fs final 10.2012

Upload: bogdan-fociac

Post on 04-Jun-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/13/2019 FS final 10.2012

    1/117

    2012

  • 8/13/2019 FS final 10.2012

    2/117

    September 20, 2012 [FEASABILITY STUDY]

    I. General Information:

    1. Project Name:

    Construction

    and

    development

    of

    a wind

    farm

    in

    the

    commune

    of

    Dolhesti

    and the city of Liteni, Suceava county;

    2. Location: commune Dolhesti and Liteni city, Suceava county; 3. Beneficiary: S.C ULLI ROWIND S.R.L; 4. General engineering company: S.C Vector Consult A.S.D. S.R.L 5. Financing sources : Own funds, coopted funds; 6. Project No.: 85 / 10.2012

    7. Planning Certificate No. :27/05.12.2011; 30/29.12.2011 issued by Dolhesti commune; 8. Planning Certificate No.: 42/18.05.2011; 7/27.01.2012 issued by Liteni city;

    II. Investment Description:1. Current status

    The beneficiary of the present investment, namely, S.C ULLI ROWIND S.R.L, after a complete survey over the green energy market in Romania and after several wind studies and measurements done in the proposed location that is studied in the current documentation, has decided to start the development of the investment for a wind farm in the LiteniDolhesti region.

    According to the solution study made by the beneficiary, for this emplacement a request for 30 MW allocation was made in the National Energetic System ( SEN), with the possibility to upgrade until a total capacity of 80 MW.

    The option studied in the present feasibility study, is that of a 30 MW wind farm located in the periphery of Dolhesti commune and in the periphery of Liteni city.

  • 8/13/2019 FS final 10.2012

    3/117

    September 20, 2012 [FEASABILITY STUDY]

    2. Proposed situation

    The area selected for the development of the wind farm, it is located in the periphery of Dolhesti commune (approx. at a distance of 1,4 km from the building fund of the Dolhestii Mari village) and in the periphery of Liteni city (approx. at a distance of 0,9 km from the building fund of the Corni village and approx. at 0,7 km from the building fund of the Rotunda village).

    The area proposed for the wind farm is located on the peak of two hills (Hill Plesului and Hill Rotunda), benefiting from a good wind area and free of obstacles. For a better emplacement of the turbines and to properly mount them it was decided to split up the wind farm in two modules:

    Module 1: emplaced on the Liteni city land, it will be comprised of 6 wind turbines with a 3 MW capacity ( surface studied in the PUZ 65 ha);

    Module 2: emplaced on the Dolhesti commune, it will be comprised of 4 wind turbines with a 3 MW capacity ( surface studied in the PUZ 45 ha);

    The zones that are studied in the two Zonal Urban Plans could allow additional turbines to be emplaced ( namely 7 more), in the case that the beneficiary will consider such a case.

    The area selected for the emplacement of this wind farm presents several advantages, related to the high voltage transport lines, namely:

    LEA 20kV ( to the South of the studied area, on the Dolhesti commune, but also to the North in the Liteni city);

    LEA 110 kV ( to the West of the studied area, on the territory of Preutesti commune); LEA 220 kV ( to the North and North East of the studied area, on the territory of the Liteni

    city);

    Also in the close vicinity of the proposed wind farm, a EON substation is located in the Dolhasca

    city (approx. 14 km). This close vicinity to the high voltage grid lines and the substation will facilitate

    the grid connection of the proposed wind farm, reducing the costs generated by this.

    3. Technical Information about the investment 3.1 Area and location

    Module 1 periphery Liteni city

    The topographic configuration of the land from the studied zone is cvasiplan, with height

    differences between +384m and +428m.

    GEOGRAFICALLYthe area in which the investment will be located is part of the morpho

  • 8/13/2019 FS final 10.2012

    4/117

    September 20, 2012 [FEASABILITY STUDY]

    corner period ....................................................................Tc = 0,7 sec;

    the region falls in the rate 6 seismic region after Msk scale.

    The studied zone presents several landslides, located on the East and South East of the Rotunda

    Hill.

    Also the land presents several characteristics improper for foundations, this creating the need for

    additional works to stabilize the land. The current area is used at the moment for crops. Because of

    this factor, during construction phase (for the turbine emplacements, for the technical spaces and for

    the access roads) it will be necessary to remove the green cover, and replace it with a proper

    mechanically stabilized layer.

    Module 2 periphery Dolhesti commune

    The topographic configuration of the land from the studied zone is cvasiplan, with height

    differences between +459m and +496m.

    GEOGRAFICALLY, the area in which the investment will be located, is part of the morpho

    structural unit of Podisul Moldovei, subunit of the Podisul Sucevei, characterized by landscape

    characterized by low hills and mostly covered by woods; The region is severed by the Somuzul Mare

    valley ( generally oriented from West to East).

    The form of the parcels in the field is an irregular one.

    According to the norm P.100/1 2006, the area surrounding the Liteni city is characterized by

    the fallowing values:

    ground acceleration .............................................................ag = 0,16;

    corner period ....................................................................Tc = 0,7 sec;

    the region falls in the rate 6 seismic region after Msk scale.

    The land studied does not have any particular geophysical characteristics, because of this there is

    no need for special works regarding land improvement. At the moment the studied zone is used as

    grazing land

    3 2 The legal status of the land

  • 8/13/2019 FS final 10.2012

    5/117

    September 20, 2012 [FEASABILITY STUDY]

    The access road to the wind farm will be made by rehabilitation and modernization of the current communal road DC 6, for a length of 1180,87 m, and a width of the carriageway of 5

    m with 2 X 0,75 shoulders; Internal roads of the wind farm will be made on the land owned by the city of Liteni on a

    surface of 16589 sqm;

    Modul 2 extravilan comuna Dolhesti

    The studied land is part of the public domain of the Dolhesti commune:

    4 of the turbines will be placed on land owned by the Dolhesti commune ( 4 X 500 sqm permanently occupied; 4X 2500 sqm occupied only during construction phase);

    The technical space will be placed on land owned by the Dolhesti commune ( 2 X 5000 sqm); The access road to the wind farm will be made by rehabilitation and modernization of the

    current communal road DC 6, for a length of 2801,87 m, and a width of the carriageway of 5

    m with 2 X 0,75 shoulders and also by rehabilitation and modernization of the service road

    DE 6A , for a length of 2231,64 m, and a width of the carriageway of 5 m with 2 X 0,75

    shoulders; Internal roads of the wind farm will be made on the land owned by the Dolhesti commune on

    a surface of 7414 sqm;

    3.3 Field studies

    The beneficiary provided to the general engineering company the fallowing studies, regarding the

    proposed emplacement of the wind farm:

    - Topographical survey; - Geotechnical study general study; - Technical expertise for the access road; - Verification report of the geotechnical study; - Solution study for SEN insertion

    3.4 Main characteristics of the constructions

    The investment for developing a wind farm in the Dolhesti Liteni region its a complex project,

    which will require the close cooperation from several specialties. The construction works needed for

  • 8/13/2019 FS final 10.2012

    6/117

    September 20, 2012 [FEASABILITY STUDY]

    This intersection between the county road DJ 208 and the communal road DC 6 will need to be

    redesigned in order to accommodate the oversized transport vehicles.

    The access road will need to undergo the fallowing intervention s in order to facilitate the access of

    the oversized transport loads:

    - Widening of the communal road DC 6 from the intersection with the county road DJ 208 for a length of 134 m;

    - Reshaping, widening, ballasting and road paving with asphalt of the communal road DC

    6

    for

    a

    length

    of

    2533,15

    m;

    - Reshaping, widening, ballasting of the communal road DC 6 for a length of 134,72 m; - Reshaping, widening, ballasting and road paving with asphalt of the communal road DC

    6 for a length of 1180,87 m; - Construction of stabilizing walls for a length of 2 X 195 m; - Construction of stabilizing walls for a length of 1140 m; - Works for stabilization of the Rotunda Hill for a length of 1140m;

    - Reshaping, widening, ballasting of the service road DE 6A for a length of 2231,64 m; - Replacement of old culverts and mounting new ones where is the case (10 pcs.); - Arrangement of grooves and shoulders of the access roads for their entire length;

    The construction of the access road will be made in order to have the fallowing road structure:

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 2 X 0,5 m; - Layer of Asphalt concrete ( rough) BAR 16 of 5 cm thickness ( in the places where the

    technical solution imposes it);

    Also on the area through which the access road leads to the module 1 of the wind farm, additional

    stabilization works will be done for a length of 1180,7 m ( this works will be comprised of planting

    shrubs that will help stabilize the Rotunda Hill).

