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/12.jpg)
iii) Mezzanine Capital: The key characteristic of mezzanine capital is that it has both debt and equity features and, correspondingly, it has a risk profile that is somewhere between debt and equity capital. Examples of mezzanine financing are subordinated
loans and preference shares. Both have the characteristics of debt, in that
regular payments of interest and/or capital are involved.
However, payments are subordinated to senior debt and need only be made when project funds are available.
When they are not available, mezzanine financing is treated like equity and no payments are made hence, mezzanine financing provides projects with an additional equity cushion.
![Page 13: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/13.jpg)
Sources of Financing
It is a normal trend that debt, equity and mezzanine capital are obtained from different sources.
However, there are cases where a single source provides more than one type of capital, in which case separate departments may handle the different types of capital separately.
![Page 14: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/14.jpg)
i) Equity Capital Providers: The main source of equity capital for a project comes from the project sponsors or other investors that have an active interest in the project. This would include governments, contractors,
equipment suppliers, purchasers of output and entrepreneurs.
Additional equity, if needed, would be sought from passive sources, such as institutional investors and possibly the general public through local or international capital markets.
They are not normally involved in the promotion and development or the management and operation of the projects in which they invest. Their capital is used to top up the equity requirements of a project that cannot be met by sponsors.
![Page 15: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/15.jpg)
ii) Commercial Banks: The most traditional source of debt financing are commercial banks. To a lesser extent, they are also providers of
mezzanine capital. Their operations essentially revolve around the
creditworthiness of their borrowers and the security of their loans.
Much stress is put on prudential lending and actions aimed at ensuring loan repayment.
![Page 16: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/16.jpg)
Some of the considerations made by commercial banks during the appraisal of a project are:The level of commitment of the sponsors and other major participants, in terms of investment and personnelThe completion and technical targets of the project’s budget, as any slippage will have an adverse effect on the economic viability of the projectThe experience and capabilities of project management in implementing this type of project The degree of confidence in the project’s cost and revenue targets will be determined by the reliability of the assumptions on which the inputs supplies and demand projections are basedThe strength of government support
![Page 17: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/17.jpg)
iii) Export Credit Agencies: Export credit agencies (ECA) are considered to be an important source of long-term credit. As lenders, ECAs have the same concerns and
requirements as commercial banks and would also be signatories to the credit agreement.
However, ECAs are usually state-owned, and their primary objective is the promotion of their country’s exports and the grants are usually tied to the purchase of equipment from the ECA’s country.
ECAs are usually substantially more generous than those of commercial banks and highly suited to the financing of long-term infrastructure projects.
![Page 18: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/18.jpg)
iv) Bilateral and Multilateral Aid Agencies: Many developing countries can also access debt, equity and mezzanine financing from bilateral and multilateral agencies, such as;
United States Agency for International Development (USAID),
The Canadian International Development Agency (CIDA),
The Overseas Development Administration of the United Kingdom (ODA),
The World Bank, The Asian Development Bank (ADB) and The European Bank for Reconstruction and
Development (EBRD), etc. African Development Bank (AfDB)
![Page 19: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/19.jpg)
v) Institutional investors: Institutional investors as a source of debt, equity and mezzanine financing are non-bank financial institutions such as insurance companies, pension funds and investment funds.
Institutional investors distinguish themselves from commercial banks in that they mobilize long-term contractual savings as opposed to short-term deposits.
By virtue of the long-term nature of the funds, many institutional investors are able to provide long-term debt, mezzanine and pure equity financing.
Institutional investors are therefore an important source of long-term funds for large projects.
vi) National and Regional Development Banks
![Page 20: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/20.jpg)
Financial Structuring Techniques
Establishing the appropriate mix of debt, equity and mezzanine financing for a project, which optimizes the use of financial resources and ensures a sound financial structure for the project is the challenge that financial structuring faces.
The security package for the project is illustrated in figure
![Page 21: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/21.jpg)
Security Package
![Page 22: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/22.jpg)
Financial Evaluation
The study of a new enterprise, or the design of a new plant, or the evaluation of two or more alternative solutions always requires the consideration of economic concepts.
The decisions that are made each day in engineering economy in industry, determine whether proposals for investment in new plants and equipments should be accepted or rejected.
Interest formulas are developed for use in engineering economy studies.
![Page 23: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/23.jpg)
1. Non-DCF Methods: does not consider the
time value of money
Payback Period
Return on Investment
Simple rate of return
Return on Capital Employed (ROCE)
Average Accounting rate of return
![Page 24: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/24.jpg)
Payback Period
The pay back period is defined as the length of
time required to recover one’s investment.
The time period is usually expressed in years
and months.
investment from income annual Netinvestment Net
period Pay back
=
![Page 25: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/25.jpg)
Payback Period To calculate the pay back period, simply work
out how long it will take to recover the initial outlay.
However, this method fails to Give considerations to cash precedes earned
after the pay back period Take into account the difference in the timing of
proceeds earned prior to the pay back date.
![Page 26: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/26.jpg)
Cash flow of two alternative machines
Pay back period for machine A is two years where as for machine B it is three years.
That is machine A will recover its investment cost one year sooner than machine B.
Where project’s are ranked by the shortest pay back period, machine A is selected in preference to machine B.
