fire island wind project summary and lessons for rural ... island wind...fire island wind project...
TRANSCRIPT
Fire Island Wind Project—Summary
and Lessons for Rural Alaska
April 30, 2013
Fire Island Wind Project Video http://youtu.be/SLqZq3FVMLY
Fire Island Wind Project
As of April 28, 2013:
•FIWP produced 37,776
megawatt-hours of electricity
•Caused no electrical system
operational issues*
•Saved CEA approximately 196
million cubic feet of now scarce
Cook Inlet natural gas in 2012*
*(data provided by CEA in Jan. 16, 2013 RCA filing)
Fire Island Wind Project An important piece of the Southcentral energy puzzle
Project statistics for January
2013:
•Produced 6,812 megawatt-
hours of electricity
•Average wind speed of 8.5 m/s
(19.0 mph)
•Predominant north wind
Fire Island Wind Project Private investment supporting Railbelt energy production
• Chugach Electric
Association Power
Purchase Agreement
• 25-year PPA
• Flat net price of
$97/MW-hour
throughout contract
• $65 million of private
investment in local
energy
Project Facts • 11 GE XLE 1.6 MW wind turbines with total project
nameplate capacity of 17.6 MW
• Expected to generate 51,000 MW hours annually
• Save 500 million cubic feet of Cook Inlet natural gas
annually (4 percent of CEA’s annual gas consumption)
• Power for 4,000 Alaska homes
Why Fire Island? Chugach Electric Association led a
group of utilities to survey Southcentral
Alaska for potential commercial wind
project sites in the 1990s.
Fire Island identified as best site
based upon:
• Wind resource
• Proximity to grid and load
• Minimal environmental impacts
• Lack of conflicting land uses
• Available land for construction
History • 1980’s – CIRI obtains Fire Island property
• 2000 – utility study identifies wind resource
at Fire Island, installs first met-towers and
conceives a 36-turbine project idea
• 2005 – CIRI becomes project developer
• 2008 – Radar software upgraded
• 2009 – Key permits issued, FAA VOR
mitigation plan negotiated
• 2010 – site clearing and preliminary
construction
• 2011— CIRI receives FAA permits, RCA
contract approval, closes project financing
Fire Island Wind Project layout
• 11 commercially operating turbines
• 22 turbine sites available for development
Project Timeline • Fall 2011
• Financing closed.
• Shoreside transmission work begins
• April 2012
• Mobilize to the island
• Start on-island construction
• July 2012
• Wind turbine installation
• September 2012
• First power generated
• Project commissioning
2011 • FAA determination of no hazard issued
• Commercial contracts and Power Purchase Agreement
• RCA approval of PPA
• Project financing closed
• On-shore transmission line construction
2012 • On-island civil and electrical construction
• Finished transmission interconnection
• Erected wind turbines on Fire Island
• Project commissioning completed and commercial operation began Sept. 2012
Transmission • Two 34.5 KV submarine transmission cables from north
point of Fire Island, 3.1 miles across Turnagain Arm to transition cabinet near Point Campbell
• 8.6 miles terrestrial transmission line
• Buried line along existing utility corridor, overhead transmission line north of Connor’s Bog
• Termination at International Substation
• System to be owned and operated by Chugach Electric
Wind Turbine Information
GE 1.6 MW XLE wind turbine:
Blade Length = 131 feet (40 meters)
Hub height = 262 feet (80 meters)
Turbine rotational speed = between 9.8
and 18.7 RPM
Turbine foundation =
steel reinforced concrete
GE Energy
1.6MW wind turbines
Relative heights
Conoco-Phillips Building 296 ft.
Atwood Building 265 ft.
Fire Island Wind Turbine hub 262 ft.
A Fire Island Wind turbine superimposed on the downtown Anchorage skyline
Lessons applicable to rural Alaska
• Logistics are key risk and cost driver
• Private investment in community energy infrastructure
• Value of expert energy project developer
• Tenacity & Vision
Contact: 907.274.8638 [email protected] facebook.com/fireislandwind www.fireislandwind.com