    Internal roads for the two models that make the current wind farm

    The access in the t o mod les of the ind farm is pro ided as fallo s:

  • 8/13/2019 FS final 10.2012

    7/117

    September 20, 2012 [FEASABILITY STUDY]

    The roads layout will also be used to lay down the interconnection infrastructure for the two

    modules (high voltage cables, data cables, etc.).

    Works for stabilizing the Rotunda Hill

    Taking in consideration the unstable character of the East and South East part of the Rotunda Hill,

    several works for hill stabilization will have to be done, specifically in the area in which two of the six

    turbines that make up the module 1 Liteni will be installed.

    Works to arrange site organization

    I order to properly arrange the site organization and in order to have a proper storage area for the

    equipment that makes a turbine (the tower, nacelle, rotor, blades, etc.), a technical space was

    considered. This technical space is located on Dolhesti commune land, has a surface of 22 ha, it is

    located on the route of the access road and it is roughly in the middle of the two modules that

    comprise the wind farm ( approx. 1 km from Module 1 Liteni and 2 km from Module 2 Dolhesti).

    Construction works needed for emplacing and mounting of the wind turbines

    For the two modules of the wind farm, the beneficiary took in consideration the same type of

    turbines, namely wind turbines of 3 MW ( with a power factor between 0,9 and 0,95 imposed by

    the solution study that was approved in the EON MOLDOVA CTE).

    The specific characteristics of these turbines will be detailed in the specialized technical

    memorandum ( that is annexed to the present study).

    In conclusion, in the field, for each turbine, a foundation with a diameter of 22 m will be made

    (permanent surface occupied by this is 380 sqm.). Also during the construction phase for the

    foundations, the necessary cabling works (high voltage and data transmission) will be executed in

    order to facilitate a proper work flow for the interconnection of the wind turbines. The effective

    surface allocated to each turbine (specified in the tabulation papers) will be of 500 sqm. During the

    construction phase a larger area will be available for the site organization for each turbine ( this is

    specified in the public private partnerships done with the commune of Dolhesti and Liteni city and

    also in the contracts made with private owners) to allow proper conditions for the mounting of the

    turbine ( 3000 sqm. for each turbine).

    The layout of the electric cables will fallow the route of the roads in order to avoid additional

  • 8/13/2019 FS final 10.2012

    8/117

    September 20, 2012 [FEASABILITY STUDY]

    The beneficiary, S.C ULLI ROWIND S.R.L, has a solution study that analyzes the possibility to connect a

    wind farm with a capacity of 30 MW in the region of Liteni Dolhesti into the National Energy System

    (SEN);

    The analysis done by the specialty engineers, propose as a solution for insertion into the SEN

    network the construction of a 110/MT substation in the location of the wind farm, and an

    interconnection cable between this substation and EON 110 kV substation in Dolhasca ( high voltage

    line, cable section 185 mm, length of approx. 14 km).

    If

    the

    beneficiary

    should

    choose

    to

    extend

    the

    production

    capacity

    of

    the

    current

    wind

    farm,

    he

    can

    do so, having at his disposal an additional solution study that allows a total capacity of 80 MW in the

    Dolhesti Liteni region, with insertion solution into SEN at same 110 kV EON substation in Dolhasca.

    All categories of works described above, will be detailed in the Technical specialties memorandums that are annexed to the present study.

    3.5 The current situation of utilities in the region

    In the areas where the two modules of the wind farm will be emplaced, no networks for sewers,

    water supply or gas are present.

    The high voltage networks ( 20 kV, 110 kV and 220 kV lines) are situated at a safe distance from

    the wind farm ( from both modules) and will not interfere with the construction procedures of the

    wind farm.

    The interconnection cable, the low voltage lines and one telecommunication line will have to be

    taken in consideration during the engineering phase.

    3.6 Environmental impact assessment conclusions

    By making this park the beneficiary will take into account all the factors of pollution which could

    have a negative impact on the two communities.

    Protection areas for these types of systems have been studied in PUZ documentations performed

    for the two modules Dolhesti and Liteni.

    In both PUZ we can observe the location of the two modules of the wind farm has taken into

    account the development priorities of the two communities (commune of Dolhesti and Liteni city)

  • 8/13/2019 FS final 10.2012

    9/117

    September 20, 2012 [FEASABILITY STUDY]

    Air protection

    technological

    equipment

    used

    during

    construction

    and

    operation

    will

    comply

    with

    HG.

    743/2002

    laying down the procedures for type approval of internal combustion engines, for non road mobile machinery and establish measures to limit the emission of gaseous and particulate pollutants from these.

    Protection of soil and subsoil:

    Temporary storage lands will be distinct, depending on their nature and function you need to head;

    Safe storage of construction materials (not to be driven by wind and rain) and removal of the waste land;

    Ensure retention of waste in secure storage spaces, filling them with inert materials.

    III. Economic evaluation;.

    To achieve the economic model of this investment has been taken into account these economic

    data:

    Description Value SourceCapital cost 1800000 euro/ MW installed This price is evaluated

    according to the European market green energy. This price includes the value of

    infrastructure

    works,

    installations and equipment.

    Operation and maintenance costs

    9 euro/ MWh European specialized industry average

    Green Certificates ( trading operator OPCOM)

    2 pcs / MWh X 50 euro / pcs 100 euro/ MWh

    Green certificates are granted by the Romanian state subsidies for green energy production.

    Selling energy to EONFurnizare

    45 euro / MWh The average value obtained when concluding a PPA (this value is an average of the current market, it is subjective, as an agreement concluded as PPA features some

  • 8/13/2019 FS final 10.2012

    10/117

    September 20, 2012 [FEASABILITY STUDY]

    VAT

    0 2 3 4 5 6

    Chapter 1. Costs for obtaining and improving the land1.1 Obtaining the land 31,050 6,872 7,452 38,502 8,521

    1.2 7.590,000 1.679,761 1.821,600 9.411,600 2.082,904

    1.3 Design for environment protection and bringing to its original state 464,440 102,786 111,466 575,906 127,455

    8.085,490 1.789,419 1.940,518 10.026,008 2.218,880

    2.1 2.110,500 467,080 506,520 2.617,020 579,179

    2.110,500 467,080 506,520 2.617,020 579,179

    CHAPTER 3. Expenses for design and technical assistance

    135,000 29,877 32,400 167,400 37,048

    3.2 82,210 18,194 0,000 5,850 1,2953.3 1.661,161 367,635 398,679 2.059,839 455,868

    3.4 9,000 1,992 2,160 11,160 2,470

    3.5 126,000 27,885 30,240 156,240 34,578

    3,6 237,309 52,519 56,954 294,263 65,124

    3,7 593,272 131,298 142,385 735,657 162,810

    2.843,951 629,402 662,818 418,482 92,615

    CHAPTER 4. Basic investment expenditures

    4.1.1 roads rehabilitation and upgrading works 7.209,543 1.595,561 1.730,290 8.939,833 1.978,496

    4.1.2 foundations and earth moving works 11.232,000 2.485,781 2.695,680 13.927,680 3.082,368

    4.1.3 retaining wall, soil stabilization 1.067,120 236,167 256,109 1.323,229 292,847

    4.1.4 electrical installations 37.800,000 8.365,608 9.072,000 46.872,000 10.373,354

    4.1.5 0,000 0,000 0,000 0,000 0,000

    4.1.6 0,000 0,000 0,000 0,000 0,000

    4.1.7 0,000 0,000 0,000 0,000 0,000

    4.1.8 0,000 0,000 0,000 0,000 0,000

    4.1.9 0,000 0,000 0,000 0,000 0,000

    57.308,663 12.683,117 13.754,079 71.062,742 15.727,065

    0,000 0,000 0,000 0,000 0,000

    0,000 0,000 0,000 0,000 0,000

    180.000,000 39.836,229 43.200,000 223.200,000 49.396,924

    180.000,000 39.836,229 43.200,000 223.200,000 49.396,924

    0,000 0,000 0,000 0,000 0,000

    0,000 0,000 0,000 0,000 0,000

    4.5.a Features 0,000 0,000 0,000 0,000 0,000

    4.5.b Other features 0,000 0,000 0,000 0,000 0,0000,000 0,000 0,000 0,000 0,000

    4.6 0,000 0,000 0,000 0,000 0,000

    0,000 0,000 0,000 0,000 0,000

    237.308,663 52.519,346 56.954,079 294.262,742 65.123,989

    CHAPTER 5. Other expenses

    1.012,104 223,991 242,905 1.255,009 277,749

    5.1.1 Construction (1.0%) 674,736 149,327 161,937 836,673 185,166

    Improving the land

    CHAPTER 2. Expenses for providing utilities needed for the objective

    Expenses for providing utilities necessary objective (ATR-SEN)

    Design and engineeringFees for obtaining permits, agreements and authorizations

    Total chapter 2

    4.3

    Technological equipment with mounting included

    Technological equipment mounting

    Technical assistance f rom the designer

    4.1

    4.3.1 - Technological equipment with mounting included ( 3 MW turbines)

    nr.crt.

