Page 1: First Floor Columns and Second Floor Slab Construction Final Cut

First Floor Columns& Second Floor Slab

Prepared by

Elton Gallimore

Page 2: First Floor Columns and Second Floor Slab Construction Final Cut

Scope of Works

• Area of construction: 86.4m x 46.8m grid= 4043.52 m2.

• To construct 39 First Floor reinforced steel concrete columns at 60 x 30 cm to a height of 2.10m.

• To construct a Second Floor Slab to an area of 4043.52 m2 thickness of 250mm. Height from first floor slab 2.45m

Page 3: First Floor Columns and Second Floor Slab Construction Final Cut

Area of Construction (zones)

15.6m

7.2m

Page 4: First Floor Columns and Second Floor Slab Construction Final Cut

Area of construction (sections)

46.8m

86.4m

Page 5: First Floor Columns and Second Floor Slab Construction Final Cut

Section Breakdown

Page 6: First Floor Columns and Second Floor Slab Construction Final Cut

Safety Platform AssemblyAccess to workableAreas will be viaTemporary stairsWhich be movedAccording to Construction schedule

Week one Week two

Week Week

Page 7: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 1 Column formwork• Sections 1-9 Column

formwork arrangement with re bar

• 3 gangs (2 men per gang), 1 gang per column

• 1 column + rebar 30mins• 12 columns = 2hrs.

Zone 2 Column formwork• Sections 10-18 Column

formwork arrangement with re bar

• 4 gangs (2 men per gang), 1 gang per column

• 1 column + rebar 30mins• 9 columns = 1.5hrs.

200kg of 10mm steel rebar per m3 of concrete (Peri requirements)

Page 8: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 3 Column formwork• Sections 19-27 Column

formwork arrangement with re bar

• 4 gangs (2 men per gang), 1 gang per column

• 1 column + rebar 30mins• 9 columns = 1.5hrs.

Zone 4 Column formwork• Sections 30-34 Column

formwork arrangement with re bar

• 4 gangs (2 men per gang), 1 gang per column

• 1 column + rebar 30mins• 9 columns = 1.5hrs.

200kg of 10mm steel rebar per m3 of concrete (Peri requirements)

Page 9: First Floor Columns and Second Floor Slab Construction Final Cut

Column formwork detail

Positioned to monolithic kickers from ground floor columns

Firs

t fl

oor

Gro

und

floor

Page 10: First Floor Columns and Second Floor Slab Construction Final Cut

Column formwork Sequence

Page 11: First Floor Columns and Second Floor Slab Construction Final Cut

Column formwork assembly zone 1

Retaining wall

Page 12: First Floor Columns and Second Floor Slab Construction Final Cut

Column formwork assembly zone 1

Page 13: First Floor Columns and Second Floor Slab Construction Final Cut

Column formwork assembly zone 1

Page 14: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 1 Ready for pour / first floor slab construction still in progress

Page 15: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 1 & 2 Concrete pour complete

Page 16: First Floor Columns and Second Floor Slab Construction Final Cut

Assembly of Peri LIWA lightweight panel

Zone 1

• 4 sections of wall formwork to be

assembled

• 1 gang (2 men) per wall section

• 15 mins per m2

• 111.72 m2 approx. 1hr 45mins.

Zone 2

• 3 sections of wall formwork to be

assembled

• 1 gang (2 men) per wall section

• 15 mins per m2

• 35.28 m2 approx. 45 mins.

Zone 3

• 3 sections of wall formwork to be

assembled

• 1 gang (2 men) per wall section

• 15 mins per m2

• 35.28 m2 approx. 45 mins.

Zone 4

• sections of wall formwork to be

assembled

• 1 gang (2 men) per wall section

• 111.72 m2 approx. 1hr 45mins.

Page 17: First Floor Columns and Second Floor Slab Construction Final Cut

LIWA lightweight panel concrete pour

Zone 1

• 4 sections of wall to be poured;

• 2 sections of 15.6 x 0.30m @ 2.45m

height

• 2 sections of 7.2 x 0.30 @ 2.45m height

• Amount of concrete required 33.5 m3

Zone 2

• 3 sections of 7.2 x 0.30m @ 2.45 height

• Amount of concrete required 31.8 m3

Zone 3

• 3 sections of 7.2 x 0.30m

@ 2.45 height

• Amount of concrete

required 31.8 m3

Zone 4

• 4 sections of wall to be

poured;

• 2 sections of 15.6 x 0.30 @

2.45m height

• 2 sections of 7.2 x 0.30 @

2.45m height

• Amount of concrete

required 33.5 m3

Page 18: First Floor Columns and Second Floor Slab Construction Final Cut

2.45m

First floor slab

• 90 panels of Skydeck per section

• Panels @ 1.50 x 0.75

• 810 panels for each zone

• 1.125m2 per section

150 kg of steel rebar for every m3 of concrete (Peri requirements)

Skydeck slab formwork assembly

Page 19: First Floor Columns and Second Floor Slab Construction Final Cut

Beams and slab rebar

Beams integrated into slab formwork

Beam layout for each zoneSection of slab rebar

Page 20: First Floor Columns and Second Floor Slab Construction Final Cut

Framing and shear wall assembly

Page 21: First Floor Columns and Second Floor Slab Construction Final Cut

Skydeck slab formwork assembly

Page 22: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 1 Skydeck slab panels & beam formwork assembled, ready for concrete pour

Page 23: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 2 slab concrete pour complete

Page 24: First Floor Columns and Second Floor Slab Construction Final Cut

Zone’s 3 & 4 column formwork assembly and pour, Zone 3 wall assembly and pour

Page 25: First Floor Columns and Second Floor Slab Construction Final Cut

Repositioning of plant machinery

Page 26: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 4 shear wall assembly and pour/ Zone 3 Slab concrete pour complete

Page 27: First Floor Columns and Second Floor Slab Construction Final Cut

Zone 4 slab concrete pour complete

Page 28: First Floor Columns and Second Floor Slab Construction Final Cut

Handover