florida gas transmission mainline hydrostatic test

22
Florida Gas Transmission Mainline Hydrostatic Test From the Golden Glades Interchange to the interchange of NW 122 nd Street with the Palmetto Expressway Miami-Dade County

Upload: sonel

Post on 23-Feb-2016

28 views

Category:

Documents


0 download

DESCRIPTION

Florida Gas Transmission Mainline Hydrostatic Test. From the Golden Glades Interchange to the interchange of NW 122 nd Street with the Palmetto Expressway Miami-Dade County. Today’s Outline. Who is Florida Gas Transmission (FGT)? Why is FGT testing? What is the test exactly? - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Florida Gas Transmission Mainline Hydrostatic Test

Florida Gas TransmissionMainline Hydrostatic Test

From the Golden Glades Interchange to the interchange of NW 122nd Street

with the Palmetto Expressway Miami-Dade County

Page 2: Florida Gas Transmission Mainline Hydrostatic Test

2

Who is Florida Gas Transmission (FGT)?

Why is FGT testing?What is the test exactly?When will the test occur?Where will the test take place?How will the test be conducted?How will the test affect me?

Today’s Outline

Page 3: Florida Gas Transmission Mainline Hydrostatic Test

3

Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf

Provide all of the natural gas for power generation in Miami-Dade County

18” diameter Mainline serving South FloridaCustomers include:

Electric utility companies Local distributors Industrial clients

Florida Gas Transmission Company

Page 4: Florida Gas Transmission Mainline Hydrostatic Test

4

The U.S. Department of Transportation regulates all interstate pipelines

Testing is federally mandatedBest practice to confirm the safety

and reliability of the pipeline Safety is our #1 priority Ensure continued superb customer

service

Need for the Test

Page 5: Florida Gas Transmission Mainline Hydrostatic Test

5

Hydrostatic Test Remove the natural gas from the line• Controlled release vents harmlessly into

atmosphere• Service is maintained on another system

Test the integrity of the pipeline by filling the line with water• Put the water under pressure for a fixed

period of time

Nature of the Test

Page 6: Florida Gas Transmission Mainline Hydrostatic Test

6

Hydrotesting the 18” Mainline systemStandard, common pipeline test

procedureRecent, successful 18” Mainline tests

were completed in: Saint Lucie Palm Beach

Last Miami-Dade test done April 2011

Background

Martin Broward

Page 7: Florida Gas Transmission Mainline Hydrostatic Test

7

Public Awareness Campaign

Project Process

Begin Project

Obtain Permits

Prepare System for

TestingConduct

HydrotestEnd Project

Page 8: Florida Gas Transmission Mainline Hydrostatic Test

8

TASK DATECommunity Awareness November 2013 – May 2014

Permit Applications November 2013 – February 2014System Preparation January 2014 – February 2014

Test Preparation February 2014 – March 2014Conduct Hydrotest 16 April 2014

Test window is set: Early morning Wednesday 16 April 2014

Coordinated with FP&L and regulators

Project Schedule

Page 9: Florida Gas Transmission Mainline Hydrostatic Test

9

Total Project Length = 10.2 miles Begin: Golden Glades Interchange End: NW 122nd Street

Generally, along the Palmetto ExpresswayWithin the limits of:

City of Miami Gardens Town of Miami Lakes City of Hialeah Unincorporated Miami-Dade County

Project Location

Page 10: Florida Gas Transmission Mainline Hydrostatic Test

10

Project Location (con’t)

Project Limit

Project Limit

N

Page 11: Florida Gas Transmission Mainline Hydrostatic Test

11

Remove natural gas from the 18” Mainline Completed the week before the hydrotest

Fill the line with waterPressurize the system

Normal operating pressure is 722 PSI Test pressure is up to 1,444 PSI• Relatively short duration (approx. 30 minutes)

Reduce to intermediate pressure at 1,108 PSI•Maintain for 8 hours

How the Test is Performed

Page 12: Florida Gas Transmission Mainline Hydrostatic Test

12

De-pressurize the lineDrain the water from the systemIf any integrity issues are found:

They are corrected as soon as possible The hydrotest is performed again• Any re-testing must be performed within the

prescribed test window timeframeResume normal natural gas service

How the Test is Performed (con’t)

Page 13: Florida Gas Transmission Mainline Hydrostatic Test

13

Safety is our #1 priorityPerformed extensive test

preparations, including an inspection of the entire system

Any pipe anomalies will be repaired in advance of conducting the hydrotest

For the duration of the high pressure test, as a safety consideration, we plan to isolate sections of the pipeline route from people and traffic

Safety During the Test

Page 14: Florida Gas Transmission Mainline Hydrostatic Test

14

Advance Preparations Make all key stakeholders aware• Adjacent property owners• Emergency service providers•General driving public

Announcements• Flyers, newspaper, FL511, website, etc.

Dynamic message signs• 2 weeks in advance

Conducting the Test

Page 15: Florida Gas Transmission Mainline Hydrostatic Test

15

Night of the Test Begin at midnight Close ramps/roads/lanes with barricades Law enforcement support Confirm all-clear along the 10.2-mile

corridor Conduct hydrotest Reopen roadways at approximately 4:00

AM

Conducting the Test (Con’t)

Page 16: Florida Gas Transmission Mainline Hydrostatic Test

16

General Utility Permit from the Florida Department of Transportation is in process

Officers will be stationed at ramp and road closures and at detours

Traffic will be detoured from: Turnpike I-95 Palmetto Expressway

Traffic Control During the Test

Page 17: Florida Gas Transmission Mainline Hydrostatic Test

17

Project Location – District 1

Page 18: Florida Gas Transmission Mainline Hydrostatic Test

18

Project Location – District 13

Page 19: Florida Gas Transmission Mainline Hydrostatic Test

19

Project Location – District 12

Page 20: Florida Gas Transmission Mainline Hydrostatic Test

20

Please visit our website:www.fgthydrotest.comOr contact FGT:

Mr. Terry Coleman2405 Lucien Way, Suite 200

Maitland, FL 32751Toll Free – 844.FGT.INFO

(844.348.4636)Office – 407.838.7054Fax – 407.838.7052

Email – [email protected]

For More Information

Page 21: Florida Gas Transmission Mainline Hydrostatic Test

21

FGT 18” Mainline Hydrotest Summary

Federal mandate Testing with water Test window is set for

Wednesday 16 April 2013

Midnight – 4:00 AM 10.2 mile section of

pipe Detours for Turnpike,

I-95, Palmetto Expressway

Law enforcement support

Project Limit

Project Limit

N

Page 22: Florida Gas Transmission Mainline Hydrostatic Test

Thank You

22