    Name of chapters and subchapters of expensesvalue ( included VAT )value ( without VAT )

    thousands eurothousands RON thousands eurothousands RONthousands RON

    3.1

    total chapter 4.2

    Field studies

    Organization of procurement procedures

    4.2

    total chapter 4.1

    4.2.1 - Technological equipment mounting

    Project supervisor

    5.1

    4.4

    Total chapter 4

    4.5

    4.4.1

    total chapter 4.6

    total chapter 4.5

    total chapter 4.4

    Site organization

    Machinery and transport equipment without installation

    Intangible assets

    1

    Consulting

    Total chapter 1

    Features

    Total chapter 3

    Buildings and facilities

    total chapter 4.3

  • 8/13/2019 FS final 10.2012

    11/117

    September 20, 2012 [FEASABILITY STUDY]

    Estimates and bill of quantities will be made after a complete technical project regarding all specialties involved.

    Summary of energy efficiency of the wind farm LiteniDolhesti

    Turbine type WinWinD WWD3 Number of installed turbines 10 Maximum hight 120 m Gross power cut ( MWh/year) 109008 Net power cut ( MWh/year) 92856,8

    Redacted Date

    Petrareanu C.

  • 8/13/2019 FS final 10.2012

    12/117

    September 20, 2012 [FEASABILITY STUDY]

    ANEXES:

    Written and drawn parts

    Technical documentation Turbine specifications WinWind WWD3 Technical report general considerations Technical report access roads Technical report electrical

  • 8/13/2019 FS final 10.2012

    13/117

    1(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

  • 8/13/2019 FS final 10.2012

    14/117

    2(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    Technical specificationContents1. General information .....................................................................................................................................4 2. General information of turbine electric systems ..................................................................................6 3. Power curve ...................................................................................................................................................7 4. Annual production of WWD-3/100 ............................................................................................................8 5. Noise level (IEC 61400-11) ..........................................................................................................................8 6. Detailed technical specification ................................................................................................................9 6.1. Tower ...............................................................................................................................................................9

    6.2. Rotor ................................................................................................................................................................9 6.3. Main bearing, planetary gear and generator. ........................................................................................9 6.4. Brake system ...............................................................................................................................................10 6.5. Glassfiber cover ..........................................................................................................................................10 6.6. Yaw system ..................................................................................................................................................10 6.7. Foundation ...................................................................................................................................................11 6.8. Grid connection ..........................................................................................................................................11 6.8.1. Transformer technical specification ......................................................................................................11 6.8.2. Switchgear, Electrical Characteristics ..................................................................................................13

    6.8.3 Frequency converter ....................................................................................................................................15 6.8.4 Reactive power control ...............................................................................................................................15 6.9. Turbine control, remote monitoring and reporting ............................................................................17 6.10. Presenting the production data on the Internet ..................................................................................18 6.11. Alarms ...........................................................................................................................................................18 6.12. Self-diagnosis of the wind turbine .........................................................................................................19 6.13. Condition monitoring .................................................................................................................................19 6.14. Lightning protection ..................................................................................................................................19 7. Earthing system ..........................................................................................................................................20

    8. Options ..........................................................................................................................................................20 8.1. Anti-icing of blades ....................................................................................................................................20 8.2. Aviation lights ..............................................................................................................................................20 8.3. Service Lift inside the Tower ...................................................................................................................20 8.4. High voltage switchgear ...........................................................................................................................21 9. Type Approvals ...........................................................................................................................................21 10 Transportation dimensions 24

  • 8/13/2019 FS final 10.2012

    15/117

    3(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    Date Revision Author RemarkApril 2004 1/2004 Eku Document createdSep 2004 4/2004 EKu An updateApr 2005 1/2005 EKu An updateMay 2005 2/2005 EKu Annual production addedOct 2005 3/2005 EKu An updateOct 2005 4/2005 EKu An update30.11.2005 5/2005 Iri Electrics update23.12.2005 1.0 GB General corrections/additions6.1.2006 1.1. EKu Power production corrected1.2.2006 1.2. EKu Power curve update20.3.2006 1.3 EKu 90 m power curve added30.8.2006 1.5 EKu General corrections/additions

  • 8/13/2019 FS final 10.2012

    16/117

    4(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    1. General information

    WinWinD has developed an innovative wind turbine for the market with itsWWD concept. WinWinDs basic values include customer satisfaction and

    the operational reliability of the products, as well as the win-win cooperationachieved between the clients and WinWinD.

    On the basis of thorough technical and economic research work the WWDconcept, which allows electricity to be produced with a new innovative inte-grated power unit, was created. The basis for design was efficiency, reliabil-ity and ease of maintenance which allows the WWD concept to offer themost cost-effective production throughout its total life, combined with thelowest operating costs.WWD-3 is pitch regulated upwind wind turbine with active yaw and three-blade rotor. The turbine consist of three main parts

    Rotor3 blades and hub, electrical pitch control

    Integrated power unitroller bearing, planetary gear and variable speedgenerator with permanent magnets

    Nacellefrequency converter, transformer and accessories

    The rotor hub is connected to the gearbox casing using a play-free double-row tapered roller bearing. The bearing transfers the rotor loads directly tothe main casing, keeping the drive train free from deformation and rotorloads. The planetary gear increases the rotating speed modestly and trans-fers the torque to the low speed permanent magnet generator. All connec-tion flanges are round and concentric resulting in clearly defined borders

  • 8/13/2019 FS final 10.2012

    17/117

    5(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    GeneralType 3 blades, up-windPower control Pitch, variable speedRated power 3000 kW (grid side)

    Rotor diameter 90 and 100 mCut-in wind speed 4 m/sRated wind speed 12,5 m/s (100 m)

    13 m/s (90 m)Cut-out wind speed 20 m/s (100 m)

    25 m/s (90 m)

  • 8/13/2019 FS final 10.2012

    18/117

    6(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    2. General information of turbine electric systems

    The WWD3-90m turbine has a water cooled permanent magnet synchro-nous generator.

    The frequency converter is also water cooled and installed in the nacelle.The frequency converter consists of two separate converter units. One con-verter unit is designed for 1,5MW and has 1500A IGBT-inverter units ongrid and generator side. This 2x1,5MW converter system is redundant, it ispossible to run only one 1,5MW converter if another converter is out of or-der. On the grid side there is an LC-filter for reducing harmonic currents.

    The main transformer is also installed in the nacelle. It is an oil-cooled fullyencapsuled version, reinforced internally to withstand vibration. Additionallyit stands on vibration dampers. Consequently all the cable connections aremade flexible. Cooling is by natural convection plus a thermostat-controlledadditional fan. The main transformer has five voltage tap settings (2x2,5%)to make a fine adjustment according to the local grid.

    Generator Synchronous machine

    Cooling Water jacket cooling around stator,Air cooling with air/water heat exchanger

    Rated gen. voltage 660 V

    Rated gen. frequency 49,2 Hz

    Frequency converter IGBT -Bridges on both generator and gridside

    Filter generator side dU/dt-Filter and common-mode filter

    Filter grid side LC Filter

  • 8/13/2019 FS final 10.2012

    19/117

    7(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    3. Power curve

    The guaranteed power curve with rotor diameter of 90 and 100 m.Air density 1.225 kg/m3. Transformer losses are not deducted.