Year 0 1 2 3 4
Machine ACash flow (Birr) -35,000 +20,000 +15,000 +10,000 +10,000
Machine BCash flow (Birr) -35,000 +10,000 +10,000 +15,000 +20,000
![Page 27: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/27.jpg)
The advantages of the payback method are:It is simple and easy to use.It uses readily available accounting data to determine cash-flows.It reduces the project's exposure to risk and uncertainty by selecting the project that has the shortest payback period.Faster payback has a favorable short-term effect on earnings per share.Disadvantages of the Pay back Period: It ignores the life of the project beyond the pay back period.It does not consider the profitability of the projects.It dose not consider the time value of money.
![Page 28: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/28.jpg)
Return on Investment (ROI)
This method first calculates the average annual
profit, which is simply the project outlay deducted
from the total gains, divided by the number of years
the investment will run.
The profit is then converted into a percentage of
the total outlay using the following equations:
Number of years (Total gains)-(Total outlay)
Average Annual Profit
=
Original Investment Average Annual Profit
Return on Investment = X 100%
![Page 29: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/29.jpg)
Using the machine selection project
Profit (A & B) = $55,000 - $35,000 = $5,000 per year (same for both machines)4
20,000 Annual Profit =
35,000 5,000
Return on Investment = X 100%= 14%
Year Cash-Flow Machine A Cash-Flow Machine B
0 ($ 35,000) ($ 35,000)
1 $20,000 $10,000
2 $15,000 $10,000
3 $10,000 $15,000
4 $10,000 $20,000
Total Gains $55,000 $55,000
![Page 30: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/30.jpg)
The return on investment method has the advantage of also being a simple technique like pay back period, but further, it considers the cash-flow over the whole project.
The main criticism of return on investment is that it averages out the profit over successive years. An investment with high initial profits would be ranked equally with a project with high profits later if the average profit was the same.
It does not consider the time value of money
![Page 31: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/31.jpg)
2. Discounted Cash flow Method(DCF) The discounted cash-flow (DCF) technique takes
into consideration the time value of money. For example, a 100Birr today will not have the
same worth or buying power as a 100Birr this time next year.
The basic DCF techniques which can model this effect are Compound interest, net present value (NPV) and internal rate of return (IRR).
These discounting techniques enable the project manager to compare two projects with different investment and cash-flow profiles.
There is, however, one major problem with DCF, besides being dependent on the accurate forecast of the cash-flows, it also requires an accurate prediction of the interest rates.
![Page 32: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/32.jpg)
Compound interest method
• CompoundingS = P (1 + r ) n where,
100S = the sum owing at time tP = principal (sum invested at time 0)N = number of time periods, usually yearsR = the percentage interest rate per time period
• DiscountingP = S (1 + r) n
100
![Page 33: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/33.jpg)
E.g. A company receives USD 136,000 in 3 yrs. attaching a 13% per annum time value of money. What amount would the company receive today?
Present Value (PV) = discounted value = 136,000 (1 + 13)3 100
= 136,000 x 0.693
= USD 94,250
Discounting rate, cut-off rate, minimum rate of return hurdle rate, cost of capital, opportunity cost of capital
1 = discount factor
(1 + r) n
![Page 34: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/34.jpg)
Net Present ValueIf you were offered $120 one year from now and the inflation and interest rate was 20%, working backwards its value in today's terms would be $100. This is called the present value, and when the cash-flow over a number of years is combined in this manner the total figure is called the net present value (NPV).
Year Project Cash-Flow Discount Factor Present Value
0
1
2
3
4
Total NPV
![Page 35: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/35.jpg)
Net Present ValueNPV = NCF0 + (NCF1 x DF1) + NCF2 x DF2) + …. + (NCFn x an)
Where, NCFn = annual net cash flow
n = number of years an = discount factor
Net present value ratio (NPVR) = Profitability index = PV of cash inflows
PV of investment
![Page 36: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/36.jpg)
Net Present Value
The advantages of using NPV are:It introduces the time value of money.It expresses all future cash-flows in today's values, which enables direct comparisons.It allows for inflation and escalation.It looks at the whole project from start to finish.It can simulate project what-if analysis using different values.It gives a more accurate profit and loss forecast than non DCF calculations.
![Page 37: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/37.jpg)
Net Present ValueThe disadvantages are:-Its accuracy is limited by the accuracy of the predicted future cash-flows and interest rates.It is biased towards short run projects.It excludes non financial data e.g. market potential.It uses a fixed interest rate over the duration of the project.
![Page 38: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/38.jpg)
Internal rate of return (IRR) Is the discount rate at which the net present
value of costs (negative cash flows) of the investment equals the net present value of the benefits (positive cash flows) of the investment.
It is commonly used to evaluate the desirability of investments or projects. The higher a project's internal rate of return, the more desirable it is to undertake the project.
Assuming all projects require the same amount of up-front investment, the project with the highest IRR would be considered the best and undertaken first.
![Page 39: Financial and Economic Evaluation. Introduction Project preparation should be geared towards the requirements of financial and economic evaluation](https://reader030.vdocuments.net/reader030/viewer/2022032605/56649e845503460f94b85897/html5/thumbnails/39.jpg)
Internal rate of return (IRR) The IRR is the value of the discount factor
when the NPV is zero. It is assumed that the costs are committed at the end of the year and these are the only costs during the year.
IRR = I1 + PV (i2 – i1 ) , where
PV + /NV/
PV= positive NPV NV= negative NPV