Transit Oriented Development: from planning to implementation

C H R I S T O P H E R Y A K E – N E L S O N N Y G A A R D

Page 2: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

overview

•The “P” Word: A little history/background

•Doing more with less: Strategic planning

•Planning is not enough: Implementation

•4 key takeaways

Page 3: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here”: a short history of the “P” word

•Voted Republican 1968-1984

•Vast majority supported Vietnam War

•Popular Gov Tom McCall (R) in office

•Traditional transportation approach…

Page 4: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 5: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Moses’ Plan for Portland

Page 6: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

divide neighborhoods with divided highways

Page 7: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

mt. hood freeway

Page 8: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

State/local bipartisan revolt

•Diverts freeway $ to light rail

•1973 Oregon Land Use Laws –enables Urban Growth Boundary

•1979 Metro Council elected (first in nation)

•Broad coalition of urbanists, environmentalists, agriculture, forestry

•Invest in transportation choices…

Page 9: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 10: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 11: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

10

12

14

16

18

20

1985 1990 1995 2000 2005 2010

Spokane Boise Denver Portland

Per Capita Vehicle Miles Traveled

Page 12: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”:

Page 13: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

Page 14: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

•Privately funded regional land use and transportation plan

Page 15: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

•Privately funded regional land use and transportation plan

•Highest transit spending per capita in the nation

Page 16: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

•Privately funded regional land use and transportation plan

•Highest transit spending per capita in the nation

•Only region building light rail, BRT, commuter rail and streetcar at the same time

Page 17: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

•Privately funded regional land use and transportation plan

•Highest transit spending per capita in the nation

•Only region building light rail, BRT, commuter rail and streetcar at the same time

•2012: 73 percent voted for Gov. Romney

•The new “Zion” of transit has moved to…

Page 18: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“We can’t do that here…”: guess the region

•Privately funded regional land use and transportation plan

•Highest transit spending per capita in the nation

•Only region building light rail, BRT, commuter rail and streetcar at the same time

•2012: 73 percent voted for Gov. Romney

•The new “Zion” of transit has moved to…

Page 19: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Planning for TOD

Page 20: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

We have done this before…

Page 21: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

why a strategic plan?

• Expanding system =

expanding eligibility

• Differentiate areas

by measuring TOD

readiness

• Target TOD

investments

11/27/2013 21

Page 22: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

$1.6 $2.9 12

93

TOD Program Funding & Eligible Areas 1998-2010

Funding (millions) eligible areas (sq miles)

1998 2010

Page 23: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

building a TOD typology Transit Orientation

Score (Urban Form + Activity )

11/27/2013 23

+ Market Strength

Page 24: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

dollars

distance destinations

distinction

demographics

The traditional trinity of TOD

density

diversity design

11/27/2013 24

Page 25: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

people

performance ped/bike connectivity

places physical form

11/27/2013 25

Potential (market)

measuring TOD readiness (p’s)

Page 26: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

people

11/27/2013 26

Page 27: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

“There are two things Oregonians

hate…. sprawl..

Former (& current) Oregon Governor John Kitzhaber

..and density.”

the “d” word

Page 28: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

places

11/27/2013 28

Page 29: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

ped/bike connectivity

11/27/2013 29

Page 30: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

performance

11/27/2013 30

Page 31: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

physical form

11/27/2013 31

Page 32: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

People

Pedestrian/Bicycle

Physical Form Places

Performance

Page 33: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 34: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 35: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 36: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 37: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 37

transit orientation score

Page 38: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 38

Page 39: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 39

Page 40: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 40

Page 41: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 41

Page 42: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 43: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 43

outer station areas for analysis

Typology (market + TOD Score)

Green Interstate Airport Westside Eastside Milwaukie

Page 44: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Station Community Typology (market + TOD Score)

11/27/2013 44 Green Interstate Airport Westside Eastside Milwaukie

Page 45: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 45 Green Interstate Airport Westside Eastside Milwaukie

Station Community Typology (market + TOD Score)

Page 46: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Plan + Partner (longer term station areas)

11/27/2013 46 Green Interstate Airport Westside Eastside Milwaukie

Page 47: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Plan + Partner (longer term station areas)

11/27/2013 47

Page 48: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Catalyze + Connect (emerging station areas)

11/27/2013 48 Green Interstate Airport Westside Eastside Milwaukie

Page 49: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Catalyze + Connect (emerging station areas)

11/27/2013 49

Page 50: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Infill + Enhance (near term station areas)

11/27/2013 50 Green Interstate Airport Westside Eastside Milwaukie

Page 51: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Infill + Enhance (near term station areas)

11/27/2013 51

Page 52: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 53: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 53

Page 54: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Implementing TOD

Page 55: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

TOD Implementation Program

• Program created in 1998 • $3 mill annual budget • Public-private “bricks and

mortar” projects tied to transportation outcomes

• > 500,000 induced annual transit trips

• $30 mill has leveraged > $300 mill private investment

11/27/2013 55

Page 56: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

TOD Program Strategies

• Create market comparables for higher density buildings near transit and centers

• Develop developers with expertise in higher-density mixed-use buildings in suburban settings

• Increase acceptance of urban style buildings through high quality design

• Carry out place making and contribute to local identity

Page 57: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Grants/easements

• compact mixed use

development is not cheap!

• acquire tod easements

• Cost premiums:

- structured parking

- elevator

- separation of uses

- complex fire systems

Page 58: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

how does it work? 1. Cost Premium Analysis

2. Capitalized Farebox Revenue from induced ridership (must have delta, daily transit fare x 30 years)

3. 7-day notice to Metro Council (de-politicizes funding decisions)

4. Development Agreement

Page 59: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

projects

Page 60: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks
Page 61: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

Example Projects

North Main Village – City of Milwaukie

Page 62: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

The Rocket – Central City Portland

Page 63: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

The Merrick - Portland

Page 64: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

The Crossings - Gresham

Page 65: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

program results 2,091 housing units

Nearly 250,000 sq ft commercial

> 100,000 tons of GHG reduced 543,000 Induced

Transit Riders Per Year

nearly 1,000 affordable units

and more than 300 senior units

20 built projects (10 in pre-development)

$318 million in private investment

2008 National APA Best Practices Award

Page 66: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

4 Takeaways • Development oriented

transit • Not all stations areas are

created equal • Support transit with

other investments ($.50 for every $1)

• Engage the private sector

early, often and forever

Page 67: from planning to implementation · 2020-03-30 · Implementing TOD . TOD Implementation Program • Program created in 1998 • $3 mill annual budget • Public-private “bricks

11/27/2013 67

q + a