    On the right side the thrust-coefficient (for wake calculations)

    v WWD-3/90 WWD-3/100m/s kW kW3 0 04 80 79

    5 220 2546 389 4587 627 7408 944 11179 1351 159510 1858 210311 2410 2505

    12 2873 287013 3032 303214 3032 303215 3030 303016 3030 303017 3030 303018 3030 3030

    19 3030 303020 3030 303021 303022 303023 303024 3030

  • 8/13/2019 FS final 10.2012

    20/117

    8(27)

    Document WWD-1003Prep. by EKUChecked by GB

    Ver 1.5 WWD-3 DETAILED TECHNICAL SPECIFICATIONAppr. by

    4. Annual production of WWD-3/100

    The calculated power production with rotor diameter 100 m.Air density 1.225 kg/m3, Weibull-C-factor = 2.Gross production (i.e. park losses, transformer losses, etc are not de-

    ducted).m/s MWh/a6,0 63606,5 75627,0 87327,5 9841

    5. Noise level (IEC 61400-11)

    The noise level values shall be guaranteed according the sales agreement.The noise guarantee will be regarded as fulfilled, if a measured soundpower level is lower or equal than the guaranteed value (the inaccuracy ofthe measurement result has been noticed in the process).

  • 8/13/2019 FS final 10.2012

    21/117

    WWD-3 Technical specification 9 (27)

    6. Detailed technical specification

    6.1. Tower

    Two different basic tower solutions are available. Steel tower andconcrete/steel hybrid tower.

    Hub height 88 m 90 m 100 mNumber of sections 4 1 + 2 1 + 2Colour of steel part RAL 7035 RAL 7035 RAL 7035Steel part height 84,5 m 49,5 m 49,5 mConcrete part height 36,5 m 46,5 m

    6.2. RotorThe rotor consists of three blades, hub and three electrical pitchdrives. The blades are made of epoxy resin reinforced glassfibre.The blades also act as aerodynamic brakes. Normally the bladesare synchronised but in case of an emergency, each blade can becontrolled individually. The pitch system is electric and equippedwith a back-up battery or capacitor. The blades are equipped withlightning conductors.

    6.3. Main bearing, planetary gear and generator.The rotor hub is connected to the gearbox casing using a play-free double-row tapered roller bearing. The bearing transfers the rotor through a part ofthe gear casing to the mainframe. The planetary gear increases the rotatingspeed modestly and transfers the torque to the low speed permanent mag-net generator. All connection flanges are round and concentric, resulting inclearly defined borders. This "black-box" design philosophy eases assem-bly and results in a well-defined load distribution. All possible deformationsdue to rotor loads have been taken into consideration when designing thegears.

    The bearing has, integrated with the gearbox, forced oil lubrication. A dou-ble radial shaft seal arrangement with grease filling in between seals to-

  • 8/13/2019 FS final 10.2012

    22/117

    WWD-3 Technical specification 10 (27)

    6.4. Brake system

    During emergency shutdown each rotor blade acts independently as anaerodynamic brake. The computer controls the system with the help ofanemometers, wind vane and other sensors.

    The stop procedures are:

    The normal stop : the blades synchronously driven into stormproofing position with a pitch speed of 4 degrees/s without us-ing the mechanical brakes.

    The emergency stop (low-level) : the blades are driven with 4deg/s to the end position and the mechanical disk brake is acti-vated at the same time. In case of grid failure the pitch powercomes automatically from the buffer battery

    The emergency stop (high-level) : the blades are driven witha certain pitch speed program. The mechanical brakes areused at the same time. In case of grid failure the pitch powercomes automatically from the buffer battery.

    Each blade is equipped with a back-up battery. If one of the blade pitchesfails, the synchronisation is turned off and each blade is driven separatelyto the storm position. In case of grid failure using the battery power shall beused.

    The system meets the standards of Germanischer Lloyd.

    6.5. Glassfiber cover

    Nacelle and hub cover are made of glassfiber sandwich. The colour is RAL7035 grey.

    6.6. Yaw system

  • 8/13/2019 FS final 10.2012

    23/117

    WWD-3 Technical specification 11 (27)

    6.7. Foundation

    The foundation is a gravity-based or pile foundation depending on the localground conditions.

    The tower is connected to the foundation by a cylindrical bolted flange.

    6.8. Grid connection

    The main transformer in the nacelle is manufactured to meet the nominalvoltage of the interconnection grid. The transformer has adjustable windingtaps 2x2,5% and the voltage of the high voltage grid must be within 5%of nominal voltage. Frequency variations within 3 Hz (50 Hz) can be han-dled. Intermittent or rapid grid frequency fluctuations may cause damage tothe turbine. For the fatigue loads, 400 grid failures within the turbines life-

    time have been assumed.

    6.8.1. Transformer technical specification

    NoteRated power of windturbine

    3000 kW on medium voltage side

    Voltage 1033 2x2,5% /0,690 kV Primary / secondary

    Phases 3Connection Dyn11 Delta/starzk 6 %Frequency 50 HzPower factor 0,951,00 Transformer HV-side

    Transformer type Silicon oil-transformerfor converter supplyPower losses Po 3 kW

    Pk 25 kWfull load, 75C reference

    Static shield Yes Between primary and secondary

  • 8/13/2019 FS final 10.2012

    24/117

    WWD-3 Technical specification 12 (27)

    active IGBT output

    bridge,Voltage = 690Vf sw = 3,6 kHzLC-filter between con-verter and transformer

    Total Harmonic Dis-tortion

    THD = 5 % (voltage)THD = 5 % (current)

    Between LC-filter and trans-former

    Vibration The transformer will beinstalled to the nacelleand good mechanicaldesign against vibrationis required.

    Cooling of transformer KNAN

  • 8/13/2019 FS final 10.2012

    25/117

    WWD-3 Technical specification 13 (27)

    6.8.2. Switchgear, Electrical Characteristics

    The medium voltage switchgear of the grid connection is located in thetower base. The SF6 insulated switchgear consists of switch-disconnector(s)and a transformer feeder circuit breaker. The switch-disconnector has 3 sta-ble positions: closed, open and earthed. The switchgear is designed so thatthe simultaneous closing of the switch or circuit breaker and the earthingswitch is impossible. The specification of the turbine switchgear is shown inthe table below.

    As an option are the following devices for the switchgear available: voltageindicator lamps, fast earthing switch (arc killer), manometer and raisingplinth.

    Rated voltage (kV) 12 24 36Network switch disconnec-

    torRated current (A) 630 630 630Breaking capacity (A no loadcable)

    30 30 25

    Making capacity (kApeak) 52,5 40 50Short-time withstand current(kArms 1 s)

    21 16 20

    Insulation level (50Hz 1 minkVrms)

    28 50 70

    Impulse voltage (kVpeak1,2/50 s)

    75 125 170

    Cable connection bushing type C 630A,disconnectableM16

    type C 630A,disconnectableM16

    please consultWinwind

    Transformer feeder circuitbreakerRated current (A) 200 200 630Breaking capacity (kApeak) 21 16 20Making capacity (kApeak) 52,5 40 50Insulation level (50Hz 1 min 28 50 70

  • 8/13/2019 FS final 10.2012

    26/117

    WWD-3 Technical specification 14 (27)

    Current, voltage and energy measurement unit can be located in towerbase if needed. The measurement unit specification is shown in table X.

    Table X. Measurement unit specification.

    Rated voltage (kV) 12 24 36Insulation air air SF6Current transformers(A)

    200-100/5/5class 0,2s

    200-100/5/5class 0,2s

    50-100/5/5class 0,5

    Voltage transformers(kV)

    10:3/0,1:3/0,1:3class 0,2

    20:3/0,1:3/0,1:3class 0,2

    30:3/0,1:3/0,1:3class 0,5

    Typical grid connection of WWD-3 wind turbine is shown in figure X. Thenumber of the switch-disconnectors depends on the supply grid type andthe number of the turbines in wind farm.

