Figure 1 FIRST STREET BRIDGE REPLACEMENT (BRANDON) Project Background The First Street Bridge was built over 40 years ago in 1972 and serves as an important north-south link over the Assiniboine River and the CPR mainline tracks in Brandon, Manitoba. Regular inspections of the bridge by Manitoba Infrastructure and Transportation (MIT) revealed significant concrete deterioration in the deck and substructure. Initially set as rehabilitation project, preliminary design work found that both the girders and substructure units would require strengthening and that the piers adjacent to the rail line would require additional protection (Figure 1). After careful consideration it was determined that the benefits to replace the bridge outweighed those to rehabilitate it (Figure 3). FALL 2015 NEWSLETTER Public and Stakeholder Interests In 2014 and 2015, the study team spoke with individuals and stakeholder groups about the proposed work in order to ensure a full perspective was taken into consideration when deciding on a preferred option and in preparing a design. Participants included: Various departments of the City of Brandon Nearby residents and businesses Local emergency services Brandon School Division (transportation division) CP Rail Utilities such as Manitoba Hydro, MTS, and local cable companies Active transportation interests Members of the general public that attended a Public Open House for the project Construction and Timing The project is now underway and will take approximately two years to complete (December 2017) (Figure 2). The first bridge (northbound) is scheduled to be completed by November 2016, weather permitting, with the second bridge (southbound) expected to be completed by November 2017. Minor site cleanup may take place in the early summer of 2018. The northbound section is being demolished and rebuilt first, followed by the southbound side. Traffic Management One lane of traffic in each direction will be maintained at all times during construction (Figure 4). Pacific Avenue will be closed at First Street for the duration of the project. O N D J F M A M J J A 2015 S O 2016 J F M A M J J A S O N D 2017 N D FIRST STAGE DETOUR AND DEMOLITION FIRST STAGE CONSTRUCTION Northbound Bridge SECOND STAGE DEMOLITION SECOND STAGE CONSTRUCTION Southbound Bridge Figure 2 CONSTRUCTION COMPLETION J 2018

Upload: buidan

Post on 02-May-2018

233 views

Category:

Documents


2 download

TRANSCRIPT

Figure 1

FIRST STREET BRIDGE REPLACEMENT (BRANDON)

Project BackgroundThe First Street Bridge was built over 40 years ago in 1972 and serves as an important north-south link over the Assiniboine River and the CPR mainline tracks in Brandon, Manitoba.

Regular inspections of the bridge by Manitoba Infrastructure and Transportation (MIT) revealed significant concrete deterioration in the deck and substructure. Initially set as rehabilitation project, preliminary design work found that both the girders and substructure units would require strengthening and that the piers adjacent to the rail line would require additional protection (Figure 1). After careful consideration it was determined that the benefits to replace the bridge outweighed those to rehabilitate it (Figure 3).

FALL 2015 NEWSLETTER

Public and Stakeholder InterestsIn 2014 and 2015, the study team spoke with individuals and stakeholder groups about the proposed work in order to ensure a full perspective was taken into consideration when deciding on a preferred option and in preparing a design. Participants included:

•Various departments of the City of Brandon

•Nearby residents and businesses

•Local emergency services

•Brandon School Division (transportation division)

•CP Rail

•Utilities such as Manitoba Hydro, MTS, and local cable companies

•Active transportation interests

•Members of the general public that attended a Public Open House for the project

Construction and TimingThe project is now underway and will take approximately two years to complete (December 2017) (Figure 2). The first bridge (northbound) is scheduled to be completed by November 2016, weather permitting, with the second bridge (southbound) expected to be completed by November 2017. Minor site cleanup may take place in the early summer of 2018.

The northbound section is being demolished and rebuilt first, followed by the southbound side.

Traffic ManagementOne lane of traffic in each direction will be maintained at all times during construction (Figure 4). Pacific Avenue will be closed at First Street for the duration of the project.

O N D J F M A M J J A2015

S O2016

J F M A M J J A S O N D2017

N D

FIRST STAGE DETOUR AND DEMOLITION

FIRST STAGECONSTRUCTION

Northbound Bridge

SECOND STAGE DEMOLITION

SECOND STAGECONSTRUCTION

Southbound Bridge

Figure 2

CONSTRUCTION COMPLETION

J2018

Inquiries can be submitted to [email protected]

Figure 3

Tying in roadworks at each end of the new bridge

Designing the bridge for greater clearance over the CP tracks and wider distance between the piers and the tracks

Sidewalks on each side of the bridge.

Existing four-lane design will be replaced with two separate bridges, with two lanes on each bridge

ROSSER AVENUE

SE

CO

ND

ST

RE

ET

This median opening will be closed during construction

GAS STATION

Gas station egress during construction

Southbound gas station access during construction

This back lane will be closed during the project

Contacts

Project website:www.landmarkplanning.ca/current-projects.php or www.gov.mb.ca/mit/wcs/constructionproj.html

Ruth J. Eden, M.Sc., P.Eng. Director of Structures Manitoba Infrastructure and Transportation 204-945-5058 [email protected]

Donovan Toews, MCP, MCIP Landmark Planning & Design 204-453-8008 [email protected]