    Typical grid connection of WWD-3 wind turbine.

    h l f (

  • 8/13/2019 FS final 10.2012

    27/117

    WWD-3 Technical specification 15 (27)

    6.8.3 Frequency converter

    A liquid cooled IGBT frequency converter is used for connecting the vari-able speed generator to the grid. The frequency converter consists of twoparallel connected converters (2x1,5MW) in separate cabinets resulting arobust and redundant system. The voltage level of converter grid side is690V and the grid synchronization is automatic. The power factor of gen-erator and grid side converters is adjustable. The communication betweenoperation control computer and the converter is made by CANopen field-bus. Due the effective grid side filters, the total harmonic distorsion of thegrid side current is low (THD < 4%).

    6.8.4 Reactive power control

    The reactive power of WWD-3 turbine can be adjusted by the frequencyconverter. It is possible to control the grid side reactive power by followingwaysPower factor = 1,0 (default)Power factor < 1,0 according to max reactive power diagram. (Note that thediagram shows the maximum value and lower reactive power productioncan be agreed).

    The turbine is able to operate with a power factor of cos=0,95 (ind) tocos=0,95 (cap) with the nominal power. With partial loads the maximum

    reactive power diagram is shown in figure X. Note that if a power factor

  • 8/13/2019 FS final 10.2012

    28/117

    WWD-3 Technical specification 16 (27)

    WWD-3 Max reactive power

    -2500

    -2000

    -1500

    -1000

    -500

    0

    500

    1000

    1500

    2000

    2500

    0 500 1000 1500 2000 2500 3000 3500

    P (kW)

    Q (

    k V a r )

    Maximum reactive power of WWD-3 turbine on grid side at the networkconnection point.

    WWD 3 Technical specification 17 (27)

  • 8/13/2019 FS final 10.2012

    29/117

    WWD-3 Technical specification 17 (27)

    6.9. Turbine control, remote monitoring and reporting

    Each turbine has its own PLC, all the PLCs of the same park are con-nected into network. See picture below.

    VPN

    VPN VPN

    Production data-actual data-cumulative data

    WinWinD Web-server

    Production data Alarms and turbine control

    Remote access for WinWinDpersonnel to control the turbine

    TCP/IP Industrial busFiberoptic cables

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    VPN

    VPN VPN

    Production data-actual data-cumulative data

    WinWinD Web-server

    Production data Alarms and turbine control

    Remote access for WinWinDpersonnel to control the turbine

    TCP/IP Industrial busFiberoptic cables

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    TurbinePLC

    WWD 3 Technical specification 18 (27)

  • 8/13/2019 FS final 10.2012

    30/117

    WWD-3 Technical specification 18 (27)

    Data connection to the park can be made using broadband access, an

    ISDN connection, an analogue telephone line or a GSM connection. Themost recommended method is broadband.

    The production data is automatically retrieved from the wind turbine PLC tothe WinWinD Web-server. From the Web-server data can be made avail-able to customers.

    The turbine control software contains several state-of-art features, which al-lows optimisation of the production based on needs of the customer, for ex-ample production optimised or noise optimised power curves, etc.

    Wind turbines can be fully remote controlled, i.e. all the main functions canbe executed remotely.

    6.10. Presenting the production data on the Internet

    The system enables presenting the production data of the wind turbines onthe Internet. Access to the data can be free or a username with passwordcan be used. Thus the production data can be viewed regardless of theplace or time; the Internet-connection, however, is a necessity.

    WWD-3 Technical specification 19 (27)

  • 8/13/2019 FS final 10.2012

    31/117

    WWD-3 Technical specification 19 (27)

    6.12. Self-diagnosis of the wind turbine

    The wind turbine is equipped with an automatic monitoring system, whichcontinuously protects and controls the generator and the grid and adjuststhe settings according to the wind and weather conditions. This way thepower production can be optimised. During the cold season the sensorsmeasure the need for heating of the power unit and lubrication oil and en-sure a safe start.

    For case of a grid drop the wind turbine has an uninterruptible power sys-tem (UPS), which ensures the control for 60 minutes.

    The anemometer and wind vane of the wind turbine monitor the changes inthe wind and the technique starts and stops the plant according to the set-tings.

    6.13. Condition monitoring

    The mechanical reliability of the wind turbine is ensured with a conditionmonitoring system. E.g. vibration and temperature is measured by usingsensors. Condition monitoring system analyses the data received from thesensors and gives a warning to the turbine controller if alarm limits are ex-ceeded. Condition monitoring system provides trends, frequency spec-trums, time domain signals as well as technical details of the wind turbine toenable accurate analysis of possible faults.

    6.14. Lightning protection

    The most advanced lightning protection technology in the field is used. Thefollowing principles are applied

    Lightning conductor in each blade Optional registration cards Varistors and fuses in the terminal box of the generator Varistors and fuses on the connectors of the inverter Shielded sensor cables Overvoltage protection on the high voltage side of the transformer

    WWD-3 Technical specification 20 (27)

  • 8/13/2019 FS final 10.2012

    32/117

    WWD 3 Technical specification 20 (27)

    7. Earthing system

    The earthing system of WWD-3 turbine consists of a ring type earthingelectrode around the foundation in the soil and connection wires from thering to the flange of the tubular tower. The main earthing bus-bar is alsoconnected to the flange of the tower and the earth termination shall have aresistance 10 . The 50mm2 copper electrode is used as a electrode wireand the electrode joints in the soil shall be weld joined to get permanentand low-resistance connections. The earthing system must be designed for

    local soil conditions and if the resistance of 10 cant be met with ring typeelectrode, then ground rods must be added to the earthing system.The star point of the main transformer is earthed, which means that the tur-bine main circuit is a TN-system.

    8. Options

    8.1. Anti-icing of blades

    Ice sensors or an anti-icing equipment of the blades is available as an op-tion.

    8.2. Aviation lights

    The following aviation light options are available:

    1. Low intensity. Red 10-200 cd.2. Medium intensity. Red/white/dual 200-2000 cd.3. Medium intensity. Red/white/dual 2000-20000 cd.

    The options are designed according to the ICAO and the FAA codes.

    When installed in a wind farm, the obstruction light flashes can be synchro-nised throughout the whole wind farm.

    WWD-3 Technical specification 21 (27)

  • 8/13/2019 FS final 10.2012

    33/117

    WWD 3 Technical specification 21 (27)

    8.4. High voltage switchgear

    The high voltage switchgear can be delivered as well.

    9. Type Approvals

    The Design Assessment is the equivalent to the German Typenprfung. Itis a certification of the basic documents of the machine, stating that thesafety philosophy is correct, all safety devices and machine componentsare correctly dimensioned and the machine has the calculated lifetime of 20years.

    The WWD3 is being assessed by Germanischer Lloyd (GL). The designassessment is valid for the machine head (Rotor and Nacelle).

    The tower will be certified separately, because it is often designed site-specific. Winwind performs the tower certifications through TV Tech-nischer berwachungs Verein.

    CE Certificate of Conformity

    98/37/EC Machinery73/23/EEC Low voltage89/336/EC Electromagnetic compatibilitySFS-EN ISO 12100-1:2003 Safety of Machinery. Part 1: Basicconcepts, general principles for design. Basic terminology andmethodology

    WWD-3 Technical specification 22 (27)

  • 8/13/2019 FS final 10.2012

    34/117

    p ( )

    WWD-3 Technical specification 23 (27)

  • 8/13/2019 FS final 10.2012

    35/117

    WWD-3 Technical specification 24 (27)

  • 8/13/2019 FS final 10.2012

    36/117

    10. Transportation dimensions

    Please refer document WWD-3 transportation dimensions, access roadsand platforms

    11. Access roads and platforms

    Please refer document WWD-3 transportation dimensions, access roadsand platforms

    12. General Reservations, Notes and Disclaimers

    All data are valid at sea level (1,225 kg/m3). Periodic operational disturbances and generator power de-rating

    may be caused by a combination of high winds, low voltage or hightemperature.

    WinWinD recommends that the electrical grid is as close to nominalas possible with little variation in frequency.

    A certain time allowance for turbine warm-up must be expected fol-lowing a grid dropout and/or periods of very low ambient tempera-ture.

    All listed start/stop parameters (e. g. wind speeds and temperatures)are equipped with hysteresis control. This can, in certain borderlinesituations, result in turbine stops even though the ambient conditionsare within the listed operation parameters.

    WWD-3 Technical specification 25 (27 )

    13. General drawings

  • 8/13/2019 FS final 10.2012

    37/117

    Detailed Technical-specification WWD-3 ver 1.5.doc

    N.B,Site drawings are always site specific

    WWD-3 Technical specification 26 (27 )

  • 8/13/2019 FS final 10.2012

    38/117

    Detailed Technical-specification WWD-3 ver 1.5.doc

    N.B, Site drawings are always site spesific

    WWD-3 Technical specification 27 (27 )

  • 8/13/2019 FS final 10.2012

    39/117

    Detailed Technical-specification WWD-3 ver 1.5.doc

    Electrical drawings are always site specific

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    40/117

    General technical report

    1. General Considerations

    The beneficiary, SC Ulli ROWIND SRL, together with the general designer set the location of a total of 10 wind turbines, each with a capacity of 3 MW, in the localities Liteni and Dolhesti.

    Following wind measurements made to determine the optimal location the hills Rotunda and

    Plesului were chosen.

    After studying ways of access, ownership papers identified in the field a conclusion has been reached to establish two wind farm modules that will form Liteni Dolhesti investment, as follows:

    Module 1 Liteni, will contain a total of 6 wind turbines with an installed capacity of 3MW/turbine (PUZ studied area 65 ha);

    Module 2 Dolhesti, will contain a total of 4 wind turbines with a capacity of 3 MW/turbine (PUZ studied area 45 ha);

    Corroborating with the situation in the field with the one in the solution study, the data provided by the manufacturer of turbines has led to the following scheme selection area:

    Module 1 periphery Liteni city

    The land studied is in the public domain of the Liteni city but also some emplacements belong to private owners:

    4 of the wind turbines will be located on land owned by the Liteni city (4 X 500 m permanently occupied , 4 X 2500 m occupied during construction phase);

    2 of wind turbines will be located on private land owners (2 X 500 m permanently occupied , 2 X 2500 m occupied during construction phase);

    Technical space will be located on land owned by the city of Liteni (1 x 3000 m); The wind farm access road (to be achieved by upgrading and rehabilitation of communal

    road DC 6 over a length of 1180.87 m and a width of 5 m carriageway and shoulders of 2 X 0.75 m);

    Internal roads of the wind farm will be made on land belonging to the city of Liteni on an

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    41/117

    0.75 m, and the rehabilitation 6A service road over a length of 2231.64 meters, with a roadway width of 5 m and shoulders of 2 X 0.75 m);

    Internal roads of the wind farm will be made on land belonging to the commune of Dolhesti on an area of 7414 square meters.

    2. Technical Considerations

    Given the fact that the investment Building wind farms in LiteniDolhesti region takes place within the territory of two administrative units, technical documentation will treat each

    UAT separately, namely Module 1 to UAT LIteni city and Module 2 on UAT Dolhesti commune.

    To ensure investment in the area will be made the fallowing mandatory cadastral works:

    Verification of the tabulation / Properties papers available; It will bring up to date all land documents in accordance with the laws in force; It will get excerpts land for each parcel will be subject to investment; It

    will

    perfect

    the

    acts

    of

    sale

    or

    lease,

    considering

    all

    relevant

    legal

    provisions

    (private

    or

    public procurement);

    Also check documents certifying the right of access to the sites which form the wind farm; It will obtain, where appropriate, written agreement of the owners for access roads to the

    area, or to lay down power cables; It will follow the issuance of certificates of planning for the proposed investment; It will prepare zoning plans for defining local urban marker;

    It will prepare technical documentation needed to obtain the building permit, as well as technical and project execution details required in the construction phase.

    Coordinates of sites in STEREO 1970 for the wind turbines expected to be installed can be found in the table below:

    Module 1 Liteni

    Nr. Crt X Y Z

    1. 665116,988 615105,574 392,81

    2. 665399,724 615511,446 420,42

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    42/117

    Module 2 Dolhesti

    Nr. Crt X Y Z

    1. 665562,024 611567,758 462,63

    2. 665501,155 611960,160 488,57

    3. 665248,035 612290,535 490,95

    4. 665000,431 612595,413 471,23

    Wind turbines will be placed observing position to each other and distances of protection from the elements constructed or protected by law in the area, public roads, electricity transmission networks, irrigation channels and antennas (as defined in Regulation Technique concerning the delimitation of protection and safety for energy capacities published in the Official Gazette, part I,

    no. 865/18.12.2007). Title objective neighboring wind plant Protection Area

    -m-Safety Area

    -m-How the safe distance ismeasured

    Public roads of national interest orcommunal interest county public roads,public roads pavements, roads private utility

    1) 1) H2) + 3m3) 5) 6) 4) 4)

    Railways, LEA, wind plants 8) Tc Airlines 1) 1) 1) 1) H2) + 3m7) H2) + 3m9) H2 + 3m

    4) 4) 4) 4)

    Aboveground piping for flammable fluidshistorical sites and buildings

    1) 1) H10) + 3m 11) 1) 4) 4)

    Installations of oil and gas extraction, oilpumping stations, control, gas measurement 1) H10) + 3m 11) 4)

    Bridges 1) H3) + 3m 12) 4)Dams, dikes buildings inhabited buildingswith flammable, potentially explosive or fire

    Airports Air emission Tc reception areas

    protected flora or fauna Sports groundsapproved

    1) 1) 1) 1) 1) 1) 1) H2) + 3m H13) H2) +3m 14) 14) 14) H2) +

    3m

    4) 4) 4) 4) 4) 4) 4)

    Car parking outdoor platforms 1) H2) + 3m 4)

    NOTES:

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    43/117

    9) The distance between the unit whose safety zone and aggregate stability nearest other wind farms will be owned equally by 7 x rotor diameter of the largest aggregate when they are placed on wind direction predominantly turbine rotor 4 x diameter of the largest aggregate when they are arranged perpendicular to the prevailing wind direction

    10) Pillar height x 1.5 plus blade length

    11) if the objective is fenced, safe distance is measured to the fencing

    12) Where appropriate, establish distance H + 3m, if the bridge goes a national road, a county road

    or a railway,

    taking

    into

    account

    the

    notes

    3)

    and

    7),

    turbine

    a distance

    equal

    to

    length

    of

    a blade,

    darn u less than 30 m, if the bridge overlooking a road, a road or a road vicinal public utility

    13) pillar height x 3, this distance may be reduced to the residential area, with the local community, to a minimum value equal to the height of the tower plus the blade length + 3m, remote wind turbines to meet the own use of an area shall be at least equal to the height of the tower plus the blade length + 3m, remote own a home wind turbine is not standardized

    14) Be determined by the competent authority to which the certificate of urbanism.

    On the studied site were not identified urban texture elements falling under Order 49/2007 of ANRE.

    Have studied the site identified the following areas for protection restriction:

    1) Working area of the rotor a circle with a radius of turbine blade length + 3 ml according to ANRE representing land area affected by the rotation of the propeller turbine horizontally.

    Turbine placement is made in accordance with town planning certificate so that it is located on private property or land acts that landowners be affected by this area to agree that the turbine blade affect their land.

    This area has the character of "protection zone" in this area is permitted except agricultural activities.

    2) Construction exclusion zone a circle with a radius of 3 turbine heights and is determined according to ANRE order to provide minimum safety distances from buildings.

    This allowed the construction and installation location, under the law, unless they do not require human presence and does not affect in any way the operation of the turbine.

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    44/117

    4 rotor diameters in other directions and refers only to new wind turbines to be located in this area.

    Also these forested areas will not and will not establish groves of trees with height greater than 8 ml.

    4) Internal network protection area of the park Each wind turbine is connected to a cable central park 1.5 ml buried deep. In this area establishes the regime of the electrical network protection consisting of:

    ensure access to appropriate intervention

    affecting in any underground electrical system

    Area of intervention in case of damage to buried cable is 1.5 ml left right from its axis and is the required minimum that could be effected without the intervention of demand compensation if the cable

    Future buildings or facilities shall comply with the minimum distances protection and safety

    according to ANRE if their location in the immediate vicinity.

    3.

    Drawings

    Framing plan Module 1Liteni sc. 1/25000............................................................................................A1

    Framing plan Module 2Dolhesti sc. 1/25000.......................................................................................A2

    Framing plan Module 1Liteni sc. 1/5000..............................................................................................A3

    Framing plan Module 2Dolhesti sc. 1/5000.........................................................................................A4

    Situation cadastral plan Module 1Liteni sc. 1/5000.............................................................................A5

    Situation cadastral plan Module 2Dolhesti sc. 1/5000........................................................................A6

  • 8/13/2019 FS final 10.2012

    45/117

  • 8/13/2019 FS final 10.2012

    46/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data10/2012

    semnatura

    cerintasemnatura

    Plansa A.2

    nume si prenumeing. Petrareanu C.

    ing. Ursachi I.

    nume si prenumeverificator/expert

    ing. arh. Adomnitei B.desenat

    LEGENDA:

    Zone functionale:- Zona aferenta turbinelor eoliene sia instalatiilor conexe, propusa pentru introducerea in intravilanulcom. Dolhesti

    - Zona destinata fazeide constructie a turbinelor eoliene, ce va fi ocupata provizoriu doar in faza de constructie

    Zone de siguranta - protectie:

  • 8/13/2019 FS final 10.2012

    47/117

    - Zona de lucru a rotorului

    - Zona de interdictie de construire

    - Zona de protectie eoliana

    - Zona de protectie a reteleiinterioare a parcului

    Retele / Cai de comunicatie

    - Drum intern de serviciu alparculuieolian ( l=5m)

    - Retea electrica interna a parculuieolian

    Limite- Limita intravilan existent alorasuluiLiteni

    - Limita UAT com. Liteni

    - Limita Parceolian Liteni

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data10/2012

    semnatura

    cerintasemnatura

    Plansa A.3

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. arh. Adomnitei B.desenat

    LEGENDA:

    Zone functionale:- Zona aferenta turbinelor eoliene sia instalatiilor conexe, propusa pentru introducerea in intravilanulcom. Dolhesti

    - Zona destinata fazeide constructie a turbinelor eoliene, ce va fi ocupata provizoriu doar in faza de constructie

    - Pasune

  • 8/13/2019 FS final 10.2012

    48/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data10/2012

    semnatura

    cerintasemnatura

    Plansa A.4

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing.arh. Adomnitei B.desenat

    Zone de siguranta - protectie:

    - Zona de lucru a rotorului

    - Zona de interdictie de construire

    - Zona de protectie eoliana

    - Zona de protectie a reteleiinterioare a parcului

    Retele / Cai de comunicatie

    - Drum intern de serviciu alparculuieolian ( l=5m)

    - Retea electrica interna a parculuieolian

    Limite- Limita intravilan existent alcom. Dolhesti

    - Limita UAT com. Dolhesti

  • 8/13/2019 FS final 10.2012

    49/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data10/2012

    semnatura

    cerintasemnatura

    Plansa A.5

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing.arh. Adomnitei B.desenat

  • 8/13/2019 FS final 10.2012

    50/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data10/2012

    semnatura

    cerintasemnatura

    Plansa A.6

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing.arh. Adomnitei B.desenat

    September 20, 2012 [FEASABILITY STUDY]

  • 8/13/2019 FS final 10.2012

    51/117

    Access road report

    1. General Considerations

    As with all the parts from the current investment, namely Construction of a wind farm in the

    Dolhesti Liteni region, also the access road has to be divided up and treated into 2 separates

    documentations, based on the fact that the two modules of the wind farm are located on two

    separate administrative entities: Liteni city and Dolhesti commune.

    2. Description of the investment

    The main access road to the wind farm will be constituted by the communal road DC 6. This road

    it connects to the county road DJ 208, that will serve as main road for accessing the region Liteni

    Dolhesti.

    In order to accommodate the overload transport capacity (caused by the supply transport with

    turbine equipment), the intersection between DC 6 and DJ 208 needs to be redone, by widening the

    intersection in order to meet the minimum curve requirement for the oversized transport.

    Module 1 Liteni:

    The access road to the Liteni module is made up by the communal road DC 6.

    Module 2

    Dolhesti:

    The access road to the Dolhesti module its comprised from two roads:

    Communal road DC 6; Service road DE 6A;

    3. Technical Data

    Module 1 Liteni

    To achieve access to the wind farm module in the Liteni city , Suceava County, the following

    interventions are required:

    September 20, 2012 [FEASABILITY STUDY]

    h d d d f d h d d d f l d k l d

  • 8/13/2019 FS final 10.2012

    52/117

    The road is not paved and specific road shows and strains degradation of land, weak gravel and

    unmaintained;

    On the road platform existence of settlements was showed, forming potholes and ruts;

    No road system clearly revealed, previously performed ballasting works being made especially in

    critical places routes with plastic roadbed due to water stagnation, but not solved the problem of

    water leakage from the road continues Platform degradation;

    Existing ditches for storm water discharges are down and no longitudinal slope and stagnant water

    in closed basins, where the slope is greater lateral longitudinal grooves, after rainfalls fallen,

    accumulate water flow at high speed produces degradation of the road platform, these sections must

    be performed pears concrete ditches;

    Existing culverts are damaged (broken or completely tubes are clogged);

    Existing culverts are appropriate section tube to drain existing gullies or water flow in ditches;

    No different from the carriageway verges, no cross slope to drains, stagnant water in ponds platform accelerates the degradation process;

    The road is not stabilized; the land on which is laid out has a serious landslide problem, because of

    this a supporting wall is needed;

    Geometry of the cross and longitudinal slopes cannot ensure correct operation of culverts;

    Missing work for traffic safety;

    Indicators for kilometers and indicators for hectometer are missing; no traffic indicators that have

    fluency traffic on these roads, connecting the county road DJ 208 and the communal road DC 6 are

    not arranged there. Danger of accidents in these intersections area being made.

    Key features of the proposed constructions

    Total length of roads: 1180.87 m of which:

    Communal roads: 1180.87 m;

    Carriageway area: 5904.35 sqm of which:

    September 20, 2012 [FEASABILITY STUDY]

    T f t ffi l i d

  • 8/13/2019 FS final 10.2012

    53/117

    Type of traffic: low, oversized;

    Occupation of land: 100%;

    Objective characteristics have been determined in accordance with the technical no. 45/1 998 on the

    design, construction and upgrading of roads and Technical Norms no. 46/1998 on the establishment

    of technical grade public roads.

    Design speed: 25 km / h, according to the Technical Regulations 46/1 998 laying down technical class

    roads Table 2.

    Category of road: technical class V.

    Besides all this, the design and planning of roads were considered and minimum requirements for

    such equipment gauge carrier exceeded (equipment that will serve the wind farm).

    Platform as Technical Standards no. 45 of designing, building and upgrading roads:

    Nr. Crt Road Length ( m) Proposed cross section1 DC 6 1180,87 Km 2+801-3+982: Pc= 5m + Ac=2*0,75

    The construction of the access road will be made in order to have the fallowing road structure:

    Profile 1 : DC6 Km 2+801 2+831

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 1 X 0,5 m;

    Profile 2 : DC6 Km 2+831 3+982

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m;

    P h 2 X0 5

    September 20, 2012 [FEASABILITY STUDY]

    Carriageway surface of 5 m;

  • 8/13/2019 FS final 10.2012

    54/117

    - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 2 X 0,5 m;

    Module 2 Dolhesti

    To achieve access to the wind farm module in the Dolhesti commune , Suceava County, the following

    interventions are required:

    widening of the intersection between the communal road Dc 6 and the county road DJ 208;

    widening of the communal road DC 6 from the intersection with DJ 208 for a length of 134 m;

    Reshaping, widening, ballasting , paving the way with asphalt of the communal road DC 6 over a

    length of 2533.15 m;

    Reshaping, widening, ballasting of the communal road DC 6 over a length of 134,72 m;

    Reshaping, widening, ballasting of the service road DE 6A over a length of 2231.64 m;

    The land on which the proposed work is situated is owned by Dolhesti commune.

    Existing situation:

    In terms of technical condition, communal road under study is as follows:

    Does not have adequate bearing capacity for taking a traffic needed construction and operation of

    wind farms;

    The road is not paved and specific road shows and strains degradation of land, weak gravel and

    unmaintained;

    On the road platform existence of settlements was showed, forming potholes and ruts;

    No road system clearly revealed, previously performed ballasting works being made especially in

    critical places routes with plastic roadbed due to water stagnation, but not solved the problem of

    water leakage from the road continues Platform degradation;

    Existing ditches for storm water discharges are down and no longitudinal slope and stagnant water

    September 20, 2012 [FEASABILITY STUDY]

    Missing work for traffic safety;

  • 8/13/2019 FS final 10.2012

    55/117

    Missing work for traffic safety;

    Indicators for kilometers and indicators for hectometer are missing; no traffic indicators that have

    fluency traffic on these roads, connecting the county road DJ 208 and the communal road DC 6 are not arranged there. Danger of accidents in these intersections area being made.

    Key features of the proposed constructions

    Total length of access roads: 5033.51 m of which:

    Communal roads: 2801.87 m;

    Service roads: 2231.64 m;

    Carriageway area: 25167.55 sqm of which:

    Communal roads: 14009.35 sqm;

    Service roads: 11158.2 sqm

    Verges area: 9321.57 sqm

    Culverts:

    800 1 pc;

    600 8 pieces;

    Pears trenches: 6500 m;

    Supporting wall: 2 X 195 m;

    Type of traffic: low;

    Occupation of land: 100%;

    Objective characteristics have been determined in accordance with the technical no. 45/1 998 on the

    design, construction and upgrading of roads and Technical Norms no. 46/1998 on the establishment

    of technical grade public roads.

    D i d 25 k / h di h T h i l R l i 46/1 998 l i d h i l l

    September 20, 2012 [FEASABILITY STUDY]

    Nr Crt Road Length ( m) Proposed cross section

  • 8/13/2019 FS final 10.2012

    56/117

    Nr. Crt Road Length ( m) Proposed cross section1 DC 6 134 Km 0+000-0+134: Pc= 6m + Ac=2*0,752 DC 6 2533,15 Km 0+134-2+533: Pc= 5m + Ac=2*0,753 DE 6 A 2231,64 Km 0+000-2+231: Pc= 5m + Ac=2*0,754 DC 6 134,72 Km 2+533-2+667: Pc= 5m + Ac=2*0,75

    The construction of the access road will be made in order to have the fallowing road structure:

    Profile 1 : DC6 Km 0+000 0+134

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 30 cm thickness; - Carriageway surface of 5,5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 1 X 0,5 m; - Layer of Asphalt concrete ( rough) BAR 16 of 5 cm thickness ( in the places where the

    technical solution imposes it);

    Profile 2 : DC6 Km 0+134 0+274; DC 6 Km 0+469 2+533;

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m;

    - Pears trenches 1 X 0,5 m; - Layer of Asphalt concrete ( rough) BAR 16 of 5 cm thickness ( in the places where the

    technical solution imposes it);

    Profile 3 : DC6 Km 2+533 2+667; DE 6 A km 0+000 2+231

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 1 X 0,5 m;

    September 20, 2012 [FEASABILITY STUDY]

    Internal roads for the Dolhesti module will be made on a total surface of 7414 sqm ( made on the

  • 8/13/2019 FS final 10.2012

    57/117

    q (current layout of service roads).

    The construction of the access road will be made in order to have the fallowing road structure:

    - Base layer of crushed stone of 30 cm thickness; - A layer of mixed ballast of 25 cm thickness; - Carriageway surface of 5 m; - Shoulders of 2 X 0,75 m; - Pears trenches 2 X 0,5 m;

    4. Drawings

    Liteni Module

    Framing plan Module 1Liteni sc. 1/25000............................................................................................A1

    Situation existing plan Module 1Liteni sc. 1/500...........................................................................A2 A5

    Proposed plan Module 1Liteni sc. 1/500........................................................................................B1 B4

    Cross section profile Module 1Liteni sc. 1/50...................................................................................C1

    Cross section profile ( internal road) Module 1Liteni sc. 1/50.........................................................C2

    Dolhesti Module

    Framing plan Module 2Dolhesti sc. 1/25000.......................................................................................A1

    Situation existing plan Module 2Dolhesti sc. 1/500....................................................................A2 A19

    Proposed plan Module 2Dolhesti sc. 1/500..................................................................................B1 B18

    Cross section profile Module 2Dolhesti sc. 1/50.........................................................................C1 C3

    Cross section profile ( internal road) Module 2Dolhesti sc. 1/50.....................................................C4

  • 8/13/2019 FS final 10.2012

    58/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.1

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Ursachi I.desenat

  • 8/13/2019 FS final 10.2012

    59/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.2

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    GRAFIC DE RACORDARE A PLANSELOR

    A2

    A3

    A4 A5

  • 8/13/2019 FS final 10.2012

    60/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.3

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/

    expert

    ing. Adomnitei C.desenat

    GRAFIC DE RACORDARE A PLANSELOR

    A2

    A3

    A4 A5

  • 8/13/2019 FS final 10.2012

    61/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.4

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    GRAFIC DE RACORDARE A PLANSELOR

    A2

    A3

    A4 A5

  • 8/13/2019 FS final 10.2012

    62/117

  • 8/13/2019 FS final 10.2012

    63/117

    GRAFIC DE RACORDARE A PLANSELOR

    B2

    B3 B4

  • 8/13/2019 FS final 10.2012

    64/117

    GRAFIC DE RACORDARE A PLANSELOR

    B2

    B3 B4

  • 8/13/2019 FS final 10.2012

    65/117

    GRAFIC DE RACORDARE A PLANSELOR

    B1

    B2

    B3 B4

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa B.3

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Ursachi I.desenat

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    66/117

    B1

    B2

    B3 B4

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa B.4

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Ursachi I.desenat

    PROFIL TRANSVERSAL TIP DC 6 intre Km 2+801 - 2+831

    PROFIL TRANSVERSAL TIP DC 6 intre Km 2+831 - 3+982

  • 8/13/2019 FS final 10.2012

    67/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa C.1

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    - piatra sparta 30cm- balast de 25 cm grosime ;

    C12 15 (Bc15)

    C8 10 (Bc10)

    Armatura rost elevatie fundatieOB37, L = 1.20m

    Cap dren - argila

    Geotextilcu rolde filtru invers

    Dren din bolovani

    Hidroizolatie- piatra sparta 30cm grosime;- balast de 25cm grosime ;- B.A.R 16 5cm grosime;

    Pereu din bolovani de riu 15 cmPat beton C8/10 de 10 cm

    25

    1.50

    25 2-4 % 2 -4%

    25

    C8/10

    25

    D

    D

    C=7.50

    VEDERE IN PLANB-B

    LC8/10 C8/10

    C=7.50

    SECTIUNE LONGITUDINALA A-AC

    C8/10

    50

    F

    F

    35

    50

    5015

    50

    1.052.70

    601.05

    1025

    SECTIUNE TRANSVERSALA F -F

    25 30 30 2550

    SECTIUNE D - D

    C8/10

    SECTIUNE C - C

    PROFIL TRANSVERSAL TIP PODET TIP PREMO 600

    PROFIL TRANSVERSAL TIP Drum de exploatare in interiorul

    parcului Eolian Liteni

  • 8/13/2019 FS final 10.2012

    68/117

    - piatra sparta 30cm

    - balast de 25 cm grosime ;

    parcului Eolian Liteni

    tubulatura cabluri electrice

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data03/2012

    semnatura

    cerintasemnatura

    Plansa C.4

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. arh. Adomnitei B.desenat

  • 8/13/2019 FS final 10.2012

    69/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.1

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Ursachi I.desenat

  • 8/13/2019 FS final 10.2012

    70/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.2

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    71/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratorisef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.3

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    72/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.4

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    73/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.5

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    74/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.6

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019 FS final 10.2012

    75/117

    S.C. VECTOR CONSULT A.S.D. S.R.L SUCEAVA

    elaboratori

    sef proiectproiectat

    REFERAT/EXPERTIZA NR./DATA

    Data02/2012

    semnatura

    cerintasemnatura

    Plansa A.7

    nume si prenumeing. Petrareanu C.

    ing. Petrareanu C.

    nume si prenumeverificator/expert

    ing. Adomnitei C.desenat

    A2

    A3

    A4

    A5

    A6

    A7

    A8

    A9

    A10

    A11

    A12 A13 A14

    A15 A16

    A17

    A18

    A19

    GRAFIC DE RACORDARE A PLANSELOR

  • 8/13/2019